Prior art keywords
train
speed
travel
unit
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2016168423A
Other languages
Japanese (ja)
Inventor
征邦 明石
Yukikuni Akashi
征邦 明石
信 小熊
Makoto Koguma
信 小熊
幸徳 外崎
Yukinori Sotozaki
幸徳 外崎
辰徳 鈴木
Tatsunori Suzuki
辰徳 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Toshiba Infrastructure Systems and Solutions Corp
Original Assignee
Toshiba Corp
Toshiba Infrastructure Systems and Solutions Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp, Toshiba Infrastructure Systems and Solutions Corp filed Critical Toshiba Corp
Priority to JP2016168423A priority Critical patent/JP2018034610A/en
Publication of JP2018034610A publication Critical patent/JP2018034610A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Electric Propulsion And Braking For Vehicles (AREA)
  • Train Traffic Observation, Control, And Security (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a travel control system which considers a positional relationship with a subsequent train and inhibits a train delay.SOLUTION: A travel control system comprises: a ground control device 101; and on-board control devices each of which is mounted on each of plural trains which travel on a roadway. The on-board control device has a first transmission part, and the ground control part comprises: a reception part 305; a prediction part 306; a generation part 311; and a second transmission part 309. The reception part receives a position and speed of a train from the on-board control device. The prediction part predicts an operation diagram of a train which is a control object and an operation diagram of a subsequent train subsequent to the train which is the control object traveling on the railway, based on the position and speed of the train. The generation part generates a travel plan in which sections where acceleration and deceleration is performed when the train which is the control object travels on the railway are adjusted, according to the predicted operation diagram. The second transmission part sends the travel plan to the on-board control device mounted on the train.SELECTED DRAWING: Figure 3

Description

本発明の実施形態は、走行制御システム、及び走行制御装置に関する。   Embodiments described herein relate generally to a travel control system and a travel control apparatus.

従来から、列車が走行している際に、先行列車に近接した場合に、運転保安システムにより自列車に保安ブレーキを作動させる技術が提案されている。このような技術においては、自列車に遅れが生じたりする可能性がある。   2. Description of the Related Art Conventionally, a technique has been proposed in which a safety brake is actuated on a local train by an operation security system when a train is running and approaches a preceding train. In such a technique, there is a possibility that the own train will be delayed.

そこで、先行列車の走行を予測して、自列車を走行させることで、自列車の加減速を抑止する技術が提案されている。   Then, the technique which suppresses the acceleration / deceleration of the own train is proposed by predicting the traveling of the preceding train and causing the own train to travel.

特開2002−204507号公報JP 2002-204507 A 特開2015−20637号公報Japanese Patent Laying-Open No. 2015-20737

しかしながら、従来技術においては、先行列車との位置関係による、自列車の加減速制御に留まり、後続列車との位置関係については考慮していなかった。   However, in the prior art, the acceleration / deceleration control of the own train based on the positional relationship with the preceding train is limited, and the positional relationship with the following train is not considered.

実施形態の走行制御システムは、地上制御装置と、線路上を走行する複数の列車の各々に搭載された車上制御装置と、を備える走行制御システムであって、車上制御装置は、第1の送信部を備え、地上制御装置は、受信部と、予測部と、生成部と、第2の送信部と、を備える。第1の送信部は、車上制御装置が搭載された列車の位置と速度とを地上制御装置に送信する。受信部は、複数の列車の各々に搭載された車上制御装置から、当該車上制御装置が搭載された列車の位置と速度とを受信する。予測部は、受信部が受信した列車の位置と速度とに基づいて、制御対象となる列車の運行ダイヤと、線路上を走行する制御対象となる列車の後ろの後続列車の運行ダイヤと、を予測する。生成部は、予測部が予測した運行ダイヤに従って制御対象となる列車と、後続列車と、が走行した場合における、制御対象となる列車と後続列車との位置関係に基づいて、制御対象となる列車が線路を走行する際の加速及び減速を行う区間を調整した、当該線路上の位置の変化に従った速度を表した走行計画を生成する。第2の送信部は、生成部が生成した走行計画を、制御対象となる列車に搭載された車上制御装置に送信する。   A travel control system according to an embodiment is a travel control system including a ground control device and an on-board control device mounted on each of a plurality of trains traveling on a track. The on-board control device is a first control device. The ground control device includes a reception unit, a prediction unit, a generation unit, and a second transmission unit. The first transmission unit transmits the position and speed of the train on which the on-board control device is mounted to the ground control device. The receiving unit receives the position and speed of the train on which the on-board control device is mounted from the on-board control device mounted on each of the plurality of trains. Based on the position and speed of the train received by the receiving unit, the prediction unit calculates the operation schedule of the train to be controlled and the operation diagram of the subsequent train behind the train to be controlled running on the track. Predict. The generator is a train to be controlled based on the positional relationship between the train to be controlled and the following train when the train to be controlled and the following train travel according to the operation schedule predicted by the prediction unit. A travel plan that expresses the speed according to the change in the position on the track, which adjusts the section for acceleration and deceleration when traveling on the track, is generated. A 2nd transmission part transmits the travel plan which the production | generation part produced | generated to the on-board control apparatus mounted in the train used as a control object.

図1は、第1の実施形態における列車走行管理システムの構成を例示した図である。FIG. 1 is a diagram illustrating a configuration of a train travel management system in the first embodiment. 図2は、第1の実施形態の列車に搭載された車上システムの構成例を示した図である。FIG. 2 is a diagram illustrating a configuration example of the on-board system mounted on the train according to the first embodiment. 図3は、第1の実施形態の地上システムの各構成を例示した図である。FIG. 3 is a diagram illustrating each configuration of the ground system according to the first embodiment. 図4は、第1の実施形態の運転曲線生成部の運転曲線の生成手法の第1の例を示した図である。FIG. 4 is a diagram illustrating a first example of the operation curve generation method of the operation curve generation unit according to the first embodiment. 図5は、第1の実施形態の運転曲線生成部の運転曲線の生成手法の第2の例を示した図である。FIG. 5 is a diagram illustrating a second example of the operation curve generation method of the operation curve generation unit according to the first embodiment. 図6は、第1の実施形態の運転曲線生成部の運転曲線の生成手法の第3の例を示した図である。FIG. 6 is a diagram illustrating a third example of the operation curve generation method of the operation curve generation unit according to the first embodiment. 図7は、第1の実施形態の地上制御装置における運転曲線の生成処理の手順を示すフローチャートである。FIG. 7 is a flowchart showing the procedure of the operation curve generation process in the ground control device of the first embodiment. 図8は、第2の実施形態の列車に搭載された車上システムの構成例を示した図である。FIG. 8 is a diagram illustrating a configuration example of the on-board system mounted on the train according to the second embodiment. 図9は、第3の実施形態の走行管理システムの概念を例示した図である。FIG. 9 is a diagram illustrating the concept of the travel management system according to the third embodiment. 図10は、第3の実施形態の車上制御装置の構成例を示した図である。FIG. 10 is a diagram illustrating a configuration example of the on-vehicle control device of the third embodiment.

(第1の実施形態)
図1は、第1の実施形態における列車走行管理システムの構成を例示した図である。図1に示される列車走行管理システムは、地上システム100と、列車毎に設けられている車上システム150と、から構成されている。
(First embodiment)
FIG. 1 is a diagram illustrating a configuration of a train travel management system in the first embodiment. The train travel management system shown in FIG. 1 includes a ground system 100 and an on-board system 150 provided for each train.

地上システム100は、地上制御装置101と、運行管理システム102と、ATC地上装置103と、地上基地局105a、105b、105cと、を備えている。これらの構成は、地上ネットワーク110を介して接続されている。   The ground system 100 includes a ground control device 101, an operation management system 102, an ATC ground device 103, and ground base stations 105a, 105b, and 105c. These components are connected via the terrestrial network 110.

運行管理システム102は、必要に応じて地上制御装置101に対して、運行ダイヤを送信する。   The operation management system 102 transmits an operation diagram to the ground control device 101 as necessary.

ATC地上装置103は、軌道回路を構成している、線路180のレールを介して閉そく区間毎に列車が存在するか否かを検知し、検知結果をATC信号として、レールを介して列車内の(図示しない)ATC車上装置に送信する。また、ATC地上装置103は、各列車に対して、前方の先行列車までの位置に関する情報(例えば先行列車までの閉そく区間数など)を、レールを介して送信する。   The ATC ground device 103 detects whether or not there is a train for each block section through the rail of the track 180 that constitutes the track circuit, and uses the detection result as an ATC signal, It transmits to the ATC on-board device (not shown). In addition, the ATC ground device 103 transmits information on the position to the preceding preceding train (for example, the number of closed sections to the preceding train, etc.) to each train via the rail.

また、ATC地上装置103は、ATC車上装置からの情報に基づいた、進路構成情報、保守ブレーキパターンの停止位置情報、臨時速度制限情報、故障情報などの情報を、地上制御装置101に送信する。   In addition, the ATC ground device 103 transmits information such as route configuration information, maintenance brake pattern stop position information, temporary speed limit information, and failure information based on information from the ATC on-board device to the ground control device 101. .

地上基地局105a、105b、105cは、線路180に沿って設置された無線基地局であって、線路180を走行する列車(例えば、列車170a、170b)との間で情報を送受信する。   The ground base stations 105a, 105b, and 105c are wireless base stations installed along the track 180, and transmit / receive information to / from trains (for example, the trains 170a and 170b) that travel on the track 180.

列車(例えば、列車170a、170b)の各々に設けられている車上システム150には、車上制御装置151が含まれており、列車(例えば、列車170a、170b)に関する様々な制御を行う。   The on-board system 150 provided in each of the trains (for example, the trains 170a and 170b) includes the on-board control device 151, and performs various controls relating to the train (for example, the trains 170a and 170b).

図2は、第1の実施形態の列車170aに搭載された車上システム150の構成例を示した図である。図2に示されるように、車上システム150は、車上制御装置151と、速度検知装置201と、位置検知装置202と、ATC車上装置203と、を備えている。   FIG. 2 is a diagram illustrating a configuration example of the on-board system 150 mounted on the train 170a according to the first embodiment. As shown in FIG. 2, the onboard system 150 includes an onboard control device 151, a speed detection device 201, a position detection device 202, and an ATC onboard device 203.

速度検知装置201は、車軸に取り付けた速度発電機などの出力信号を処理して列車170aの速度を算出し、速度情報として、車上制御装置151に送信する。   The speed detection device 201 calculates the speed of the train 170a by processing an output signal from a speed generator attached to the axle, and transmits it to the on-board control device 151 as speed information.

位置検知装置202は、速度検知装置201により検出された速度情報を積算して、駅からの移動距離を算出するとともに、地上の定点に設置された地上子から検出された地上子信号に基づいて、移動距離に基づく位置情報を調整することで、列車170aの位置情報を算出する。本実施形態では、位置情報として、線路180上の起点地点からの距離を示したキロ程を算出するが、列車170aの位置を示す情報であれば良い。そして、位置検知装置202は、算出した位置情報を、車上制御装置151に送信する。   The position detection device 202 integrates the speed information detected by the speed detection device 201 to calculate the movement distance from the station, and based on the ground element signal detected from the ground element installed at a fixed point on the ground. The position information of the train 170a is calculated by adjusting the position information based on the movement distance. In the present embodiment, as the position information, the kilometer indicating the distance from the starting point on the track 180 is calculated, but any information indicating the position of the train 170a may be used. Then, the position detection device 202 transmits the calculated position information to the on-vehicle control device 151.

なお、本実施形態は、列車170aの速度情報や位置情報を算出する構成として、速度検知装置201や位置検知装置202を適用する例について説明するが、これらの構成に制限するものではなく、列車170aの走行状態を検出できれば、どのような装置・システムを利用しても良い。例えば、列車170aの位置情報を検出する装置として、GPS受信機を用いても良い。   In addition, although this embodiment demonstrates the example which applies the speed detection apparatus 201 and the position detection apparatus 202 as a structure which calculates the speed information and position information of the train 170a, it does not restrict | limit to these structures, A train Any device / system may be used as long as the traveling state of 170a can be detected. For example, you may use a GPS receiver as an apparatus which detects the positional information on the train 170a.

ATC車上装置203は、運転保安システムの一部であり、ATC地上装置103から受信した、前方の先行列車までの位置に関する情報に基づいて、未開通進路への進入防止や先行列車への衝突を防止する。例えば、ATC車上装置203は、先行列車の手前(外方)に停止するための保守ブレーキパターンを生成する。   The ATC on-board device 203 is a part of the driving security system, and is based on the information about the position to the preceding preceding train received from the ATC ground device 103, preventing entry to an unopened route and collision with the preceding train. To prevent. For example, the ATC on-board device 203 generates a maintenance brake pattern for stopping before (outside) the preceding train.

保守ブレーキパターンは、先行列車の手前に停止するために、列車170aの位置に対する速度が、許容された速度(照査速度)の範囲か否かを照合するための情報とする。   In order to stop before the preceding train, the maintenance brake pattern is information for checking whether the speed with respect to the position of the train 170a is within an allowable speed (check speed) range.

ATC車上装置203は、速度検知装置201による速度情報、位置検知装置202による位置情報に基づいて、列車170aの速度が、現在の列車170aの位置に対する保守ブレーキパターンの照査速度を超えたか否かを判断する。ATC車上装置203は、照査速度を超過したと判定した場合、保安ブレーキを作動させて列車170aを停車させる。また、列車170aの速度が、照査速度を所定値より下回っていた場合、保安ブレーキを解除する。例えば、先行列車が次の閉そく区間に移動し、ATC車上装置203は、運転曲線が進行方向に移動するように更新した場合に、保安ブレーキが解除され、力行可能となる。   The ATC on-board device 203 determines whether or not the speed of the train 170a exceeds the verification speed of the maintenance brake pattern for the current position of the train 170a based on the speed information from the speed detection device 201 and the position information from the position detection device 202. Judging. When it is determined that the verification speed has been exceeded, the ATC on-board device 203 activates the safety brake to stop the train 170a. In addition, when the speed of the train 170a is lower than the verification speed, the safety brake is released. For example, when the preceding train moves to the next closed section and the ATC on-board device 203 is updated so that the driving curve moves in the traveling direction, the safety brake is released and power running becomes possible.

車上制御装置151は、路線データベース251と、車両データベース252と、情報送信部253と、情報受信部254と、ノッチ情報取得部255と、ATO機能部256と、を備えている。車上制御装置151は、速度検知装置201から速度情報、位置検知装置202から位置情報を取得する。   The on-board controller 151 includes a route database 251, a vehicle database 252, an information transmission unit 253, an information reception unit 254, a notch information acquisition unit 255, and an ATO function unit 256. The on-board control device 151 acquires speed information from the speed detection device 201 and position information from the position detection device 202.

車両データベース252は、列車170aの車両に相当する車両データを記憶する。車両データとしては、列車長、列車重量などの他、編成の引張力特性テーブルおよび制動力特性テーブル(列車速度に対応した引張力または制動力の特性を定義したテーブル)、列車力行時の力行電流特性テーブルや制動時の回生電流テーブル(列車速度に対応した編成の力行電流または回生電流の特性を定義したテーブル)が含まれている。   The vehicle database 252 stores vehicle data corresponding to the vehicle of the train 170a. The vehicle data includes train length, train weight, etc., as well as train tension and braking force characteristics tables and braking force characteristics tables (tables that define the characteristics of tensile force or braking force corresponding to train speed), and power running current during train power running A characteristic table and a regenerative current table during braking (a table that defines the characteristics of the power running current or the regenerative current of the train corresponding to the train speed) are included.

路線データベース251は、走行経路上の勾配、曲線、トンネル、速度制限などの路線データを記憶している。   The route database 251 stores route data such as gradients, curves, tunnels, and speed limits on the travel route.

ノッチ情報取得部255は、列車170aの速度を制御するためのノッチ情報を取得する。   The notch information acquisition unit 255 acquires notch information for controlling the speed of the train 170a.

情報送信部253は、地上基地局105aを介して、地上制御装置101に対して、車上制御装置151が搭載された列車170aの速度情報、位置情報、及びノッチ情報をリアルタイムに送信する。   The information transmission unit 253 transmits the speed information, the position information, and the notch information of the train 170a on which the on-board control device 151 is mounted to the ground control device 101 via the ground base station 105a in real time.

情報受信部254は、地上基地局105aを介して、地上制御装置101から、列車170aを含む列車群のダイヤ情報や、列車170aを走行制御するための列車走行指令情報を、リアルタイムに受信する。受信したダイヤ情報、及び列車走行指令情報は、ATO機能部256に受け渡される。   The information receiving unit 254 receives, in real time, the schedule information of the train group including the train 170a and the train travel command information for traveling control of the train 170a from the ground control device 101 via the ground base station 105a. The received diamond information and train travel command information are transferred to the ATO function unit 256.

ATO機能部256は、取得したダイヤ情報、列車走行指令情報を参照して、列車170aの自動運転操作(力行/ブレーキ指令の出力)を行う。これにより、列車170aが走行する。   The ATO function unit 256 refers to the acquired diamond information and train travel command information, and performs an automatic driving operation (power running / brake command output) of the train 170a. Thereby, the train 170a travels.

列車走行指令情報としては、例えば、列車170aが存在する位置に対応する速度など、当該線路180上の位置の変化に従った速度が表された車両の走行計画の一種である、運転曲線が考えられるが、列車170aの走行を指示できる(自動運転制御できる)情報であれば他の情報であっても良い。   As the train travel command information, for example, an operation curve, which is a kind of vehicle travel plan in which a speed according to a change in the position on the track 180, such as a speed corresponding to a position where the train 170a exists, is considered. However, other information may be used as long as the information can instruct the traveling of the train 170a (can perform automatic operation control).

なお、ATO機能部256は、地上制御装置101と通信ができない状況においても、取得済みのダイヤ情報、路線データベース251に記憶された路線データ、及び車両データベース252に記憶された車両データ等に基づいて、列車170aの走行計画となる運転曲線を生成しても良い。   Note that the ATO function unit 256 is based on the acquired diagram information, the route data stored in the route database 251, the vehicle data stored in the vehicle database 252, etc. even in a situation where communication with the ground control device 101 is not possible. An operation curve that is a travel plan of the train 170a may be generated.

列車170aの走行を開始する際の手順について説明する。まず、列車170aの始発駅における出発準備として、運転士が車上制御装置151に列車番号を設定する。車上制御装置151が、列番情報を自動的に取得し、設定するようにしても良い。車上制御装置151に列車番号が設定された場合に、車上制御装置151は、地上制御装置101に、列車走行指令情報の送信要求を行う。地上制御装置101は、ダイヤ情報に従って生成した運転曲線を、列車走行指令情報として車上制御装置151に送信する。その後、運転士が、出発時刻以降に出発ボタンを押下した場合に、車上制御装置151のATO機能部256が自動運転を開始する。   A procedure for starting the traveling of the train 170a will be described. First, the driver sets a train number in the on-board controller 151 as preparation for departure at the first station of the train 170a. The on-board controller 151 may automatically acquire and set the column number information. When the train number is set in the on-board controller 151, the on-board controller 151 sends a transmission request for train travel command information to the ground controller 101. The ground control device 101 transmits the driving curve generated according to the diagram information to the on-board control device 151 as train travel command information. Thereafter, when the driver presses the departure button after the departure time, the ATO function unit 256 of the on-board controller 151 starts automatic operation.

次に地上制御装置101を含めた地上システムについて説明する。図3は、第1の実施形態の地上システムの各構成を例示した図である。   Next, the ground system including the ground control apparatus 101 will be described. FIG. 3 is a diagram illustrating each configuration of the ground system according to the first embodiment.

運行管理システム102は、運行ダイヤデータベース351を備えている。運行管理システム102は、運行ダイヤデータベース351に記憶された運行ダイヤで示されたダイヤ情報を、地上制御装置101等に送信する。   The operation management system 102 includes an operation diagram database 351. The operation management system 102 transmits the diagram information indicated by the operation schedule stored in the operation diagram database 351 to the ground control device 101 or the like.

地上基地局群105(地上基地局105a〜地上基地局105c)は、それぞれ受信部361と、送信部362と、を備え、列車170a〜170bと、地上制御装置101と、の間で情報の送受信を行う。   The ground base station group 105 (ground base station 105a to ground base station 105c) includes a receiving unit 361 and a transmitting unit 362, and transmits and receives information between the trains 170a to 170b and the ground control device 101. I do.

例えば、受信部361は、列車170a〜170b、又は地上制御装置101から、情報を受信する。送信部362は、列車170a〜170b、又は地上制御装置101に対して、受信部361が受信した情報を送信する。さらに、地上基地局群105は、一方の列車から受信した情報を、他方の列車に送信しても良い。   For example, the receiving unit 361 receives information from the trains 170 a to 170 b or the ground control device 101. The transmission unit 362 transmits the information received by the reception unit 361 to the trains 170a to 170b or the ground control device 101. Further, the ground base station group 105 may transmit information received from one train to the other train.

地上制御装置101は、路線データベース301と、車両データベース302と、制御データベース303と、運行履歴データベース304と、受信部305と、運行予測部306と、判定部307と、運転曲線生成部308と、送信部309と、を備えている。   The ground control apparatus 101 includes a route database 301, a vehicle database 302, a control database 303, an operation history database 304, a reception unit 305, an operation prediction unit 306, a determination unit 307, an operation curve generation unit 308, A transmission unit 309.

路線データベース301は、線路180の走行経路上の勾配、曲線、トンネル、速度制限などの路線データを記憶している。   The route database 301 stores route data such as gradients, curves, tunnels, speed limits, and the like on the travel route of the track 180.

車両データベース302は、線路180を走行する各列車の車両に相当する車両データを記憶する。   The vehicle database 302 stores vehicle data corresponding to vehicles of each train traveling on the track 180.

制御データベース303は、閉そく制御条件、連動制御条件、信号制御条件などの制御条件を記憶する。   The control database 303 stores control conditions such as closing control conditions, interlocking control conditions, and signal control conditions.

運行履歴データベース304は、線路180を走行していた列車の走行履歴を記憶する。例えば、運行履歴データベース304は、過去の運行中の車両故障などに関する故障原因と、回復までに要した時間と、を履歴として記憶する。   The operation history database 304 stores a travel history of a train that has traveled on the track 180. For example, the operation history database 304 stores, as a history, a cause of a failure related to a vehicle failure in the past operation and a time required for recovery.

受信部305は、地上基地局105a、105b、105cを介して、線路180上の各列車の各々に搭載された車上制御装置151から、当該車上制御装置151が搭載された列車の速度情報、位置情報、及びノッチ情報を受信する。   The receiving unit 305 receives the speed information of the train on which the on-board control device 151 is mounted from the on-board control device 151 mounted on each train on the track 180 via the ground base stations 105a, 105b, and 105c. , Position information and notch information are received.

また、受信部305は、運行管理システム102から、運行ダイヤデータベース351に格納されていた各列車のダイヤ情報を受信する。また、運行管理システム102上でダイヤ情報が変更された場合、受信部305は、変更されたダイヤ情報を受信する。   The receiving unit 305 receives the schedule information of each train stored in the schedule diagram database 351 from the schedule management system 102. Further, when the diamond information is changed on the operation management system 102, the receiving unit 305 receives the changed diamond information.

ダイヤ情報には、例えば、線路180を走行する予定の列車毎の列車番号、運用車両種別、上り・下りの運転方向や走行区間、各駅における到着時刻、出発時刻、使用番線が含まれている。   The schedule information includes, for example, the train number for each train scheduled to travel on the track 180, the operating vehicle type, the up / down driving directions and travel sections, the arrival time at each station, the departure time, and the use number line.

なお、ダイヤ情報は、当日実施予定の運行ダイヤだけでなく、既に列車が走行済みの区間の実績ダイヤの情報も含まれてもよい。実績ダイヤの情報は、運行履歴データベース304に格納される。   Note that the diagram information may include not only the operation schedule scheduled to be implemented on the day, but also information on the actual schedule of the section in which the train has already traveled. Information of the actual schedule is stored in the operation history database 304.

また、受信部305は、ATC地上装置103から、地上ATCモニタ情報を受信する。地上ATCモニタ情報には、進路構成情報や保守ブレーキパターンの停止位置情報、臨時速度制限情報、故障情報などの情報が含まれている。   The receiving unit 305 receives terrestrial ATC monitor information from the ATC ground device 103. The ground ATC monitor information includes information such as track configuration information, maintenance brake pattern stop position information, temporary speed limit information, and failure information.

運転曲線生成部308は、生成部311と、選択部312と、を備え、運行ダイヤ通りに運行している場合、運行管理システム102から受信したダイヤ情報に基づいて、運行ダイヤに従って走行するための各列車の運転曲線を生成する。   The driving curve generation unit 308 includes a generation unit 311 and a selection unit 312. When the operation curve generation unit 308 operates according to the operation schedule, the operation curve generation unit 308 is configured to travel according to the operation schedule based on the schedule information received from the operation management system 102. Generate a running curve for each train.

本実施形態の運転曲線生成部308は、ダイヤ情報の予定出発時刻、予定到着時刻から各駅間での運行ダイヤ上の駅間走行時間を算出し、駅間走行時間で列車を走行させる運転曲線を生成する。運転曲線生成部308は、既に提案されている動的計画法のアルゴリズムを用いて駅間走行時間分を所定の誤差範囲内とした上で消費エネルギーが最小となるように、運転曲線を生成しても良い。さらに、運転曲線生成部308は、駅間最高速度を所定の低減幅で低減させてゆき、繰返し計算により、駅間走行時間が所定の誤差範囲内となる運転曲線を生成するアルゴリズムを用いても良い。このように、運転曲線を生成するために、種々の運転曲線作成アルゴリズムを利用しても良い。   The driving curve generation unit 308 of the present embodiment calculates the traveling time between stations on the operation schedule between each station from the scheduled departure time and the scheduled arrival time of the schedule information, and generates a driving curve for running the train with the traveling time between stations. Generate. The driving curve generation unit 308 generates a driving curve so that the energy consumption is minimized while the inter-station travel time is set within a predetermined error range by using the already proposed dynamic programming algorithm. May be. Further, the driving curve generation unit 308 may use an algorithm that reduces the maximum speed between stations by a predetermined reduction width and generates a driving curve in which the traveling time between stations is within a predetermined error range by repeated calculation. good. As described above, various operation curve creation algorithms may be used to generate the operation curve.

より詳細な例としては、運転曲線生成部308は、運行管理システム102から取得したダイヤ情報から、運転曲線の生成対象となる対象列車の列車番号(または固有の列車IDなどでも良い)をキーとして、対象列車のダイヤ情報を抽出する。そして、運転曲線生成部308は、ダイヤ情報に含まれている運用車両種別の情報から、運用に供される車種を判断し、車両データベース302から該当する車両の車両データを取得する。さらに、運転曲線生成部308は、路線データベース301から走行経路上の勾配、曲線、トンネル、速度制限などの路線データを取得する。運転曲線生成部308は、取得した車両データ、路線データ、及びダイヤ情報に基づいて、対象列車の運転曲線を生成する。   As a more detailed example, the driving curve generation unit 308 uses the train number (or a unique train ID or the like) of the target train to be generated as a driving curve from the diamond information acquired from the operation management system 102 as a key. , Extract the schedule information of the target train. Then, the driving curve generation unit 308 determines the vehicle type used for the operation from the information on the operating vehicle type included in the diagram information, and acquires the vehicle data of the corresponding vehicle from the vehicle database 302. Furthermore, the driving curve generation unit 308 acquires route data such as a gradient, a curve, a tunnel, and a speed limit on the travel route from the route database 301. The driving curve generation unit 308 generates a driving curve of the target train based on the acquired vehicle data, route data, and diagram information.

判定部307は、運転曲線生成部308が再び運転曲線の生成が必要か否かを判定する。例えば、判定部307は、受信部305が受信した列車情報(位置情報、速度情報、ノッチ情報)に基づいて、遅延が生じたか否かの判定を行う。遅延が生じた原因としては、例えば事故等が考えられる。   The determination unit 307 determines whether or not the operation curve generation unit 308 needs to generate an operation curve again. For example, the determination unit 307 determines whether a delay has occurred based on the train information (position information, speed information, notch information) received by the reception unit 305. As the cause of the delay, for example, an accident can be considered.

運行予測部306は、判定部307の判定結果から、事故等により列車の遅れが生じていると判定された場合に、各列車からリアルタイムで受信した速度情報、位置情報、ノッチ情報、ダイヤ情報や、制御データベース303に格納された閉そく制御条件、連動制御条件、信号制御条件などの制御条件に基づいて、ATCなどの運転保安システムの動作を考慮した、列車群の運行シミュレーションを行う。本実施形態の運行予測部306は、各列車の所定の時間毎の線路上の位置まで具体的に予測し、例えば、運転曲線自体を予測しても良い。   When it is determined from the determination result of the determination unit 307 that the train is delayed due to an accident or the like, the operation prediction unit 306 receives the speed information, position information, notch information, diamond information, Based on the control conditions such as the block control condition, the interlock control condition, and the signal control condition stored in the control database 303, a train group operation simulation is performed in consideration of the operation of the operation security system such as ATC. The operation prediction unit 306 of the present embodiment specifically predicts the position on the track for each predetermined time of each train, and may predict the operation curve itself, for example.

例えば、運行予測部306は、受信部305が受信した列車群の位置情報と速度情報とに基づいて、(制御対象となる列車の前を走行している)先行列車の運行ダイヤと、制御対象となる列車の運行ダイヤと、制御対象となる列車の後ろを走行している後続列車の運行ダイヤと、を予測する。先行列車は、例えば、事故等に巻き込まれたために遅延が生じた先頭の列車が考えられる。   For example, the operation prediction unit 306 is based on the position information and speed information of the train group received by the reception unit 305, and the operation schedule of the preceding train (running in front of the train to be controlled) and the control target The operation schedule of the train to be and the operation diagram of the subsequent train running behind the train to be controlled are predicted. The leading train may be, for example, the leading train that has been delayed due to being involved in an accident or the like.

運行予測部306は、先行列車の運行ダイヤとして、先行列車が存在していると予測される地点から、所定の加速度(例えば、先行列車が出力可能な最大加速度)で加速して走行したと仮定した場合の、当該先行列車の運行ダイヤを予測してもよい。判定部307による判定をリアルタイムに所定時間毎に行い、当該判定結果に応じて運行予測部306が予測を行うことで、当該予測がはずれた場合でも、次の判定時に修正可能とする。   It is assumed that the operation prediction unit 306 has accelerated and traveled at a predetermined acceleration (for example, the maximum acceleration that the preceding train can output) from a point where the preceding train is predicted to exist as the operation diagram of the preceding train. In such a case, the operation schedule of the preceding train may be predicted. The determination by the determination unit 307 is performed at predetermined time intervals in real time, and the operation prediction unit 306 performs prediction according to the determination result, so that even when the prediction is lost, it can be corrected at the next determination.

また、運行予測部306は、運行履歴データベース304に格納されている列車の運行履歴に基づいて、現在の状況に近い過去の履歴を参照して、各列車の運行ダイヤを予測しても良い。   Further, the operation prediction unit 306 may predict the operation schedule of each train with reference to the past history close to the current situation based on the operation history of the train stored in the operation history database 304.

運転曲線生成部308の生成部311は、運行予測部306が予測した運行ダイヤに従って列車群が走行した場合の、制御対象となる列車と、その前後で走行している列車との位置関係に基づいて、制御対象となる列車が線路180を走行する際の加速及び減速を行う区間を調整した運転曲線を複数生成する。   The generation unit 311 of the operation curve generation unit 308 is based on the positional relationship between the train to be controlled and the train traveling before and after the train group when traveling according to the operation schedule predicted by the operation prediction unit 306. Thus, a plurality of operation curves are generated in which sections for acceleration and deceleration when the train to be controlled travels on the track 180 are adjusted.

例えば、生成部311は、運行予測部306が予測した運行ダイヤに従って、制御対象となる列車と、先行列車と、を走行させた場合における、制御対象となる列車と先行列車との位置関係に基づいて、制御対象となる列車が線路180を走行する際の加速及び減速を行う区間を調整した運転曲線を生成する。   For example, the generation unit 311 is based on the positional relationship between the control target train and the preceding train when the control target train and the preceding train are run according to the operation schedule predicted by the operation prediction unit 306. Thus, an operation curve is generated in which a section for acceleration and deceleration when the train to be controlled travels on the track 180 is adjusted.

他の例としては、生成部311は、後続列車が、制御対象となる列車の遅れの影響を受ける可能性がある位置に存在する場合に、運行予測部306が予測した運行ダイヤに従って、制御対象となる列車と、後続列車と、を走行させた場合に、制御対象となる列車と後続列車との位置関係に基づいて、後続列車に遅れを生じさせないように、制御対象となる列車が線路180を走行する際の加速及び減速を行う区間を調整した運転曲線を生成する。   As another example, the generation unit 311 controls the control target according to the operation schedule predicted by the operation prediction unit 306 when the subsequent train is present at a position that may be affected by the delay of the train to be controlled. When the train to be operated and the succeeding train are run, the train to be controlled is set to the line 180 so that the succeeding train is not delayed based on the positional relationship between the train to be controlled and the succeeding train. A driving curve is generated that adjusts the section for acceleration and deceleration when traveling.

選択部312は、生成部311が複数の運転曲線を生成した場合に、当該複数の運転曲線のうち、制御対象の列車に送信する運転曲線を選択する。また、選択部312が運転曲線を選択する際に、判定部307が複数の運転曲線の各々について後続列車に遅れを生じさせるか否かの判定を行う。選択部312は、判定部307の判定結果から、後続列車に遅れを生じさせないように、後続列車との位置関係を考慮した運転曲線を選択する。また、選択部312は、位置関係だけでなく、列車の消費電力を考慮して、運転曲線を選択しても良い。   When the generation unit 311 generates a plurality of operation curves, the selection unit 312 selects an operation curve to be transmitted to the controlled train from the plurality of operation curves. Further, when the selection unit 312 selects a driving curve, the determination unit 307 determines whether or not to cause a delay in the subsequent train for each of the plurality of driving curves. The selection unit 312 selects an operation curve in consideration of the positional relationship with the subsequent train so as not to cause a delay in the subsequent train from the determination result of the determination unit 307. The selection unit 312 may select an operation curve in consideration of not only the positional relationship but also the power consumption of the train.

送信部309は、選択部312により選択された運転曲線で示された列車走行指令情報を、制御対象の列車に送信する。また、送信する列車走行指令情報は、列車の走行計画が表された情報であればよく、例えば、運転曲線自体であっても良い。   The transmission unit 309 transmits the train travel command information indicated by the operation curve selected by the selection unit 312 to the control target train. Moreover, the train travel command information to be transmitted may be information indicating a train travel plan, and may be, for example, the operation curve itself.

図4は、本実施形態の運転曲線生成部308の運転曲線の生成手法の第1の例を示した図である。図4に示される例では、説明を容易にするために、先行列車401と、制御対象となる列車402とを、運転曲線451に従って走行する計画であったとする。しかしながら、先行列車401が、時刻t0において、何らかの理由で駅間の閉そく区間k内の位置411で停止したものとする。この場合、運転曲線451での走行に対して遅れが生じる。これに対して、後続の列車402は、時刻t0において位置421で運転曲線451上を走行している。   FIG. 4 is a diagram illustrating a first example of the operation curve generation method of the operation curve generation unit 308 of the present embodiment. In the example shown in FIG. 4, for ease of explanation, it is assumed that the preceding train 401 and the train 402 to be controlled are planned to travel according to the operation curve 451. However, it is assumed that the preceding train 401 stops at a position 411 in the block section k between stations for some reason at time t0. In this case, a delay occurs with respect to the travel on the operation curve 451. On the other hand, the following train 402 is running on the operation curve 451 at the position 421 at the time t0.

後続の列車402は、ATC地上装置103から先行列車401に関する情報を受信した場合に、ATC車上装置203は、先行列車401が停車している閉そく区間kの進行反対側の閉そく区間(k+1)と閉そく区間kの境界431を、速度0km/hとなる起点として、先行列車401と接触することを抑止する保守ブレーキパターン461を生成する。そして、列車402の位置に対応する速度が保守ブレーキパターン461を超過した場合、列車402では、保安ブレーキが自動的に作動し、当該保守ブレーキパターン461に従って減速が行われる。   When the succeeding train 402 receives information related to the preceding train 401 from the ATC ground device 103, the ATC on-board device 203 determines that the closing section (k + 1) on the opposite side of the traveling of the closing section k where the preceding train 401 is stopped. A maintenance brake pattern 461 that suppresses contact with the preceding train 401 is generated using the boundary 431 of the block section k as a starting point at a speed of 0 km / h. When the speed corresponding to the position of the train 402 exceeds the maintenance brake pattern 461, the safety brake is automatically activated in the train 402, and deceleration is performed according to the maintenance brake pattern 461.

先行列車401は、停車原因が解消した後、新たに生成した運転曲線452に従って加速し、時刻t1で位置412に到達する。時刻t1において、先行列車401は、閉そく区間kから閉そく区間(k−1)に遷移した場合に、列車402のATC車上装置203は、保守ブレーキパターン461から、保守ブレーキパターン462に変更する。   The preceding train 401 is accelerated according to the newly generated operation curve 452 after the cause of the stoppage is resolved, and reaches the position 412 at time t1. When the preceding train 401 transitions from the block section k to the block section (k-1) at time t1, the ATC on-board device 203 of the train 402 changes from the maintenance brake pattern 461 to the maintenance brake pattern 462.

列車402は、運転曲線451上を走行していた場合、保守ブレーキパターン461に抵触した時に、減速が行われる。例えば、位置422に列車402が存在する時刻t1で、保守ブレーキパターン461から保守ブレーキパターン462に変化する。このため、列車402の保安ブレーキが解除され、保守ブレーキパターン462に抵触するまで再度加速できる。   When the train 402 is traveling on the operation curve 451, the train 402 is decelerated when it conflicts with the maintenance brake pattern 461. For example, the maintenance brake pattern 461 changes to the maintenance brake pattern 462 at time t1 when the train 402 exists at the position 422. For this reason, the safety brake of the train 402 is released, and the vehicle can be accelerated again until the maintenance brake pattern 462 is violated.

これに対して、運行予測部306が、時刻t0で、先行列車401が時刻t1で閉そく区間kから閉そく区間(k−1)に移動することを予測できた場合、運転曲線生成部308が、運転曲線451の代わりに、列車402の速度を予め一時低減させて、時刻t1以降に保守ブレーキパターン461で示された位置に対応する速度に到達する運転曲線453を再生成し、送信部309が、列車402の車上システム150に送信する。この場合、列車402が、運転曲線453に従って走行することで、保守ブレーキパターン461に抵触せずに、時刻t1で元の運転曲線451と同じ速度で走行を実現できる。   On the other hand, when the operation prediction unit 306 can predict that the preceding train 401 will move from the block section k to the block section (k-1) at time t1 at time t0, the driving curve generation unit 308 Instead of the driving curve 451, the speed of the train 402 is temporarily reduced in advance to regenerate the driving curve 453 that reaches the speed corresponding to the position indicated by the maintenance brake pattern 461 after time t1, and the transmission unit 309 , To the on-board system 150 of the train 402. In this case, the train 402 can travel at the same speed as the original operation curve 451 at time t <b> 1 without conflicting with the maintenance brake pattern 461 by traveling according to the operation curve 453.

換言すれば、再生成された運転曲線453で走行せず、元の運転曲線451で走行した場合に、時刻t1で保守ブレーキパターン461に従って減速するため、元の運転曲線451で示された速度に復帰するためには再加速が必要となる。この場合に再加速が必要な分だけ遅れが生じる。   In other words, when the vehicle does not travel on the regenerated driving curve 453 but travels on the original driving curve 451, the vehicle decelerates according to the maintenance brake pattern 461 at time t1, and thus the speed indicated by the original driving curve 451 is reached. Re-acceleration is required to return. In this case, there is a delay by the amount necessary for reacceleration.

これに対して、再生成された運転曲線453で走行した場合に、時刻t1の時点で、列車402は、元の運転曲線451で示された位置に対応する速度で走行している。本実施形態では、再生成された運転曲線453で列車402を走行させることで、最小限の遅れで元の運転曲線451と同様の走行に復帰できる。   In contrast, when traveling on the regenerated driving curve 453, the train 402 is traveling at a speed corresponding to the position indicated by the original driving curve 451 at the time t1. In this embodiment, it is possible to return to the same traveling as the original driving curve 451 with a minimum delay by running the train 402 with the regenerated driving curve 453.

図4に示される例では、先行列車401と、列車402との位置関係に基づいて、運転曲線を生成する例について説明したが、列車402の後続の列車も遅延の影響が生じる可能性がある。   In the example illustrated in FIG. 4, the example in which the operation curve is generated based on the positional relationship between the preceding train 401 and the train 402 has been described. However, the train subsequent to the train 402 may be affected by the delay. .

図5は、本実施形態の運転曲線生成部308の運転曲線の生成手法の第2の例を示した図である。図5に示される例では、図4と同様に、先行列車501と、制御対象となる列車502と、列車502の後続列車503とは、運転曲線451に従って走行する計画であったものとする。しかしながら、先行列車501が、時刻t0において、何らかの理由で駅間の閉そく区間k内の位置411で停止したものとする。この場合、運転曲線451での走行に対して遅れが生じる。これに対して、制御対象となる列車502は、時刻t0において位置421で運転曲線451上を走行している。そして、列車502の後方の後続列車503は、時刻t0において位置520で運転曲線451上を走行している。このような場合に、列車502の速度を低減させると、保守ブレーキパターン461との接触による、後続列車503の遅延が生じる可能性がある。   FIG. 5 is a diagram illustrating a second example of the operation curve generation method of the operation curve generation unit 308 of the present embodiment. In the example shown in FIG. 5, as in FIG. 4, it is assumed that the preceding train 501, the train 502 to be controlled, and the succeeding train 503 of the train 502 are planned to travel according to the operation curve 451. However, it is assumed that the preceding train 501 stops at a position 411 in the block section k between stations for some reason at time t0. In this case, a delay occurs with respect to the travel on the operation curve 451. On the other hand, the train 502 to be controlled is running on the operation curve 451 at the position 421 at the time t0. Then, the succeeding train 503 behind the train 502 travels on the operation curve 451 at the position 520 at time t0. In such a case, if the speed of the train 502 is reduced, there is a possibility that the subsequent train 503 may be delayed due to contact with the maintenance brake pattern 461.

図4の先行列車401と同様に、先行列車501は、停車後に運転曲線452に従って加速して、時刻t1において位置412に到達する。このタイミングで、列車502のATC車上装置203は、保守ブレーキパターン461から、保守ブレーキパターン462に変更する。   Similar to the preceding train 401 in FIG. 4, the preceding train 501 accelerates according to the driving curve 452 after stopping, and reaches the position 412 at time t1. At this timing, the ATC on-board device 203 of the train 502 changes from the maintenance brake pattern 461 to the maintenance brake pattern 462.

この場合に、地上制御装置101の運転曲線生成部308の生成部311は、3種類の運転曲線553、554、555を生成する。これら3種類の運転曲線553、554、555のうち、どれに従った場合でも、先行列車501が閉そく区間kから移動すると予測される時刻t1以降に、閉そく区間kに基づいた保守ブレーキパターン461で減速させる位置521まで、運転曲線451に従った速度で、列車502が到達するように設定されている。このように、列車502が位置521に到達する前に保守ブレーキパターン461が変更されることで、列車502は位置521で元の運転曲線451上と同様の走行に復帰できる。これにより、先行列車501の遅延の影響を抑止できる。   In this case, the generation unit 311 of the operation curve generation unit 308 of the ground control apparatus 101 generates three types of operation curves 553, 554, and 555. In any of these three types of driving curves 553, 554, 555, the maintenance brake pattern 461 based on the block section k is used after the time t1 when the preceding train 501 is predicted to move from the block section k. The train 502 is set to reach the position 521 to be decelerated at a speed according to the operation curve 451. As described above, the maintenance brake pattern 461 is changed before the train 502 reaches the position 521, so that the train 502 can return to the same traveling as that on the original operation curve 451 at the position 521. Thereby, the influence of the delay of the preceding train 501 can be suppressed.

運転曲線553は、時刻t0で減速を開始して、速度低減幅は小さいが、低減された速度で長距離を等速走行させる運転曲線とする。   The driving curve 553 is a driving curve that starts deceleration at time t0 and travels at a constant speed over a long distance at a reduced speed although the speed reduction width is small.

このように、生成部311は、先行列車501が閉そく区間kから移動すると予測される時刻t1に、当該閉そく区間kに基づいた、列車502を減速させる位置521まで、列車502が移動しないように、列車502の現在の走行速度V1から、等速運転用の速度V2まで低下させた後、当該等速運転用の速度V2で可能な限り長い距離を走行させた後に加速し、保守ブレーキパターンが変更されると予想される時刻t1より後に位置521に、通常の運行ダイヤ(換言すれば運転曲線451)に従った速度で到達する運転曲線553を生成する。   As described above, the generation unit 311 prevents the train 502 from moving to the position 521 for decelerating the train 502 based on the block section k at the time t1 when the preceding train 501 is predicted to move from the block section k. After the train 502 is lowered from the current traveling speed V1 to the speed V2 for constant speed operation, the vehicle is accelerated after traveling as long as possible at the speed V2 for constant speed operation. An operation curve 553 is generated that reaches the position 521 at a speed according to a normal operation diagram (in other words, the operation curve 451) after the time t1 that is expected to be changed.

運転曲線555は、減速した後に加速を行うことで、減速した後の等速走行する区間を極力短くした運転曲線とする。このため、運転曲線555の速度低減幅は、運転曲線553、554と比べて最も大きくなる。   The operation curve 555 is an operation curve in which a section where the vehicle travels at a constant speed after deceleration is shortened as much as possible by performing acceleration after decelerating. For this reason, the speed reduction width of the operation curve 555 is the largest as compared with the operation curves 553 and 554.

このように、生成部311は、先行列車501が閉そく区間kから移動すると予測される時刻t1に、当該閉そく区間kに基づいた、列車502を減速させる位置521まで、列車502を移動させず、且つ、列車502の(運転曲線451で示された)現在の走行速度V1を維持させるため、位置521より進行方向反対側の位置522まで現在の走行速度V1で走行した後、現在の走行速度V1より低い速度V3(等速運転用の速度V2より低い速度)まで減速させた後、当該速度V3から加速させることで、時刻t1より後に位置521に、通常の運行ダイヤ(運転曲線451)に従った走行速度V1で到達する運転曲線555を生成する。なお、位置522は、列車の性能(例えば、速度低減幅及び速度加速幅)を考慮して、時刻t1で位置521に到着しないように算出された位置として、説明を省略する。運転曲線555は、速度V3まで減速させた後、等速走行を行わずに、走行速度V1まで加速する例とするが、全く等速走行を行わないものに制限されるものではない。   As described above, the generation unit 311 does not move the train 502 to the position 521 for decelerating the train 502 based on the block section k at the time t1 when the preceding train 501 is predicted to move from the block section k. In addition, in order to maintain the current travel speed V1 (indicated by the operation curve 451) of the train 502, after traveling at the current travel speed V1 from the position 521 to the position 522 on the opposite side of the traveling direction, the current travel speed V1. After decelerating to a lower speed V3 (a speed lower than the speed V2 for constant speed operation) and accelerating from the speed V3, the position 521 is followed by a normal operation diagram (operation curve 451) after time t1. A driving curve 555 that reaches at the traveling speed V1 is generated. The position 522 is a position calculated so as not to arrive at the position 521 at the time t1 in consideration of the performance of the train (for example, the speed reduction width and the speed acceleration width), and the description thereof is omitted. The driving curve 555 is an example in which, after decelerating to the speed V3, accelerating to the traveling speed V1 without performing constant speed traveling, the driving curve 555 is not limited to those that do not perform constant speed traveling at all.

運転曲線554は、運転曲線553と運転曲線555の中間であって、減速開始位置が運転曲線553より進行方向側に存在し、速度低減幅が運転曲線553と運転曲線555の中間であって、減速した後の等速走行する区間が、運転曲線553よりも短く運転曲線555より長い区間として存在する。   The operation curve 554 is intermediate between the operation curve 553 and the operation curve 555, the deceleration start position is present on the traveling direction side of the operation curve 553, and the speed reduction width is intermediate between the operation curve 553 and the operation curve 555, A section in which the vehicle travels at a constant speed after deceleration exists as a section that is shorter than the driving curve 553 and longer than the driving curve 555.

しかしながら、後続列車503は、列車502と列車間隔や速度差、閉そく区間の長さなどの関係によっては、減速を行う可能性がある。例えば、減速の開始が最も早い運転曲線553で列車502が減速を行う場合、後続列車503に保守ブレーキパターン561に従った減速が生じる可能性がある。一方、減速の開始が最も遅い運転曲線555で列車502が減速を行う場合に、後続列車503は列車502の閉そく区間に基づく保守ブレーキパターン561に接触せずに、減速が必要とならない可能性がある。   However, the following train 503 may be decelerated depending on the relationship between the train 502 and the train interval, speed difference, length of the closed section, and the like. For example, when the train 502 decelerates on the operation curve 553 with the earliest start of deceleration, the subsequent train 503 may be decelerated according to the maintenance brake pattern 561. On the other hand, when the train 502 decelerates on the operation curve 555 with the slowest start of deceleration, the succeeding train 503 may not contact the maintenance brake pattern 561 based on the block section of the train 502 and may not require deceleration. is there.

そこで、本実施形態では、生成部311が複数の運転曲線を生成した場合に、選択部312は、先行列車501との位置関係だけでなく、後続列車503との位置関係を考慮して、制御対象の列車502に適用する運転曲線を選択する。このように後続列車503の遅れを考慮することで、線路180を走行する列車群全体での遅れの影響を抑止できる。   Therefore, in this embodiment, when the generation unit 311 generates a plurality of operation curves, the selection unit 312 controls not only the positional relationship with the preceding train 501 but also the positional relationship with the subsequent train 503. An operation curve to be applied to the target train 502 is selected. Thus, by considering the delay of the following train 503, the influence of the delay in the entire train group traveling on the track 180 can be suppressed.

例えば、生成部311は、列車502の運転曲線を生成する際に、時刻t0から減速を開始して、速度低減幅が最小となる運転曲線553を生成する。そして、判定部307は、運行予測部306が、列車502が運転曲線553に従って走行を行った場合の後続列車503の遅れを予測する。後続列車503の遅れが発生しないと判定された場合、選択部312は、当該運転曲線553を、列車502の運転曲線として選択する。   For example, when generating the operation curve of the train 502, the generation unit 311 starts deceleration from time t0 and generates an operation curve 553 that minimizes the speed reduction width. Then, the determination unit 307 predicts the delay of the subsequent train 503 when the operation prediction unit 306 travels according to the operation curve 553. When it is determined that the delay of the following train 503 does not occur, the selection unit 312 selects the operation curve 553 as the operation curve of the train 502.

遅れが生じる場合には、生成部311は、運転曲線554や運転曲線555を生成する。そして、選択部312は、生成された運転曲線554、555で走行した場合の後続列車503の遅れを予測する。このように、選択部312は、後続列車503に遅れを生させない運転曲線を探索する。列車502が、減速開始のタイミングが最も遅くなる運転曲線に従った場合でも、後続列車503に遅れを生じさせる場合、運転曲線生成部308は、さらに、後続列車503の運転曲線も生成する。   When a delay occurs, the generation unit 311 generates an operation curve 554 and an operation curve 555. And the selection part 312 estimates the delay of the following train 503 at the time of drive | working with the produced | generated driving curves 554,555. As described above, the selection unit 312 searches for an operation curve that does not cause a delay in the subsequent train 503. Even when the train 502 follows the operation curve with the slowest timing for starting deceleration, the operation curve generation unit 308 also generates an operation curve of the subsequent train 503 when the subsequent train 503 is delayed.

図6は、本実施形態の運転曲線生成部308の運転曲線の生成手法の第3の例を示した図である。図6に示される例では、図5と同様に、生成部311が、列車502の運転曲線553、554、555を生成した後に、後続列車503の運転曲線の生成も必要と判定し、運転曲線651、652、653を生成した例とする。そして、選択部312は、後続列車503より後続の列車の遅れを考慮して、運転曲線651、652、653から、後続列車503の運転曲線を選択する。この場合に、後続列車503のさらに後ろの後続列車の遅れを考慮して、運転曲線を選択する。   FIG. 6 is a diagram illustrating a third example of the operation curve generation method of the operation curve generation unit 308 of the present embodiment. In the example shown in FIG. 6, similarly to FIG. 5, after the generation unit 311 generates the operation curves 553, 554, and 555 of the train 502, it is determined that it is necessary to generate the operation curve of the subsequent train 503. Assume that 651, 652, and 653 are generated. Then, the selection unit 312 selects the operation curve of the subsequent train 503 from the operation curves 651, 652, and 653 in consideration of the delay of the subsequent train from the subsequent train 503. In this case, an operation curve is selected in consideration of the delay of the succeeding train further behind the succeeding train 503.

本実施形態の運転曲線生成部308は、先行列車501、列車502、後続列車503等の遅れ時間の合計が最小になるように、運転曲線を生成し、選択する。なお、本実施形態では、遅れ時間の合計を最小とするように制御する例について説明したが、他の基準に基づいて、運転曲線を生成し、選択しても良い。例えば、運転曲線生成部308は、遅れの影響のある列車数を最小にしたり、最大遅延時間を最小化したり、総遅延時間(各駅での到着時刻や出発時刻における遅延時間の総和)を最小化するようにしてもよい。このように、路線の特性や運用に適切と考えられる評価指標に基づいて、運転曲線の最適化を行えばよい。   The operation curve generation unit 308 of this embodiment generates and selects an operation curve so that the total delay time of the preceding train 501, the train 502, the subsequent train 503, and the like is minimized. In the present embodiment, an example in which the total delay time is controlled to be minimum has been described. However, an operation curve may be generated and selected based on other criteria. For example, the operation curve generation unit 308 minimizes the number of trains affected by delay, minimizes the maximum delay time, or minimizes the total delay time (the sum of the delay times at the arrival time and departure time at each station). You may make it do. In this way, the driving curve may be optimized based on the evaluation characteristics considered appropriate for route characteristics and operation.

また、選択部312が運転曲線を選択する際の基準は、後続列車の遅れに基づいて運転曲線を選択することに制限するものではなく、他の基準に基づいて運転曲線を選択しても良い。例えば、生成された複数の運転曲線のうち、どの運転曲線を選択しても、後続列車に遅れが生じる場合に、選択部312は、複数の運転曲線から、消費エネルギーを低減できる運転曲線を選択することが考えられる。例えば、減速から再力行するまでの速度低減幅が大きいと消費エネルギーが無駄になる。さらには、選択部312が列車遅れの評価指標に対して、消費エネルギーを所定の重み付けで加算した結果を、評価指標として用いて運転曲線を選択しても良い。   Moreover, the reference | standard at the time of the selection part 312 selecting an operation curve is not restrict | limited to selecting an operation curve based on the delay of a following train, You may select an operation curve based on another reference | standard. . For example, when any of the generated driving curves is selected, if any of the driving curves is delayed, the selection unit 312 selects an operating curve that can reduce energy consumption from the plurality of driving curves. It is possible to do. For example, if the speed reduction range from deceleration to repowering is large, energy consumption is wasted. Furthermore, the selection unit 312 may select a driving curve by using, as an evaluation index, a result obtained by adding energy consumption with a predetermined weight to an evaluation index for train delay.

例えば、列車502と、後続列車503との間隔が十分開いていれば、列車502用に生成された複数の運転曲線553、554、555のうち、どれを選択した場合でも、後続列車503が列車502との間の保守ブレーキパターンに抵触することがない場合もある。この場合、選択部312は、複数の運転曲線553、554、555の各々に従って列車502を走行させた場合の消費電力を算出する。そして、選択部312は、算出した消費電力を評価指標として、複数の運転曲線553、554、555から、消費電力が最も小さくなる運転曲線を選択する。   For example, if the interval between the train 502 and the succeeding train 503 is sufficiently wide, the succeeding train 503 is trained regardless of which of the plurality of operation curves 553, 554, and 555 generated for the train 502 is selected. In some cases, the maintenance brake pattern with 502 is not violated. In this case, the selection unit 312 calculates the power consumption when the train 502 is run according to each of the plurality of operation curves 553, 554, and 555. Then, the selection unit 312 selects an operation curve with the smallest power consumption from the plurality of operation curves 553, 554, and 555 using the calculated power consumption as an evaluation index.

ところで、先行列車及び後続列車の走行速度等によっては、先行列車の保守ブレーキパターンが解除される時に、後続列車を元の運転曲線上に戻すのが難しい場合がある。このような場合は、運転曲線生成部308は、後続列車のために、保守ブレーキパターンに抵触するような運転曲線を生成しても良い。例えば、後続列車が先行列車の保守ブレーキパターンへの抵触が避けられないような場合、生成部311は、運転曲線を等速走行して保守ブレーキパターンに抵触するような運転曲線を生成するのではなく、時刻t0など可能な限り早い時期から惰行を開始し、図4で示した保守ブレーキパターン461に抵触する時機を遅らせるような運転曲線を生成しても良い。   By the way, depending on the traveling speed of the preceding train and the succeeding train, it may be difficult to return the succeeding train to the original operation curve when the maintenance brake pattern of the preceding train is released. In such a case, the driving curve generation unit 308 may generate a driving curve that conflicts with the maintenance brake pattern for the following train. For example, when the following train cannot avoid the maintenance brake pattern of the preceding train, the generation unit 311 does not generate an operation curve that runs at the same speed along the operation curve and conflicts with the maintenance brake pattern. Alternatively, coasting may be started from the earliest possible time such as time t0, and an operation curve may be generated that delays the timing of conflict with the maintenance brake pattern 461 shown in FIG.

そして、運転曲線生成部308による遅れの影響を受ける全ての列車についての運転曲線の生成、及び選択が完了した場合に、送信部309が、選択された運転曲線を、列車走行指令情報として、各列車に送信する。   Then, when the generation and selection of operation curves for all trains affected by the delay by the operation curve generation unit 308 are completed, the transmission unit 309 uses the selected operation curve as train travel command information, Send to train.

そして、各列車の車上制御装置151のATO機能部256は、受信した列車走行指令情報に従って、列車の自動運転を行う。   And the ATO function part 256 of the on-board controller 151 of each train performs the automatic driving | operation of a train according to the received train travel command information.

次に、本実施形態の地上制御装置101における運転曲線の生成処理について説明する。図7は、本実施形態の地上制御装置101における上述した処理の手順を示すフローチャートである。   Next, operation curve generation processing in the ground control device 101 of the present embodiment will be described. FIG. 7 is a flowchart showing the above-described processing procedure in the ground control apparatus 101 of the present embodiment.

まず、地上制御装置101は、当日の列車運行開始前に起動し、初期化処理を行う(S701)。この際に、地上制御装置101は、各種機器・システム故障およびエラーの検出や、各処理機能におけるメモリの初期化や、他システムとの情報伝送の確立等を行う。また、何らかの異常やエラーが生じた場合、その旨を(図示しない)管理コンソール画面などに表示し、指令員や管理者による対応を促す。   First, the ground control device 101 is activated before the start of train operation on that day, and performs an initialization process (S701). At this time, the ground control apparatus 101 detects various equipment / system failures and errors, initializes memory in each processing function, establishes information transmission with other systems, and the like. In addition, if any abnormality or error occurs, that fact is displayed on a management console screen (not shown) or the like, and a response by the commander or administrator is encouraged.

次に、受信部305は、地上ネットワーク110を介して、運行管理システム102から、ダイヤ情報を受信する(S702)。当該ダイヤ情報を受信するために、送信部309が、運行管理システム102に対して、ダイヤ情報の送信を要求しても良い。   Next, the receiving unit 305 receives diamond information from the operation management system 102 via the ground network 110 (S702). In order to receive the diamond information, the transmission unit 309 may request the operation management system 102 to transmit the diamond information.

次に、運転曲線生成部308が、ダイヤ情報に従って各列車が走行するために、列車毎の運転曲線を生成する(S703)。そして、送信部309が、生成された運転曲線を、各列車に送信する。   Next, the operation curve generation unit 308 generates an operation curve for each train in order for each train to travel according to the schedule information (S703). And the transmission part 309 transmits the produced | generated driving | running curve to each train.

次に、判定部307が、運行管理システム102からの新たなダイヤ情報の受信の有無から、運行ダイヤに変更があるか否かを判定する(S704)。ダイヤの変更がないと判定した場合(S704:No)、S706に遷移する。   Next, the determination unit 307 determines whether or not there is a change in the operation diagram based on whether or not new diagram information is received from the operation management system 102 (S704). When it is determined that there is no diamond change (S704: No), the process proceeds to S706.

一方、判定部307が、運行管理システム102からの新たなダイヤ情報の受信の有無から、運行ダイヤに変更があると判定した場合(S704:Yes)、運転曲線生成部308が、変更後の運行ダイヤに従って、各列車が走行するために、列車毎の運転曲線を再生成する(S705)。そして、送信部309が、生成された運転曲線を、各列車に送信する。   On the other hand, when the determination unit 307 determines that there is a change in the operation diagram based on whether or not new schedule information is received from the operation management system 102 (S704: Yes), the operation curve generation unit 308 operates after the change. In order for each train to travel according to the schedule, an operation curve for each train is regenerated (S705). And the transmission part 309 transmits the produced | generated driving | running curve to each train.

次に、地上制御装置101の受信部305は、地上基地局105a〜150cを介して、線路180を走行する各列車の車上制御装置151から、列車の速度情報、位置情報、ノッチ情報を受信する(S706)。当該受信は、所定の間隔毎に行われる。   Next, the receiving unit 305 of the ground control device 101 receives train speed information, position information, and notch information from the on-board control device 151 of each train traveling on the track 180 via the ground base stations 105a to 150c. (S706). The reception is performed at predetermined intervals.

そして、判定部307は、受信した列車の速度情報、位置情報、及びノッチ情報に基づいて、列車に遅延が生じているか否かを判定する(S707)。遅延が生じていないと判定された場合(S707:No)、S712に遷移する。   And the determination part 307 determines whether the delay has arisen in the train based on the received train speed information, position information, and notch information (S707). When it is determined that no delay has occurred (S707: No), the process proceeds to S712.

列車に遅延が生じているか否かの判定は、どのような手法を用いても良い。例えば、判定部307は、ダイヤ情報に従って生成された運転曲線から、現在時刻における列車の位置および速度を特定できる。そして、判定部307は、特定された位置及び速度と、各列車から受信した速度情報及び位置情報とを比較する。そして、判定部307は、運転曲線上の列車位置と、実際の列車位置との間に所定値以上の距離差が生じた場合に、当該列車を遅延と判定する。運転曲線と実際の列車の位置及び速度とを比較することで、採時地点である駅だけでなく駅間走行中の遅れを把握できる。   Any method may be used to determine whether the train is delayed. For example, the determination unit 307 can specify the train position and speed at the current time from the operation curve generated according to the diagram information. Then, the determination unit 307 compares the identified position and speed with the speed information and position information received from each train. And the determination part 307 determines the said train to be a delay, when the distance difference more than predetermined value arises between the train position on a driving | running curve, and an actual train position. By comparing the driving curve with the actual position and speed of the train, it is possible to grasp not only the station that is the timing point but also the delay during traveling between stations.

また、判定部307は、通常の列車の遅れの判定手法である、各駅における実績ダイヤと計画ダイヤとを比較して判断してもよい。   Moreover, the determination part 307 may determine by comparing the actual schedule and the planned schedule at each station, which is a normal train delay determination method.

他の例としては、判定部307は、速度情報で示される、リアルタイムの現在位置における速度が、運転曲線上の現在位置における速度に対して、所定の速度差以上低い場合、遅延が生じていると予測を行っても良い。   As another example, the determination unit 307 causes a delay when the speed at the current position in real time indicated by the speed information is lower than a predetermined speed difference with respect to the speed at the current position on the driving curve. You may make a prediction.

判定部307は、遅延が生じていると判定した場合(S707:Yes)、運行予測部306が、受信した列車情報と、運行履歴データベース304と、から遅延が生じた後の各列車の運行ダイヤを予測する(S708)。   If the determination unit 307 determines that a delay has occurred (S707: Yes), the operation prediction unit 306 has received the train information and the operation history database 304, and the operation schedule of each train after the delay has occurred. Is predicted (S708).

遅延列車が生じていると判定された場合、運行予測部306が、各列車の速度情報、位置情報、ノッチ情報を初期値として、現在時刻以降の列車群の運行をシミュレーションにより予測する。予測する際に、閉そく装置、転てつ器、連動装置、信号装置などの運転保安システムの動作を考慮した、いわゆる列車群運行シミュレーションを実施し、先行列車による保守ブレーキパターンへの抵触などの影響を考慮した予測を行う。   When it is determined that a delayed train has occurred, the operation prediction unit 306 predicts the operation of the train group after the current time by simulation using the speed information, position information, and notch information of each train as initial values. When forecasting, we conduct a so-called train group operation simulation that considers the operation of operation and safety systems such as blockers, switchers, interlocking devices, signal devices, etc., and influences such as conflicts with the maintenance brake pattern by the preceding train Make a prediction that takes into account.

なお、何らかの異常の発生に起因する遅れが生じた場合、異常の継続時間などを見積もることは困難な場合が多い。運行予測部306が列車運行を予測する際に、このようなケースについても、何らかの条件を仮定して予測を行う。例えば、運転曲線から逸脱して遅れ始めた列車が存在する場合、列車の走行の予測として、現在の列車速度からさらに減速して遅れが拡大する、現在の列車速度で等速走行する、現在の列車速度から元の運転曲線に戻るように加速して遅れが縮小する、などが考えられる。本実施形態の運行予測部306は、予測が外れた場合でも、発生した遅れが解消するまで、所定の周期で予測を繰り返し行う。このため、予測を誤った場合でも以降の予測で修正できるものと考え、遅れが生じた列車が最大限の回復運転を行う(例えば、最大加速度で加速する)ものと仮定して、予測を行う。   When a delay due to the occurrence of some abnormality occurs, it is often difficult to estimate the duration of the abnormality. When the operation prediction unit 306 predicts the train operation, such a case is also predicted by assuming some condition. For example, if there is a train that has started to delay after deviating from the driving curve, the current train speed will be further decelerated from the current train speed, and the delay will increase. For example, the delay may be reduced by accelerating the train speed back to the original driving curve. The operation prediction unit 306 of the present embodiment repeatedly performs the prediction at a predetermined cycle until the generated delay is eliminated even when the prediction is lost. For this reason, even if the prediction is incorrect, it is assumed that it can be corrected by the subsequent prediction, and the prediction is performed on the assumption that the delayed train performs the maximum recovery operation (for example, accelerates at the maximum acceleration). .

他の例としては、ラッシュ時に駅での旅客の乗降時間の増加により停車時間が延びる場合などがある。このような場合の遅れを予測するため、運行履歴データベース304に、過去の実績の運行における列車の運転曲線や駅における停車時間などを格納しておく。そして、運行予測部306は、当該運行履歴データベース304を参照し、現在の状況との統計的な類似性に基づいて、列車の遅延時間を予測しても良い。   As another example, there is a case where the stop time is extended due to an increase in passenger boarding time at the station during rush hours. In order to predict the delay in such a case, the operation history database 304 stores the train operation curve in the past actual operation, the stop time at the station, and the like. Then, the operation prediction unit 306 may refer to the operation history database 304 and predict the delay time of the train based on the statistical similarity with the current situation.

また、列車などの故障などに起因する遅れを予測するため、運行履歴データベース304に、過去の運行中の車両故障などに関する故障原因と回復までに要した平均時間や最大時間などを格納しておく。そして、運行予測部306は、列車に搭載されているモニタ装置が検出した故障情報と、運行履歴データベース304に格納されている情報と、に基づいて、車両故障時における遅延時間を予測しても良い。   In addition, in order to predict a delay caused by a failure of a train or the like, the operation history database 304 stores a failure cause related to a vehicle failure during the past operation and an average time or maximum time required for recovery. . The operation predicting unit 306 predicts the delay time at the time of the vehicle failure based on the failure information detected by the monitor device mounted on the train and the information stored in the operation history database 304. good.

遅れが生じた場合、受信部305が、停車や徐行運転の発生地点、発生時刻、及び継続時間等を、実績の情報として受信し、運行予測部306が、受信した実績の情報に基づいて、列車群運行シミュレーションを行い、運行ダイヤを予測する。例えば、運行予測部306が、降雨や風速による運行制限および臨時速度制限や、車両機器の故障にともなう速度制限、ホーム混雑による旅客乗降遅延等に基づいて、予測される運行ダイヤを生成する。   When a delay occurs, the receiving unit 305 receives the stop point, slow driving occurrence point, occurrence time, duration, and the like as performance information, and the operation prediction unit 306 based on the received performance information, Train group operation simulation and predict operation schedule. For example, the operation prediction unit 306 generates a predicted operation diagram based on operation limitation and temporary speed limitation due to rainfall or wind speed, speed limitation due to failure of vehicle equipment, passenger boarding / departure delay due to crowded home, and the like.

先行列車の遅れが後続列車に遅延を生じさせると予測される場合、運行予測部306は、予測される全ての遅延列車について、予測された遅れに関する「遅れ評価値」を生成する。遅れ評価値は、例えば遅延列車本数や、最大遅延時分、総遅延時分(遅延のある列車の各駅での到着時刻および出発時刻における遅れ時分の総和)、遅延回復までの所要時間、またはこれらに所定の重みを乗じて加算した値など種々考えられるが、対象路線の運用および評価に適切な評価値を利用すれば良い。   When the delay of the preceding train is predicted to cause a delay in the subsequent train, the operation prediction unit 306 generates a “delay evaluation value” related to the predicted delay for all predicted delayed trains. Delay evaluation value is, for example, the number of delayed trains, maximum delay time, total delay time (sum of arrival time and delay time at each station of the delayed train), time required for delay recovery, or Various values such as a value obtained by multiplying these by a predetermined weight can be considered, but an evaluation value appropriate for the operation and evaluation of the target route may be used.

そして、運転曲線生成部308の生成部311は、予測された運行ダイヤに従って、運転曲線を生成する(S709)。   And the production | generation part 311 of the driving curve production | generation part 308 produces | generates a driving curve according to the estimated operation schedule (S709).

そして、判定部307は、生成された運転曲線に従って走行した場合に、先行列車の位置関係で制御対象列車に生じる遅れや、後続列車との位置関係で後続列車に生じる遅れが許容範囲内か否かを判定する(S710)。許容範囲内と判定した場合(S710:Yes)、選択部312が当該運転曲線を送信対象として選択し、S711に遷移する。   Then, when the determination unit 307 travels according to the generated operation curve, the delay that occurs in the control target train due to the positional relationship of the preceding train or the delay that occurs in the subsequent train due to the positional relationship with the subsequent train is within an allowable range. Is determined (S710). When it determines with it being in an tolerance | permissible_range (S710: Yes), the selection part 312 selects the said driving | operation curve as transmission object, and changes to S711.

一方、許容範囲内ではないと判定した場合(S710:No)、S709において、生成部311が、減速する位置等を変更した運転曲線を再生成し、S710による判定を行う。S709による運転曲線の生成は、図4〜図6で説明した通りとして、説明を省略する。   On the other hand, when it determines with it not being in an allowable range (S710: No), in S709, the production | generation part 311 regenerates the driving | running curve which changed the position etc. to decelerate, and performs determination by S710. The generation of the operation curve in S709 is as described with reference to FIGS.

そして、送信部309は、選択された運転曲線に従った、列車走行指示情報を、制御対象の列車に送信する(S711)。   And the transmission part 309 transmits the train travel instruction information according to the selected driving | operation curve to the control object train (S711).

その後、判定部307は、全ての列車の運行が終了したか否かを判定する(S712)。終了していないと判定した場合(S712:No)、S704から再び処理を行う。   Thereafter, the determination unit 307 determines whether or not all trains have been operated (S712). If it is determined that the process has not been completed (S712: No), the process is performed again from S704.

一方、判定部307は、全ての列車の運行が終了したと判定した場合(S712:Yes)、処理を終了する。   On the other hand, the determination part 307 complete | finishes a process, when it determines with the operation | movement of all the trains having been complete | finished (S712: Yes).

本実施形態においては、車上制御装置151から、速度情報、位置情報、ノッチ情報を受信する例について説明したが、受信する列車情報を、速度情報、位置情報、ノッチ情報に制限するものではない。例えば、ノッチ情報は、列車の加減速に関わる情報であって、列車走行の予測精度の向上を目的としている。このため、ノッチ情報の代わりに、列車の主電動機の出力や引張力などの情報を受信しても良い。また、地上制御装置101の運行履歴データベース304が、各列車の速度情報、位置情報について時間推移を含めて記憶しても良い。これにより、運行予測部306は、格納された情報から、列車の加減速を推定した上で、運行ダイヤを生成できる。この場合、情報伝送量の削減や、伝送周期の向上を期待することができる。さらには、車上制御装置151から、加速度情報を受信しても良い。受信した加速度情報を、運行予測に適用することで、より高い精度の予測を実現できる。   In the present embodiment, the example in which the speed information, the position information, and the notch information are received from the on-board controller 151 has been described. However, the received train information is not limited to the speed information, the position information, and the notch information. . For example, the notch information is information related to the acceleration / deceleration of the train, and is intended to improve the prediction accuracy of train travel. For this reason, you may receive information, such as the output of the main motor of a train, and tensile force, instead of notch information. Further, the operation history database 304 of the ground control device 101 may store the speed information and position information of each train including time transitions. Thereby, the operation prediction unit 306 can generate an operation diagram after estimating the acceleration / deceleration of the train from the stored information. In this case, a reduction in the amount of information transmission and an improvement in the transmission cycle can be expected. Further, acceleration information may be received from the on-vehicle controller 151. By applying the received acceleration information to the operation prediction, higher accuracy prediction can be realized.

また、本実施形態では、運転保安システムとしてATC(自動列車制御装置)を適用した例について説明した。しかしながら、先行列車との位置関係による保守ブレーキパターンの推移や進路開通時機を予測可能なものであれば良い。例えば、パターン制御式ATS(自動列車停止装置)システムや、CBTCなどの無線列車制御システムを使用してもよい。   Moreover, in this embodiment, the example which applied ATC (automatic train control apparatus) as a driving | operation security system was demonstrated. However, it is only necessary to be able to predict the transition of the maintenance brake pattern based on the positional relationship with the preceding train and the course opening timing. For example, a pattern control type ATS (automatic train stop device) system or a radio train control system such as CBTC may be used.

本実施の形態においては、このようにして作成した運転曲線を、列車走行指令情報として、地上制御装置101から地上ネットワーク110、地上基地局群105、車上制御装置の情報受信部254を介して、各列車の車上制御装置151に送信している。しかし、地上システムと車上システム間の通信回線の容量などによっては送信する情報を圧縮してデータ伝送時間の短縮化や必要な伝送帯域の削減を図るため、運転曲線データを間引きしたり、運転曲線データ上における速度やノッチ(または加速度や引張力、制動力)などの条件変化点や操作変化点の情報のみを送信するようにしてもよい。その他、ATO機能部256によって列車走行を制御することが可能なデータであれば列車走行指令情報としてどのような形式のデータを送信するようにしても良い。   In the present embodiment, the operation curve thus created is used as train travel command information from the ground control device 101 via the ground network 110, the ground base station group 105, and the information receiving unit 254 of the on-board control device. To the on-board controller 151 of each train. However, depending on the capacity of the communication line between the ground system and the on-board system, the transmission information is compressed to shorten the data transmission time and reduce the necessary transmission bandwidth. Only information on condition change points and operation change points such as speed and notch (or acceleration, tensile force, braking force) on the curve data may be transmitted. In addition, any type of data may be transmitted as the train travel command information as long as the train travel can be controlled by the ATO function unit 256.

本実施形態では、車上制御装置151は、地上制御装置101から受信した列車走行指令情報に基づいて自動運転を行うことで、列車群の遅れの影響が最小となるような最適な列車運行を実現できる。   In the present embodiment, the on-board control device 151 performs optimum driving so that the influence of the delay of the train group is minimized by performing automatic operation based on the train travel command information received from the ground control device 101. realizable.

さらに、地上制御装置101の運転曲線生成部308は、後続列車の遅れを考慮した運転曲線を生成することで、後続列車への遅れを抑止できる。   Further, the operation curve generation unit 308 of the ground control device 101 can suppress the delay to the subsequent train by generating an operation curve in consideration of the delay of the subsequent train.

(第2の実施形態)
なお、第1の実施形態においては、車上制御装置151のATO機能部256が、列車を自動運転する例について説明したが、自動運転する手法に制限するものではない。そこで、第2の実施形態では、運転士が運転する例について説明する。
(Second Embodiment)
In addition, in 1st Embodiment, although the ATO function part 256 of the on-board control apparatus 151 demonstrated the example which drives a train automatically, it does not restrict | limit to the method of driving automatically. Therefore, in the second embodiment, an example in which a driver drives will be described.

図8は、第2の実施形態の、列車170aに搭載された車上システム150aの構成例を示した図である。図8に示されるように、車上システム150aは、第1の実施形態の車上制御装置151の代わりに車上制御装置800が設けられている。なお、第1の実施形態と同一の構成については同一の符号を割り当て、説明を省略する。   FIG. 8 is a diagram illustrating a configuration example of the on-board system 150a mounted on the train 170a according to the second embodiment. As shown in FIG. 8, the on-board system 150a is provided with an on-board controller 800 instead of the on-board controller 151 of the first embodiment. In addition, the same code | symbol is assigned about the structure same as 1st Embodiment, and description is abbreviate | omitted.

車上制御装置800は、第1の実施形態の車上制御装置151と比べて、ATO機能部256の代わりに、運転支援機能部801が設けられている。   The on-board control device 800 is provided with a driving support function unit 801 instead of the ATO function unit 256, as compared with the on-board control device 151 of the first embodiment.

運転支援機能部801は、表示器850に接続されている。表示器850は、運転台上に設置されている。そして、運転支援機能部801は、受信した列車走行指令情報に基づいた、運転士への運転操作に関する情報を、表示器850に表示する。これにより、本実施形態は、地上制御装置101で生成された運転曲線に従った、運転士の運転操縦を実現できる。本実施形態では、当該構成を実現することで、列車にATO機能の搭載が不要となる。このため、既存路線への導入が容易になるとともに、コスト低減が図れる。   The driving support function unit 801 is connected to the display unit 850. The indicator 850 is installed on the cab. And the driving assistance function part 801 displays the information regarding the driving operation with respect to the driver based on the received train travel command information on the display unit 850. Thereby, this embodiment can implement | achieve a driver | operator's driving control according to the driving curve produced | generated by the ground control apparatus 101. FIG. In the present embodiment, it is not necessary to install an ATO function in the train by realizing the configuration. For this reason, the introduction to the existing route is facilitated and the cost can be reduced.

(第3の実施形態)
上述した実施形態では、地上制御装置101が運転曲線を生成する例について説明した。しかしながら、運転曲線を生成するのを地上制御装置101に制限するものではない。そこで、第3の実施形態では、車上制御装置で生成する場合について説明する。
(Third embodiment)
In the above-described embodiment, an example in which the ground control device 101 generates an operation curve has been described. However, the generation of the operation curve is not limited to the ground control device 101. Therefore, in the third embodiment, a case where the vehicle-mounted control device generates the data will be described.

図9は、本実施形態の走行管理システムの概念を例示した図である。図9に示されるように、運行管理システム102と通信を行う列車に搭載された車上制御装置901が、列車群の運転曲線を生成する。   FIG. 9 is a diagram illustrating the concept of the travel management system of the present embodiment. As shown in FIG. 9, the on-board controller 901 mounted on a train that communicates with the operation management system 102 generates an operation curve of the train group.

図10は、本実施形態の車上制御装置901の構成例を示した図である。図10に示されるように、車上システム150bは、車上制御装置901が設けられている。車上制御装置901は、ノッチ情報取得部255、ATO機能部256に加えて、路線データベース301、車両データベース302、制御データベース303、運行履歴データベース304、運行予測部306、判定部307、運転曲線生成部308、受信部1001、送信部1002を備えている。   FIG. 10 is a diagram illustrating a configuration example of the on-vehicle control device 901 of the present embodiment. As shown in FIG. 10, the on-board system 150b is provided with an on-board controller 901. The on-board controller 901 includes a route database 301, a vehicle database 302, a control database 303, an operation history database 304, an operation prediction unit 306, a determination unit 307, and a driving curve generation in addition to the notch information acquisition unit 255 and the ATO function unit 256. Unit 308, receiving unit 1001, and transmitting unit 1002.

つまり、路線データベース301、車両データベース302、制御データベース303、運行履歴データベース304、運行予測部306、判定部307、運転曲線生成部308を、車上制御装置901に設けることで、上述した実施形態の地上制御装置101と同様の処理を実現できる。   That is, the route database 301, the vehicle database 302, the control database 303, the operation history database 304, the operation prediction unit 306, the determination unit 307, and the driving curve generation unit 308 are provided in the on-board control device 901, so that the above-described embodiment. Processing similar to that of the ground control device 101 can be realized.

そして、受信部1001、及び送信部1002は、運行管理システム102との間で情報を送受信するだけではなく、各列車の車上制御装置901との間で情報の送受信を行う。   The receiving unit 1001 and the transmitting unit 1002 not only transmit / receive information to / from the operation management system 102, but also transmit / receive information to / from the on-board controller 901 of each train.

これにより、受信部1001は、車車間通信によって、各列車の速度情報、位置情報、ノッチ情報を受信する。さらに、送信部1002が、ダイヤ情報や、列車走行指令情報を、各列車に送信する。列車間の通信手法としては、どのような手法を用いても良い。   Thereby, the receiving part 1001 receives the speed information of each train, position information, and notch information by vehicle-to-vehicle communication. Furthermore, the transmission part 1002 transmits diamond information and train travel command information to each train. Any method may be used as a communication method between trains.

本実施形態では、地上制御装置101及び地上基地局105a〜105cを削減できるので、コスト低減を図ることができる。また、車上制御装置は、列車毎に搭載されているため、運転曲線を生成するシステムを二重化することができる。これにより、ある列車の車上制御装置の一部に故障が生じた場合でも、他の車上制御装置で運転曲線を生成できるため、システムの可用性を高めることができる。   In the present embodiment, since the ground control device 101 and the ground base stations 105a to 105c can be reduced, the cost can be reduced. Moreover, since the on-board control device is mounted for each train, the system for generating the driving curve can be duplicated. Thereby, even when a failure occurs in a part of the on-board control device of a certain train, the operation curve can be generated by another on-board control device, so that the system availability can be increased.

本実施形態では、列車同士の情報伝送として、車車間通信を行う例について説明したが、列車間隔が長い場合などに、地上無線基地局を経由して情報伝送を行っても良い。さらには、車車間通信と地上無線基地局経由の通信を混在させてもよい。   In the present embodiment, an example in which inter-vehicle communication is performed as information transmission between trains has been described, but information transmission may be performed via a ground radio base station when the train interval is long. Furthermore, inter-vehicle communication and communication via a terrestrial radio base station may be mixed.

車上制御装置901の受信部1001は、始発駅を出発前に、運行管理システム102から、少なくとも自列車、自列車の後続列車、及び自列車が追い越す予定の列車のダイヤ情報を受信する。   The reception unit 1001 of the on-board controller 901 receives at least the own train, the subsequent train of the own train, and the schedule information of the train that the own train is overtaking from the operation management system 102 before leaving the first station.

ダイヤ情報を受信する際には、例えば、各駅に設置された無線LANなどを経由して受信することが考えられる。例えば、始発駅を出発前に、自列車の列車番号の設定が予め行われているため、送信部1002が、設定された列車番号を用いて、運行管理システム102にダイヤ情報の送信要求を行えば良い。   When receiving the diamond information, for example, it may be received via a wireless LAN installed at each station. For example, since the train number of the own train is set in advance before leaving the first station, the transmission unit 1002 makes a transmission request for the schedule information to the operation management system 102 using the set train number. Just do it.

また、列車と運行管理システム102との間の伝送容量に余裕がある場合、受信部1001が、現在時刻以降に運用される全ての列車のダイヤ情報を受信しても良い。このようにダイヤ情報に変更があった場合、受信部1001が、全列車のダイヤ情報を一括して受信したATO、車車間通信によって、走行中の他の列車のダイヤ情報を更新できる。   Further, when there is a margin in the transmission capacity between the train and the operation management system 102, the receiving unit 1001 may receive the schedule information of all trains operated after the current time. In this way, when there is a change in the diagram information, the receiving unit 1001 can update the diagram information of other running trains by ATO and the inter-vehicle communication that collectively receive the diagram information of all trains.

各列車の車上制御装置901は、各駅を出発するまでに、ダイヤ情報に設定された駅間走行時間に基づいて、少なくとも次駅までの運転曲線を生成する。そして、運転士が出発時刻以降に出発ボタンを押下することで、ATO機能部256が、列車の自動運転を行う。   The on-board controller 901 of each train generates an operation curve to at least the next station based on the inter-station travel time set in the diagram information before leaving each station. Then, when the driver depresses the departure button after the departure time, the ATO function unit 256 performs automatic operation of the train.

車上制御装置901は、所定の周期で列車の速度、位置を取得している。このため、車上制御装置901の判定部307は、運転曲線と比較することで、自列車に遅れが生じているか否かを判定できる。そして、遅れが所定の範囲内にあると判定された場合、ATO機能部256が、運転曲線に基づいた自動運転を継続する。   The on-board controller 901 acquires the train speed and position at a predetermined cycle. For this reason, the determination unit 307 of the on-board controller 901 can determine whether or not there is a delay in the own train by comparing with the driving curve. When it is determined that the delay is within the predetermined range, the ATO function unit 256 continues the automatic operation based on the operation curve.

判定部307が、自列車に遅れが生じていると判定した場合、ATCの進路開通情報などの情報に基づいて、先行列車による保守ブレーキパターンへの抵触による遅れか否かを判定する。先行列車による保守ブレーキパターンへの抵触ではなく、自列車が遅延の先頭であると判定した場合、当該列車の車上制御装置901が、自列車と後続列車を含む列車群の運行制御を行う。運行予測部306が、自列車、先行列車、後続列車を含む列車群のダイヤ情報に基づいて、列車群運行シミュレーションを行い、自列車および後続列車の遅れを予測する。運行予測部306は、ダイヤ情報に基づいて後続列車の走行について遅れを予測しても良いが、後続列車から速度情報、位置情報、ノッチ情報等を車車間通信で受信することで、精度の良い予測を実現できる。   If the determination unit 307 determines that the own train has a delay, it determines whether or not the delay is due to a conflict with the maintenance brake pattern by the preceding train based on information such as the route opening information of the ATC. When it is determined that the own train is the head of the delay rather than a conflict with the maintenance brake pattern by the preceding train, the on-board control device 901 of the train performs operation control of the train group including the own train and the subsequent train. The operation prediction unit 306 performs a train group operation simulation based on the schedule information of the train group including the own train, the preceding train, and the subsequent train, and predicts the delay of the own train and the subsequent train. The operation prediction unit 306 may predict a delay in the travel of the subsequent train based on the diagram information. However, the operation prediction unit 306 receives the speed information, the position information, the notch information, and the like from the subsequent train through inter-vehicle communication, thereby improving the accuracy. Predictions can be realized.

運行予測部306により自列車の後続列車の遅れが予測された場合、さらに後続列車への遅れの影響が考えられる。このため、運行予測部306は、遅延の影響が予測されなくなる列車まで、順次後続列車のダイヤ情報に基づいて、当該後続列車の遅れを予測する。   When the operation prediction unit 306 predicts the delay of the subsequent train of the own train, the influence of the delay on the subsequent train can be considered. For this reason, the operation predicting unit 306 sequentially predicts the delay of the subsequent train based on the diagram information of the subsequent train up to the train where the influence of the delay is not predicted.

次に、運転曲線生成部308が、自列車および遅延の影響が予測された全ての後続列車について、遅れの影響が小さくなるような運転曲線を生成する。なお、遅れの影響が小さくなるような運転曲線の例は、第1の実施形態で説明したので、説明を省略する。   Next, the operation curve generation unit 308 generates an operation curve that reduces the influence of the delay for the own train and all subsequent trains for which the influence of the delay is predicted. In addition, since the example of the driving | running curve in which the influence of delay becomes small was demonstrated in 1st Embodiment, description is abbreviate | omitted.

運転曲線生成部308が、遅れの影響が予測された全ての後続列車について、運転曲線を生成した場合に、送信部1002が、運転曲線に基づいた列車走行指令情報を、後続列車に送信する。なお、自列車用の運転曲線に基づいた列車走行指令情報は、自列車のATO機能部256に受け渡される。これにより、自列車及び後続列車は、遅れの影響が少なくなるような自動運転制御が行われる。   When the operation curve generation unit 308 generates operation curves for all subsequent trains for which the influence of delay is predicted, the transmission unit 1002 transmits train travel command information based on the operation curves to the subsequent trains. In addition, the train travel command information based on the operation curve for the own train is transferred to the ATO function unit 256 of the own train. As a result, the own train and the following train are subjected to the automatic operation control so that the influence of the delay is reduced.

本実施形態においては、自列車の遅れが所定値未満となり、遅延が解消された場合に、自列車による、列車群の運行制御を終了する。そして、後続列車に遅れが残っている場合、遅れの先頭となった列車が、列車群の運行制御を行う。なお、列車群の運行制御は、上述した制御と同様とする。   In the present embodiment, when the delay of the own train is less than a predetermined value and the delay is eliminated, the operation control of the train group by the own train is terminated. And when a delay remains in a succeeding train, the train which became the head of delay performs operation control of a train group. The operation control of the train group is the same as the control described above.

なお、本実施形態では、遅延の先頭の列車に搭載された車上制御装置901が、後続の運転曲線を生成する例について説明したが、遅延の先頭の列車が他の列車の運転曲線を生成することに制限するものではない。例えば、線路180を走行している先頭列車が、当該線路180上を走行している全ての列車群の運転曲線を生成しても良い。   In the present embodiment, the on-board control device 901 mounted on the first train in the delay has been described as generating a subsequent driving curve. However, the first train in the delay generates a driving curve of another train. You are not limited to doing that. For example, the head train traveling on the track 180 may generate the operation curves of all train groups traveling on the track 180.

また、本実施形態は、第1の実施形態と同様にATO機能部256を備えた例について説明するが、第2の実施形態と同様に運転支援機能部801を設けても良い。これにより、運転士の運転を支援できるため、第2の実施形態と同様の効果を得られる。   Moreover, although this embodiment demonstrates the example provided with the ATO function part 256 similarly to 1st Embodiment, you may provide the driving assistance function part 801 similarly to 2nd Embodiment. Thereby, since a driver | operator's driving | operation can be supported, the effect similar to 2nd Embodiment can be acquired.

上述した実施形態によれば、列車に遅延が発生した場合、後続列車との運転間隔を考慮して、運転曲線を生成した。これにより、後続列車の遅れを抑止することができる。また、運転曲線を生成する際に、制御対象列車と後続列車との運転間隔だけで無く、制御対象列車と先行列車との運転間隔も考慮して、運転曲線を生成した。これにより、先行列車との位置関係による減速等を抑止できるため、遅れをさらに抑止できる。また、後続列車だけでなく、さらにその後続列車も考慮し、列車群の遅れが少なくなるように制御できる。   According to the above-described embodiment, when a delay occurs in the train, the operation curve is generated in consideration of the operation interval with the subsequent train. Thereby, the delay of a following train can be suppressed. Further, when generating the operation curve, the operation curve was generated in consideration of not only the operation interval between the control target train and the following train but also the operation interval between the control target train and the preceding train. Thereby, since the deceleration etc. by the positional relationship with a preceding train can be suppressed, a delay can be further suppressed. Further, not only the following train but also the succeeding train can be taken into consideration, and the delay of the train group can be controlled.

本発明のいくつかの実施形態を説明したが、これらの実施形態は、例として提示したものであり、発明の範囲を限定することは意図していない。これら新規な実施形態は、その他の様々な形態で実施されることが可能であり、発明の要旨を逸脱しない範囲で、種々の省略、置き換え、変更を行うことができる。これら実施形態やその変形は、発明の範囲や要旨に含まれるとともに、特許請求の範囲に記載された発明とその均等の範囲に含まれる。   Although several embodiments of the present invention have been described, these embodiments are presented by way of example and are not intended to limit the scope of the invention. These novel embodiments can be implemented in various other forms, and various omissions, replacements, and changes can be made without departing from the scope of the invention. These embodiments and modifications thereof are included in the scope and gist of the invention, and are included in the invention described in the claims and the equivalents thereof.

100…地上システム、101…地上制御装置、102…運行管理システム、103…ATC地上装置、105a〜105c…地上基地局、110…地上ネットワーク、150…車上システム、151…車上制御装置、170a〜170b…列車、180…線路、201…速度検知装置、202…位置検知装置、203…ATC車上装置、251…路線データベース、252…車両データベース、253…情報送信部、254…情報受信部、255…ノッチ情報取得部、256…ATO機能部、301…路線データベース、302…車両データベース、303…制御データベース、304…運行履歴データベース、305…受信部、306…運行予測部、307…判定部、308…運転曲線生成部、309…送信部、311…生成部、312…選択部、351…運行ダイヤデータベース、800…車上制御装置、801…運転支援機能部、850…表示器、901…車上制御装置、1001…受信部、1002…送信部。   DESCRIPTION OF SYMBOLS 100 ... Ground system, 101 ... Ground control apparatus, 102 ... Operation management system, 103 ... ATC ground apparatus, 105a-105c ... Ground base station, 110 ... Ground network, 150 ... On-board system, 151 ... On-board control apparatus, 170a ˜170b ... train, 180 ... track, 201 ... speed detector, 202 ... position detector, 203 ... ATC on-board device, 251 ... route database, 252 ... vehicle database, 253 ... information transmitter, 254 ... information receiver, 255 ... Notch information acquisition unit, 256 ... ATO function unit, 301 ... Route database, 302 ... Vehicle database, 303 ... Control database, 304 ... Operation history database, 305 ... Reception unit, 306 ... Operation prediction unit, 307 ... Determination unit, 308 ... Driving curve generation unit, 309 ... transmission unit, 311 ... generation unit, 312 Selecting unit, 351 ... operation schedule database, 800 ... train control unit, 801 ... driving support function unit, 850 ... display, 901 ... train control unit, 1001 ... receiving unit, 1002 ... transmitting portion.

Claims (10)

地上制御装置と、線路上を走行する複数の列車の各々に搭載された車上制御装置と、を備える走行制御システムであって、
前記車上制御装置は、
前記車上制御装置が搭載された列車の位置と速度とを前記地上制御装置に送信する第1の送信部を備え、
前記地上制御装置は、
前記複数の列車の各々に搭載された車上制御装置から、当該車上制御装置が搭載された列車の位置と速度とを受信する受信部と、
前記受信部が受信した列車の位置と速度とに基づいて、制御対象となる列車の運行ダイヤと、前記線路上を走行する前記制御対象となる列車の後ろの後続列車の運行ダイヤと、を予測する予測部と、
前記予測部が予測した前記運行ダイヤに従って前記制御対象となる列車と、前記後続列車と、が走行した場合における、前記制御対象となる列車と前記後続列車との位置関係に基づいて、前記制御対象となる列車が前記線路を走行する際の加速及び減速を行う区間を調整した、当該線路上の位置の変化に従った速度を表した走行計画を生成する生成部と、
前記生成部が生成した前記走行計画を、前記制御対象となる列車に搭載された前記車上制御装置に送信する第2の送信部と、
を備える走行制御システム。
A travel control system comprising a ground control device and an on-board control device mounted on each of a plurality of trains traveling on a track,
The on-vehicle controller is
A first transmission unit that transmits the position and speed of the train on which the on-board control device is mounted to the ground control device;
The ground control device is:
From the onboard control device mounted on each of the plurality of trains, a receiving unit that receives the position and speed of the train on which the onboard control device is mounted;
Based on the position and speed of the train received by the receiver, the operation schedule of the train to be controlled and the operation diagram of the subsequent train behind the train to be controlled traveling on the track are predicted. A prediction unit to
Based on the positional relationship between the train to be controlled and the subsequent train when the train to be controlled and the succeeding train travel according to the operation schedule predicted by the prediction unit, the control target A generation unit that generates a travel plan that represents a speed according to a change in position on the track, in which a train to be accelerated and decelerated when the train travels on the track is adjusted,
A second transmission unit that transmits the travel plan generated by the generation unit to the on-board control device mounted on the train to be controlled;
A travel control system comprising:
前記予測部は、さらに、前記制御対象となる列車より前の先行列車の運行ダイヤとして、当該先行列車の存在地点から、所定の加速度で加速して走行すると仮定した場合の、当該先行列車の運行ダイヤを予測し、
前記生成部は、前記予測部が予測した前記運行ダイヤに従って、前記制御対象となる列車と、前記先行列車と、を走行させた場合における、前記制御対象となる列車と前記先行列車との位置関係に基づいて、前記制御対象となる列車が前記線路を走行する際の加速及び減速を行う区間を調整した走行計画を生成する、
請求項1に記載の走行制御システム。
The prediction unit further operates the preceding train when it is assumed that the vehicle travels at a predetermined acceleration from the location of the preceding train as an operation diagram of the preceding train before the train to be controlled. Predict diamonds,
The generation unit, when the train to be controlled and the preceding train are run according to the operation schedule predicted by the prediction unit, the positional relationship between the train to be controlled and the preceding train Based on the, to generate a travel plan that adjusts the section to perform acceleration and deceleration when the train to be controlled travels on the track,
The travel control system according to claim 1.
前記生成部は、前記先行列車及び後続列車との位置関係に応じた走行計画を導出する際に、前記先行列車に基づいた基準位置までの走行経路のうち、減速する位置、減速度合い、及び減速してから走行する区間のうちいずれか一つ以上を異ならせた複数の走行計画を生成し、前記後続列車との位置関係に応じて、前記複数の走行計画からいずれか一つを選択する、
請求項2に記載の走行制御システム。
The generation unit, when deriving a travel plan according to the positional relationship between the preceding train and the subsequent train, among the travel routes to the reference position based on the preceding train, the position to decelerate, the degree of deceleration, Then, generate a plurality of travel plans that differ in any one or more of the sections to travel, and select one of the plurality of travel plans according to the positional relationship with the subsequent train,
The travel control system according to claim 2.
前記生成部は、前記後続列車との位置関係と、列車の電力消費量と、に応じて、前記複数の走行計画からいずれか一つを選択する、
請求項3に記載の走行制御システム。
The generation unit selects one of the plurality of travel plans according to the positional relationship with the subsequent train and the power consumption of the train.
The travel control system according to claim 3.
前記生成部は、前記先行列車が閉そく区間から移動すると予測される時刻に、当該閉そく区間に基づいた、前記制御対象となる列車を減速させる第1の位置まで、前記制御対象となる列車を移動させず、且つ、前記制御対象となる列車の現在の走行速度である、第1の速度を維持させるため、前記第1の位置より進行方向反対側の第2の位置まで前記第1の速度で走行した後、前記第1の速度より低い第2の速度まで減速させた後、当該第2の速度から加速させることで、前記予測される時刻より後に前記第1の位置に、前記第1の速度で到達する運転曲線を生成する、
請求項2乃至4のいずれか一つに記載の走行制御システム。
The generation unit moves the control target train to a first position based on the block section to decelerate the control target train at a time when the preceding train is predicted to move from the block section. In order to maintain the first speed, which is the current traveling speed of the train to be controlled, at the first speed to the second position on the opposite side of the traveling direction from the first position. After traveling, the vehicle is decelerated to a second speed lower than the first speed, and then accelerated from the second speed, so that the first position is moved to the first position after the predicted time. Generate a driving curve that reaches at speed,
The travel control system according to any one of claims 2 to 4.
前記生成部は、当該先行列車が閉そく区間から移動すると予測される時刻に、当該閉そく区間に基づいた、前記制御対象となる列車を減速させる第1の位置まで、前記制御対象となる列車が移動しないように、前記制御対象となる列車の現在の走行速度である、第1の速度から第3の速度まで低下させた後、前記第3の速度で可能な限り長い距離を走行させた運転曲線を生成する、
請求項2乃至4のいずれか一つに記載の走行制御システム。
The generation unit moves the control target train to a first position based on the block section to decelerate the control target train at a time when the preceding train is predicted to move from the block section. So that the current running speed of the train to be controlled is reduced from the first speed to the third speed, and then traveled as long as possible at the third speed. Generate
The travel control system according to any one of claims 2 to 4.
前記生成部は、当該先行列車が存在する閉そく区間に基づいた、前記制御対象となる列車を減速させる第1の位置まで、惰行で走行させる運転曲線を生成する、
請求項2乃至4のいずれか一つに記載の走行制御システム。
The generation unit generates an operation curve that runs on coasting to a first position that decelerates the train to be controlled based on a closed section where the preceding train exists.
The travel control system according to any one of claims 2 to 4.
過去の運行中の車両故障などに関する故障原因と、回復までに要した時間と、を記憶した記憶部を、さらに備え、
前記予測部は、前記記憶部を参照して、前記制御対象となる列車の運行ダイヤと、前記後続列車の運行ダイヤと、を予測する、
請求項1乃至7のいずれか一つに記載の走行制御システム。
A storage unit that stores the cause of failure related to vehicle failures in the past and the time required for recovery is further provided,
The prediction unit refers to the storage unit and predicts a train schedule of the control target train and a schedule of the subsequent train.
The travel control system according to any one of claims 1 to 7.
自列車の位置と速度とを取得する取得部と、
前記自列車より後ろを走行する後続列車から、位置と速度とを受信する受信部と、
前記取得部が取得した前記自列車の位置と速度、及び前記受信部が受信した前記後続列車の位置と速度に基づいて、前記自列車の運行ダイヤと、前記後続列車の運行ダイヤと、を予測する予測部と、
前記予測部が予測した前記運行ダイヤに従って前記自列車と、前記後続列車と、が走行した場合における、前記自列車と前記後続列車との位置関係に基づいて、前記自列車が線路を走行する際の加速及び減速を行う区間を調整した、当該線路上の位置の変化に従った速度を表した走行計画を生成する生成部と、
前記生成部が生成した前記走行計画に従って、前記自列車の走行を制御する制御部と、
を備える走行制御装置。
An acquisition unit for acquiring the position and speed of the own train;
A receiving unit that receives a position and a speed from a subsequent train that runs behind the own train;
Based on the position and speed of the own train acquired by the acquisition unit and the position and speed of the subsequent train received by the reception unit, the operation schedule of the own train and the operation diagram of the subsequent train are predicted. A prediction unit to
When the own train travels on the track based on the positional relationship between the own train and the subsequent train when the own train and the subsequent train travel according to the operation schedule predicted by the prediction unit. A generation unit that generates a travel plan that represents a speed according to a change in the position on the track, in which a section for performing acceleration and deceleration is adjusted,
In accordance with the travel plan generated by the generation unit, a control unit that controls the travel of the own train,
A travel control device comprising:
前記生成部は、さらに、前記予測部が予測した前記運行ダイヤに従って前記自列車と、前記後続列車と、が走行した場合における、前記自列車と前記後続列車との位置関係に基づいて、前記後続列車が前記線路を走行する際の加速及び減速を行う区間を調整した、当該線路上の位置の変化に従った速度を表した第2の走行計画を生成し、
前記生成部が生成した前記第2の走行計画を、前記後続列車に送信する送信部を、さらに備える、
請求項9に記載の走行制御装置。
The generation unit is further configured based on a positional relationship between the own train and the subsequent train when the own train and the subsequent train travel according to the operation schedule predicted by the prediction unit. A second travel plan that represents the speed according to the change in position on the track, adjusting the section for acceleration and deceleration when the train travels on the track,
A transmission unit for transmitting the second travel plan generated by the generation unit to the subsequent train;
The travel control device according to claim 9.
JP2016168423A 2016-08-30 2016-08-30 Travel control system and travel control device Pending JP2018034610A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016168423A JP2018034610A (en) 2016-08-30 2016-08-30 Travel control system and travel control device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016168423A JP2018034610A (en) 2016-08-30 2016-08-30 Travel control system and travel control device

Publications (1)

Publication Number Publication Date
JP2018034610A true JP2018034610A (en) 2018-03-08

Family

ID=61566738

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016168423A Pending JP2018034610A (en) 2016-08-30 2016-08-30 Travel control system and travel control device

Country Status (1)

Country Link
JP (1) JP2018034610A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021041858A (en) * 2019-09-12 2021-03-18 公益財団法人鉄道総合技術研究所 Simulation device and program for the same
JP2021121149A (en) * 2020-01-30 2021-08-19 株式会社東芝 Train control device and train control method
CN114348061A (en) * 2021-12-17 2022-04-15 交控科技股份有限公司 Train route handling method and system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021041858A (en) * 2019-09-12 2021-03-18 公益財団法人鉄道総合技術研究所 Simulation device and program for the same
JP7361298B2 (en) 2019-09-12 2023-10-16 公益財団法人鉄道総合技術研究所 Simulation equipment and programs
JP2021121149A (en) * 2020-01-30 2021-08-19 株式会社東芝 Train control device and train control method
JP7433933B2 (en) 2020-01-30 2024-02-20 株式会社東芝 Train control device and train control method
CN114348061A (en) * 2021-12-17 2022-04-15 交控科技股份有限公司 Train route handling method and system

Similar Documents

Publication Publication Date Title
KR102096963B1 (en) Method for constructing virtual-coupled train sets and train control device thereof
US8774992B2 (en) Operation support device and automatic operation device
US9689681B2 (en) System and method for vehicle operation
CN107709136B (en) Method and device for determining driving authorization for a rail vehicle
EP2292492A2 (en) Apparatus and method for controlling speed in automatic train operation
EP2857255A1 (en) Train control device
JP2018172053A (en) Train operation control system
CN109532955B (en) Micro-rail scheduling control method and system
KR101866610B1 (en) Apparatus for Warning of Exceeding Speed Limit in Railway Vehicles
CN111422226B (en) Block partition setting method and device and storage medium
JP5813396B2 (en) Train control system
KR20210013210A (en) Controllers, systems and methods for vehicle control
CN109625029A (en) A kind of Train Group control method out of the station and system
JP2018034610A (en) Travel control system and travel control device
CN110877616A (en) Electric energy consumption optimization method, storage medium and automatic driving and monitoring system
JP2006137337A (en) Train control system and train control method
EP2470408B1 (en) Initialisation of a signalling system
JP7433933B2 (en) Train control device and train control method
KR20160071645A (en) Train coupling-decoupling system
JP5512193B2 (en) Train control method, train control device, and vehicle
JP6126669B1 (en) Train control system, on-board device, and train control method
JP2010136561A (en) Method and device for controlling train operation
JP2018083495A (en) Train operation control system
JP2019089449A (en) Device, method and program for train travel control
JPWO2018207480A1 (en) Automatic train security equipment and on-board equipment

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20170911

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20170912