JP3789100B2 - How to build a widening tunnel - Google Patents

How to build a widening tunnel Download PDF

Info

Publication number
JP3789100B2
JP3789100B2 JP2002083417A JP2002083417A JP3789100B2 JP 3789100 B2 JP3789100 B2 JP 3789100B2 JP 2002083417 A JP2002083417 A JP 2002083417A JP 2002083417 A JP2002083417 A JP 2002083417A JP 3789100 B2 JP3789100 B2 JP 3789100B2
Authority
JP
Japan
Prior art keywords
tunnel
precast plate
existing tunnel
existing
new
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002083417A
Other languages
Japanese (ja)
Other versions
JP2003278479A (en
Inventor
英人 真下
浩久 蒲田
純一郎 中森
信一 下寺
道裕 稲生
敏郎 城所
範行 伊藤
秋秀 阿久津
栄一 畑山
憲三 水原
直樹 井上
英雄 神山
昭浩 中北
隆治 手島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Kumagai Gumi Co Ltd
Okumura Corp
National Research and Development Agency Public Works Research Institute
Original Assignee
Kajima Corp
Public Works Research Institute
Kumagai Gumi Co Ltd
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Public Works Research Institute, Kumagai Gumi Co Ltd, Okumura Corp filed Critical Kajima Corp
Priority to JP2002083417A priority Critical patent/JP3789100B2/en
Publication of JP2003278479A publication Critical patent/JP2003278479A/en
Application granted granted Critical
Publication of JP3789100B2 publication Critical patent/JP3789100B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、一般車両を通行させた状態で既設のトンネルを拡幅する拡幅トンネルの築造方法に関する。
【0002】
【従来の技術】
昨今、交通量の増大、トンネルの老朽化、車高の高いISO規格のコンテナ車の通行を可能にさせるため、あるいは最近の道路構造令に適合させるために既存のトンネルの断面を拡大させる必要が生じている。
【0003】
既存のトンネルの断面を拡大させる方法としては、既存のトンネルに近接して、より大断面の新設トンネルを掘削し、新設トンネル完成後に既存トンネルに交通を移す方法、または、別に、迂回ルートを設定し既存トンネルを完全に通行止めにしてトンネルの断面を拡大する方法、或いは既存トンネルの内空にプロテクタを設置して通過車輌を防護しながら既存トンネルの覆工を取り壊し、トンネルの断面を大きくする方法が採られている。
【0004】
【発明が解決しようとする課題】
しかしながら、既存トンネルに近接して新設トンネル構築する方法は、地形的、社会的な制約が多く、更に新設トンネルに至るアクセス道路の建設も必要となる。
【0005】
また、既存トンネルを完全に通行止めにする方法は、迂回道路がない場合や、大幅な迂回になる場合もあり、渋滞等地域の交通に影響を及ぼすことがある。
【0006】
更に既存トンネルの内空にプロテクタを設置する方法は、車輌防護のため堅固なプロテクタとなるので、通過車輌の車線は減少し、交通渋滞等地域の交通に与える影響が大きい。また、堅固なプロテクタのため、作業空間が限定され、通常のトンネルの掘削で使用される汎用機械が使えず、能率の低い機械を使用することになるので、工期が長期化し、地域の交通への影響も長期化する。
【0007】
本発明はこのような問題を鑑みてなされたものでその目的とするところは、既存トンネルの通常の通行を確保したまま、容易にトンネル断面を拡大できる拡幅トンネルの築造方法を提供することにある。
【0008】
【課題を解決するための手段】
本発明は、上記の目的を有効に達成するために、次のような構成にしてある。すなわち、請求項1記載の本発明の拡幅トンネルの築造方法は、既設トンネルを幅方向に拡幅して、アーチ状の拡幅トンネルを築造する方法であって、既設トンネル内を車両を通行させつつ、既設トンネルの外側の一側方及び上方の地盤を掘削する工程と、掘削された新設トンネルの掘削壁面の一側部および頂部に、円弧状に湾曲した矩形面状の複数のプレキャスト版を互いに連結して設置し、上記掘削壁面とプレキャスト版との空隙に裏込注入する工程と、設置された頂部のプレキャスト版より掘削底面に亘って、垂直方向に防護柵を設置する工程と、上記プレキャスト版と防護柵とで囲まれた新設トンネルの 空間内に車両を通行させつつ、既設トンネルを撤去する工程と、既設トンネル撤去後の新設トンネルの残りの掘削壁面にプレキャスト版を設置し、上記頂部のプレキャスト版と連結すると共に、上記掘削壁面とプレキャスト版との空隙に裏込注入する工程と、その後、防護柵を撤去する工程とからなり、上記頂部のプレキャスト版は、その周方向端部が既設トンネル側に張り出して設けられていることを特徴とする構成である。
【0009】
請求項2記載の本発明の拡幅トンネルの築造方法は、請求項1記載の拡幅トンネルの築造方法において、既設トンネルを幅方向に拡幅して、アーチ状の拡幅トンネルを築造する方法であって、既設トンネル内を車両を通行させつつ、既設トンネルの外側の一側方及び上方の地盤を掘削する工程と、掘削された新設トンネルの掘削壁面の一側部および頂部に、円弧状に湾曲した矩形面状の複数のプレキャスト版を互いに連結して設置し、上記掘削壁面とプレキャスト版との空隙に裏込注入する工程と、設置された頂部のプレキャスト版より掘削底面に亘って、垂直方向に防護柵を設置する工程と、上記プレキャスト版と防護柵とで囲まれた新設トンネルの 空間内に車両を通行させつつ、既設トンネルを撤去する工程と、既設トンネル撤去後の新設トンネルの残りの掘削壁面にプレキャスト版を設置し、上記頂部のプレキャスト版と連結すると共に、上記掘削壁面とプレキャスト版との空隙に裏込注入する工程と、その後、防護柵を撤去する工程とからなり、上記頂部のプレキャスト版は、その周方向端部が上記防護柵より張り出して設けられていることを特徴とする構成である。
【0010】
【0011】
【0012】
【発明の実施の形態】
以下、図面に基づいて本発明の実施の形態を詳細に説明する。図1〜図5は、本発明の拡幅トンネルの築造方法の施工手順を示す断面図である。
【0013】
図1、図2に示されるように、地山1中に既設トンネル2が既に構築されている。既設トンネル2を拡幅する場合、一般車輌のプロテクタとして既設トンネル2を使用するために、更には、既設トンネル2の側方を掘削することにより、既設トンネル2に作用する上左のバランスが崩れることをも考慮して、予め既設トンネル覆工3のコンクリートの補強を必要箇所について行う。
【0014】
補強方法としては、主に既設トンネル覆工3の天端部へ裏込め注入を行ったり、拡幅されない側の既設トンネル2の側方地盤1aに向ってロックボルトを設置したり、既設トンネル覆工3の内側へ支保工を建て込んだり、根固めコンクリート等で根固めしたりする方法がある。
【0015】
既設トンネル覆工3のコンクリートのクラックの程度、既設トンネル覆工3の裏側の空洞の程度、地山1の強度等により、これらの補強方法のうち、いくつかを選択する。(図示せず。)
【0016】
既設トンネル覆工3の補強の後、既設トンネル2内は、これまで通り交通を確保したまま、新設トンネル4の上半部分に相当する新設トンネル上半部5の掘削を行う。掘削機(図示せず)は既設トンネル覆工3には載せず、新設トンネル上半部5の上半盤6に載せる。このことは、既設トンネル覆工3自体をプロテクタとしているため、既設トンネル覆工3に、荷重をかけないようにするためである。
【0017】
この場合、既設トンネル2の断面位置を新設トンネル4の断面の片側に寄せて計画しているため、比較的大きな空間を掘削することになり、ロードヘッダ、ツインヘッダ、ブレーカ等の汎用の掘削機械、或いはこのような掘削機械を改造した機械を使用できる。
【0018】
また、既設トンネル覆工3の上部にあたる新設トンネル上半部5の隅角部7(a−b間)の外側の地山1は、作業空間に制約があり、掘削機械土砂搬送機械が導入できないため、掘削せず残す。
【0019】
新設トンネル上半部5の掘削が終了後、その掘削壁面(a−c間)に、吹付コンクリート8を打設し、支保工(図示せず)を設置したり、ロックボルト等を打設したりして、必要な支保を行う。
【0020】
隅角部7は、新設トンネル上半部5のアーチ部の構造的弱点と考えられる部分である。そのため、隅角部7(a−b間)にも吹付コンクリート9を打設する。更にa点において、支保工の根巻をして、支保工を固定する。これにより、支保工にかかる力を確実に地山1に伝えることが出来るため、安全性が高まる。
【0021】
次に、図2に示すように、既設トンネル2内の交通を確保したまま、新設トンネル上半部5の下方の新設トンネル下半部10の掘削を行う。この新設トンネル下半部10の掘削も、前述したような掘削機械あるいは汎用機械を改造した機械を使用する。
【0022】
新設トンネル下半部10の掘削の後、新設トンネル下半部10に吹付コンクリート11を設け、支保工(図示せず)を設置したり、ロックボルト等で支保を行う。
【0023】
次に、既設トンネル2内の交通を確保したまま、インバート部12の掘削を行う。インバート部12の掘削も、新設トンネル上半部5の掘削と同様に、汎用の掘削機械あるいは汎用機械を改造した機械を使用する。
【0024】
次に、図3に示すようにインバート部12の掘削の後、インバートコンクリート13を施工する。インバートコンクリート13が硬化したら、その上に砕石、砂利12aなどを、敷きつめ、転圧して、新設トンネル4の路盤21を構築すると共に、掘削した既設トンネル2上方からの崩落物を受止する防護柵14を、新設トンネル4の中央部付近でインバートコンクリート13の上方に立ち上げる。
【0025】
このようにして、既設トンネル2の全線にわたって、新設トンネル上半部5、新設トンネル下半部10を繰り返し掘削し、吹付コンクリート8、11、インバートコンクリート13、新設トンネル4の路盤21等を設ける。
【0026】
次に、新設トンネル4の路盤21上に、軌道レール15を設置し、このレール15上に、(後述する)プレキャスト版の搬送台車16を移動可能に載置すると共に、吹付コンクリート面8a、11aを防止シート17で被覆しておく。
【0027】
プレキャスト版18は、弧状に湾曲した矩形面状に形成されており、複数個をトンネル周方向に連結した状態で、搬送台車16の上面に載置される。材質は、コンクリート、銅板、樹脂等適宣使用できる。
【0028】
次に、複数のプレキャスト版18を連結状態で載置した搬送台車16を、レール15上を移動させて新設トンネル4の側部4bおよび天端部4cの吹付コンクリート面8a、11aに位置させる。
【0029】
次に、ジャッキ等の手段19により、プレキャスト版18を吹付コンクリート面8a、11aに近づける。
【0030】
次に、吹付コンクリート面8a、11aと各プレキャスト版18の外周面18aとの空隙部20にモルタル等の裏込注入を行う。この裏込注入の際、必要に応じてアンカーボルト(図示せず)によって、プレキャスト版18を地盤(地山1)側から固定しておく。
【0031】
裏込注入完了後、搬入台車16を移動させると共に、防護柵14を上方に伸して、天端部4cに位置するプレキャスト版18を支持させる。
【0032】
以上の作業を繰り返すことにより、全線に亘り、プレキャスト版18を設置すると共に、路盤上のレール15を撤去し、既設トンネル2の舗装面2aと高さが同一となるように、新設トンネル4の路盤21上に舗装を施す。
【0033】
舗装が完了したら、図4に示すように、一般車両の交通を、既設トンネル2から新設トンネル4内のプレキャスト版18と防護柵14とで囲まれた空間29に切り替える。
【0034】
このとき、既設トンネル2と新設トンネル4の舗装面2a、22の高さは同じであるので、既設トンネル2への進入出路を壊すことなく、この進入出路に沿って新たな進入路を増設すればよく、効率的である。
【0035】
さらに、新設トンネル4内は、プレキャスト版18と防護柵14とで囲まれているため、吹付コンクリートの剥落や 吹付コンクリート面8a、11aからの漏水、ひいては、地盤の崩落から空間29を防護でき、一般車両を安全に通行させることができる。
【0036】
前述のように、既設トンネル2から新設トンネル4内のプレキャスト版18と防護柵14とで囲まれた空間29内に交通を切り替えた後、図5に示すように、上記新設トンネル4内の空間29内に車輌を通過させながら、既設トンネル覆工3(図4の仮想線で示す箇所)を取り壊すと共に、新設トンネル上半部5の掘削時(図2参照)に、掘り残した隅角部7の外側の地山1の掘削も行い、吹付コンクリート23(図4参照)を設ける。この際、新設トンネル覆工24と接する部分の既設トンネル覆工3bは、取り壊さず残す。次に、新設トンネル下半部10の既設トンネル2との重複部分の支保工(図示せず)を設置する。
【0037】
次に、既設トンネル2(図4参照)の下方である新設トンネル4の下方のインバート部25の掘削を行う。この際、既設トンネル覆工3bの底盤部26を取り壊す。インバート部25を掘削後、インバートコンクリート13と対称となるようにインバートコンクリート27を施工し、新設トンネル4の路盤面28まで構造物を構築して、新設トンネル4の路盤面28の舗装を行う。
【0038】
このようにして、インバート部12,25が構築される。そして、新設トンネル4の全線にわたって、既設トンネル2を取り壊し、残りの新設トンネル4の構築を繰り返す。
【0039】
次に、新設トンネル4の左手空間29内に車輌を通過させながら、残り新設トンネル4の全線にわたり、プレキャスト版18を設置する。尚、既設トンネル覆工3bの部分では、既設トンネル覆工3bの内側に新設トンネル4のプレキャスト版18が打設される。またこの際、左手のプレキャスト版備え付けに使用した搬送台車16(図3参照)を使用してプレキャスト版18の設置を行う。
【0040】
新設トンネル4のプレキャスト版18がアーチ状に構築されると、新設トンネル左手空間29内の交通を一次通行止めにし、防護柵14を撤去する。この際、プレキャスト版18はアーチ状に形成されているので、アーチアクションにより、防護柵14で天端を支持しなくても安定的に固定される。この後、新設トンネル4内の交通を中央部によせ、歩道、照明、諸設備等の整備を行い、新設トンネル4が完成する。
【0041】
尚、新設トンネル4の内空幅は、既設トンネル2の内空幅の概ね2倍ないしはそれ以上あることが好ましい。また、防護柵14はその下部を残した状態で撤去してもよく、この場合、残された下部を新設トンネル4の完成時に中央分離帯として用いることができる。
【0042】
このようにしてトンネル内の交通を確保したまま、既設トンネル2を拡幅し、新設トンネル4を構築する。この際、プロテクタとして本設のプレキャスト版18を用いることにより、仮設プロテクタと比較して、車輌の通行幅を広くできると共に、プロテクタにかかる費用を低減できる。また、既設トンネル2の断面位置を新設トンネル4の片側に寄せることにより、新設トンネル4の拡大部分の掘削断面が大きくなり、汎用の機械もしくは、汎用の機械を改造した機械の使用が可能となり、掘削効率の向上に役立つ。
【0043】
【発明の効果】
以上のように本発明によれば、既存トンネルの通常の通行を確保したまま、容易にトンネル断面を拡大できる。また、仮設のプロテクタと比べ内空を大きくとれる(車両の通行幅を大きくとれる)。また、上部も掘削しておくことにより、プレキャスト版設置後の右半の掘削・既設トンネル撤去時の地山の変形がなく、プレキャスト版が破損することがない。そして仮設のプロテクタを設ける必要がなく経済的であり、プレキャスト版なら設置も早い。
【0044】
また、頂部のプレキャスト版は、その周方向端部が既設トンネル側に張り出して設けられていることにより、上方地盤の崩落を確実に抑えることができ、左半の車両の通行を安全に行わせることができる。
【0045】
また、頂部のプレキャスト版は、その周方向端部が防護柵より張り出して設けられていることにより、残りのプレキャスト版の組付けが容易にできる。組み付け時に新設トンネルの左半の活線部分に悪影響を与えない。例えば、新設トンネルの右半のプレキャスト版と連結するときに左半での作業がなく、左半の交通を一時通行止めにする必要がない。
【0046】
また、頂部のプレキャスト版は、防護柵により支持されていることにより、プレキャスト版自体の落下を確実に防止できる。アンカーボルトによる支持だけでは地盤によっては不適な場合もあり、特に天端に位置するプレキャスト版を支持するには、側部のプレキャスト版を支持するより大きな支持強度が必要になり、これが不足する場合もあり、これらの場合において、有効な手段となり得る。また、施工の煩雑なアンカーボルト打設作業を省略することも可能である。
【0047】
【図面の簡単な説明】
【図1】拡幅トンネルの築造方法の施工手順を示す断面図である。
【図2】拡幅トンネルの築造方法の施工手順を示す断面図である。
【図3】拡幅トンネルの築造方法の施工手順を示す断面図である。
【図4】拡幅トンネルの築造方法の施工手順を示す断面図である。
【図5】拡幅トンネルの築造方法の施工手順を示す断面図である。
【符号の説明】
2 既設トンネル
4 新設トンネル
14 防護柵
18 プレキャスト版
20 空隙
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a widening tunnel construction method for widening an existing tunnel in a state where a general vehicle is allowed to pass.
[0002]
[Prior art]
Nowadays, it is necessary to enlarge the cross section of existing tunnels to increase traffic volume, tunnel aging, to allow high-height ISO standard container vehicles to pass, or to comply with recent road structure regulations. Has occurred.
[0003]
As a method of enlarging the cross section of the existing tunnel, a new tunnel with a larger cross section is excavated close to the existing tunnel, and traffic is transferred to the existing tunnel after the new tunnel is completed, or another detour route is set. The method of enlarging the cross section of the tunnel by completely closing the existing tunnel, or the method of enlarging the cross section of the tunnel by destroying the lining of the existing tunnel while protecting the passing vehicle by installing a protector inside the existing tunnel Has been adopted.
[0004]
[Problems to be solved by the invention]
However, the method of constructing a new tunnel in the vicinity of an existing tunnel has many topographical and social restrictions, and it is also necessary to construct an access road that leads to the new tunnel.
[0005]
In addition, the method of completely closing an existing tunnel may affect a local traffic such as a traffic jam when there is no detour road or a large detour.
[0006]
Furthermore, the method of installing a protector in the interior of an existing tunnel is a strong protector for protecting the vehicle, so the lanes of passing vehicles are reduced and the traffic on traffic such as traffic congestion is greatly affected. In addition, because of the solid protector, the work space is limited, and general-purpose machines used in ordinary tunnel excavation cannot be used, and low-efficiency machines are used. The effect of this will also be prolonged.
[0007]
The present invention has been made in view of such problems, and an object of the present invention is to provide a method for constructing a widening tunnel that can easily enlarge the cross section of the tunnel while ensuring normal passage of the existing tunnel. .
[0008]
[Means for Solving the Problems]
In order to effectively achieve the above object, the present invention has the following configuration. That is, the construction method of the widening tunnel of the present invention according to claim 1 is a method of widening the existing tunnel in the width direction to construct an arch-shaped widening tunnel, while passing the vehicle through the existing tunnel, The process of excavating the ground on one side and the upper side of the existing tunnel, and a plurality of precast plates with a rectangular surface curved in an arc shape are connected to one side and the top of the excavation wall of the newly excavated tunnel And installing the protective fence in the vertical direction across the bottom of the excavation from the precast plate at the top, and the precast plate. The process of removing the existing tunnel while passing the vehicle through the space of the new tunnel surrounded by the protective fence and the remaining excavation wall surface of the new tunnel after removing the existing tunnel. A plate is installed, connected to the top precast plate, and back-filled into the gap between the excavation wall and the precast plate, and then the protective fence is removed. The top precast plate Is a configuration characterized in that the circumferential end portion is provided to protrude to the existing tunnel side.
[0009]
The method for building a widening tunnel of the present invention according to claim 2 is a method for building an arch-shaped widening tunnel by widening an existing tunnel in the width direction in the method for building a widening tunnel according to claim 1 , A process of excavating the ground on one side and the upper side of the existing tunnel while passing the vehicle through the existing tunnel, and a rectangle curved in an arc shape on one side and the top of the excavated wall surface of the newly excavated tunnel A plurality of planar precast plates are installed connected to each other, and the process of pouring into the gap between the excavation wall surface and the precast plate, and the vertical protection from the installed precast plate to the bottom of the excavation The process of installing the fence and the new tunnel surrounded by the precast plate and the protective fence The process of removing the existing tunnel while allowing the vehicle to pass through the space, and installing a precast plate on the remaining excavation wall of the new tunnel after the removal of the existing tunnel, connecting with the precast plate at the top, and It consists of the step of backfilling the gap with the precast plate and the step of removing the protective fence, and the precast plate at the top is provided with its circumferential end protruding from the protective fence. This is a characteristic configuration.
[0010]
[0011]
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail based on the drawings. 1-5 is sectional drawing which shows the construction procedure of the construction method of the widening tunnel of this invention.
[0013]
As shown in FIGS. 1 and 2, an existing tunnel 2 has already been constructed in the natural ground 1. When widening the existing tunnel 2, in order to use the existing tunnel 2 as a protector for a general vehicle, further, excavating the side of the existing tunnel 2, the balance between the upper left and the left acting on the existing tunnel 2 is broken. In consideration of the above, concrete reinforcement of the existing tunnel lining 3 is performed in advance on necessary portions.
[0014]
Reinforcing methods mainly include backfill injection into the top end of the existing tunnel lining 3, installation of lock bolts toward the side ground 1 a of the existing tunnel 2 that is not widened, or existing tunnel lining There is a method of building a support work inside 3 or solidifying with rooting concrete.
[0015]
Some of these reinforcing methods are selected according to the degree of concrete cracks in the existing tunnel lining 3, the degree of the cavity behind the existing tunnel lining 3, the strength of the natural ground 1, and the like. (Not shown)
[0016]
After reinforcement of the existing tunnel lining 3, the existing tunnel 2 is excavated in the upper half 5 of the new tunnel 4 corresponding to the upper half of the new tunnel 4 while maintaining traffic as before. The excavator (not shown) is not placed on the existing tunnel lining 3 but on the upper half 6 of the upper half 5 of the new tunnel. This is because the existing tunnel lining 3 itself is used as a protector, so that no load is applied to the existing tunnel lining 3.
[0017]
In this case, since the cross-sectional position of the existing tunnel 2 is planned to approach one side of the cross-section of the new tunnel 4, a relatively large space will be excavated, and general-purpose excavating machines such as road headers, twin headers, breakers, etc. Alternatively, a machine modified from such an excavating machine can be used.
[0018]
Further, the ground 1 outside the corner portion 7 (between a and b) of the upper half portion 5 of the new tunnel, which is the upper portion of the existing tunnel lining 3, has a limited working space, and the excavating machine and the earth and sand transport machine cannot be introduced. So leave without digging.
[0019]
After excavation of the upper half 5 of the new tunnel is completed, shotcrete 8 is placed on the excavation wall surface (between a and c), a supporting work (not shown) is installed, or a lock bolt is installed. Or provide necessary support.
[0020]
The corner portion 7 is a portion considered as a structural weak point of the arch portion of the upper half portion 5 of the new tunnel. Therefore, shotcrete 9 is also placed in the corner portion 7 (between a and b). Further, at point a, the support work is rooted and fixed. Thereby, since the force concerning support work can be reliably transmitted to the natural ground 1, safety increases.
[0021]
Next, as shown in FIG. 2, the new tunnel lower half 10 below the new tunnel upper half 5 is excavated while the traffic in the existing tunnel 2 is secured. For excavation of the lower half 10 of the new tunnel, the excavating machine as described above or a machine modified from a general-purpose machine is used.
[0022]
After excavation of the lower half 10 of the new tunnel, shotcrete 11 is provided in the lower half 10 of the new tunnel, and a support work (not shown) is installed, or is supported by a lock bolt or the like.
[0023]
Next, the invert section 12 is excavated while securing the traffic in the existing tunnel 2. The excavation of the invert part 12 uses a general-purpose excavating machine or a machine modified from a general-purpose machine, similarly to the excavation of the upper half 5 of the new tunnel.
[0024]
Next, as shown in FIG. 3, after excavation of the invert portion 12, invert concrete 13 is applied. When the invert concrete 13 is hardened, crushed stones, gravel 12a, etc. are laid on it and rolled to build the roadbed 21 of the new tunnel 4 and to protect the fallen objects from the excavated existing tunnel 2 above. 14 is raised above the invert concrete 13 near the center of the new tunnel 4.
[0025]
In this manner, the new tunnel upper half 5 and the new tunnel lower half 10 are repeatedly excavated over the entire line of the existing tunnel 2 to provide the shotcrete 8 and 11, the invert concrete 13, the roadbed 21 of the new tunnel 4, and the like.
[0026]
Next, a track rail 15 is installed on the roadbed 21 of the new tunnel 4, and a precast version transport carriage 16 (to be described later) is movably mounted on the rail 15, and the shotcrete surfaces 8 a and 11 a. Is covered with the prevention sheet 17 in advance.
[0027]
The precast plate 18 is formed in a rectangular surface curved in an arc shape, and is placed on the upper surface of the transport carriage 16 in a state where a plurality of precast plates 18 are connected in the circumferential direction of the tunnel. As the material, concrete, copper plate, resin, etc. can be used appropriately.
[0028]
Next, the transport carriage 16 on which the plurality of precast plates 18 are placed in a connected state is moved on the rail 15 to be positioned on the sprayed concrete surfaces 8a and 11a of the side 4b and the top end 4c of the new tunnel 4.
[0029]
Next, the precast plate 18 is brought close to the sprayed concrete surfaces 8a and 11a by means 19 such as a jack.
[0030]
Next, back injection of mortar or the like is performed in the gap 20 between the shotcrete surfaces 8a and 11a and the outer peripheral surface 18a of each precast plate 18. At the time of this back injection, the precast plate 18 is fixed from the ground (ground 1) side with an anchor bolt (not shown) as necessary.
[0031]
After completion of the back-injection, the carry-in carriage 16 is moved, and the guard fence 14 is extended upward to support the precast plate 18 located at the top end 4c.
[0032]
By repeating the above work, the precast plate 18 is installed over the entire line, the rail 15 on the roadbed is removed, and the height of the paved surface 2a of the existing tunnel 2 is the same as that of the existing tunnel 4 Pave the roadbed 21.
[0033]
When the paving is completed, as shown in FIG. 4, the traffic of the general vehicle is switched from the existing tunnel 2 to a space 29 surrounded by the precast plate 18 and the protective fence 14 in the new tunnel 4.
[0034]
At this time, since the heights of the paved surfaces 2a and 22 of the existing tunnel 2 and the new tunnel 4 are the same, a new approach path can be added along the approach / exit path without breaking the entrance / exit path to the existing tunnel 2. It is good and efficient.
[0035]
Further, since the new tunnel 4 is surrounded by the precast plate 18 and the protective fence 14, the space 29 can be protected from the peeling of the shotcrete, the leakage from the shotcrete surfaces 8a and 11a, and the collapse of the ground. A general vehicle can pass safely.
[0036]
As described above, after the traffic is switched from the existing tunnel 2 to the space 29 surrounded by the precast plate 18 and the protective fence 14 in the new tunnel 4, the space in the new tunnel 4 is shown in FIG. 29. While passing the vehicle through 29, the existing tunnel lining 3 (the portion indicated by the phantom line in FIG. 4) is demolished and the corner portion left uncut when the upper half 5 of the new tunnel is excavated (see FIG. 2). Excavation of the natural ground 1 outside 7 is also performed, and shotcrete 23 (see FIG. 4) is provided. At this time, the existing tunnel lining 3 b in contact with the new tunnel lining 24 is left without being demolished. Next, a supporting work (not shown) of the overlapping part with the existing tunnel 2 in the lower half 10 of the new tunnel is installed.
[0037]
Next, excavation of the invert portion 25 below the new tunnel 4 that is below the existing tunnel 2 (see FIG. 4) is performed. At this time, the bottom plate portion 26 of the existing tunnel lining 3b is demolished. After excavating the invert portion 25, the invert concrete 27 is constructed so as to be symmetric with the invert concrete 13, the structure is constructed up to the roadbed surface 28 of the new tunnel 4, and the roadbed surface 28 of the new tunnel 4 is paved.
[0038]
In this way, the invert units 12 and 25 are constructed. Then, the existing tunnel 2 is demolished over the entire line of the new tunnel 4, and the construction of the remaining new tunnel 4 is repeated.
[0039]
Next, the precast plate 18 is installed over the remaining lines of the new tunnel 4 while passing the vehicle through the left hand space 29 of the new tunnel 4. In the existing tunnel lining 3b, the precast plate 18 of the new tunnel 4 is placed inside the existing tunnel lining 3b. At this time, the precast plate 18 is installed using the transport carriage 16 (see FIG. 3) used for mounting the precast plate on the left hand.
[0040]
When the precast version 18 of the new tunnel 4 is constructed in an arch shape, traffic in the left side space 29 of the new tunnel is temporarily closed, and the protective fence 14 is removed. At this time, since the precast plate 18 is formed in an arch shape, the precast plate 18 is stably fixed by the arch action without supporting the top end by the protective fence 14. Thereafter, the traffic in the new tunnel 4 is directed to the center, and the sidewalk, lighting, various facilities, etc. are maintained, and the new tunnel 4 is completed.
[0041]
Note that the inner space width of the new tunnel 4 is preferably approximately twice or more than the inner space width of the existing tunnel 2. Moreover, you may remove the protection fence 14 in the state which left the lower part, In this case, the remaining lower part can be used as a median strip at the time of completion of the new tunnel 4.
[0042]
In this way, the existing tunnel 2 is widened and the new tunnel 4 is constructed while securing the traffic in the tunnel. At this time, by using the permanent precast plate 18 as a protector, the width of the vehicle can be widened and the cost of the protector can be reduced as compared with the temporary protector. Also, by moving the cross-sectional position of the existing tunnel 2 to one side of the new tunnel 4, the excavation cross section of the enlarged portion of the new tunnel 4 becomes large, and it becomes possible to use a general-purpose machine or a machine modified from a general-purpose machine. Helps improve drilling efficiency.
[0043]
【The invention's effect】
As described above, according to the present invention, it is possible to easily expand the tunnel cross section while ensuring normal traffic of the existing tunnel. In addition, the interior space can be made larger than that of the temporary protector (the width of the vehicle can be increased). Moreover, by excavating the upper part, there is no deformation of the natural ground when excavating the right half after installing the precast plate and removing the existing tunnel, and the precast plate is not damaged. It is economical because there is no need to install a temporary protector, and the precast version can be installed quickly.
[0044]
In addition, the precast plate at the top is provided with its circumferential end projecting toward the existing tunnel, so that the collapse of the upper ground can be reliably suppressed, and the vehicle on the left half can be safely passed. be able to.
[0045]
Moreover, the precast plate at the top is provided with its circumferential end projecting from the protective fence, so that the remaining precast plates can be easily assembled. Does not adversely affect the live part of the left half of the new tunnel when assembled. For example, when connecting with the precast version of the right half of a new tunnel, there is no work on the left half and there is no need to temporarily block traffic on the left half.
[0046]
Moreover, since the precast plate at the top is supported by the protective fence, the precast plate itself can be reliably prevented from falling. Support with anchor bolts alone may not be suitable depending on the ground, especially when supporting the precast plate located at the top requires a greater support strength than the side precast plate, which is insufficient. In these cases, it can be an effective means. Moreover, it is possible to omit the complicated construction of anchor bolts.
[0047]
[Brief description of the drawings]
FIG. 1 is a cross-sectional view showing a construction procedure of a method for constructing a widening tunnel.
FIG. 2 is a cross-sectional view showing a construction procedure of a method for constructing a widening tunnel.
FIG. 3 is a cross-sectional view showing a construction procedure of a method for constructing a widening tunnel.
FIG. 4 is a cross-sectional view showing a construction procedure of a method for constructing a widening tunnel.
FIG. 5 is a cross-sectional view showing a construction procedure of a method for constructing a widening tunnel.
[Explanation of symbols]
2 Existing tunnel 4 New tunnel 14 Guard fence 18 Precast version 20 Air gap

Claims (2)

既設トンネルを幅方向に拡幅して、アーチ状の拡幅トンネルを築造する方法であって、既設トンネル内を車両を通行させつつ、既設トンネルの外側の一側方及び上方の地盤を掘削する工程と、掘削された新設トンネルの掘削壁面の一側部および頂部に、円弧状に湾曲した矩形面状の複数のプレキャスト版を互いに連結して設置し、上記掘削壁面とプレキャスト版との空隙に裏込注入する工程と、設置された頂部のプレキャスト版より掘削底面に亘って、垂直方向に防護柵を設置する工程と、上記プレキャスト版と防護柵とで囲まれた新設トンネルの 空間内に車両を通行させつつ、既設トンネルを撤去する工程と、既設トンネル撤去後の新設トンネルの残りの掘削壁面にプレキャスト版を設置し、上記頂部のプレキャスト版と連結すると共に、上記掘削壁面とプレキャスト版との空隙に裏込注入する工程と、その後、防護柵を撤去する工程とからなり、上記頂部のプレキャスト版は、その周方向端部が既設トンネル側に張り出して設けられていることを特徴とする拡幅トンネルの築造方法。A method of constructing an arch-shaped widened tunnel by widening an existing tunnel in the width direction, and excavating the ground on one side and the upper side of the existing tunnel while passing a vehicle through the existing tunnel; and A plurality of precast plates having a rectangular surface curved in an arc shape are connected to each other on one side and the top of the excavated wall surface of the newly excavated tunnel, and back into the gap between the excavated wall surface and the precast plate. The process of injecting, the process of installing a protective fence in the vertical direction from the installed precast plate to the bottom of the excavation, and passing the vehicle through the space of the new tunnel surrounded by the precast plate and the protective fence While removing the existing tunnel, and installing the precast plate on the remaining excavation wall of the new tunnel after the existing tunnel removal, and connecting with the above precast plate, It consists of a step of back-filling the gap between the excavation wall surface and the precast plate, and then a step of removing the protective fence. The top precast plate is provided with its circumferential end projecting to the existing tunnel side. The construction method of the widening tunnel characterized by being. 既設トンネルを幅方向に拡幅して、アーチ状の拡幅トンネルを築造する方法であって、既設トンネル内を車両を通行させつつ、既設トンネルの外側の一側方及び上方の地盤を掘削する工程と、掘削された新設トンネルの掘削壁面の一側部および頂部に、円弧状に湾曲した矩形面状の複数のプレキャスト版を互いに連結して設置し、上記掘削壁面とプレキャスト版との空隙に裏込注入する工程と、設置された頂部のプレキャスト版より掘削底面に亘って、垂直方向に防護柵を設置する工程と、上記プレキャスト版と防護柵とで囲まれた新設トンネルの 空間内に車両を通行させつつ、既設トンネルを撤去する工程と、既設トンネル撤去後の新設トンネルの残りの掘削壁面にプレキャスト版を設置し、上記頂部のプレキャスト版と連結すると共に、上記掘削壁面とプレキャスト版との空隙に裏込注入する工程と、その後、防護柵を撤去する工程とからなり、上記頂部のプレキャスト版は、その周方向端部が上記防護柵より張り出して設けられていることを特徴とする拡幅トンネルの築造方法。 A method of constructing an arch-shaped widened tunnel by widening an existing tunnel in the width direction, and excavating the ground on one side and the upper side of the existing tunnel while passing a vehicle through the existing tunnel; and A plurality of precast plates having a rectangular surface curved in an arc shape are connected to each other on one side and the top of the excavated wall surface of the newly excavated tunnel, and back into the gap between the excavated wall surface and the precast plate. A step of injecting, a step of installing a protective fence in the vertical direction from the precast plate at the top to the bottom of the excavation, and a new tunnel surrounded by the precast plate and the protective fence. The process of removing the existing tunnel while allowing the vehicle to pass through the space, and installing a precast plate on the remaining excavation wall of the new tunnel after the removal of the existing tunnel, connecting with the precast plate at the top, and It consists of the step of backfilling the gap with the precast plate and the step of removing the protective fence, and the precast plate at the top is provided with its circumferential end protruding from the protective fence. A method for constructing a widening tunnel.
JP2002083417A 2002-03-25 2002-03-25 How to build a widening tunnel Expired - Fee Related JP3789100B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002083417A JP3789100B2 (en) 2002-03-25 2002-03-25 How to build a widening tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002083417A JP3789100B2 (en) 2002-03-25 2002-03-25 How to build a widening tunnel

Publications (2)

Publication Number Publication Date
JP2003278479A JP2003278479A (en) 2003-10-02
JP3789100B2 true JP3789100B2 (en) 2006-06-21

Family

ID=29231208

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002083417A Expired - Fee Related JP3789100B2 (en) 2002-03-25 2002-03-25 How to build a widening tunnel

Country Status (1)

Country Link
JP (1) JP3789100B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102102521B (en) * 2010-12-29 2012-11-28 上海浦东工程建设管理有限公司 Method for broadening and rebuilding soft soil shallow tunnel in operation state
CN103953351B (en) * 2014-05-20 2016-08-17 长安大学 Enlarging construction method is dug under existing tunnel in the case of a kind of uninterrupted traffic
JP7248236B2 (en) * 2019-01-23 2023-03-29 鉄建建設株式会社 Tunnel repair method and equipment for existing tunnels
CN110529165B (en) * 2019-09-20 2021-02-26 北京中矿创新联盟能源环境科学研究院 Anchor rod/cable drilling and supporting integrated equipment
CN112727501B (en) * 2020-12-08 2023-01-24 中交一公局集团有限公司 Temporary supporting structure of transverse passage and construction method of transverse passage
CN113802564B (en) * 2021-09-24 2022-09-02 中水珠江规划勘测设计有限公司 Construction method of deep foundation pit between existing operation tunnels
CN117449864B (en) * 2023-12-22 2024-03-05 洛阳高飞桥隧机械股份有限公司 Tunnel widening driving protection construction device and tunnel widening construction method

Also Published As

Publication number Publication date
JP2003278479A (en) 2003-10-02

Similar Documents

Publication Publication Date Title
CN101294447B (en) Buildings pile underpinning method
KR20130105147A (en) The construction method of steel-concrete underpass
JP3586864B2 (en) Underground structure construction method and elevated traffic path
JP5843413B1 (en) Lowering method of existing tunnel
JP3789100B2 (en) How to build a widening tunnel
JP2020084474A (en) Widening construction method of existing tunnel
JP6170268B1 (en) Ballast track subbase formation method
JP6944882B2 (en) How to build an invert in an existing tunnel
JP6872931B2 (en) Invert construction method
JP3893056B2 (en) Construction method of underground structure
JP6144726B2 (en) Rehabilitation method for mountain road tunnels on expressway and suspension pier for rehabilitation method
JP3796524B2 (en) Tunnel widening method and tunnel
JP2004285711A (en) Construction method for enlarged tunnel
CN107513963A (en) A kind of roadbed concrete guardrail recycles construction method
JPH0258606A (en) Repair of median strip and fender block used therefor
JP3188328B2 (en) Structure of concrete precast guard fence
JP2992400B2 (en) Underground construction method
JP3188436B2 (en) Construction method of guard fence using precast guard fence block made of concrete and structure of guard fence using precast guard fence block constructed by the construction method
JP7501869B2 (en) Mountain tunnel renewal method and lining structure
JP2020117928A (en) Tunnel repairing method and repairing device for existing tunnel
JP6871344B1 (en) Tunnel repair method and repair equipment for existing tunnels
KR200212421Y1 (en) An electric pole foundation for electric railway
CN213869893U (en) Reserved structure for long-term construction of subway station end
JP2023127632A (en) Method for installing guard fence and guard fence
KR102146635B1 (en) Apparatus for protecting road gutter and installation method of road gutter using the same

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041228

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050524

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050720

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050823

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20051005

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060228

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060327

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100407

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110407

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120407

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130407

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)