JP2018180662A - Material receiving inspection system - Google Patents

Material receiving inspection system Download PDF

Info

Publication number
JP2018180662A
JP2018180662A JP2017074989A JP2017074989A JP2018180662A JP 2018180662 A JP2018180662 A JP 2018180662A JP 2017074989 A JP2017074989 A JP 2017074989A JP 2017074989 A JP2017074989 A JP 2017074989A JP 2018180662 A JP2018180662 A JP 2018180662A
Authority
JP
Japan
Prior art keywords
construction
data
materials
inspection system
image data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2017074989A
Other languages
Japanese (ja)
Inventor
利彰 安井
Toshiaki Yasui
利彰 安井
祐二 新井
Yuji Arai
祐二 新井
嵩弓 今井
Takayumi Imai
嵩弓 今井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP2017074989A priority Critical patent/JP2018180662A/en
Publication of JP2018180662A publication Critical patent/JP2018180662A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Length Measuring Devices By Optical Means (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve receiving inspection about the quantity and dimensions and traceability of a material for use in building a construction structure, or the like in a process from manufacturing to building through introduction.SOLUTION: A material receiving inspection system comprises: three-dimensional image data acquisition means 10 which acquires three-dimensional image data of materials; and material data generation means 20 which performs deep learning on the basis of the acquired three-dimensional data to generate material data including at least a type, dimensions and a quantity of each of the materials. The material data is generated at least either when manufacturing the materials or when receiving the materials.SELECTED DRAWING: Figure 3

Description

本発明は、資材の検収システムに関するものであり、詳しくは、3Dカメラ等を用いて撮影した画像データを利用して、建設構造物の施工に用いる資材等の数量や寸法の検収や、トレーサビリティの向上を図るためのシステムに関するものである。   The present invention relates to a material inspection system, and more specifically, inspection of the quantity and dimensions of materials used for construction of a construction structure, and traceability, using image data captured using a 3D camera or the like. It relates to a system for improving.

建設構造物を施工するための資材をはじめとして、その他各種の資材の管理は人手や時間を要する作業であった。例えば、建設構造物を施工するための資材を工場で作製する際、工事現場に受け入れる際には、建設現場の職員立ち会いのもと、目視や計測等によって出来形、数量及び品質を確認している。また、このような資材を用いて建設構造物を施工する際には、図面上の適切な位置に資材を設置して、設置した資材に関する情報を管理、記録している   Management of various other materials, including materials for constructing construction structures, was a labor-intensive and time-consuming task. For example, when manufacturing materials for construction of a construction structure at a factory, when accepting it at a construction site, confirm the finished form, quantity and quality by visual inspection or measurement with the staff present at the construction site. There is. In addition, when constructing a construction structure using such materials, the materials are installed at appropriate positions on the drawing, and information on the installed materials is managed and recorded.

従来、資材の検収及びトレーサビリティを適切に管理して、人為的ミスをなくすようにした技術が種々開示されている(以下に示す各特許文献参照)。   Heretofore, various techniques for appropriately managing material inspection and traceability to eliminate human error have been disclosed (refer to patent documents shown below).

特許文献1には、コンクリート製品のトレーサビリティを確立することにより、製作や据え付けのプロセスを改善して、個々の製品の維持管理を効率的に行うことを目的とした技術が開示されている。特許文献1に記載されたコンクリート製品統合管理システムは、二次元コードおよびICタグを備えた管理用タグをコンクリート製品に固定する。また、個々のコンクリート製品ごとの各種情報(製作・据え付けのプロセスや維持管理に関する情報)をデータベースに格納しておく。そして、コンクリート製品に付した二次元コード及びICタグから情報を読み取り、データベースに格納した情報との照合を行って、コンクリート製品のトレーサビリティを確立するとしている。   Patent Document 1 discloses a technique aimed at efficiently performing maintenance and management of individual products by improving the manufacturing and installation processes by establishing traceability of concrete products. The concrete product integrated management system described in Patent Document 1 fixes a management tag provided with a two-dimensional code and an IC tag to a concrete product. In addition, various information for each concrete product (information about the process of production and installation and maintenance and management) is stored in the database. Then, information is read from the two-dimensional code attached to the concrete product and the IC tag, and comparison with the information stored in the database is performed to establish the traceability of the concrete product.

特許文献2には、現場合わせ作業や現場加工作業をなくすことにより、工数や労務費を抑制し、建築廃棄物をゼロにするとともに、既存建築物のデータを効率よく整理し、墨出しの手間を軽減し、人的ミスの発生を防止することを目的とした技術が開示されている。特許文献2に記載された建築生産システムは、建築物の既存部分の電子化データを3次元CADデータに変換して、3次元レーザースキャナにより取得された点群データや、該点群データから作成された3次元ポリゴンモデルなどの各種現場調査データとともに格納する既存部分調査手段と、3次元ポリゴンモデルに対して新たに施工される部材オブジェクトを配置する施工部材設計手段と、部材工場でプレカットされた部材に取り付けられた電子タグをIDリーダで読み取ることにより得られた部材オブジェクトをその施工位置情報と共に3次元CADモデルから検索して出力する部材施工位置出力手段と、部材施工位置出力手段により出力された部材オブジェクトの施工位置情報に基づき、既存部分における部材の施工位置を指し示す自動位置指示装置とを備えている。   In patent document 2, while eliminating man-hours and labor costs and eliminating construction waste by eliminating on-site setting work and on-site processing work, efficiently organizing data of existing buildings, time and effort of drawing out ink Technology aimed at reducing the risk of human error and preventing the occurrence of human error is disclosed. The building production system described in Patent Document 2 converts the digitized data of the existing part of the building into three-dimensional CAD data, and creates it from point cloud data acquired by the three-dimensional laser scanner and the point cloud data. The existing part surveying means stored together with various field survey data such as the 3D polygon model and the like, the construction member design means for arranging the member object newly constructed for the 3D polygon model, and the precut in the member factory A member construction position output unit that searches and outputs a member object obtained by reading an electronic tag attached to a member with an ID reader along with its construction position information from a three-dimensional CAD model, and is output by the member construction position output unit Based on the construction position information of the member object, the self position indicating the construction position of the member in the existing part And a pointing device.

特許文献3には、ICタグ等を付すことができない流動物(例えば、生コンクリート)等のトレーサビリティを向上させるための技術が開示されている。特許文献3に記載されたトレーサビリティシステムは、製品等の運搬物に直接ICタグ等を付するのではなく、運搬物の受け渡しを行う設備間で運搬物に関する管理情報の受け渡しを行うことにより、運搬物の流通履歴を管理するようになっている。   Patent Document 3 discloses a technique for improving the traceability of a fluid (eg, fresh concrete) to which an IC tag or the like can not be attached. The traceability system described in Patent Document 3 does not directly attach an IC tag or the like to a transported object such as a product, but transfers the management information regarding the transported object between facilities that deliver the transported object. It is designed to manage the distribution history of goods.

特開2006−243918号公報JP, 2006-243918, A 特開2013−149119号公報JP, 2013-149119, A 特開2011−39992号公報JP, 2011-39992, A

上述したように、例えば、建設構造物を施工するためには多種多様の資材が必要であり、これらの資材を施工現場へ搬入する場合には、その都度、数量や寸法の検収及びその後の数量管理に多大な労力や時間を要する。このため、種々の技術が提案されているが、ICタグや二次元コードを用いた場合には、施工後の資材を確認するために、ICタグ等から情報を読み取らなければならず、省力化が図られているとは言い難かった。   As mentioned above, for example, in order to construct a construction structure, a wide variety of materials are required, and when these materials are carried to the construction site, inspection of the quantity and size and the subsequent quantity each time It takes a lot of effort and time to manage. For this reason, various techniques have been proposed, but in the case of using an IC tag or a two-dimensional code, it is necessary to read information from the IC tag or the like in order to confirm the material after construction. It was hard to say that

また、運搬物の受け渡しを行う設備間で運搬物に関する管理情報の受け渡しを行う技術では、その施工位置等について総合的に管理できるとは言い難かった。   Moreover, in the technique which delivers the management information regarding a conveyance thing between the facilities which deliver a conveyance thing, it was hard to say that it can manage comprehensively about the construction position etc.

本発明は、上述した事情に鑑み提案されたもので、建設構造物を施工するための資材等について、製造から搬入及び施工に至るまでの過程において、資材の数量や寸法の検収や、トレーサビリティの向上を図ることが可能なシステムを提供することを目的とする。   The present invention has been proposed in view of the above-mentioned circumstances, and regarding materials and the like for constructing a construction structure, inspection of the quantity and size of materials, traceability, etc. in the process from production to delivery and construction. An object is to provide a system that can be improved.

本発明に係る資材の検収システムは、上述した目的を達成するため、以下の特徴点を有している。すなわち、本発明に係る資材の検収システムは、三次元画像データ取得手段及び資材データ生成手段を主要な構成要素としている。また、施工条件データ取得手段、施工管理データ生成手段、施工位置指示手段を備えることが可能である。   The material inspection system according to the present invention has the following features in order to achieve the above-described object. That is, the inspection system for materials according to the present invention mainly includes three-dimensional image data acquisition means and material data generation means. In addition, it is possible to include a construction condition data acquisition unit, a construction management data generation unit, and a construction position instruction unit.

三次元画像データ取得手段は、資材の三次元画像データを取得するための手段である。資材データ生成手段は、取得した三次元画像データに基づきディープラーニングを行い、各資材について、少なくとも種類、寸法、数量を含む資材データを生成するための手段である。この資材データ生成手段による資材データの生成は、資材の製造時または受け入れ時の少なくとも一方で実施することが可能である。   The three-dimensional image data acquisition means is a means for acquiring three-dimensional image data of the material. The material data generation means is a means for performing deep learning based on the acquired three-dimensional image data, and generating material data including at least the type, size, and quantity of each material. The generation of the material data by the material data generation means can be performed at least at one of the time of manufacture or reception of the material.

施工条件データ取得手段は、施工対象の施工に必要な資材に関する施工条件データを取得するための手段である。施工管理データ生成手段は、資材データ生成手段により生成した資材データに基づき、各資材について、少なくとも施工位置、在庫数を含む施工管理データを生成するための手段である。施工位置指示手段は、施工管理データに基づいて、資材の施工位置を指示するための手段である。   The construction condition data acquisition means is a means for acquiring construction condition data regarding materials necessary for construction of a construction target. The construction management data generation means is a means for generating construction management data including at least the construction position and the number of stocks for each material based on the material data generated by the material data generation means. The construction position designating means is a means for designating the construction position of the material based on the construction management data.

本発明に係る資材の検収システムでは、3Dカメラ等を用いて取得した資材の三次元画像データに基づいて、資材の種類、寸法、数量等のデータを把握することができるので、資材に貼付したり埋め込んだりしたICタグからデータを読み取る作業等を行う必要がなく、検収作業の手間を大幅に省力化することができる。   In the material inspection system according to the present invention, data such as the type, size, and quantity of the material can be grasped based on the three-dimensional image data of the material acquired using the 3D camera etc. There is no need to read data from the embedded IC tag or the like, and it is possible to save labor for inspection work.

すなわち、本発明に係る資材の検収システムによれば、建設構造物を施工するための資材等について、製造から搬入及び施工に至るまでの過程において、資材の数量や寸法の検収や、トレーサビリティの向上を図ることが可能となる。また、資材の施工位置の指示についても、機械学習した資材データを用いているので、正確かつ適切な資材管理を行うことができる。   That is, according to the inspection system for materials according to the present invention, with regard to materials and the like for constructing a construction structure, inspection of quantities and dimensions of materials and improvement of traceability in the process from manufacturing to delivery and construction It is possible to In addition, since the machine-learned material data is used also for the instruction of the construction position of the material, accurate and appropriate material management can be performed.

本発明の実施形態に係る資材の検収システムの構成を示すブロック図。The block diagram showing the composition of the inspection system of the materials concerning the embodiment of the present invention. 資材の三次元画像データの取得を示す説明図。Explanatory drawing which shows acquisition of three-dimensional image data of material. 資材の検収及びトレーサビリティの手順を示すフローチャート。The flowchart which shows the procedure of inspection and traceability of materials.

以下、図面を参照して、本発明の実施形態に係る資材の検収システムを説明する。図1〜図3は本発明の実施形態に係る資材の検収システムを説明するもので、図1はシステム構成を示すブロック図、図2は資材の三次元画像データの取得を示す説明図、図3は資材の検収及びトレーサビリティの手順を示すフローチャートである。   Hereinafter, a material inspection system according to an embodiment of the present invention will be described with reference to the drawings. 1 to 3 illustrate a material inspection system according to an embodiment of the present invention. FIG. 1 is a block diagram showing a system configuration, and FIG. 2 is an explanatory view showing acquisition of three-dimensional image data of material. 3 is a flowchart showing the procedure of material acceptance and traceability.

<資材の検収システムの概要>
本発明の実施形態に係る資材の検収システムは、建設構造物の施工に使用する資材等について、その検収及びトレーサビリティを向上させるためのシステムに関するものである。建設構造物の施工に使用する資材とは、例えば、プレキャスト部材や鉄筋のことであり、これらの資材を3Dカメラ等により撮像し、撮像した三次元画像データに基づきディープラーニングを行うことにより、各資材について、種類、寸法、数量等のデータを含む資材データを生成する。資材データは、施工現場における受け入れ時に生成してもよいし、工場製品の場合には製造時に生成してもよい。
<Overview of material inspection system>
The material inspection system according to the embodiment of the present invention relates to a system for improving the inspection and traceability of materials used for construction of a construction structure. Materials used for construction of a construction structure are, for example, precast members and reinforcing bars, and these materials are imaged by a 3D camera or the like, and deep learning is performed based on the imaged three-dimensional image data. For materials, generate material data including data such as type, size, and quantity. Material data may be generated upon receipt at the construction site or may be generated at the time of manufacture in the case of a factory product.

<資材の検収システムの構成>
本発明の実施形態に係る資材の検収システムは、三次元画像データに基づいて生成した資材データを、資材の検収やトレーサビリティに使用することにより、検収やトレーサビリティに関わる職員の労力を軽減するとともに、正確性を確保するため、図1に示すように、三次元画像データ取得手段10と、資材データ生成手段20とを備えている。また、これらの手段に加えて、施工条件データ取得手段30と、施工管理データ生成手段40と、施工位置指示手段50とを備えていてもよい。
<Configuration of material inspection system>
The material inspection system according to the embodiment of the present invention uses the material data generated based on the three-dimensional image data for material inspection and traceability, thereby reducing the labor of staff involved in the inspection and traceability. In order to ensure accuracy, as shown in FIG. 1, a three-dimensional image data acquisition unit 10 and a material data generation unit 20 are provided. Further, in addition to these means, construction condition data acquisition means 30, construction management data generation means 40, and construction position indication means 50 may be provided.

以下、各手段について説明する。なお、各手段は、光学機器や電子機器及びその付属装置と、コンピュータに読み込まれることにより、ハードウェア資源と協働して機能を発揮するソフトウェアと、これと同等の機能を実現することが可能な論理回路等のことをいう。   Each means will be described below. In addition, each means can realize software and a function equivalent to this in cooperation with hardware resources by being read into an optical device, an electronic device and its accessory device, and a computer. Logic circuit and so on.

<三次元画像データ取得手段>
三次元画像データ取得手段10は、資材の三次元画像データを取得するための手段であり、例えば、図2に示すように、3Dカメラにより構成することができる。3Dカメラは、2眼撮像方式であってもよいし、偏光子を用いた単眼撮像方式であってもよい。三次元画像データ取得手段10で取得した三次元画像データは、RAM等の一時記憶領域に記憶して、資材データの生成に使用する。
<Three-dimensional image data acquisition means>
The three-dimensional image data acquisition means 10 is a means for acquiring three-dimensional image data of a material, and can be configured by, for example, a 3D camera as shown in FIG. The 3D camera may be a binocular imaging system or a monocular imaging system using a polarizer. The three-dimensional image data acquired by the three-dimensional image data acquisition means 10 is stored in a temporary storage area such as a RAM and used for generating material data.

<資材データ生成手段>
資材データ生成手段20は、取得した三次元画像データに基づきディープラーニングを行い、各資材について、少なくとも種類、寸法、数量を含む資材データを生成するための手段であり、例えば、画像認識を行うためのプログラムとこれをインストールしたコンピュータからなる。
<Material data generation means>
The material data generation means 20 is a means for performing deep learning based on the acquired three-dimensional image data, and generating material data including at least a type, a size, and a quantity for each material, for example, to perform image recognition. Programs and a computer with this installed.

資材データ生成手段20では、取得した三次元画像データを画像認識するとともにディープラーニングを行うことにより、各資材の種類、寸法、数量を認識して資材データを生成する。資材データは、種類、寸法、数量に限られず、さらに、資材を区別するための他のデータ(例えば、色彩、模様、材質等)を含んでいてもよい。資材データ生成手段20で生成した資材データは、HDD等の記憶手段に記憶して、資材データの管理に使用する。   The material data generation means 20 recognizes the type, size, and quantity of each material and generates material data by performing image recognition on the acquired three-dimensional image data and performing deep learning. The material data is not limited to the type, size, and quantity, and may further include other data (for example, color, pattern, material, etc.) for distinguishing materials. The material data generated by the material data generation means 20 is stored in a storage means such as an HDD and used for managing the material data.

<施工条件データ取得手段>
施工条件データ取得手段30は、建設構造物の施工に必要な資材に関する施工条件データを取得するための手段である。施工条件データは、施工対象となる建設構造物等について、必要となる各資材の種類、寸法、数量等に関するデータである。施工条件データは、必要となる資材に関する種類、寸法、数量だけではなく、資材を区別するための他のデータ(例えば、色彩、模様、材質等)を含んでいてもよい。
<Construction condition data acquisition means>
The construction condition data acquisition means 30 is a means for acquiring construction condition data regarding materials necessary for construction of a construction structure. The construction condition data is data relating to the type, size, quantity, and the like of each material required for the construction structure to be constructed. The construction condition data may include not only the type, size, and quantity of the required material, but also other data (eg, color, pattern, material, etc.) for distinguishing the material.

施工条件データ記憶手段60は、施工条件データ取得手段30で取得する施工条件データを記憶するための手段であり、例えば、HDDやSDD等の大容量記憶装置により構成することができる。なお、施工条件データ記憶手段60は、サーバーの機能手段として構成することが好ましく、例えば、クラウドサーバー上に設置される。   The construction condition data storage unit 60 is a unit for storing construction condition data acquired by the construction condition data acquisition unit 30, and can be configured by, for example, a large-capacity storage device such as an HDD or an SDD. The construction condition data storage unit 60 is preferably configured as a functional unit of the server, and is installed on, for example, a cloud server.

本実施形態では、クラウドサーバー上に設置された施工条件データ記憶手段60に、施工対象となる各建設構造物の施工条件データを記憶しておき、インターネット、公衆電話回線、専用データ通信回線、無線LAN回線、有線LAN回線等の電子通信回線を単独でまたは組み合わせて使用することにより、クラウドサーバーにアクセスして、所望の施工条件データを受信し、あるいは施工条件データに変更を加えることができる。   In the present embodiment, the construction condition data of each construction structure to be constructed is stored in the construction condition data storage means 60 installed on the cloud server, and the Internet, public telephone line, dedicated data communication line, wireless By using an electronic communication line such as a LAN line or a wired LAN line alone or in combination, it is possible to access a cloud server, receive desired construction condition data, or change the construction condition data.

<施工管理データ生成手段>
施工管理データ生成手段40は、資材データ生成手段20により生成した資材データ及び施工条件データ取得手段30により取得した施工条件データに基づき、各資材について、少なくとも種類、在庫数、施工位置を含む施工管理データを生成するための手段である。施工管理データは、各資材の管理を行うためのデータであり、資材を区別するための他のデータ(例えば、色彩、模様、材質等)を含んでいてもよい。施工管理データ生成手段40で生成した施工管理データは、HDD等の記憶手段に記憶して、資材の施工管理に使用する。
<Construction management data generation means>
The construction management data generation unit 40 performs construction management including at least the type, the number of stocks, and the construction position for each material based on the material data generated by the material data generation unit 20 and the construction condition data acquired by the construction condition data acquisition unit 30. It is a means to generate data. The construction management data is data for managing each material, and may include other data (for example, color, pattern, material, etc.) for distinguishing the materials. The construction management data generated by the construction management data generation unit 40 is stored in a storage unit such as an HDD and used for material construction management.

<施工位置指示手段>
施工位置指示手段50は、施工管理データ生成手段40で生成した施工管理データに基づいて、資材の施工位置を指示するための手段であり、例えば、データ分析を行うためのプログラムとこれをインストールしたコンピュータからなる。施工位置を指示するには、例えば、AR(拡張現実)、MR(複合現実)、VR(仮想現実)等の技術を用いて、利用者が装着したデバイスや表示装置の表示画面に各資材の施工位置(施工すべき場所、向き等)を表示すればよい。また、プロジェクションマッピングの技術を用いて、実際の施工場所に対して資材の施工位置を投影してもよい。
<Construction position indication means>
The construction position designating means 50 is a means for designating the construction position of the material based on the construction management data generated by the construction management data generating means 40, and for example, a program for performing data analysis and this are installed It consists of a computer. In order to indicate the construction position, for example, the technology of AR (Augmented Reality), MR (Mixed Reality), VR (Virtual Reality), etc. is used to display on the display screen of the device or display device worn by the user. The position of construction (place to be constructed, direction, etc.) may be displayed. Also, projection mapping techniques may be used to project the construction position of the material relative to the actual construction site.

<表示手段>
図1に示すように、本実施形態に係る資材の検収システムでは、ビデオ信号の表示制御を行う表示制御手段70と、各種のデータを表示するための液晶表示装置等からなる表示手段80とを備えている。資材データ、施工管理データ、施工位置指示データ、資材維持管理データは、表示手段80により、作業者や監督者等が視認可能となるように表示することができる。この表示制御手段70及び表示手段80は、コンピュータ及びその付属機器により構成することができる。
<Display means>
As shown in FIG. 1, in the material inspection system according to the present embodiment, a display control means 70 for controlling display of a video signal, and a display means 80 comprising a liquid crystal display device for displaying various data, etc. Have. The material data, the construction management data, the construction position instruction data, and the material maintenance management data can be displayed by the display unit 80 so that the operator or the supervisor can visually recognize. The display control means 70 and the display means 80 can be configured by a computer and its attached devices.

資材データ、施工管理データ、施工位置指示データ等の各種データを表示手段80の表示画面に表示することにより、作業者や監督者が各種データを把握することができる。また、各種データは、所定のテンプレートに適用し、プリンタを用いて印刷してもよい。これにより、資材の検収及びトレーサビリティに関する帳票類を自動的に作成することができる。   By displaying various data such as material data, construction management data, and construction position instruction data on the display screen of the display means 80, the operator or supervisor can grasp the various data. Further, various data may be applied to a predetermined template and printed using a printer. As a result, it is possible to automatically create forms relating to material inspection and traceability.

<資材の検収及びトレーサビリティ>
本実施形態に係る資材の検収システムを用いて、資材の検収を行う手順及びトレーサビリティについて説明する。なお、以下の説明では、プレキャスト部材や鉄筋等のように工場で生産した資材や、その他の施工資材を施工現場に搬入する際の具体的な検収及びトレーサビリティについて説明する。
<Material inspection and traceability>
The procedure and traceability which inspect the material using the inspection system of the material concerning this embodiment are explained. In the following description, specific inspection and traceability at the time of carrying in a construction site materials such as pre-cast members and rebars and other construction materials produced in a factory will be described.

<モデルデータの取得>
図3に示すように、施工条件データ取得手段30の機能により、施工対象の図面や施工計画書のデータ、資材データ等からなるモデルデータを取得する(S3)。なお、最初にモデルデータを取得するとしているが、資材の検収を行うだけであれば、資材の三次元画像データを取得してディープラーニングを行い、各資材の資材データを生成すればよい(S1、S2)。
<Acquisition of model data>
As shown in FIG. 3, model data consisting of drawings of a construction object, data of a construction plan, material data and the like is acquired by the function of the construction condition data acquisition means 30 (S3). In addition, although it is said that model data is acquired first, if only inspection of materials is performed, three-dimensional image data of materials may be acquired and deep learning may be performed to generate material data of each material (S1 , S2).

<製造時における資材の検収>
図3に示すように、資材がプレキャスト部材や鉄筋等工場製品である場合には、三次元データ取得手段(3Dカメラ)の機能により、資材の3D写真(3次元空間情報)を撮影する(S1)。続いて、資材データ生成手段20の機能により、撮影した3D写真に基づいてディープラーニングを行い、各資材の資材データ(種類、寸法、数量等)を生成する(S2)。続いて、施工管理データ生成手段40の機能により、生成した資材データ及び取得した施工条件データに基づいて、各資材の施工管理データ(種類、在庫数、施工位置等)を生成する(S4)。
<Inspection of materials at the time of manufacture>
As shown in FIG. 3, when the material is a factory product such as a precast member or a reinforcing bar, a 3D photograph (three-dimensional space information) of the material is photographed by the function of the three-dimensional data acquisition means (3D camera) (S1) ). Subsequently, deep learning is performed based on the photographed 3D photograph by the function of the material data generation means 20, and material data (type, size, quantity, etc.) of each material is generated (S2). Subsequently, construction management data (type, number of stocks, construction position, etc.) of each material is generated based on the generated material data and the acquired construction condition data by the function of the construction management data generation means 40 (S4).

<施工現場における資材の検収及び施工位置の指示>
資材が施工現場に搬入されたら、製造時と同様に、三次元データ取得手段(3Dカメラ)の機能により、資材の3D写真(3次元空間情報)を撮影し(S1)、資材データ生成手段20の機能により、撮影した3D写真に基づいてディープラーニングを行い、各資材の資材データ(種類、寸法、数量等)を生成する(S2)。資材の搬入が完了したら、施工位置指示手段50の機能により、施工管理データに基づいて、各資材の施工位置を指示する(S5)。例えば、AR(拡張現実)、MR(複合現実)、VR(仮想現実)等の技術を用い、あるいはプロジェクションマッピングの技術を用いて、各資材の施工位置を指示することができる。
<Inspection of materials at construction site and indication of construction position>
When the material is carried to the construction site, the 3D photograph (three-dimensional space information) of the material is photographed by the function of the three-dimensional data acquisition means (3D camera) in the same manner as at the time of manufacturing (S1). Deep learning is performed based on the photographed 3D photograph by the function of to generate material data (type, size, quantity, etc.) of each material (S2). When the loading of the material is completed, the construction position of each material is instructed by the function of the construction position instruction means 50 based on the construction management data (S5). For example, using a technique such as AR (Augmented Reality), MR (Mixed Reality), VR (Virtual Reality) or the like, or using a technique of projection mapping, the construction position of each material can be indicated.

<従来技術と比較した有利な効果>
本発明に係る資材の検収システムでは、撮影した資材の3D写真をディープラーニングにより分析することで、従来の手法において個別化していた作業(写真撮影、寸法計測、数量確認、各種のデータ整理等)について、最初の計測を除いて自動化されるので、その後のトレーサビリティも容易になる。すなわち、作業の自動化による省力化および時間短縮を図ることができ、在庫管理が自動化されるので作業が簡略化され、資材データと図面等のデータを連動させることにより、資材の使用位置を指示することができるため、誤った資材の使用などの手戻りを無くすことができる。
<Advantages compared to the prior art>
The material inspection system according to the present invention analyzes the photographed 3D photograph of the material by deep learning, and the work (individual photography, dimension measurement, quantity confirmation, various data arrangement, etc.) individually performed in the conventional method Because it is automated except for the first measurement, its subsequent traceability also becomes easier. In other words, labor saving and time reduction can be achieved by automation of work, and inventory management is automated, so work is simplified, and the use position of materials is indicated by interlocking material data and data such as drawings. It is possible to eliminate rework such as using the wrong material.

また、AR(拡張現実)、MR(複合現実)、VR(仮想現実)、プロジェクションマッピング等の技術を用いることにより、資材の使用位置を視覚化することができるので、資材の維持管理を容易に行うことができる。さらに、プレキャスト部材などのように同一形状の資材(製品)を取り扱う場合には、資材の使用位置の判別が困難になるため、日々の進捗や工程等のデータ入力が必要不可欠となっていたが、本発明に係る資材の検収システムを用いることにより、従来、人手により行っていた種々の作業を自動化することができる。   In addition, by using technologies such as AR (Augmented Reality), MR (Mixed Reality), VR (Virtual Reality), and projection mapping, it is possible to visualize the use position of materials, making it easy to maintain and manage materials. It can be carried out. Furthermore, when handling materials (products) of the same shape, such as pre-cast members, it is difficult to determine the use position of the materials, so data input such as daily progress and processes has become essential. By using the material inspection system according to the present invention, various operations conventionally performed manually can be automated.

10 三次元画像データ取得手段
20 資材データ生成手段
30 施工条件データ取得手段
40 施工管理データ生成手段
50 施工位置指示手段
60 施工条件データ記憶手段
70 表示制御手段
80 表示手段
10 Three-Dimensional Image Data Acquisition Means 20 Material Data Generation Means 30 Construction Condition Data Acquisition Means 40 Construction Management Data Generation Means 50 Construction Position Indication Means 60 Construction Condition Data Storage Means 70 Display Control Means 80 Display Means

Claims (4)

資材の三次元画像データを取得する三次元画像データ取得手段と、
前記取得した三次元画像データに基づきディープラーニングを行い、各資材について、少なくとも種類、寸法、数量を含む資材データを生成する資材データ生成手段と、
を備えたことを特徴とする資材の検収システム。
3D image data acquisition means for acquiring 3D image data of materials;
Material data generating means for performing deep learning based on the acquired three-dimensional image data and generating material data including at least the type, size, and quantity of each material;
Material inspection system characterized by having.
前記資材データ生成手段による前記資材データの生成は、資材の製造時または受け入れ時の少なくとも一方で実施することを特徴とする請求項1に記載の資材の検収システム。   The material inspection system according to claim 1, wherein the generation of the material data by the material data generation means is performed at least at one of manufacturing time and receiving time of the material. 施工対象となる建設構造物の施工に必要な資材に関する施工条件データを取得する施工条件データ取得手段と、
前記資材データ生成手段により生成した資材データ及び前記施工条件データ取得手段により取得した施工条件データに基づき、各資材について、少なくとも種類、在庫数、施工位置を含む施工管理データを生成する施工管理データ生成手段と、
を備えたことを特徴とする請求項1又は2に記載の資材の検収システム。
Construction condition data acquisition means for acquiring construction condition data on materials necessary for construction of a construction structure to be constructed;
Construction management data generation to generate construction management data including at least type, number of stocks, construction position for each material based on the material data generated by the material data generation means and the construction condition data acquired by the construction condition data acquisition means Means,
The material inspection system according to claim 1 or 2, further comprising:
前記施工管理データに基づいて、資材の施工位置を指示する施工位置指示手段を備えたことを特徴とする請求項3に記載の資材の検収システム。   The material inspection system according to claim 3, further comprising construction position instruction means for instructing a construction position of the material based on the construction management data.
JP2017074989A 2017-04-05 2017-04-05 Material receiving inspection system Pending JP2018180662A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017074989A JP2018180662A (en) 2017-04-05 2017-04-05 Material receiving inspection system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017074989A JP2018180662A (en) 2017-04-05 2017-04-05 Material receiving inspection system

Publications (1)

Publication Number Publication Date
JP2018180662A true JP2018180662A (en) 2018-11-15

Family

ID=64276578

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017074989A Pending JP2018180662A (en) 2017-04-05 2017-04-05 Material receiving inspection system

Country Status (1)

Country Link
JP (1) JP2018180662A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110826668A (en) * 2019-11-07 2020-02-21 上海建工材料工程有限公司 Intelligent inspection recording system and method for concrete production equipment
CN111259791A (en) * 2020-01-15 2020-06-09 大亚湾核电运营管理有限责任公司 Nuclear power station material acceptance method and device, computer equipment and storage medium
JP2020152531A (en) * 2019-03-20 2020-09-24 株式会社タダノ crane
JP2020179662A (en) * 2019-07-01 2020-11-05 Arithmer株式会社 Information processing device, information processing method, dimensional data calculation device, product manufacturing device
JP2020181283A (en) * 2019-04-24 2020-11-05 Arithmer株式会社 Information processing device, information processing method, dimensional data calculation device, product manufacturing device
CN113034004A (en) * 2021-03-26 2021-06-25 福建汇川物联网技术科技股份有限公司 Construction safety inspection method and device
KR20220110049A (en) * 2021-01-29 2022-08-05 (주)가설안전이엔씨 System Scaffold Management System and Management Method
US11922649B2 (en) 2018-11-30 2024-03-05 Arithmer Inc. Measurement data calculation apparatus, product manufacturing apparatus, information processing apparatus, silhouette image generating apparatus, and terminal apparatus

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006127386A (en) * 2004-11-01 2006-05-18 Ntt Power & Building Facilities Inc Material production control system and material production control method
JP2008265909A (en) * 2007-04-18 2008-11-06 Hitachi-Ge Nuclear Energy Ltd Material storage position management system, and its method
JP2012180191A (en) * 2011-03-02 2012-09-20 Hitachi-Ge Nuclear Energy Ltd Method and device for supporting plant construction
JP2013067499A (en) * 2011-09-23 2013-04-18 Nec Corp Article inspection device, article inspection system, article inspection method, and program
JP2015043138A (en) * 2013-08-26 2015-03-05 三菱重工業株式会社 Material management method and material management system
JP2017054324A (en) * 2015-09-10 2017-03-16 千代田化工建設株式会社 Construction Material Management System and Construction Material Management Method
KR101715001B1 (en) * 2015-12-30 2017-03-23 연세대학교 산학협력단 Display system for safety evaluation in construction sites using of wearable device, and thereof method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006127386A (en) * 2004-11-01 2006-05-18 Ntt Power & Building Facilities Inc Material production control system and material production control method
JP2008265909A (en) * 2007-04-18 2008-11-06 Hitachi-Ge Nuclear Energy Ltd Material storage position management system, and its method
JP2012180191A (en) * 2011-03-02 2012-09-20 Hitachi-Ge Nuclear Energy Ltd Method and device for supporting plant construction
JP2013067499A (en) * 2011-09-23 2013-04-18 Nec Corp Article inspection device, article inspection system, article inspection method, and program
JP2015043138A (en) * 2013-08-26 2015-03-05 三菱重工業株式会社 Material management method and material management system
JP2017054324A (en) * 2015-09-10 2017-03-16 千代田化工建設株式会社 Construction Material Management System and Construction Material Management Method
KR101715001B1 (en) * 2015-12-30 2017-03-23 연세대학교 산학협력단 Display system for safety evaluation in construction sites using of wearable device, and thereof method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
片岡浩人: "特集「未来につながる技術」", 大林組技術研究所報, JPN6021000036, 27 December 2016 (2016-12-27), pages 1 - 17, ISSN: 0004534347 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11922649B2 (en) 2018-11-30 2024-03-05 Arithmer Inc. Measurement data calculation apparatus, product manufacturing apparatus, information processing apparatus, silhouette image generating apparatus, and terminal apparatus
JP2020152531A (en) * 2019-03-20 2020-09-24 株式会社タダノ crane
JP2020181283A (en) * 2019-04-24 2020-11-05 Arithmer株式会社 Information processing device, information processing method, dimensional data calculation device, product manufacturing device
JP2020179662A (en) * 2019-07-01 2020-11-05 Arithmer株式会社 Information processing device, information processing method, dimensional data calculation device, product manufacturing device
CN110826668A (en) * 2019-11-07 2020-02-21 上海建工材料工程有限公司 Intelligent inspection recording system and method for concrete production equipment
CN110826668B (en) * 2019-11-07 2023-05-26 上海建工建材科技集团股份有限公司 Intelligent inspection recording system and method for concrete production equipment
CN111259791A (en) * 2020-01-15 2020-06-09 大亚湾核电运营管理有限责任公司 Nuclear power station material acceptance method and device, computer equipment and storage medium
CN111259791B (en) * 2020-01-15 2023-09-08 大亚湾核电运营管理有限责任公司 Nuclear power station material acceptance method and device, computer equipment and storage medium
KR20220110049A (en) * 2021-01-29 2022-08-05 (주)가설안전이엔씨 System Scaffold Management System and Management Method
KR102621130B1 (en) * 2021-01-29 2024-01-05 (주)가설안전이엔씨 System Scaffold Management System and Management Method
CN113034004A (en) * 2021-03-26 2021-06-25 福建汇川物联网技术科技股份有限公司 Construction safety inspection method and device

Similar Documents

Publication Publication Date Title
JP2018180662A (en) Material receiving inspection system
US10423905B2 (en) Work information modelling
US8041650B2 (en) Method and system for directed documentation of construction projects
US20190325089A1 (en) Computation of point clouds and joint display of point clouds and building information models with project schedules for monitoring construction progress, productivity, and risk for delays
US10607163B2 (en) LOD work package
JP4790090B2 (en) Drawing management apparatus for structure management and processing program therefor
EP3055648B1 (en) Method and system for 3d modeling using feature detection
JP2019021190A (en) Construction support method and construction support system
JP2014153819A (en) Member installation determination system
TW578056B (en) Device and method for assisting the monitoring process on building construction
Braun et al. Process-and computer vision-based detection of as-built components on construction sites
JP2019027817A (en) Construction completion degree data acquisition system
DE102019202304B4 (en) Method and arrangement for creating a digital building model
Braun et al. Bim-based progress monitoring
KR101476909B1 (en) Real-time Process Monitoring System using Block Image
JP2022155087A (en) Integrated data generation system, construction plan management system, integrated data generation method, construction plan management method, and program
JP5642735B2 (en) Construction work support system and operation method thereof
Meadati et al. Building information modeling implementation-current and desired status
JP2005327170A (en) Quality check system in construction site
Morgenstern et al. Quantified point clouds and enriched BIM-Models for digitalised maintenance planning
JP7033851B2 (en) Construction volume data acquisition system
JP2017199259A (en) Material recognition device and material recognition method
CN111242497A (en) Construction cost management system and method based on building information model
Saidi et al. Development and use of the NIST intelligent and automated construction job site testbed
JP2008225596A (en) System for supporting confirmation of work progress

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200218

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20201127

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210108

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20210629