JP3443035B2 - Connecting pins for scaffolding frames - Google Patents

Connecting pins for scaffolding frames

Info

Publication number
JP3443035B2
JP3443035B2 JP13664599A JP13664599A JP3443035B2 JP 3443035 B2 JP3443035 B2 JP 3443035B2 JP 13664599 A JP13664599 A JP 13664599A JP 13664599 A JP13664599 A JP 13664599A JP 3443035 B2 JP3443035 B2 JP 3443035B2
Authority
JP
Japan
Prior art keywords
pin body
pin
posture
support rod
engaging projection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP13664599A
Other languages
Japanese (ja)
Other versions
JP2000328779A (en
Inventor
彰夫 真宮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Alinco Inc
Original Assignee
Alinco Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Alinco Inc filed Critical Alinco Inc
Priority to JP13664599A priority Critical patent/JP3443035B2/en
Publication of JP2000328779A publication Critical patent/JP2000328779A/en
Application granted granted Critical
Publication of JP3443035B2 publication Critical patent/JP3443035B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、順次上方に連結し
ていくのに適した仮設用足場建枠の連結ピンに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a connecting pin for a scaffolding construction frame for temporary construction, which is suitable for sequentially connecting upwards.

【0002】[0002]

【従来の技術】建物の建築現場において、足場建枠を順
次上方に組み立てていくには、上下に対向する足場建枠
を互いに連結するための連結手段が必要となる。この連
結手段として、下方側の足場建枠の左右上端部に連結ピ
ンを突設し、これに上方側の足場建枠の左右上端部を差
し込むようにしている。
2. Description of the Related Art In a construction site of a building, in order to sequentially assemble the scaffolding frames upward, a connecting means for connecting the vertically facing scaffolding frames to each other is required. As this connecting means, connecting pins are provided so as to project from the left and right upper end portions of the lower scaffold building frame, and the left and right upper end portions of the upper scaffold building frame are inserted therein.

【0003】しかして、従来の連結ピンでは、中空状ピ
ン本体の内部に、ばねに付勢されてピン本体の外部に突
出する係合突起を設け、係合突起に、この係合突起をば
ねの付勢力に抗してピン本体の内部に退入力を負荷する
滑り面と、この係合突起をピン本体の内部方向の退入位
置に係合する係合段部とを設けている。
However, in the conventional connecting pin, the hollow pin main body is provided with an engaging projection that is biased by the spring and projects outside the pin main body, and the engaging projection is spring-loaded. There is provided a sliding surface that applies a retraction force to the inside of the pin body against the urging force of the pin body, and an engagement step portion that engages the engagement protrusion with the retracted position in the inner direction of the pin body.

【0004】この連結ピンの使用において、下方側足場
建枠の縦パイプにその下端側を連結したピン本体に、上
方側足場建枠の縦パイプの下端部を差し込むことによっ
て、その差込み途上で、係合突起の滑り面に縦パイプの
下端が当接し、その当接力により負荷される退入力によ
って係合突起がピン本体内部に退入し、縦パイプの下端
部がピン本体に挿入され、この挿入途上で、係合突起が
ばねに付勢されて縦パイプ下端部の係合孔に係合し、ロ
ック状態となって上下の足場建枠が互いに連結される。
そして、足場建枠を取り外すときは、上方側足場建枠の
縦パイプ下端部から突出している係合突起を作業者の足
先等で退入方向に押圧すれば、その退入途上で係合突起
が係合段部に係合して退入位置、即ち解放位置に保持さ
れるから、上方側足場建枠の縦パイプをピン本体から抜
き出して、足場建枠は取り外すことができる。
In using this connecting pin, by inserting the lower end of the vertical pipe of the upper scaffolding frame into the pin body in which the lower end side is connected to the vertical pipe of the lower scaffolding frame, on the way of insertion, The lower end of the vertical pipe abuts on the sliding surface of the engaging protrusion, and the engaging protrusion retracts into the pin body due to the retraction force applied by the contact force, and the lower end of the vertical pipe is inserted into the pin body. During the insertion, the engaging projection is biased by the spring to engage with the engaging hole at the lower end of the vertical pipe, and in the locked state, the upper and lower scaffold building frames are connected to each other.
When removing the scaffolding frame, the engaging protrusions protruding from the lower end of the vertical pipe of the upper side scaffolding frame are pushed in the direction of withdrawal by the operator's foot or the like, and the engagement is performed during the withdrawal. Since the projection engages with the engagement step and is held in the retracted position, that is, the released position, the vertical pipe of the upper scaffolding frame can be pulled out from the pin body and the scaffolding frame can be removed.

【0005】[0005]

【発明が解決しようとする課題】上記従来の連結ピンで
は、上下足場建枠が連結された状態において、上方側足
場建枠の縦パイプ下端部から外部に突出している係合突
起の先端突出部を押圧することによって、係合突起がロ
ック解除位置に保持されることから、作業中に物や作業
者の足が係合突起の先端突出部に当たると、この係合突
起が押されて、知らぬ間に係合突起が解放状態となり、
不測の事態をまねくおそれがあった。
In the above-mentioned conventional connecting pin, in the state where the upper and lower scaffolding building frames are connected, the tip projection portion of the engaging projection projecting outward from the lower end portion of the vertical pipe of the upper side scaffolding building frame. By pressing, the engaging projection is held in the unlocked position, so if an object or a worker's foot hits the tip protrusion of the engaging projection during work, this engaging projection is pushed and the The engaging projection is released while
There was a risk of causing an unexpected situation.

【0006】本発明は、上記のような課題に鑑み、足場
建枠が相互に連結された状態において係合突起が簡単に
解放状態となることがなく、作業上の安全性を確保でき
るようにした連結ピンを提供することを目的とする。
In view of the above problems, the present invention ensures that the engagement projections are not easily released when the scaffolding frames are connected to each other, thus ensuring work safety. The purpose of the present invention is to provide a connecting pin.

【0007】[0007]

【課題を解決するための手段】請求項1に係る発明の足
場建枠用連結ピンは、中空状ピン本体7の内部に、ピン
本体7の内壁に沿って軸方向に延びる支持杆12と、支
持杆12の上端部及び下端部に設けられて夫々ピン本体
7の外部に突出する係合突起9及び連結用突起11と、
支持杆12を介して前記両突起9,11をピン本体7の
外部に突出させるように付勢するばね13とを設け、ピ
ン本体7には、外部に操作片19を突出したロック部材
20を、支持杆12との間で、ピン本体7の内壁に沿っ
て平行に位置するロック姿勢と、ロック姿勢から部材上
端部側がピン本体7内壁から離れるように傾転した非ロ
ック姿勢とに亘って姿勢変更可能に設け、前記操作片1
9を引き起こしてロック部材20をロック姿勢から非ロ
ック姿勢に傾転させることにより、係合突起9がばね付
勢力に抗してピン本体7内部へ後退するようにしたこと
を特徴とする。
According to a first aspect of the present invention, there is provided a scaffolding frame connecting pin, wherein a support rod 12 is provided inside a hollow pin body 7 and extends axially along an inner wall of the pin body 7. An engaging projection 9 and a connecting projection 11 which are provided at the upper end and the lower end of the support rod 12 and project to the outside of the pin body 7, respectively.
A spring 13 for urging the projections 9 and 11 so as to project to the outside of the pin body 7 via a support rod 12 is provided, and a lock member 20 that projects an operation piece 19 to the outside is provided on the pin body 7. Between the support rod 12 and the lock rod, which is parallel to the inner wall of the pin body 7, and the non-lock posture in which the upper end of the member is tilted away from the inner wall of the pin body 7 from the lock posture. The operation piece 1 is provided so that the posture can be changed.
9 is caused to tilt the lock member 20 from the locked posture to the non-locked posture, so that the engaging projection 9 is retracted into the pin body 7 against the spring biasing force.

【0008】請求項2は、請求項1に記載の足場建枠用
連結ピンにおいて、支持杆12下端部の連結用突起11
を、支持杆12に対しその長手方向前後に若干量スライ
ドできるように取り付けてなることを特徴とする。
According to a second aspect of the present invention, in the scaffolding frame connecting pin according to the first aspect, the connecting projection 11 at the lower end of the support rod 12 is used.
Is attached to the support rod 12 so that the support rod 12 can slide a little forward and backward in the longitudinal direction thereof.

【0009】請求項3は、請求項1又は2に記載の足場
建枠用連結ピンにおいて、係合突起9の先端部は、ロッ
ク部材20が非ロック姿勢にあって係合突起9がばね付
勢力に抗して後退している時でも、ピン本体7の外側面
から若干突出した状態にあり、しかして係合突起9の先
端部が押圧されて係合突起9が更にピン本体7内に後退
されることにより、ロック部材20は、支持杆12との
押接状態から解放されて、その自重によりロック姿勢に
傾転するようになっていることを特徴としている。
According to a third aspect of the present invention, in the scaffolding frame connecting pin according to the first or second aspect, the tip end portion of the engagement protrusion 9 has the lock member 20 in the unlocked posture and the engagement protrusion 9 is spring-loaded. Even when retracting against the force, it is in a state of slightly protruding from the outer surface of the pin main body 7, and the tip of the engaging projection 9 is pressed so that the engaging projection 9 further moves into the pin main body 7. When the lock member 20 is retracted, the lock member 20 is released from the pressed state with the support rod 12, and is tilted to the lock posture by its own weight.

【0010】[0010]

【発明の実施の形態】図1は、上方側の足場建枠aと下
方側の足場建枠bとの連結前の状態を示す。各足場建枠
a,bは、左右の縦パイプ1,1と両パイプ1,1をつ
なぐ横パイプ2と縦横パイプ1,2間にわたって取り付
けられた補強桟3,3とからなるもので、横パイプ2に
は足場板4が、その爪4aを横パイプ2に掛合すること
によって懸架されている。そして、各縦パイプ1の下端
部には足場板4側に面して係合孔5が穿設されており、
上下足場建枠a,bの対向する縦パイプ1,1間に本発
明に係る連結ピン6が差し込まれるようになっている。
DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows a state before an upper scaffolding frame a and a lower scaffolding frame b are connected. Each scaffold building frame a, b is composed of left and right vertical pipes 1, 1 and a horizontal pipe 2 connecting both pipes 1, 1 and reinforcing bars 3, 3 attached between the vertical and horizontal pipes 1, 2. A scaffolding plate 4 is suspended from the pipe 2 by engaging its claws 4a with the lateral pipe 2. An engaging hole 5 is formed at the lower end of each vertical pipe 1 facing the scaffolding plate 4 side.
The connecting pin 6 according to the present invention is inserted between the vertical pipes 1 and 1 of the upper and lower scaffolding building frames a and b facing each other.

【0011】図2は、連結ピン6の外観斜視図で、同図
の(A)は、後述するロック部材20がロック姿勢にあ
って、係合突起9がピン本体7の外部に突出している状
態を示し、(B)は、ロック部材20が非ロック姿勢に
あって、係合突起9がピン本体7内部へ後退している状
態を示す。図3の(A)は、図2の(A)に示される状
態にある連結ピン6の正面図、同図の(B)はその縦断
面図である。また、図4及び図5は、連結ピン6によっ
て下方側足場建枠bに上方側足場建枠aを連結する場合
及び上方側足場建枠aを取り外す場合の作用を示す縦断
面図である。
FIG. 2 is an external perspective view of the connecting pin 6. In FIG. 2A, a lock member 20 described later is in a locked posture, and an engagement projection 9 projects outside the pin body 7. FIG. 3B shows a state in which the lock member 20 is in the unlocked posture and the engagement projection 9 is retracted into the pin body 7. 3A is a front view of the connecting pin 6 in the state shown in FIG. 2A, and FIG. 3B is a longitudinal sectional view thereof. 4 and 5 are vertical cross-sectional views showing the operation when connecting the upper scaffold building frame a to the lower scaffold building frame b by the connecting pin 6 and when removing the upper scaffold building frame a.

【0012】これらの図から分かるように、連結ピン6
は円管状のピン本体7を有し、このピン本体7の軸方向
中央部に短管部材8が嵌合固着されて、この短管部材8
とピン上部7a及びピン下部7bとの間に外周段部8
a,8bを形成し、ピン上部7aに差し込まれる上方側
足場建枠aの縦パイプ1と、ピン下部7bに差し込まれ
る下方側足場建枠bの縦パイプ1とは、それぞれの端面
が上記外周段部8a,8bに当接して位置決めされ、そ
の位置で縦パイプ1下端部の係合孔5にピン本体7から
突出する係合突起9が係合すると共に、下方側足場建枠
bの縦パイプ1上端部の連結孔10にピン本体7の連結
用突起11が係合するようになっている。尚、短管部材
8に代えて、ピン本体7の軸方向中央部を肉厚に一体形
成するようにしてもよい。
As can be seen from these figures, the connecting pin 6
Has a circular tube-shaped pin body 7, and a short tube member 8 is fitted and fixed to an axially central portion of the pin body 7.
And an outer peripheral step portion 8 between the pin upper portion 7a and the pin lower portion 7b.
The vertical pipe 1 of the upper scaffolding building frame a that forms a and 8b and is inserted into the pin upper portion 7a and the vertical pipe 1 of the lower scaffolding building frame b that is inserted into the pin lower portion 7b have their respective end surfaces on the outer circumference. Positioning is performed by abutting on the stepped portions 8a and 8b, and at that position, the engaging projection 5 projecting from the pin body 7 engages with the engaging hole 5 at the lower end of the vertical pipe 1, and the vertical direction of the lower scaffolding building frame b The connecting projection 10 of the pin body 7 is adapted to engage with the connecting hole 10 at the upper end of the pipe 1. Instead of the short pipe member 8, the axial center portion of the pin body 7 may be integrally formed to be thick.

【0013】係合突起9は、ピン本体7の内壁に沿って
軸方向に延びる支持杆12の上端部に垂直横向きに突設
されており、支持杆12の下端部には連結用突起11が
係合突起9と同じ垂直横向きに突設されてはいるが、こ
の連結用突起11は、支持杆12の長手方向前後に若干
量スライドできるように支持杆12に取り付けられてい
る。支持杆12の背面側にはその長手方向中央部に、両
端部がピン本体7の内壁面に摺動可能に弾接される側面
視円弧状の板ばね13の長手方向中央部が固着され、こ
の板ばね13の付勢力によって、係合突起9及び連結用
突起11がピン上部7aのピン孔14a及びピン下部7
bのピン孔14bから夫々外部に突出するようになって
いる。また、係合突起9の上面側には下方に向かって傾
斜する滑り面17が形成されると共に、この係合突起9
の下面側先端部には上方に向かって傾斜する副滑り面1
8が形成されている。
The engaging projection 9 is provided on the upper end of a support rod 12 extending in the axial direction along the inner wall of the pin body 7 so as to extend vertically and laterally. The lower end of the support rod 12 is provided with a connecting projection 11. The connecting projection 11 is attached to the support rod 12 so that it can slide a little forward and backward in the longitudinal direction of the support rod 12, although it is provided to project in the same vertical direction as the engaging projection 9. On the back side of the support rod 12, a central portion in the longitudinal direction of a leaf spring 13, which is arcuate in side view and is slidably contacted with the inner wall surface of the pin body 7, is fixed to the central portion in the longitudinal direction. Due to the biasing force of the leaf spring 13, the engagement protrusion 9 and the coupling protrusion 11 cause the pin hole 14a of the pin upper portion 7a and the pin lower portion 7
Each of the pin holes 14b of b is projected to the outside. Further, a sliding surface 17 that is inclined downward is formed on the upper surface side of the engagement projection 9 and the engagement projection 9 is formed.
A sub-sliding surface 1 which is inclined upward at the lower end of the lower surface of the
8 is formed.

【0014】支持杆12は、図3、図6及び図7から分
かるように、板状本体12aと両側壁12b,12bと
によって断面略コ字形に形成されたもので、板状本体1
2aの一端部(上端部)に係合突起9が取付軸体30に
よって固着されている。この板状本体12aの他端部
(下端部)には板状本体12aの長手方向に長い長孔3
1が設けてあって、この長孔31に連結用突起11の取
付軸体32が挿通され、これによって連結用突起11は
支持杆12に対し垂直横向き姿勢に保持された状態で支
持杆12長手方向前後に2mm程度スライドできるよう
になっている。また板ばね13は、カシメ材33によっ
て板状本体12aに取付けられている。
As can be seen from FIGS. 3, 6 and 7, the support rod 12 is formed by a plate-shaped main body 12a and both side walls 12b, 12b into a substantially U-shaped cross section.
An engaging projection 9 is fixed to one end (upper end) of 2a by a mounting shaft body 30. At the other end (lower end) of the plate-shaped body 12a, a long hole 3 that is long in the longitudinal direction of the plate-shaped body 12a is formed.
1 is provided, and the mounting shaft body 32 of the connecting projection 11 is inserted into the elongated hole 31. As a result, the connecting projection 11 is held in a vertical lateral position with respect to the supporting rod 12, and the supporting rod 12 extends longitudinally. It can be slid back and forth in the direction of about 2 mm. The leaf spring 13 is attached to the plate-shaped main body 12a by the caulking material 33.

【0015】また、ピン本体7には、外部に操作片19
を突出させたロック部材20が、支持杆12との間にお
いて、図4に示すようにピン本体7の内壁に沿って平行
に位置するロック姿勢と、このロック姿勢から当該部材
12の上端部側がピン本体7の内壁から離れるように傾
転した図5の(A)に示すような非ロック姿勢とに亘っ
て姿勢変更可能に設けられ、上記操作片19を引き起こ
してロック部材20をロック姿勢から非ロック姿勢に傾
転させることにより、係合突起9が板ばね13の付勢力
に抗してピン本体7の内部へ後退するようになってい
る。
Further, the pin body 7 is provided with an operation piece 19 on the outside.
The locking member 20 that protrudes from the support rod 12 is positioned in parallel with the inner wall of the pin body 7 as shown in FIG. The pin body 7 is tilted away from the inner wall of the pin body 7 so as to be capable of changing its posture to an unlocked posture as shown in FIG. 5 (A). By tilting to the non-locked posture, the engaging projection 9 is retracted into the pin body 7 against the biasing force of the leaf spring 13.

【0016】ロック部材20は、図3及び図6の(B)
から分かるように、コ字形断面の支持杆12内に嵌合さ
れる矩形体状本体部21の外面側に幅狭の係嵌部22を
介して操作片19を一体に突設すると共に、本体部21
の上端突起部21aと幅狭係嵌部22の上端面との間に
係止用段部26を形成してなるもので、ピン本体7側に
は、図6の(A)に示すように、ロック部材20の操作
片19が挿脱可能な上部側の横長溝部23と幅狭係嵌部
22が係脱可能な縦長溝部24とからなる略T字形のガ
イド溝25が、短管部材8とピン本体7とに亘って貫設
されている。しかして、このロック部材20をピン本体
7に取り付けるにあたっては、図6の(B)に示すよう
に、ロック部材20の本体部21を、支持杆12内にそ
の長手方向中間部よりも係合突起9側に寄った位置に嵌
合した状態でピン本体7内に挿入し、操作片19をT字
形ガイド溝25の横長溝部23から外部へ突出させて、
幅狭係嵌部22を縦長溝部24に係嵌させることによ
り、図2の(A)及び図3の(A)、(B)に示すよう
な状態となる。
The lock member 20 is shown in FIG. 3 and FIG. 6 (B).
As can be seen from the above, the operating piece 19 is integrally projected on the outer surface side of the rectangular body portion 21 fitted in the support rod 12 having a U-shaped cross section through the narrow engaging portion 22, and Part 21
The stepped portion 26 for locking is formed between the upper end projecting portion 21a and the upper end surface of the narrow engagement portion 22, and on the pin body 7 side, as shown in FIG. A substantially T-shaped guide groove 25 including an upper lateral groove 23 into which the operating piece 19 of the lock member 20 can be inserted / removed and a vertical groove 24 into which the narrow engagement portion 22 can be engaged / disengaged is provided. And the pin body 7 are provided. Then, when attaching the lock member 20 to the pin body 7, as shown in FIG. 6B, the body portion 21 of the lock member 20 is engaged with the support rod 12 rather than the longitudinal intermediate portion thereof. Inserted into the pin body 7 in a state of being fitted to a position close to the protrusion 9 side, projecting the operating piece 19 from the laterally elongated groove portion 23 of the T-shaped guide groove 25 to the outside,
By engaging the narrow engagement portion 22 with the longitudinal groove portion 24, the state shown in FIGS. 2A and 3A and 3B is obtained.

【0017】図2の(A)及び図3の(A)、(B)は
ロック部材20がロック姿勢となっている状態を示すも
ので、このロック姿勢では、幅狭係嵌部22がT字形ガ
イド溝25の縦長溝部24に傾転可能に係嵌していて、
操作片19が略水平に突出すると共に本体部21がピン
本体7の内壁に沿って平行に位置している。このロック
姿勢の状態から、図5(A)に示すように操作片19を
上向きに引き起こして、本体部21をその上端部側がピ
ン本体7内壁から離れるように傾転させ、ロック部材2
0を非ロック姿勢に姿勢変更することによって、支持杆
12の上端部側、即ち係合突起9側が、ばね13の付勢
力に抗して下端部の連結用突起11を中心に傾倒し、そ
れにより係合突起9は図5(A)のようにピン本体7の
内部側へ後退して解放状態となる。この時、ロック部材
20の係止用段部26がT字形ガイド溝25の横長溝部
23上端とピン本体7内壁との隅角部に係止されると共
に、本体部21の内面側上端部が支持杆12に押接さ
れ、この状態でロック部材20は非ロック姿勢に保持さ
れている。
2A and 3A and 3B show a state in which the lock member 20 is in the lock posture, and in this lock posture, the narrow engagement portion 22 is T. The vertically elongated groove portion 24 of the character-shaped guide groove 25 is fitted so as to be tiltable,
The operation piece 19 projects substantially horizontally, and the body portion 21 is positioned parallel to the inner wall of the pin body 7. From this locked state, as shown in FIG. 5A, the operation piece 19 is raised upward to tilt the main body portion 21 so that its upper end side is away from the inner wall of the pin main body 7, and the lock member 2
By changing the attitude of 0 to the unlocked attitude, the upper end side of the support rod 12, that is, the engaging projection 9 side tilts against the urging force of the spring 13 about the connecting projection 11 at the lower end, As a result, the engagement projection 9 is retracted toward the inside of the pin body 7 and is in the released state as shown in FIG. 5 (A). At this time, the locking stepped portion 26 of the lock member 20 is locked at the corner between the upper end of the laterally elongated groove portion 23 of the T-shaped guide groove 25 and the inner wall of the pin body 7, and the inner surface side upper end portion of the body portion 21 is The lock member 20 is pressed against the support rod 12, and in this state, the lock member 20 is held in the unlocked posture.

【0018】上記のように係合突起9がばね付勢力に抗
して後退した解放状態にあっても、この係合突起9の先
端部は図5の(A)に示すようにピン本体7の外側面か
ら若干突出した状態となっている。しかして、このよう
な状態から係合突起9の先端部を押圧して係合突起9を
更にピン本体7内に後退させることによって、ロック部
材20は、支持杆12との押接状態から解放されて、図
5の(B)に示すように自重によって非ロック姿勢から
ロック姿勢へと傾転するようになっている。
Even when the engaging projection 9 is in the released state in which it is retracted against the spring biasing force as described above, the tip portion of the engaging projection 9 is the pin body 7 as shown in FIG. 5 (A). Is slightly protruding from the outer surface of the. Then, by pushing the tip end portion of the engaging protrusion 9 from such a state to further retract the engaging protrusion 9 into the pin body 7, the lock member 20 is released from the pressed state with the support rod 12. As a result, as shown in FIG. 5 (B), it is tilted from its non-locked posture to its locked posture by its own weight.

【0019】上述のように構成される足場建枠用連結ピ
ン6の使用に際しては、先ず、ピン孔14bから外部に
突出した連結用突起11を板ばね13の付勢力に抗して
ピン本体7内へ退入させた状態で、ピン本体7のピン下
部7bを下方側足場建枠bの縦パイプ1の上端部に差し
込み、連結用突起11を縦パイプ1の連結孔10に係合
させて図3に示すような状態とする。これによって、ピ
ン本体7は、下方側足場建枠bの縦パイプ1の上端部に
取り付けられ、以後は足場建枠の不使用時でも取り外す
必要はない。このとき、ロック部材20はロック姿勢に
あって、係合突起9は板ばね13の付勢力によりピン本
体7の外部に突出したロック位置に保持されている。
In using the scaffolding frame connecting pin 6 constructed as described above, first, the connecting protrusion 11 protruding outward from the pin hole 14b resists the biasing force of the leaf spring 13 and the pin body 7 is pushed. In the state of being retracted inward, the pin lower portion 7b of the pin body 7 is inserted into the upper end portion of the vertical pipe 1 of the lower scaffolding building frame b, and the connecting projection 11 is engaged with the connecting hole 10 of the vertical pipe 1. The state is as shown in FIG. Thereby, the pin body 7 is attached to the upper end of the vertical pipe 1 of the lower scaffolding building frame b, and thereafter, it is not necessary to remove it even when the scaffolding building frame is not used. At this time, the lock member 20 is in the locked posture, and the engagement protrusion 9 is held at the lock position protruding outside the pin body 7 by the biasing force of the leaf spring 13.

【0020】次に、上方側足場建枠aの縦パイプ1を、
下方側足場建枠bに取り付けたピン本体のピン上部7a
に差し込むと、その差し込み途上で、係合突起9の滑り
面17に縦パイプ1の下端部が当接し、その当接力によ
り負荷される退入力によって、係合突起9は図4の
(A)に示すようにピン本体7の内部側へ後退して解放
状態となる。このとき、ロック部材20は、同図のよう
なロック姿勢にある。
Next, the vertical pipe 1 of the upper side scaffolding frame a is
Pin upper part 7a of the pin body attached to the lower scaffold building frame b
4A, the lower end of the vertical pipe 1 comes into contact with the sliding surface 17 of the engaging projection 9 during the insertion, and the engaging projection 9 is moved by the retraction force applied by the abutting force. As shown in FIG. 5, the pin body 7 is retracted to the released state. At this time, the lock member 20 is in the lock posture as shown in FIG.

【0021】そして、係合突起9の先端部が、上方側足
場建枠aの縦パイプ1内側面に当接した状態で更に下動
し、図4の(B)に示すように縦パイプ1の下端がピン
上部7aの外周段部8aに当接すると、この縦パイプ1
の係合孔5に係合突起9が対向位置することになって、
係合突起9は板ばね13の付勢力により突出して縦パイ
プ1の係合孔5に係合し、これによって上方側足場建枠
aと下方側足場建枠bとが互いに連結されることにな
る。
Then, the tip end of the engaging projection 9 is further moved downward in a state of being in contact with the inner surface of the vertical pipe 1 of the upper scaffolding building frame a, and as shown in FIG. When the lower end of the vertical pipe comes into contact with the outer peripheral stepped portion 8a of the pin upper portion 7a, the vertical pipe 1
The engaging projections 9 are located opposite to the engaging holes 5 of
The engagement protrusion 9 projects by the biasing force of the leaf spring 13 and engages with the engagement hole 5 of the vertical pipe 1, whereby the upper side scaffolding frame a and the lower side scaffolding frame b are connected to each other. Become.

【0022】上方側足場建枠aを下方側足場建枠bから
取り外す場合には、図4(B)のようにロック姿勢にあ
るロック部材20の操作片19を図5の(A)に示すよ
うに引き起こして、このロック部材20をロック姿勢か
ら非ロック姿勢へと傾転させることにより、係合突起9
が板ばね13の付勢力に抗してピン本体7内へ後退し、
解放されるから、この状態で上方側足場建枠aの縦パイ
プ1を下方側足場建枠bの縦パイプ1に取り付けられた
ピン本体7から抜き出せばよい。
When removing the upper side scaffolding frame a from the lower side scaffolding frame b, the operation piece 19 of the lock member 20 in the locked posture as shown in FIG. 4B is shown in FIG. 5A. Thus causing the locking member 20 to tilt from the locked posture to the unlocked posture, the engagement projection 9
Resists the biasing force of the leaf spring 13 and retracts into the pin body 7,
Since it is released, in this state, the vertical pipe 1 of the upper scaffold building frame a may be pulled out from the pin body 7 attached to the vertical pipe 1 of the lower scaffold building frame b.

【0023】この際、図5の(A)に示すように係合突
起9の先端部がピン本体7外側面から若干突出している
が、この係合突起9の下面側先端部には上方に向かって
傾斜する副滑り面18が形成されているから、縦パイプ
1の抜き取り時にこの縦パイプ1の係合孔5の下端縁部
が副滑り面18に当接し、それによって係合突起9は板
ばね13の付勢力に抗してピン本体7内部へ更に後退
し、縦パイプ1の抜き取りに支障を来すことがない。
At this time, as shown in FIG. 5 (A), the tip of the engaging projection 9 slightly projects from the outer surface of the pin body 7. Since the sub-sliding surface 18 that is inclined toward the side is formed, the lower end edge of the engaging hole 5 of the vertical pipe 1 abuts the sub-sliding surface 18 when the vertical pipe 1 is pulled out, so that the engaging protrusion 9 It resists the biasing force of the leaf spring 13 and further retracts into the inside of the pin body 7, so that the vertical pipe 1 can be pulled out without any trouble.

【0024】また、上記のように係合突起9がピン本体
7内部へ更に後退する時に、ロック部材20は、支持杆
12との押接状態から解放されて、図5の(B)に示す
ように自重により非ロック姿勢からロック姿勢へと傾転
して、自動的に元の状態(初期状態)に復帰する。この
ため、次回使用時に、元の状態に戻してやる必要がな
く、ロックし忘れることがない。
When the engaging projection 9 is further retracted into the pin body 7 as described above, the lock member 20 is released from the pressed state with the support rod 12 and is shown in FIG. 5 (B). As described above, the vehicle tilts from the non-locked posture to the locked posture by its own weight, and automatically returns to the original state (initial state). For this reason, it is not necessary to return to the original state the next time it is used, and never forget to lock it.

【0025】また、上方側足場建枠aの縦パイプ1を下
方側足場建枠bの縦パイプ1に取り付けられたピン本体
7から抜き取る際に、上方側足場建枠aの縦パイプ1が
ピン本体7に対し真に平行状態で差し込まれている時は
問題ないのであるが、縦パイプ1がピン本体7に対し傾
いた状態で差し込まれている場合には、普通の構造であ
れば、操作片19の引起し操作が困難となって、抜き取
りができなくなることがある。斯かる場合には、既に説
明したように、連結用突起11が支持杆12に対し垂直
横向き姿勢に保持された状態で支持杆12長手方向前後
に2mm程度スライドできるようになっていることか
ら、そのような場合でも操作片19の引起し操作を容易
に行えて、縦パイプ1の抜き取りが可能となる。
When the vertical pipe 1 of the upper scaffolding frame a is pulled out from the pin body 7 attached to the vertical pipe 1 of the lower scaffolding frame b, the vertical pipe 1 of the upper scaffolding frame a is pinned. There is no problem when the vertical pipe 1 is inserted in a state of being truly parallel to the main body 7, but when the vertical pipe 1 is inserted in a state of being inclined with respect to the pin main body 7, it is possible to operate with a normal structure. The piece 19 may be difficult to pull up and may not be able to be pulled out. In such a case, as described above, since the connecting projection 11 can be slid about 2 mm back and forth in the longitudinal direction of the support rod 12 while being held in the vertical lateral orientation with respect to the support rod 12. Even in such a case, the operation piece 19 can be easily pulled up and the vertical pipe 1 can be pulled out.

【0026】即ち、縦パイプ1がピン本体7に対し傾い
た状態で差し込まれている時には、縦パイプ1の係合孔
5が係合突起9に対し食い付いた状態となって、支持杆
12がピン本体7と一体化しているような状態にあるか
ら、操作片19によるロック部材20の傾転操作ができ
なくなる。然るに、上記のように場合には、連結用突起
11が支持杆12に対し支持杆12長手方向前後に2m
m程度スライドできるようになっていることにより、連
結用突起11が支持杆12長手方向前後に適宜にスライ
ドして、縦パイプ1の係合孔5が係合突起9に食い付く
ようなことがなく、そのため操作片19の引起し操作が
容易に行え、係合突起9をピン本体7内部へ後退させて
縦パイプ1の抜き取りを行うことができる。
That is, when the vertical pipe 1 is inserted into the pin body 7 in an inclined state, the engaging hole 5 of the vertical pipe 1 bites into the engaging projection 9 and the supporting rod 12 is inserted. Is in a state of being integrated with the pin body 7, the tilting operation of the lock member 20 by the operation piece 19 cannot be performed. However, in the case as described above, the connecting projection 11 is 2 m behind the support rod 12 in the longitudinal direction of the support rod 12.
By being able to slide about m, the connecting projection 11 may slide appropriately back and forth in the longitudinal direction of the support rod 12, and the engaging hole 5 of the vertical pipe 1 may bite into the engaging projection 9. Therefore, the operation piece 19 can be easily pulled up, and the engagement projection 9 can be retracted into the pin body 7 to extract the vertical pipe 1.

【0027】以上説明したような足場建枠用連結ピン6
によれば、上方側足場建枠aの縦パイプ1を下方側足場
建枠bに取り付けたピン本体のピン上部7aに差し込む
だけで、係合突起9がピン本体7の内部側へ後退して解
放状態となった後、板ばね13の付勢力により突出して
縦パイプ1の係合孔5に係合し、これによって上方側足
場建枠aが下方側足場建枠bに自動的に連結されること
になる。
Connecting pin 6 for scaffolding frame as described above
According to this, the engagement projection 9 is retracted to the inside of the pin body 7 simply by inserting the vertical pipe 1 of the upper side scaffolding frame a into the pin upper portion 7a of the pin body attached to the lower side scaffolding frame b. After being in the released state, it projects by the biasing force of the leaf spring 13 and engages with the engagement hole 5 of the vertical pipe 1, whereby the upper side scaffolding frame a is automatically connected to the lower side scaffolding frame b. Will be.

【0028】また、上方側足場建枠aを下方側足場建枠
bから取り外す場合には、係合突起9のピン本体7内部
への後退によって、ロック部材20が支持杆12との押
接状態から解放されて、自重により非ロック姿勢からロ
ック姿勢へと傾転し、自動的に元の状態(初期状態)に
復帰するため、次回使用時に、元の状態に戻してやる必
要がなく、ロックし忘れるようなことがない。
When the upper side scaffolding frame a is removed from the lower side scaffolding frame b, the locking member 20 is pressed against the support rod 12 by retracting the engaging projection 9 into the pin body 7. It is released from, and tilts from the non-locked posture to the locked posture by its own weight, and automatically returns to the original state (initial state), so there is no need to return to the original state the next time you use it There is nothing to forget.

【0029】また、上方側足場建枠aの縦パイプ1を下
方側足場建枠bの縦パイプ1に取り付けられたピン本体
7から抜き取る時に、上方側足場建枠aの縦パイプ1が
ピン本体7に対し傾いた状態で差し込まれている場合に
は、操作片19の引起し操作が困難となって、抜き取り
ができなくなることがあるが、連結用突起11が支持杆
12に対し垂直横向き姿勢に保持された状態で支持杆1
2長手方向前後に若干量スライドできるようになってい
るから、斯かる場合でも操作片19の引起し操作が可能
で、縦パイプ1の抜き取りを容易に行うことができる。
When the vertical pipe 1 of the upper scaffolding frame a is pulled out from the pin main body 7 attached to the vertical pipe 1 of the lower scaffolding frame b, the vertical pipe 1 of the upper scaffolding frame a is pin body. When it is inserted in a state inclined with respect to 7, it may be difficult to pull up the operation piece 19 and it may become impossible to extract it, but the connecting projection 11 is in a vertical horizontal direction with respect to the support rod 12. Support rod 1 while being held by
(2) Since it can be slid slightly back and forth in the longitudinal direction, even in such a case, the operation piece 19 can be pulled up and the vertical pipe 1 can be easily pulled out.

【0030】[0030]

【発明の効果】請求項1に係る発明の足場建枠用連結ピ
ンによると、操作片によってロック部材をロック姿勢に
しておけば、係合突起をピン本体の外部に突出するロッ
ク状態に保持でき、連結ピンの使用中に、物や作業者の
足が係合突起の先端突出部に当たっても、係合突起は解
放状態とならず、作業上の安全を確保できる。また、上
方側足場建枠の縦パイプを下方側足場建枠に取り付けた
ピン本体のピン上部に差し込むだけで、係合突起がピン
本体の内部側へ後退して解放状態となった後、ばねの付
勢力により突出して縦パイプの係合孔に係合し、これに
よって上方側足場建枠を下方側足場建枠に自動的に連結
させることができる。
According to the scaffolding frame connecting pin of the invention of claim 1, if the locking member is set in the locked posture by the operation piece, the engaging protrusion can be held in a locked state protruding to the outside of the pin body. Even if an object or a worker's foot hits the tip projection of the engaging projection while the connecting pin is in use, the engaging projection does not become in the released state, and the safety of work can be secured. Also, by simply inserting the vertical pipe of the upper scaffolding frame into the upper part of the pin of the pin body attached to the lower scaffolding frame, the engaging projection retracts to the inside of the pin body and is released, and the spring is released. It is projected by the biasing force of and engages with the engagement hole of the vertical pipe, whereby the upper side scaffolding frame can be automatically connected to the lower side scaffolding frame.

【0031】請求項2に記載のように、支持杆下端部の
連結用突起を支持杆に対しその長手方向前後に若干量ス
ライドできるように取り付けることにより、上方側足場
建枠の縦パイプを下方側足場建枠の縦パイプに取り付け
られたピン本体から抜き取る際に、上方側足場建枠の縦
パイプがピン本体に対し傾いた状態で差し込まれていて
も、操作片の引起し操作が可能となって、縦パイプの抜
き取りを容易に行うことができる。
According to a second aspect of the present invention, the connecting pipe at the lower end of the supporting rod is attached to the supporting rod so as to be slidable in the longitudinal direction of the supporting rod so that the vertical pipe of the upper side scaffolding frame is lowered. When pulling out from the pin body attached to the vertical pipe of the side scaffolding frame, even if the vertical pipe of the upper side scaffolding frame is inserted in a state inclined with respect to the pin body, it is possible to raise the operation piece. As a result, the vertical pipe can be easily pulled out.

【0032】請求項3に記載のよれば、係合突起の先端
部は、ロック部材が非ロック姿勢にあって係合突起がば
ね付勢力に抗して後退している時でも、ピン本体の外側
面から若干突出した状態にあって、係合突起の先端部が
押圧されて係合突起が更にピン本体内に後退されること
により、ロック部材が支持杆との押接状態から解放され
て、自重によりロック姿勢に傾転するようになっている
から、上方側足場建枠を下方側足場建枠から取り外す場
合には、係合突起のピン本体内部への後退によって、ロ
ック部材が支持杆との押接状態から解放されて、自重に
より非ロック姿勢からロック姿勢へと傾転し、自動的に
元の状態(初期状態)に復帰するため、次回使用時に、
元の状態に戻してやる必要がなく、ロックし忘れるよう
なことがない。
According to the third aspect of the present invention, the tip portion of the engaging projection is provided with the pin body of the pin body even when the locking member is in the unlocked posture and the engaging projection is retracted against the spring biasing force. When the tip of the engaging projection is pressed and the engaging projection is further retracted into the pin body in a state of slightly protruding from the outer side surface, the lock member is released from the pressed state with the support rod. , The lock member is tilted to the lock posture by its own weight, and therefore, when the upper side scaffolding frame is removed from the lower side scaffolding frame, the locking member is supported by retracting the engaging projection into the pin body. It is released from the pressing state with and is tilted from the non-locked posture to the locked posture by its own weight, and automatically returns to the original state (initial state), so the next time you use it,
There is no need to restore it to its original state, and you will never forget to lock it.

【図面の簡単な説明】[Brief description of drawings]

【図1】 上方側の足場建枠と下方側の足場建枠との連
結前の状態を示す斜視図である。
FIG. 1 is a perspective view showing a state before the upper scaffolding frame and the lower scaffolding frame are connected.

【図2】 連結ピンを示す外観斜視図で、(A)は、ロ
ック部材がロック姿勢にあって、係合突起がピン本体の
外部に突出している状態を示し、(B)は、ロック部材
が非ロック姿勢にあって、係合突起がピン本体内部へ後
退している状態を示す。
2A and 2B are external perspective views showing a connecting pin, FIG. 2A shows a state in which a lock member is in a lock posture, and an engaging protrusion projects to the outside of a pin body; FIG. 2B shows a lock member. Shows a state in which the engaging protrusion is retracted into the pin body in the unlocked posture.

【図3】 (A)は図2の(A)に示される状態にある
連結ピンの正面図、(B)はその縦断面図である。
3A is a front view of the connecting pin in the state shown in FIG. 2A, and FIG. 3B is a longitudinal sectional view thereof.

【図4】 (A)は上方側足場建枠の縦パイプをピン本
体に差し込んでいる途中の状態を示す連結ピンの縦断面
図、(B)は同縦パイプをピン本体に差し込み終えた状
態を示す連結ピンの縦断面図である。
FIG. 4A is a vertical cross-sectional view of the connecting pin showing a state in which the vertical pipe of the upper scaffolding frame is being inserted into the pin body, and FIG. 4B is a state in which the vertical pipe is completely inserted into the pin body. FIG. 6 is a vertical sectional view of a connecting pin showing

【図5】 (A)は上方側足場建枠の縦パイプをピン本
体から抜き出すに際し、ロック部材をロック姿勢から非
ロック姿勢へ傾転している状態を示す縦断面図、(B)
は縦パイプをピン本体から抜き出す際に、ロック部材が
元の状態に復帰する状態を示す縦断面図である。
FIG. 5 (A) is a vertical cross-sectional view showing a state in which the lock member is tilted from the locked position to the unlocked position when the vertical pipe of the upper scaffolding building frame is pulled out from the pin body;
FIG. 6 is a vertical cross-sectional view showing a state in which the lock member returns to the original state when the vertical pipe is pulled out from the pin body.

【図6】 (A)はピン本体の一部を示すもので、T字
状のガイド溝を示す斜視図、(B)は支持杆の両端部に
突設された係合突起及び連結用突起と、支持杆に係合す
るロック部材とを示す斜視図である。
FIG. 6A is a perspective view showing a part of the pin body, showing a T-shaped guide groove, and FIG. 6B is an engaging projection and a connecting projection projecting from both ends of the supporting rod. FIG. 6 is a perspective view showing a lock member that engages with a support rod.

【図7】 (A)は支持杆と、これに取り付けられた係
合突起、連結用突起及び板ばねを支持杆の正面側から見
た正面図、(B)はその側面図である。
FIG. 7A is a front view of a support rod, and engagement protrusions, connection protrusions, and leaf springs attached to the support rod as seen from the front side of the support rod, and FIG. 7B is a side view thereof.

【符号の説明】[Explanation of symbols]

a 上方側足場建枠 b 下方側足場建枠 1 縦パイプ 5 係合孔 6 連結ピン 7 ピン本体 9 係合突起 11 連結用突起 12 支持杆 13 板ばね 17 滑り面 18 副滑り面 19 操作片 20 ロック部材 a Upper scaffolding frame b Lower scaffolding frame 1 vertical pipe 5 engagement holes 6 connecting pins 7-pin body 9 Engagement protrusion 11 Connecting projection 12 Support rod 13 leaf spring 17 sliding surface 18 Secondary sliding surface 19 Operation piece 20 Lock member

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 中空状ピン本体の内部に、ピン本体の内
壁に沿って軸方向に延びる支持杆と、支持杆の上端部及
び下端部に設けられて夫々ピン本体の外部に突出する係
合突起及び連結用突起と、支持杆を介して前記両突起を
ピン本体の外部に突出させるように付勢するばねとを設
け、ピン本体には、外部に操作片を突出したロック部材
を、支持杆との間で、ピン本体の内壁に沿って平行に位
置するロック姿勢と、ロック姿勢から部材上端部側がピ
ン本体内壁から離れるように傾転した非ロック姿勢とに
亘って姿勢変更可能に設け、前記操作片を引き起こして
ロック部材をロック姿勢から非ロック姿勢に傾転させる
ことにより、係合突起がばね付勢力に抗してピン本体内
部へ後退するようにした足場建枠用連結ピン。
1. A support rod extending axially along the inner wall of the pin body inside the hollow pin body, and engagements provided at the upper and lower ends of the support rod and projecting to the outside of the pin body, respectively. Provided with a protrusion and a connecting protrusion, and a spring for urging the protrusions so as to protrude to the outside of the pin body through a support rod, and the pin body supports a lock member protruding the operation piece to the outside. Provided so that the posture can be changed between the rod and the rod, which is parallel to the inner wall of the pin body, and in a non-locked posture in which the upper end of the member tilts away from the inner wall of the pin body from the lock posture. A scaffolding frame connecting pin in which the engaging projection is retracted into the pin body against the spring biasing force by inclining the lock member from the locked posture to the unlocked posture by inducing the operation piece.
【請求項2】 支持杆下端部の連結用突起を、支持杆に
対しその長手方向前後に若干量スライドできるように取
り付けてなる請求項1に記載の足場建枠用連結ピン。
2. The scaffolding frame connecting pin according to claim 1, wherein the connecting projection at the lower end portion of the supporting rod is attached to the supporting rod so as to be able to slide slightly forward and backward in the longitudinal direction thereof.
【請求項3】 係合突起の先端部は、ロック部材が非ロ
ック姿勢にあって係合突起がばね付勢力に抗して後退し
ている時でも、ピン本体の外側面から若干突出した状態
にあり、しかして係合突起の先端部が押圧されて係合突
起が更にピン本体内に後退されることにより、ロック部
材は、支持杆との押接状態から解放されて、その自重に
よりロック姿勢に傾転するようになっている請求項1又
は2に記載の足場建枠用連結ピン。
3. The tip of the engaging projection is in a state of slightly protruding from the outer surface of the pin body even when the locking member is in the unlocked posture and the engaging projection is retracted against the spring biasing force. When the tip of the engaging projection is pressed and the engaging projection is further retracted into the pin body, the lock member is released from the pressed state with the support rod and locked by its own weight. The scaffolding frame connecting pin according to claim 1 or 2, wherein the scaffolding frame connecting pin is tilted to a posture.
JP13664599A 1999-05-18 1999-05-18 Connecting pins for scaffolding frames Expired - Fee Related JP3443035B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13664599A JP3443035B2 (en) 1999-05-18 1999-05-18 Connecting pins for scaffolding frames

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13664599A JP3443035B2 (en) 1999-05-18 1999-05-18 Connecting pins for scaffolding frames

Publications (2)

Publication Number Publication Date
JP2000328779A JP2000328779A (en) 2000-11-28
JP3443035B2 true JP3443035B2 (en) 2003-09-02

Family

ID=15180171

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13664599A Expired - Fee Related JP3443035B2 (en) 1999-05-18 1999-05-18 Connecting pins for scaffolding frames

Country Status (1)

Country Link
JP (1) JP3443035B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2504363A1 (en) * 2004-07-27 2006-01-27 Daniel Grenon Adjustable and transportable scaffolding
EP1820920B1 (en) * 2006-01-24 2017-10-18 Combisafe International Ab Safety post
JP5328143B2 (en) * 2007-06-18 2013-10-30 ジーオーピー株式会社 Portable worktable
JP5878898B2 (en) * 2013-08-08 2016-03-08 信和株式会社 Scaffolding coupling device
JP7460987B2 (en) 2020-10-27 2024-04-03 日本電信電話株式会社 Pipe joining equipment and pipe joining equipment assembly

Also Published As

Publication number Publication date
JP2000328779A (en) 2000-11-28

Similar Documents

Publication Publication Date Title
TW200914741A (en) Fixture, fixing structure of fixed member, fixing method of fixed member and fixation-releasing method of fixture
US5400870A (en) Scaffolding frame system
JP3443035B2 (en) Connecting pins for scaffolding frames
JPH09302922A (en) Pipe joint
JP2007143274A (en) Clamp
JP4042105B2 (en) Scaffolding bracket
JP2653975B2 (en) Pipe joint
JP2005106241A (en) Pipe joint
JP3306001B2 (en) Connecting pins for scaffolding frames
JP2530773B2 (en) Scaffolding frame
JP3061770B2 (en) Telescopic leg fixing device
JP2543644B2 (en) Connecting pin for scaffolding frame
JPH07292958A (en) Joint of scaffolding frame
JPH0724521Y2 (en) Pipe joint
JP3631400B2 (en) Scaffolding frame connector
JP2543651B2 (en) Connecting pin for scaffolding frame
JP2548893B2 (en) Connecting pin for scaffolding frame
JP2872605B2 (en) Connection structure of scaffold frame
JP2530774B2 (en) Connection device for building frame for scaffolding
JPH085611Y2 (en) Folding table top plate metal fittings
JPH0316949Y2 (en)
JPS60257088A (en) Device detachably attaching device
JPH066699U (en) Telescopic ladder fixing device
JP2004324353A (en) Connection metal fitting for temporary installation
JP2543635B2 (en) Single pipe connection device for temporary installation

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20030521

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080620

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090620

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100620

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110620

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees