JP2017106236A - Structure construction method and structure - Google Patents

Structure construction method and structure Download PDF

Info

Publication number
JP2017106236A
JP2017106236A JP2015240845A JP2015240845A JP2017106236A JP 2017106236 A JP2017106236 A JP 2017106236A JP 2015240845 A JP2015240845 A JP 2015240845A JP 2015240845 A JP2015240845 A JP 2015240845A JP 2017106236 A JP2017106236 A JP 2017106236A
Authority
JP
Japan
Prior art keywords
footing member
precast
precast member
footing
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2015240845A
Other languages
Japanese (ja)
Other versions
JP6628588B2 (en
Inventor
太朗 水谷
Taro Mizutani
太朗 水谷
正樹 村瀬
Masaki Murase
正樹 村瀬
智紀 八須
Tomonori Hachisu
智紀 八須
伸悟 梶原
Shingo Kajiwara
伸悟 梶原
博文 稲田
Hirobumi Inada
博文 稲田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2015240845A priority Critical patent/JP6628588B2/en
Publication of JP2017106236A publication Critical patent/JP2017106236A/en
Application granted granted Critical
Publication of JP6628588B2 publication Critical patent/JP6628588B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To efficiently construct a structure while securing erection accuracy of a skeleton thereof to be installed on a seismic isolation device.SOLUTION: A construction method of a structure 1 comprises the processes to: install a lower footing member 60 made of precast concrete on a seismic isolation device 5; install an upper footing member 70 made of the precast concrete on the lower footing member 60 with a gap S above the same; adjust erection of the upper footing member 70; fill the gap S between the upper footing member 70 with the erection thereof adjusted and the lower footing member 60 with a filling material 100 and harden the same; and connect the upper footing member 70 to at least either a column section 7 or a foundation beam 8 constituting a skeleton of the structure 1.SELECTED DRAWING: Figure 1

Description

本発明は、構造物の施工方法、構造物に関する。   The present invention relates to a structure construction method and a structure.

各種の構造物の基礎部に免震装置を設け、地震等の発生時に、地盤から躯体に伝達される振動を減衰させる免震構造が用いられている。このような免震構造では、地盤上に構築した下部基礎と、躯体の底部に形成される上部基礎との間に、免震装置を介在させる。   Seismic isolation devices are used in the base of various structures to attenuate the vibrations transmitted from the ground to the frame in the event of an earthquake. In such a seismic isolation structure, a seismic isolation device is interposed between the lower foundation constructed on the ground and the upper foundation formed at the bottom of the frame.

ここで、基礎部は、鉄筋の配筋密度も高く、使用するコンクリートの量も多いため、現場打ちで基礎部を施工すると、時間とコストが掛かる。
そこで、特許文献1、2には、躯体の構築を効率良く行うため、下部基礎上に設けた免震装置上に、上部基礎の一部を形成するプレキャストコンクリート製のPCa部材を設ける構成が開示されている。
Here, since the foundation part has a high reinforcing bar arrangement density and a large amount of concrete to be used, it takes time and cost to construct the foundation part on site.
Therefore, Patent Documents 1 and 2 disclose a configuration in which a precast concrete PCa member that forms a part of the upper foundation is provided on the base isolation device provided on the lower foundation in order to efficiently construct the frame. Has been.

特開2014−95201号公報JP 2014-95201 A 特許第5232106号公報Japanese Patent No. 5232106

上記したようなPCa材からなるフーチング上には、構造物の躯体を構成する柱が立設され、この柱の基部に基礎梁が接合される。このため、フーチング上における柱の立設、柱と基礎梁との接合部の施工に、依然として時間とコストが掛かる。   On the footing made of the PCa material as described above, a pillar constituting the structural body is erected, and a foundation beam is joined to the base of the pillar. For this reason, it takes time and cost to erect the pillar on the footing and to construct the joint between the pillar and the foundation beam.

これに対し、PCa材に柱材を一体に形成することも考えられるが、このような構成では、PCa材を免震装置上に設置する際に、柱材の建方精度が決まってしまう。免震装置上にPCa材を載せる構造では、PCa材の建方調整を行うのは困難である。
そこでなされた本発明の目的は、免震装置上に設ける構造物の躯体の建方精度を確保しつつ、施工を効率良く行うことのできる構造物の施工方法、構造物を提供することである。
On the other hand, it is conceivable to form the pillar material integrally with the PCa material. However, in such a configuration, the construction accuracy of the pillar material is determined when the PCa material is installed on the seismic isolation device. In the structure in which the PCa material is placed on the seismic isolation device, it is difficult to adjust the construction of the PCa material.
An object of the present invention made there is to provide a structure construction method and a structure capable of performing construction efficiently while ensuring the accuracy of the construction of the structural frame provided on the seismic isolation device. .

本発明は、上記課題を解決するため、以下の手段を採用する。
すなわち、本発明の構造物の施工方法は、免震装置上にプレキャストコンクリートからなる第一プレキャスト部材を設置する工程と、プレキャストコンクリートからなる第二プレキャスト部材を、前記第一プレキャスト部材の上方に間隙を空けて設置する工程と、前記第二プレキャスト部材の建方調整を行う工程と、建方調整を行った前記第二プレキャスト部材と前記第一プレキャスト部材との前記間隙に硬化性充填材を充填し、硬化させる工程と、前記第二プレキャスト部材に、構造物の躯体を構成する柱および梁の少なくとも一方を接合する工程と、を備えることを特徴とする。
The present invention employs the following means in order to solve the above problems.
That is, the construction method of the structure of the present invention includes a step of installing a first precast member made of precast concrete on a seismic isolation device, and a second precast member made of precast concrete with a gap above the first precast member. And a step of adjusting the construction of the second precast member, and filling the gap between the second precast member and the first precast member subjected to the construction adjustment with a curable filler. And a step of curing, and a step of joining at least one of a column and a beam constituting a housing of the structure to the second precast member.

このような構成によれば、免震装置上に第一プレキャスト部材を設置した後、その上方に第二プレキャスト部材を配置し、建方調整を行う。この後、第二プレキャスト部材と第一プレキャスト部材との間隙に硬化性充填材を充填して硬化させる。これにより、構造物の躯体を構成する柱および梁の少なくとも一方が接合される第二プレキャスト部材を、建方精度を確保して設置することができる。
また、構造物の躯体を構成する柱および梁の少なくとも一方が接合される接合部を、プレキャストコンクリート造の第二プレキャスト部材で構成することで、現場での鉄筋配筋やコンクリート打ち作業の量を抑えることができる。
According to such a structure, after installing a 1st precast member on a seismic isolation apparatus, a 2nd precast member is arrange | positioned upwards and a construction adjustment is performed. Thereafter, the gap between the second precast member and the first precast member is filled with a curable filler and cured. Thereby, the 2nd precast member to which at least one of the pillar and beam which constitutes the frame of a structure is joined can be installed, ensuring construction accuracy.
Also, by constructing the joint where at least one of the pillars and beams that make up the structure's frame are joined with the second precast member made of precast concrete, the amount of rebar reinforcement and concrete placement work at the site can be reduced. Can be suppressed.

本発明の一態様においては、前記第二プレキャスト部材に、前記柱の最下端部が接続される柱接続部材の基部が埋設されている。
このような構成によれば、第二プレキャスト部材の建方調整を行うことによって、柱接続部材も同時に建方調整がなされる。したがって、硬化性充填材の硬化後は、構造物の躯体を構成する柱を柱接続部材に速やかに接合して、施工作業を進めることが可能となる。これによっても、施工の効率化を図ることができる。
In one aspect of the present invention, a base portion of a column connecting member to which the lowermost end portion of the column is connected is embedded in the second precast member.
According to such a configuration, the column connecting member is also adjusted in the construction at the same time by adjusting the construction of the second precast member. Therefore, after the curable filler is cured, it is possible to quickly join the columns constituting the structural body to the column connection member and to proceed with the construction work. Also by this, construction efficiency can be improved.

本発明の一態様においては、前記第一プレキャスト部材の上面に凹部または凸部からなる係合部が形成され、前記第二プレキャスト部材の下面に前記係合部に係合する被係合部が形成されている。
このような構成によれば、第一プレキャスト部材の係合部と第二プレキャスト部材の被係合部を係合させることで、第一プレキャスト部材と第二プレキャスト部材との間で、水平方向のせん断力を確実に伝達することが可能となる。
In one aspect of the present invention, an engaging portion formed of a concave portion or a convex portion is formed on the upper surface of the first precast member, and an engaged portion that engages with the engaging portion is formed on the lower surface of the second precast member. Is formed.
According to such a configuration, by engaging the engaging portion of the first precast member and the engaged portion of the second precast member, the horizontal direction is between the first precast member and the second precast member. It is possible to reliably transmit the shearing force.

また、本発明の構造物は、基礎上に設けられた免震装置と、前記免震装置上に設けられ、プレキャストコンクリートからなる第一プレキャスト部材と、プレキャストコンクリートからなり、前記第一プレキャスト部材の上方に間隙を空けて設けられ、構造物の躯体を構成する柱および梁の少なくとも一方が接合される第二プレキャスト部材と、前記第二プレキャスト部材と前記第一プレキャスト部材との前記間隙に充填された硬化性充填材と、を備えることを特徴とする。
このような構成は、免震装置上に第一プレキャスト部材を設置し、その上方に第二プレキャスト部材を配置し、建方調整を行った後、第二プレキャスト部材と第一プレキャスト部材との間隙に硬化性充填材を充填して硬化させることが実現できる。これにより、構造物の躯体を構成する柱および梁の少なくとも一方が接合される第二プレキャスト部材を、建方精度を確保して設置することができる。
また、構造物の躯体を構成する柱および梁の少なくとも一方が接合される接合部を、プレキャストコンクリート造の第二プレキャスト部材で構成することで、現場での鉄筋配筋やコンクリート打ち作業の量を抑えることができる。
Moreover, the structure of the present invention is provided with a base isolation device provided on a foundation, a first precast member provided on the base isolation device and made of precast concrete, and a precast concrete. A gap is provided between the second precast member and the first precast member, and a second precast member which is provided with a gap above and to which at least one of a column and a beam constituting a structural body is joined. And a curable filler.
In such a configuration, after the first precast member is installed on the seismic isolation device, the second precast member is disposed above the seismic isolation device, and the construction is adjusted, the gap between the second precast member and the first precast member is set. It can be realized that the curable filler is filled and cured. Thereby, the 2nd precast member to which at least one of the pillar and beam which constitutes the frame of a structure is joined can be installed, ensuring construction accuracy.
Also, by constructing the joint where at least one of the pillars and beams that make up the structure's frame are joined with the second precast member made of precast concrete, the amount of rebar reinforcement and concrete placement work at the site can be reduced. Can be suppressed.

本発明の一態様においては、前記第一プレキャスト部材の上端は、前記第二プレキャスト部材に接合される前記梁の下面よりも上方に位置している。
このような構成によれば、第一プレキャスト部材と梁とが直接突き当たり、水平方向のせん断力の伝達を効率よくかつ確実に行うことができる。
In one mode of the present invention, the upper end of the first precast member is located above the lower surface of the beam joined to the second precast member.
According to such a configuration, the first precast member and the beam directly abut against each other, and the horizontal shear force can be transmitted efficiently and reliably.

本発明によれば、免震装置上に設ける構造物の躯体の建方精度を確保しつつ、施工を効率良く行うことが可能となる。   ADVANTAGE OF THE INVENTION According to this invention, it becomes possible to perform construction efficiently, ensuring the construction accuracy of the frame of the structure provided on a seismic isolation apparatus.

本実施形態に係る構造物の基礎部の構成を示す立断面図である。It is a sectional elevation showing the composition of the foundation of the structure concerning this embodiment. 上記構造物を構成する下部フーチング部材の構成を示す立断面図である。It is a sectional elevation showing the composition of the lower footing member which constitutes the above-mentioned structure. 下部フーチング部材を示す平面図である。It is a top view which shows a lower footing member. 上部フーチング部材の構成を示す立断面図である。It is an elevation sectional view showing the composition of the upper footing member. 基礎梁部材の構成を示す断面図である。It is sectional drawing which shows the structure of a foundation beam member. 構造物の施工方法の流れを示す図である。It is a figure which shows the flow of the construction method of a structure. 構造物の施工方法を示す図であり、免震装置を設置した状態を示す立断面図である。It is a figure which shows the construction method of a structure, and is a vertical sectional view which shows the state which installed the seismic isolation apparatus. 免震装置上に下部フーチング部材を設置した状態を示す立断面図である。It is an elevation sectional view showing the state where the lower footing member was installed on the seismic isolation device. 下部フーチング部材上に上部フーチング部材を配置した状態を示す立断面図である。It is an elevation sectional view showing the state where the upper footing member is arranged on the lower footing member. 上部フーチング部材の周囲に基礎梁部材を配置した状態を示す立断面図である。It is an elevation sectional view showing the state where the foundation beam member is arranged around the upper footing member.

以下、添付図面を参照して、本発明による構造物の施工方法、構造物を実施するための形態について、図面に基づいて説明する。   DESCRIPTION OF EMBODIMENTS Hereinafter, a construction method for a structure according to the present invention and a mode for carrying out the structure will be described with reference to the accompanying drawings.

図1は、本実施形態に係る構造物の基礎部の構成を示す立断面図である。
図1に示すように、構造物1は、基礎部2上に構築されている。
基礎部2は、地盤上に構築された下部基礎(基礎)3と、下部基礎3の上方に間隔を空けて設けられ、構造物1の躯体(図示無し)を支持する上部基礎4と、下部基礎3と上部基礎4との間に設けられる免震装置5と、を備えている。
FIG. 1 is an elevational cross-sectional view showing the configuration of the foundation of the structure according to the present embodiment.
As shown in FIG. 1, the structure 1 is constructed on a base portion 2.
The base part 2 includes a lower base (foundation) 3 constructed on the ground, an upper base 4 provided above the lower base 3 with a space therebetween, and supporting a frame (not shown) of the structure 1; A seismic isolation device 5 provided between the foundation 3 and the upper foundation 4.

下部基礎3は、現場打ちコンクリートにより形成され、地盤上に沿って設けられた基礎スラブ31と、基礎スラブ31上の所定位置に形成され、上方に向かって突出する基礎ベース32と、を備えている。   The lower foundation 3 includes a foundation slab 31 that is formed of cast-in-place concrete and is provided along the ground, and a foundation base 32 that is formed at a predetermined position on the foundation slab 31 and protrudes upward. Yes.

免震装置5は、上下に設けられたフランジプレート51,52と、これらフランジプレート51,52間に設けられた積層ゴム部53と、を備えている。免震装置5は、基礎ベース32上に、下部ベースプレート54を介して設置され、下方のフランジプレート51が下部ベースプレート54とともに、複数本のアンカーボルト55によって基礎ベース32に固定されている。   The seismic isolation device 5 includes flange plates 51 and 52 provided on the upper and lower sides, and a laminated rubber portion 53 provided between the flange plates 51 and 52. The seismic isolation device 5 is installed on the foundation base 32 via a lower base plate 54, and a lower flange plate 51 is fixed to the foundation base 32 by a plurality of anchor bolts 55 together with the lower base plate 54.

上部基礎4は、免震装置5上に設けられたフーチング部6と、フーチング部6から鉛直上方に向かって延びる柱部(柱)7と、フーチング部6から水平方向に延びる基礎梁(梁)8と、を備える。つまり、柱部7と基礎梁8とは、フーチング部6で互いに接合されている。これにより、フーチング部6は、柱部7と基礎梁8との柱梁接合部を構成している。   The upper foundation 4 includes a footing portion 6 provided on the seismic isolation device 5, a column portion (column) 7 extending vertically upward from the footing portion 6, and a foundation beam (beam) extending horizontally from the footing portion 6. 8. That is, the column part 7 and the foundation beam 8 are joined to each other by the footing part 6. Thereby, the footing part 6 comprises the column beam junction part of the column part 7 and the foundation beam 8. FIG.

フーチング部6は、免震装置5上に上部ベースプレート56を介して設けられた下部フーチング部材(第一プレキャスト部材)60と、下部フーチング部材60の上方に設けられた(第二プレキャスト部材)上部フーチング部材70と、下部フーチング部材60と上部フーチング部材70との間に充填された充填材(硬化性充填材)100と、を備えている。   The footing unit 6 includes a lower footing member (first precast member) 60 provided on the base isolation device 5 via the upper base plate 56 and an upper footing provided above the lower footing member 60 (second precast member). A member 70 and a filler (curable filler) 100 filled between the lower footing member 60 and the upper footing member 70 are provided.

図2は、下部フーチング部材の構成を示す立断面図である。図3は、下部フーチング部材を示す平面図である。
この図2、図3に示すように、下部フーチング部材60は、略直方体状のプレキャストコンクリート製で、その下面60b(図2参照)は平面状とされ、上面60aの中央部には、凹部(係合部)61が形成されている。凹部61は、平面視正方形状で、上面60aと平行な底面61aと、底面61aの外周部から上方に向かって漸次外周側に広がる傾斜面61bと、を有している。
FIG. 2 is an elevational sectional view showing the configuration of the lower footing member. FIG. 3 is a plan view showing the lower footing member.
As shown in FIGS. 2 and 3, the lower footing member 60 is made of precast concrete having a substantially rectangular parallelepiped shape, and the lower surface 60b (see FIG. 2) has a planar shape, and a recess ( (Engagement portion) 61 is formed. The recess 61 has a square shape in plan view, and includes a bottom surface 61a parallel to the upper surface 60a, and an inclined surface 61b that gradually spreads upward from the outer periphery of the bottom surface 61a toward the outer periphery.

図2に示すように、下部フーチング部材60には、補強筋62と、接続筋(鉄筋)63と、接続ナット(ナット)64と、が埋設されている。   As shown in FIG. 2, a reinforcing bar 62, a connecting bar (rebar) 63, and a connecting nut (nut) 64 are embedded in the lower footing member 60.

接続筋63は、凹部61の外周側に、周方向に間隔を空けて複数設けられている。各接続筋63は、その上端部63tが下部フーチング部材60の上面60aから上方に突出するよう設けられている。   A plurality of connecting bars 63 are provided on the outer peripheral side of the recess 61 with a gap in the circumferential direction. Each connecting bar 63 is provided such that its upper end 63 t protrudes upward from the upper surface 60 a of the lower footing member 60.

接続ナット64は、下部フーチング部材60の中心軸回りに周方向に間隔を空けて複数設けられている。各接続ナット64は、その下端が下部フーチング部材60の下面60bに露出するよう設けられている。接続ナット64の上端部には、下部フーチング部材60に埋設された定着部材アンカー65が連結されている。   A plurality of connection nuts 64 are provided around the central axis of the lower footing member 60 at intervals in the circumferential direction. Each connection nut 64 is provided such that its lower end is exposed on the lower surface 60 b of the lower footing member 60. A fixing member anchor 65 embedded in the lower footing member 60 is connected to the upper end portion of the connection nut 64.

図1に示すように、各接続ナット64には、免震装置5の上方のフランジプレート52および上部ベースプレート56を貫通し、締結ボルト(接合ボルト)57が締結されている。これにより、免震装置5と下部フーチング部材60とが連結されている。   As shown in FIG. 1, a fastening bolt (joint bolt) 57 is fastened to each connection nut 64 through the flange plate 52 and the upper base plate 56 above the seismic isolation device 5. Thereby, the seismic isolation apparatus 5 and the lower footing member 60 are connected.

図2、図3に示すように、下部フーチング部材60には、グラウト材充填孔66が形成されている。グラウト材充填孔66は、一端66aが下部フーチング部材60の側面60sに開口し、他端66bが凹部61の底面61aの中央部に開口している。   As shown in FIGS. 2 and 3, a grout material filling hole 66 is formed in the lower footing member 60. The grout material filling hole 66 has one end 66 a that opens to the side surface 60 s of the lower footing member 60, and the other end 66 b that opens to the center of the bottom surface 61 a of the recess 61.

図4は、上部フーチング部材の構成を示す立断面図である。
図4に示すように、上部フーチング部材70は、プレキャストコンクリート製のPCa部71を有する。PCa部71は、略直方体状で、平面視したときの外形寸法が下部フーチング部材60と同一とされている。
PCa部71は、その上面71aが平面状とされ、下面71bには、下方に向かって突出する凸部(被係合部)72を備えている。凸部72は、下部フーチング部材60の上面60aに形成された凹部61(図1参照)内に挿入される。この凸部72は、下面71bよりも下方に位置し、下面71bと平行に形成された下端面72aと、下端面72aの外周部から上方に向かって漸次外方に傾斜した傾斜面72bと、を備える。
FIG. 4 is an elevational sectional view showing the configuration of the upper footing member.
As shown in FIG. 4, the upper footing member 70 has a PCa portion 71 made of precast concrete. The PCa portion 71 has a substantially rectangular parallelepiped shape, and has the same outer dimensions as the lower footing member 60 when viewed in plan.
The PCa portion 71 has a flat upper surface 71a, and a lower surface 71b provided with a convex portion (engaged portion) 72 protruding downward. The convex portion 72 is inserted into a concave portion 61 (see FIG. 1) formed on the upper surface 60a of the lower footing member 60. The convex portion 72 is located below the lower surface 71b and is formed in parallel with the lower surface 71b, a lower end surface 72a, and an inclined surface 72b that gradually inclines outward from the outer peripheral portion of the lower end surface 72a, Is provided.

上部フーチング部材70のPCa部71には、鉄骨部73と、補強筋74と、接続筋75と、が埋設されている。   In the PCa portion 71 of the upper footing member 70, a steel frame portion 73, a reinforcing bar 74, and a connecting bar 75 are embedded.

鉄骨部73は、各基礎梁8のそれぞれに向かって水平方向に延びる梁接続部73Jを有している。この鉄骨部73は、基礎梁8が四方に配置されているのであれば平面視十字状をなし、基礎梁8が三方に配置されているのであれば平面視T字状をなす。鉄骨部73の各梁接続部73Jは、鉛直面内に位置するウェブ73aと、ウェブ73aの上下に形成され、水平面内に位置するフランジ73b,73bと、を備えている。   The steel frame portion 73 has beam connection portions 73J extending in the horizontal direction toward the respective foundation beams 8. The steel frame 73 has a cross shape in plan view if the foundation beam 8 is arranged in four directions, and has a T-shape in plan view if the foundation beam 8 is arranged in three directions. Each beam connecting portion 73J of the steel frame portion 73 includes a web 73a located in the vertical plane, and flanges 73b and 73b formed above and below the web 73a and located in the horizontal plane.

補強筋74は、各梁接続部73Jに沿って延びる主筋74aと、フープ筋74bとを備えている。   The reinforcing bar 74 includes a main bar 74a extending along each beam connecting portion 73J and a hoop bar 74b.

各梁接続部73Jの先端部73sと、主筋74aの先端部74sとは、PCa71の側面71sから水平方向外方に向かって突出している。   The distal end portion 73s of each beam connecting portion 73J and the distal end portion 74s of the main bar 74a protrude from the side surface 71s of the PCa 71 outward in the horizontal direction.

接続筋75は、PCa部71内で上下方向に延びて設けられている。接続筋75は、凸部72の外周側で周方向に間隔を空けて複数設けられている。PCa部71には、筒状の機械式継手76が埋設されている。この機械式継手76の下端はPCa部71の下面71bに露出している。各接続筋75は、その下端部が機械式継手76内に挿入されている。
また、PCa部71の側面71sには、各機械式継手76内に連通する注入穴77が形成されている。
The connecting bar 75 is provided so as to extend in the vertical direction in the PCa portion 71. A plurality of connecting bars 75 are provided at intervals on the outer peripheral side of the convex portion 72 in the circumferential direction. A cylindrical mechanical joint 76 is embedded in the PCa portion 71. The lower end of the mechanical joint 76 is exposed on the lower surface 71 b of the PCa portion 71. Each connecting bar 75 has a lower end inserted into the mechanical joint 76.
An injection hole 77 communicating with each mechanical joint 76 is formed on the side surface 71 s of the PCa portion 71.

各機械式継手76には、下部フーチング部材60の上面60aから上方に突出した接続筋63の上端部63t(図2参照)が挿入される。
機械式継手76内に挿入された接続筋75の下端部と接続筋63の上端部とは、注入穴77を通して機械式継手76内に注入されるモルタル等の接合材により一体に接合される。
In each mechanical joint 76, an upper end portion 63t (see FIG. 2) of the connecting bar 63 protruding upward from the upper surface 60a of the lower footing member 60 is inserted.
The lower end portion of the connecting bar 75 inserted into the mechanical joint 76 and the upper end portion of the connecting bar 63 are integrally joined by a joining material such as mortar injected into the mechanical joint 76 through the injection hole 77.

図1に示したように、このような上部フーチング部材70は、PCa部71の下面71bに形成された凸部72を、下部フーチング部材60の上面60aに形成された凹部61内に挿入した状態で設置される。   As shown in FIG. 1, such an upper footing member 70 is in a state in which the convex portion 72 formed on the lower surface 71 b of the PCa portion 71 is inserted into the concave portion 61 formed on the upper surface 60 a of the lower footing member 60. Installed at.

図4に示すように、上部フーチング部材70の鉄骨部73上には、上方に向かって延びる基柱鉄骨(柱接続部材)79が設けられている。基柱鉄骨79は、その基部79aのみがPCa部71に埋設され、基部79aよりも上方は、PCa部71の上面71aから上方に向かって突出している。
柱部7は、この基柱鉄骨79上に接合されて構成される。この実施形態において、柱部7は、鉄骨造であり、基柱鉄骨79上に、溶接等により接合される。
As shown in FIG. 4, a base column steel frame (column connection member) 79 extending upward is provided on the steel frame portion 73 of the upper footing member 70. Only the base 79a of the base column steel frame 79 is embedded in the PCa portion 71, and the upper side of the base portion 79a protrudes upward from the upper surface 71a of the PCa portion 71.
The column portion 7 is configured to be joined on the base column steel frame 79. In this embodiment, the column portion 7 is made of steel and is joined to the base column steel frame 79 by welding or the like.

図1に示すように、充填材100は、下部フーチング部材60と上部フーチング部材70との間に充填されている。充填材100は、例えばモルタル等の硬化性充填材である。充填材100は、後に詳述するが、建方精度を出した上部フーチング部材70を下部フーチング部材60の上方に位置決めした状態で、下部フーチング部材60に形成したグラウト材充填孔66(図2参照)から充填し、硬化させる。   As shown in FIG. 1, the filler 100 is filled between the lower footing member 60 and the upper footing member 70. The filler 100 is a curable filler such as mortar. As will be described in detail later, the filler 100 has a grout material filling hole 66 (see FIG. 2) formed in the lower footing member 60 in a state where the upper footing member 70 with high building accuracy is positioned above the lower footing member 60. ) And cured.

各基礎梁8は、本実施形態では鉄骨鉄筋コンクリート造とされている。基礎梁8は、プレキャストコンクリート造の基礎梁部材80を用いて形成されている。
図5は、基礎梁部材の構成を示す断面図である。
図1、図5に示すように、基礎梁部材80は、梁鉄骨81と、主筋83およびフープ筋84からなる鉄筋82とが、プレキャストコンクリート製のPCa部85に埋設されて構成されている。
図1に示すように、梁鉄骨81の端部81aと、主筋83の端部83aとは、PCa部85の端面85sから、それぞれの長さ方向に突出して設けられている。
Each foundation beam 8 is made of steel reinforced concrete in this embodiment. The foundation beam 8 is formed using a foundation beam member 80 made of precast concrete.
FIG. 5 is a cross-sectional view showing the configuration of the foundation beam member.
As shown in FIGS. 1 and 5, the foundation beam member 80 is configured by embedding a beam steel frame 81 and a reinforcing bar 82 including a main bar 83 and a hoop bar 84 in a PCa portion 85 made of precast concrete.
As shown in FIG. 1, the end portion 81 a of the beam steel frame 81 and the end portion 83 a of the main bar 83 are provided so as to protrude from the end surface 85 s of the PCa portion 85 in the respective length directions.

上部フーチング部材70と、各基礎梁8とは、現場打ちコンクリートによって接合されている。すなわち、梁接続部73Jの先端部73sと、基礎梁8の梁鉄骨81の端部81aとは、継手プレート90を介して接合されている。また、上部フーチング部材70のPca部71の側面71sから突出した主筋74aの先端部74sと、基礎梁8のPCa部85の端面85sから突出した主筋83の端部83aとは、筒状の機械式継手91を介して接合されている。さらに、主筋74a、83の周囲には、フープ筋92が設けられている。そして、上部フーチング部材70のPCa部71の側面71sと、各基礎梁8のPCa部85の端面85sとの間に打設されたコンクリート93により、上部フーチング部材70と各基礎梁8とが接合されている。   The upper footing member 70 and each foundation beam 8 are joined by spot cast concrete. That is, the distal end portion 73 s of the beam connecting portion 73 </ b> J and the end portion 81 a of the beam steel frame 81 of the foundation beam 8 are joined via the joint plate 90. Further, the distal end portion 74s of the main bar 74a protruding from the side surface 71s of the Pca portion 71 of the upper footing member 70 and the end portion 83a of the main bar 83 protruding from the end surface 85s of the PCa portion 85 of the foundation beam 8 are cylindrical machines. They are joined via a type joint 91. Further, a hoop line 92 is provided around the main bars 74a and 83. The upper footing member 70 and each foundation beam 8 are joined by the concrete 93 placed between the side surface 71s of the PCa portion 71 of the upper footing member 70 and the end surface 85s of the PCa portion 85 of each foundation beam 8. Has been.

ここで、上記上部フーチング部材70のPCa部71の下面71bは、基礎梁8の下端8bよりも上方に位置し、さらに下部フーチング部材60の上面60aが、基礎梁8の下端8bよりも上方に位置するよう設けられている。これにより、下部フーチング部材60と、基礎梁8とが直接突き当たる部分を設け、下部フーチング部材60と基礎梁8との間で、水平方向のせん断力伝達を確実に行うことができる。   Here, the lower surface 71b of the PCa portion 71 of the upper footing member 70 is located above the lower end 8b of the foundation beam 8, and the upper surface 60a of the lower footing member 60 is located above the lower end 8b of the foundation beam 8. It is provided to be located. Accordingly, a portion where the lower footing member 60 and the foundation beam 8 directly abut each other is provided, and the horizontal shearing force can be reliably transmitted between the lower footing member 60 and the foundation beam 8.

次に、上記したような構造物の施工方法について説明する。
図6は、構造物の施工方法の流れを示す図である。図7は、構造物の施工方法を示す図であり、免震装置を設置した状態を示す立断面図である。図8は、免震装置上に下部フーチング部材を設置した状態を示す立断面図である。図9は、下部フーチング部材上に上部フーチング部材を配置した状態を示す立断面図である。図10は、上部フーチング部材の周囲に基礎梁部材を配置した状態を示す立断面図である。
Next, a construction method for the structure as described above will be described.
FIG. 6 is a diagram illustrating a flow of a construction method for a structure. FIG. 7 is a diagram showing a construction method of the structure, and is an elevational sectional view showing a state where the seismic isolation device is installed. FIG. 8 is an elevational sectional view showing a state where the lower footing member is installed on the seismic isolation device. FIG. 9 is an elevational sectional view showing a state in which the upper footing member is disposed on the lower footing member. FIG. 10 is an elevational sectional view showing a state in which a foundation beam member is arranged around the upper footing member.

まず、図6、図7に示すように、地盤上に構築した下部基礎3の基礎ベース32上に、下部ベースプレート54および免震装置5を設置する(工程S1)。免震装置5の下方のフランジプレート51は、複数本のアンカーボルト55により、基礎ベース32に締結固定する。   First, as shown in FIGS. 6 and 7, the lower base plate 54 and the seismic isolation device 5 are installed on the base base 32 of the lower base 3 constructed on the ground (step S1). The flange plate 51 below the seismic isolation device 5 is fastened and fixed to the foundation base 32 by a plurality of anchor bolts 55.

次いで、図6、図8に示すように、免震装置5上に、上部ベースプレート56、および予め製作しておいた下部フーチング部材60を載せる(工程S2)。免震装置5と下部フーチング部材60とは、下部フーチング部材60に埋設された接続ナット64に締結ボルト57を締結することで接合する。   Next, as shown in FIGS. 6 and 8, the upper base plate 56 and the lower footing member 60 manufactured in advance are placed on the seismic isolation device 5 (step S2). The seismic isolation device 5 and the lower footing member 60 are joined by fastening a fastening bolt 57 to a connection nut 64 embedded in the lower footing member 60.

図6、図9に示すように、このようにして設置した下部フーチング部材60上に、予め製作しておいた上部フーチング部材70を載せる(工程S3)。上部フーチング部材70は、図示しない支保工等により支持しておく。
このとき、上部フーチング部材70の下面70bに形成した凸部72は、下部フーチング部材60の上面60aに形成した凹部61内に挿入して配置する。下部フーチング部材60の上面60aから上方に突出した接続筋63は、上部フーチング部材70に埋め込まれた機械式継手76内に挿入する。
また、上部フーチング部材70の下面70bと上部フーチング部材60の上面60aとの間には、充填材100を充填できるよう、所定寸法以上の間隙Sを形成しておく。
As shown in FIGS. 6 and 9, the upper footing member 70 manufactured in advance is placed on the lower footing member 60 installed in this manner (step S3). The upper footing member 70 is supported by a support work (not shown).
At this time, the convex portion 72 formed on the lower surface 70 b of the upper footing member 70 is inserted and disposed in the concave portion 61 formed on the upper surface 60 a of the lower footing member 60. The connecting bar 63 protruding upward from the upper surface 60 a of the lower footing member 60 is inserted into a mechanical joint 76 embedded in the upper footing member 70.
Further, a gap S having a predetermined dimension or more is formed between the lower surface 70 b of the upper footing member 70 and the upper surface 60 a of the upper footing member 60 so that the filler 100 can be filled.

図10に示すように、上部フーチング部材70の周囲に、予め製作しておいた基礎梁部材80を、図示しない支保工等により支持して配置する。   As shown in FIG. 10, around the upper footing member 70, a prefabricated foundation beam member 80 is supported and arranged by a support work (not shown).

次に、梁接続部73Jの先端部73sと、基礎梁8の梁鉄骨81の端部81aとを、継手プレート90を介して接合する。また、上部フーチング部材70のPca部71の側面71sから突出した主筋74aの先端部74sと、基礎梁8のPCa部85の端面85sから突出した主筋83の端部83aとを、筒状の機械式継手91を介して接合する。   Next, the distal end portion 73 s of the beam connecting portion 73 </ b> J and the end portion 81 a of the beam steel frame 81 of the foundation beam 8 are joined via the joint plate 90. Further, the tip end portion 74s of the main bar 74a protruding from the side surface 71s of the Pca portion 71 of the upper footing member 70 and the end portion 83a of the main bar 83 protruding from the end surface 85s of the PCa portion 85 of the foundation beam 8 are formed into a cylindrical machine. It joins via the type | formula coupling 91. FIG.

この後、上部フーチング部材70の建方調整を行う(工程S4)。これには、上部フーチング部材70の基柱鉄骨79の鉛直度、各梁接続部73Jの水平度等が、予め定めた基準範囲となるようにする。   Thereafter, the construction of the upper footing member 70 is adjusted (step S4). For this purpose, the verticality of the base column steel frame 79 of the upper footing member 70, the horizontality of each beam connecting portion 73J, and the like are set within a predetermined reference range.

次に、図10、図6に示すように、下部フーチング部材60と上部フーチング部材70との間隙Sに、充填材100を充填する(工程S5)。
これには、下部フーチング部材60に形成したグラウト材充填孔66の一端66a(図2、図3参照)から、ポンプ等を用いて流動性を有した状態の充填材100を注入する。すると、充填材100は、下部フーチング部材60の上面60aに形成された凹部61の底面61aの中央部に形成されたグラウト材充填孔66の他端66bから、間隙Sに送り込まれる。下部フーチング部材60と上部フーチング部材70との間隙S内において、充填材100は、グラウト材充填孔66の他端66bが開口した中央部から外周側に広がるようにして充填されていく。
このとき、図9に示すように、間隙Sは、下部フーチング部材60の上面60aに形成された凹部61内に上部フーチング部材70の下面70bに形成された凸部72が挿入されることで形成されている。したがって、間隙Sを中央部側から外周側に向かって流れる充填材100は、中央部の底面61aと下端面72aとの間の領域から、その外周側の傾斜面61bと傾斜面72bとの間の傾斜部Kを経ることで、斜め上方に向かって流れる。したがって、充填材100に空気が泡状に噛み込んでいても、空気が自然に上方に押し流されやすい。その結果、充填材100に空気が噛み込むのを抑え、効率よく充填することができる。
Next, as shown in FIGS. 10 and 6, the filler 100 is filled in the gap S between the lower footing member 60 and the upper footing member 70 (step S5).
For this purpose, the filler 100 having fluidity is injected from one end 66a (see FIGS. 2 and 3) of the grout material filling hole 66 formed in the lower footing member 60 using a pump or the like. Then, the filler 100 is fed into the gap S from the other end 66b of the grout material filling hole 66 formed in the center of the bottom surface 61a of the recess 61 formed in the upper surface 60a of the lower footing member 60. In the gap S between the lower footing member 60 and the upper footing member 70, the filler 100 is filled so as to spread from the central portion where the other end 66b of the grout material filling hole 66 is opened to the outer peripheral side.
At this time, as shown in FIG. 9, the gap S is formed by inserting the convex portion 72 formed on the lower surface 70 b of the upper footing member 70 into the concave portion 61 formed on the upper surface 60 a of the lower footing member 60. Has been. Therefore, the filler 100 that flows in the gap S from the central portion side toward the outer peripheral side is between the inclined surface 61b and the inclined surface 72b on the outer peripheral side from the region between the bottom surface 61a and the lower end surface 72a in the central portion. By passing through the inclined portion K, the air flows obliquely upward. Therefore, even if air is entrained in the filler 100 in a bubble shape, the air is naturally easily pushed upward. As a result, air can be prevented from being caught in the filler 100 and can be filled efficiently.

充填した充填材100が硬化し、所定の強度を発現することで、下部フーチング部材60と上部フーチング部材70とが接合される。   When the filled filler 100 is cured and develops a predetermined strength, the lower footing member 60 and the upper footing member 70 are joined.

また、上部フーチング部材70のPCa部71の側面に開口した注入穴77(図4参照)から、機械式継手76内にモルタル等の接合材を充填する。これにより、機械式継手76内に挿入された接続筋75の下端部と接続筋63の上端部63t(図2、図9参照)とが接合される。
機械式継手76内への接合材の充填は、上記充填材100の充填と並行して行ってもよい。
Further, a bonding material such as mortar is filled into the mechanical joint 76 from the injection hole 77 (see FIG. 4) opened in the side surface of the PCa portion 71 of the upper footing member 70. As a result, the lower end portion of the connecting bar 75 inserted into the mechanical joint 76 and the upper end portion 63t of the connecting bar 63 (see FIGS. 2 and 9) are joined.
The filling of the bonding material into the mechanical joint 76 may be performed in parallel with the filling of the filler 100.

この後、図1、図6に示すように、上部フーチング部材70のPCa部71の側面71sと、各基礎梁8のPCa部85の端面85sとの間に、図示しない型枠を組み、型枠内にコンクリート93を打設する。打設されたコンクリート93が硬化して所定の強度を発現することで、上部フーチング部材70と各基礎梁8とが接合される(工程S6)。   Thereafter, as shown in FIGS. 1 and 6, a mold (not shown) is assembled between the side surface 71 s of the PCa portion 71 of the upper footing member 70 and the end surface 85 s of the PCa portion 85 of each foundation beam 8. Concrete 93 is placed in the frame. When the placed concrete 93 is hardened and develops a predetermined strength, the upper footing member 70 and each foundation beam 8 are joined (step S6).

この後は、型枠及び支保工を解体撤去する。
これにより、免震装置5上への上部基礎4の構築が完了する。
しかる後は、上部フーチング部材70のPCa部71から鉛直上方に延びる基柱鉄骨79に、柱部7を構成する鉄骨(図示無し)を接続し、構造物1の躯体(図示無し)を構築していく。
After this, the formwork and support work will be dismantled and removed.
Thereby, the construction of the upper foundation 4 on the seismic isolation device 5 is completed.
After that, a steel frame (not shown) constituting the column portion 7 is connected to a base column steel frame 79 extending vertically upward from the PCa portion 71 of the upper footing member 70 to construct a frame (not shown) of the structure 1. To go.

上述した構造物の施工方法、構造物によれば、免震装置5上に下部フーチング部材60を設置した後、その上方に上部フーチング部材70を配置し、建方調整を行う。この後、上部フーチング部材70と下部フーチング部材60との間隙Sに充填材100を充填して硬化させるようにした。これにより、構造物1の躯体を構成する柱部7および基礎梁8が接合される上部フーチング部材70を、建方精度を確保して設置することができる。
また、構造物1の躯体を構成する柱部7および基礎梁8が接合される接合部を、プレキャストコンクリート造の上部フーチング部材70で構成することで、現場での鉄筋配筋やコンクリート打ち作業の量を抑えることができる。
その結果、免震装置5上に設ける構造物1の躯体の建方精度を確保しつつ、施工を効率良く行うことが可能となる。
According to the construction method and the structure described above, after the lower footing member 60 is installed on the seismic isolation device 5, the upper footing member 70 is disposed above the lower footing member 60 to adjust the construction. After that, the filler 100 was filled in the gap S between the upper footing member 70 and the lower footing member 60 and cured. Thereby, the upper footing member 70 to which the column part 7 and the foundation beam 8 which comprise the housing of the structure 1 are joined can be installed ensuring a construction accuracy.
Moreover, the joint part to which the column part 7 and the foundation beam 8 which comprise the frame of the structure 1 are joined is comprised by the upper footing member 70 of a precast concrete structure, Therefore Reinforcement reinforcement on the spot and concrete placement work are carried out. The amount can be reduced.
As a result, it is possible to perform the construction efficiently while ensuring the accuracy of the construction of the frame of the structure 1 provided on the seismic isolation device 5.

また、上部フーチング部材70に、柱部7の最下端部が接続される基柱鉄骨79の基部79aが埋設されているので、上部フーチング部材70の建方調整を行うことによって、基柱鉄骨79も同時に建方調整がなされる。したがって、充填材100の硬化後は、基柱鉄骨79に構造物1の躯体を構成する柱部7を速やかに接合し、施工作業を進めることが可能となる。これによっても、施工の効率化を図ることができる。   Further, since the base portion 79a of the base column steel frame 79 to which the lowermost end portion of the column part 7 is connected is embedded in the upper footing member 70, the base column steel frame 79 is adjusted by adjusting the construction of the upper footing member 70. At the same time, the construction is adjusted. Therefore, after the filler 100 is cured, the column portion 7 constituting the casing of the structure 1 can be quickly joined to the base column steel frame 79, and the construction work can proceed. Also by this, construction efficiency can be improved.

また、下部フーチング部材60の上面に凹部61が形成され、上部フーチング部材70の下面に凹部61に係合する凸部72が形成されている。このような構成によれば、下部フーチング部材60の凹部61と上部フーチング部材70の凸部72を係合させることで、下部フーチング部材60と上部フーチング部材70との間で、水平方向のせん断力を確実に伝達することが可能となる。   Further, a recess 61 is formed on the upper surface of the lower footing member 60, and a protrusion 72 that engages with the recess 61 is formed on the lower surface of the upper footing member 70. According to such a configuration, the horizontal shearing force between the lower footing member 60 and the upper footing member 70 is obtained by engaging the concave portion 61 of the lower footing member 60 and the convex portion 72 of the upper footing member 70. Can be reliably transmitted.

また、上部フーチング部材70と下部フーチング部材60との間隙Sに、中央部から充填材100を充填することによって、充填材100は間隙Sの中央部から外周側に向かって広がるように充填される。これによって、上部フーチング部材70と下部フーチング部材60との間隙Sに、充填材100を隙間無く充填することが可能となる。   In addition, by filling the gap S between the upper footing member 70 and the lower footing member 60 with the filler 100 from the center, the filler 100 is filled so as to spread from the center of the gap S toward the outer peripheral side. . As a result, the filler 100 can be filled in the gap S between the upper footing member 70 and the lower footing member 60 without a gap.

また、上部フーチング部材70と下部フーチング部材60との間隙Sは、間隙Sの内周側から外周側に向かって漸次上方に傾斜する傾斜部Kを有している。このような構成によれば、間隙Sに充填した充填材100に空気が噛み込んでいた場合であっても、空気が漸次上方に抜けやすい。したがって、充填材100を隙間無く充填することが可能となる。   Further, the gap S between the upper footing member 70 and the lower footing member 60 has an inclined portion K that is gradually inclined upward from the inner peripheral side of the gap S toward the outer peripheral side. According to such a configuration, even when air is entrained in the filler 100 filled in the gap S, the air is likely to gradually escape upward. Therefore, it becomes possible to fill the filler 100 without gaps.

また、下部フーチング部材60に、上部フーチング部材70に向かって突出する接続筋63が埋設され、上部フーチング部材70に、接続筋63が接合される機械式継手76が埋設されている。このような構成によれば、上部フーチング部材70を下部フーチング部材60上に設置する際に接続筋63を機械式継手76に挿入し、さらに下部フーチング部材60と上部フーチング部材70との間隙Sに充填材100を充填することで、下部フーチング部材60と上部フーチング部材70とを強固に接合することができる。   Further, a connecting bar 63 protruding toward the upper footing member 70 is embedded in the lower footing member 60, and a mechanical joint 76 to which the connecting bar 63 is bonded is embedded in the upper footing member 70. According to such a configuration, when installing the upper footing member 70 on the lower footing member 60, the connecting bar 63 is inserted into the mechanical joint 76, and further, in the gap S between the lower footing member 60 and the upper footing member 70. By filling the filler 100, the lower footing member 60 and the upper footing member 70 can be firmly joined.

また、下部フーチング部材60の下面60bに、免震装置5と下部フーチング部材60とを接合する締結ボルト57が締結される接続ナット64が埋設されている。このような構成によれば、下部フーチング部材60を免震装置5上に設置した後、締結ボルト57を接続ナット64に締結することで、免震装置5と下部フーチング部材60とを容易に接合することができる。しかも、免震装置5と下部フーチング部材60との間で、上下方向の引張力に対し、高い性能を発揮することができる。   Further, a connection nut 64 to which a fastening bolt 57 for joining the seismic isolation device 5 and the lower footing member 60 is fastened is embedded in the lower surface 60 b of the lower footing member 60. According to such a configuration, after the lower footing member 60 is installed on the seismic isolation device 5, the fastening bolt 57 is fastened to the connection nut 64 so that the seismic isolation device 5 and the lower footing member 60 are easily joined. can do. In addition, high performance can be exhibited against the tensile force in the vertical direction between the seismic isolation device 5 and the lower footing member 60.

また、下部フーチング部材60の上端は、上部フーチング部材70に接合される基礎梁8の下面よりも上方に位置している。このような構成によれば、下部フーチング部材60と基礎梁8とが直接突き当たり、水平方向のせん断力の伝達を効率よくかつ確実に行うことができる。   Further, the upper end of the lower footing member 60 is located above the lower surface of the foundation beam 8 joined to the upper footing member 70. According to such a configuration, the lower footing member 60 and the foundation beam 8 directly contact each other, and the horizontal shear force can be transmitted efficiently and reliably.

(その他の実施形態)
なお、本発明は、図面を参照して説明した上述の実施形態に限定されるものではなく、その技術的範囲において様々な変形例が考えられる。
例えば、下部基礎3や上部基礎4の構成は、上記した構成に限らない。
また、柱部7は、鉄骨造に限らず、鉄筋コンクリート造や鉄骨鉄筋コンクリート造であってもよい。
さらに、上記実施形態では、第一プレキャスト部材である下部フーチング部材60に係合部としての凹部61を形成し、第二プレキャスト部材である上部フーリング部材70に、被係合部としての凸部72を設けるようにしたが、これに限らない。第一プレキャスト部材の上面に凸部からなる係合部を設け、第二プレキャスト部材の下面に被係合部を形成するようにしてもよい。
これ以外にも、本発明の主旨を逸脱しない限り、上記実施の形態で挙げた構成を取捨選択したり、他の構成に適宜変更したりすることが可能である。
(Other embodiments)
The present invention is not limited to the above-described embodiment described with reference to the drawings, and various modifications can be considered within the technical scope thereof.
For example, the configuration of the lower foundation 3 and the upper foundation 4 is not limited to the above-described configuration.
Further, the column portion 7 is not limited to a steel structure, and may be a reinforced concrete structure or a steel reinforced concrete structure.
Furthermore, in the said embodiment, the recessed part 61 as an engaging part is formed in the lower footing member 60 which is a 1st precast member, and the convex part 72 as an engaged part is formed in the upper footing member 70 which is a 2nd precast member. However, the present invention is not limited to this. An engaging portion made of a convex portion may be provided on the upper surface of the first precast member, and the engaged portion may be formed on the lower surface of the second precast member.
In addition to this, the configuration described in the above embodiment can be selected or changed to another configuration as appropriate without departing from the gist of the present invention.

1 構造物
3 下部基礎(基礎)
4 上部基礎
5 免震装置
7 柱部(柱)
8 基礎梁(梁)
57 締結ボルト(接合ボルト)
60 下部フーチング部材(第一プレキャスト部材)
61 凹部(係合部)
63 接続筋(鉄筋)
64 接続ナット(ナット)
70 上部フーチング部材(第二プレキャスト部材)
72 凸部(被係合部)
76 機械式継手
79 基柱鉄骨(柱接続部材)
79a 基部
100 充填材(硬化性充填材)
K 傾斜部
S 間隙
1 Structure 3 Lower foundation (foundation)
4 Upper foundation 5 Seismic isolation device 7 Column (column)
8 Foundation beams (beams)
57 Fastening bolt (joint bolt)
60 Lower footing member (first precast member)
61 Recess (engagement part)
63 Connecting bars (reinforcing bars)
64 Connection nut (nut)
70 Upper footing member (second precast member)
72 Convex (engaged part)
76 Mechanical joint 79 Base column steel frame (column connection member)
79a Base 100 Filler (Curable Filler)
K inclined part S gap

Claims (5)

免震装置上にプレキャストコンクリートからなる第一プレキャスト部材を設置する工程と、
プレキャストコンクリートからなる第二プレキャスト部材を、前記第一プレキャスト部材の上方に間隙を空けて設置する工程と、
前記第二プレキャスト部材の建方調整を行う工程と、
建方調整を行った前記第二プレキャスト部材と前記第一プレキャスト部材との前記間隙に硬化性充填材を充填し、硬化させる工程と、
前記第二プレキャスト部材に、構造物の躯体を構成する柱および梁の少なくとも一方を接合する工程と、
を備えることを特徴とする構造物の施工方法。
Installing the first precast member made of precast concrete on the seismic isolation device;
Installing a second precast member made of precast concrete with a gap above the first precast member;
A step of adjusting the construction of the second precast member;
Filling the gap between the second precast member and the first precast member that have been erected and curing, and curing the filler,
Joining the second precast member to at least one of a column and a beam constituting a structural body; and
A construction method for a structure characterized by comprising:
前記第二プレキャスト部材に、前記柱の最下端部が接続される柱接続部材の基部が埋設されている
ことを特徴とする請求項1に記載の構造物の施工方法。
The construction method for a structure according to claim 1, wherein a base portion of a column connecting member to which a lowermost end portion of the column is connected is embedded in the second precast member.
前記第一プレキャスト部材の上面に凹部または凸部からなる係合部が形成され、
前記第二プレキャスト部材の下面に前記係合部に係合する被係合部が形成されている
ことを特徴とする請求項1または2に記載の構造物の施工方法。
An engaging portion consisting of a concave portion or a convex portion is formed on the upper surface of the first precast member,
The construction method for a structure according to claim 1, wherein an engaged portion that engages with the engaging portion is formed on a lower surface of the second precast member.
基礎上に設けられた免震装置と、
前記免震装置上に設けられ、プレキャストコンクリートからなる第一プレキャスト部材と、
プレキャストコンクリートからなり、前記第一プレキャスト部材の上方に間隙を空けて設けられ、構造物の躯体を構成する柱および梁の少なくとも一方が接合された第二プレキャスト部材と、
前記第二プレキャスト部材と前記第一プレキャスト部材との前記間隙に充填された硬化性充填材と、を備える
ことを特徴とする構造物。
A seismic isolation device installed on the foundation,
A first precast member provided on the seismic isolation device and made of precast concrete;
A second precast member made of precast concrete, provided with a gap above the first precast member, to which at least one of a column and a beam constituting a structural body is joined;
A structure comprising: a curable filler filled in the gap between the second precast member and the first precast member.
前記第一プレキャスト部材の上端は、前記第二プレキャスト部材に接合される前記梁の下面よりも上方に位置している、
ことを特徴とする請求項4に記載の構造物。
The upper end of the first precast member is located above the lower surface of the beam to be joined to the second precast member,
The structure according to claim 4.
JP2015240845A 2015-12-10 2015-12-10 Construction method of structures, structures Active JP6628588B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015240845A JP6628588B2 (en) 2015-12-10 2015-12-10 Construction method of structures, structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015240845A JP6628588B2 (en) 2015-12-10 2015-12-10 Construction method of structures, structures

Publications (2)

Publication Number Publication Date
JP2017106236A true JP2017106236A (en) 2017-06-15
JP6628588B2 JP6628588B2 (en) 2020-01-08

Family

ID=59060663

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015240845A Active JP6628588B2 (en) 2015-12-10 2015-12-10 Construction method of structures, structures

Country Status (1)

Country Link
JP (1) JP6628588B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019112788A (en) * 2017-12-21 2019-07-11 株式会社竹中工務店 Foundation structure and construction method thereof
JP2020002580A (en) * 2018-06-27 2020-01-09 株式会社フジタ Aseismic upper foundation structure and construction method thereof, and installation method of aseismic foundation
JP2020016076A (en) * 2018-07-25 2020-01-30 株式会社フジタ Base isolation upper foundation structure and manufacturing method of the same
JP2020026634A (en) * 2018-08-09 2020-02-20 株式会社フジタ Seismic isolation upper foundation structure and method for manufacturing the same, footing structure, and method for constructing seismic isolation foundation
JP2022116247A (en) * 2018-07-25 2022-08-09 株式会社フジタ Method for manufacturing upper base isolation foundation structure and method for manufacturing foundation structure
JP7362448B2 (en) 2019-11-25 2023-10-17 株式会社竹中工務店 Construction method of seismic isolation foundation beam

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04189919A (en) * 1990-11-22 1992-07-08 Misawa Homes Co Ltd Precast concrete foundation
JP2001152462A (en) * 2000-09-21 2001-06-05 Hiroshi Yamada Footing structure of building and construction method therefor
JP2002138492A (en) * 2000-10-30 2002-05-14 Shimizu Corp Foundation execution method of building
JP2011047201A (en) * 2009-08-27 2011-03-10 Taisei Corp Method of constructing base isolation structure
EP2322742A1 (en) * 2009-11-16 2011-05-18 Tecnostrutture SRL System of seismic-resistant prefabricated elements for the building trade, and relative laying method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04189919A (en) * 1990-11-22 1992-07-08 Misawa Homes Co Ltd Precast concrete foundation
JP2001152462A (en) * 2000-09-21 2001-06-05 Hiroshi Yamada Footing structure of building and construction method therefor
JP2002138492A (en) * 2000-10-30 2002-05-14 Shimizu Corp Foundation execution method of building
JP2011047201A (en) * 2009-08-27 2011-03-10 Taisei Corp Method of constructing base isolation structure
EP2322742A1 (en) * 2009-11-16 2011-05-18 Tecnostrutture SRL System of seismic-resistant prefabricated elements for the building trade, and relative laying method

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019112788A (en) * 2017-12-21 2019-07-11 株式会社竹中工務店 Foundation structure and construction method thereof
JP7186003B2 (en) 2017-12-21 2022-12-08 株式会社竹中工務店 Construction method of foundation structure
JP2020002580A (en) * 2018-06-27 2020-01-09 株式会社フジタ Aseismic upper foundation structure and construction method thereof, and installation method of aseismic foundation
JP7149744B2 (en) 2018-06-27 2022-10-07 株式会社フジタ Seismic isolation upper foundation structure, its fabrication method, and seismic isolation foundation construction method
JP2020016076A (en) * 2018-07-25 2020-01-30 株式会社フジタ Base isolation upper foundation structure and manufacturing method of the same
JP7083285B2 (en) 2018-07-25 2022-06-10 株式会社フジタ Seismic isolation upper foundation structure and its manufacturing method
JP2022116247A (en) * 2018-07-25 2022-08-09 株式会社フジタ Method for manufacturing upper base isolation foundation structure and method for manufacturing foundation structure
JP7270816B2 (en) 2018-07-25 2023-05-10 株式会社フジタ Seismic isolation upper foundation structure fabrication method and foundation structure fabrication method
JP2020026634A (en) * 2018-08-09 2020-02-20 株式会社フジタ Seismic isolation upper foundation structure and method for manufacturing the same, footing structure, and method for constructing seismic isolation foundation
JP7194531B2 (en) 2018-08-09 2022-12-22 株式会社フジタ Seismic isolation upper foundation structure and manufacturing method thereof, footing structure, and seismic isolation foundation construction method
JP7362448B2 (en) 2019-11-25 2023-10-17 株式会社竹中工務店 Construction method of seismic isolation foundation beam

Also Published As

Publication number Publication date
JP6628588B2 (en) 2020-01-08

Similar Documents

Publication Publication Date Title
JP6628588B2 (en) Construction method of structures, structures
JP6424075B2 (en) REINFORCED CONCRETE COLUMN STEEL BEAM JOINTING MEMBER, ITS MANUFACTURING METHOD, AND BUILDING CONSTRUCTION METHOD
JP5456626B2 (en) Connection structure and method of connection between pile and steel column
JP2010242390A (en) Joining method and structure of column-beam joint part having steel brace
JP6792329B2 (en) Construction method of column beam frame using precast concrete columns
JP2018188851A (en) Steel concrete composite structure and construction method of steel concrete composite structure
JP6543077B2 (en) Construction method of structure
JP2006104883A (en) Base-isolated building
JP2010261270A (en) Composite structure and method for constructing composite structure building
JP4949116B2 (en) Wall unit and shear wall
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JP6953723B2 (en) Construction method of seismic isolation structure
JP3851563B2 (en) Frame reinforcement structure and its construction method
JP7200048B2 (en) pile foundation structure
JP2017082548A (en) Concrete foundation joint member and pile structure
JP2021173023A (en) Construction method of anchor bolt and box-removing form used in the method
JP5891121B2 (en) Construction pillar and method for producing construction pillar
JP6611303B2 (en) Foundation structure
JP2007051500A (en) Joint structure of column and pile
JP6083001B1 (en) Reinforcement structure of building
JP6220315B2 (en) Joining structure and joining method
JP5327615B2 (en) Joint structure of column and flat slab
KR101657628B1 (en) Top-down method for building undergroud structure using steel pipe
JP7200042B2 (en) pile foundation structure
JP7423418B2 (en) Column base fixed structure, building, and construction method of column base fixed structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20181130

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190924

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20191001

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20191023

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20191112

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20191203

R150 Certificate of patent or registration of utility model

Ref document number: 6628588

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150