JP3218456B2 - Base surface finishing management system - Google Patents

Base surface finishing management system

Info

Publication number
JP3218456B2
JP3218456B2 JP24340996A JP24340996A JP3218456B2 JP 3218456 B2 JP3218456 B2 JP 3218456B2 JP 24340996 A JP24340996 A JP 24340996A JP 24340996 A JP24340996 A JP 24340996A JP 3218456 B2 JP3218456 B2 JP 3218456B2
Authority
JP
Japan
Prior art keywords
bulldozer
center position
displayed
information
base surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP24340996A
Other languages
Japanese (ja)
Other versions
JPH1091059A (en
Inventor
俊介 藤瀬
幹男 大浦
純一 藤田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP24340996A priority Critical patent/JP3218456B2/en
Publication of JPH1091059A publication Critical patent/JPH1091059A/en
Application granted granted Critical
Publication of JP3218456B2 publication Critical patent/JP3218456B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Operation Control Of Excavators (AREA)
  • Position Fixing By Use Of Radio Waves (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、造成工事等の土
木工事において、GPS(人工衛星による測位システ
ム)を利用して基盤仕上げを行う施工管理システムに関
するもので、特に、無人の遠隔操作式ブルドーザを用い
るタイプにおいて有人のブルドーザによる場合と同等以
上の操作性を発揮して効率的かつ的確に基盤面仕上げ作
業を実現する基盤面仕上げ管理システムの開発に関する
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction management system for finishing a foundation using a GPS (positioning system using an artificial satellite) in civil engineering work such as construction work, and more particularly to an unmanned remote-controlled bulldozer. The present invention relates to the development of a base surface finishing management system that realizes an efficient and accurate base surface finishing operation by exhibiting operability equal to or greater than that of a manned bulldozer in a type using a manned bulldozer.

【0002】[0002]

【従来の技術】本発明者らは、建設機械による無人化施
工を実現するため従来より提案されている技術的手段、
すなわち、少なくとも4個の衛星によるGPS測位シス
テムを利用して建設ロボットによる無人化施工を行うよ
うにしたもの(特開平4ー296683号公報)、又は
造成されつつある地山の出来高測量画像と計画画像とを
スーパーインポーズして監視センターに配備する表示装
置に表示して現在の地山の出来形を計画図と対比して把
握できるようにしたもの(特開平4ー290915号公
報)では、無人化した建設機械を走行させたり、ある程
度の掘削等の実作業を行うことはできても、掘削、盛
土、押土等というその機械のもつ本来的な機能を十分発
揮しながら最後まで完結した作業を行うことが困難であ
ることに鑑みて、GPS技術及びテレビカメラを利用し
て、オペレータが無人化した建設機械の位置、姿勢等が
リアルタイムでモニタりングされるモニター画面を見な
がら当該建設機械を遠隔操作する構成としたGPS無人
施工システムを発明した。
2. Description of the Related Art The present inventors have proposed technical means for realizing unmanned construction using construction machines.
That is, an unmanned construction is performed by a construction robot using a GPS positioning system with at least four satellites (Japanese Patent Laid-Open No. Hei 4-296683), or a volumetric survey image of a ground being constructed and a plan. In a system in which images are superimposed and displayed on a display device provided at a monitoring center so that the current formation of the ground can be grasped by comparing it with a plan map (Japanese Patent Laid-Open No. 4-290915), Although it was possible to run unmanned construction machinery and perform some actual work such as excavation, it was completed to the end while fully exhibiting the original functions of the machine, such as excavation, embankment, and embankment. In view of the difficulty in performing the work, the position and posture of the unmanned construction machine are monitored in real time by an operator using GPS technology and a television camera. Ri while watching the packaging is the monitor screen invented GPS unattended installation system the construction machine is configured to be remotely operated.

【0003】このGPS無人施工システムによれば、G
PS技術及びテレビカメラ等による複数の画像情報や施
工情報をオペレータが見ながら遠隔操作盤を操作するよ
うにしたので、オペレータが搭乗して操作を行う場合に
おける視界、平衡感覚等の情報と略同等か、又はそれ以
上の情報内容を得ることができるから、容易かつ確実な
遠隔操作が担保されることになり、当該建設機械の本来
的な機能を十分に発揮することができ、それゆえ、完全
無人化施工を実現することができる。
According to this GPS unmanned construction system, G
Since the operator operates the remote control panel while viewing multiple pieces of image information and construction information from PS technology and TV cameras, etc., it is almost equivalent to information such as the field of view and sense of balance when the operator performs operations while boarding Or more information content can be obtained, so that easy and reliable remote operation can be ensured, and the essential functions of the construction machine can be fully exhibited, and therefore, Unmanned construction can be realized.

【0004】しかしながら、当該建設機械により基盤面
部分を掘削、押土等して仕上げ作業を行う場合には、必
ずしも一律に所定の厚さの土砂を削り取るという単純作
業のみならず、凹凸で構成される複雑な面を時には部分
的に削り取り、時には部分的に盛土するという細かい高
さの調整作業が必要となるため、通常の平面部分を掘削
等する場合と同様な考え方に立って施工管理しようとす
ると、均等で平滑な基盤面を得ることが困難となる。
[0004] However, when a finishing operation is performed by excavating or pressing a base surface portion using the construction machine, not only a simple operation of uniformly removing a predetermined thickness of soil and sand, but also a concavo-convex structure. It is necessary to finely adjust the height of the complex surface by partially shaving it and sometimes embanking it, so try to manage the construction based on the same concept as when excavating a normal flat part. Then, it is difficult to obtain a uniform and smooth base surface.

【0005】また、掘削床付面やコンクリート打設天端
面等の基盤面は、通常、かなり広範囲に亘っていること
から、効率的かつ迅速な施工が実現されることになれ
ば、これがもたらす経済的な波及効果はきわめて大きな
ものとなる。
[0005] In addition, the base surface such as the surface with the excavated floor and the top end surface of concrete casting is usually quite extensive, so that if efficient and quick construction is to be realized, the economics brought by this will be brought about. The spillover effect is extremely large.

【0006】[0006]

【発明が解決しようとする課題】そこで、この発明は、
GPS無人施工システムに係る遠隔操作式ブルドーザを
用いて基盤面部分の仕上げ作業を行う場合において、部
分的に必要となる細かい高さの調整作業を容易になし得
るとともに、作業面全体に亘り効率的かつ迅速な基盤面
仕上げ作業を実現し得る基盤面仕上げ管理システムを提
供することを目的とする。
SUMMARY OF THE INVENTION Therefore, the present invention
When finishing a base surface portion using a remotely operated bulldozer related to a GPS unmanned construction system, it is possible to easily perform a fine height adjustment work that is partially required, and efficiently perform the entire work surface. It is another object of the present invention to provide a base surface finishing management system capable of realizing a quick base surface finishing operation.

【0007】[0007]

【課題を解決するための手段】すなわち、この発明に係
る基盤面仕上げ管理システムは、図1に示すように、施
工領域のうち、無人区域にGPSアンテナ1を具備した
遠隔操作式ブルドーザ2を配備して、テレビカメラによ
る当該ブルドーザ2の画像情報3、及び少なくとも4個
の衛星を利用して把握した施工情報4がリアルタイムで
表示されるモニター画面5を見ながら、無人区域以外の
有人区域のオペレータ6が遠隔操作盤を操作して無人区
域の当該ブルドーザ2に基盤面の仕上げをさせる基盤面
仕上げ管理システムにおいて、前記施工情報4は、均等
な複数のブロック5aからなるモニター画面5上の矩形
領域5bに基盤面仕上げ範囲を当てはめて表示する基盤
面仕上げ範囲情報7と、計画高さに対する現況高さの高
低差を段階別に色分けして各段階に対応する高低差を有
するブロック5aが対応する色で表示されるブロック別
高低差情報8と、設定時間の経過に伴うGPSアンテナ
1の電気的中心位置Eの平面移動の方向、及び当該移動
後の電気的中心位置Eを基礎として、当該ブルドーザ2
の位置及び前後方向を示す当該ブルドーザ2の平面図が
矩形領域5bの対応する部位にリアルタイムで表示され
るブルドーザ位置方向情報9とを具備して、前記電気的
中心位置Eから把握される当該ブルドーザ2の機械的中
心位置Mの高さの変動に追従してブロック内の表示色が
リアルタイムに新しい高低差に対応した色に置き換わる
ようにしたことを特徴とするものである。
That is, in the base surface finishing management system according to the present invention, as shown in FIG. 1, a remotely operated bulldozer 2 having a GPS antenna 1 is installed in an unmanned area in a construction area. Then, while viewing the image information 3 of the bulldozer 2 by the television camera and the monitor screen 5 in which the construction information 4 grasped using at least four satellites is displayed in real time, the operator of the manned area other than the unmanned area is operated. In the base surface finish management system 6 for operating the remote control panel to finish the base surface of the bulldozer 2 in the unmanned area, the construction information 4 includes a rectangular area on the monitor screen 5 including a plurality of uniform blocks 5a. The base surface finish range information 7 displayed by applying the base surface finish range to 5b, and the height difference of the current height with respect to the planned height are displayed in different colors. In addition, the block-by-block height difference information 8 in which the block 5a having the height difference corresponding to each stage is displayed in the corresponding color, the direction of the planar movement of the electrical center position E of the GPS antenna 1 with the elapse of the set time, And the bulldozer 2 based on the electrical center position E after the movement.
The bulldozer 2 includes a bulldozer position direction information 9 that is displayed in real time at a corresponding portion of the rectangular area 5b, and the bulldozer 2 is grasped from the electrical center position E. The display color in the block is replaced in real time with a color corresponding to a new height difference in accordance with a change in the height of the mechanical center position M of No. 2.

【0008】このような技術的手段において、遠隔操作
式ブルドーザ2としては、ラジオコントロールの原理を
基礎として、当該ブルドーザ2の有する本来的な機能で
ある掘削、整地等の作業を行うことが可能であれば、足
回りがクローラ式であるか、又はタイヤ式であるか等、
その形式については特に問わなが、基盤面仕上げという
整地を主体とした作業の特徴から、例えば、通常のブル
ドーザやモーターグレーダー等のように排土板等で地山
を削り取るタイプのものであることが必要とされるほ
か、排土板等で地山を削り取った後すぐにその位置を計
測する必要があることから、排土板等、地山を削り取る
アタッチメントが配備される部分の後方にGPSアンテ
ナ1が配備されている必要がある。
[0008] In such technical means, the remote control bulldozer 2 can perform operations such as excavation and leveling which are essential functions of the bulldozer 2 based on the principle of radio control. If so, whether the underbody is a crawler type, or a tire type, etc.
There is no particular question about the type, but due to the characteristics of work that mainly consists of terrain finishing of the base surface, it must be of the type that removes the ground with a dumping plate, such as a normal bulldozer or motor grader Is required, and the position must be measured immediately after the ground is scraped off by the earth removal plate. Therefore, the GPS is installed behind the part where the attachment for shaving the earth such as the earth removal plate is provided. The antenna 1 needs to be provided.

【0009】また、画像情報3としては、テレビカメラ
により当該ブルドーザ2の動きを捉えたものであればよ
く、オペレータの操作性の向上を図る観点からすれば、
一台の遠隔操作式ブルドーザにつき二以上のテレビカメ
ラを設置して多方向からの画像を得ることが好ましい。
The image information 3 may be any information obtained by capturing the movement of the bulldozer 2 with a television camera. From the viewpoint of improving the operability of the operator,
Preferably, more than one television camera is installed per remote controlled bulldozer to obtain images from multiple directions.

【0010】さらに、施工情報4としては、基盤面仕上
げ範囲情報7、ブロック別高低差情報8、及びブルドー
ザ位置方向情報9とを具備して、電気的中心位置Eから
把握される当該ブルドーザ2の機械的中心位置Mの高さ
の変動に追従してブロック内の表示色がリアルタイムに
新しい高低差に対応した色に置き換わるようにしたもの
であればよい。
Further, the construction information 4 includes base surface finish range information 7, block-specific elevation difference information 8, and bulldozer position / direction information 9, and includes information on the bulldozer 2 grasped from the electrical center position E. Any configuration may be used as long as the display color in the block is replaced in real time with a color corresponding to the new height difference following the change in the height of the mechanical center position M.

【0011】さらに、モニター画面5としては、画像情
報3及び施工情報4を表示できるものであればよく、オ
ペレータの操作性に支障をきたさない限度において、一
のモニター画面内を分割表示とするものや、複数のモニ
ター画面を一個所の集めてユニット状に設置したもの
等、その形式については問わない。
Further, the monitor screen 5 is only required to be able to display the image information 3 and the construction information 4, and the one monitor screen is divided and displayed as long as the operability of the operator is not hindered. There is no limitation on the type of the monitor, such as a plurality of monitor screens collected in one place and installed in a unit.

【0012】さらにまた、ブルドーザ位置方向情報9と
しては、設定時間の経過に伴うGPSアンテナ1の電気
的中心位置Eの平面移動の方向、及び当該移動後の電気
的中心位置Eを基礎として、当該ブルドーザ2の位置及
び前後方向を示す当該ブルドーザ2の平面図が矩形領域
5bの対応する部位にリアルタイムで表示されればよい
が、GPS測位システムの計測誤差により当該ブルドー
ザ2の平面図が頻繁に反転する事態を回避してオペレー
タの操作性の向上を図る観点からすれば、設定時間の経
過に伴うGPSアンテナ1の電気的中心位置Eの平面移
動量が予め設定した長さ寸法に満たない場合には遠隔操
作式ブルドーザ2が平面移動していないものとみなして
当該ブルドーザ2の平面図を静止表示とするようにした
ことが好ましい。
Further, the bulldozer position direction information 9 is based on the direction of the planar movement of the electric center position E of the GPS antenna 1 with the elapse of the set time and the electric center position E after the movement. The plan view of the bulldozer 2 showing the position and the front-back direction of the bulldozer 2 may be displayed in real time at the corresponding portion of the rectangular area 5b, but the plan view of the bulldozer 2 is frequently inverted due to a measurement error of the GPS positioning system. From the viewpoint of avoiding the situation and improving the operability of the operator, when the planar movement amount of the electric center position E of the GPS antenna 1 with the elapse of the set time is less than the length dimension set in advance. Preferably, the bulldozer 2 is regarded as not moving in a plane, and the plan view of the bulldozer 2 is preferably displayed as a static display.

【0013】また、当該ブルドーザ2のバック走行を反
転と認識して平面図の前後方向が逆に表示される事態を
未然に防止してオペレータの操作性の向上を図る観点か
らすれば、前記ブルドーザ位置方向情報9としては、設
定時間の経過に伴うGPSアンテナ1の電気的中心位置
Eの平面移動方向が転換された場合において、転換前の
電気的中心位置Eの平面移動方向と転換後の電気的中心
位置Eの平面移動方向とがなす角度が予め設定した角度
より大きい場合に限って、遠隔操作式ブルドーザ2が方
向転換したものとみなして当該ブルドーザ2の平面図の
前後方向を転換させて表示するようにしたことが好まし
い。
Further, from the viewpoint of recognizing the reverse running of the bulldozer 2 as reversal and preventing the front-rear direction of the plan view from being displayed in reverse, thereby improving the operability of the bulldozer, As the position / direction information 9, when the plane moving direction of the electric center position E of the GPS antenna 1 is changed with the elapse of the set time, the plane moving direction of the electric center position E before the change and the electric direction after the change are changed. Only when the angle formed between the target center position E and the plane moving direction is larger than a preset angle, it is considered that the remote-controlled bulldozer 2 has changed direction, and the front-rear direction of the plan view of the bulldozer 2 is changed. Preferably, it is displayed.

【0014】なお、設定時間とは、ブルドーザが現に走
行している平面方向を知るためGPSアンテナの電気的
中心位置Eの平面移動方向を計測する目的から、予め設
定される計測タイミングの間隔時間のことであり、短け
れば短いほど限りなく実際に近似する値(ブルドーザの
走行方向)を得ることが可能である。
Note that the set time is defined as an interval time between measurement timings set in advance for the purpose of measuring the plane movement direction of the electrical center position E of the GPS antenna in order to know the plane direction in which the bulldozer is actually traveling. In other words, it is possible to obtain a value (the running direction of the bulldozer) that is actually approximated as much as possible as soon as possible.

【0015】また、電気的中心位置Eとは、GPS衛星
からの電波を受信する場合のGPSアンテナの略中心部
分に位置する計測原点であり、機械的中心位置Mとは、
当該ブルドーザ2に固着されるGPSアンテナの電気的
中心位置Eを通る垂線と当該ブルドーザの足回りが載置
される仮想の基準面との交点を意味する。
The electrical center position E is a measurement origin located substantially at the center of the GPS antenna when receiving a radio wave from a GPS satellite, and the mechanical center position M is
It means the intersection of a perpendicular passing through the electrical center position E of the GPS antenna fixed to the bulldozer 2 and a virtual reference plane on which the underbody of the bulldozer is placed.

【0016】[0016]

【発明の実施の形態】以下、添付図面に示す実施の形態
に基づいてこの発明について詳細に説明する。図2はこ
の発明に係る基盤面仕上げ管理システムの一実施の形態
が無人で施工する砂防ダム工事現場に適用された場合に
おける施工状況を示す説明図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below in detail based on an embodiment shown in the accompanying drawings. FIG. 2 is an explanatory diagram showing a construction situation when an embodiment of the base surface finish management system according to the present invention is applied to a sabo dam construction site constructed by unmanned personnel.

【0017】同図において、符号21は始点位置21a
から終点位置21bまでの矩形範囲であって現在仕上げ
作業中、又はこれから仕上げ作業を行うはずの基盤面で
あるコンクリート天端面の仕上げを行う基盤面仕上げ範
囲、22はGPSアンテナ22a、及び無線アンテナ2
2bを有して基盤面の仕上げ作業をするラジコンブルド
ーザ、23はGPSアンテナ23a及び無線アンテナ2
3bを有してラジコンブルドーザ22では対応できない
補助的作業をするラジコンバックホウ、24は無線アン
テナ24aを有して生コンクリートを基盤面仕上げ範囲
21へと搬入するラジコンダンプトラック、25は第1
テレビカメラ25a及び無線アンテナ25bを有する第
1ラジコン高所作業車、26は第2テレビカメラ26a
及び無線アンテナ26bを有する第2ラジコン高所作業
車である。
In FIG. 1, reference numeral 21 denotes a starting point position 21a.
To the end point position 21b and a base surface finishing range for finishing a concrete top end surface, which is a base surface that is currently being finished or is to be finished from now on, 22 is a GPS antenna 22a and a radio antenna 2
Radio-controlled bulldozer for finishing the base surface with 2b, 23 is a GPS antenna 23a and a radio antenna 2
A radio-controlled backhoe having an auxiliary work that cannot be handled by the radio-controlled bulldozer 22 having a 3b; a radio-controlled dump truck 24 having a radio antenna 24a for carrying ready-mixed concrete into the base surface finishing area 21;
A first radio controlled aerial vehicle having a television camera 25a and a radio antenna 25b, 26 is a second television camera 26a
And a second radio-controlled aerial vehicle having a radio antenna 26b.

【0018】この実施の形態に係るラジコンブルドーザ
22は、図3に示すように、モニターデスク31上に固
着されている2段構成のモニターユニット32に載置さ
れているモニター画面33と、モニターデスク31上に
載置されているキーボード34aを有するコンピュータ
34と、当該モニター画面33の正面に配置されるラジ
コン操作盤35と、このラジコン操作盤35を操作すべ
く座るためのイス36とで構成されるラジコン操作ユニ
ット37を施工個所から離して配備した上で、オペレー
タ38がイス36に腰掛けてモニター画面33に表示さ
れる各種情報を見ながら、ラジコン操作盤35を操作す
ることによりラジオコントロールされることになる。
As shown in FIG. 3, a radio controlled bulldozer 22 according to this embodiment has a monitor screen 33 mounted on a two-stage monitor unit 32 fixed on a monitor desk 31, and a monitor desk 33. It comprises a computer 34 having a keyboard 34a mounted on the base 31, a radio control panel 35 arranged in front of the monitor screen 33, and a chair 36 for sitting down to operate the radio control panel 35. After the radio-controlled operation unit 37 is deployed away from the construction location, the operator 38 operates the radio-controlled operation panel 35 while sitting on the chair 36 and viewing various information displayed on the monitor screen 33 to perform radio control. Will be.

【0019】また、モニター画面33は、第1テレビカ
メラ25aからの画像を表示するAモニター33aと、
第2テレビカメラ25aからの画像を表示するBモニタ
ー33bと、GPS測位システム及び無線通信システム
を利用して検出したラジコンブルドーザ22の位置デー
タ及び姿勢データをコンピュータ34により処理して施
工情報として表示するCモニター33cとで構成されて
おり、全部で3画面を有している。
The monitor screen 33 includes an A monitor 33a for displaying an image from the first television camera 25a,
A computer 34 processes the position data and attitude data of the radio controlled bulldozer 22 detected using the B monitor 33b that displays an image from the second television camera 25a and the GPS positioning system and the wireless communication system, and displays the processed information as construction information. The C monitor 33c has three screens in total.

【0020】このCモニターに係る施工情報は、図4に
示すように、同一の正方形ブロック41aの複数が集結
してなるCモニター33c上の矩形領域41に基盤面仕
上げ範囲を当てはめて表示する基盤面仕上げ範囲情報4
2と、計画高さに対する現況高さの高低差を段階別に色
分けして各段階に対応する高低差を有する正方形ブロッ
ク41aが対応する色で表示されるブロック別高低差情
報43と、ラジコンブルドーザ22の位置及び前後方向
を示すラジコンブルドーザ22の平面絵図44aが矩形
領域41の対応する部位にリアルタイムで表示されるブ
ルドーザ位置方向情報44とを重ね合わせて表示すると
いうものである。
As shown in FIG. 4, the construction information related to the C monitor is displayed by applying the base surface finishing range to the rectangular area 41 on the C monitor 33c in which a plurality of the same square blocks 41a are gathered. Surface finish range information 4
2, a block height difference information 43 in which a square block 41a having a height difference corresponding to each stage is displayed in a corresponding color by classifying the height difference of the current height with respect to the planned height by a stage, and a radio controlled bulldozer 22 Of the radio controlled bulldozer 22 indicating the position and the front-back direction of the radio-controlled bulldozer 22 is displayed by superimposing the bulldozer position / direction information 44 displayed in real time on the corresponding portion of the rectangular area 41.

【0021】この基盤面仕上げ範囲情報42は、具体的
には、予め現場において基盤面の仕上げ作業を行うべき
範囲の始点位置及び終点位置に実際にラジコンブルドー
ザ22等を停止位置させて各々の平面座標の確認をした
後、当該平面座標をコンピュータ34にキーボード34
aから入力することにより、Cモニター33c上の矩形
領域41の左上隅に基盤面仕上げ範囲の始点位置を示す
平面座標(Xs,Ys)が表示されるとともに、当該矩
形領域41の右下隅に基盤面仕上げ範囲の終点位置を示
す平面座標(Xe,Ye)が表示されるというものであ
る。
Specifically, the base surface finishing range information 42 is obtained by actually stopping the radio-controlled bulldozer 22 or the like at the start point and the end point of the range in which the base surface finishing operation is to be performed on the site in advance. After confirming the coordinates, the plane coordinates are input to the computer 34 by the keyboard 34.
By inputting from a, the plane coordinates (Xs, Ys) indicating the starting point position of the substrate surface finishing range are displayed at the upper left corner of the rectangular area 41 on the C monitor 33c, and the substrate is located at the lower right corner of the rectangular area 41. Plane coordinates (Xe, Ye) indicating the end point position of the surface finishing range are displayed.

【0022】したがって、この基盤面仕上げ範囲情報4
2によれば、現在、施工管理されている基盤面の平面範
囲が常にオペレータ38に明確に知らされることになる
とともに、正方形ブロック41aの各々の辺の現場にお
ける長さ寸法(Cモニター33c上では正方形で表示さ
れるが、実際には正方形であるとは限らない)を知るこ
とができ、オペレータ38はラジコンブルドーザ23の
ラジコン操作を効率的かつ的確に行うことが可能とな
る。
Therefore, the base surface finish range information 4
According to 2, the plane area of the base surface currently under construction management is always clearly known to the operator 38, and the length of each side of the square block 41 a at the site (on the C monitor 33 c). Is displayed as a square, but it is not necessarily a square), and the operator 38 can perform the radio control operation of the radio controlled bulldozer 23 efficiently and accurately.

【0023】また、ブロック別高低差情報43は、予め
作業効率、操作性等を考慮して計画高さに対する現況高
さの高低差を最適な6段階に分けて設定するとともに、
各段階に対応する色を設定してCモニター33c上の画
面下部に表示するようにした上で、現場の基盤面仕上げ
範囲内において、所定の段階の標高となっている部位に
対応する正方形ブロック41aが対応する色で表示され
るというものであり、しかも、ラジコンブルドーザ22
の電気的中心位置Eから把握される当該ブルドーザ2の
機械的中心位置Mの高さの変動に追従して正方形ブロッ
ク41aの表示色がリアルタイムで新しい高低差に対応
した色に置き換わることになり、これにより、矩形領域
41内のすべての正方形ブロック41aはリアルタイム
で現場の実際の標高に対応した色で表示することが可能
となる。
The block-by-block height difference information 43 sets the height difference of the current height with respect to the planned height in six optimal stages in consideration of work efficiency, operability, and the like in advance.
After setting the color corresponding to each stage and displaying it at the lower part of the screen on the C monitor 33c, a square block corresponding to a site having an altitude at a predetermined stage within the finishing area of the base surface of the site. 41a is displayed in a corresponding color.
Following the change in the height of the mechanical center position M of the bulldozer 2 grasped from the electrical center position E, the display color of the square block 41a is replaced in real time with a color corresponding to the new height difference, Thus, all the square blocks 41a in the rectangular area 41 can be displayed in real time with a color corresponding to the actual altitude at the site.

【0024】さらに、ブルドーザ位置方向情報44は、
予め一定の時間、例えば、3秒間を設定して、この3秒
間が経過する間におけるラジコンブルドーザ22に係る
GPSアンテナ22aの電気的中心位置Eの平面移動の
方向、及び当該移動後の電気的中心位置Eの平面座標に
基づいて、コンピュータ34でグラフィックス処理をし
てラジコンブルドーザ22に係る平面絵図44aを矩形
領域41の対応する部位にリアルタイムで表示してラジ
コンブルドーザ22の平面位置を表示するとともに、前
記平面絵図44aにブレード44bの方向を正しく示す
ことにより、ラジコンブルドーザ22の前後方向をも表
示するようになっている。
Further, the bulldozer position / direction information 44 includes:
A predetermined time, for example, 3 seconds, is set in advance, and the direction of the planar movement of the electric center position E of the GPS antenna 22a of the radio controlled bulldozer 22 during the 3 seconds elapses, and the electric center after the movement. Based on the plane coordinates of the position E, the computer 34 performs graphics processing, displays a plan picture 44a of the radio controlled bulldozer 22 in a corresponding portion of the rectangular area 41 in real time, and displays the plane position of the radio controlled bulldozer 22. By correctly indicating the direction of the blade 44b in the plan picture 44a, the front-back direction of the radio-controlled bulldozer 22 is also displayed.

【0025】すなわち、ラジコンブルドーザ22に係る
平面絵図44aは、原則として、3秒間が経過する間に
おけるラジコンブルドーザ22に係るGPSアンテナ2
2aの電気的中心位置Eの平面移動の方向にブレード4
4bを表示した状態で当該方向に沿って平面絵図44a
が表示されると同時に、電気的中心位置Eの平面移動後
の電気的中心位置Eの平面座標に対応する矩形領域41
上のポイントと当該平面絵図44aに表示される電気的
中心位置eとが合致するように表示されることになる
(図5参照)。
That is, the plan picture 44a relating to the radio-controlled bulldozer 22 basically indicates that the GPS antenna 2 pertaining to the radio-controlled bulldozer 22 during three seconds has elapsed.
The blade 4 moves in the direction of the plane movement of the electrical center position E of 2a.
4b is displayed along the direction with the plane picture 44a displayed.
Is displayed, and at the same time, a rectangular area 41 corresponding to the plane coordinates of the electric center position E after the electric center position E is moved in a plane.
The upper point and the electrical center position e displayed on the plan picture 44a are displayed so as to match (see FIG. 5).

【0026】また、この実施の形態では、3秒間が経過
する間におけるGPSアンテナ22aの電気的中心位置
Eの平面移動量が10cmに満たない場合には、ラジコ
ンブルドーザ22が平面移動していないものとみなすこ
ととしており、矩形領域41上においてもラジコンブル
ドーザ22の平面図を静止したまま表示するような処置
をしているが、これは、通常、GPS測位システムの計
測誤差は常に1〜2cm程度は確実に存在することか
ら、仮に、このような許容範囲を設定しないとすれば、
平面絵図44aが頻繁に反転する事態を招くことにな
り、オペレータ38の操作性に支障をきたすことになる
ためである。
In this embodiment, when the planar movement of the electric center position E of the GPS antenna 22a during the lapse of three seconds is less than 10 cm, the radio-controlled bulldozer 22 does not move in a plane. It is assumed that the plan view of the radio controlled bulldozer 22 is displayed in a stationary state even on the rectangular area 41. However, this is usually because the measurement error of the GPS positioning system is always about 1 to 2 cm. Exists, so if we don't set such a tolerance,
This is because the situation in which the plan picture 44a is frequently inverted is caused, which hinders the operability of the operator 38.

【0027】さらに、この実施の形態では、3秒間が経
過する間におけるGPSアンテナ22aの電気的中心位
置Eの平面移動方向が転換された場合において、転換さ
れる前の電気的中心位置Eの平面移動方向と転換された
後の電気的中心位置Eの平面移動方向とがなす角度が予
め設定した角度である30°より大きい場合に限り、ラ
ジコンブルドーザ22が方向転換したものとみなすこと
としており、矩形領域41上においてもラジコンブルド
ーザ22の平面絵図44aの前後方向を転換させて表示
するようにしている。
Further, in this embodiment, when the plane moving direction of the electric center position E of the GPS antenna 22a is changed during the elapse of 3 seconds, the plane of the electric center position E before the change is changed. Only when the angle between the moving direction and the plane moving direction of the electrical center position E after the turning is larger than the preset angle of 30 °, the radio-controlled bulldozer 22 is considered to have changed direction. Even in the rectangular area 41, the front and rear directions of the plan picture 44a of the radio controlled bulldozer 22 are changed and displayed.

【0028】このような処置をすることにより、ラジコ
ンブルドーザ22が単にバック走行したに過ぎないにも
拘わらず、反転してブレード44bの方向を転換させた
ものと誤認して、平面絵図44aの前後方向が逆に表示
される事態を未然に略防止することができるから、この
ような処置は、オペレータの操作性の向上を図ることに
寄与することになる。
By performing such a treatment, the radio control bulldozer 22 mistakenly recognizes that the direction of the blade 44b has been reversed by reversing the direction of the blade 44b despite the fact that the radio controlled bulldozer 22 simply travels in the reverse direction. Since it is possible to substantially prevent a situation in which the direction is displayed in reverse, such a measure contributes to improving the operability of the operator.

【0029】ここで、図5を用いて、予め設定した時間
である3秒間の経過を一区切りとしてラジコンブルドー
ザ22の平面移動に伴う平面絵図44aに係る電気的中
心位置eの軌跡に着目して、当該平面絵図44aの作動
について詳細に説明する。
Here, referring to FIG. 5, focusing on the locus of the electrical center position e in the plane pictorial diagram 44a accompanying the plane movement of the radio controlled bulldozer 22 with the elapse of 3 seconds, which is a preset time, as one interval, The operation of the plan picture 44a will be described in detail.

【0030】(a)平面移動開始 現場の基盤面仕上げ範囲において、ラジコンブルドーザ
22に係るGPSアンテナ22aは静止しているため、
矩形領域41上において、ラジコンブルドーザ22に係
る平面絵図44aも静止しており、よって、平面絵図4
4aに係る電気的中心位置eも静止している。
(A) Start of plane movement Since the GPS antenna 22a related to the radio-controlled bulldozer 22 is stationary in the finishing area of the base surface at the site,
On the rectangular area 41, the plan picture 44a of the radio-controlled bulldozer 22 is also stationary, so that the plan picture 4
The electrical center position e according to 4a is also stationary.

【0031】この時、ラジコンブルドーザ22に係るG
PSアンテナ22aの位置データの検出結果は、経時的
に1〜2cmの間で変動することになるが、この実施の
形態では、3秒間が経過する間におけるGPSアンテナ
22aの電気的中心位置Eの平面移動量が10cmに未
満のときは、ラジコンブルドーザ22が平面移動してい
ないものとみなすように設定されているため、平面絵図
44aがその都度反転するような不都合はない。
At this time, the G related to the radio-controlled bulldozer 22
Although the detection result of the position data of the PS antenna 22a fluctuates between 1 and 2 cm with time, in this embodiment, the position of the electrical center position E of the GPS antenna 22a during 3 seconds elapses. When the plane movement amount is less than 10 cm, the radio controlled bulldozer 22 is set to be regarded as not moving on the plane, so that there is no inconvenience that the plane picture 44a is inverted each time.

【0032】(b)平面移動中(3秒後) 次いで、現場の基盤面仕上げ範囲において、ラジコンブ
ルドーザ22に係るGPSアンテナ22aが基盤面仕上
げ作業を行うべく平面移動(走行)すると、これに追従
してGPSアンテナ22aの電気的中心位置Eも平面移
動することになるが、3秒間が経過したタイミングで
は、当該電気的中心位置Eの移動後の位置に対応する矩
形領域41上のポイントと、前記平面絵図44aに表示
される電気的中心位置eとが合致するように表示される
ことになる。
(B) During Plane Movement (After 3 Seconds) Next, when the GPS antenna 22a of the radio-controlled bulldozer 22 moves (runs) in a plane to perform the work for finishing the base surface in the range for finishing the base surface at the site, the movement follows. As a result, the electric center position E of the GPS antenna 22a also moves in a plane, but at the timing when 3 seconds have elapsed, a point on the rectangular area 41 corresponding to the position after the movement of the electric center position E, The electric center position e displayed on the plan picture 44a is displayed so as to match.

【0033】この時、前記平面絵図44aの方向は、平
面絵図44aに係る電気的中心位置eの軌跡45の方向
と同一方向に設定されるとともに、ブレード44bの方
向も前記軌跡45の進行方向に合わせて表示されること
になる。
At this time, the direction of the plan picture 44a is set in the same direction as the direction of the locus 45 of the electric center position e according to the plan picture 44a, and the direction of the blade 44b is also the direction of travel of the locus 45. It will be displayed together.

【0034】この場合において、GPSアンテナ22a
の電気的中心位置Eも平面移動量は10cmに未満であ
るので、平面絵図44aは当該平面移動量に対応した分
だけ平面移動することとなる。
In this case, the GPS antenna 22a
Since the electric center position E of the electric field E has a plane movement amount of less than 10 cm, the plane picture 44a moves on the plane by an amount corresponding to the plane movement amount.

【0035】(c)平面移動中(6秒後) 次いで、現場の基盤面仕上げ範囲において、平面移動開
始後3秒間が経過したタイミングにおける位置から平面
移動方向を転換して、ラジコンブルドーザ22に係るG
PSアンテナ22aが基盤面仕上げ作業を行うべく更に
平面移動(走行)すると、これに追従してGPSアンテ
ナ22aの電気的中心位置Eも平面移動することになる
が、平面移動開始後6秒間が経過したタイミングでは、
当該電気的中心位置Eの6秒経過後の位置に対応する矩
形領域41上のポイントと、前記平面絵図44aに表示
される電気的中心位置eとが合致するように表示される
ことになる。
(C) During plane movement (after 6 seconds) Next, in the finishing area of the base surface of the site, the plane movement direction is changed from the position at the timing when 3 seconds have elapsed since the start of the plane movement, and the radio controlled dozer 22 is operated. G
When the PS antenna 22a further moves (travels) in a plane to perform the substrate surface finishing work, the electric center position E of the GPS antenna 22a also moves in a plane following the movement, but six seconds elapse after the start of the plane movement. At the timing,
The point on the rectangular area 41 corresponding to the position of the electric center position E after 6 seconds has elapsed and the electric center position e displayed on the plan picture 44a are displayed so as to match.

【0036】この時、前記平面絵図44aの方向は、平
面絵図44aに係る電気的中心位置eの軌跡46の方向
と同一方向に設定されることになるが、ブレード44b
の方向については3秒間が経過する間における電気的中
心位置eの軌跡が軌跡45から軌跡46へと転換されて
いるため、以下のような判断がなされることになる。
At this time, the direction of the plan picture 44a is set in the same direction as the direction of the trajectory 46 of the electric center position e according to the plan picture 44a.
In the direction of, since the trajectory of the electrical center position e is changed from the trajectory 45 to the trajectory 46 during the elapse of 3 seconds, the following determination is made.

【0037】すなわち、平面移動方向が転換される前の
電気的中心位置eの軌跡45と平面移動方向が転換され
た後の電気的中心位置eの軌跡46とがなす平面角度が
30°よりも大きい場合には、ラジコンブルドーザ22
の方向が転換されたものとみなしてブレード44bを反
転表示することとする一方、当該角度が30°よりも小
さい場合には、ラジコンブルドーザ22の方向は転換さ
れず単にバック走行したものとみなしてブレード44b
を反転表示しないこととする。
That is, the trajectory 45 of the electric center position e before the plane moving direction is changed and the trajectory 46 of the electric center position e after the plane moving direction is changed have a plane angle of more than 30 °. If large, radio controlled bulldozer 22
The direction of the radio controlled bulldozer 22 is assumed to be simply reversed when the angle is smaller than 30 °. Blade 44b
Is not displayed in reverse video.

【0038】今回の場合は、軌跡45と軌跡46とがな
す平面角度47が30°よりも大きいので、ラジコンブ
ルドーザ22の方向が転換されたものとみなして、矩形
領域41上において、ブレード44bを反転表示するこ
ととする。
In this case, since the plane angle 47 between the trajectory 45 and the trajectory 46 is larger than 30 °, it is considered that the direction of the radio-controlled bulldozer 22 has been changed, and the blade 44 b is moved on the rectangular area 41. It will be displayed in reverse video.

【0039】(d)平面移動中(9秒後) 次に、現場の基盤面仕上げ範囲において、平面移動開始
後6秒間が経過したタイミングにおける位置から平面移
動方向を転換して、ラジコンブルドーザ22に係るGP
Sアンテナ22aが更に基盤面仕上げ作業を行うべく平
面移動(走行)すると、これに追従してGPSアンテナ
22aの電気的中心位置Eも平面移動することになる
が、平面移動開始後9秒間が経過したタイミングでは、
当該電気的中心位置Eの9秒経過後の位置に対応する矩
形領域41上のポイントと、前記平面絵図44aに表示
される電気的中心位置eとが合致するように表示される
ことになる。
(D) During plane movement (after 9 seconds) Next, in the finishing area of the base surface of the site, the plane movement direction is changed from the position at the timing when 6 seconds have elapsed after the start of the plane movement, and Such GP
When the S antenna 22a further moves (runs) in a plane to perform the substrate surface finishing work, the electrical center position E of the GPS antenna 22a also moves in a plane following the movement, but 9 seconds have elapsed after the start of the plane movement. At the timing,
The point on the rectangular area 41 corresponding to the position after 9 seconds from the electric center position E is displayed so as to match the electric center position e displayed in the plan picture 44a.

【0040】この時、前記平面絵図44aの方向は、平
面絵図44aに係る電気的中心位置eの軌跡46の方向
と同一方向に設定されることになるが、ブレード44b
の方向については3秒間が経過する間における電気的中
心位置eの軌跡が軌跡46から軌跡48へと転換されて
いるため、以下のような判断がなされることになる。
At this time, the direction of the plan picture 44a is set in the same direction as the direction of the trajectory 46 of the electric center position e according to the plan picture 44a.
In the direction of, since the trajectory of the electrical center position e has been changed from the trajectory 46 to the trajectory 48 during the elapse of 3 seconds, the following judgment is made.

【0041】すなわち、平面移動方向が転換される前の
電気的中心位置eの軌跡46と平面移動方向が転換され
た後の電気的中心位置eの軌跡48とがなす平面角度4
9が30°よりも小さいので、ラジコンブルドーザ22
の方向は転換されず単にバック走行したものとみなし
て、矩形領域41上において、ブレード44bを反転表
示しないこととする。
That is, the plane angle 4 formed by the locus 46 of the electric center position e before the plane moving direction is changed and the locus 48 of the electric center position e after the plane moving direction is changed.
Since 9 is smaller than 30 °, the radio-controlled bulldozer 22
Is not changed, and it is assumed that the vehicle has just traveled in the reverse direction, and the blade 44b is not displayed in reverse on the rectangular area 41.

【0042】次に、図4及び図6に示す法面仕上げ管理
システムの全体構成図に基づいて、この実施の形態に係
るラジコンブルドーザ22の制御プロセスについて説明
する。
Next, a control process of the radio-controlled bulldozer 22 according to this embodiment will be described based on the entire configuration diagram of the slope finishing management system shown in FIGS.

【0043】先ず、第1テレビカメラ25a、第2テレ
ビカメラ26aによりそれぞれ撮影した画像データをリ
アルタイムで無線中継装置51に転送すると、略同時に
当該転送データは無線中継装置51からAモニター33
a、Bモニター33bへとそれぞれ転送されて表示され
る。
First, when image data respectively taken by the first television camera 25a and the second television camera 26a is transferred to the wireless relay device 51 in real time, the transferred data is transmitted from the wireless relay device 51 to the A monitor 33 almost simultaneously.
a and B are transferred to and displayed on the B monitor 33b, respectively.

【0044】この実施の形態では、画像データの転送方
法として、無線中継装置51を用いる方法を採用したた
め、山岳地帯等での通信障害に対して特に有効な役割を
果たすことになり、また、この無線中継装置を例えばラ
ジコンクローラダンプに搭載するようにすると、通信状
態に応じて任意選択的に有利な場所へと移動させること
により、常に良好な通信状態を得ることも可能である。
In this embodiment, since the method using the wireless relay device 51 is employed as a method of transferring image data, it plays a particularly effective role against a communication failure in a mountain area or the like. If the wireless relay device is mounted on, for example, a radio-controlled crawler dump, it is possible to always obtain a good communication condition by optionally moving the wireless relay device to an advantageous place according to the communication condition.

【0045】一方、GPS測位システム及び無線通信シ
ステム52によりラジコンブルドーザ22の位置データ
及び姿勢データがリアルタイムで検出されるとともに、
その検出結果がコンピュータ34に格納されるコンピュ
ータプログラム53のデータベース上に自動入力される
とともに、当該プログラム上でデータ処理がなされるこ
とにより、基盤面仕上げ範囲情報42、ブロック別高低
差情報43、及びラジコンブルドーザ22の位置及び方
向情報44が平面情報としてアルタイムでCモニター3
3cに表示されることになる。
On the other hand, the position data and the attitude data of the radio controlled dozer 22 are detected in real time by the GPS positioning system and the wireless communication system 52,
The detection result is automatically input to a database of a computer program 53 stored in the computer 34, and the data processing is performed on the program, whereby the base surface finish range information 42, the block-based height difference information 43, and The position and direction information 44 of the radio-controlled bulldozer 22 is used as plane information in real time in the C monitor 3.
3c.

【0046】このようにして、Aモニター〜Bモニター
の2領域には、他の建設機械との接触を防止したり、概
略の敷均し作業を行う等、主にラジコンブルドーザ22
の動きの概略を把握するための画像情報が表示されるこ
とになるとともに、Cモニターには、効率的かつ的確に
法面の仕上げ作業を行うための施工情報が表示されるこ
とになり、Aモニター〜Cモニターの3領域をばらばら
でなくユニット化して一個所に集中して表示することに
より、オペレータ38がモニター画面33に対向してラ
ジコン操作盤35の操作を行う際には、当該3領域に表
示される情報のすべてがオペレータ38の視界に容易に
入るようになっている。
As described above, the radio controlled bulldozer 22 is mainly provided in the two areas of the monitor A and the monitor B, for example, to prevent contact with other construction machines or to perform a general leveling operation.
The image information for grasping the outline of the movement of the slope is displayed, and the construction information for performing the slope finishing work efficiently and accurately is displayed on the C monitor. When the operator 38 operates the radio-controlled operation panel 35 in opposition to the monitor screen 33 by displaying the three areas of the monitor to the C monitor as a unit instead of being separated and displaying them in one place, the three areas are displayed. All of the information displayed in the field of view can easily enter the field of view of the operator 38.

【0047】このため、運転席に搭乗した場合に得られ
るはずの視界や平衡感覚等の情報が得られない状況には
あるが、オペレータ38の視覚からはそれ以上の情報内
容を効果的に得ることができるから、オペレータが搭乗
する場合と同等以上に容易かつ確実にラジコン操作盤3
5を操作してラジコンブルドーザ22をラジオコントロ
ールすることができ、その結果、基盤面仕上げ作業に対
してラジコンブルドーザ22が有する能力のすべてが発
揮されることになることに加え、1〜2cmというきわ
めて高い精度の視覚情報、すなわち、GPSアンテナ2
2aに係る電気的中心位置Eから把握される機械的中心
位置Mの高さの変動に追従して正方形ブロック41aの
表示色がリアルタイムで新しい高低差に対応した色に置
き換わるように表示することとしたので、従前のように
現地で別途測量をする必要がないばかりか、正方形ブロ
ック41a別に高さの凹凸として把握することができる
ため、凹凸で構成される複雑な基盤面における細かい高
さの調整作業を容易になし得ることになるとともに、矩
形領域41を全体からみた当該正方形ブロック41aの
高低差を相対的に把握することができるため、効率的か
つ的確な基盤面仕上げ作業を最後まで完結させることが
可能となる。
For this reason, there is a situation in which information such as a field of view and a sense of balance, which should be obtained when the driver gets into the driver's seat, cannot be obtained, but more information can be effectively obtained from the visual sense of the operator 38. Therefore, the radio control panel 3 is easier and more reliable than when the operator is on board.
5 to control the radio-controlled bulldozer 22 by radio, so that all of the capabilities of the radio-controlled bulldozer 22 can be exhibited for the finishing work on the base surface, in addition to the extremely small size of 1-2 cm. High accuracy visual information, ie GPS antenna 2
Displaying the display color of the square block 41a in real time so as to replace the color corresponding to the new height difference in accordance with the change in the height of the mechanical center position M grasped from the electrical center position E according to 2a. As a result, it is not necessary to separately perform on-site surveying as in the past, and since it is possible to grasp the height unevenness for each square block 41a, it is possible to finely adjust the height of a complicated base surface composed of unevenness. Since the work can be easily performed, and the height difference of the square block 41a as viewed from the whole of the rectangular area 41 can be relatively grasped, the efficient and accurate base surface finishing work is completed to the end. It becomes possible.

【0048】このようにして、ラジコンブルドーザ22
がオペレータ38によりラジオコントロールされると、
ラジコンブルドーザ22の作動に追従して変動していく
画像情報が第1テレビカメラ25a及び第2テレビカメ
ラ26aにより無線中継装置51を介してAモニター及
びBモニターに表示されるとともに、ラジコンブルドー
ザ22の作動をGPS測位システム及び無線通信システ
ムにより把握したラジコンブルドーザ22の位置データ
及び方向データに基づく施工情報もコンピュータ34を
介してCモニターにリアルタイムで表示されることにな
り、このプロセスが繰り返されることにより、基盤面仕
上げ作業は進捗していくことになる。
Thus, the radio controlled bulldozer 22
Is radio controlled by the operator 38,
Image information that fluctuates following the operation of the radio controlled bulldozer 22 is displayed on the A monitor and the B monitor via the wireless relay device 51 by the first television camera 25a and the second television camera 26a, and the The construction information based on the position data and the direction data of the radio controlled bulldozer 22 whose operation has been grasped by the GPS positioning system and the wireless communication system is also displayed in real time on the C monitor via the computer 34, and this process is repeated. The work of finishing the base surface will progress.

【0049】[0049]

【発明の効果】以上説明したように、この発明によれ
ば、無人区域にGPSアンテナを具備した遠隔操作式ブ
ルドーザを配備して、当該ブルドーザの画像情報、及び
少なくとも4個の衛星を利用して把握した施工情報が表
示されるモニター画面を見ながら、有人区域のオペレー
タが遠隔操作盤を操作して当該ブルドーザに基盤面の仕
上げをさせる構成とした上で、前記施工情報は、複数ブ
ロックからなるモニター画面上の矩形領域に基盤面仕上
げ範囲を当てはめて表示する基盤面仕上げ範囲情報と、
計画高さとの高低差を段階別に色分けして各段階に対応
する高低差を有するブロックを対応する色で表示するブ
ロック別高低差情報と、当該ブルドーザの位置及び前後
方向を表示するブルドーザ位置方向情報とを具備して、
前記電気的中心位置から把握される当該ブルドーザの機
械的中心位置の高さの変動に追従してブロックの表示色
がリアルタイムに新しい高低差に対応した色に置き換わ
るようにしたので、部分的に必要となる細かい高さの調
整作業を容易に行うことができるとともに、作業範囲全
体に亘り効率的かつ迅速な基盤面仕上げ作業を行うこと
ができる。
As described above, according to the present invention, a remotely operated bulldozer equipped with a GPS antenna is installed in an unmanned area, and image information of the bulldozer and at least four satellites are used. While looking at the monitor screen on which the grasped construction information is displayed, the operator of the manned area operates the remote control panel to finish the base surface of the bulldozer, and the construction information is composed of a plurality of blocks. Base surface finish range information displayed by applying the base surface finish range to the rectangular area on the monitor screen,
Height difference information for each block, in which the height difference from the planned height is color-coded for each stage and blocks having a height difference corresponding to each stage are displayed in a corresponding color, and bulldozer position / direction information for displaying the position and the front-back direction of the bulldozer With
Since the display color of the block is replaced in real time with a color corresponding to a new height difference in accordance with a change in the height of the mechanical center position of the bulldozer grasped from the electrical center position, it is partially necessary. It is possible to easily perform the fine height adjustment work, and to perform the efficient and quick base surface finishing work over the entire work range.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明に係る基盤面仕上げ管理システムの概
略を示す説明図である。
FIG. 1 is an explanatory view schematically showing a base surface finish management system according to the present invention.

【図2】この発明に係る基盤面仕上げ管理システムの一
実施の形態が適用された場合における施工状況を示す説
明図である。
FIG. 2 is an explanatory diagram showing a construction state when an embodiment of a base surface finish management system according to the present invention is applied.

【図3】この発明に係る基盤面仕上げ管理システムの一
実施の形態に使用されるラジコン操作ユニットの構成を
示す説明図である。
FIG. 3 is an explanatory diagram showing a configuration of a radio control operation unit used in an embodiment of the base surface finish management system according to the present invention.

【図4】この発明に係る基盤面仕上げ管理システムの一
実施の形態に使用されるモニター画面の表示構成を示す
説明図である。
FIG. 4 is an explanatory diagram showing a display configuration of a monitor screen used in an embodiment of the base surface finish management system according to the present invention.

【図5】この発明に係る基盤面仕上げ管理システムの一
実施の形態に使用されるラジコンブルドーザに係る平面
絵図の作動を示す説明図である。
FIG. 5 is an explanatory view showing an operation of a plan picture of a radio-controlled bulldozer used in an embodiment of the base surface finish management system according to the present invention.

【図6】この発明に係る基盤面仕上げ管理システムの一
実施の形態に使用されるラジコンブルドーザの制御プロ
セスを示す説明図である。
FIG. 6 is an explanatory diagram showing a control process of a radio-controlled bulldozer used in an embodiment of the base surface finish management system according to the present invention.

【符号の説明】[Explanation of symbols]

1…GPSアンテナ 2…遠隔操作式ブルドーザ 3…画面情報 4…施工情報 5…モニター画面 5a…ブロック 5b…矩形領域 6…オペレータ 7…基盤面仕上げ範囲情報 8…ブロック別高低差情報 9…ブルドーザ位置方向情報 21…基盤面仕上げ範囲 22…ラジコンブルドーザ 22a…GPSアンテナ 22b…無線アンテナ 23…ラジコンバックホウ 23a…GPSアンテナ 23b…無線アンテナ 24…ラジコンダンプトラック 24a…無線アンテナ 25…第1ラジコン高所作業車 25a…第1テレビカメラ 25b…無線アンテナ 26…第2ラジコン高所作業車 26a…第2テレビカメラ 26b…無線アンテナ 31…モニターデスク 32…モニターユニット 33…モニター画面 33a…Aモニター 33b…Bモニター 33c…Cモニター 34…コンピュータ 34a…キーボード 35…ラジコン操作盤 36…イス 37…ラジコン操作ユニット 38…オペレータ 41…矩形領域 41a…正方形ブロック 42…基盤面仕上げ範囲情報 43…ブロック別高低差情報 44…ブルドーザ位置方向情報 44a…平面絵図 45…軌跡 47…平面角度 51…無線中継装置 52…GPS測位システム及び無線通信システム 53…コンピュータプログラム E…電気的中心位置 M…機械的中心位置 e…電気的中心位置(平面絵図) DESCRIPTION OF SYMBOLS 1 ... GPS antenna 2 ... Remote operation bulldozer 3 ... Screen information 4 ... Construction information 5 ... Monitor screen 5a ... Block 5b ... Rectangular area 6 ... Operator 7 ... Base surface finishing range information 8 ... Height difference information by block 9 ... Bulldozer position Direction information 21: Base surface finishing area 22 ... Radio controlled bulldozer 22a ... GPS antenna 22b ... Radio antenna 23 ... Radio control backhoe 23a ... GPS antenna 23b ... Radio antenna 24 ... Radio control dump truck 24a ... Radio antenna 25 ... First radio control aerial work platform 25a: first television camera 25b: wireless antenna 26: second radio-controlled aerial vehicle 26a: second television camera 26b: wireless antenna 31: monitor desk 32: monitor unit 33: monitor screen 33a: A monitor 33b: B monitor 33c ... C monitor 34 ... computer 34a ... keyboard 35 ... radio control panel 36 ... chair 37 ... radio control operation unit 38 ... operator 41 ... rectangular area 41a ... square block 42 ... base surface finish range information 43 ... height difference information by block 44 ... bulldozer Position and direction information 44a ... Plan picture 45 ... Trace 47 ... Plane angle 51 ... Wireless relay device 52 ... GPS positioning system and wireless communication system 53 ... Computer program E ... Electrical center position M ... Mechanical center position e ... Electrical center position (Plan view)

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 国際公開95/16228(WO,A1) (58)調査した分野(Int.Cl.7,DB名) E02F 9/20 G01C 7/04 G01C 15/00 G01S 5/14 ──────────────────────────────────────────────────続 き Continued on the front page (56) References WO 95/16228 (WO, A1) (58) Fields investigated (Int.Cl. 7 , DB name) E02F 9/20 G01C 7/04 G01C 15/00 G01S 5/14

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 施工領域のうち、無人区域にGPSアン
テナを具備した遠隔操作式ブルドーザを配備して、テレ
ビカメラによる当該ブルドーザの画像情報、及び少なく
とも4個のGPS衛星を利用して把持した施工情報がリ
アルタイムで表示されるモニター画面を見ながら、無人
区域以外の有人区域のオペレータが遠隔操作盤を操作し
て無人区域の当該ブルドーザに基盤面の仕上げをさせる
基盤面仕上げ管理システムであって、 前記施工情報は、均等な複数のブロックからなるモニタ
ー画面上の矩形領域に基盤面仕上げ範囲を当てはめて表
示する基盤面仕上げ情報と、計画高さに対する現況高さ
の高低差を段階別に色分けして各段階に対応する高低差
を有するブロックが対応する色で表示されるブロック別
高低差情報と、設定時間の経過に伴うGPSアンテナの
電気的中心位置の平面移動の方向、及び当該移動後の電
気的中心位置を基礎として、当該ブルドーザの位置及び
前後方向を示す当該ブルドーザの平面図が矩形領域の対
応する部位にリアルタイムで表示されるブルドーザ位置
方向情報であって、設定時間の経過に伴うGPSアンテ
ナの電気的中心位置の平面移動量が予め設定した長さ寸
法に満たない場合には遠隔操作式ブルドーザが平面移動
していないものとみなして当該ブルドーザの平面図を静
止表示とするようにしたものとを具備して、前記電気的
中心位置から把握される当該ブルドーザの機械的中心位
置の高さの変動に追従してブロック内の表示色がリアル
タイムに新しい高低差に対応した色に置き換わるように
したことを特徴とする、 基盤面仕上げ管理システム。
1. A remotely operated bulldozer equipped with a GPS antenna is provided in an unmanned area in a construction area, and image information of the bulldozer is provided by a television camera, and the construction is grasped using at least four GPS satellites. A board surface finishing management system in which an operator of a manned area other than an unmanned area operates a remote control panel to finish the board surface on the bulldozer of the unmanned area while watching a monitor screen in which information is displayed in real time, The construction information, the base surface finish information to be displayed by applying the base surface finish range to the rectangular area on the monitor screen consisting of a plurality of blocks, and the height difference of the current height with respect to the plan height is color-coded by stage. A block having a height difference corresponding to each stage is displayed in a corresponding color, and the height difference information for each block is displayed as the set time elapses. Based on the direction of the planar movement of the electric center position of the GPS antenna and the electric center position after the movement, the plan view of the bulldozer indicating the position and the front-back direction of the bulldozer is provided in real time at a corresponding portion of the rectangular area. If the bulldozer position and direction information to be displayed is such that the planar movement amount of the electrical center position of the GPS antenna with the elapse of the set time is less than a preset length, the remote-controlled bulldozer is performing planar movement. That the bulldozer is considered to be a static display of the plan view of the bulldozer, to follow the fluctuation of the height of the mechanical center position of the bulldozer grasped from the electrical center position. A base surface finish management system, characterized in that the display colors in the blocks are replaced in real time with colors that correspond to the new height difference.
【請求項2】 施工領域のうち、無人区域にGPSアン
テナを具備した遠隔操作式ブルドーザを配備して、テレ
ビカメラによる当該ブルドーザの画像情報、及び少なく
とも4個のGPS衛星を利用して把持した施工情報がリ
アルタイムで表示されるモニター画面を見ながら、無人
区域以外の有人区域のオペレータが遠隔操作盤を操作し
て無人区域の当該ブルドーザに基盤面の仕上げをさせる
基盤面仕上げ管理システムであって、 前記施工情報は、均等な複数のブロックからなるモニタ
ー画面上の矩形領域に基盤面仕上げ範囲を当てはめて表
示する基盤面仕上げ情報と、計画高さに対する現況高さ
の高低差を段階別に色分けして各段階に対応する高低差
を有するブロックが対応する色で表示されるブロック別
高低差情報と、設定時間の経過に伴うGPSアンテナの
電気的中心位置の平面移動の方向、及び当該移動後の電
気的中心位置を基礎として、当該ブルドーザの位置及び
前後方向を示す当該ブルドーザの平面図が矩形領域の対
応する部位にリアルタイムで表示されるブルドーザ位置
方向情報であって、設定時間の経過に伴うGPSアンテ
ナの電気的中心位置の平面移動方向が転換された場合に
おいて、転換前の電気的中心位置の平面移動方向と転換
後の電気的中心位置の平面移動方向とがなす角度が予め
設定した角度より大きい場合に限って、遠隔操作式ブル
ドーザが方向転換したものとみなして当該ブルドーザの
平面図の前後方向を転換させて表示するようにしたもの
とを具備して、前記電気的中心位置から把握される当該
ブルドーザの機械的中心位置の高さの変動に追従してブ
ロック内の表示色がリアルタイムに新しい高低差に対応
した色に置き換わるようにしたことを特徴とする、 基盤面仕上げ管理システム。
2. A construction in which a remotely operated bulldozer equipped with a GPS antenna is provided in an unmanned area in a construction area, and image information of the bulldozer by a television camera and at least four GPS satellites are used for grasping. A board surface finishing management system in which an operator of a manned area other than an unmanned area operates a remote control panel to finish the board surface on the bulldozer of the unmanned area while watching a monitor screen in which information is displayed in real time, The construction information, the base surface finish information to be displayed by applying the base surface finish range to the rectangular area on the monitor screen consisting of a plurality of blocks, and the height difference of the current height with respect to the plan height is color-coded by stage. A block having a height difference corresponding to each stage is displayed in a corresponding color, and the height difference information for each block is displayed as the set time elapses. Based on the direction of the planar movement of the electric center position of the GPS antenna and the electric center position after the movement, the plan view of the bulldozer indicating the position and the front-back direction of the bulldozer is provided in real time at a corresponding portion of the rectangular area. The displayed bulldozer position / direction information, wherein when the plane movement direction of the electrical center position of the GPS antenna is changed with the elapse of the set time, the plane movement direction of the electric center position before the change and the plane movement direction after the change Only when the angle between the plane moving direction of the electrical center position and the plane moving direction is larger than a preset angle, the remote control type bulldozer is regarded as having changed direction and the front and rear directions of the plan view of the bulldozer are changed and displayed. The bulldozer is configured to follow the fluctuation of the height of the mechanical center position of the bulldozer grasped from the electric center position. A base surface finish management system, characterized in that the display color in the lock is replaced in real time with a color corresponding to the new height difference.
【請求項3】 前記ブルドーザ位置方向情報は、設定時
間の経過に伴うGPSアンテナの電気的中心位置の平面
移動方向が転換された場合において、転換前の電気的中
心位置の平面移動方向と転換後の電気的中心位置の平面
移動方向とがなす角度が予め設定した角度より大きい場
合に限って、遠隔操作式ブルドーザが方向転換したもの
とみなして当該ブルドーザの平面図の前後方向を転換さ
せて表示するようにしたことを特徴とする、 請求項1に記載の基盤面仕上げ管理システム。
3. The bulldozer position / direction information may include: when the planar movement direction of the electrical center position of the GPS antenna is changed with the elapse of a set time, the planar movement direction of the electric center position before the change is equal to the plane movement direction after the change. Only when the angle between the electric center position and the plane moving direction is larger than a preset angle, the remote control type bulldozer is regarded as having changed direction and the front view of the bulldozer is turned forward and backward and displayed. The base surface finish management system according to claim 1, wherein the base surface finish management system is used.
JP24340996A 1996-09-13 1996-09-13 Base surface finishing management system Expired - Fee Related JP3218456B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24340996A JP3218456B2 (en) 1996-09-13 1996-09-13 Base surface finishing management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24340996A JP3218456B2 (en) 1996-09-13 1996-09-13 Base surface finishing management system

Publications (2)

Publication Number Publication Date
JPH1091059A JPH1091059A (en) 1998-04-10
JP3218456B2 true JP3218456B2 (en) 2001-10-15

Family

ID=17103441

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24340996A Expired - Fee Related JP3218456B2 (en) 1996-09-13 1996-09-13 Base surface finishing management system

Country Status (1)

Country Link
JP (1) JP3218456B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4041410B2 (en) * 2003-02-07 2008-01-30 日立建機株式会社 Mine disposal management method and system
JP6514973B2 (en) * 2015-06-30 2019-05-15 株式会社トプコン Field management system, flight detection method and program
JP6096980B2 (en) * 2015-12-18 2017-03-15 株式会社小松製作所 Construction information display device and construction information display method
JP6982765B2 (en) * 2016-03-25 2021-12-17 パナソニックIpマネジメント株式会社 Operation terminal, remote control cleaning system and remote control method
JP6910245B2 (en) * 2017-08-29 2021-07-28 株式会社小松製作所 Work vehicle control systems, methods, and work vehicles
JP7009236B2 (en) * 2018-01-30 2022-01-25 株式会社小松製作所 Work vehicle control systems, methods, and work vehicles
JP7233496B2 (en) * 2020-04-06 2023-03-06 住友重機械工業株式会社 Excavator operating device, excavator operating method, and excavator operating program

Also Published As

Publication number Publication date
JPH1091059A (en) 1998-04-10

Similar Documents

Publication Publication Date Title
JP6987186B2 (en) Display system, construction machinery, and display method
US11841703B2 (en) System and method for autonomous operation of a machine
US7532967B2 (en) Excavation teaching apparatus for construction machine
JP3585237B2 (en) Method and apparatus for operating a compression molding machine used at a worksite
US20170175364A1 (en) Construction information display device and method for displaying construction information
CN108028911B (en) Display device and display system for work machine
JP2005011058A (en) Work support and management system for work machine
JP4012448B2 (en) Construction machine excavation work teaching device
JP3218456B2 (en) Base surface finishing management system
JP2019132062A (en) Construction machine
JP3987777B2 (en) Construction machine excavation work teaching device
JP7215742B2 (en) Construction Machinery Management System, Construction Machinery Management Program, Construction Machinery Management Method, Construction Machinery and External Management Device for Construction Machinery
WO2018026019A1 (en) Construction management system
CN113195838B (en) Construction machine management system, construction machine management program, construction machine management method, construction machine, and external management device for construction machine
JP3198403B2 (en) Slope finishing management system
JP2879664B2 (en) Compaction management system
JP2929369B2 (en) Leveling range management method and leveling range management device
US20220316188A1 (en) Display system, remote operation system, and display method
JP6684004B1 (en) Construction machine management system, construction machine management program, construction machine management method, construction machine and construction machine external management device
JP7138018B2 (en) Scaffold design device and scaffold design method
JP3118173B2 (en) Geodetic system
JP2008050748A (en) Unmanned construction method by construction supporting system
JPH1088624A (en) Gps unmanned execution control system
WO2024106423A1 (en) Work management method for construction machine
EP4187026A1 (en) Automated work system

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090810

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100810

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110810

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110810

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120810

Year of fee payment: 11

LAPS Cancellation because of no payment of annual fees