JP3612761B2 - Construction method of underground structure - Google Patents
Construction method of underground structure Download PDFInfo
- Publication number
- JP3612761B2 JP3612761B2 JP32706594A JP32706594A JP3612761B2 JP 3612761 B2 JP3612761 B2 JP 3612761B2 JP 32706594 A JP32706594 A JP 32706594A JP 32706594 A JP32706594 A JP 32706594A JP 3612761 B2 JP3612761 B2 JP 3612761B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- underground
- small
- basement
- pillar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Foundations (AREA)
Description
【0001】
【産業上の利用分野】
本発明は、地面に打込まれる構真柱を用いて構築される地下構造物の構築法に関する。
【0002】
【従来の技術】
多層階ビル等の地下架構部分を構築するにあたって、構真柱を用いた逆打工法が採用されている。この逆打工法を行う場合、施工性,省力化および省仮設化等を考慮してフラットスラブ工法(特開昭61−261556号公報,特開平3−72119号公報参照)が用いられることがある。即ち、フラットスラブ工法では梁を用いることなく、地面を地下階の階層毎に掘削しつつ、掘削した底面部分にコンクリートを打設して床面を構築するようになっている。
【0003】
【発明が解決しようとする課題】
しかしながら、かかる従来のフラットスラブ工法を用いた逆打工法では、次に列挙するような課題があった。
【0004】
▲1▼下層階へと掘削を行う際に上層階のフラットスラブが存在するため、このフラットスラブが邪魔となって掘削効率が低下すると共に、換気設備や照明設備を各スラブ毎に設ける必要がある。
【0005】
▲2▼土水圧等の水平力をフラットスラブで受けているために、このフラットスラブに形成する下層階を掘削するための仮設開口部を任意の位置に設けることができず、この点からも掘削効率が低下する。
【0006】
▲3▼上層階のフラットスラブのコンクリートが硬化するのを待って下層階の掘削を行う必要があるため、工期が長期化する。
【0007】
そこで、本発明はかかる従来の課題に鑑みて、水平力を一階床面を構成する梁と連続地中壁とで受け持たせると共に、本設小梁を切梁として兼用することにより、地下部分の架構を施工していく段階でのフラットスラブを不要とし、工期の短縮化および経費削減を図ることができる地下構造物の構築法を提供することを目的とする。
【0008】
かかる目的を達成するために本発明は、連続地中壁内に杭と共に構真柱を打込む地下支柱打設工程と、打設された構真柱の上端部に一階部分の梁部材を取付ける一階梁構築工程と、構築された梁下で地下階の一階高さ分だけ掘削する掘削工程と、掘削により露出した構真柱に掘削した地下階部分の大梁を取付ける大梁構築工程と、構築された大梁の先端部間に本設小梁を切梁兼用として格子状をなすように接続する小梁構築工程とを備え、掘削工程,大梁構築工程および小梁構築工程を繰り返して、地下架構を構築する。
本発明において、梁接合部材を構真柱に載置した後、前記大梁を前記梁接合部材に固定することにより前記大梁を構真柱に対してピン結合状態とすることもできる。
【0009】
【作用】
以上の構成により本発明の地下構造物の構築法にあっては、地下支柱打設工程で打込んだ構真柱の上端部に、一階梁構築工程によって梁部材を取付け、その後、掘削工程,大梁構築工程および小梁構築工程を繰り返して目的の地下階部分まで地下架構を構築することができる。このとき、一階梁構築工程でまず一階の床面を構成する梁部材が構真柱の上端部に取り付けられるので、この梁部材と連続地中壁とで地震等の水平力を支持した状態で地下部分の構築を遂行することができる。そして、前記小梁構築工程で大梁に取付けられる小梁を切梁兼用として用いるようになっているため、各地下階の床部分に作用する土水圧等を前記小梁で支持することができる。従って、目的の地下階部分まで地下架構を構築する際に、各地下階の床面部分は大梁と小梁の組付け状態で工事を進行することができる。このため、各地下階の床面部分が大きく開口され、任意の開口部分から掘削機械とか資材等を下層階に簡単に搬入できると共に、地下階全体が連通状態となることにより、良好な換気および十分な照明を確保することができ、また掘削作業性も向上させることができる。また、下層階の掘削を行う際に、各床面部分へのコンクリートの打設がないことから、工期の大幅な短縮化が達成される。
【0010】
【実施例】
以下、本発明の実施例を添付図面を参照して詳細に説明する。図1から図3は本発明にかかる地下構造物の構築法の一実施例を示し、図1は地下構造物の構築途中を示す平面図、図2は地下構造物の構築途中を示す正面図、図3は構真柱と梁との接続部分を示す拡大正面図である。
【0011】
即ち、本実施例では地下構造物として多層階ビルの地下架構10を例にとって示し、この地下架構10は構真柱12を用いた逆打工法により構築されるようになっている。尚、本実施例では前記地下架構10は、地下一階B1,地下二階B2,地下三階B3を備えて構成される。前記構真柱12は図1に示すように、構築しようとする地下架構10の外周に形成した連続地中壁14の領域内に碁盤の目状に配置され、そして、これら構真柱12は図2に示すように地中にボーリングした削孔16に杭18と共に打設される(地下支柱打設工程)。
【0012】
前記構真柱12の上端部には一階床面20を構成する梁部材としての大梁22が縦横に格子状に接続される(一階梁構築工程)。前記大梁22はH形鋼で形成され、この大梁22が外周の前記連続地中壁14に結合され、この状態で、構築されようとする地下架構10に作用する地震や土水圧等の水平力を、前記大梁22と連続地中壁14とで受け持つようになっている。
【0013】
前記一階の床面20を構成する大梁22が接続された後、この大梁22の間の開口部から掘削機械を搬入し、地下一階B1部分を掘削する(掘削工程)。そして、この掘削により露出した構真柱12に、地下一階床面24を構成する大梁26をX字状に接続し(大梁構築工程)、このX字状の大梁26の先端部間に小梁28を、格子状をなすように接続する(小梁構築工程)。前記大梁26および前記小梁28はそれぞれ大きさの異なるH形鋼で形成され、大梁26の構真柱12への接合は、図3に示すように梁接合部材30を介して行われる。
【0014】
前記梁接合部材30は前記大梁26と同じH形鋼を短く切断して用いられ、それぞれの梁接合部材30は構真柱12を中心に十字状に配置される。前記梁接合部材30は構真柱12に接合されることなく、いわゆるピン構造として構成される。また、下方のフランジ30aと構真柱12との間には、三角状の補強板32が取付けられてこの上に梁接合部材30が載置され、これにより大梁26の荷重が支持される。そして、前記梁接合部材30を構真柱12に載置した後、前記大梁26のフランジ26aおよびウエブ26bは、梁接合部材30のフランジ30aおよびウエブ30bに添え板34を介してボルト,ナットで固定される。
【0015】
前記大梁26の端部は図3に示したように端板36が固設されて、この端板36の下端部に閉塞断面の取付台38がボルト,ナットで固定される。そして、この取付台38の上側に前記小梁28が載置された状態で、小梁28が取付台38にボルト,ナットで固定される。尚、前記大梁26と小梁28との接続部分の他の実施例として図4に示すように、前記端板36および取付台38を設けることなく、小梁28から側方にブラケット40を突設し、このブラケット40を大梁26のウエブ26bにボルト,ナットで固定してもよい。
【0016】
そして、格子状に配置された前記小梁28の各端部は、地中連続壁14の内側に近接させて、これら小梁28と地中連続壁14との間にグラウト材を注入することなどにより結合し、この小梁28を切梁兼用として用いるようになっている。
【0017】
このようにして、地下一階B1の床面24を構成する大梁26および小梁28の接続が完了すると、小梁28間に形成される開口部から掘削機械を搬入して地下二階B2部分を掘削し(掘削工程)、この地下二階B2部分の構真柱12を露出する。そして、露出した構真柱12には前記地下一階B1の場合と同様に、地下二階B2の床面42を構成する大梁26を接続する(大梁構築工程)と共に、それぞれの大梁26の先端部に小梁28を接続する(小梁構築工程)。尚、地下二階B2の床面42を構成する大梁26にあっても、梁接合部材30を介して構真柱12にX字状に接続されるのは勿論のこと、この梁接合部材30も上記と同様にして、補強板32を介して構真柱12に載置される。また、前記床面42を構成する小梁28は同様に切梁兼用として用いられる。
【0018】
一方、地下二階B2の床面42を構成する大梁26および小梁28の接続が完了すると、同様にして地下三階B3部分を掘削するのであるが、この地下三階B3の床面44の下方に基礎および地中梁48を構築する。その後、各地下階の構真柱12の外周に配筋および型枠を配してコンクリート打設することにより鉄骨鉄筋コンクリート柱50を構築すると共に、大梁26,小梁28の上側に床スラブを敷設してコンクリートを打設することにより床面24,42,44を構築し、また、連続地中壁14の内周に鉄筋コンクリートによって外周壁52を構築する。尚、この外周壁52には前記小梁28の端部が埋設される。
【0019】
以上の構築法により構築された地下架構10では、地中に打設された構真柱12の上端部に一階の床面20を構成する大梁22を接続した後、地下一階B1,地下二階B2,地下三階B3を地下階毎に掘削しつつ、露出した構真柱12に大梁26および小梁28を接続することにより、地下架構10を構築することができる。このとき、前記小梁28の端部は外周の連続地中壁14に接続されて、この小梁28を切梁兼用として用いるようになっているため、土水圧等は小梁28で支持することができる。
【0020】
従って、目的の地下階部分まで地下架構10を構築する際に、各地下階の床面24,42,44部分は大梁26と小梁28の組付け状態で工事を進行することができる。このため、各地下階の床面24,42,44部分が格子状に組み合わされた小梁28間で大きく開口され、任意の開口部分から掘削機械とか資材等を下層階に簡単に搬入できると共に、地下階全体が連通状態となることにより、良好な換気と十分な照明とを確保できる。また、本実施例では下層階の掘削を行う際に、フラットスラブ工法のように各床面部分へのコンクリートの打設を行う必要がなく、従って、打設したコンクリートの硬化を待つ必要がないことから工期が大幅に短縮化される。
【0021】
ところで、本実施例では格子状に組み合わされた前記小梁28は、X字状に配置された大梁26を介して構真柱12に支持され、この大梁26がフラットスラブのいわゆるキャピタルと同様に機能して十分な支持力を発揮するようになっている。また、前記大梁26は梁接合部材30を介して構真柱12に載置され、これにより大梁26は構真柱12に対してピン結合状態となり、小梁28に入力された水平力を当該接合部分で逃がすことができる。
【0022】
また、本実施例ではフラットスラブに代えて小梁28で土水圧等を受け持つことができるため、各床面24,42,44を構築する際にこれら大梁26および小梁28の上側に打設されるスラブコンクリートの肉厚を大幅に薄肉化することができる。
【0023】
図5には、図3に示した梁接合部材30を介しての、大梁26の構真柱12への取付部分の変形例が示されている。上記実施例では、構真柱12に接合した補強板32上に梁接合部材30を載置し、このようにして構真柱12に支持させた梁接合部材30のフランジ30a及びウエブ30bに大梁26のフランジ26a及びウエブ26bをボルト,ナットで接合して、当該大梁26を構真柱12に対してピン構造で載置するように構成したが、図5の実施例では、さらに梁接合部材30と大梁26との下フランジ26d,30d同士の接合をも省略して、接合作業の省力化を図っている。さらに梁接合部材30と大梁26とのウエブ26b,30b同士の結合強度を確保できる場合には、これらの上フランジ26c,30c同士の接合を省略しても良い。いずれの場合にあっても、梁接合部材30及び補強板32を介して大梁26を構真柱12にピン構造で載置できることはもちろんである。
【0024】
図6には、大梁26の配置の変形例が示されている。上記実施例にあっては、構真柱12と、小梁28相互の接合部とを連結するX字状に大梁26を配置した例を示したが、小梁28の強度が十分な場合には図示するように、小梁28の中途部と構真柱12とを連結するように十字状に大梁26を配置しても良い。またさらに、小梁28の強度が十分であれば、図に破線で示したように、十字のうちの2本を残し、他の一方向の大梁26を省略する構成としても良い。この場合における小梁28相互の連結構造としては、図5のA部を拡大して示した図7のような構造とすることができる。図7(a)に示したものは、小梁28が、中空角形材を2本併設して構成された場合であり、これら中空角形材の小梁28を互いに直交させて配置し、両者をボルト,ナットで接合するようにしている。また、図7(b)に示したものは、一方の小梁28aがH型鋼であり、これと直交配置される小梁28cが、中空角形材である場合であり、H型鋼の小梁28aのウエブ28bを貫通するボルトにナットを螺着させて、中空角形材の小梁28cをH型鋼の小梁28aに一括して接合するようにしている。
【0025】
これらの実施例にあっても、上記実施例と同様な作用・効果を奏することはもちろんである。
【0026】
【発明の効果】
以上説明したように本発明の地下構造物の構築法にあっては、一階梁構築工程でまず一階の床面を構成する梁部材が構真柱の上端部に取り付けられるので、この梁部材と連続地中壁とで地震等の水平力を支持した状態で、地下部分の構築を安全に遂行することができる。
【0027】
また、小梁構築工程で大梁に取付けられる小梁を切梁兼用として用いるようになっているため、各地下階の床部分に作用する土水圧等を前記小梁で支持させることができる。このため、目的の地下階部分まで地下架構を構築する際に、各地下階の床面部分は大梁と小梁の組付け状態で工事を進行することができるため、各地下階の床面部分を全体に亘って大きく開口できる。従って、任意の開口部分から掘削機械とか資材等を下層階に簡単に搬入できることから掘削効率を著しく向上すると共に、地下階全体が連通状態となって良好な換気および十分な照明を確保することができ、また掘削作業性も向上させることができる。
【0028】
更に、下層階の掘削を行う際に、各床面部分へのコンクリート打設の必要性がなくなることから、工期の大幅な短縮化を達成することができる。また、各地下階の床面荷重を前記大梁および小梁で支持することができるため、最終的に床面に打設されるスラブコンクリートの肉厚を薄肉化して、床面の軽量化および後打ちコンクリート量を削減することができるという各種優れた効果を奏する。
【図面の簡単な説明】
【図1】本発明にかかる地下構造物の一実施例の構築途中を示す平面図である。
【図2】本発明にかかる地下構造物の一実施例の構築途中を示す正面図である。
【図3】本発明の地下構造物の構築法を用いた構真柱と梁との接続部分の一実施例を示す拡大正面図である。
【図4】本発明の他の実施例を示す大梁と小梁との接続部分の要部構成図である。
【図5】図3で示した接続部分の変形例を示す拡大正面図である。
【図6】大梁の配置の変形例を示す平面図である。
【図7】図6のA部拡大正面図である。
【符号の説明】
10 地下架構(地下構造物) 12 構真柱
14 連続地中壁 18 杭
20 一階床面 22 大梁(梁部材)
24 地下一階床面 26 大梁
28 小梁 30 梁接合部材
42 地下二階床面 44 地下三階床面[0001]
[Industrial application fields]
The present invention relates to a method for constructing an underground structure constructed using a structural pillar that is driven into the ground.
[0002]
[Prior art]
In constructing underground structures such as multi-story buildings, a reverse driving method using a structural pillar is adopted. When performing this reverse driving method, a flat slab method (see Japanese Patent Laid-Open Nos. 61-261556 and 3-72119) may be used in consideration of workability, labor saving, temporary saving, and the like. . That is, in the flat slab construction method, the floor is constructed by placing concrete on the bottom portion of the excavated ground while excavating the ground for each level of the underground floor without using beams.
[0003]
[Problems to be solved by the invention]
However, the reverse hammering method using the conventional flat slab method has the following problems.
[0004]
(1) Since there is a flat slab on the upper floor when excavating to the lower floor, this flat slab interferes with the excavation efficiency, and it is necessary to provide ventilation and lighting equipment for each slab. is there.
[0005]
(2) Since horizontal force such as earth and water pressure is received by the flat slab, a temporary opening for excavating the lower floor formed in the flat slab cannot be provided at an arbitrary position. Drilling efficiency is reduced.
[0006]
(3) Since it is necessary to excavate the lower floors after the concrete of the flat slabs on the upper floors has hardened, the construction period will be prolonged.
[0007]
Therefore, in view of such conventional problems, the present invention allows the horizontal force to be received by the beam constituting the first floor and the continuous underground wall, and by combining the main beam as a cut beam, An object of the present invention is to provide a construction method of an underground structure that eliminates the need for a flat slab at the stage of constructing a partial frame, shortens the construction period, and reduces costs.
[0008]
In order to achieve such an object, the present invention provides an underground strut placing step of driving a structural pillar with a pile into a continuous underground wall, and a beam member of the first floor portion at the upper end of the constructed structural pillar. The first floor beam installation process to be installed, the excavation process for excavating the underground floor by the height of the first floor under the constructed beam, and the large beam construction process for attaching the large beam of the underground floor part excavated to the structural pillar exposed by excavation , and a small beam constructing step to connect this設小beam between the tip portion of the girder which is constructed so as to form a grid pattern as Setsuhari combined, the excavation process, by repeating the girder construction process and the beams constructing step Build an underground frame.
In the present invention, after the beam connecting member is placed on the beam column, the beam is fixed to the beam bonding member so that the beam can be in a pin-coupled state to the beam column.
[0009]
[Action]
In the construction method of the underground structure of the present invention with the above configuration, the beam member is attached to the upper end portion of the structural pillar driven in the underground strut placing process by the first floor beam construction process, and then the excavation process , It is possible to build the underground frame to the target basement by repeating the large beam construction process and the small beam construction process. At this time, in the first floor beam construction process, first, the beam member that constitutes the floor surface of the first floor is attached to the upper end of the structural pillar, so that horizontal force such as earthquake was supported by this beam member and the continuous underground wall. Underground conditions can be completed. And since the small beam attached to a large beam in the said small beam construction process is used also as a cutting beam, the earth-and-water pressure etc. which act on the floor part of each underground floor can be supported by the said small beam. Therefore, when the underground structure is constructed up to the target basement part, the construction can be performed in the state where the floor surface part of each basement is assembled with a large beam and a small beam. For this reason, the floor portion of each basement floor is greatly opened, and excavating machines and materials can be easily carried into the lower floor from any opening portion. Sufficient lighting can be ensured and excavation workability can be improved. In addition, when excavating the lower floors, since there is no concrete placement on each floor surface part, the construction period can be greatly shortened.
[0010]
【Example】
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. 1 to 3 show an embodiment of an underground structure construction method according to the present invention, FIG. 1 is a plan view showing the construction of the underground structure, and FIG. 2 is a front view showing the construction of the underground structure. FIG. 3 is an enlarged front view showing a connecting portion between the structural pillar and the beam.
[0011]
That is, in this embodiment, an
[0012]
A
[0013]
After the
[0014]
The
[0015]
As shown in FIG. 3, an
[0016]
And each end part of the said
[0017]
In this way, when the connection of the
[0018]
On the other hand, when the connection of the
[0019]
In the
[0020]
Therefore, when the
[0021]
By the way, in the present embodiment, the
[0022]
Further, in this embodiment, since it is possible to handle the soil water pressure or the like with the
[0023]
FIG. 5 shows a modification of the attachment portion of the
[0024]
FIG. 6 shows a modified example of the arrangement of the large beams 26. In the above embodiment, the example in which the
[0025]
Even in these embodiments, it is a matter of course that the same operations and effects as the above-described embodiments can be achieved.
[0026]
【The invention's effect】
As described above, in the construction method of an underground structure according to the present invention, the beam member constituting the floor surface of the first floor is first attached to the upper end portion of the construction column in the first floor beam construction process. Construction of the underground part can be performed safely with the member and the continuous underground wall supporting a horizontal force such as an earthquake.
[0027]
In addition, since the small beam attached to the large beam in the small beam construction process is also used as a cutting beam, the soil pressure acting on the floor portion of each underground floor can be supported by the small beam. For this reason, when constructing an underground structure up to the target basement, the floor of each basement can be constructed with large beams and small beams assembled. Can be greatly opened throughout. Therefore, excavation machines and materials can be easily carried into the lower floor from any opening, so that excavation efficiency can be remarkably improved, and the entire basement can be connected to ensure good ventilation and sufficient lighting. And excavation workability can be improved.
[0028]
Furthermore, when excavating the lower floors, the necessity of placing concrete on each floor surface portion is eliminated, so that the construction period can be greatly shortened. In addition, since the floor load of each basement can be supported by the large beams and small beams, the thickness of the slab concrete that is finally placed on the floor surface is reduced to reduce the weight of the floor surface. Various excellent effects that the amount of cast concrete can be reduced are exhibited.
[Brief description of the drawings]
FIG. 1 is a plan view showing the construction of an embodiment of an underground structure according to the present invention.
FIG. 2 is a front view showing the construction of an embodiment of an underground structure according to the present invention.
FIG. 3 is an enlarged front view showing an embodiment of a connecting portion between a structural pillar and a beam using the underground structure building method of the present invention.
FIG. 4 is a main part configuration diagram of a connecting portion between a large beam and a small beam according to another embodiment of the present invention.
FIG. 5 is an enlarged front view showing a modified example of the connection portion shown in FIG. 3;
FIG. 6 is a plan view showing a modified example of the arrangement of the large beams.
7 is an enlarged front view of a part A in FIG. 6;
[Explanation of symbols]
10 Underground structure (underground structure) 12
24
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP32706594A JP3612761B2 (en) | 1994-12-28 | 1994-12-28 | Construction method of underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP32706594A JP3612761B2 (en) | 1994-12-28 | 1994-12-28 | Construction method of underground structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH08184067A JPH08184067A (en) | 1996-07-16 |
JP3612761B2 true JP3612761B2 (en) | 2005-01-19 |
Family
ID=18194911
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP32706594A Expired - Fee Related JP3612761B2 (en) | 1994-12-28 | 1994-12-28 | Construction method of underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3612761B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6226123B2 (en) * | 2013-09-11 | 2017-11-08 | 株式会社竹中工務店 | Building construction method |
-
1994
- 1994-12-28 JP JP32706594A patent/JP3612761B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH08184067A (en) | 1996-07-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20090094971A (en) | Under ground top-down method | |
KR100313720B1 (en) | Composite Underground Structure Construction Method | |
KR20110122310A (en) | Construction method for basement structure without temporary structure | |
KR20200104534A (en) | Method for constructing underground structure busing PC integrating method without support | |
JP2004263467A (en) | Reconstruction method using existing underground skeleton | |
JP3612761B2 (en) | Construction method of underground structure | |
JPS6137692Y2 (en) | ||
JP3644606B2 (en) | Installation method of formwork support in reverse placement method | |
JP3586121B2 (en) | Mixed structure of reinforced concrete column and steel beam and its construction method | |
JP2004339728A (en) | Recyclable continuous footing and recycling method for continuous footing | |
JP2900840B2 (en) | How to build underground structures | |
KR102523155B1 (en) | Connecting structure of middle girder and construction method thereof | |
JP2959436B2 (en) | How to build underground structures | |
KR101256311B1 (en) | Structual deepening method | |
JP2894217B2 (en) | Building structural frame | |
JP3341034B2 (en) | How to build underground structures | |
JP2763488B2 (en) | Prefabricated pillar and inverted ramen prefabricated construction method | |
JPH08177068A (en) | Construction of underground structure | |
JPS63277342A (en) | Reverse execution of underground story | |
KR20220094841A (en) | Middle connecting structure of steel pilar and construction method thereof | |
JP2940451B2 (en) | How to build underground structures | |
JP2605563B2 (en) | Basement structure of building | |
JP3061934B2 (en) | Retaining wall construction method | |
KR20230021231A (en) | Retaining wall structure using rectangular wall-type piles | |
KR20240023364A (en) | Floor support system for top-down mehtod without soil pressure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040521 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040601 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040802 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20041005 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20041018 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071105 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081105 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091105 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091105 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101105 Year of fee payment: 6 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101105 Year of fee payment: 6 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111105 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121105 Year of fee payment: 8 |
|
LAPS | Cancellation because of no payment of annual fees |