JP3692043B2 - Construction method of three-dimensional detour - Google Patents
Construction method of three-dimensional detour Download PDFInfo
- Publication number
- JP3692043B2 JP3692043B2 JP2001030605A JP2001030605A JP3692043B2 JP 3692043 B2 JP3692043 B2 JP 3692043B2 JP 2001030605 A JP2001030605 A JP 2001030605A JP 2001030605 A JP2001030605 A JP 2001030605A JP 3692043 B2 JP3692043 B2 JP 3692043B2
- Authority
- JP
- Japan
- Prior art keywords
- bridge
- traffic
- road
- detour
- dimensional
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Road Paving Structures (AREA)
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、立体式迂回路の構築方法に関するものである。
【0002】
【従来の技術】
交通路等を開削して地下にトンネル等の構造物を構築する施工方法では、作業区間の交通路を撤去して掘削を行い、地下に構造物を構築した後に作業区間の交通路を復元するため、作業区間の交通路の通行が規制されていた。
【0003】
このように、通行規制された交通路では、以下の方法によって既存の車両の通行を確保していた。
(1)作業区間の交通路の周辺に構築した同一平面上の迂回路を経由して既存の車両を通行させる、迂回路による通行方法。
(2)作業区間の交通路を分割して規制し、部分的に車線の通行を停止して施工を行い、同時に他の車線のみを用いて交互に既存の車両を通行させる、分割規制による通行方法。
【0004】
【発明が解決しようとする課題】
しかしながら、従来の作業区間における交通路の通行方法では、以下の問題が存在していた。
(1)前記迂回路による通行方法では、同一平面上の迂回路の構築用地を確保しなければならず、また、同一平面上の迂回路の構築に係る施工期間を長く必要とするため、施工費が高くなっていた。
【0005】
(2)前記分割規制による通行方法では、作業区間の交通路の通行量が制限されるため、交通渋滞が発生し、周辺地域社会の環境及び経済活動に対する影響が大きくなり、また、一括して施工が行えないため、施工期間が長く必要となり、施工費が高くなっていた。
【0006】
したがって、作業区間の交通路の直上に立体式迂回路を構築して通行を確保することが望まれるが、立体式迂回路の構築は交通路の通行を停止する必要があり、周辺地域社会の環境及び経済活動に対する影響が大きくなるため、効果的な施工方法の開発が望まれていた。
【0007】
そこで本発明は、既存の交通路上に作業領域を確保する場合において、迂回路の構築用地を確保する必要がなく、既存の交通に対する影響を低減して立体式迂回路を容易に構築することで、周辺地域社会の環境および経済活動に対する影響を低減するとともに、施工期間の短縮及び施工費の削減が実現可能な立体式迂回路の構築方法を提供することを課題とする。
【0008】
【課題を解決するための手段】
本発明は、前記課題を解決すべく構成されるものであり、請求項1に記載の発明は、交通路における立体式迂回路の構築方法であって、(1)交通路に立設した作業台から分割された橋梁を可動式架台に受け替え、交通路で可動式架台を移動させることにより、作業台から分割された橋梁を順次に送り出し、可動式架台によって搬送された分割された橋梁を、交通路に沿って所定の間隔をあけて打設した複数の支柱間に架設することで、前記交通路の上方に橋梁を構築する、橋梁送り出し工程と、(2)橋梁の所定部を降下させて、橋梁と交通路を接続することで、橋梁によって交通路に立体式迂回路を構築する、橋梁降下工程とを含むことを特徴とする。
【0009】
ここで、交通路とは、道路、鉄道線路等の各種交通機関の通行路をいう。
【0010】
請求項1に記載の発明によれば、橋梁降下工程では、橋梁の所定部を降下させることで、交通路に立体式迂回路を容易に構築できるため、施工期間を短縮することができる。
【0012】
また、交通路の上方空間を利用して、分割された橋梁を作業台から支柱間に順次に送り出すことで、橋梁を交通路の上方に構築するため、既存の交通路の通行に影響を与えることなく施工を行うことができる。
さらに、橋梁を交通路の上方空間である作業台で分割製作することができるため、搬入が容易になるとともに、施工用地を縮小することができる。
【0014】
また、可動式架台によって分割された橋梁の送り出しを、交通路の上方空間を利用して行うため、既存の交通路の通行に影響を与えることなく、施工を行うことができる。
【0015】
また、請求項2に記載の発明は、請求項1に記載の立体式迂回路の構築方法であって、橋梁降下工程において、橋梁の所定部を支柱の降下装置によって降下させることを特徴とする。
【0016】
これによれば、橋梁の降下を目的とした装置を交通路に設置する必要がないことから、橋梁の降下作業が簡易化されるため、夜間等の交通路の停止時間帯に施工を完了することができる。
【0017】
また、請求項3に記載の発明は、請求項1または請求項2に記載の立体式迂回路の構築方法であって、前記橋梁が仮設橋であることを特徴とする。
【0018】
ここで、請求項3に記載の発明を必要とする交通路は、地下に構造物を構築するための開削工事、あるいは、交通路の破損、補修等により、既存の交通路上に作業領域を確保する必要があり、一部区間を作業区間として通行を規制する交通路である。
また、仮設橋とは、既存の交通路上の作業期間のみに使用されるものであり、作業終了後は撤去されることになる。
【0019】
請求項3に記載の発明によれば、仮設の立体式迂回路を既存の交通路の通行に影響を与えずに容易に構築することができる。
【0020】
したがって、本発明の立体式迂回路の構築方法では、交通路の上方に既存の交通に対する影響を低減して立体式迂回路を容易に構築し、立体式迂回路と交通路を容易に接続することができるため、周辺地域社会の環境及び経済活動に対する影響が低減されるとともに、施工期間の短縮及び施工費の削減を図ることができる。
【0021】
【発明の実施の形態】
以下、添付図面に基づいて本発明の実施の形態を詳細に説明する。なお、同一要素には同一符号を用い、重複する説明は省略するものとする。
【0022】
[第1実施形態]
本発明の第1実施形態に係る立体式迂回路の構築方法は、自動車の道路、列車の線路、あるいは歩道等の交通路に適用可能であるが、この実施の形態では、自動車の道路を開削して地下にトンネル等の構造物を構築する施工方法を対象とし、地下に構造物を構築するために規制された作業区間における車両の通行を、仮設の立体式迂回路に盛り替える場合を例として説明する。
【0023】
図1は仮設橋送り出し工程を示した図で、作業台及び支柱の側面図である。図2は仮設橋送り出し工程を示した図で、(a)は図1のA−A断面図、(b)は図1のB−B断面図である。図3は仮設橋送り出し工程を示した図で、仮設橋を送り出した際を示す側面図である。図4は仮設橋送り出し工程を示した図で、図3のC−C断面図である。図5は仮設橋降下工程を示した図で、(a)は仮設橋の側面図、(b)は仮設橋の降下側面図である。図6は仮設橋降下工程を示した図で、仮設橋降下後の地下トンネル等の工事状況図(図5(b)のD−D断面図)である。
【0024】
まず、本発明の第1実施形態に係る立体式迂回路の構築方法における各装置を説明する。
作業台6は後記する仮設橋2を分割製作する作業場としての役割を果たすものであり、図1,図2(a)に示すように、道路3の両側の路肩3’,3’に立設している脚部7,7と、その脚部7,7の上部に架設されている板状のステージ8とから構成されている、門型形状の台である。この作業台6のステージ8は安定性を考慮して複数の脚部7によってステージ8を支持するのが好ましい。
【0025】
そして、支柱4及び支持梁5は仮設橋2を支持する役割を果たすものであり、、図1,図2(b)に示すように、支柱4は道路3の両側の路肩3’,3’に左右対称に打設されている棒状の柱であり、一箇所において数本で対となる各支柱4,4の上部に支持梁5が道路3を横断する方向に架設されていて、この支持梁5で仮設橋2を支持する。さらに、支持梁5は支柱4に設置したジャッキ構造等の降下装置(図示せず)によって垂直方向に移動することができる。
【0026】
また、可動式架台9は後記する分割された仮設橋2’を作業台6から支柱4に搬送する役割を果たすものであり、図3,図4に示すように、道路3の両側の路肩3’,3’に立設している脚部11,11の上部に、支持梁10が道路3を横断する方向に架設されていて、この支持梁10で仮設橋2を支持する。さらに、脚部11の下部に車輪12が設置されていて、後記する2本のレール13上を可動式架台9が移動できる。
そして、2本のレール13は、道路3の路肩3’において、道路3の長手方向に沿って仮設架台9の脚部11,11と同じ幅をあけて敷設されている。
ここで、作業台6、支柱4及び可動式架台9は、仮設橋2を支持したときの荷重に耐えられるものであれば、その材料及び構造は限定されるものではないが、仮設橋2を支持したときの安定性を十分考慮した構造とする必要がある。
【0027】
そして、仮設橋2は立体式迂回路1を構成する役割を果たすものであり、図3,図4に示すように、上面に路面15を有する橋であって、長手方向に複数の分割された仮設橋2’から構成されている。この分割された仮設橋2’は、車両20の通行を安全に行えるものであれば、その材質及び構造は限定されるものではないが、作業台6のステージ8上で製作されることを考慮すると、作業工程を簡略化して短期間に製作することが望まれるため、例えば、鋼材などによるトラス構造の骨組みに、鋼板又は鉄筋コンクリート製などの板を路面15として設置する、組立式の構造が好ましい。
【0028】
次に、本発明の第1実施形態に係る立体式迂回路の構築方法について説明する。
(1)前記仮設橋送り出し工程では、図1,図2(a)に示すように、作業台6を道路3の所定の位置に立設する。これにより、作業台6のステージ8は道路3の直上に配置される。
次に、図1,図2(b)に示すように、各支柱4を道路3の長手方向に所定の間隔をあけて道路3に打設する。これにより、各支柱4の上部に架設した支持梁5は道路3の直上に配置される。
次に、図3,図4に示すように、道路3の路肩3’に仮設架台9の脚部11,11と同じ幅をあけて2本のレール13,13を敷設する。
そして、レール13,13上に可動式架台9を立設する。これにより、可動式架台9は道路3を移動することができるため、可動式架台9の支持梁10は道路3の直上を移動することができる。
【0029】
次に、作業台6のステージ8を作業場として、分割された仮設橋2’を道路3の直上で製作する。この分割された仮設橋2’は分割した部材で構成されるため、施工現場に容易に搬入し、仮設橋2の製作を道路3の上方空間で行うことにより、仮設橋2の搬入におけるトラック等の搬送機械及びクレーン等の揚重機が小型化できる。
次に、図3,図4に示すように、分割された仮設橋2’を可動式架台9の支持梁10に受け替える。そして、道路3の直上で可動式架台9を所定の位置まで移動させて、長手方向に隣接する支柱4間に架設することにより、支柱4の支持梁5に受け替える。
【0030】
次に、図5(a)に示すように、仮設橋送り出し工程を繰り返すことにより、道路3の直上に分割した仮設橋2’によって構成された仮設橋2を構築する。
また、仮設橋降下工程の後において、作業台6、可動式架台9及びレール13は以降の工程で使用しないため、作業に影響を与えるのであれば撤去するのが好ましい。
【0031】
以上、仮設橋送り出し工程では、道路3の上方空間を利用して、仮設橋2を道路3の上方に構築するため、既存の車両30の通行に影響を与えずに施工を行うことができる。
【0032】
そして、(2)立体式迂回路降下工程では、図5(b)に示すように、分割された仮設橋2’を支持している各支柱4の支持梁5の位置を、各支柱4ごとに定められた所定位置まで降下させることで仮設橋2に斜路部Lを設け、仮設橋2の両端部に摺付け部14を設置して道路3と接続することで、道路3に立体式迂回路1を容易に短時間で構築できる。
このとき、支持梁5の降下は支柱4に設置された降下装置(図示せず)によって行う。この降下装置の構造は限定されるものではないが、ジャッキ構造等の簡易な構造のものが好ましい。例えば、先端部が支持梁5を支持しているロッドを縮退させることにより、その位置を降下させる、油圧ジャッキ式装置等を用いることができる。
【0033】
最後に、図6に示すように、道路3の直上にある立体式迂回路1の路面15を使用して既存の車両30の通行を確保しながら、立体式迂回路1の直下の道路3を掘削して地下に構造物を構築し、道路3を復元した後に、立体式迂回路1を撤去する。
【0034】
以上、前記仮設橋降下工程では、仮設橋2の降下を目的とした装置を道路3に設置する必要がなく、仮設橋2の降下作業が簡易化され、夜間等の道路3の停止時間帯に施工を完了することができる。
【0035】
[第2実施形態]
前記第1実施形態では、仮設の立体式迂回路を構築する場合について説明したが、本発明の立体式迂回路の構築方法は、下部における作業が終了した後に、立体式迂回路の撤去を行わずに、そのまま本設橋として使用する立体式迂回路(以下、「本設の立体式迂回路」という)を構築する場合にも適用することができる。
この第2実施形態では、橋梁を使用して本設の立体式迂回路を構築する場合を例として説明する。
【0036】
図7は本設の立体式迂回路の橋梁降下工程を示した図で、(a)は橋梁の側面図、(b)は橋梁の降下側面図である。図8は本設の立体式迂回路を示した図7(b)のE−E断面図である。図9は橋梁送り出し工程を示した図で、(a)は橋梁を送り出した際を示す正面断面図、(b)は補強用桁を送り出した際を示す正面断面図である。
【0037】
この本設の立体式迂回路1’の構築方法は、前記仮設の立体式迂回路1の構築方法と略同様の構成となっており、橋梁20と仮設橋2の構造のみが異なっている。すなわち、橋梁20は、図7及び図8に示すように、周辺地域に対する騒音を低減するため、橋梁20を構成する中空の橋桁21の中空部22に吸音材23を設けるとともに、本設橋として長期間の使用に対する耐久性を備える必要があるため、橋梁20の下面に補強用桁24を備えた構造である。そのため、可動式架台9による送り出し工程において、図9(a)に示すように、まず、分割した橋梁20’を可動式架台9によって送り出し、支柱4の支持梁5に仮受けする。次に、図9(b)に示すように、補強用桁24を可動式架台9によって送り出し、分割した橋梁20’と一体化した後に、支柱4の支持梁5に受け替えることにより、道路3の直上に橋梁20を構築する。
これにより、騒音を低減するとともに、耐久性に優れた本設の立体式迂回路1’を、道路3の通行に影響を与えずに容易に構築することができる。
【0038】
以上、本発明を前記実施形態によって説明したが、本発明は前記実施形態に限定されるものではない。前記本発明の立体式迂回路の構築方法と実質的に同一な構成を有し、同様な作用効果を奏するものは、いかなるものであっても本発明の技術的範囲に包含される。
【0039】
【発明の効果】
したがって、本発明の立体式迂回路の構築方法では、交通路の上方に既存の交通に対する影響を低減して立体式迂回路を容易に構築し、立体式迂回路と交通路を容易に接続することができることから、周辺地域社会の環境及び経済活動に対する影響を低減するとともに、施工期間の短縮及び施工費の削減を図ることができる。
【図面の簡単な説明】
【図1】本発明の第1実施形態に係る仮設橋送り出し工程を示した図で、作業台及び支柱の側面図である。
【図2】本発明の第1実施形態に係る仮設橋送り出し工程を示した図で、(a)は図1のA−A断面図、(b)は図1のB−B断面図である。
【図3】本発明の第1実施形態に係る仮設橋送り出し工程を示した図で、仮設橋を送り出した際を示す側面図である。
【図4】本発明の第1実施形態に係る仮設橋送り出し工程を示した図で、図3のC−C断面図である。
【図5】本発明の第1実施形態に係る仮設橋降下工程を示した図で、(a)は仮設橋の側面図、(b)は架設橋の降下側面図である。
【図6】本発明の第1実施形態に係る仮設橋降下工程を示した図で、仮設橋降下後の地下トンネル等の工事状況図(図5(b)のD−D断面図)である。
【図7】本発明の第2実施形態に係る本設の立体式迂回路の橋梁降下工程を示した図で、(a)は橋梁の側面図、(b)は橋梁の降下側面図である。
【図8】本発明の第2実施形態に係る本設の立体式迂回路を示した図7(b)のE−E断面図である。
【図9】本発明の第2実施形態に係る橋梁送り出し工程を示した図で、(a)は橋梁を送り出した際を示す正面断面図、(b)は補強用桁を送り出した際を示す正面断面図である。
【符号の説明】
1.......仮設の立体式迂回路
1’......本設の立体式迂回路
2.......仮設橋
2’......分割された仮設橋
3.......既存の道路
3’......既存の道路の路肩
4.......支柱
5.......支柱の支持梁
6.......作業台
7.......作業台の脚部
8.......作業台のステージ
9.......可動式架台
10.......可動式架台の支持梁
11.......可動式架台の脚部
12.......可動式架台の車輪
13.......レール
14.......摺付け部
15.......立体式迂回路の道路
20.......橋梁
20’......分割された橋梁
21.......橋桁
22.......橋桁の中空部
23.......吸音材
24.......補強用桁
30.......車両
L.......立体式迂回路の斜路部[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing a three-dimensional detour.
[0002]
[Prior art]
In construction methods that excavate traffic roads and build structures such as tunnels underground, excavate and excavate the traffic roads in the work section, and then restore the traffic roads in the work section after building the structure underground For this reason, traffic on the work section was restricted.
[0003]
In this way, on traffic routes that are restricted in traffic, the passage of existing vehicles has been secured by the following method.
(1) A method of passing by a detour that allows an existing vehicle to pass through a detour on the same plane constructed around the traffic route of the work section.
(2) Traffic by division regulation that divides and regulates the traffic route of the work section, partially stops lane traffic and performs construction at the same time, and allows existing vehicles to pass alternately using only other lanes. Method.
[0004]
[Problems to be solved by the invention]
However, the following problems existed in the conventional method of passing traffic in the work section.
(1) In the method of passing by the detour, it is necessary to secure a site for constructing a detour on the same plane, and the construction period for constructing the detour on the same plane is long. The cost was high.
[0005]
(2) In the traffic method based on the above-mentioned division regulation, the traffic volume of the work section is limited, resulting in traffic congestion, increasing the impact on the environment and economic activities of the surrounding community. Since construction was not possible, the construction period was long and construction costs were high.
[0006]
Therefore, it is desirable to secure a traffic by constructing a three-dimensional detour directly above the traffic route in the work section, but the construction of the three-dimensional detour needs to stop the traffic route, Development of an effective construction method has been desired because of the large impact on the environment and economic activities.
[0007]
Therefore, the present invention eliminates the need to secure a detour construction site when securing a work area on an existing traffic route, and reduces the influence on existing traffic and easily constructs a three-dimensional detour. It is an object of the present invention to provide a method for constructing a three-dimensional detour that can reduce the influence on the environment and economic activities of surrounding communities, and can shorten the construction period and the construction cost.
[0008]
[Means for Solving the Problems]
The present invention is configured to solve the above-mentioned problems, and the invention according to
[0009]
Here, the traffic route means a traffic route of various transportation such as a road and a railroad track.
[0010]
According to the invention described in
[0012]
In addition , by using the space above the traffic road, the divided bridges are sequentially sent from the work bench between the columns, so that the bridge is constructed above the traffic road, affecting the traffic on the existing traffic road. Construction can be performed without any problems.
Furthermore , since the bridge can be divided and manufactured on a work table which is an upper space of the traffic road, it is easy to carry in and the construction site can be reduced.
[0014]
In addition , since the bridge divided by the movable mount is sent out using the space above the traffic road, the construction can be performed without affecting the traffic on the existing traffic road.
[0015]
The invention described in
[00 16 ]
According to this, since it is not necessary to install a device for descent of the bridge in the traffic road, the descent work of the bridge is simplified, so the construction is completed in the traffic road stoppage time such as at night. be able to.
[0017]
The invention described in
[0018]
Here, the traffic road that requires the invention according to claim 3 secures a work area on the existing traffic road by excavation work for constructing the structure underground, or damage or repair of the traffic road. It is a traffic route that regulates traffic with a section as a work section.
In addition, the temporary bridge is used only during the work period on the existing traffic road, and is removed after the work is completed.
[0019]
According to the third aspect of the present invention, it is possible to easily construct a temporary three-dimensional detour without affecting the passage of existing traffic paths.
[00 20 ]
Therefore, in the method for constructing the three-dimensional detour according to the present invention, the three-dimensional detour is easily constructed by reducing the influence on the existing traffic above the traffic route, and the three-dimensional detour and the traffic route are easily connected. Therefore, the influence on the environment and economic activities of the surrounding community can be reduced, and the construction period can be shortened and the construction cost can be reduced.
[00 21 ]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. In addition, the same code | symbol is used for the same element and the overlapping description shall be abbreviate | omitted.
[00 22 ]
[First embodiment]
The method for constructing a three-dimensional detour according to the first embodiment of the present invention is applicable to traffic roads such as automobile roads, train tracks, or sidewalks. In this embodiment, car roads are excavated. For example, a case where the construction method of building a structure such as a tunnel in the basement is targeted, and the traffic of the vehicle in the work section regulated to build the structure in the basement is replaced with a temporary three-dimensional detour Will be described.
[00 23 ]
FIG. 1 is a side view of a workbench and a column, showing a temporary bridge delivery process. 2A and 2B are diagrams showing a temporary bridge feeding process, where FIG. 2A is a cross-sectional view taken along the line AA in FIG. 1, and FIG. 2B is a cross-sectional view taken along the line BB in FIG. FIG. 3 is a side view showing the temporary bridge delivery process, and shows the state when the temporary bridge is delivered. FIG. 4 is a view showing a temporary bridge feeding process, and is a cross-sectional view taken along the line CC of FIG. FIGS. 5A and 5B are diagrams showing a temporary bridge lowering process, where FIG. 5A is a side view of the temporary bridge, and FIG. 5B is a lower side view of the temporary bridge. FIG. 6 is a diagram showing the temporary bridge descent process, and is a diagram showing the construction status of the underground tunnel and the like after the temporary bridge descent (DD sectional view of FIG. 5B).
[00 24 ]
First, each device in the method for constructing a three-dimensional detour according to the first embodiment of the present invention will be described.
The work table 6 serves as a work place for dividing the
[00 25 ]
The
[0026]
The
The two
Here, as long as the work platform 6, the
[00 27 ]
And the
[00 28 ]
Next, a method for constructing a three-dimensional detour according to the first embodiment of the present invention will be described.
(1) In the temporary bridge delivery step, the work table 6 is erected at a predetermined position on the
Next, as shown in FIG. 1 and FIG. 2B, each
Next, as shown in FIGS. 3 and 4, two
Then, the
[00 29 ]
Next, using the stage 8 of the work table 6 as a work place, the divided
Next, as shown in FIGS. 3 and 4, the divided
[00 30 ]
Next, as shown in FIG. 5A, the
In addition, after the temporary bridge descent process, the work table 6, the
[0031]
Above, the provisional設橋delivery process, by utilizing the space above the
[00 32 ]
Then, (2) in the three-dimensional detour descent process, as shown in FIG. 5 (b), the position of the
At this time, the
[00 33 ]
Finally, as shown in FIG. 6, the
[00 34 ]
As described above, in the temporary bridge descent process, there is no need to install a device for descent of the
[00 35 ]
[Second Embodiment]
In the first embodiment, the case of constructing a temporary three-dimensional detour has been described. However, in the method of constructing a three-dimensional detour according to the present invention, the three-dimensional detour is removed after the work in the lower part is completed. In addition, the present invention can also be applied to a case where a three-dimensional detour (hereinafter referred to as “main three-dimensional detour”) is used as it is as a main bridge.
In the second embodiment, a case where a three-dimensional detour is constructed using a bridge will be described as an example.
[00 36 ]
FIGS. 7A and 7B are views showing the bridge descent process of the three-dimensional detour of the present installation, where FIG. 7A is a side view of the bridge, and FIG. 7B is a side view of the bridge. FIG. 8 is a cross-sectional view taken along the line E-E of FIG. FIGS. 9A and 9B are views showing a bridge sending process, in which FIG. 9A is a front sectional view showing when the bridge is sent out, and FIG. 9B is a front sectional view showing when the reinforcing beam is sent out.
[00 37 ]
This construction method of the three-dimensional detour 1 'is substantially the same as the construction method of the temporary three-
As a result, it is possible to easily construct the three-
[00 38 ]
As mentioned above, although this invention was demonstrated by the said embodiment, this invention is not limited to the said embodiment. Any device that has substantially the same configuration as the method for constructing a three-dimensional detour according to the present invention and that exhibits the same function and effect is included in the technical scope of the present invention.
[00 39 ]
【The invention's effect】
Therefore, in the method for constructing the three-dimensional detour according to the present invention, the three-dimensional detour is easily constructed by reducing the influence on the existing traffic above the traffic route, and the three-dimensional detour and the traffic route are easily connected. Therefore, it is possible to reduce the influence on the environment and economic activities of the surrounding community, shorten the construction period, and reduce the construction cost.
[Brief description of the drawings]
FIG. 1 is a view showing a temporary bridge sending-out process according to a first embodiment of the present invention, and is a side view of a work table and a column.
2A and 2B are diagrams showing a temporary bridge feeding process according to the first embodiment of the present invention, in which FIG. 2A is a cross-sectional view taken along line AA in FIG. 1, and FIG. 2B is a cross-sectional view taken along line BB in FIG. .
FIG. 3 is a view showing a temporary bridge delivery process according to the first embodiment of the present invention, and is a side view showing when the temporary bridge is delivered.
4 is a view showing a temporary bridge feeding process according to the first embodiment of the present invention, and is a cross-sectional view taken along the line CC in FIG. 3. FIG.
5A and 5B are diagrams showing a temporary bridge descent process according to the first embodiment of the present invention, in which FIG. 5A is a side view of the temporary bridge, and FIG.
FIG. 6 is a diagram showing a temporary bridge descent process according to the first embodiment of the present invention, and is a construction status diagram of the underground tunnel and the like after the temporary bridge descent (cross-sectional view taken along the line DD in FIG. 5B). .
FIGS. 7A and 7B are diagrams illustrating a bridge descent process of a permanent three-dimensional detour according to a second embodiment of the present invention, where FIG. 7A is a side view of the bridge, and FIG. 7B is a side view of the bridge descent; .
FIG. 8 is a cross-sectional view taken along line EE of FIG. 7 (b) showing a permanent three-dimensional detour according to a second embodiment of the present invention.
FIGS. 9A and 9B are diagrams showing a bridge delivery process according to a second embodiment of the present invention, where FIG. 9A is a front cross-sectional view showing when the bridge is delivered, and FIG. 9B is a diagram showing when the reinforcing beam is delivered. It is front sectional drawing.
[Explanation of symbols]
1. . . . . . . Temporary three-dimensional detour 1 '. . . . . . 1. Three-dimensional detour of permanent installation . . . . . . Temporary bridge 2 '. . . . . . Divided
Claims (3)
(1)交通路に立設した作業台から分割された橋梁を可動式架台に受け替え、前記交通路で前記可動式架台を移動させることにより、前記作業台から前記分割された橋梁を順次に送り出し、前記可動式架台によって搬送された前記分割された橋梁を、前記交通路に沿って所定の間隔をあけて打設した複数の支柱間に架設することで、前記交通路の上方に橋梁を構築する、橋梁送り出し工程。
(2)前記橋梁の所定部を降下させて、前記橋梁と前記交通路を接続することで、前記橋梁によって前記交通路に立体式迂回路を構築する、橋梁降下工程。A method for constructing a three-dimensional detour on a traffic road, comprising the following steps.
(1) instead receives the bridges split from worktable erected to exchange passage movable platform, by moving the movable platform in the transport path, successively to the divided bridges from the worktable The divided bridge transported by the movable platform is erected between a plurality of struts placed at predetermined intervals along the traffic path , so that a bridge is formed above the traffic path. Bridge delivery process to build.
(2) A bridge lowering step of constructing a three-dimensional detour in the traffic road by the bridge by lowering a predetermined portion of the bridge and connecting the bridge and the traffic road.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001030605A JP3692043B2 (en) | 2000-09-08 | 2001-02-07 | Construction method of three-dimensional detour |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000-272920 | 2000-09-08 | ||
JP2000272920 | 2000-09-08 | ||
JP2001030605A JP3692043B2 (en) | 2000-09-08 | 2001-02-07 | Construction method of three-dimensional detour |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002155501A JP2002155501A (en) | 2002-05-31 |
JP3692043B2 true JP3692043B2 (en) | 2005-09-07 |
Family
ID=26599526
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001030605A Expired - Fee Related JP3692043B2 (en) | 2000-09-08 | 2001-02-07 | Construction method of three-dimensional detour |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3692043B2 (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4519588B2 (en) * | 2004-09-14 | 2010-08-04 | 鹿島建設株式会社 | Three-dimensional intersection construction method |
JP4512562B2 (en) * | 2006-03-16 | 2010-07-28 | 前田建設工業株式会社 | Approach section construction method |
KR100777777B1 (en) | 2006-09-27 | 2007-11-21 | (주)에스텍컨설팅그룹 | Earthwork temporary ramp using mainsteel structure |
CN102635061B (en) * | 2012-04-18 | 2014-05-07 | 中建二局第三建筑工程有限公司 | Mountain stream river-crossing cable-stayed chain trestle and hoisting method thereof |
CN105568799A (en) * | 2016-01-22 | 2016-05-11 | 绍兴县明煌建材科技有限公司 | Efficient assembly type transportation junction fast and convenient to use |
CN113914224A (en) * | 2021-10-18 | 2022-01-11 | 北京城乡建设集团有限责任公司 | Installation method of cross-lane construction support |
-
2001
- 2001-02-07 JP JP2001030605A patent/JP3692043B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2002155501A (en) | 2002-05-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4504910B2 (en) | Dolly and method of erection of temporary pier using it | |
US11391004B1 (en) | Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder | |
JP5477898B2 (en) | Construction equipment and construction method for foundation work of directly elevated viaduct | |
KR20210054303A (en) | Concrete lining formwork for tunnels with sloped construction | |
CN103255693B (en) | A kind of assembled stereoscopic urban road system and installation construction | |
KR101040731B1 (en) | Movable temporary structure for constructing composite covering arch structure | |
JP5184248B2 (en) | Construction method of level crossing | |
JP2003253623A (en) | Rebuilding construction method for bridge beam | |
JP3692043B2 (en) | Construction method of three-dimensional detour | |
JP2000230205A (en) | Elevated track construction method and device | |
JP5187969B2 (en) | Overhead viaduct construction equipment and construction method | |
CN112211112A (en) | Steel box girder installation method adopting double-guide-girder erection machine on existing bridge | |
CN111705682A (en) | Construction method and equipment for removing and rebuilding superstructure of widened bridge across electrified railway | |
CN112610244B (en) | Prefabricated part for expanding existing elevated operation subway station platform and installation method thereof | |
CN111172819B (en) | Platform for assembling and walking shield trailer and construction method thereof | |
CN103410104B (en) | The bearing replacement method and apparatus of overhead road of city | |
JP2000008304A (en) | Pedestal for rail road work beam and execution method of pedestal for rail road work beam | |
JP3682247B2 (en) | Construction method of elevated traffic route | |
JP7003376B2 (en) | Construction method of structure | |
JP3940587B2 (en) | Construction method of divided bridge type traffic route | |
KR101653559B1 (en) | Method of repairing railway | |
JP4519588B2 (en) | Three-dimensional intersection construction method | |
CN209875161U (en) | Shield constructs construction jack-up and horizontal transport equipment | |
JPS5829388B2 (en) | Approach work equipment for railroad tracks, etc. | |
KR20170139824A (en) | Apparatus of Installing Pillar for Mulriplex arch tunnel and Installing Method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20041015 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20041027 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20041125 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050608 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050617 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 3692043 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090624 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100624 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110624 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110624 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120624 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130624 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130624 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140624 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |