JP2018144676A - Train control system, train control method and onboard device of train - Google Patents

Train control system, train control method and onboard device of train Download PDF

Info

Publication number
JP2018144676A
JP2018144676A JP2017042396A JP2017042396A JP2018144676A JP 2018144676 A JP2018144676 A JP 2018144676A JP 2017042396 A JP2017042396 A JP 2017042396A JP 2017042396 A JP2017042396 A JP 2017042396A JP 2018144676 A JP2018144676 A JP 2018144676A
Authority
JP
Japan
Prior art keywords
train
speed
travel
target
target speed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017042396A
Other languages
Japanese (ja)
Other versions
JP6802091B2 (en
JP2018144676A5 (en
Inventor
努 宮内
Tsutomu Miyauchi
努 宮内
基也 鈴木
Motoya Suzuki
基也 鈴木
小熊 賢司
Kenji Oguma
賢司 小熊
宏志 水津
Hiroshi Minazu
宏志 水津
鈴木 一也
Kazuya Suzuki
一也 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2017042396A priority Critical patent/JP6802091B2/en
Priority to PCT/JP2017/040345 priority patent/WO2018163508A1/en
Publication of JP2018144676A publication Critical patent/JP2018144676A/en
Publication of JP2018144676A5 publication Critical patent/JP2018144676A5/ja
Application granted granted Critical
Publication of JP6802091B2 publication Critical patent/JP6802091B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60LPROPULSION OF ELECTRICALLY-PROPELLED VEHICLES; SUPPLYING ELECTRIC POWER FOR AUXILIARY EQUIPMENT OF ELECTRICALLY-PROPELLED VEHICLES; ELECTRODYNAMIC BRAKE SYSTEMS FOR VEHICLES IN GENERAL; MAGNETIC SUSPENSION OR LEVITATION FOR VEHICLES; MONITORING OPERATING VARIABLES OF ELECTRICALLY-PROPELLED VEHICLES; ELECTRIC SAFETY DEVICES FOR ELECTRICALLY-PROPELLED VEHICLES
    • B60L15/00Methods, circuits, or devices for controlling the traction-motor speed of electrically-propelled vehicles
    • B60L15/40Adaptation of control equipment on vehicle for remote actuation from a stationary place
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B61RAILWAYS
    • B61LGUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
    • B61L27/00Central railway traffic control systems; Trackside control; Communication systems specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Power Engineering (AREA)
  • Transportation (AREA)
  • Electric Propulsion And Braking For Vehicles (AREA)
  • Train Traffic Observation, Control, And Security (AREA)

Abstract

PROBLEM TO BE SOLVED: To reduce energy consumption and delay increase by preventing stopping between stations which occurs when a subsequent train excessively approaches the preceding train in the case that a delay occurs at a departure time of a train because of an increase in getting-on time due to crowded people, running-onto tain, or the like.SOLUTION: The shortest release time being a time at which the disappearance of a brake pattern is earliest in the case that the brake pattern disappears, is calculated from the brake pattern for stopping a train before an occupation section by the preceding train traveling in front of the train on the basis of a departure time of the preceding train at a target station, a station approach limit position for preventing the train from approaching the target station is calculated from the brake pattern, a target speed of the train is calculated from the station approach limit position of the train, the current position, deceleration and the shortest release time, and a travel command to control travel of the train is determined on the basis of the target speed of the train, the present speed and the brake pattern.SELECTED DRAWING: Figure 6

Description

本発明は、先行列車の遅延により、その後ろを走行する後続列車に対して発生する遅延波及を抑制する列車制御システム、列車制御方法および列車の車上装置に関し、先行列車の出発時刻の遅れの予測が困難な状況において、後続列車の駅間停止を抑制することでエネルギー増大を防止するものである。   The present invention relates to a train control system, a train control method, and a train onboard device for suppressing a delay spread generated for a subsequent train traveling behind the preceding train due to a delay of the preceding train. In a situation where the prediction is difficult, an increase in energy is prevented by suppressing the stop of the following train between stations.

鉄道システムにおいて、同一走行路を走行する列車は、列車同士が衝突しないように信号によって制御されていることから、信号を考慮して設計されているダイヤの通りに列車が走行をしている場合には、信号によって後続列車にブレーキがかかる状況はあまり発生しない。   In a railway system, trains traveling on the same route are controlled by signals so that the trains do not collide with each other. However, the situation where the following train is braked by a signal does not occur much.

しかしながら、ある列車が遅延しダイヤ上の余裕を無くした場合には、その後ろを走行する後続列車に対して、先行列車との衝突を回避するためにブレーキがかかる現象が頻繁に起こり得る。特に、都市部のように高密度に列車が走行している場合には、その更に後ろを走行している後続列車に対してもこの現象が波及することになる。これによって、加減速の増大による消費エネルギーの増加を招くとともに、更に遅延が波及する事態を招くことになる。   However, when a certain train is delayed and there is no room on the diagram, a phenomenon in which a brake is frequently applied to a subsequent train traveling behind the train to avoid a collision with a preceding train may occur. In particular, when a train is traveling at a high density as in an urban area, this phenomenon also affects a subsequent train traveling further behind the train. This leads to an increase in energy consumption due to an increase in acceleration / deceleration, and a situation in which a delay spreads further.

このような事態を解決するための技術として、特許文献1には、地上装置と、地上装置が管理する領域内のすべての列車上にある車上装置とをネットワークにより結んだ地上車上連携システムにおいて、地上装置は、各列車上にある車上装置から列車走行情報を入手し、内部にある処理装置によって該当する後続列車に対する目標情報を作成し、この目標情報を各列車上にある車上装置に送付することにより、当該車上装置は、送付された目標情報に従い走行する方法が記述されている。   As a technique for solving such a situation, Patent Literature 1 discloses an on-vehicle cooperation system in which a ground device and on-vehicle devices on all trains in an area managed by the ground device are connected by a network. In the above, the ground device obtains the train travel information from the on-board device on each train, creates target information for the corresponding subsequent train by the internal processing device, and uses this target information on the vehicle on each train. By sending the information to the device, a method is described in which the on-board device travels according to the sent target information.

特開2011−006009号公報JP 2011-006009 A

しかしながら、特許文献1に記述されている方法は、列車が到着した時刻情報を基に処理をするため、混雑に伴う乗降時間の増加や駆け込み乗車などにより出発時刻に遅延が発生するなど、乗客の動態に依存する出発時刻の遅延に対してまで対応を図ることは、不可能である。このような状況下では、後続列車が先行列車に過剰に接近することとなり、信号によって後続列車にブレーキがかかり駅中間で停車することになる。さらに、その後続列車も同じように過剰に接近することになるため、連鎖的に駅中間で停車することになる。   However, since the method described in Patent Document 1 performs processing based on the time information when the train arrives, a delay occurs in the departure time due to an increase in boarding time due to congestion or a boarding ride, etc. It is impossible to cope with the departure time delay depending on the dynamics. Under such circumstances, the succeeding train will excessively approach the preceding train, and the succeeding train will be braked by the signal and will stop in the middle of the station. In addition, the subsequent trains will be approached excessively in the same manner, so that the trains will stop in the middle of the station.

このように、先行列車の出発の遅れがその後ろを走行する後続列車に影響を与え、さらに後続する列車へと波及することが起こる。その結果として、平常運転時と比較して消費エネルギーが増大するとともに、列車遅延の波及を招くことになる。   In this way, the departure delay of the preceding train affects the subsequent train traveling behind it, and further spreads to the following train. As a result, energy consumption increases as compared to normal operation, and a train delay is spread.

本発明に係る列車制御システムは、上記課題を解決するために、地上側が備える最短解放時刻計算部と、列車の車上側または地上側が備える目標速度算出部と、車上側が備える走行制御装置とを有し、最短解放時刻計算部は、列車の前方を走行する先行列車による占有区間の手前に当該列車を停止させるためのブレーキパターンから、目標駅における先行列車の出発時刻に基づいて、当該ブレーキパターンが消失するとした場合に該消失に至る最も早い時刻である最短解放時刻を計算し、目標速度算出部は、ブレーキパターンから列車が目標駅へ進入することを防止するための駅進入限界位置を求め、列車の駅進入限界位置、現在位置、減速度および最短解放時刻から列車の目標速度を算出し、走行制御装置は、列車の目標速度および現在速度並びにブレーキパターンに基づいて、列車の走行を制御するための走行指令を決定する走行決定部または列車の運転者に対して自列車の運転支援情報を提供する運転支援部を備え、列車の走行を、走行制御装置により制御することを特徴とする。   In order to solve the above problems, the train control system according to the present invention includes a shortest release time calculation unit provided on the ground side, a target speed calculation unit provided on the vehicle upper side or the ground side of the train, and a travel control device provided on the vehicle upper side. The shortest release time calculation unit has the brake pattern based on the departure time of the preceding train at the target station from the brake pattern for stopping the train before the occupied section by the preceding train traveling in front of the train. When the vehicle disappears, the shortest release time which is the earliest time to disappear is calculated, and the target speed calculation unit obtains a station entry limit position for preventing the train from entering the target station from the brake pattern. The train's target speed is calculated from the train station entry limit position, current position, deceleration, and shortest release time. And a driving determination unit that determines a driving command for controlling the traveling of the train based on the brake pattern or a driving support unit that provides driving support information of the own train to the driver of the train. It is controlled by a travel control device.

本発明によれば、列車の駅間停止を最小限に抑制して回避することが可能となり、平常運転時と比較して消費エネルギーの増大を防ぐとともに、列車遅延の増大や波及を防ぐことが可能となる。   According to the present invention, it is possible to minimize and avoid a stop between stations of a train, and it is possible to prevent an increase in energy consumption and prevent an increase or spread of a train delay as compared with normal operation. It becomes possible.

図1は、本発明の実施例1に係るシステム構成の一例およびデータフローを示す図である。FIG. 1 is a diagram illustrating an example of a system configuration and a data flow according to the first embodiment of the present invention. 図2は、最短解放時刻計算装置が実行する処理のフローチャートを示す図である。FIG. 2 is a diagram illustrating a flowchart of processing executed by the shortest release time calculation apparatus. 図3は、自動列車走行装置の内部構成の一例を示す図である。FIG. 3 is a diagram illustrating an example of an internal configuration of the automatic train travel device. 図4は、目標速度算出装置が実行する処理のフローチャートを示す図である。FIG. 4 is a diagram illustrating a flowchart of processing executed by the target speed calculation device. 図5は、走行決定装置の内部構成の一例を示す図である。FIG. 5 is a diagram illustrating an example of an internal configuration of the travel determination device. 図6は、本発明に係る列車制御を実施した場合の効果を示す図である。FIG. 6 is a diagram showing an effect when the train control according to the present invention is performed. 図7は、本発明の実施例2に係るシステム構成の一例およびデータフローを示す図である。FIG. 7 is a diagram illustrating an example of a system configuration and data flow according to the second embodiment of the present invention. 図8は、列車走行装置の内部構成の一例を示す図である。FIG. 8 is a diagram illustrating an example of an internal configuration of the train traveling device. 図9は、運転支援装置によって表示される運転支援画面の一構成例を示す図である。FIG. 9 is a diagram illustrating a configuration example of a driving support screen displayed by the driving support device. 図10は、本発明の実施例3に係るシステム構成の一例およびデータフローを示す図である。FIG. 10 is a diagram illustrating an example of a system configuration and a data flow according to the third embodiment of the present invention.

本発明を実施するための形態として、実施例1〜3について、図面を用いて以下に説明する。   As modes for carrying out the present invention, Examples 1 to 3 will be described below with reference to the drawings.

図1は、本発明の実施例1に係るシステム構成の一例およびデータフローを示す図である。
地上装置101は、管轄する路線の情報を管理し、管轄する路線を走行する列車102A、102B、102C、…(以下、全てを総称して「列車102」とする)に対して情報を送信する。列車102(102A、102B、102C、…)は、送信された情報を基に自列車を制御する。
FIG. 1 is a diagram illustrating an example of a system configuration and a data flow according to the first embodiment of the present invention.
The ground device 101 manages the information of the route under the jurisdiction, and transmits information to the trains 102A, 102B, 102C,... (Hereinafter collectively referred to as “train 102”) traveling on the route under the jurisdiction. . The train 102 (102A, 102B, 102C,...) Controls its own train based on the transmitted information.

また、地上装置101は、管轄する路線を走行する列車の発着状況を管理する発着状況管理装置103、各駅の時隔データ(列車到着の時間間隔を示すデータ)を管理する時隔データベース104、管轄する路線のダイヤを記録しておくダイヤデータベース105、発着状況管理装置103と時隔データベース104とダイヤデータベース105とからの各情報を入力とする最短解放時刻計算装置106および列車102(102A、102B、102C、…)に情報を送信する地上側送信装置107から構成される。   In addition, the ground device 101 includes an arrival / departure situation management device 103 that manages the arrival / departure situation of trains that travel on the route under jurisdiction, a time interval database 104 that manages time interval data (data indicating the time interval of train arrival), The schedule database 105 for recording the schedule of the route to be operated, the arrival / departure situation management device 103, the time interval database 104, and the shortest release time calculation device 106 which receives each information from the diagram database 105 and the train 102 (102A, 102B, 102C,...)) Is configured from a ground-side transmitting device 107 that transmits information.

ここで、最短解放時刻計算装置106は、発着状況管理装置103、時隔データベース104およびダイヤデータベース105からの各入力情報を基にして、各列車102A、102B、102C、…が進入しようとする駅への進入防止を図るブレーキパターンの最短解放時刻151A、151B、151C、…(以下、全てを総称して「最短解放時刻151」とする)および各列車の駅進入限界位置152A、152B、152C、…(以下、全てを総称して「駅進入限界位置152」とする)を計算する。ここで、この最短解放時刻とは、上記ブレーキパターンが消失するとした場合に、この消失することに至る最も早い時刻を示している。   Here, the shortest release time calculation device 106 is a station to which each train 102A, 102B, 102C,... Enters, based on the input information from the arrival / departure situation management device 103, the time interval database 104, and the diagram database 105. Brake pattern shortest release times 151A, 151B, 151C,... (Hereinafter collectively referred to as “shortest release time 151”) and station entry limit positions 152A, 152B, 152C for each train (Hereinafter collectively referred to as “station entry limit position 152”) is calculated. Here, the shortest release time indicates the earliest time that the brake pattern disappears when the brake pattern disappears.

地上側送信装置107は、最短解放時刻151(151A、151B、151C、…)および駅進入限界位置152(152A、152B、152C、…)の各情報を列車102(102A、102B、102C、…)に送信する。   The ground-side transmitting device 107 uses the train 102 (102A, 102B, 102C,...) For each information of the shortest release time 151 (151A, 151B, 151C,...) And the station entry limit position 152 (152A, 152B, 152C,. Send to.

列車102(図1の下図、参照)は、地上装置101から情報を受信する車上側受信装置108、列車の加減速特性を記録するデータベース109、現在の列車速度154および現在の列車位置155を計測する速度計測装置110および列車の走行方法を決定する自動列車走行装置111から構成される。   The train 102 (see the lower diagram in FIG. 1) measures the upper vehicle receiving device 108 that receives information from the ground device 101, the database 109 that records the acceleration / deceleration characteristics of the train, the current train speed 154, and the current train position 155. A speed measuring device 110 that performs the operation and a train traveling device 111 that determines a train traveling method.

ここで、車上側受信装置108は、地上装置101から最短解放時刻151および駅進入限界位置152を受信するとともに、信号装置(図示せず)から自列車の前方を走行する先行列車との関係で定まる自列車進入限界位置153を受信する。   Here, the vehicle upper side receiving device 108 receives the shortest release time 151 and the station entry limit position 152 from the ground device 101, and also has a relationship with a preceding train that travels in front of the own train from a signal device (not shown). The fixed train approach limit position 153 is received.

速度計測装置110は、現在の列車速度154および現在の列車速度154を積分することで得られる現在の列車位置155を計測する。速度計測装置110としては、速度発電機やGPSなどを用いてもよい。   The speed measuring device 110 measures the current train position 155 obtained by integrating the current train speed 154 and the current train speed 154. As the speed measuring device 110, a speed generator, GPS, or the like may be used.

自動列車走行装置111は、最短解放時刻151、駅進入限界位置152、自列車進入限界位置153、現在の列車速度154、現在の列車位置155およびデータベース109に記録された加減速特性156を基にして、列車の走行方法を決定する。自動列車走行装置111が決定した走行方法に従って、列車102は自動運転を行う。   The automatic train traveling device 111 is based on the shortest release time 151, the station entry limit position 152, the own train entry limit position 153, the current train speed 154, the current train position 155, and the acceleration / deceleration characteristics 156 recorded in the database 109. Determine how the train will travel. The train 102 performs automatic operation according to the travel method determined by the automatic train travel device 111.

図2は、最短解放時刻計算装置106が実行する処理のフローチャートを示す図である。以下、このフローチャートに沿って処理内容を説明する。なお、以下の各ステップでは、最短解放時刻計算装置106を「計算装置106」と簡略して記す。   FIG. 2 is a diagram illustrating a flowchart of processing executed by the shortest release time calculation device 106. Hereinafter, the processing content will be described with reference to this flowchart. In the following steps, the shortest release time calculation device 106 is simply referred to as “calculation device 106”.

ステップ201で、計算装置106は、管轄する路線上に存在する列車のリストを抽出し、ステップ202に進む。このリストの抽出に際し、ダイヤデータベース105を参酌して、発着状況管理装置101により発着状況に応じた適宜の補正を加える。   In step 201, the computing device 106 extracts a list of trains that exist on the route under the jurisdiction, and proceeds to step 202. In extracting this list, the diamond database 105 is taken into consideration, and an appropriate correction according to the arrival / departure situation is added by the arrival / departure situation management apparatus 101.

ステップ202で、計算装置106は、ステップ201で抽出した列車のリストの中から駅間に存在する1列車を抽出し、ステップ203に進む。   In step 202, the computing device 106 extracts one train existing between stations from the train list extracted in step 201, and proceeds to step 203.

ステップ203で、計算装置106は、ステップ202で抽出した列車が向かっている駅までの間に、自列車より前に停車している列車数Nを算出し(抽出した列車が向かっている駅に停車している列車も含む)、ステップ204に進む。この算出には、ダイヤデータベース105および発着状況管理装置101を用いる。   In step 203, the calculation device 106 calculates the number N of trains that have stopped before the own train until the station where the train extracted in step 202 is heading (to the station where the extracted train is heading). (Including trains that are stopped), the process proceeds to step 204. For this calculation, the diamond database 105 and the arrival / departure situation management apparatus 101 are used.

ステップ204で、計算装置106は、ステップ202で抽出した列車が向かっている駅に停車している他列車が出発遅延しているか否かをチェックする。他列車が停車しかつ出発遅延している場合(Y)には、ステップ205に進む。他方、他列車が停車していない、あるいは他列車が停車していても出発遅延していない場合(N)には、ステップ206に進む。   In step 204, the computing device 106 checks whether or not another train stopped at the station where the train extracted in step 202 is heading is delayed. If another train stops and is delayed (Y), the process proceeds to step 205. On the other hand, if the other train is not stopped, or if the other train is stopped but the departure is not delayed (N), the process proceeds to step 206.

ステップ205で、計算装置106は、ステップ203で抽出した列車数Nを基に、以下の計算式により最短解放時刻を算出し、ステップ207に進む。ここで、時隔のデータは、時隔データベース104により得る。
最短解放時刻=現在時刻+時隔×列車数N
In step 205, the calculation device 106 calculates the shortest release time by the following calculation formula based on the number N of trains extracted in step 203, and proceeds to step 207. Here, the time interval data is obtained from the time interval database 104.
Shortest release time = current time + time interval x number of trains N

ステップ206で、計算装置106は、抽出した列車が向かっている駅に到着するまでに、最短解放時刻が一度でも出されている場合には、その中で最も直近に出された最短解放時刻を指令し、ステップ207に進む。一度も出されていない場合には、最短解放時刻を指定しない。   In step 206, when the shortest release time has been issued even once until the computer 106 arrives at the station where the extracted train is heading, the calculation device 106 sets the shortest release time most recently issued among them. Command and go to step 207. If it has never been issued, the shortest release time is not specified.

ステップ207で、計算装置106は、管轄する路線上に存在する列車のリストから現在の列車を削除し、ステップ208に進む。   In step 207, the computing device 106 deletes the current train from the list of trains that exist on the line under its jurisdiction, and proceeds to step 208.

ステップ208で、計算装置106は、管轄する路線上に存在する列車のリストにまだ列車が存在するか否かをチェックし、存在する(Y)場合にはステップ202に戻り、存在しない(N)場合には処理を終了する。   In step 208, the computing device 106 checks whether there is still a train in the list of trains that exist on the route under its jurisdiction, and if it exists (Y), returns to step 202 and does not exist (N). If so, the process ends.

図3は、車上装置102が搭載する自動列車走行装置111の内部構成の一例を示す図である。
自動列車走行装置111は、目標速度351を算出する目標速度算出装置301、目標走行パターン352を格納する走行パターンデータベース302および走行指令353を決定する走行決定装置303から構成される。
FIG. 3 is a diagram illustrating an example of an internal configuration of the automatic train travel device 111 mounted on the on-board device 102.
The automatic train travel device 111 includes a target speed calculation device 301 that calculates a target speed 351, a travel pattern database 302 that stores a target travel pattern 352, and a travel determination device 303 that determines a travel command 353.

目標速度算出装置301は、最短解放時刻151、駅進入限界位置152、現在の列車位置155および加減速特性156を基にして、自列車の目標速度351を算出する。
走行パターンデータベース302は、(位置、速度)の集合で構成される自列車の目標走行パターン352を記憶している。その際には、走行パターンデータベース302には、あらかじめ作成した走行パターンおよび走行中に作成した走行パターンの少なくとも一方を格納する。
The target speed calculation device 301 calculates the target speed 351 of the own train based on the shortest release time 151, the station entry limit position 152, the current train position 155, and the acceleration / deceleration characteristics 156.
The travel pattern database 302 stores a target travel pattern 352 of the own train configured by a set of (position, speed). At that time, the travel pattern database 302 stores at least one of a travel pattern created in advance and a travel pattern created during travel.

走行決定装置303は、自列車進入限界位置153、現在の列車速度154、現在の列車位置155、加減速特性156、目標速度351および自列車の目標走行パターン352を基にして、自列車の走行指令353を決定する。   The travel determination device 303 travels based on the own train approach limit position 153, the current train speed 154, the current train position 155, the acceleration / deceleration characteristics 156, the target speed 351, and the target travel pattern 352 of the own train. Command 353 is determined.

図4は、自動列車走行装置111に設ける目標速度算出装置301が実行する処理のフローチャートを示す図である。以下に、このフローチャートに沿って処理内容を説明する。なお、以下の各ステップでは、目標速度算出装置301を「算出装置301」と簡略して記す。   FIG. 4 is a diagram illustrating a flowchart of processing executed by the target speed calculation device 301 provided in the automatic train travel device 111. The processing contents will be described below along this flowchart. In the following steps, the target speed calculation device 301 is simply referred to as “calculation device 301”.

ステップ401で、算出装置301は、最短解放時刻151(T_Release)があるかどうかをチェックし、それがある(Y)場合にはステップ402に進み、それがない(N)場合には、ステップ405に進む。   In step 401, the calculation device 301 checks whether or not there is the shortest release time 151 (T_Release). If there is (Y), the calculation apparatus 301 proceeds to step 402, and if there is not (N), step 405 is performed. Proceed to

ステップ402で、算出装置301は、駅進入限界位置152(X_LMA)を取得し、ステップ403に進む。   In step 402, the calculation apparatus 301 acquires the station entry limit position 152 (X_LMA), and proceeds to step 403.

ステップ403で、算出装置301は、加減速特性156を基にして列車の減速度(β[m/s/s])を取得し、ステップ404に進む。   In step 403, the calculation device 301 acquires the train deceleration (β [m / s / s]) based on the acceleration / deceleration characteristics 156, and proceeds to step 404.

ステップ404で、算出装置301は、列車の現在位置155(X[m])、ステップ402で取得した駅進入限界位置152(X_LMA[m])、ステップ403で取得した列車の減速度(β[m/s/s])および最短解放時刻151(T_Release)と現在時刻Tとの差分値(ΔT[s])から、以下の式を用いて目標速度351(V[km/h])を算出し、処理を終了する。
V={−ΔT+(ΔT+2/β×|X_LMA−X|)1/2}×β×3.6
In step 404, the calculation device 301 calculates the current train position 155 (X [m]), the station entry limit position 152 (X_LMA [m]) acquired in step 402, and the train deceleration (β [ m / s / s]) and the difference value (ΔT [s]) between the shortest release time 151 (T_Release) and the current time T, the target speed 351 (V [km / h]) is calculated using the following formula: Then, the process ends.
V = {− ΔT + (ΔT 2 + 2 / β × | X_LMA−X |) 1/2 } × β × 3.6

他方、ステップ405で、算出装置301は、列車の最高速度を目標速度351に設定し、処理を終了する。   On the other hand, in step 405, the calculation device 301 sets the maximum speed of the train to the target speed 351 and ends the process.

図5は、自動列車走行装置111に設ける走行決定装置303の内部構成の一例を示す図である。
走行決定装置303は、第1の走行指令551を決定する走行追従制御部501、信号速度552を算出する信号速度算出部502、第2の走行指令554を決定する目標速度制御部504および比較処理部503並びに505から構成される。
FIG. 5 is a diagram illustrating an example of an internal configuration of a travel determination device 303 provided in the automatic train travel device 111.
The travel determination device 303 includes a travel follow-up control unit 501 that determines a first travel command 551, a signal speed calculation unit 502 that calculates a signal speed 552, a target speed control unit 504 that determines a second travel command 554, and a comparison process. It consists of parts 503 and 505.

走行追従制御部501は、現在の列車速度154、現在の列車位置155および目標走行パターン352を基にして、現在の列車速度154および現在の列車位置155を目標走行パターン352に近づけるように、第1の走行指令551を決定する。   The travel follow-up control unit 501 is configured to make the current train speed 154 and the current train position 155 closer to the target travel pattern 352 based on the current train speed 154, the current train position 155, and the target travel pattern 352. 1 running command 551 is determined.

信号速度算出部502は、自列車進入限界位置153、現在の列車位置155および加減速特性156を基にして、現在の列車位置における自列車のブレーキパターン速度に相当する信号速度552を算出する。   Based on the own train approach limit position 153, the current train position 155, and the acceleration / deceleration characteristics 156, the signal speed calculation unit 502 calculates a signal speed 552 corresponding to the brake pattern speed of the own train at the current train position.

比較処理部503は、信号速度552と目標速度351の小さい方の数値を追従目標速度553として出力する。
目標速度制御部504は、現在の列車速度154を追従目標速度553に近づけるように、第2の走行指令554を決定する。
The comparison processing unit 503 outputs the smaller value of the signal speed 552 and the target speed 351 as the follow target speed 553.
The target speed control unit 504 determines the second travel command 554 so that the current train speed 154 approaches the tracking target speed 553.

比較処理部505は、第1の走行指令551と第2の走行指令554の小さい方の指令値を自列車の走行指令353として出力する。   The comparison processing unit 505 outputs a smaller command value of the first travel command 551 and the second travel command 554 as a travel command 353 for the own train.

なお、走行追従制御部501からの第1の走行指令551の決定方法および目標速度制御機能504からの第2の走行指令554の決定方法は、公知の手法を用いてもよく、例えば、目標速度と現在速度の偏差による比例制御などを用いればよい。   Note that a known method may be used as a determination method of the first travel command 551 from the travel follow-up control unit 501 and a determination method of the second travel command 554 from the target speed control function 504, for example, the target speed Proportional control based on the deviation of the current speed may be used.

また、信号速度算出部502の信号速度552の算出方法には、信号速度552をV_ATP[km/h]、自列車進入限界位置153をY_LMA[m]、現在の列車位置155をX[m]、加減速特性156で定まる列車の減速度をβ[m/s/s]とした場合に、以下の式を用いる。
V_ATP=(2×β×|Y_LMA−X|)1/2×3.6
In addition, the signal speed calculation unit 502 calculates the signal speed 552 as follows: the signal speed 552 is V_ATP [km / h], the own train entry limit position 153 is Y_LMA [m], and the current train position 155 is X [m]. When the train deceleration determined by the acceleration / deceleration characteristics 156 is β [m / s / s], the following equation is used.
V_ATP = (2 × β × | Y_LMA−X |) 1/2 × 3.6

図6は、本発明に係る列車制御を実施した場合の効果を示す図である。
時刻T0の時点で、駅Bに列車1が停車し、駅Aから駅Bに向かって列車2、その後を列車3が走行している状態を想定する。この後、列車1が駅Bで出発遅延した際に、本発明に係る制御を適用した場合に得られる効果を説明する。
FIG. 6 is a diagram showing an effect when the train control according to the present invention is performed.
It is assumed that the train 1 stops at the station B at the time T0, the train 2 travels from the station A toward the station B, and the train 3 travels thereafter. After this, the effect obtained when the control according to the present invention is applied when the train 1 is delayed at the station B will be described.

図6において、左側の図(以下、「図6左図」という)は、横軸を速度、縦軸を位置とし、列車3に対して、本発明に係る制御を適用した場合の走行の軌跡(速度変化)を示している。右側の図(以下、「図6右図」という)は、横軸を時刻、縦軸を位置とし、列車1、列車2および列車3それぞれの時々刻々の位置を示している。   In FIG. 6, the diagram on the left side (hereinafter referred to as “the left diagram in FIG. 6”) shows a travel locus when the control according to the present invention is applied to the train 3 with the horizontal axis representing speed and the vertical axis representing position. (Speed change). The diagram on the right side (hereinafter referred to as “the right diagram in FIG. 6”) shows the position of each of train 1, train 2 and train 3 from time to time, with the horizontal axis representing time and the vertical axis representing position.

以下では、図2および図4に示す処理フロー並びに図5に示す構成による走行指令を決定する制御態様に沿って、図6右図を中心にして効果を説明する。   In the following, the effects will be described with reference to the right diagram of FIG. 6 along the processing flow shown in FIGS. 2 and 4 and the control mode for determining the travel command by the configuration shown in FIG.

(1)時刻T0まで
時刻T0までは、列車1に出発遅延がない状態である。このため、時刻T0までは、列車2および列車3に対して、図2に示す最短解放時刻計算装置106の処理フローでは、いずれもステップ201→202→203→204(N)→206→207→208と処理は進み、最短解放時刻は指定されない(ステップ206では、直近に出された最短解放時刻がないため、指定されない)。なお、ステップ203で抽出されるNは、列車2に対してはN=1、列車3に対してはN=2となる。
(1) Until time T0 Until time T0, train 1 has no departure delay. Therefore, until time T0, in the processing flow of the shortest release time calculation device 106 shown in FIG. 2 for both train 2 and train 3, step 201 → 202 → 203 → 204 (N) → 206 → 207 → The process proceeds to 208, and the shortest release time is not specified (in step 206, there is no shortest release time that has been issued most recently, so it is not specified). Note that N extracted in step 203 is N = 1 for the train 2 and N = 2 for the train 3.

また、図4に示す目標速度算出装置301の処理フローでは、列車2および列車3に対して、いずれもステップ401(N)→405と処理は進み、目標速度は列車最高速度の設定となる。   Further, in the processing flow of the target speed calculation device 301 shown in FIG. 4, the process proceeds to step 401 (N) → 405 for both the train 2 and the train 3, and the target speed is set to the maximum train speed.

さらに、図5に示す制御態様を実施することにより、列車2および列車3の走行指令が確定する。列車2(走行パターンを図示せず)については、図6右図に示す時刻−位置の軌跡から、時刻T0の時点で向かっている駅の進入限界位置近くまで到達している。しかし、時刻T0の時点では駅の進入限界位置から発生するブレーキパターンに抵触することなく、かつ先行する列車1に出発遅延が発生していないことから、駅Bへの停車に向けて走行する。列車2に後続する列車3は、目標速度に向けて加速する。   Further, by executing the control mode shown in FIG. 5, the traveling commands for train 2 and train 3 are determined. Train 2 (running pattern not shown) has reached from the time-position trajectory shown in the right figure of FIG. 6 to the vicinity of the approach limit position of the station heading at time T0. However, at time T0, there is no conflict with the brake pattern generated from the approach limit position of the station, and there is no departure delay in the preceding train 1, so the vehicle travels to stop at station B. The train 3 following the train 2 accelerates toward the target speed.

(2)時刻T1
時刻T1の時点で、列車1には出発遅延が発生する。この時、列車2および列車3に対して、図2に示す最短解放時刻計算装置106の処理フローでは、いずれもステップ201→202→203→204(Y)→205→207→208と進み、それぞれの最短開放時刻TO21およびTO31が算出される。なお、ステップ203で抽出されるNは、列車2に対してはN=1、列車3に対してはN=2となる。
(2) Time T1
At time T1, a departure delay occurs in the train 1. At this time, in the processing flow of the shortest release time calculation device 106 shown in FIG. 2 for the train 2 and the train 3, both proceed in the order of step 201 → 202 → 203 → 204 (Y) → 205 → 207 → 208, respectively. The shortest opening times TO21 and TO31 are calculated. Note that N extracted in step 203 is N = 1 for the train 2 and N = 2 for the train 3.

また、図4に示す目標速度算出装置301の処理フローでは、列車2および列車3に対して、いずれもステップ401(Y)→402→403→404と進み、それぞれの目標速度VO21およびVO31が算出される。   Further, in the processing flow of the target speed calculation device 301 shown in FIG. 4, for each of the train 2 and the train 3, the process proceeds from step 401 (Y) → 402 → 403 → 404, and the respective target speeds VO21 and VO31 are calculated. Is done.

この目標速度VO21およびVO31に従って、列車2および列車3は、図5に示す制御態様を行う。列車2(走行パターンを図示せず)については、図6右図に示す時刻−位置の軌跡から、時刻T1の時点で、向かっている駅の進入限界位置から発生するブレーキパターンPT3に抵触することになり、制動状態となる。   According to the target speeds VO21 and VO31, the train 2 and the train 3 perform the control mode shown in FIG. For train 2 (running pattern not shown), from the time-position trajectory shown in the right diagram of FIG. 6, at time T1, the brake pattern PT3 generated from the approach limit position of the station that is heading is in conflict. Becomes a braking state.

一方、列車3については、向かっている駅の進入限界および先行する列車2によって定まる自列車の進入限界P1で定まるブレーキパターンPT1までは距離があることから、目標速度VO31に応じて制御することになる。なお、目標速度VO31が現在速度よりも大きいため、列車3は加速状態(図6左図)となる。   On the other hand, the train 3 is controlled according to the target speed VO31 because there is a distance to the brake limit PT1 determined by the approach limit P1 of the own train determined by the approach limit of the station that is heading and the preceding train 2. Become. Since the target speed VO31 is higher than the current speed, the train 3 is in an accelerated state (the left figure in FIG. 6).

(3)時刻T1〜T2
時刻T1からT2へ進むと、列車2は駅進入限界位置に停車することになる。目標速度VO21は、列車2が進入限界位置に到達したため0となる。このため、制動の指令が出されたままとなる。以下、列車2については、時刻T4までは同じ挙動となるため、時刻T4までは触れない。
(3) Time T1 to T2
When traveling from time T1 to T2, the train 2 stops at the station entry limit position. The target speed VO21 becomes 0 because the train 2 has reached the approach limit position. For this reason, the braking command remains issued. Hereinafter, the train 2 does not touch until the time T4 because the behavior is the same until the time T4.

一方、列車3の目標速度VO31は、現在速度に近づく方向ではあるが、現在速度よりも高い値となっている。また、先行する列車2によって定まる自列車の進入限界P2で定まるブレーキパターンPT2までは距離があることから、目標速度VO31に応じて制御することになる。このため、列車3は引き続き加速する(図6左図)。   On the other hand, the target speed VO31 of the train 3 is in a direction approaching the current speed, but has a value higher than the current speed. Further, since there is a distance to the brake pattern PT2 determined by the approach limit P2 of the own train determined by the preceding train 2, control is performed according to the target speed VO31. For this reason, the train 3 continues to accelerate (left figure in FIG. 6).

(4)時刻T2
時刻T2の時点で、列車3は、X2の位置に到達し、速度V2となる。列車3に対して、図2に示す最短解放時刻計算装置106の処理フローでは、ステップ201→202→203→204(Y)→205→207→208と進み、最短開放時刻TO32が算出される。なお、ステップ203で抽出されるNは、列車2に対してはN=1、列車3に対してはN=2となる。
(4) Time T2
At time T2, the train 3 reaches the position X2 and becomes the speed V2. In the processing flow of the shortest release time calculation device 106 shown in FIG. 2 for the train 3, the process proceeds from step 201 → 202 → 203 → 204 (Y) → 205 → 207 → 208, and the shortest release time TO32 is calculated. Note that N extracted in step 203 is N = 1 for the train 2 and N = 2 for the train 3.

また、図4に示す目標速度算出装置301の処理フローでは、ステップ401(Y)→402→403→404と進み、目標速度VO32が算出される。また、先行する列車2によって定まる自列車の進入限界P2で定まるブレーキパターンPT2までは距離があることから、目標速度VO32に応じて制御することになる。この目標速度VO32が、現在の速度V2と一致するため、列車3は現在の速度V2を保つように動作する。   Further, in the processing flow of the target speed calculation device 301 shown in FIG. 4, the process proceeds from step 401 (Y) → 402 → 403 → 404, and the target speed VO32 is calculated. Further, since there is a distance to the brake pattern PT2 determined by the approach limit P2 of the own train determined by the preceding train 2, control is performed according to the target speed VO32. Since the target speed VO32 coincides with the current speed V2, the train 3 operates so as to maintain the current speed V2.

(5)時刻T3
時刻T3の時点で、列車3は、X3の位置に到達し、速度V3となる。列車3に対して、図2に示す最短解放時刻計算装置106の処理フローでは、ステップ201→202→203→204(Y)→205→207→208と進み、最短開放時刻TO33が算出される。なお、ステップ203で抽出されるNは、列車2に対してはN=1、列車3に対してはN=2となる。
(5) Time T3
At time T3, the train 3 reaches the position X3 and becomes the speed V3. In the processing flow of the shortest release time calculation device 106 shown in FIG. 2 for the train 3, the process proceeds from step 201 → 202 → 203 → 204 (Y) → 205 → 207 → 208, and the shortest release time TO33 is calculated. Note that N extracted in step 203 is N = 1 for the train 2 and N = 2 for the train 3.

また、図4に示す目標速度算出装置301の処理フローでは、ステップ401(Y)→402→403→404と進み、目標速度VO33が算出される。また、先行する列車2によって定まる自列車の進入限界P2で定まるブレーキパターンPT2までは距離があることから、目標速度VO33に応じて制御することになる。目標速度VO33は、現在速度V3よりも低いため、列車3は目標速度VO33となるように減速する(図6左図)。   In the processing flow of the target speed calculation device 301 shown in FIG. 4, the process proceeds from step 401 (Y) → 402 → 403 → 404, and the target speed VO33 is calculated. Further, since there is a distance to the brake pattern PT2 determined by the approach limit P2 of the own train determined by the preceding train 2, control is performed according to the target speed VO33. Since the target speed VO33 is lower than the current speed V3, the train 3 decelerates to become the target speed VO33 (the left diagram in FIG. 6).

(6)時刻T3〜T4
時刻T3からT4へと進むに従い、列車3の目標速度VO33は、現在の速度よりも低くなる値が算出される。また、先行する列車2によって定まる自列車の進入限界P2で定まるブレーキパターンPT2までは依然距離があることから、目標速度VO33に応じて制御することになる。すなわち、列車3は目標速度VO33になるように減速する(図6左図)。
(6) Time T3 to T4
As the time advances from time T3 to T4, the target speed VO33 of the train 3 is calculated to be a value that is lower than the current speed. Further, since there is still a distance to the brake pattern PT2 determined by the approach limit P2 of the own train determined by the preceding train 2, control is performed according to the target speed VO33. That is, the train 3 decelerates to reach the target speed VO33 (the left diagram in FIG. 6).

(7)時刻T4
時刻T4になると、駅Bに停車していた列車1が出発する。列車2および列車3に対して、図2に示す最短解放時刻計算装置106の処理フローでは、いずれもステップ201→202→203→204(Y)→205→207→208と進み、それぞれの最短開放時刻TO24およびTO34が算出される。なお、ステップ203で抽出されるNは、列車2に対してはN=1、列車3に対してはN=2となる。
(7) Time T4
At time T4, the train 1 stopped at the station B departs. In the processing flow of the shortest release time calculation device 106 shown in FIG. 2 for train 2 and train 3, both proceed in the order of step 201 → 202 → 203 → 204 (Y) → 205 → 207 → 208, and the shortest release of each. Times TO24 and TO34 are calculated. Note that N extracted in step 203 is N = 1 for the train 2 and N = 2 for the train 3.

また、図4に示す目標速度算出装置301の処理フローでは、列車2および列車3に対していずれもステップ401(Y)→402→403→404と進み、目標速度VO24およびVO34が算出される。この目標速度VO24およびVO34に従って、列車2および列車3は走行制御を行う。但し、列車2に対する目標速度VO24はまだ0であるため、列車2は停車状態を維持する。   Further, in the processing flow of the target speed calculation device 301 shown in FIG. 4, both the train 2 and the train 3 proceed in steps 401 (Y) → 402 → 403 → 404, and the target speeds VO24 and VO34 are calculated. According to the target speeds VO24 and VO34, the train 2 and the train 3 perform traveling control. However, since the target speed VO24 for the train 2 is still 0, the train 2 remains stopped.

一方、列車3は、X4の位置に到達しているものの、先行する列車2によって定まる自列車の進入限界P2で定まるブレーキパターンPT2までは依然距離があることから、目標速度VO34に応じて制御することになる。列車3は、現在の速度がV4となっているが、目標速度VO34は現在の速度V4よりも低いため、目標速度VO34となるように減速する(図6左図)。   On the other hand, although the train 3 has reached the position of X4, since there is still a distance to the brake pattern PT2 determined by the approach limit P2 of the own train determined by the preceding train 2, control is performed according to the target speed VO34. It will be. The current speed of the train 3 is V4, but since the target speed VO34 is lower than the current speed V4, the train 3 decelerates to the target speed VO34 (the left figure in FIG. 6).

(8)時刻T5
時刻T5は、列車1が駅Bから出発し終えた時刻である。列車2および列車3に対して、図2に示す最短解放時刻計算装置106の処理フローでは、いずれもステップ201→202→203→204(Y)→206→207→208と進み、それぞれの最短開放時刻は、この直近に出力されていたTO24およびTO34が算出される。なお、ステップ203で抽出されるNは、列車2に対してはN=0、列車3に対してはN=1となる。
(8) Time T5
Time T5 is the time when the train 1 has left the station B. In the processing flow of the shortest release time calculation device 106 shown in FIG. 2 for train 2 and train 3, both proceed in the order of step 201 → 202 → 203 → 204 (Y) → 206 → 207 → 208, and the shortest release for each. As for the time, TO24 and TO34 that have been output most recently are calculated. Note that N extracted in step 203 is N = 0 for the train 2 and N = 1 for the train 3.

また、図4に示す目標速度算出装置301の処理フローでは、列車2および列車3に対していずれもステップ401(Y)→402→403→404と進み、最短開放時刻のTO24およびTO34並びにそれぞれの駅進入限界位置も変化していないことから、目標速度VO24およびVO34が算出される。この目標速度VO24およびVO34に従って、列車2および列車3は走行制御を行う。但し、列車2に対する目標速度VO24はまだ0であるため、列車2は停車状態を維持する。   Further, in the processing flow of the target speed calculation device 301 shown in FIG. 4, both the train 2 and the train 3 proceed in steps 401 (Y) → 402 → 403 → 404, and the TO24 and TO34 of the shortest opening time and the respective Since the station entry limit position has not changed, the target speeds VO24 and VO34 are calculated. According to the target speeds VO24 and VO34, the train 2 and the train 3 perform traveling control. However, since the target speed VO24 for the train 2 is still 0, the train 2 remains stopped.

一方、列車3は、X5の位置に到達しているものの、先行する列車2によって定まる自列車の進入限界P2で定まるブレーキパターンPT2までは依然距離があることから、目標速度VO34に応じて制御することになる。列車3は、現在の速度V5(=目標速度VO34)となっているため、目標速度VO34を維持するように走行する(図6左図)。   On the other hand, although the train 3 has reached the position of X5, since there is still a distance to the brake pattern PT2 determined by the approach limit P2 of the own train determined by the preceding train 2, control is performed according to the target speed VO34. It will be. Since the train 3 has the current speed V5 (= target speed VO34), the train 3 travels so as to maintain the target speed VO34 (the left diagram in FIG. 6).

(9)時刻T5〜T6
時刻T5からT6へと進んでいる間、列車2および列車3の目標速度は、それぞれの最短開放時刻および駅進入限界位置が変動しないことから、それぞれの目標速度は、時刻T5で算出したVO24(=0)およびVO34から変動しない。すなわち、列車2は停車状態を維持する。
(9) Time T5 to T6
While traveling from time T5 to T6, the target speeds of the train 2 and the train 3 are not changed in the shortest opening time and the station entry limit position. Therefore, the target speeds are calculated according to the VO24 ( = 0) and no change from VO34. That is, the train 2 maintains a stop state.

また、列車3は、X5からX6の位置に移動するが、先行する列車2によって定まる自列車の進入限界P2で定まるブレーキパターンPT2までは依然距離があることから、目標速度VO34に応じて制御することになる。すなわち、列車3は、速度V5(=目標速度VO34)となっているため、目標速度VO34を維持するように走行する(図6左図)。   In addition, the train 3 moves from the position X5 to the position X6, but since there is still a distance to the brake pattern PT2 determined by the approach limit P2 of the own train determined by the preceding train 2, control is performed according to the target speed VO34. It will be. That is, since the train 3 has a speed V5 (= target speed VO34), the train 3 travels so as to maintain the target speed VO34 (the left figure in FIG. 6).

(10)時刻T6
時刻T6は、列車1による駅進入防止が解除された時刻である。列車2および列車3に対して、図2に示す最短解放時刻計算装置106の処理フローでは、いずれもステップ201→202→203→204(Y)→206→207→208と進み、それぞれの最短開放時刻は、この直近に出力されていたTO24およびTO34が算出される。なお、ステップ203で抽出されるNは、列車2に対してはN=0、列車3に対してはN=1となる。
(10) Time T6
Time T6 is a time when the prevention of entering the station by the train 1 is canceled. In the processing flow of the shortest release time calculation device 106 shown in FIG. 2 for train 2 and train 3, both proceed in the order of step 201 → 202 → 203 → 204 (Y) → 206 → 207 → 208, and the shortest release for each. As for the time, TO24 and TO34 that have been output most recently are calculated. Note that N extracted in step 203 is N = 0 for the train 2 and N = 1 for the train 3.

また、図4に示す目標速度算出装置301の処理フローでは、列車2および列車3に対していずれもステップ401(Y)→402→403→404と進み、列車2については最短開放時刻がTO24であるところ、駅Bまで進入可能となったため、0を超える目標速度VO26が算出され、列車2は再加速を始め駅Bに向かう。後続する列車3については、最短開放時刻がTO34であり駅進入限界位置は変化しないため、目標速度はVO34のまま変化しない。   Further, in the processing flow of the target speed calculation device 301 shown in FIG. 4, both the train 2 and the train 3 proceed in steps 401 (Y) → 402 → 403 → 404, and the shortest opening time for the train 2 is TO24. At some point, since it is possible to enter the station B, the target speed VO26 exceeding 0 is calculated, and the train 2 starts re-acceleration and heads for the station B. For the following train 3, since the shortest opening time is TO34 and the station entry limit position does not change, the target speed remains VO34.

また、列車3は、X6の位置に到達しているものの、先行する列車2によって定まる自列車の進入限界P2で定まるブレーキパターンPT2までは依然距離があることから、目標速度VO34に応じて制御することになる。すなわち、列車3は、速度V5(=目標速度VO34)となっているため、目標速度VO34を維持するように走行する(図6左図)。   In addition, although the train 3 has reached the position of X6, since there is still a distance to the brake pattern PT2 determined by the approach limit P2 of the own train determined by the preceding train 2, control is performed according to the target speed VO34. It will be. That is, since the train 3 has a speed V5 (= target speed VO34), the train 3 travels so as to maintain the target speed VO34 (the left figure in FIG. 6).

(11)時刻T6〜T7
時刻T6からT7へと進んでいる間、列車2および列車3に対して、図2に示す最短解放時刻計算装置106の処理フローでは、いずれもステップ201→202→203→204(Y)→206→207→208と進む。その結果、列車2および列車3の最短開放時刻は、この直近に出力されていたTO24およびTO34が算出される。なお、ステップ203で抽出されるNは、列車2に対してはN=0、列車3に対してはN=1となる。
(11) Time T6 to T7
In the processing flow of the shortest release time calculation device 106 shown in FIG. 2 for the train 2 and the train 3 while proceeding from the time T6 to the time T7, both step 201 → 202 → 203 → 204 (Y) → 206 → Go to 207 → 208. As a result, the latest opening times of the train 2 and the train 3 are calculated as the TO24 and TO34 that have been output most recently. Note that N extracted in step 203 is N = 0 for the train 2 and N = 1 for the train 3.

また、図4に示す目標速度算出装置301の処理フローでは、列車2および列車3に対して、いずれもステップ401(Y)→402→403→404と進む。列車2については、最短開放時刻がTO24であるところ、駅進入限界位置が駅Bに変化しているため、0を超える目標速度VO27が算出されるとともに、駅Bに近づいているため停車に向けた制御を行う。列車3については、最短開放時刻がTO34であり、進入限界は変化しないため、目標速度はVO34のまま変化しない。   Further, in the processing flow of the target speed calculation device 301 shown in FIG. 4, both the train 2 and the train 3 proceed in steps 401 (Y) → 402 → 403 → 404. For train 2, when the shortest opening time is TO24, since the station entry limit position has changed to station B, the target speed VO27 exceeding 0 is calculated, and the vehicle is approaching station B. Control. For train 3, the shortest opening time is TO34, and the approach limit does not change, so the target speed remains VO34.

さらに、列車3は、位置がX6からX7に移動するものの、走行中の先行する列車2によって定まる自列車の進入限界P2で定まるブレーキパターンPT2まで、また、先行する列車2が駅Bに停車後は駅進入限界位置で定まるブレーキパターンPT3までは、距離があることから、目標速度VO34に応じて制御することになる。すなわち、列車3は、速度V5(=目標速度VO34)となっているため、目標速度VO34を維持するように走行する(図6左図)。   Furthermore, although the position of the train 3 moves from X6 to X7, up to the brake pattern PT2 determined by the approach limit P2 of the own train determined by the preceding train 2 that is running, and after the preceding train 2 stops at the station B Since there is a distance to the brake pattern PT3 determined by the station entry limit position, control is performed according to the target speed VO34. That is, since the train 3 has a speed V5 (= target speed VO34), the train 3 travels so as to maintain the target speed VO34 (the left figure in FIG. 6).

(12)時刻T7
時刻T7は、列車2が出発する時刻である。列車3に対して、図2に示す最短解放時刻計算装置106の処理フローでは、ステップ201→202→203→204(Y)→206→207→208と進み、最短開放時刻は直近で出力されたTO34が算出される。なお、ステップ203で抽出されるNは、列車3に対してN=0となる。
(12) Time T7
Time T7 is the time when the train 2 departs. In the processing flow of the shortest release time calculation device 106 shown in FIG. 2 for the train 3, the process proceeds from step 201 → 202 → 203 → 204 (Y) → 206 → 207 → 208, and the shortest release time was output most recently. TO34 is calculated. Note that N extracted in step 203 is N = 0 for the train 3.

また、図4に示す目標速度算出装置301の処理フローでは、列車3に対してステップ401(Y)→402→403→404と進み、最短開放時刻がTO34であり進入限界は変化しないため、目標速度はVO34のまま変化しない。   In the processing flow of the target speed calculation device 301 shown in FIG. 4, the process proceeds from the train 401 to Step 401 (Y) → 402 → 403 → 404, the shortest opening time is TO34, and the approach limit does not change. The speed remains unchanged at VO34.

一方、列車3は、X7の位置に到達するものの、先行する列車2によって定まる自列車の進入限界が駅進入限界位置と同値であり、駅進入限界位置で定まるブレーキパターンPT3までは距離があることから、目標速度VO34に応じて制御することになる。すなわち、列車3は、速度V5(=目標速度VO34)となっているため、目標速度VO34を維持するように走行する(図6左図)。   On the other hand, although the train 3 reaches the position of X7, the approach limit of the own train determined by the preceding train 2 is the same value as the station entry limit position, and there is a distance to the brake pattern PT3 determined by the station entry limit position Therefore, control is performed according to the target speed VO34. That is, since the train 3 has a speed V5 (= target speed VO34), the train 3 travels so as to maintain the target speed VO34 (the left figure in FIG. 6).

(13)時刻T8
時刻T8は、列車3に対して先行する列車2による駅進入防止が解除された時刻である。列車3に対して、図2に示す最短解放時刻計算装置106の処理フローでは、ステップ201→202→203→204(Y)→206→207→208と進み、その結果、最短開放時刻は、この直近に出力されていたTO34が算出される。なお、ステップ203で抽出されるNは、列車3に対してはN=0となる。
(13) Time T8
Time T <b> 8 is the time when the prevention of entering the station by the train 2 that precedes the train 3 is canceled. In the processing flow of the shortest release time calculation device 106 shown in FIG. 2 for the train 3, the process proceeds from step 201 → 202 → 203 → 204 (Y) → 206 → 207 → 208. The most recently output TO 34 is calculated. Note that N extracted in step 203 is N = 0 for the train 3.

また、図4に示す目標速度算出装置301の処理フローでは、ステップ401(Y)→402→403→404と進み、最短開放時刻はTO34であるところ、駅Bまで進入可能となったため、これまでの目標速度VO34を超える目標速度VO38が算出される。このため、列車3は再加速を始め、駅Bに向かう。なお、この時点で、列車3はちょうど駅進入限界位置に到達し、無駄な制動をかけることなく走行できていることが理解できる。   Further, in the processing flow of the target speed calculation device 301 shown in FIG. 4, the process proceeds from step 401 (Y) → 402 → 403 → 404, and the shortest opening time is TO34. A target speed VO38 exceeding the target speed VO34 is calculated. For this reason, the train 3 starts re-acceleration and heads for the station B. At this time, it can be understood that the train 3 has just reached the station entry limit position and can travel without applying unnecessary braking.

時刻T8以降となれば、列車3は、駅Bに向かって、図6左図に示すような速度パターンによって運行を行う。   If it becomes after time T8, the train 3 will operate toward the station B according to a speed pattern as shown in the left diagram of FIG.

以上のとおり、本発明に係る制御を実施することにより、先行列車の出発遅延で起こる後続列車の駅間停止を最小限に抑制することが可能となり、消費エネルギーの増大を防ぐことができる。また、進入限界が解除される時点に当該進入限界に到達するように制御することで、遅延の増大や波及を防ぐことが可能となる。   As described above, by performing the control according to the present invention, it is possible to minimize the stop of the subsequent train between stations that occurs due to the departure delay of the preceding train, and it is possible to prevent an increase in energy consumption. Further, by controlling so as to reach the approach limit when the approach limit is released, it becomes possible to prevent an increase in the delay and the spread.

図7は、本発明の実施例2に係るシステム構成の一例およびデータフローを示す図である。実施例2では、図7に示すとおり、図1に示す列車102および自動列車走行装置111を、それぞれ列車701および列車走行装置702に置き換えたシステム構成になっている。なお、図1と同じ番号の構成要素については実施例1と同じ内容であるため、以下ではその説明を省略する。   FIG. 7 is a diagram illustrating an example of a system configuration and data flow according to the second embodiment of the present invention. In the second embodiment, as shown in FIG. 7, the train 102 and the automatic train travel device 111 shown in FIG. 1 are replaced with a train 701 and a train travel device 702, respectively. The components having the same numbers as those in FIG. 1 have the same contents as those in the first embodiment, and hence the description thereof is omitted below.

図7の下図に示す列車701は、車上側受信装置108、列車の加減速特性を記録するデータベース109、現在の列車速度および速度位置に関する計測装置110および走行方法を決定する列車走行装置702とから構成される。   The train 701 shown in the lower diagram of FIG. 7 includes an upper-side receiving device 108, a database 109 that records the acceleration / deceleration characteristics of the train, a measuring device 110 relating to the current train speed and speed position, and a train traveling device 702 that determines a traveling method. Composed.

車上側受信装置108は、地上装置101から、最短解放時刻151および駅進入限界位置152を受信するとともに、信号装置(図示せず)から自列車の前方を走行している列車との関係で定まる自列車進入限界位置153を受信する。   The vehicle upper side receiving device 108 receives the shortest release time 151 and the station entry limit position 152 from the ground device 101 and is determined by the relationship with the train traveling in front of the own train from the signal device (not shown). The own train approach limit position 153 is received.

速度計測装置110は、現在の列車速度154および現在の列車速度154を積分することで得られる現在の列車位置155を計測する。   The speed measuring device 110 measures the current train position 155 obtained by integrating the current train speed 154 and the current train speed 154.

列車走行装置702は、最短解放時刻151、駅進入限界位置152、自列車進入限界位置153、現在の列車速度154、現在の列車位置155および加減速特性156を基にして、走行方法を決定する。   The train travel device 702 determines a travel method based on the shortest release time 151, the station entry limit position 152, the own train entry limit position 153, the current train speed 154, the current train position 155, and the acceleration / deceleration characteristics 156. .

図8は、列車走行装置702の構成の一例を示す図である。列車走行装置702は、図3に示す実施例1の自動列車走行装置111から、走行パターンデータベース302を除くとともに、走行決定装置303を運転支援装置801に置き換えた構成であり、それ以外(目標速度算出装置301)には変更はない。   FIG. 8 is a diagram illustrating an example of the configuration of the train travel device 702. The train travel device 702 has a configuration in which the travel pattern database 302 is removed from the automatic train travel device 111 of the first embodiment shown in FIG. 3 and the travel determination device 303 is replaced with a drive support device 801. There is no change in the calculation device 301).

運転支援装置801は、最短解放時刻151、自列車進入限界位置153、現在の列車速度154、現在の列車位置155および目標速度351を基にして、運転支援情報を決定する。運転支援装置801は、表示部を有する構成としてもよい。
図9は、運転支援装置801によって表示される運転支援画面の一構成例を示す図である。
The driving support device 801 determines driving support information based on the shortest release time 151, the own train approach limit position 153, the current train speed 154, the current train position 155, and the target speed 351. The driving support device 801 may have a display unit.
FIG. 9 is a diagram illustrating a configuration example of a driving support screen displayed by the driving support device 801.

図示のように、画面の左上部分に、現在時刻、最短解放時刻151、最短解放時刻151と現在時刻との差分である残時間を表示し、画面左側部分に、速度計を表示し、この速度計上に目標速度351および現在の列車速度154を表示する。また、画面右側部分に、横軸を時刻、縦軸を位置とした運転履歴情報および運転目標情報を表示する。これらの情報に関しては、現在の列車位置155と現在時刻を組み合わせることで運転履歴情報を、また、最短解放時刻151と自列車進入限界位置153を組み合わせることで運転目標情報を、それぞれ生成することが可能である。   As shown in the figure, the current time, the shortest release time 151, the remaining time that is the difference between the shortest release time 151 and the current time are displayed in the upper left part of the screen, and a speedometer is displayed in the left part of the screen. The target speed 351 and the current train speed 154 are displayed in the account. In addition, on the right side of the screen, the operation history information and the operation target information are displayed with the time on the horizontal axis and the position on the vertical axis. Regarding these pieces of information, driving history information can be generated by combining the current train position 155 and the current time, and driving target information can be generated by combining the shortest release time 151 and the own train entry limit position 153. Is possible.

以上のとおり、運転支援装置801が生成する運転支援情報に基づいて運転士が運転することによって、先の図6に示すような列車制御を行うことが可能となる。その結果、実施例2によっても、前述した実施例1と同様の効果を奏することができる。   As described above, when the driver drives based on the driving support information generated by the driving support device 801, it is possible to perform the train control as shown in FIG. As a result, even in the second embodiment, the same effects as in the first embodiment can be obtained.

図10は、本発明の実施例3に係るシステム構成の一例およびデータフローを示す図である。先の実施例1と異なる点は、実施例1の列車102の自動列車走行装置111が有する目標速度算出装置301の機能を、実施例3の地上装置1001側に持たせるために、地上装置1001が、実施例1の地上装置101が備える構成に加えて、列車データベース1003、列車位置管理装置1004および目標速度算出装置1005を設けた点である。ただし、実施例3も先の実施例1と同様に、管轄する路線の情報を管理する地上装置1001から、管轄する路線を走行する列車1002A、1002B、1002C、…(以下、全てを総称して「列車1002」とする)に対して情報を送信し、列車1002(1002A、1002B、1002C、…)は、送信された情報を基に自らを制御する形態である。   FIG. 10 is a diagram illustrating an example of a system configuration and a data flow according to the third embodiment of the present invention. The difference from the first embodiment is that the ground device 1001 has the function of the target speed calculation device 301 of the automatic train traveling device 111 of the train 102 of the first embodiment on the ground device 1001 side of the third embodiment. However, in addition to the structure with which the ground apparatus 101 of Example 1 is provided, the train database 1003, the train position management apparatus 1004, and the target speed calculation apparatus 1005 are provided. However, in the same way as in the first embodiment, the third embodiment also uses trains 1002A, 1002B, 1002C,... (Hereinafter collectively referred to as the trains 1001A, 1002C,... Information is transmitted to “train 1002”), and the train 1002 (1002A, 1002B, 1002C,...) Controls itself based on the transmitted information.

地上装置1001が、実施例1の地上装置101から追加した構成要素について、以下に説明する。
列車データベース1003は、管轄する路線を走行する列車に関する加減速特性を記録格納している。
The components added by the ground device 1001 from the ground device 101 according to the first embodiment will be described below.
The train database 1003 records and stores acceleration / deceleration characteristics relating to trains traveling on the jurisdiction.

列車位置管理装置1004は、管轄する路線を走行する列車に関する列車位置1051をリアルタイムで管理する。   The train position management device 1004 manages the train position 1051 related to the train traveling on the jurisdiction line in real time.

目標速度算出装置1005は、最短解放時刻151、駅進入限界位置152、ダイヤデータベース105からの情報、列車データベース1003に記録された列車の加減速特性および列車位置管理装置1004からの列車位置1051に基づいて、列車1002(1002A、1002B、1002C、…)の目標速度1052A、1052B、1052C、…(以下、全てを総称して「目標速度1052」とする)を計算する。目標速度算出装置1005からの目標速度1052(1052A、1052B、1052C、…)は、地上側送信装置1006から列車1002(1002A、1002B、1002C、…)に送信される。   The target speed calculation device 1005 is based on the shortest release time 151, the station entry limit position 152, information from the diagram database 105, the train acceleration / deceleration characteristics recorded in the train database 1003, and the train position 1051 from the train position management device 1004. Then, the target speeds 1052A, 1052B, 1052C,... Of the train 1002 (1002A, 1002B, 1002C,...) (Hereinafter collectively referred to as “target speed 1052”) are calculated. A target speed 1052 (1052A, 1052B, 1052C,...) From the target speed calculation apparatus 1005 is transmitted from the ground side transmission apparatus 1006 to the train 1002 (1002A, 1002B, 1002C,...).

一方、図10の下図に示す列車1002は、前述のとおり実施例1の目標速度算出装置301を有さない。車上側受信装置108は、地上装置1001から目標速度1052を受信するとともに、信号装置(図示せず)から自列車の前方を走行している列車との関係で定まる自列車進入限界位置153を受信する。   On the other hand, the train 1002 shown in the lower part of FIG. 10 does not have the target speed calculation device 301 of the first embodiment as described above. The vehicle upper side receiving device 108 receives the target speed 1052 from the ground device 1001 and receives the own train approach limit position 153 determined by the relationship with the train traveling in front of the own train from a signal device (not shown). To do.

列車の加減速特性を記録するデータベース109、現在の列車速度154および現在の列車速度154を積分することで得られる現在の列車位置155を計測する速度計測装置110および(位置、速度)の集合で構成される自列車の目標走行パターン352を記憶する走行パターンデータベース302に関しては、実施例1と同様である。   A set of a database 109 that records the acceleration / deceleration characteristics of a train, a current train speed 154 and a speed measurement device 110 that measures the current train position 155 obtained by integrating the current train speed 154 and (position, speed) The traveling pattern database 302 that stores the target traveling pattern 352 of the own train that is configured is the same as in the first embodiment.

走行決定装置1007は、目標走行パターン352、目標速度1052、自列車進入限界位置153、現在の列車速度154、現在の列車位置155および加減速特性156を基にして、走行方法を決定する。   The travel determination device 1007 determines a travel method based on the target travel pattern 352, the target speed 1052, the own train approach limit position 153, the current train speed 154, the current train position 155, and the acceleration / deceleration characteristics 156.

列車1002は、走行決定装置1007が決定した走行方法に従って、自動運転により運転を行う。   The train 1002 operates by automatic operation according to the traveling method determined by the traveling determination device 1007.

ここで、地上装置1001に設けた目標速度計算機能1005は、図4に示す目標速度算出装置301の処理フローと同じであり、ステップ404で使用する列車の現在位置155(X[m])を列車位置管理装置1004からの列車位置1051に変更すればよい。   Here, the target speed calculation function 1005 provided in the ground device 1001 is the same as the processing flow of the target speed calculation device 301 shown in FIG. 4, and the current position 155 (X [m]) of the train used in step 404 is determined. What is necessary is just to change to the train position 1051 from the train position management apparatus 1004.

一方、列車1002が有する走行決定装置1007の内部構成は、図5に示す走行決定装置303の目標速度351を、地上装置1001から受信する目標速度1052に変更することとなる。また、自動列車走行装置1007を、実施例2に係る運転支援装置801で代用してもよい。   On the other hand, the internal configuration of the travel determination device 1007 included in the train 1002 changes the target speed 351 of the travel determination device 303 shown in FIG. 5 to the target speed 1052 received from the ground device 1001. In addition, the driving support device 801 according to the second embodiment may be substituted for the automatic train traveling device 1007.

以上のとおり、実施例3においても、先の図6に示すような列車制御を行うことが可能となる。その結果、実施例3によっても、前述した実施例1および実施例2と同様の効果を奏することができる。   As described above, also in Example 3, train control as shown in FIG. 6 can be performed. As a result, also in Example 3, the same effects as those of Example 1 and Example 2 described above can be obtained.

101:地上装置、102,102A,102B,102C:列車、
103:発着状況管理装置、104:時隔データベース、105:ダイヤデータベース、
106:最短解放時刻計算装置、107:地上側送信装置、108:車上側受信装置、
109:列車の加減速特性を記録するデータベース、110:速度計測装置、
111:列車走行装置、151:最短解放時刻、152:駅進入限界位置、
153:自列車進入限界位置、154:現在の列車速度、155:現在の列車位置、
156:加減速特性、301:目標速度算出装置、302:走行パターンデータベース、
303:走行決定装置、351:目標速度、352:自列車の目標走行パターン、
353:自列車の走行指令、501:走行追従制御部、502:信号速度算出部、
503,505:比較処理部、504:目標速度制御部、
551:第1の走行指令、552:信号速度、553:追従目標速度、554:第2の走行指令、
701,701A,701B,701C:列車、702:列車走行装置、801:運転支援装置、
1001:地上装置、1002,1002A,1002B,1002C:列車、
1003:列車データベース、1004:列車位置管理装置、1005:目標速度算出装置、1006:地上側送信装置、1007:走行決定装置、
1051:列車位置、1052,1052A,1052B,1052C:目標速度、
101: Ground device, 102, 102A, 102B, 102C: Train,
103: Arrival / departure situation management device, 104: Time interval database, 105: Diamond database,
106: shortest release time calculation device, 107: ground side transmission device, 108: vehicle upper side reception device,
109: Database for recording acceleration / deceleration characteristics of trains, 110: Speed measuring device,
111: Train traveling device, 151: Shortest release time, 152: Station entry limit position,
153: Own train approach limit position, 154: Current train speed, 155: Current train position,
156: acceleration / deceleration characteristics, 301: target speed calculation device, 302: travel pattern database,
303: Travel determination device, 351: Target speed, 352: Target travel pattern of own train,
353: own train travel command, 501: travel follow-up control unit, 502: signal speed calculation unit,
503, 505: comparison processing unit, 504: target speed control unit,
551: First travel command, 552: Signal speed, 553: Follow target speed, 554: Second travel command,
701, 701A, 701B, 701C: train, 702: train traveling device, 801: driving support device,
1001: Ground equipment, 1002, 1002A, 1002B, 1002C: Train,
1003: Train database, 1004: Train position management device, 1005: Target speed calculation device, 1006: Ground side transmission device, 1007: Travel determination device,
1051: Train position, 1052, 1052A, 1052B, 1052C: Target speed,

Claims (7)

地上側が備える最短解放時刻計算部と、
列車の車上側または前記地上側が備える目標速度算出部と、
前記車上側が備える走行制御装置と
を有し、
前記最短解放時刻計算部は、前記列車の前方を走行する先行列車による占有区間の手前に前記列車を停止させるためのブレーキパターンから、目標駅における前記先行列車の出発時刻に基づいて、当該ブレーキパターンが消失するとした場合に該消失に至る最も早い時刻である最短解放時刻を計算し、
前記目標速度算出部は、前記ブレーキパターンから前記列車が前記目標駅へ進入することを防止するための駅進入限界位置を求め、前記列車の前記駅進入限界位置、現在位置、減速度および前記最短解放時刻から前記列車の目標速度を算出し、
前記走行制御装置は、前記列車の前記目標速度および現在速度並びに前記ブレーキパターンに基づいて、前記列車の走行を制御するための走行指令を決定する走行決定部または前記列車の運転者に対して自列車の運転支援情報を提供する運転支援部を備え、
前記列車の走行を、前記走行制御装置により制御する
ことを特徴とする列車制御システム。
The shortest release time calculation unit on the ground side,
A target speed calculator provided on the upper side of the train or on the ground side; and
A travel control device provided on the vehicle upper side,
The shortest release time calculation unit, based on the departure time of the preceding train at the target station, from the brake pattern for stopping the train before the occupied section by the preceding train traveling in front of the train, the brake pattern And the shortest release time which is the earliest time to reach the disappearance
The target speed calculation unit obtains a station entry limit position for preventing the train from entering the target station from the brake pattern, the station entry limit position of the train, the current position, the deceleration, and the shortest Calculate the target speed of the train from the release time,
The travel control device is configured to automatically execute a travel determination unit that determines a travel command for controlling travel of the train or a driver of the train based on the target speed and current speed of the train and the brake pattern. It has a driving support section that provides train driving support information,
A train control system, wherein the travel of the train is controlled by the travel control device.
請求項1に記載の列車制御システムであって、
前記走行制御装置が前記走行決定部を備える場合に、
前記走行決定部は、目標走行パターンから前記列車の現在位置および現在速度に基づいて第1の走行指令を求め、前記ブレーキパターンから前記列車の現在位置に基づいて算出したブレーキパターン速度と前記目標速度とから小さい方の速度を第2の目標速度とし、前記列車の速度を前記第2の目標速度とするための走行指令を第2の走行指令とし、前記第1の走行指令および前記第2の走行指令から小さい方を前記列車の走行指令として決定する
ことを特徴とする列車制御システム。
The train control system according to claim 1,
When the travel control device includes the travel determination unit,
The travel determination unit obtains a first travel command based on the current position and current speed of the train from a target travel pattern, and calculates the brake pattern speed and the target speed calculated based on the current position of the train from the brake pattern. The smaller one of the speeds is set as the second target speed, the travel command for setting the speed of the train as the second target speed is set as the second travel command, and the first travel command and the second A train control system for determining a smaller one from a travel command as a travel command for the train.
請求項1に記載の列車制御システムであって、
前記走行制御装置が前記運転支援部を備える場合に、
前記運転支援部は、前記列車の前記目標速度、現在速度、前記最短解放時刻および現在時刻を表示する表示部を有する
ことを特徴とする列車制御システム。
The train control system according to claim 1,
When the travel control device includes the driving support unit,
The driving support unit includes a display unit that displays the target speed, the current speed, the shortest release time, and the current time of the train.
列車のブレーキパターンを作成して当該ブレーキパターンによって列車の速度を制御する列車制御方法であって、
前記ブレーキパターンとして、前記列車の前方を走行する先行列車による占有区間の手前に前記列車を停止させるためのブレーキパターンを作成し、
目標駅における前記先行列車の出発時刻に基づいて、当該ブレーキパターンが消失するとした場合に該消失に至る最も早い時刻である最短解放時刻を計算し、
前記列車の速度を逐次制御して、前記最短解放時刻に前記列車を前記ブレーキパターンに沿った走行に到達させる
ことを特徴とする列車制御方法。
A train control method for creating a train brake pattern and controlling the train speed by the brake pattern,
As the brake pattern, create a brake pattern for stopping the train before the occupied section by the preceding train that runs in front of the train,
Based on the departure time of the preceding train at the target station, if the brake pattern disappears, calculate the shortest release time that is the earliest time to reach the disappearance,
A train control method characterized by sequentially controlling the speed of the train to cause the train to travel along the brake pattern at the shortest release time.
請求項4に記載の列車制御方法であって、
前記ブレーキパターンから前記列車が前記目標駅へ進入することを防止するための駅進入限界位置を求め、
前記列車の前記駅進入限界位置、現在位置、減速度および前記最短解放時刻から前記列車の目標速度を算出し、
前記目標速度に基づいて前記列車の走行指令を決定する
ことを特徴とする列車制御方法。
The train control method according to claim 4,
Finding the station entry limit position for preventing the train from entering the target station from the brake pattern,
Calculate the target speed of the train from the station entry limit position, current position, deceleration and the shortest release time of the train,
A train control method for determining a travel command for the train based on the target speed.
請求項5に記載の列車制御方法であって、
前記列車の走行指令は、
目標走行パターンから前記列車の現在位置および現在速度に基づいて第1の走行指令を求め、前記ブレーキパターンから前記列車の現在位置に基づいて算出したブレーキパターン速度と前記目標速度とから小さい方の速度を第2の目標速度とし、前記列車の速度を前記第2の目標速度とするための走行指令として第2の走行指令を求め、前記第1の走行指令および前記第2の走行指令から小さい方に決定される
ことを特徴とする列車制御方法。
The train control method according to claim 5,
The train command is
A first travel command is obtained based on the current position and current speed of the train from the target travel pattern, and the smaller speed from the brake pattern speed calculated based on the current position of the train from the brake pattern and the target speed Is the second target speed, the second travel command is obtained as a travel command for setting the train speed to the second target speed, and the smaller one is obtained from the first travel command and the second travel command. A train control method characterized by being determined.
列車の車上装置であって、
受信部と、
目標速度算出部と、
走行決定部または運転支援部と
を備え、
前記受信部は、地上装置が、自列車の前方を走行する先行列車による占有区間の手前に自列車を停止させるためのブレーキパターンから、目標駅における前記先行列車の出発時刻に基づいて、当該ブレーキパターンが消失するとした場合に該消失に至る最も早い時刻として計算した最短解放時刻を、当該地上装置から受信し、
前記目標速度算出部は、前記ブレーキパターンから自列車が前記目標駅へ進入することを防止するための駅進入限界位置を求め、自列車の前記駅進入限界位置、現在位置、減速度および前記最短解放時刻から自列車の目標速度を算出し、
前記走行決定部は、目標走行パターンから自列車の現在位置および現在速度に基づいて第1の走行指令を求め、前記ブレーキパターンから自列車の現在位置に基づいて算出したブレーキパターン速度と前記目標速度とから小さい方の速度を第2の目標速度とし、自列車の速度を前記第2の目標速度とするための走行指令を第2の走行指令とし、前記第1の走行指令および前記第2の走行指令から小さい方を自列車の走行指令として決定し、
前記運転支援部は、自列車の前記目標速度、現在速度、前記最短解放時刻および現在時刻を表示する表示部を有する
ことを特徴とする列車の車上装置。
A train on-board device,
A receiver,
A target speed calculator,
With a travel decision unit or a driving support unit,
From the brake pattern for the ground device to stop the own train before the occupied section by the preceding train traveling in front of the own train based on the departure time of the preceding train at the target station. When the pattern disappears, the shortest release time calculated as the earliest time to reach the disappearance is received from the ground device,
The target speed calculation unit obtains a station entry limit position for preventing the own train from entering the target station from the brake pattern, the station entry limit position of the own train, the current position, the deceleration, and the shortest Calculate the target speed of your train from the release time,
The travel determination unit obtains a first travel command based on the current position and current speed of the own train from the target travel pattern, and calculates the brake pattern speed and the target speed calculated based on the current position of the own train from the brake pattern. The second speed is used as the second target speed, and the second travel command is used to set the speed of the own train as the second target speed. The first travel command and the second Decide the smaller one from the running command as the running command for your train,
The driving support unit includes a display unit that displays the target speed, the current speed, the shortest release time, and the current time of the own train.
JP2017042396A 2017-03-07 2017-03-07 Train control system, train control method and on-board equipment of train Active JP6802091B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2017042396A JP6802091B2 (en) 2017-03-07 2017-03-07 Train control system, train control method and on-board equipment of train
PCT/JP2017/040345 WO2018163508A1 (en) 2017-03-07 2017-11-09 Train control system, train control method, and train on-board device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017042396A JP6802091B2 (en) 2017-03-07 2017-03-07 Train control system, train control method and on-board equipment of train

Publications (3)

Publication Number Publication Date
JP2018144676A true JP2018144676A (en) 2018-09-20
JP2018144676A5 JP2018144676A5 (en) 2019-12-12
JP6802091B2 JP6802091B2 (en) 2020-12-16

Family

ID=63448435

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017042396A Active JP6802091B2 (en) 2017-03-07 2017-03-07 Train control system, train control method and on-board equipment of train

Country Status (2)

Country Link
JP (1) JP6802091B2 (en)
WO (1) WO2018163508A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7413177B2 (en) 2020-07-21 2024-01-15 株式会社東芝 Driving curve creation device, driving support device, and driving control device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05193502A (en) * 1991-10-25 1993-08-03 Toshiba Corp Optimum traveling pattern calculating device and system
JPH0740835A (en) * 1993-07-30 1995-02-10 Nippon Signal Co Ltd:The Digital transmission type automatic train control device
WO2015118671A1 (en) * 2014-02-07 2015-08-13 三菱電機株式会社 Train travel management device
JP2017030674A (en) * 2015-08-05 2017-02-09 株式会社東芝 Train control system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05193502A (en) * 1991-10-25 1993-08-03 Toshiba Corp Optimum traveling pattern calculating device and system
JPH0740835A (en) * 1993-07-30 1995-02-10 Nippon Signal Co Ltd:The Digital transmission type automatic train control device
WO2015118671A1 (en) * 2014-02-07 2015-08-13 三菱電機株式会社 Train travel management device
JP2017030674A (en) * 2015-08-05 2017-02-09 株式会社東芝 Train control system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7413177B2 (en) 2020-07-21 2024-01-15 株式会社東芝 Driving curve creation device, driving support device, and driving control device

Also Published As

Publication number Publication date
JP6802091B2 (en) 2020-12-16
WO2018163508A1 (en) 2018-09-13

Similar Documents

Publication Publication Date Title
CN102470868B (en) Vehicle control device, vehicle control method, and vehicle control system
JP5944229B2 (en) Train control device
JP6351142B2 (en) Operation management system, operation management method and program
JP2011042361A (en) Apparatus and method for controlling speed in automatic train operation
JP2013257856A (en) Apparatus and method for speed control on curved road in smart cruise control system
US10150491B2 (en) Device and method for controlling train
JP5972781B2 (en) Time-series curve plotter
JP2005231447A (en) Train operation support device
JPH10329718A (en) Train operation control system
JP6466116B2 (en) Operation control system
WO2018163508A1 (en) Train control system, train control method, and train on-board device
WO2018008337A1 (en) Running pattern creation device and running pattern creation method
KR20150137902A (en) Apparatus for controlling velocity, center managing server, system and method for controlling velocity vechicles of using the same
JP2006006030A (en) Drive pattern creation device, vehicle speed control device and vehicle drive support device
WO2019135310A1 (en) Operation assistance system
JP2018034610A (en) Travel control system and travel control device
JPH06321115A (en) Train controller
US20170210405A1 (en) Train control device
JP2019089449A (en) Device, method and program for train travel control
JP5364682B2 (en) Train speed control method and apparatus
JP7376413B2 (en) Autonomous vehicle operation management device and operation management method
JP2017204197A (en) Drive support method and drive support system
JP7045287B2 (en) Train control system and train control method
JP2005280542A (en) Atc/o device
CN110626391A (en) Information prediction method of passenger information system

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20191101

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20191101

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200721

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200908

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20201124

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20201126

R150 Certificate of patent or registration of utility model

Ref document number: 6802091

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150