JP2021155930A - Shovel control system - Google Patents

Shovel control system Download PDF

Info

Publication number
JP2021155930A
JP2021155930A JP2020054706A JP2020054706A JP2021155930A JP 2021155930 A JP2021155930 A JP 2021155930A JP 2020054706 A JP2020054706 A JP 2020054706A JP 2020054706 A JP2020054706 A JP 2020054706A JP 2021155930 A JP2021155930 A JP 2021155930A
Authority
JP
Japan
Prior art keywords
excavator
remaining life
boom
calculated
attachment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2020054706A
Other languages
Japanese (ja)
Other versions
JP7460414B2 (en
Inventor
正樹 小川
Masaki Ogawa
正樹 小川
文乃 階戸
Ayano Kaito
文乃 階戸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Heavy Industries Ltd
Original Assignee
Sumitomo Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Heavy Industries Ltd filed Critical Sumitomo Heavy Industries Ltd
Priority to JP2020054706A priority Critical patent/JP7460414B2/en
Priority to CN202110319920.XA priority patent/CN113445566B/en
Publication of JP2021155930A publication Critical patent/JP2021155930A/en
Priority to JP2024008026A priority patent/JP2024028566A/en
Application granted granted Critical
Publication of JP7460414B2 publication Critical patent/JP7460414B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/26Indicating devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Component Parts Of Construction Machinery (AREA)
  • Operation Control Of Excavators (AREA)

Abstract

To provide a shovel control system allowing setting of a guarantee content corresponding to a using state.SOLUTION: A shovel control system related to an embodiment of the present invention has a state detection device detecting the operation state of a shovel to be evaluated, a control device that calculates a fatigue degree of the shovel on the basis of the detected operation state, and calculates guarantee content information related to the calculated fatigue degree, and a display device displaying the calculated guarantee content information.SELECTED DRAWING: Figure 4

Description

本開示は、ショベルの管理システムに関する。 This disclosure relates to a shovel management system.

従来、ショベルの作動状態を複数のセンサで検出し、解析モデルを用いて解析することにより、ショベルの部品に加わる応力を算出する技術が知られている(例えば、特許文献1参照)。 Conventionally, there is known a technique of calculating the stress applied to a component of an excavator by detecting the operating state of the excavator with a plurality of sensors and analyzing it using an analysis model (see, for example, Patent Document 1).

特開2014−85293号公報Japanese Unexamined Patent Publication No. 2014-85293

ところで、従来のショベルの保証期間は、予め定められた期間で一義的に決められている。しかしながら、上記のようなショベルでは、ブレーカ作業のように構造部材への負荷が大きい作業や、仕上げ作業、積み込み作業、均し作業のように構造部材への負荷が小さい作業等、種々の作業が存在する。 By the way, the warranty period of the conventional excavator is uniquely determined by a predetermined period. However, with the above-mentioned excavator, various operations such as work with a large load on the structural member such as breaker work, work with a small load on the structural member such as finishing work, loading work, and leveling work can be performed. exist.

そこで、上記事情に鑑み、使用状況に応じた保証内容を設定できるショベルの管理システムを提供することを目的とする。 Therefore, in view of the above circumstances, it is an object of the present invention to provide a shovel management system that can set the guarantee contents according to the usage situation.

本発明の実施形態に係るショベルの管理システムは、評価対象のショベルの作動状態を検出する状態検出装置と、前記検出された前記作動状態に基づき前記ショベルの疲労度を算出し、前記算出された前記疲労度と関連付けられた保証内容情報を算出する制御装置と、前記算出された前記保証内容情報を表示する表示装置と、を備える。 The shovel management system according to the embodiment of the present invention calculates the fatigue degree of the shovel based on the state detection device that detects the operating state of the shovel to be evaluated and the detected operating state, and is calculated. A control device for calculating the guarantee content information associated with the fatigue level and a display device for displaying the calculated guarantee content information are provided.

上述のショベルの管理システムによれば、使用状況に応じた保証内容を設定できる。 According to the excavator management system described above, the guarantee contents can be set according to the usage situation.

一実施形態のショベルの管理システムを示す図The figure which shows the excavator management system of one Embodiment 一実施形態のショベルの管理システムのブロック図Block diagram of the excavator management system of one embodiment 疲労度算出処理の一例を示すフローチャートFlowchart showing an example of fatigue calculation processing 一実施形態の表示画面の一例を示す図The figure which shows an example of the display screen of one Embodiment 一実施形態の表示画面の別の例を示す図The figure which shows another example of the display screen of one Embodiment 一実施形態の表示画面の更に別の例を示す図The figure which shows still another example of the display screen of one Embodiment

以下、図面を参照して発明を実施するための形態について説明する。各図面において、同一構成部分には同一符号を付し、重複した説明を省略する場合がある。 Hereinafter, modes for carrying out the invention will be described with reference to the drawings. In each drawing, the same components may be designated by the same reference numerals and duplicate description may be omitted.

図1を参照し、一実施形態のショベルの管理システム(以下、単に「管理システム」ともいう。)について説明する。図1は、一実施形態のショベルの管理システムを示す図である。 With reference to FIG. 1, the excavator management system of one embodiment (hereinafter, also simply referred to as “management system”) will be described. FIG. 1 is a diagram showing a shovel management system of one embodiment.

管理システム300は、管理対象のショベル100及び管理装置200を含む。ショベル100及び管理装置200は、通信ネットワークNWを介して相互に通信を行う。 The management system 300 includes a shovel 100 to be managed and a management device 200. The excavator 100 and the management device 200 communicate with each other via the communication network NW.

ショベル100の下部走行体1には、旋回機構2を介して上部旋回体3が旋回可能に搭載されている。上部旋回体3には、ブーム4が取り付けられている。ブーム4の先端にはアーム5が取り付けられ、アーム5の先端にはエンドアタッチメントとしてのバケット6が取り付けられている。 An upper swivel body 3 is mounted on the lower traveling body 1 of the excavator 100 so as to be swivelable via a swivel mechanism 2. A boom 4 is attached to the upper swing body 3. An arm 5 is attached to the tip of the boom 4, and a bucket 6 as an end attachment is attached to the tip of the arm 5.

ブーム4、アーム5及びバケット6は、アタッチメントの一例としての掘削アタッチメントを構成する。ブーム4はブームシリンダ7により駆動され、アーム5はアームシリンダ8により駆動され、バケット6はバケットシリンダ9により駆動される。ブーム4にはブーム角度センサS1が取り付けられ、アーム5にはアーム角度センサS2が取り付けられ、バケット6にはバケット角度センサS3が取り付けられている。ブーム角度センサS1、アーム角度センサS2及びバケット角度センサS3は、集合的に「姿勢センサ」とも称される。アタッチメントの姿勢を特定する際に利用されるためである。 The boom 4, arm 5, and bucket 6 constitute an excavation attachment as an example of the attachment. The boom 4 is driven by the boom cylinder 7, the arm 5 is driven by the arm cylinder 8, and the bucket 6 is driven by the bucket cylinder 9. A boom angle sensor S1 is attached to the boom 4, an arm angle sensor S2 is attached to the arm 5, and a bucket angle sensor S3 is attached to the bucket 6. The boom angle sensor S1, the arm angle sensor S2, and the bucket angle sensor S3 are collectively also referred to as a "posture sensor". This is because it is used to specify the posture of the attachment.

ブーム角度センサS1は、ブーム4の回動角度を検出する。本実施形態では、ブーム角度センサS1は加速度センサであり、上部旋回体3に対するブーム4の回動角度(以下、「ブーム角度」とする。)を検出する。ブーム角度は、例えば、ブーム4を最も下げたときに最小角度となり、ブーム4を上げるにつれて大きくなる。 The boom angle sensor S1 detects the rotation angle of the boom 4. In the present embodiment, the boom angle sensor S1 is an acceleration sensor, and detects the rotation angle of the boom 4 with respect to the upper swing body 3 (hereinafter, referred to as “boom angle”). The boom angle becomes the minimum angle when the boom 4 is lowered to the maximum, and increases as the boom 4 is raised.

アーム角度センサS2は、アーム5の回動角度を検出する。本実施形態では、アーム角度センサS2は加速度センサであり、ブーム4に対するアーム5の回動角度(以下、「アーム角度」とする。)を検出する。アーム角度は、例えば、アーム5を最も閉じたときに最小角度となり、アーム5を開くにつれて大きくなる。 The arm angle sensor S2 detects the rotation angle of the arm 5. In the present embodiment, the arm angle sensor S2 is an acceleration sensor and detects the rotation angle of the arm 5 with respect to the boom 4 (hereinafter, referred to as “arm angle”). The arm angle becomes the minimum angle when the arm 5 is closed most, and increases as the arm 5 is opened.

バケット角度センサS3は、バケット6の回動角度を検出する。本実施形態では、バケット角度センサS3は加速度センサであり、アーム5に対するバケット6の回動角度(以下、「バケット角度」とする。)を検出する。バケット角度は、例えば、バケット6を最も閉じたときに最小角度となり、バケット6を開くにつれて大きくなる。 The bucket angle sensor S3 detects the rotation angle of the bucket 6. In the present embodiment, the bucket angle sensor S3 is an acceleration sensor, and detects the rotation angle of the bucket 6 with respect to the arm 5 (hereinafter, referred to as “bucket angle”). The bucket angle becomes the minimum angle when the bucket 6 is closed most, and increases as the bucket 6 is opened.

ブーム角度センサS1、アーム角度センサS2及びバケット角度センサS3は、それぞれ可変抵抗器を利用したポテンショメータ、対応する油圧シリンダのストローク量を検出するストロークセンサ、連結ピン回りの回動角度を検出するロータリエンコーダ、ジャイロセンサ、加速度センサとジャイロセンサの組み合わせで構成される慣性計測装置等であってもよい。 The boom angle sensor S1, the arm angle sensor S2, and the bucket angle sensor S3 are a potentiometer using a variable resistor, a stroke sensor that detects the stroke amount of the corresponding hydraulic cylinder, and a rotary encoder that detects the rotation angle around the connecting pin. , A gyro sensor, an inertial measuring device composed of a combination of an acceleration sensor and a gyro sensor, or the like.

ブームシリンダ7には、ブームロッド圧センサS7R及びブームボトム圧センサS7Bが取り付けられている。アームシリンダ8には、アームロッド圧センサS8R及びアームボトム圧センサS8Bが取り付けられている。バケットシリンダ9には、バケットロッド圧センサS9R及びバケットボトム圧センサS9Bが取り付けられている。ブームロッド圧センサS7R、ブームボトム圧センサS7B、アームロッド圧センサS8R、アームボトム圧センサS8B、バケットロッド圧センサS9R及びバケットボトム圧センサS9Bは、集合的に「シリンダ圧センサ」とも称される。 A boom rod pressure sensor S7R and a boom bottom pressure sensor S7B are attached to the boom cylinder 7. An arm rod pressure sensor S8R and an arm bottom pressure sensor S8B are attached to the arm cylinder 8. A bucket rod pressure sensor S9R and a bucket bottom pressure sensor S9B are attached to the bucket cylinder 9. The boom rod pressure sensor S7R, boom bottom pressure sensor S7B, arm rod pressure sensor S8R, arm bottom pressure sensor S8B, bucket rod pressure sensor S9R and bucket bottom pressure sensor S9B are also collectively referred to as "cylinder pressure sensor".

ブームロッド圧センサS7Rはブームシリンダ7のロッド側油室の圧力(以下、「ブームロッド圧」とする。)を検出し、ブームボトム圧センサS7Bはブームシリンダ7のボトム側油室の圧力(以下、「ブームボトム圧」とする。)を検出する。アームロッド圧センサS8Rはアームシリンダ8のロッド側油室の圧力(以下、「アームロッド圧」とする。)を検出し、アームボトム圧センサS8Bはアームシリンダ8のボトム側油室の圧力(以下、「アームボトム圧」とする。)を検出する。バケットロッド圧センサS9Rはバケットシリンダ9のロッド側油室の圧力(以下、「バケットロッド圧」とする。)を検出し、バケットボトム圧センサS9Bはバケットシリンダ9のボトム側油室の圧力(以下、「バケットボトム圧」とする。)を検出する。 The boom rod pressure sensor S7R detects the pressure in the rod side oil chamber of the boom cylinder 7 (hereinafter referred to as “boom rod pressure”), and the boom bottom pressure sensor S7B detects the pressure in the bottom side oil chamber of the boom cylinder 7 (hereinafter referred to as “boom rod pressure”). , "Boom bottom pressure") is detected. The arm rod pressure sensor S8R detects the pressure in the rod side oil chamber of the arm cylinder 8 (hereinafter referred to as “arm rod pressure”), and the arm bottom pressure sensor S8B detects the pressure in the bottom side oil chamber of the arm cylinder 8 (hereinafter referred to as “arm rod pressure”). , "Arm bottom pressure") is detected. The bucket rod pressure sensor S9R detects the pressure in the rod side oil chamber of the bucket cylinder 9 (hereinafter referred to as "bucket rod pressure"), and the bucket bottom pressure sensor S9B detects the pressure in the bottom side oil chamber of the bucket cylinder 9 (hereinafter referred to as "bucket rod pressure"). , "Bucket bottom pressure") is detected.

振動センサS10は、旋回減速機20の振動を検出する。本実施形態では、振動センサS10は、加速度センサで構成されている。圧電素子を利用したアコースティックエミッション(AE)センサであってもよい。振動センサS10は、旋回減速機20を定期的に診断できるように、旋回減速機20にワンタッチで着脱できるように構成されている。但し、振動センサS10は、ショベル100の稼働中にも旋回減速機20の振動を検出できるように旋回減速機20に固定されていてもよい。 The vibration sensor S10 detects the vibration of the swivel reducer 20. In this embodiment, the vibration sensor S10 is composed of an acceleration sensor. It may be an acoustic emission (AE) sensor using a piezoelectric element. The vibration sensor S10 is configured to be attached to and detached from the turning speed reducer 20 with one touch so that the turning speed reducer 20 can be diagnosed periodically. However, the vibration sensor S10 may be fixed to the swivel reducer 20 so that the vibration of the swivel reducer 20 can be detected even while the excavator 100 is in operation.

上部旋回体3には、運転室であるキャビン10が設けられ且つエンジン11等の動力源が搭載されている。また、上部旋回体3には、コントローラ30、表示装置40、入力装置42、音出力装置43、記憶装置47、測位装置P1、機体傾斜センサS4、旋回角速度センサS5、撮像装置S6及び通信装置T1が取り付けられている。 The upper swing body 3 is provided with a cabin 10 which is an driver's cab and is equipped with a power source such as an engine 11. Further, the upper swivel body 3 includes a controller 30, a display device 40, an input device 42, a sound output device 43, a storage device 47, a positioning device P1, a machine body tilt sensor S4, a swivel angle speed sensor S5, an image pickup device S6, and a communication device T1. Is installed.

コントローラ30は、ショベル100の駆動制御を行う主制御部として機能する。本実施形態では、コントローラ30は、CPU、RAM、ROM等を含むコンピュータで構成されている。コントローラ30における1又は複数の機能は、例えば、ROMに格納されたプログラムをCPUが実行することで実現される。 The controller 30 functions as a main control unit that controls the drive of the excavator 100. In this embodiment, the controller 30 is composed of a computer including a CPU, RAM, ROM, and the like. One or more functions in the controller 30 are realized, for example, by the CPU executing a program stored in the ROM.

表示装置40は、情報を表示する。表示装置40は、CAN等の通信ネットワークを介してコントローラ30に接続されていてもよく、専用線を介してコントローラ30に接続されていてもよい。 The display device 40 displays information. The display device 40 may be connected to the controller 30 via a communication network such as CAN, or may be connected to the controller 30 via a dedicated line.

入力装置42は、操作者が情報をコントローラ30に入力できるようにする。入力装置42は、キャビン10内に設置されたタッチパネル、ノブスイッチ、メンブレンスイッチ等を含む。 The input device 42 allows the operator to input information to the controller 30. The input device 42 includes a touch panel, a knob switch, a membrane switch, and the like installed in the cabin 10.

音出力装置43は、各種の音情報を出力する装置である。音出力装置43は、例えば、コントローラ30に接続される車載スピーカであってもよく、ブザー等の警報器であってもよい。本実施形態では、音出力装置43は、コントローラ30からの音出力指令に応じて各種音情報を出力する。 The sound output device 43 is a device that outputs various sound information. The sound output device 43 may be, for example, an in-vehicle speaker connected to the controller 30, or an alarm device such as a buzzer. In the present embodiment, the sound output device 43 outputs various sound information in response to a sound output command from the controller 30.

記憶装置47は、情報を記憶するための装置である。記憶装置47は、例えば、半導体メモリ等の不揮発性記憶媒体である。記憶装置47は、ショベル100の動作中に1又は複数の機器が出力する情報を記憶してもよく、ショベル100の動作が開始される前に1又は複数の機器を介して取得する或いは入力される情報を記憶してもよい。記憶装置47は、例えば、通信装置T1等を介して取得される目標施工面に関するデータを記憶していてもよい。目標施工面は、ショベル100の操作者が設定したものであってもよく、施工管理者等が設定したものであってもよい。 The storage device 47 is a device for storing information. The storage device 47 is, for example, a non-volatile storage medium such as a semiconductor memory. The storage device 47 may store information output by one or more devices during the operation of the excavator 100, and is acquired or input through the one or more devices before the operation of the excavator 100 is started. Information may be stored. The storage device 47 may store data regarding the target construction surface acquired via, for example, the communication device T1 or the like. The target construction surface may be set by the operator of the excavator 100, or may be set by the construction manager or the like.

測位装置P1は、上部旋回体3の位置及び向きを測定する。測位装置P1は、例えばGNSSコンパスであり、上部旋回体3の位置及び向きを検出し、検出値をコントローラ30に対して出力する。そのため、測位装置P1は、上部旋回体3の向きを検出する向き検出装置として機能し得る。向き検出装置は、上部旋回体3に取り付けられた方位センサであってもよい。 The positioning device P1 measures the position and orientation of the upper swing body 3. The positioning device P1 is, for example, a GNSS compass, detects the position and orientation of the upper swing body 3, and outputs the detected value to the controller 30. Therefore, the positioning device P1 can function as a direction detecting device for detecting the direction of the upper swing body 3. The orientation detection device may be an orientation sensor attached to the upper swing body 3.

機体傾斜センサS4は、水平面に対する上部旋回体3の傾斜を検出する。本実施形態では、機体傾斜センサS4は上部旋回体3の前後軸回りの前後傾斜角及び左右軸回りの左右傾斜角を検出する加速度センサである。上部旋回体3の前後軸及び左右軸は、例えば、ショベル100の旋回軸上の一点であるショベル中心点で互いに直交する。機体傾斜センサS4は、加速度センサとジャイロセンサの組み合わせで構成される慣性計測装置であってもよい。 The body tilt sensor S4 detects the tilt of the upper swing body 3 with respect to the horizontal plane. In the present embodiment, the body tilt sensor S4 is an acceleration sensor that detects the front-rear tilt angle around the front-rear axis and the left-right tilt angle around the left-right axis of the upper swing body 3. The front-rear axis and the left-right axis of the upper swivel body 3 are orthogonal to each other at, for example, the excavator center point, which is one point on the swivel axis of the shovel 100. The airframe tilt sensor S4 may be an inertial measurement unit composed of a combination of an acceleration sensor and a gyro sensor.

旋回角速度センサS5は、上部旋回体3の旋回角速度及び旋回角度を検出する。本実施形態では、ジャイロセンサである。レゾルバ、ロータリエンコーダ等であってもよい。 The turning angular velocity sensor S5 detects the turning angular velocity and the turning angle of the upper swing body 3. In this embodiment, it is a gyro sensor. It may be a resolver, a rotary encoder, or the like.

撮像装置S6は、ショベル100の周辺の画像を取得する。本実施形態では、撮像装置S6は、ショベル100の前方の空間を撮像する前カメラS6F、ショベル100の左方の空間を撮像する左カメラS6L、ショベル100の右方の空間を撮像する右カメラS6R、及びショベル100の後方の空間を撮像する後カメラS6Bを含む。 The image pickup apparatus S6 acquires an image around the excavator 100. In the present embodiment, the image pickup apparatus S6 includes a front camera S6F that images the space in front of the excavator 100, a left camera S6L that images the space on the left side of the excavator 100, and a right camera S6R that images the space on the right side of the excavator 100. , And a post-camera S6B that images the space behind the excavator 100.

撮像装置S6は、例えば、CCD、CMOS等の撮像素子を有する単眼カメラであり、撮像した画像を表示装置40に出力する。撮像装置S6は、ステレオカメラ、距離画像カメラ等であってもよい。 The image pickup device S6 is, for example, a monocular camera having an image pickup element such as a CCD or CMOS, and outputs the captured image to the display device 40. The image pickup device S6 may be a stereo camera, a distance image camera, or the like.

前カメラS6Fは、例えば、キャビン10の天井、すなわちキャビン10の内部に取り付けられている。但し、キャビン10の屋根、ブーム4の側面等、キャビン10の外部に取り付けられていてもよい。左カメラS6Lは上部旋回体3の上面左端に取り付けられ、右カメラS6Rは上部旋回体3の上面右端に取り付けられ、後カメラS6Bは上部旋回体3の上面後端に取り付けられている。 The front camera S6F is mounted, for example, on the ceiling of the cabin 10, that is, inside the cabin 10. However, it may be attached to the outside of the cabin 10, such as the roof of the cabin 10 and the side surface of the boom 4. The left camera S6L is attached to the upper left end of the upper swivel body 3, the right camera S6R is attached to the upper right end of the upper swivel body 3, and the rear camera S6B is attached to the upper surface rear end of the upper swivel body 3.

通信装置T1は、ショベル100の外部にある外部機器との通信を制御する。本実施形態では、通信装置T1は、衛星通信網、携帯電話通信網、インターネット網等を介した外部機器との通信を制御する。 The communication device T1 controls communication with an external device outside the excavator 100. In the present embodiment, the communication device T1 controls communication with an external device via a satellite communication network, a mobile phone communication network, an Internet network, or the like.

図2は、一実施形態のショベルの管理システム300のブロック図である。なお、機械的動力伝達ライン、作動油ライン、パイロットライン、電気制御ライン及び通信ラインをそれぞれ二重線、実線、破線、点線及び一点鎖線で示している。 FIG. 2 is a block diagram of the excavator management system 300 of one embodiment. The mechanical power transmission line, hydraulic oil line, pilot line, electric control line and communication line are indicated by double-dashed line, solid line, broken line, dotted line and alternate-dashed line, respectively.

ショベル100の基本システムは、主に、エンジン11、レギュレータ13、メインポンプ14、パイロットポンプ15、コントロールバルブ17、操作装置26、吐出圧センサ28、操作圧センサ29、コントローラ30等を含む。 The basic system of the excavator 100 mainly includes an engine 11, a regulator 13, a main pump 14, a pilot pump 15, a control valve 17, an operating device 26, a discharge pressure sensor 28, an operating pressure sensor 29, a controller 30, and the like.

エンジン11は、ショベルの駆動源である。本実施形態では、エンジン11は、例えば、所定の回転数を維持するように動作するディーゼルエンジンである。また、エンジン11の出力軸は、メインポンプ14及びパイロットポンプ15の入力軸に連結されている。 The engine 11 is a drive source for the excavator. In the present embodiment, the engine 11 is, for example, a diesel engine that operates so as to maintain a predetermined rotation speed. Further, the output shaft of the engine 11 is connected to the input shafts of the main pump 14 and the pilot pump 15.

メインポンプ14は、作動油ラインを介して作動油をコントロールバルブ17に供給する。本実施形態では、メインポンプ14は、斜板式可変容量型油圧ポンプである。 The main pump 14 supplies hydraulic oil to the control valve 17 via the hydraulic oil line. In the present embodiment, the main pump 14 is a swash plate type variable displacement hydraulic pump.

レギュレータ13は、メインポンプ14の吐出量を制御する。本実施形態では、レギュレータ13は、コントローラ30からの制御指令に応じてメインポンプ14の斜板傾転角を調節することによってメインポンプ14の吐出量を制御する。例えば、コントローラ30は、操作圧センサ29等の出力を受信し、必要に応じてレギュレータ13に対して制御指令を出力し、メインポンプ14の吐出量を変化させる。 The regulator 13 controls the discharge amount of the main pump 14. In the present embodiment, the regulator 13 controls the discharge amount of the main pump 14 by adjusting the swash plate tilt angle of the main pump 14 in response to a control command from the controller 30. For example, the controller 30 receives the output of the operating pressure sensor 29 or the like, outputs a control command to the regulator 13 as needed, and changes the discharge amount of the main pump 14.

パイロットポンプ15は、パイロットラインを介して操作装置26を含む1又は複数の油圧機器に作動油を供給する。本実施形態では、パイロットポンプ15は、固定容量型油圧ポンプである。 The pilot pump 15 supplies hydraulic oil to one or more hydraulic devices including the operating device 26 via a pilot line. In the present embodiment, the pilot pump 15 is a fixed displacement hydraulic pump.

コントロールバルブ17は、ショベルにおける油圧システムを制御する油圧制御装置である。本実施形態では、コントロールバルブ17は、複数の制御弁を含むバルブブロックとして構成されている。コントロールバルブ17は、1又は複数の制御弁を通じ、メインポンプ14が吐出する作動油を、1又は複数の油圧アクチュエータに選択的に供給する。制御弁は、メインポンプ14から油圧アクチュエータに流れる作動油の流量及び油圧アクチュエータから作動油タンクに流れる作動油の流量を制御する。油圧アクチュエータは、ブームシリンダ7、アームシリンダ8、バケットシリンダ9、左側走行用油圧モータ1L、右側走行用油圧モータ1R及び旋回用油圧モータ2Aを含む。旋回用油圧モータ2Aは、電動アクチュエータとしての旋回用電動発電機で置き換えられてもよい。 The control valve 17 is a flood control device that controls a flood control system in an excavator. In the present embodiment, the control valve 17 is configured as a valve block including a plurality of control valves. The control valve 17 selectively supplies the hydraulic oil discharged from the main pump 14 to the one or a plurality of hydraulic actuators through one or a plurality of control valves. The control valve controls the flow rate of the hydraulic oil flowing from the main pump 14 to the hydraulic actuator and the flow rate of the hydraulic oil flowing from the hydraulic actuator to the hydraulic oil tank. The hydraulic actuator includes a boom cylinder 7, an arm cylinder 8, a bucket cylinder 9, a left-side traveling hydraulic motor 1L, a right-side traveling hydraulic motor 1R, and a turning hydraulic motor 2A. The swivel hydraulic motor 2A may be replaced with a swivel motor generator as an electric actuator.

操作装置26は、操作者がアクチュエータの操作のために用いる装置である。アクチュエータは、油圧アクチュエータ及び電動アクチュエータの少なくとも一方を含む。本実施形態では、操作装置26は、パイロットラインを介して、パイロットポンプ15が吐出する作動油を、コントロールバルブ17内の対応する制御弁のパイロットポートに供給する。パイロットポートのそれぞれに供給される作動油の圧力(パイロット圧)は、油圧アクチュエータのそれぞれに対応する操作装置26の操作方向及び操作量に応じた圧力である。操作装置26は、パイロットラインを介し、パイロットポンプ15が吐出する作動油を、コントロールバルブ17内の対応する制御弁のパイロットポートに供給できるように構成されている。操作装置26は、例えば図示しない左操作レバー、右操作レバー、左走行レバー及び右走行レバーを含む。 The operating device 26 is a device used by the operator to operate the actuator. Actuators include at least one of a hydraulic actuator and an electric actuator. In this embodiment, the operating device 26 supplies the hydraulic oil discharged by the pilot pump 15 to the pilot port of the corresponding control valve in the control valve 17 via the pilot line. The pressure of the hydraulic oil (pilot pressure) supplied to each of the pilot ports is a pressure corresponding to the operation direction and the operation amount of the operation device 26 corresponding to each of the hydraulic actuators. The operating device 26 is configured to supply the hydraulic oil discharged by the pilot pump 15 to the pilot port of the corresponding control valve in the control valve 17 via the pilot line. The operating device 26 includes, for example, a left operating lever, a right operating lever, a left traveling lever, and a right traveling lever (not shown).

吐出圧センサ28は、メインポンプ14の吐出圧を検出する。本実施形態では、吐出圧センサ28は、検出した値をコントローラ30に対して出力する。 The discharge pressure sensor 28 detects the discharge pressure of the main pump 14. In the present embodiment, the discharge pressure sensor 28 outputs the detected value to the controller 30.

操作圧センサ29は、操作装置26を用いた操作者の操作内容を検出する。本実施形態では、操作圧センサ29は、アクチュエータのそれぞれに対応する操作装置26の操作方向及び操作量を圧力の形で検出し、検出した値をコントローラ30に対して出力する。操作装置26の操作内容は、操作圧センサ以外の他のセンサを用いて検出されてもよい。 The operating pressure sensor 29 detects the operation content of the operator using the operating device 26. In the present embodiment, the operating pressure sensor 29 detects the operating direction and operating amount of the operating device 26 corresponding to each of the actuators in the form of pressure, and outputs the detected value to the controller 30. The operation content of the operation device 26 may be detected by using a sensor other than the operation pressure sensor.

コントローラ30は、データ処理ユニット35、判定ユニット36及び表示ユニット38を機能要素として有する。本実施形態では、各機能要素は、ソフトウェアとして実現されているが、ハードウェア、ファームウェア等で実現されていてもよい。 The controller 30 has a data processing unit 35, a determination unit 36, and a display unit 38 as functional elements. In the present embodiment, each functional element is realized as software, but may be realized by hardware, firmware, or the like.

データ処理ユニット35は、情報取得装置が取得する情報を処理するように構成されている。本実施形態では、データ処理ユニット35は、情報取得装置が出力するデータを判定ユニット36及び管理装置200の制御装置210のそれぞれが利用できるように、情報取得装置が出力するデータを処理する。情報取得装置が取得する情報は、ブーム角度、アーム角度、バケット角度、前後傾斜角、左右傾斜角、旋回角速度、旋回角度、撮像装置S6が撮像した画像、ブームロッド圧、ブームボトム圧、アームロッド圧、アームボトム圧、バケットロッド圧、バケットボトム圧、振動センサS10が検出した旋回減速機の振動、アタッチメントやフレームに貼り付けられた歪センサの検出値、メインポンプ14の吐出圧、操作装置26のそれぞれに関する操作圧等のうちの少なくとも1つを含む。そして、情報取得装置は、ブーム角度センサS1、アーム角度センサS2、バケット角度センサS3、機体傾斜センサS4、旋回角速度センサS5、撮像装置S6、ブームロッド圧センサS7R、ブームボトム圧センサS7B、アームロッド圧センサS8R、アームボトム圧センサS8B、バケットロッド圧センサS9R、バケットボトム圧センサS9B、振動センサS10、歪センサ(図示せず)、吐出圧センサ28、操作圧センサ29等のうちの少なくとも1つを含む。判定ユニット36及び制御装置210のそれぞれが情報取得装置からのデータを直接利用できるのであれば、データ処理ユニット35は省略されてもよい。 The data processing unit 35 is configured to process the information acquired by the information acquisition device. In the present embodiment, the data processing unit 35 processes the data output by the information acquisition device so that the data output by the information acquisition device can be used by each of the determination unit 36 and the control device 210 of the management device 200. The information acquired by the information acquisition device includes boom angle, arm angle, bucket angle, front-back tilt angle, left-right tilt angle, swivel angular velocity, swivel angle, image captured by the image pickup device S6, boom rod pressure, boom bottom pressure, and arm rod. Pressure, arm bottom pressure, bucket rod pressure, bucket bottom pressure, vibration of the swivel speed reducer detected by the vibration sensor S10, detection value of the strain sensor attached to the attachment or frame, discharge pressure of the main pump 14, operating device 26 Includes at least one of the operating pressures and the like for each of the above. The information acquisition device includes a boom angle sensor S1, an arm angle sensor S2, a bucket angle sensor S3, a body tilt sensor S4, a turning angle speed sensor S5, an image pickup device S6, a boom rod pressure sensor S7R, a boom bottom pressure sensor S7B, and an arm rod. At least one of pressure sensor S8R, arm bottom pressure sensor S8B, bucket rod pressure sensor S9R, bucket bottom pressure sensor S9B, vibration sensor S10, strain sensor (not shown), discharge pressure sensor 28, operating pressure sensor 29, etc. including. If each of the determination unit 36 and the control device 210 can directly use the data from the information acquisition device, the data processing unit 35 may be omitted.

データ処理ユニット35は、情報取得装置が出力するデータを所定時間にわたって保持するように構成されている。本実施形態では、データ処理ユニット35は、情報取得装置が出力するデータを揮発性記憶媒体に少なくとも所定時間にわたって一時的に記録する。データ処理ユニット35は、情報取得装置が出力するデータを記憶装置47に記録してもよい。 The data processing unit 35 is configured to hold the data output by the information acquisition device for a predetermined time. In the present embodiment, the data processing unit 35 temporarily records the data output by the information acquisition device on the volatile storage medium for at least a predetermined time. The data processing unit 35 may record the data output by the information acquisition device in the storage device 47.

判定ユニット36は、情報取得装置が出力するデータの集まり(以下、「データセット」とする。)が後述する管理装置200の制御装置210による診断に適しているか否かを判定するように構成されている。例えば、判定ユニット36は、振動センサS10が出力するデータセットが制御装置210による診断に適しているか否かを判定する。制御装置210による診断に適していないデータセットが制御装置210に供給されてしまうのを防止するためである。 The determination unit 36 is configured to determine whether or not a collection of data output by the information acquisition device (hereinafter referred to as a “data set”) is suitable for diagnosis by the control device 210 of the management device 200 described later. ing. For example, the determination unit 36 determines whether or not the data set output by the vibration sensor S10 is suitable for diagnosis by the control device 210. This is to prevent a data set unsuitable for diagnosis by the control device 210 from being supplied to the control device 210.

表示ユニット38は、各種の情報を表示装置40に表示させるように構成されている。本実施形態では、コントローラ30からの指令に応じて所定の画面を表示装置40に表示させる。 The display unit 38 is configured to display various types of information on the display device 40. In the present embodiment, a predetermined screen is displayed on the display device 40 in response to a command from the controller 30.

管理装置200は、制御装置210と、通信装置220と、表示装置230と、を備えている。また、制御装置210は、ショベル情報管理部211と、疲労度算出部212と、繁忙期情報管理部213と、保証内容決定部214と、を機能要素として有する。なお、制御装置210の各機能要素は、ソフトウェアとして実現されていてもよく、ハードウェア、ファームウェア等で実現されていてもよい。 The management device 200 includes a control device 210, a communication device 220, and a display device 230. Further, the control device 210 has an excavator information management unit 211, a fatigue degree calculation unit 212, a busy season information management unit 213, and a guarantee content determination unit 214 as functional elements. Each functional element of the control device 210 may be realized as software, or may be realized by hardware, firmware, or the like.

ショベル情報管理部211は、情報取得装置が出力するデータセットを記憶して管理するように構成されている。データセットは、ショベル100の通信装置T1から送信され、通信ネットワークNW、通信装置220を介して、ショベル情報管理部211に入力される。なお、通信装置T1から送信されるデータセットには判定ユニット36での判定結果が付されていてもよい。また、判定ユニット36により診断に適していると判定されたデータセットのみが通信装置T1から送信される構成であってもよい。 The excavator information management unit 211 is configured to store and manage the data set output by the information acquisition device. The data set is transmitted from the communication device T1 of the excavator 100, and is input to the excavator information management unit 211 via the communication network NW and the communication device 220. The data set transmitted from the communication device T1 may be accompanied by the determination result of the determination unit 36. Further, only the data set determined by the determination unit 36 to be suitable for diagnosis may be transmitted from the communication device T1.

疲労度算出部212は、ショベル情報管理部211に記憶されているデータセットに基づいてアタッチメントの疲労度を算出するように構成されている。本実施形態では、疲労度算出部212は、ショベル100から収集された稼働情報に基づいて、ショベル100の各部品の疲労度を算出する。疲労度は、ショベル100の各部品に蓄積されている累積損傷度、各部品の余寿命を含む。この評価には、現時点までに記憶装置203に蓄積されている稼働情報、累積損傷度等が利用される。部品に蓄積されている累積損傷度及び余寿命の評価方法については、後述する。累積損傷度及び余寿命の評価結果は、ショベル情報管理部211に記憶される。 The fatigue degree calculation unit 212 is configured to calculate the fatigue degree of the attachment based on the data set stored in the excavator information management unit 211. In the present embodiment, the fatigue degree calculation unit 212 calculates the fatigue degree of each part of the excavator 100 based on the operation information collected from the excavator 100. The fatigue degree includes the cumulative damage degree accumulated in each part of the excavator 100 and the remaining life of each part. For this evaluation, the operation information, the cumulative damage degree, and the like accumulated in the storage device 203 up to the present time are used. The evaluation method of the cumulative damage degree and the remaining life accumulated in the parts will be described later. The evaluation results of the cumulative damage degree and the remaining life are stored in the excavator information management unit 211.

繁忙期情報管理部213は、時期と、価格の決定に用いる繁忙期係数と、を対応付けして記憶している。例えば、時期を、繁忙期・通常期・閑散期の3段階の繁忙期情報として分類する場合、通常期における係数を繁忙期における係数よりも低く設定し、閑散期の係数を通常期よりも低く設定してもよい。例えば、会計年度末のような補修の依頼が増える時期を繁忙期と設定してもよい。また、ショベル100の稼働率が高くなる時期を繁忙期としてもよい。 The busy season information management unit 213 stores the time and the busy season coefficient used for determining the price in association with each other. For example, when classifying the period as information on three stages of busy season, busy season, normal season, and off-season, the coefficient in the normal season is set lower than the coefficient in the busy season, and the coefficient in the off-season is lower than the normal season. It may be set. For example, a period when the number of repair requests increases, such as the end of the fiscal year, may be set as a busy period. Further, the busy period may be a period when the operating rate of the excavator 100 is high.

保証内容決定部214は、ショベル情報管理部211に記憶されたショベル100の情報に基づいて、保証内容を決定する。保証内容は、例えば保証期間、補修費用、使用料金を含む。ユーザは、例えば管理装置200にアクセスすることにより、管理装置200の表示装置230に保証内容の情報(以下「保証内容情報」ともいう。)等を表示させることができる。 The guarantee content determination unit 214 determines the guarantee content based on the information of the excavator 100 stored in the excavator information management unit 211. The warranty includes, for example, the warranty period, repair costs, and usage fees. By accessing the management device 200, for example, the user can display the guarantee content information (hereinafter, also referred to as “guarantee content information”) on the display device 230 of the management device 200.

保証期間は、例えばブーム4、アーム5、バケット6等のアタッチメントの保証期間である。保証期間は、メーカ保証等の無償保証期間である通常保証期間と、通常保証期間に追加して設定される追加保証期間と、を含む。保証期間は、疲労度算出部212により算出されるアタッチメントの疲労度に基づいて設定される。例えば、疲労度算出部212により算出されるアタッチメントの累積損傷度が基準累積損傷度よりも小さいほど、追加保証期間が長く設定される。基準累積損傷度は、標準的な作業内容でショベル100を作動させたときに想定される累積損傷度であり、例えばショベル100の納品からの経過日数に応じて設定される。また、疲労度算出部212により算出されるアタッチメントの余寿命が基準余寿命よりも長いほど、追加保証期間が長く設定される。基準余寿命は、標準的な作業内容でショベル100を作動させたときに想定される余寿命であり、例えばショベル100の納品からの経過日数に応じて設定される。標準的な作業内容は、例えばブレーカ作業のように構造部材への負荷が大きい作業(高負荷作業)と、仕上げ作業、積み込み作業、均し作業のように構造部材への負荷が小さい作業(低負荷作業)とを所定の比率(例えば、1:1)で行った場合の作業内容である。 The warranty period is, for example, the warranty period for attachments such as the boom 4, the arm 5, and the bucket 6. The warranty period includes a normal warranty period, which is a free warranty period such as a manufacturer's warranty, and an additional warranty period set in addition to the normal warranty period. The warranty period is set based on the fatigue degree of the attachment calculated by the fatigue degree calculation unit 212. For example, the smaller the cumulative damage degree of the attachment calculated by the fatigue degree calculation unit 212 is smaller than the reference cumulative damage degree, the longer the additional warranty period is set. The reference cumulative damage degree is the cumulative damage degree assumed when the excavator 100 is operated with standard work contents, and is set according to, for example, the number of days elapsed from the delivery of the excavator 100. Further, the longer the remaining life of the attachment calculated by the fatigue degree calculation unit 212 is longer than the standard remaining life, the longer the additional warranty period is set. The reference remaining life is the remaining life assumed when the excavator 100 is operated with standard work contents, and is set according to, for example, the number of days elapsed from the delivery of the excavator 100. The standard work contents are work with a large load on the structural member (high load work) such as breaker work, and work with a small load on the structural member such as finishing work, loading work, and leveling work (low load work). This is the work content when the load work) is performed at a predetermined ratio (for example, 1: 1).

補修費用は、例えばブーム4、アーム5、バケット6等のアタッチメントの補修費用である。補修費用は、アタッチメントに亀裂が生じた後に疲労度算出部212により算出されたアタッチメントの余寿命に基づいて決定される補修時期に基づいて設定される。例えば、アタッチメントに亀裂が生じた直後に補修を行う場合には、補修費用は基準額に所定の第1割増額を追加した費用に設定される。また、アタッチメントに亀裂が生じた後に余寿命の範囲内で所定期間(例えば2日〜1週間)アタッチメントの使用を継続した後に補修を行う場合には、補修費用は基準額に第1割増額よりも低額の第2割増額を追加した費用に設定される。また、アタッチメントに亀裂が生じた後に余寿命が長くなるように作業内容を変更し、且つ、該余寿命の範囲内で所定期間(例えば1週間〜1ヶ月)アタッチメントの使用を継続した後に補修を行う場合には、補修費用は基準額に割増額を追加しない費用に設定される。さらに、補修費用は、基準額に繁忙期情報管理部213の繁忙期係数を積算したものとしてもよい。 The repair cost is, for example, the repair cost of attachments such as the boom 4, the arm 5, and the bucket 6. The repair cost is set based on the repair time determined based on the remaining life of the attachment calculated by the fatigue degree calculation unit 212 after the attachment has cracked. For example, when repairing is performed immediately after a crack occurs in the attachment, the repair cost is set to a cost obtained by adding a predetermined 10% increase to the standard amount. In addition, if repairs are performed after the attachment has been used for a specified period (for example, 2 days to 1 week) within the remaining life after the attachment has cracked, the repair cost will be 10% higher than the standard amount. Is set as an additional cost with a low 20% increase. In addition, the work content is changed so that the remaining life is extended after the attachment is cracked, and repair is performed after continuing to use the attachment for a predetermined period (for example, 1 week to 1 month) within the remaining life. If so, the repair cost will be set to a cost that does not add a surcharge to the standard amount. Further, the repair cost may be obtained by adding the busy season coefficient of the busy season information management unit 213 to the standard amount.

使用料金は、ショベル100の使用料金であり、例えばショベル100をレンタルした者がレンタル会社に支払う料金、レンタル会社からショベル100をレンタルした者に還付される還付金を含む。使用料金は、疲労度算出部212により算出される疲労度に基づいて設定される。例えば、疲労度算出部212により算出されるアタッチメントの累積損傷度が基準累積損傷度よりも小さいほど、還付金が高額に設定される。基準累積損傷度は、標準的な作業内容でショベル100を作動させたときに想定される累積損傷度であり、例えばショベル100をレンタルした者がショベル100の使用を開始してからの経過日数に応じて設定される。また、疲労度算出部212により算出されるアタッチメントの余寿命が基準余寿命よりも長いほど、還付金が高額に設定される。基準余寿命は、標準的な作業内容でショベル100を作動させたときに想定される余寿命であり、例えばショベル100をレンタルした者がショベル100の使用を開始してからの経過日数に応じて設定される。 The usage fee is a usage fee of the excavator 100, and includes, for example, a fee paid by the person who rented the excavator 100 to the rental company, and a refund refunded to the person who rented the excavator 100 from the rental company. The usage fee is set based on the fatigue level calculated by the fatigue level calculation unit 212. For example, the smaller the cumulative damage degree of the attachment calculated by the fatigue degree calculation unit 212 than the reference cumulative damage degree, the higher the refund is set. The reference cumulative damage degree is the cumulative damage degree assumed when the excavator 100 is operated with standard work contents, for example, the number of days elapsed since the person who rented the excavator 100 started using the excavator 100. Set accordingly. Further, the longer the remaining life of the attachment calculated by the fatigue degree calculation unit 212 is longer than the standard remaining life, the higher the refund is set. The standard remaining life is the remaining life assumed when the excavator 100 is operated with standard work contents. For example, depending on the number of days elapsed since the person who rented the excavator 100 started using the excavator 100. Set.

通信装置220は、通信ネットワークNWを通じて、他の装置、例えばショベル100と通信可能に構成されている。 The communication device 220 is configured to be able to communicate with another device, for example, the excavator 100, through the communication network NW.

表示装置230は、各種の情報を表示させるように構成されている。 The display device 230 is configured to display various types of information.

図3を参照して、ショベル100の疲労度を算出する処理(以下「疲労度算出処理」という。)について説明する。疲労度算出処理は、管理装置200の制御装置210により実行される。図3は、疲労度算出処理の一例を示すフローチャートである。 A process of calculating the fatigue degree of the excavator 100 (hereinafter referred to as “fatigue degree calculation process”) will be described with reference to FIG. The fatigue degree calculation process is executed by the control device 210 of the management device 200. FIG. 3 is a flowchart showing an example of the fatigue degree calculation process.

まず、ステップST1において、管理装置200が、ショベル100によって作業中に繰り返される一連の動作の少なくとも1周期分の測定値を、アタッチメントの姿勢センサ、アタッチメントのシリンダ圧センサ及び旋回角速度センサS5から取得する。これらの測定値と共に、作業種別、作業年月日、機体識別番号等の情報が取得される。 First, in step ST1, the management device 200 acquires measured values for at least one cycle of a series of operations repeated during work by the excavator 100 from the attachment posture sensor, the attachment cylinder pressure sensor, and the turning angular velocity sensor S5. .. Along with these measured values, information such as work type, work date, and aircraft identification number is acquired.

旋回角速度センサS5から、上部旋回体3の旋回角が取得される。アタッチメントの姿勢センサ及び旋回角速度センサS5の検出値によって、ショベル100の姿勢が特定される。ショベル100の一連の動作のうち、アタッチメントの姿勢センサ、アタッチメントのシリンダ圧センサ及び旋回角速度センサS5で測定値を取得する時間の範囲は、管理装置200の管理オペレータが設定してもよいし、ショベル100の運転者または保守要員が設定してもよい。ショベル100で繰り返される一連の動作は、例えば掘削開始、持ち上げ旋回、排土、戻り旋回を含む工程を1周期として、該工程が繰り返される。 The turning angle of the upper turning body 3 is acquired from the turning angular velocity sensor S5. The posture of the excavator 100 is specified by the detected values of the posture sensor of the attachment and the turning angular velocity sensor S5. In the series of operations of the excavator 100, the range of time for acquiring the measured values by the attitude sensor of the attachment, the cylinder pressure sensor of the attachment, and the turning angular velocity sensor S5 may be set by the management operator of the management device 200, or the excavator may be set. It may be set by 100 drivers or maintenance personnel. The series of operations repeated by the excavator 100 is repeated with one cycle including, for example, excavation start, lifting turn, soil removal, and return turn.

ステップST2において、一連の動作の1周期内で、解析すべき複数の時刻(以下、「解析時刻」という。)を抽出する。例えば、シリンダ内の油圧、旋回角度の時間波形のピーク、変曲点等の特徴的な時刻を、解析時刻として抽出する。抽出する解析時刻の個数を多くすると、解析精度が向上するが、解析に要する計算時間は長くなる。管理装置200が、ショベル100の動作中におけるブームシリンダ7内の油圧、アーム5の先端の高さ及び旋回角度の時間波形に基づいて解析時刻を自動的に抽出するようにしてもよいし、オペレータが該時間波形を観察して解析時刻を決定し、解析時刻を入力するようにしてもよい。 In step ST2, a plurality of times to be analyzed (hereinafter, referred to as “analysis time”) are extracted within one cycle of a series of operations. For example, characteristic times such as the oil pressure in the cylinder, the peak of the time waveform of the turning angle, and the inflection point are extracted as the analysis time. Increasing the number of analysis times to be extracted improves the analysis accuracy, but the calculation time required for the analysis becomes long. The management device 200 may automatically extract the analysis time based on the time waveform of the oil pressure in the boom cylinder 7 during the operation of the excavator 100, the height of the tip of the arm 5, and the turning angle, or the operator. May observe the time waveform, determine the analysis time, and input the analysis time.

ステップST3において、解析時刻の各々において、解析モデルを用い、ブーム4、アーム5等の部品の各々に加わっている応力の分布を算出する。応力の分布は、解析時刻ごとに決定されているショベル100の特定の姿勢に基づいて計算される。すなわち、繰り返される一連の動作の1周期内に現れる種々のショベル100の姿勢ごとに、ショベル100の部品に加わっている荷重に基づいて、応力の分布を算出する。応力の分布の算出には、例えば有限要素法等の数値解析手法を適用できる。このとき、ショベル100の姿勢及びショベル100の部品に加わる荷重が解析条件として用いられる。ここで、荷重はベクトルで表される。荷重の大きさ及び向きは、油圧シリンダ内の油圧、油圧シリンダの軸方向(アタッチメントの姿勢)及び旋回角加速度により求まる。旋回角加速度は、旋回角を2回微分することにより算出される。応力は、解析モデルを構成する要素及び節点ごとに算出される。応力分布の解析結果が、解析時刻ごとに、かつ部品ごとに算出される。 In step ST3, the distribution of stress applied to each of the parts such as the boom 4 and the arm 5 is calculated by using the analysis model at each of the analysis times. The stress distribution is calculated based on the specific posture of the excavator 100, which is determined for each analysis time. That is, the stress distribution is calculated based on the load applied to the parts of the excavator 100 for each posture of the excavator 100 appearing in one cycle of the repeated series of operations. A numerical analysis method such as the finite element method can be applied to the calculation of the stress distribution. At this time, the posture of the excavator 100 and the load applied to the parts of the excavator 100 are used as analysis conditions. Here, the load is represented by a vector. The magnitude and direction of the load can be obtained from the hydraulic pressure in the hydraulic cylinder, the axial direction of the hydraulic cylinder (attachment posture), and the turning angular acceleration. The turning angular acceleration is calculated by differentiating the turning angle twice. The stress is calculated for each element and node that make up the analytical model. The stress distribution analysis result is calculated for each analysis time and for each part.

ステップST4において、各部品の評価点ごとに、1周期の動作期間中に蓄積される損傷度(以下「単周期損傷度」という。)を算出する。これにより、部品内における単周期損傷度の分布が得られる。単周期損傷度は、応力の時間変化から抽出される応力の極値に基づいて算出される。単周期損傷度は、公知の方法により算出できる。 In step ST4, the degree of damage accumulated during the operation period of one cycle (hereinafter referred to as “single cycle damage degree”) is calculated for each evaluation point of each component. As a result, the distribution of the degree of single-cycle damage in the component can be obtained. The degree of single-cycle damage is calculated based on the extremum of stress extracted from the time variation of stress. The degree of single-cycle damage can be calculated by a known method.

ステップST5において、部品の累積損傷度及び余寿命の分布を算出する。以下、累積損傷度及び余寿命の算出方法について説明する。管理装置200は、管理対象のショベル100の機体ごと及び部品ごとに、機体の稼働開始時点から現時点までの単周期損傷度の総和(累積損傷度)を算出する。今回のデータ収集の対象となる動作を開始するまでに蓄積された累積損傷度は、ショベル情報管理部211に記憶されている。ショベル100の部品の、ある箇所の累積損傷度が1になると、その箇所で破断が生じる可能性が高くなる。1から累積損傷度を減算することにより、余寿命が求まる。 In step ST5, the distribution of the cumulative damage degree and the remaining life of the parts is calculated. Hereinafter, a method for calculating the cumulative damage degree and the remaining life will be described. The management device 200 calculates the total amount of single-cycle damages (cumulative damages) from the start of operation of the machine to the present time for each machine and parts of the excavator 100 to be managed. The cumulative damage degree accumulated up to the start of the operation to be collected this time is stored in the excavator information management unit 211. When the cumulative damage degree of a part of the excavator 100 becomes 1 at a certain point, the possibility of breakage at that point increases. The remaining life can be obtained by subtracting the cumulative damage degree from 1.

ステップST6において、ステップST5で求められた累積損傷度及び余寿命が、機体識別番号等の情報と関連付けられて、ショベル情報管理部211に記憶される。 In step ST6, the cumulative damage degree and remaining life obtained in step ST5 are stored in the excavator information management unit 211 in association with information such as the aircraft identification number.

図4を参照し、ショベルの管理システム300によって生成される表示画面の表示例について説明する。図4は、一実施形態の表示画面の一例を示す図である。なお、以下の説明においては、表示画面400は、管理装置200の表示装置230に表示されるものとし、疲労度算出処理により算出された余寿命と該余寿命と関連付けられた保証期間とを含む情報を表示するものとする。 A display example of the display screen generated by the excavator management system 300 will be described with reference to FIG. FIG. 4 is a diagram showing an example of a display screen of one embodiment. In the following description, the display screen 400 shall be displayed on the display device 230 of the management device 200, and includes the remaining life calculated by the fatigue degree calculation process and the warranty period associated with the remaining life. Information shall be displayed.

表示画面400は、保証期間表示部410、最弱箇所表示部420、余寿命表示部430を有する。図4の例では、保証期間表示部410、最弱箇所表示部420及び余寿命表示部430は上方からこの順に配置されている。但し、保証期間表示部410、最弱箇所表示部420及び余寿命表示部430の配置は、図4に示される配置に限定されるものではない。 The display screen 400 has a warranty period display unit 410, a weakest point display unit 420, and a remaining life display unit 430. In the example of FIG. 4, the warranty period display unit 410, the weakest point display unit 420, and the remaining life display unit 430 are arranged in this order from the top. However, the arrangement of the warranty period display unit 410, the weakest part display unit 420, and the remaining life display unit 430 is not limited to the arrangement shown in FIG.

保証期間表示部410は、アタッチメントの保証期間に関する情報を表示する。図4の例では、保証期間表示部410には、アタッチメントの通常保証期間を表すバーゲージ411及び追加保証期間を表すバーゲージ412が表示されている。通常保証期間は、例えばメーカ保証等の無償保証期間であり、予め設定された保証期間に基づいて表示される。追加保証期間は、疲労度算出処理で算出されるアタッチメントの余寿命に基づいて表示される。 The warranty period display unit 410 displays information regarding the warranty period of the attachment. In the example of FIG. 4, the warranty period display unit 410 displays a bar gauge 411 indicating the normal warranty period of the attachment and a bar gauge 412 representing the additional warranty period. The normal warranty period is, for example, a free warranty period such as a manufacturer's warranty, and is displayed based on a preset warranty period. The additional warranty period is displayed based on the remaining life of the attachment calculated by the fatigue degree calculation process.

例えば、疲労度算出処理で算出されるアタッチメントの余寿命が基準余寿命よりも長い場合、追加保証期間を表すバーゲージ412は算出された余寿命と基準余寿命との差に応じた長さで、通常保証期間を表すバーゲージ411の右側に表示される。一方、疲労度算出処理で算出されるアタッチメントの余寿命が基準余寿命よりも短い場合、追加保証期間を表すバーゲージ412は表示されない。基準余寿命は、標準的な作業内容でショベル100を作動させたときに想定される余寿命であり、例えばショベル100の納品からの経過日数に応じて設定される。標準的な作業内容は、例えばブレーカ作業のように構造部材への負荷が大きい作業(高負荷作業)と、仕上げ作業、積み込み作業、均し作業のように構造部材への負荷が小さい作業(低負荷作業)とを所定の比率(例えば、1:1)で行った場合の作業内容である。 For example, when the remaining life of the attachment calculated by the fatigue degree calculation process is longer than the standard remaining life, the bar gauge 412 representing the additional warranty period is a length corresponding to the difference between the calculated remaining life and the standard remaining life. It is displayed on the right side of the bar gauge 411, which normally represents the warranty period. On the other hand, if the remaining life of the attachment calculated by the fatigue degree calculation process is shorter than the standard remaining life, the bar gauge 412 indicating the additional warranty period is not displayed. The reference remaining life is the remaining life assumed when the excavator 100 is operated with standard work contents, and is set according to, for example, the number of days elapsed from the delivery of the excavator 100. The standard work contents are work with a large load on the structural member (high load work) such as breaker work, and work with a small load on the structural member such as finishing work, loading work, and leveling work (low load work). This is the work content when the load work) is performed at a predetermined ratio (for example, 1: 1).

また、図4の例では、通常保証期間と追加保証期間との区別を容易にするために、通常保証期間を表すバーゲージ411が実線で表示され、追加保証期間を表すバーゲージ413が破線で表示されている。但し、通常保証期間と追加保証期間の表示方法はこれに限定されず、例えば色分け表示されていてもよい。 Further, in the example of FIG. 4, in order to facilitate the distinction between the normal warranty period and the additional warranty period, the bar gauge 411 representing the normal warranty period is displayed with a solid line, and the bar gauge 413 indicating the additional warranty period is displayed with a broken line. ing. However, the display method of the normal warranty period and the additional warranty period is not limited to this, and may be displayed in different colors, for example.

最弱箇所表示部420は、アタッチメントの最弱箇所を特定する情報を表示する。図4の例では、最弱箇所表示部420には、アーム5の画像421、アーム5における最弱箇所を特定する画像422、ブーム4の画像423及びブーム4における最弱箇所を特定する画像424が表示されている。アーム5における最弱箇所及びブーム4における最弱箇所は、疲労度算出処理で算出される疲労度(例えば、累積損傷度、余寿命)の分布に基づいて表示される。例えば、アーム5における最弱箇所及びブーム4における最弱箇所は、疲労度算出処理で算出される累積損傷度の分布において累積損傷度が最も大きい箇所である。また、例えばアーム5における最弱箇所及びブーム4における最弱箇所は、疲労度算出処理で算出される余寿命の分布において余寿命が最も短い箇所である。なお、図4の例では、アーム5の画像421及びブーム4の画像422は左右に並んで表示されているが、これに限定されず、例えば上下に並んで表示されていてもよい。また、アーム5の画像421とブーム4の画像422のいずれか一方のみが表示されていてもよい。 The weakest part display unit 420 displays information for identifying the weakest part of the attachment. In the example of FIG. 4, the weakest part display unit 420 has an image 421 of the arm 5, an image 422 that identifies the weakest part of the arm 5, an image 423 of the boom 4, and an image 424 that identifies the weakest part of the boom 4. Is displayed. The weakest part of the arm 5 and the weakest part of the boom 4 are displayed based on the distribution of the fatigue degree (for example, cumulative damage degree, remaining life) calculated by the fatigue degree calculation process. For example, the weakest part in the arm 5 and the weakest part in the boom 4 are the parts having the largest cumulative damage degree in the distribution of the cumulative damage degree calculated by the fatigue degree calculation process. Further, for example, the weakest part in the arm 5 and the weakest part in the boom 4 are the parts having the shortest remaining life in the distribution of the remaining life calculated by the fatigue degree calculation process. In the example of FIG. 4, the image 421 of the arm 5 and the image 422 of the boom 4 are displayed side by side, but the present invention is not limited to this, and the image 421 of the arm 5 and the image 422 of the boom 4 may be displayed side by side, for example. Further, only one of the image 421 of the arm 5 and the image 422 of the boom 4 may be displayed.

余寿命表示部430は、アタッチメントの余寿命を表示する。図4の例では、余寿命表示部430には、現在のアーム5の余寿命を表すバーゲージ431及び現在のブーム4の余寿命を表すバーゲージ432が表示されている。アーム5の余寿命及びブーム4の余寿命は、疲労度算出処理で算出される余寿命の分布に基づいて表示される。例えば、現在のアーム5の余寿命及び現在のブーム4の余寿命は、それぞれ疲労度算出処理で算出される余寿命の分布における最も短い余寿命であってもよく、平均値や中央値であってもよい。また、余寿命表示部430には、現在のアーム5の余寿命を表すバーゲージ431及び現在のブーム4の余寿命を表すバーゲージ432に重畳して、基準余寿命を表す画像が表示されていてもよい。基準余寿命を表す画像が表示されることにより、管理者は基準余寿命に対する現在の余寿命を容易に把握できる。また、余寿命表示部430には、アタッチメントの余寿命に代えて、又は余寿命と共に、アタッチメントの累積損傷度が表示されるようにしてもよい。 The remaining life display unit 430 displays the remaining life of the attachment. In the example of FIG. 4, the remaining life display unit 430 displays a bar gauge 431 indicating the remaining life of the current arm 5 and a bar gauge 432 indicating the remaining life of the current boom 4. The remaining life of the arm 5 and the remaining life of the boom 4 are displayed based on the distribution of the remaining life calculated by the fatigue degree calculation process. For example, the current remaining life of the arm 5 and the current remaining life of the boom 4 may be the shortest remaining life in the distribution of the remaining life calculated by the fatigue degree calculation process, respectively, and are an average value or a median value. You may. Further, even if the remaining life display unit 430 displays an image showing the reference remaining life by superimposing it on the bar gauge 431 showing the remaining life of the current arm 5 and the bar gauge 432 showing the remaining life of the current boom 4. good. By displaying an image showing the standard remaining life, the administrator can easily grasp the current remaining life with respect to the standard remaining life. Further, the remaining life display unit 430 may display the cumulative damage degree of the attachment instead of or together with the remaining life of the attachment.

以上に説明したように、一実施形態の管理システム300によれば、図4に示されるように、アタッチメントの余寿命(若しくは、累積損傷度)と保証期間とが関連付けして表示される。これにより、管理者は、表示装置230の表示画面400に表示された情報に基づいて、ショベル100の使用状況に応じた保証期間を設定できる。例えば、管理者は、表示装置230の表示画面400に表示されたアタッチメントの余寿命が基準余寿命よりも長い場合にアタッチメントの通常保証期間に追加保証期間を付加した保証期間を設定できる。 As described above, according to the management system 300 of one embodiment, as shown in FIG. 4, the remaining life (or cumulative damage degree) of the attachment and the warranty period are displayed in association with each other. As a result, the administrator can set the warranty period according to the usage status of the excavator 100 based on the information displayed on the display screen 400 of the display device 230. For example, the administrator can set a warranty period in which an additional warranty period is added to the normal warranty period of the attachment when the remaining life of the attachment displayed on the display screen 400 of the display device 230 is longer than the standard remaining life.

図4の事例では、例えば、保証期間を5000時間とした場合、保証期間内における80%(4000時間)を利用した事例である。この場合でも、負荷が小さい作業を行っていると、基準として設定された保証期間内に保証された基準余寿命(100%)のうち、ブーム4、アーム5の余寿命は60%程度残っている。つまり、40%程度しか利用されていない。このため、保証期間内の80%(4000時間)を利用した時点で、1500時間(130%)の追加保証期間を設定できる。 In the case of FIG. 4, for example, when the warranty period is 5000 hours, 80% (4000 hours) within the warranty period is used. Even in this case, if the work is performed with a small load, about 60% of the remaining life of the boom 4 and arm 5 remains out of the standard remaining life (100%) guaranteed within the warranty period set as the standard. There is. That is, only about 40% is used. Therefore, when 80% (4000 hours) of the warranty period is used, an additional warranty period of 1500 hours (130%) can be set.

なお、図4の例では、アタッチメントの余寿命と保証期間とを含む情報が管理装置200の表示装置230に表示される場合を示したが、本開示はこれに限定されず、例えばショベル100の表示装置40に表示されてもよい。また、管理装置200と通信ネットワークNWを通じて通信可能な他の装置に表示されてもよい。 In the example of FIG. 4, the case where the information including the remaining life of the attachment and the warranty period is displayed on the display device 230 of the management device 200 is shown, but the present disclosure is not limited to this, and for example, the excavator 100. It may be displayed on the display device 40. Further, it may be displayed on another device capable of communicating with the management device 200 through the communication network NW.

また、図4の例では、表示装置230の表示画面400に、アタッチメントの余寿命と保証期間とが関連付けされて表示される場合を示したが、本開示はこれに限定されず、例えばアタッチメントの累積損傷度と保証期間とが関連付けされて表示されてもよい。この場合、管理者は、表示装置230の表示画面400に表示されたアタッチメントの累積損傷度が基準累積損傷度よりも小さい場合にアタッチメントの通常保証期間に追加保証期間を付加した保証期間を設定できる。 Further, in the example of FIG. 4, the case where the remaining life of the attachment and the warranty period are displayed in association with each other on the display screen 400 of the display device 230 is shown, but the present disclosure is not limited to this, and for example, the attachment The cumulative damage level and the warranty period may be displayed in association with each other. In this case, the administrator can set a warranty period in which an additional warranty period is added to the normal warranty period of the attachment when the cumulative damage degree of the attachment displayed on the display screen 400 of the display device 230 is smaller than the reference cumulative damage degree. ..

また、表示画面400には日時、機番、使用者、これまでの使用時間(図示せず)が表示されてもよい。 Further, the date and time, the machine number, the user, and the past usage time (not shown) may be displayed on the display screen 400.

図5を参照し、ショベルの管理システム300によって生成される表示画面の別の表示例について説明する。図5は、一実施形態の表示画面の別の例を示す図である。なお、以下の説明においては、表示画面500は、管理装置200の表示装置230に表示されるものとし、疲労度算出処理により算出された余寿命と該余寿命と関連付けられた補修費用とを含む情報を表示するものとする。 With reference to FIG. 5, another display example of the display screen generated by the excavator management system 300 will be described. FIG. 5 is a diagram showing another example of the display screen of one embodiment. In the following description, the display screen 500 shall be displayed on the display device 230 of the management device 200, and includes the remaining life calculated by the fatigue degree calculation process and the repair cost associated with the remaining life. Information shall be displayed.

表示画面500は、余寿命表示部510、補修費用表示部520、最弱箇所表示部530を有する。図5の例では、余寿命表示部510、補修費用表示部520及び最弱箇所表示部530は上方からこの順に配置されている。但し、余寿命表示部510、補修費用表示部520及び最弱箇所表示部530の配置は、図5に示される配置に限定されるものではない。 The display screen 500 has a remaining life display unit 510, a repair cost display unit 520, and a weakest location display unit 530. In the example of FIG. 5, the remaining life display unit 510, the repair cost display unit 520, and the weakest location display unit 530 are arranged in this order from the top. However, the arrangement of the remaining life display unit 510, the repair cost display unit 520, and the weakest location display unit 530 is not limited to the arrangement shown in FIG.

余寿命表示部510は、アタッチメントの余寿命を表示する。図5の例では、余寿命表示部510には、バーゲージ511、バーゲージ512、図形513〜515が表示されている。バーゲージ511は、現在の作業内容(現作業内容)でショベル100の使用を継続した場合のアタッチメントの余寿命を表す。バーゲージ512は、現在の作業内容から余寿命を延ばすために推奨される作業内容(推奨作業内容)に変更してショベル100を使用する場合のアタッチメントの余寿命を表す。推奨作業内容は、例えば、地山の掘削作業のショベルに対しては搬出作業等への変更である。岩盤作業を行っているショベルに対しては、平地掘削等への変更である。図形513〜515は、それぞれ異なる補修時期を表す。図形513は、アタッチメントに亀裂が生じた直後に補修を行う時期(若しくは、亀裂が生じた時点)を表す。図形514は、アタッチメントに亀裂が生じた後に現在の作業内容でショベル100の使用を継続した場合の余寿命の範囲内の期間(例えば2日〜1週間)を表す。図形515は、アタッチメントに亀裂が生じた後に現在の作業内容から余寿命を延ばすために推奨される作業内容に変更した場合の余寿命の範囲内の期間(例えば1週間〜1ヶ月)を表す。現在の作業でショベル100の使用を継続した場合のアタッチメントの余寿命及び推奨される作業でショベル100を使用する場合のアタッチメントの余寿命は、疲労度算出処理で算出される余寿命に基づいて表示される。例えば、現在の作業でショベル100の使用を継続した場合のアタッチメントの余寿命及び推奨される作業でショベル100を使用する場合のアタッチメントの余寿命は、それぞれ疲労度算出処理で算出される余寿命の分布における最も短い余寿命であってもよく、平均値や中央値であってもよい。 The remaining life display unit 510 displays the remaining life of the attachment. In the example of FIG. 5, the bar gauge 511, the bar gauge 512, and the figures 513 to 515 are displayed on the remaining life display unit 510. The bar gauge 511 represents the remaining life of the attachment when the shovel 100 is continuously used in the current work content (current work content). The bar gauge 512 represents the remaining life of the attachment when the excavator 100 is used by changing from the current work content to the recommended work content (recommended work content) for extending the remaining life. The recommended work content is, for example, a change to a shovel for excavation work in the ground to carry-out work. For excavators performing rock work, it is a change to flat ground excavation. Figures 513 to 515 represent different repair times. The figure 513 represents the time (or the time when the crack occurs) for repairing immediately after the crack occurs in the attachment. FIG. 514 represents a period (for example, 2 days to 1 week) within the remaining life when the shovel 100 is continued to be used in the current work content after the attachment is cracked. FIG. 515 represents a period (for example, 1 week to 1 month) within the range of the remaining life when the current work content is changed to the recommended work content for extending the remaining life after the attachment is cracked. The remaining life of the attachment when the excavator 100 is used in the current work and the remaining life of the attachment when the excavator 100 is used in the recommended work are displayed based on the remaining life calculated by the fatigue degree calculation process. Will be done. For example, the remaining life of the attachment when the shovel 100 is used continuously in the current work and the remaining life of the attachment when the shovel 100 is used in the recommended work are the remaining life calculated by the fatigue degree calculation process, respectively. It may be the shortest remaining life in the distribution, or it may be the mean or median.

補修費用表示部520は、アタッチメントの補修費用に関する情報を表示する。図5の例では、補修費用表示部520には、バーゲージ521〜523が表示されている。バーゲージ521は、余寿命表示部510に表示された図形513で示される時期にアタッチメントを補修する場合の補修費用を表す。バーゲージ521で表される補修費用は、基準額521aに所定の第1割増額521bを追加した費用である。バーゲージ522は、余寿命表示部510に表示された図形514で示される期間にアタッチメントを補修する場合の補修費用を表す。バーゲージ522で表される補修費用は、基準額522aに第1割増額521bよりも低額の第2割増額522bを追加した費用である。バーゲージ523は、余寿命表示部510に表示された図形515で示される期間にアタッチメントを補修する場合の補修費用を表す。バーゲージ523で表される補修費用は、基準額523aに割増額を追加しない費用である。また、基準額521a,522a,523a、第1割増額521b及び第2割増額522bは、繁忙期情報管理部213の繁忙期係数が積算されたものであってもよい。 The repair cost display unit 520 displays information on the repair cost of the attachment. In the example of FIG. 5, bar gauges 521 to 523 are displayed on the repair cost display unit 520. The bar gauge 521 represents a repair cost when the attachment is repaired at the time indicated by the figure 513 displayed on the remaining life display unit 510. The repair cost represented by the bar gauge 521 is the cost obtained by adding a predetermined 10% increase amount 521b to the standard amount 521a. The bar gauge 522 represents the repair cost when the attachment is repaired during the period shown by the figure 514 displayed on the remaining life display unit 510. The repair cost represented by the bar gauge 522 is the cost obtained by adding the 20% increase 522b, which is lower than the 10% increase 521b, to the standard amount 522a. The bar gauge 523 represents a repair cost when the attachment is repaired during the period shown by the figure 515 displayed on the remaining life display unit 510. The repair cost represented by the bar gauge 523 is a cost that does not add an extra amount to the standard amount 523a. Further, the reference amounts 521a, 522a, 523a, the 10% increase amount 521b and the 20% increase amount 522b may be the sum of the busy period coefficients of the busy period information management unit 213.

最弱箇所表示部530は、アタッチメントの最弱箇所を特定する情報を表示する。図5の例では、最弱箇所表示部530には、ブーム4における現時点での最弱箇所を表す画像531及び推奨される作業内容に変更した場合の予測されるブーム4における最弱箇所を表す画像532が表示されている。ブーム4における最弱箇所は、疲労度算出処理で算出される疲労度(例えば、累積損傷度、余寿命)の分布に基づいて表示される。例えば、ブーム4における最弱箇所は、疲労度算出処理で算出される累積損傷度の分布において累積損傷度が最も大きい箇所である。また、例えばブーム4における最弱箇所は、疲労度算出処理で算出される余寿命の分布において余寿命が最も短い箇所である。なお、図5の例では、ブーム4における現時点での最弱箇所を表す画像531及び推奨される作業内容に変更した場合の予測されるブーム4における最弱箇所を表す画像532は左右に並んで表示されているが、これに限定されず、例えば上下に並んで表示されていてもよい。 The weakest part display unit 530 displays information for identifying the weakest part of the attachment. In the example of FIG. 5, the weakest part display unit 530 shows the image 531 showing the weakest part of the boom 4 at the present time and the weakest part of the boom 4 predicted when the work content is changed to the recommended work content. Image 532 is displayed. The weakest point in the boom 4 is displayed based on the distribution of the fatigue degree (for example, cumulative damage degree, remaining life) calculated by the fatigue degree calculation process. For example, the weakest point in the boom 4 is the place where the cumulative damage degree is the largest in the distribution of the cumulative damage degree calculated by the fatigue degree calculation process. Further, for example, the weakest part in the boom 4 is the part having the shortest remaining life in the distribution of the remaining life calculated by the fatigue degree calculation process. In the example of FIG. 5, the image 531 showing the weakest part of the boom 4 at the present time and the image 532 showing the predicted weakest part of the boom 4 when changed to the recommended work content are arranged side by side. Although it is displayed, the present invention is not limited to this, and for example, it may be displayed side by side.

以上に説明したように、一実施形態の管理システム300によれば、図5に示されるように、アタッチメントの余寿命と補修費用とが関連付けして表示される。これにより、管理者は、表示装置230の表示画面500に表示された情報に基づいて、ショベル100の使用状況に応じた補修費用を設定できる。例えば、管理者は、表示装置230の表示画面500に表示されたアタッチメントの余寿命及び補修時期に基づいて、基準額に割増額を追加した補修費用を設定できる。また、作業内容と補修費用とが関連付けされてもよい。また、作業内容と余寿命とが関連付けされてもよい。また、作業内容と保証期間とが関連付けされてもよい。 As described above, according to the management system 300 of one embodiment, as shown in FIG. 5, the remaining life of the attachment and the repair cost are displayed in association with each other. As a result, the administrator can set the repair cost according to the usage status of the excavator 100 based on the information displayed on the display screen 500 of the display device 230. For example, the administrator can set the repair cost by adding an extra amount to the reference amount based on the remaining life of the attachment displayed on the display screen 500 of the display device 230 and the repair time. In addition, the work content and the repair cost may be associated with each other. Further, the work content and the remaining life may be associated with each other. In addition, the work content and the warranty period may be associated with each other.

なお、図5の例では、アタッチメントの余寿命と補修費用とを含む情報が管理装置200の表示装置230に表示される場合を示したが、本開示はこれに限定されず、例えばショベル100の表示装置40に表示されてもよい。また、管理装置200と通信ネットワークNWを通じて通信可能な他の装置に表示されてもよい。 In the example of FIG. 5, information including the remaining life of the attachment and the repair cost is displayed on the display device 230 of the management device 200, but the present disclosure is not limited to this, for example, the excavator 100. It may be displayed on the display device 40. Further, it may be displayed on another device capable of communicating with the management device 200 through the communication network NW.

また、表示画面500には日時、機番、使用者、これまでの使用時間(図示せず)が表示されてもよい。 Further, the date and time, the machine number, the user, and the past usage time (not shown) may be displayed on the display screen 500.

図6を参照し、ショベルの管理システム300によって生成される表示画面の更に別の表示例について説明する。図6は、一実施形態の表示画面の更に別の例を示す図である。なお、以下の説明においては、表示画面600は、管理装置200の表示装置230に表示されるものとし、疲労度算出処理により算出された累積損傷度と該累積損傷度と関連付けられた使用料金とを含む情報を表示するものとする。 Further, another display example of the display screen generated by the excavator management system 300 will be described with reference to FIG. FIG. 6 is a diagram showing still another example of the display screen of one embodiment. In the following description, the display screen 600 is assumed to be displayed on the display device 230 of the management device 200, and the cumulative damage degree calculated by the fatigue degree calculation process and the usage fee associated with the cumulative damage degree are used. Information including.

表示画面600は、使用料金表示部610、最弱箇所表示部620、累積損傷度表示部630を有する。図6の例では、使用料金表示部610、最弱箇所表示部620及び累積損傷度表示部630は上方からこの順に配置されている。但し、使用料金表示部610、最弱箇所表示部620及び累積損傷度表示部630の配置は、図6に示される配置に限定されるものではない。 The display screen 600 has a usage fee display unit 610, a weakest location display unit 620, and a cumulative damage degree display unit 630. In the example of FIG. 6, the usage charge display unit 610, the weakest location display unit 620, and the cumulative damage degree display unit 630 are arranged in this order from the top. However, the arrangement of the usage fee display unit 610, the weakest part display unit 620, and the cumulative damage degree display unit 630 is not limited to the arrangement shown in FIG.

使用料金表示部610は、ショベル100の使用料金に関する情報を表示する。図6の例では、使用料金表示部610には、ショベル100をレンタルした者がレンタル会社に支払う料金を表すバーゲージ611及びレンタル会社からショベル100をレンタルした者に還付される還付金を表すバーゲージ612が表示されている。還付金を表すバーゲージ612は、疲労度算出処理で算出される疲労度(例えば、累積損傷度、余寿命)に基づいて表示される。例えば、還付金を表すバーゲージ612は、疲労度算出処理により算出されるアタッチメントの累積損傷度が基準累積損傷度よりも小さいほど、長いバーゲージで表示される。 The usage fee display unit 610 displays information on the usage fee of the excavator 100. In the example of FIG. 6, the usage fee display unit 610 shows a bar gauge 611 showing the fee paid to the rental company by the person who rented the excavator 100, and a bar gauge 612 showing the refund refunded to the person who rented the shovel 100 from the rental company. Is displayed. The bar gauge 612 representing the refund is displayed based on the fatigue degree (for example, cumulative damage degree, remaining life) calculated by the fatigue degree calculation process. For example, the bar gauge 612 representing the refund is displayed as a longer bar gauge as the cumulative damage degree of the attachment calculated by the fatigue degree calculation process is smaller than the reference cumulative damage degree.

最弱箇所表示部620は、アタッチメントの最弱箇所を特定する情報を表示する。図6の例では、最弱箇所表示部620には、アーム5の画像621、アーム5における最弱箇所を特定する画像622、ブーム4の画像623及びブーム4における最弱箇所を特定する画像624が表示されている。アーム5における最弱箇所及びブーム4における最弱箇所は、疲労度算出処理で算出される疲労度(例えば、累積損傷度、余寿命)の分布に基づいて表示される。例えば、アーム5における最弱箇所及びブーム4における最弱箇所は、疲労度算出処理で算出される累積損傷度の分布において累積損傷度が最も大きい箇所である。また、例えばアーム5における最弱箇所及びブーム4における最弱箇所は、疲労度算出処理で算出される余寿命の分布において余寿命が最も短い箇所である。なお、図6の例では、アーム5の画像621及びブーム4の画像622は左右に並んで表示されているが、これに限定されず、例えば上下に並んで表示されていてもよい。また、アーム5の画像621とブーム4の画像622のいずれか一方のみが表示されていてもよい。 The weakest part display unit 620 displays information for identifying the weakest part of the attachment. In the example of FIG. 6, the weakest part display unit 620 has an image 621 of the arm 5, an image 622 of specifying the weakest part of the arm 5, an image 623 of the boom 4, and an image 624 of specifying the weakest part of the boom 4. Is displayed. The weakest part of the arm 5 and the weakest part of the boom 4 are displayed based on the distribution of the fatigue degree (for example, cumulative damage degree, remaining life) calculated by the fatigue degree calculation process. For example, the weakest part in the arm 5 and the weakest part in the boom 4 are the parts having the largest cumulative damage degree in the distribution of the cumulative damage degree calculated by the fatigue degree calculation process. Further, for example, the weakest part in the arm 5 and the weakest part in the boom 4 are the parts having the shortest remaining life in the distribution of the remaining life calculated by the fatigue degree calculation process. In the example of FIG. 6, the image 621 of the arm 5 and the image 622 of the boom 4 are displayed side by side, but the present invention is not limited to this, and the image 621 may be displayed side by side, for example. Further, only one of the image 621 of the arm 5 and the image 622 of the boom 4 may be displayed.

累積損傷度表示部630は、アタッチメントの累積損傷度を表示する。図6の例では、累積損傷度表示部630には、現在のアーム5の累積損傷度を表すバーゲージ631及び現在のブーム4の累積損傷度を表すバーゲージ632が表示されている。アーム5の余寿命及びブーム4の余寿命は、疲労度算出処理で算出される累積損傷度の分布に基づいて表示される。例えば、現在のアーム5の累積損傷度及び現在のブーム4の累積損傷度は、それぞれ疲労度算出処理で算出される累積損傷度の分布における最も大きい累積損傷度であってもよく、平均値や中央値であってもよい。また、累積損傷度表示部630には、現在のアーム5の累積損傷度を表すバーゲージ631及び現在のブーム4の累積損傷度を表すバーゲージ632に重畳して、基準累積損傷度を表す画像が表示されていてもよい。基準累積損傷度を表す画像が表示されることにより、管理者は基準累積損傷度に対する現在の累積損傷度を容易に把握できる。 The cumulative damage degree display unit 630 displays the cumulative damage degree of the attachment. In the example of FIG. 6, the cumulative damage degree display unit 630 displays a bar gauge 631 indicating the cumulative damage degree of the current arm 5 and a bar gauge 632 indicating the cumulative damage degree of the current boom 4. The remaining life of the arm 5 and the remaining life of the boom 4 are displayed based on the distribution of the cumulative damage degree calculated by the fatigue degree calculation process. For example, the current cumulative damage degree of the arm 5 and the current cumulative damage degree of the boom 4 may be the largest cumulative damage degree in the distribution of the cumulative damage degree calculated by the fatigue degree calculation process, respectively, and may be an average value or an average value. It may be the median. Further, the cumulative damage degree display unit 630 displays an image showing the reference cumulative damage degree by superimposing it on the bar gauge 631 showing the cumulative damage degree of the current arm 5 and the bar gauge 632 showing the cumulative damage degree of the current boom 4. It may have been. By displaying an image showing the reference cumulative damage level, the administrator can easily grasp the current cumulative damage level with respect to the reference cumulative damage level.

以上に説明したように、一実施形態の管理システム300によれば、図6に示されるように、アタッチメントの累積損傷度と使用料金とが関連付けして表示される。これにより、管理者は、表示装置230の表示画面400に表示された情報に基づいて、ショベル100の使用状況に応じた使用料金を設定できる。例えば、管理者は、表示装置230の表示画面400に表示された所定期間(例えば、レンタル期間)におけるアタッチメントの累積損傷度が基準累積損傷度よりも大きい場合に、所定期間におけるアタッチメントの累積損傷度と基準累積損傷度との差に応じて、ショベル100の使用料金の一部を還付する還付金を設定できる。 As described above, according to the management system 300 of one embodiment, as shown in FIG. 6, the cumulative damage degree of the attachment and the usage fee are displayed in association with each other. As a result, the administrator can set the usage fee according to the usage status of the excavator 100 based on the information displayed on the display screen 400 of the display device 230. For example, when the cumulative damage degree of the attachment in the predetermined period (for example, the rental period) displayed on the display screen 400 of the display device 230 is larger than the reference cumulative damage degree, the administrator can perform the cumulative damage degree of the attachment in the predetermined period. A refund can be set to refund a part of the usage fee of the excavator 100 according to the difference between the standard cumulative damage and the standard cumulative damage level.

図6の事例では、予測される使用状況(作業内容、累積損傷度等)と実績とを対比させる事例である。図6の事例では、例えば、使用期間終了時点において、基準累積損傷度(例えば100%)に達しない場合(例えば60%)、使用料金を20%還付する事例である。つまり、使用開始時に想定される累積損傷度に達しない場合、未達の度合いに応じて使用料金を還付する事例である。余寿命(若しくは、累積損傷度)と補修費用と関連付けができることで、余寿命(若しくは、累積損傷度)と使用料金とも関連付けができる。作業内容と使用料金とが関連付けされてもよい。作業内容と保証期間とが関連付けされてもよい。 The case of FIG. 6 is a case of comparing the predicted usage situation (work content, cumulative damage degree, etc.) with the actual result. In the case of FIG. 6, for example, when the standard cumulative damage degree (for example, 100%) is not reached (for example, 60%) at the end of the usage period, the usage fee is refunded by 20%. In other words, if the cumulative damage level assumed at the start of use is not reached, the usage fee will be refunded according to the degree of non-delivery. By being able to associate the remaining life (or cumulative damage degree) with the repair cost, it is also possible to associate the remaining life (or cumulative damage degree) with the usage fee. The work content and the usage fee may be associated with each other. The work content and the warranty period may be associated.

なお、図6の例では、アタッチメントの累積損傷度と使用料金とを含む情報が管理装置200の表示装置230に表示される場合を示したが、本開示はこれに限定されず、例えばショベル100の表示装置40に表示されてもよい。また、管理装置200と通信ネットワークNWを通じて通信可能な他の装置に表示されてもよい。 In the example of FIG. 6, information including the cumulative damage degree of the attachment and the usage fee is displayed on the display device 230 of the management device 200, but the present disclosure is not limited to this, for example, the excavator 100. May be displayed on the display device 40 of. Further, it may be displayed on another device capable of communicating with the management device 200 through the communication network NW.

また、図6の例では、表示装置230の表示画面400に、アタッチメントの累積損傷度と使用料金とが関連付けされて表示される場合を示したが、本開示はこれに限定されず、例えばアタッチメントの余寿命と使用料金とが関連付けされて表示されてもよい。この場合、管理者は、表示装置230の表示画面400に表示されたアタッチメントの余寿命が基準余寿命よりも長い場合に、所定期間におけるアタッチメントの余寿命と基準余寿命との差に応じて、ショベル100の使用料金の一部を還付する還付金を設定できる。 Further, in the example of FIG. 6, the case where the cumulative damage degree of the attachment and the usage fee are displayed in association with each other on the display screen 400 of the display device 230 is shown, but the present disclosure is not limited to this, and for example, the attachment. The remaining life of the product and the usage fee may be displayed in association with each other. In this case, when the remaining life of the attachment displayed on the display screen 400 of the display device 230 is longer than the reference remaining life, the administrator determines the difference between the remaining life of the attachment and the reference remaining life in a predetermined period. A refund can be set to refund a part of the usage fee of the excavator 100.

また、表示画面600には日時、機番、使用者、これまでの使用時間(図示せず)が表示されてもよい。 Further, the date and time, the machine number, the user, and the past usage time (not shown) may be displayed on the display screen 600.

以上、本発明の好ましい実施形態について説明したが、本発明は、上述した実施形態に制限されることなく、本発明の範囲を逸脱することなしに上述した実施形態に種々の変更及び置換を加えることができる。 Although the preferred embodiments of the present invention have been described above, the present invention is not limited to the above-described embodiments, and various modifications and substitutions are made to the above-described embodiments without departing from the scope of the present invention. be able to.

例えば、管理システム300の表示装置として、携帯端末等の支援装置を利用してもよい。支援装置は、典型的には携帯端末装置であり、例えば、施工現場にいる作業者等が携帯するノートPC、タブレットPC、又はスマートフォン等である。支援装置は、ショベル100の操作者が携帯するコンピュータであってもよい。支援装置は、固定端末装置であってもよい。 For example, a support device such as a mobile terminal may be used as the display device of the management system 300. The support device is typically a mobile terminal device, for example, a notebook PC, a tablet PC, a smartphone, or the like carried by a worker or the like at a construction site. The support device may be a computer carried by the operator of the excavator 100. The support device may be a fixed terminal device.

100 ショベル
200 管理装置
210 制御装置
211 ショベル情報管理部
212 疲労度算出部
213 繁忙期情報管理部
214 保証内容決定部
230 表示装置
300 管理システム
400、500、600 表示画面
100 Excavator 200 Management device 210 Control device 211 Excavator information management unit 212 Fatigue calculation unit 213 Busy season information management unit 214 Guarantee content determination unit 230 Display device 300 Management system 400, 500, 600 Display screen

Claims (5)

評価対象のショベルの作動状態を検出する状態検出装置と、
前記検出された前記作動状態に基づき前記ショベルの疲労度を算出し、前記算出された前記疲労度と関連付けられた保証内容情報を算出する制御装置と、
前記算出された前記保証内容情報を表示する表示装置と、
を備える、ショベルの管理システム。
A state detection device that detects the operating state of the excavator to be evaluated, and
A control device that calculates the fatigue level of the excavator based on the detected operating state and calculates the guarantee content information associated with the calculated fatigue level.
A display device that displays the calculated warranty content information, and
Excavator management system with.
所定期間における評価対象のショベルの作動状態を検出する状態検出装置と、
前記検出された前記作動状態に基づき前記所定期間における前記ショベルの疲労度を算出し、前記算出された前記疲労度と関連付けられた費用情報を算出する制御装置と、
前記算出された前記費用情報を表示する表示装置と、
を備える、ショベルの管理システム。
A state detection device that detects the operating state of the excavator to be evaluated during a predetermined period, and
A control device that calculates the fatigue degree of the excavator in the predetermined period based on the detected operating state, and calculates the cost information associated with the calculated fatigue degree.
A display device that displays the calculated cost information and
Excavator management system with.
前記疲労度は、少なくとも余寿命及び累積損傷度のいずれか1つを含み、
前記表示装置には、前記余寿命が最も短い箇所又は前記累積損傷度が最も大きい箇所が表示される、
請求項1又は2に記載のショベルの管理システム。
The fatigue level includes at least one of the remaining life and the cumulative damage level.
The display device displays the portion having the shortest remaining life or the portion having the largest cumulative damage degree.
The excavator management system according to claim 1 or 2.
前記表示装置には、前記算出された前記疲労度が表示される、
請求項1乃至3のいずれか一項に記載のショベルの管理システム。
The calculated fatigue level is displayed on the display device.
The excavator management system according to any one of claims 1 to 3.
前記保証内容情報は、繁忙期情報に基づいて算出される、
請求項1に記載のショベルの管理システム。
The guarantee content information is calculated based on the busy season information.
The excavator management system according to claim 1.
JP2020054706A 2020-03-25 2020-03-25 excavator management system Active JP7460414B2 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
JP2020054706A JP7460414B2 (en) 2020-03-25 2020-03-25 excavator management system
CN202110319920.XA CN113445566B (en) 2020-03-25 2021-03-25 Management system for excavator
JP2024008026A JP2024028566A (en) 2020-03-25 2024-01-23 excavator management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020054706A JP7460414B2 (en) 2020-03-25 2020-03-25 excavator management system

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2024008026A Division JP2024028566A (en) 2020-03-25 2024-01-23 excavator management system

Publications (2)

Publication Number Publication Date
JP2021155930A true JP2021155930A (en) 2021-10-07
JP7460414B2 JP7460414B2 (en) 2024-04-02

Family

ID=77809324

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2020054706A Active JP7460414B2 (en) 2020-03-25 2020-03-25 excavator management system
JP2024008026A Pending JP2024028566A (en) 2020-03-25 2024-01-23 excavator management system

Family Applications After (1)

Application Number Title Priority Date Filing Date
JP2024008026A Pending JP2024028566A (en) 2020-03-25 2024-01-23 excavator management system

Country Status (2)

Country Link
JP (2) JP7460414B2 (en)
CN (1) CN113445566B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114910122A (en) * 2022-04-15 2022-08-16 中国矿业大学 Detection system and detection method for crack symptoms of structural member and excavator
JP7488932B1 (en) 2023-03-27 2024-05-22 日立建機株式会社 Work Machine

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002138515A (en) * 2000-11-01 2002-05-14 Kobelco Contstruction Machinery Ltd Rental service method, device and system for construction machine
JP2012233336A (en) * 2011-04-28 2012-11-29 Hitachi Constr Mach Co Ltd Operating machine and maintenance inspection information generating device
JP2014085293A (en) * 2012-10-26 2014-05-12 Sumitomo Heavy Ind Ltd Loading shovel management device, and loading shovel management method
US20140244101A1 (en) * 2011-09-20 2014-08-28 Tech Mining Pty Ltd Stress and/or accumulated damage monitoring system
JP2015190114A (en) * 2014-03-27 2015-11-02 住友重機械工業株式会社 shovel support device and shovel
WO2020013252A1 (en) * 2018-07-10 2020-01-16 住友重機械工業株式会社 Display method for construction machine and assistance device for construction machine

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4689136B2 (en) * 2000-03-31 2011-05-25 日立建機株式会社 Method for detecting actual operation time of work machine deployed at work site, data collection / management system, and base station
CN1954122B (en) * 2004-04-28 2010-12-08 株式会社小松制作所 Maintenance support system for construction machine
JP6320185B2 (en) * 2014-06-16 2018-05-09 住友重機械工業株式会社 Excavator support device
JP2016023489A (en) * 2014-07-23 2016-02-08 住友重機械工業株式会社 Shovel assisting device and shovel management method
CA2971748C (en) * 2014-12-24 2022-08-30 Cqms Pty Ltd A system and method of estimating fatigue in a lifting member
KR20180009874A (en) * 2016-07-20 2018-01-30 현대중공업 주식회사 Apparatus for measuring fatigue of construction machinery

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002138515A (en) * 2000-11-01 2002-05-14 Kobelco Contstruction Machinery Ltd Rental service method, device and system for construction machine
JP2012233336A (en) * 2011-04-28 2012-11-29 Hitachi Constr Mach Co Ltd Operating machine and maintenance inspection information generating device
US20140052299A1 (en) * 2011-04-28 2014-02-20 Hitachi Construction Machinery Co., Ltd. Operating machine and maintenance and inspection information generating apparatus
US20140244101A1 (en) * 2011-09-20 2014-08-28 Tech Mining Pty Ltd Stress and/or accumulated damage monitoring system
JP2014085293A (en) * 2012-10-26 2014-05-12 Sumitomo Heavy Ind Ltd Loading shovel management device, and loading shovel management method
JP2015190114A (en) * 2014-03-27 2015-11-02 住友重機械工業株式会社 shovel support device and shovel
WO2020013252A1 (en) * 2018-07-10 2020-01-16 住友重機械工業株式会社 Display method for construction machine and assistance device for construction machine
US20210158409A1 (en) * 2018-07-10 2021-05-27 Sumitomo Heavy Industries, Ltd. Information output method and assist device for construction machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114910122A (en) * 2022-04-15 2022-08-16 中国矿业大学 Detection system and detection method for crack symptoms of structural member and excavator
JP7488932B1 (en) 2023-03-27 2024-05-22 日立建機株式会社 Work Machine

Also Published As

Publication number Publication date
JP2024028566A (en) 2024-03-04
CN113445566A (en) 2021-09-28
CN113445566B (en) 2022-12-27
JP7460414B2 (en) 2024-04-02

Similar Documents

Publication Publication Date Title
JP2024028566A (en) excavator management system
WO2018062363A1 (en) Shovel
KR20170053909A (en) Load weighing method and system for wheel loader
JP7387583B2 (en) Construction machinery support devices and support systems
JP6605291B2 (en) Control parameter change system for construction machinery
JP7234398B2 (en) motion identification device
CN114127745A (en) Work information generation system and work information generation method for construction machine
WO2021064776A1 (en) Fatigue management system
WO2019117166A1 (en) Shovel machine
US20210158409A1 (en) Information output method and assist device for construction machine
US10900197B2 (en) Work machine management apparatus
JP7073146B2 (en) Construction machinery, display equipment for construction machinery, and management equipment for construction machinery
US20220154424A1 (en) Construction machine, display apparatus of construction machine, and management apparatus of construction machine
JP7401696B2 (en) Work machine condition management device
JP2021155995A (en) Shovel support device, shovel management device
JP5025237B2 (en) Machine total information management device
WO2021019949A1 (en) System for determining content of work performed by construction machine and method for determining work
JP6163126B2 (en) Construction machine operating state recording apparatus and operating state recording method
JP7257430B2 (en) Excavators and systems for excavators
JP7500241B2 (en) Machinery management system
US20140172127A1 (en) Instrument System with Portable Computing Device
JP2022146689A (en) Excavator, excavator display device, and excavator management device
JP2023061194A (en) Shovel, shovel management system, and shovel management device
KR20240042101A (en) Systems, methods, and working machines for working machines

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20221214

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230712

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230718

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230829

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20231024

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240123

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20240130

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240227

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240321

R150 Certificate of patent or registration of utility model

Ref document number: 7460414

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150