JP2015117562A - Flat slab structure - Google Patents

Flat slab structure Download PDF

Info

Publication number
JP2015117562A
JP2015117562A JP2013263546A JP2013263546A JP2015117562A JP 2015117562 A JP2015117562 A JP 2015117562A JP 2013263546 A JP2013263546 A JP 2013263546A JP 2013263546 A JP2013263546 A JP 2013263546A JP 2015117562 A JP2015117562 A JP 2015117562A
Authority
JP
Japan
Prior art keywords
capital
floor slab
steel
floor
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2013263546A
Other languages
Japanese (ja)
Other versions
JP6300228B2 (en
Inventor
克己 中山
Katsumi Nakayama
克己 中山
幹雄 児玉
Mikio Kodama
幹雄 児玉
典雄 元古
Norio Motofuru
典雄 元古
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
C & C Engineering Kk
GENKO TEKKOU Inc
Kobelco Wire Co Ltd
Original Assignee
C & C Engineering Kk
GENKO TEKKOU Inc
Shinko Wire Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by C & C Engineering Kk, GENKO TEKKOU Inc, Shinko Wire Co Ltd filed Critical C & C Engineering Kk
Priority to JP2013263546A priority Critical patent/JP6300228B2/en
Publication of JP2015117562A publication Critical patent/JP2015117562A/en
Application granted granted Critical
Publication of JP6300228B2 publication Critical patent/JP6300228B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a flat slab structure capable of ensuring sufficient earthquake resistance without installing an earthquake-resisting wall, at the same time curtailing construction period and suppressing construction costs.SOLUTION: A flat slab structure includes: a plurality of reinforced concrete columns 11 that constitute a building; capitals 12 and 13 installed at a top of each of the columns 11; a plurality of reinforced concrete floor slabs supported and fixed by the capitals 12 and 13 on each of the columns 11; and steel braces 14 installed between adjacent floors of the building. The steel brace 14 is installed diagonally to a rectangular frame formed by an axis of each of the columns 11 and a side of the floor slab 10, and its end is connected to the capital 12.

Description

この発明は、高い耐震性を確保し、施工時の作業効率を向上させるとともにコストを抑制することが可能なフラットスラブ構造に関するものである。   The present invention relates to a flat slab structure capable of ensuring high earthquake resistance, improving work efficiency during construction, and suppressing cost.

例えば複数の階層を有する倉庫等を構築する場合には、建造物の各柱頭を接続する梁を省略して床スラブを支えるフラットスラブ工法がある(例えば、特許文献1参照)。このような床構造を用いる場合には、鉄筋コンクリート造の耐震壁を適当な位置に設けて耐震性を向上させている。
また、上記の床スラブを構築する際に、鉄筋とともにアンボンドPC鋼線を配置してコンクリートを打設し、コンクリート硬化後にアンボンドPC鋼線を緊張させ、床強度を高めるとともに作業の簡素化を図ることも行われている(例えば、特許文献2参照)。
For example, when building a warehouse or the like having a plurality of hierarchies, there is a flat slab method for supporting a floor slab by omitting a beam connecting each pillar of a building (for example, see Patent Document 1). When such a floor structure is used, a seismic wall made of reinforced concrete is provided at an appropriate position to improve the earthquake resistance.
Moreover, when constructing the above-mentioned floor slab, an unbonded PC steel wire is placed together with a reinforcing bar to place concrete, and after the concrete is hardened, the unbonded PC steel wire is tensioned to increase the floor strength and simplify the work. (For example, refer to Patent Document 2).

図1は、従来のフラットスラブ構造を示す説明図である。この図は、フラットスラブ構造を用いた建造物の一部分を表しており、図1(a)は、建造物の床スラブ101等を上方視したときの配置構成を表し、図1(b)は二つの階層の床スラブ101を側方視したときの配置構成を表している。
図1に例示した建造物は、複数の柱102が等間隔で配置されており、各柱102の柱頭に床スラブ101を支えるキャピタル103が設けられている。
床スラブ101は、鉄筋を格子状に配置して、さらに適当な本数のアンボンドPC鋼線を上記の格子状の鉄筋間に配線し、これにコンクリートを打設した鉄筋コンクリート造であり、フラットスラブ構造を成すように平板状に形成されている。
FIG. 1 is an explanatory view showing a conventional flat slab structure. This figure shows a part of a building using a flat slab structure. FIG. 1A shows an arrangement configuration when the floor slab 101 of the building is viewed from above, and FIG. The arrangement | positioning structure when the floor slab 101 of two hierarchy is seen from the side is represented.
In the building illustrated in FIG. 1, a plurality of pillars 102 are arranged at equal intervals, and a capital 103 that supports the floor slab 101 is provided at the top of each pillar 102.
The floor slab 101 is a reinforced concrete structure in which reinforcing bars are arranged in a grid, an appropriate number of unbonded PC steel wires are wired between the above-described grid-like reinforcing bars, and concrete is placed on the reinforcing bars. Is formed in a flat plate shape.

柱102は、高さ方向に主鉄筋を配筋した鉄筋コンクリート造であり、また柱102の柱頭であるキャピタル103は、柱102の高さ方向に直交する水平方向に主鉄筋を配筋し、これにコンクリートを打設した鉄筋コンクリート造である。
キャピタル103の主鉄筋は、床スラブ101の主鉄筋と重ね継ぎされており、これらにコンクリートを打設したとき、キャピタル103が床スラブ101を支持するように設置されている。
床スラブ101を施工するときには、型枠を設置した後、前述のように各鉄筋を配置してコンクリートを打設し、コンクリートが硬化した後、図示されないアンボンドPC鋼線を緊張させて当該床スラブ101の強度を高める。
The column 102 is a reinforced concrete structure in which the main reinforcing bars are arranged in the height direction, and the capital 103 which is the head of the column 102 arranges the main reinforcing bars in the horizontal direction perpendicular to the height direction of the columns 102. It is a reinforced concrete structure in which concrete is cast on the wall.
The main rebar of the capital 103 is overlapped with the main rebar of the floor slab 101, and the capital 103 is installed so as to support the floor slab 101 when concrete is placed on them.
When constructing the floor slab 101, after installing the formwork, placing the reinforcing bars as described above, placing the concrete, hardening the concrete, and then tensioning the unbonded PC steel wire (not shown) Increase the strength of 101.

また、図1に示した従来のフラットスラブ構造は、建造物の耐震性を高めるため、特に水平方向の震動に対抗するように適当な位置の柱間に耐震壁104を設けている。
耐震壁104は、例えば柱102の高さ方向に設置された格子状の鉄筋にコンクリートを打設したものである。
耐震壁104の主鉄筋は、上下方向に設置されている二つの床スラブ101の主鉄筋と重ね継ぎされている。また複数の柱102ならびにキャピタル103の一部分の主鉄筋とも重ね継ぎされており、例えば2本の柱102間を補強するように設けられている。
Further, in the conventional flat slab structure shown in FIG. 1, in order to enhance the earthquake resistance of the building, the earthquake resistant walls 104 are provided between the columns at appropriate positions so as to particularly resist the horizontal vibration.
The earthquake-resistant wall 104 is obtained by placing concrete on a grid-like reinforcing bar installed in the height direction of the pillar 102, for example.
The main reinforcing bars of the seismic wall 104 are overlapped with the main reinforcing bars of the two floor slabs 101 installed in the vertical direction. Further, the plurality of pillars 102 and a main reinforcing bar of a part of the capital 103 are also overlapped and provided, for example, so as to reinforce between the two pillars 102.

前述のようにフラットスラブ構造は、建造物の梁型枠を設置する必要がないことから施工作業が容易になる。また、床面積の大きな建造物では、上記のように床面内部に梁が設置されないことから、例えばフライングショアを使用して同一型枠を転用する工法も可能になり、作業効率や均一性などを向上させることが可能になる。
また、フラットスラブ構造は、比較的水平方向の震動に弱いとされているが、上記のように適当な位置の柱間に鉄筋コンクリート造の耐震壁104を設けることによって耐震性を向上させている。
As described above, since the flat slab structure does not require installation of a beam formwork of a building, construction work is facilitated. In addition, in buildings with a large floor area, since beams are not installed inside the floor as described above, for example, it is possible to use the same formwork using a flying shore, and work efficiency, uniformity, etc. It becomes possible to improve.
Further, the flat slab structure is considered to be relatively weak against horizontal vibrations, but the earthquake resistance is improved by providing the reinforced concrete seismic walls 104 between the columns at appropriate positions as described above.

特公昭61−39455号公報Japanese Examined Patent Publication No. 61-39455 特公平1−23615号公報Japanese Patent Publication No. 1-2615

従来のフラットスラブ構造は以上のように構成されているので、耐震性を向上させるために中柱等に耐震壁を設置する必要があり、この耐震壁の施工に相当の工程を要するために工期が長くなってコストを押し上げてしまうという問題点があった。   Since the conventional flat slab structure is constructed as described above, it is necessary to install a seismic wall on the middle pillar to improve seismic resistance. There is a problem in that this increases the cost.

この発明は上記のような課題を解決するためになされたもので、耐震壁を設置することなく十分な耐震性を確保し、工期短縮を可能にするとともに建設コストを抑制することができるフラットスラブ構造を提供することを目的とする。   The present invention has been made to solve the above-described problems, and is a flat slab capable of ensuring sufficient earthquake resistance without installing a seismic wall, enabling shortening of the construction period and suppressing construction cost. The purpose is to provide a structure.

この発明に係るフラットスラブ構造は、建造物を形成する鉄筋コンクリート造の複数の柱と、前記柱の各柱頭に設置されるキャピタルと、前記各柱のキャピタルによって支持固定された鉄筋コンクリート造の複数の床スラブと、前記建造物の上下階層間に設置される鉄骨ブレースと、を有し、前記鉄骨ブレースは、前記各柱の軸線および前記床スラブの一辺部によって形成される四辺形の軸組に対角線状に設置され、端部を前記キャピタルに接合する、ことを特徴とする。   The flat slab structure according to the present invention includes a plurality of reinforced concrete columns forming a building, a capital installed at each column head, and a plurality of reinforced concrete floors supported and fixed by the capital of each column. And a steel brace installed between upper and lower layers of the building, and the steel brace is diagonal to a quadrangular shaft formed by the axis of each column and one side of the floor slab. It is installed in a shape and the end is joined to the capital.

また、前記キャピタルは、鉄筋コンクリート造であり、所定位置に配置される該キャピタルは前記鉄骨ブレースの端部と接合する固定部を有し、前記鉄骨ブレースは、一端部を前記キャピタルの固定部に接合し、他端部を該キャピタルの斜め下方または斜め上方に配置されている、床スラブに設置された固定部または他のキャピタルの固定部に接合する、ことを特徴とする。   The capital is reinforced concrete, and the capital arranged at a predetermined position has a fixing portion that joins an end portion of the steel brace, and the steel brace joins one end portion to the fixing portion of the capital. The other end is joined to a fixed part installed on the floor slab or a fixed part of another capital, which is disposed obliquely below or obliquely above the capital.

また、前記キャピタルは、鉄骨造であり、所定位置に配置される該キャピタルは前記鉄骨ブレースの端部と接合する固定部を有し、前記鉄骨ブレースは、一端部を前記キャピタルの固定部に接合し、他端部を該キャピタルの斜め下方または斜め上方に配置されている、床スラブに設置された固定部または他のキャピタルの固定部に接合する、ことを特徴とする。   Further, the capital is a steel frame, and the capital arranged at a predetermined position has a fixing portion that joins an end portion of the steel brace, and the steel brace joins one end portion to the fixing portion of the capital. The other end is joined to a fixed part installed on the floor slab or a fixed part of another capital, which is disposed obliquely below or obliquely above the capital.

また、必要な耐力に応じて鉄骨造のキャピタルまたは鉄筋コンクリート造のキャピタルをそれぞれの柱に設ける、ことを特徴とする。   Further, according to the required proof stress, a steel-framed capital or a reinforced concrete-structured capital is provided on each column.

この発明によれば、ブレースを柱や床スラブ等に固定することによって耐震性を高めるようにしたので、工場等で製造したブレースを建設現場に搬送して設置施工することから、建設現場での工程を簡易にするとともに工期を短縮することができる。   According to the present invention, the brace is fixed to a pillar, a floor slab or the like so as to improve the earthquake resistance, so that the brace manufactured at the factory or the like is transported to the construction site for installation and construction. The process can be simplified and the construction period can be shortened.

従来のフラットスラブ構造を示す説明図である。It is explanatory drawing which shows the conventional flat slab structure. 実施例によるフラットスラブ構造を有する建造物の一部分を示した説明図である。It is explanatory drawing which showed a part of building which has the flat slab structure by an Example. 図2のフラットスラブ構造に用いる鉄骨造のキャピタルの構成を示す説明図である。It is explanatory drawing which shows the structure of the steel structure capital used for the flat slab structure of FIG. 実施例によるフラットスラブ構造の施工工程を示す説明図である。It is explanatory drawing which shows the construction process of the flat slab structure by an Example. 実施例によるフラットスラブ構造の施工工程を示す説明図である。It is explanatory drawing which shows the construction process of the flat slab structure by an Example.

以下、この発明の実施の一形態を図に基づいて説明する。
(実施例)
図2は、この発明の実施例によるフラットスラブ構造を有する建造物の一部分を示した説明図である。図2(a)は、建造物の床部分を正面視したときの各部の配置等を表し、図2(b)は、上記の建造物を側方視したときの各部の配置等を表している。
図示した建造物は複数階層を有するもので、フラットスラブ構造によって各階のフロアを形成している。また、図2(a)中において上下左右に等間隔で各柱11を設置しており、それぞれの柱頭にはキャピタル12が設けられている。
Hereinafter, an embodiment of the present invention will be described with reference to the drawings.
(Example)
FIG. 2 is an explanatory view showing a part of a building having a flat slab structure according to an embodiment of the present invention. FIG. 2A shows the arrangement of each part when the floor portion of the building is viewed from the front, and FIG. 2B shows the arrangement of each part when the above-mentioned building is viewed from the side. Yes.
The illustrated building has a plurality of levels, and the floor of each floor is formed by a flat slab structure. Further, in FIG. 2A, each pillar 11 is installed at equal intervals in the vertical and horizontal directions, and a capital 12 is provided at each pillar head.

床スラブ10は、建造物の床部分を形成するもので、各柱11の上方において型枠を設置して鉄筋格子を配置固定し、さらにこれら鉄筋の間にアンボンドPC鋼線を配線してコンクリートを打設したものである。具体的には、鉄筋コンクリート造の例えば厚さが一定の四辺形板状に形成したものである。
当該建造物の床部分は、同一寸法形状の型枠によって形成された床スラブ10を複数並べることによって大部分が形成されている。また、建造物の床面中央部分等には梁等を設置していない。
上記のアンボンドPC鋼線は、例えば7本のPC鋼より線をポリエチレンシース内に収納し、緊張させたときの摩擦を低減するためシース内の間隙にグリースを充填したものである。
柱11は、断面形状が例えば略四辺形の鉄筋コンクリート造であり、柱頭にキャピタル12またはキャピタル13を備えており、床スラブ10、もしくは各床スラブ10によって形成されたフロアを支持するように適当な間隔を設けて設置されている。
The floor slab 10 forms a floor portion of a building. A formwork is installed above each pillar 11 to arrange and fix a reinforcing bar lattice, and an unbonded PC steel wire is wired between the reinforcing bars to provide concrete. It is a thing that was laid. Specifically, it is formed of a reinforced concrete structure, for example, in a quadrilateral plate shape with a constant thickness.
Most of the floor portion of the building is formed by arranging a plurality of floor slabs 10 formed by a form having the same size and shape. Also, no beams etc. are installed at the center of the floor of the building.
The above-mentioned unbonded PC steel wire is one in which, for example, seven PC steel wires are housed in a polyethylene sheath, and grease is filled in the gap in the sheath in order to reduce friction when tensioned.
The column 11 is a reinforced concrete structure having a substantially quadrangular cross-section, for example, and includes a capital 12 or a capital 13 at the top of the column, and is suitable for supporting the floor slab 10 or a floor formed by each floor slab 10. It is installed at intervals.

キャピタル12は、柱11の柱頭において床スラブ10と接する部分を大きくするために当該柱11の高さ方向と直交する方向に拡げて形成したもので、例えば床面上において正四辺形となるように鉄筋コンクリート造によって形成されている。即ち、柱11の軸線に直交する断面において、床スラブ10と接して支持する部分を拡げたものである。
キャピタル12は、例えば格子状の鉄筋によって形成されており、キャピタル12の中央部分において上記の格子状の鉄筋間を柱11の主鉄筋(柱筋)が貫通している。この柱11の主鉄筋は、キャピタル12を貫通して上階部分まで延設されている。
The capital 12 is formed by expanding in a direction orthogonal to the height direction of the pillar 11 in order to enlarge a portion of the pillar 11 that contacts the floor slab 10, for example, a regular quadrilateral on the floor surface. It is made of reinforced concrete. That is, in the cross section orthogonal to the axis of the column 11, the portion to be supported in contact with the floor slab 10 is expanded.
The capital 12 is formed by, for example, a lattice-shaped reinforcing bar, and the main reinforcing bars (columns) of the pillars 11 pass through the lattice-shaped reinforcing bars in the central portion of the capital 12. The main reinforcing bar of the pillar 11 extends through the capital 12 to the upper floor portion.

また、キャピタル12は、柱11の柱筋と接合するとともに、床スラブ10を形成する主鉄筋(下端筋等)と接合し、床スラブ10の型枠にコンクリートを打設した後には床スラブ10と接合するように形成されている。
また、適当な位置に配置された柱11のキャピタル12は、後述するブレース14のウェブ部の端部と接合するアンカー等を備えている。なお、このブレース14のアンカー等は、全てのキャピタル12に備えられるものではない。
In addition, the capital 12 is joined to the column reinforcement of the column 11 and to the main reinforcing bars (lower end reinforcement etc.) forming the floor slab 10, and after placing concrete in the formwork of the floor slab 10, the floor slab 10. It is formed to join.
Moreover, the capital 12 of the pillar 11 arranged at an appropriate position is provided with an anchor or the like that joins an end portion of a web portion of a brace 14 to be described later. The anchors of the brace 14 are not provided in all the capitals 12.

図3は、図2のフラットスラブ構造に用いる鉄骨造のキャピタルの構成を示す説明図である。図2に示したものと同一部分に同じ符号を使用し、その説明を省略する。なお、図示したキャピタル13は、鉄骨造キャピタルの一構成例であり、同様な作用効果を有する他の鉄骨構造を有するものでもよい。
図3(a)は、鉄骨造のキャピタル13を上方視したもので、図3(b)は柱11の柱頭においてキャピタル13が床スラブ10を支持している状態を側方視したものである。
キャピタル13は、複数の鉄骨を略ロの字状に接続固定した枠体13a、枠体13aの開口内部において例えば十字状に配置固定されている鉄骨13bと鉄骨13c、上記の開口部を適当に塞ぐキーストンプレート30によって構成されている。上記の十字状に固定された鉄骨13b,13cは、下方(図3(a)の奥手方向)から柱11の主鉄筋(図示省略)が貫通している。また、上記のキーストンプレート30は、柱11が貫通したときに生じる開口空間を塞ぐように配置固定されている。
FIG. 3 is an explanatory view showing the structure of a steel-framed capital used in the flat slab structure of FIG. The same reference numerals are used for the same parts as those shown in FIG. The illustrated capital 13 is an example of a structure of a steel-framed capital, and may have another steel structure having the same function and effect.
3A is a top view of the steel-framed capital 13, and FIG. 3B is a side view of the state in which the capital 13 supports the floor slab 10 at the stigma of the column 11. .
The capital 13 includes a frame 13a in which a plurality of steel frames are connected and fixed in a substantially square shape, and a steel frame 13b and a steel frame 13c that are arranged and fixed in, for example, a cross shape inside the opening of the frame 13a. It is comprised by the keystone plate 30 to close. In the steel frames 13b and 13c fixed in the above-mentioned cross shape, the main reinforcing bar (not shown) of the column 11 penetrates from below (the back direction in FIG. 3A). Moreover, said keystone plate 30 is arrange | positioned and fixed so that the opening space produced when the pillar 11 penetrates may be closed.

キャピタル13は、上端部分を図3(b)に示したように例えば床スラブ10の下端(下端筋)に接合しており、また、例えばこの部分において図示を省略した複数のボルト、ナット、スタッドジベルやアンカー金具等を用いて当該床スラブ10を固定している。
なお、必要に応じて、後述するブレース14のウェブ部の端部を固定するアンカー(固定部)等を当該キャピタル13の鉄骨部分に備える。
As shown in FIG. 3B, the capital 13 is joined to, for example, the lower end (lower end bar) of the floor slab 10, and, for example, a plurality of bolts, nuts, studs, which are not shown in this portion. The floor slab 10 is fixed using a gibber, an anchor fitting or the like.
In addition, the steel frame part of the said capital 13 is equipped with the anchor (fixing part) etc. which fix the edge part of the web part of the brace 14 mentioned later as needed.

フラットスラブ構造は比較的水平方向の震動に弱いことから、図2に示したものは、建造物の適当な位置に、2本の柱11間や上階の床スラブ10などによって建造物の高さ方向に形成される四辺形の軸組において、例えば筋交いとなる複数のブレース14を設置している。
また、鉄筋コンクリート造のキャピタル12と鉄骨造のキャピタル13は、建造物各部に生じるストレスや各柱にかかる荷重などに対応させて、即ち各位置において必要な耐力を有するようにそれぞれの柱頭に適したものが設けられる。
なお、上記の軸組みは、隣設した柱間や上下方向に隣設した床スラブによって形成されるものに限定されず、例えば複数階層の床スラブや柱などにわたって形成されたものなど、適宜、様々な大きさの軸組みについて上記のようにブレース14が設置される。
Since the flat slab structure is relatively weak against horizontal vibrations, the structure shown in FIG. 2 is placed at an appropriate position of the building between the two pillars 11 and the floor slab 10 on the upper floor. For example, a plurality of braces 14 that form braces are provided in a quadrilateral shaft formed in the vertical direction.
In addition, the reinforced concrete capital 12 and the steel capital 13 are suitable for each stigma so as to correspond to the stress generated in each part of the building and the load applied to each column, that is, to have the necessary strength at each position. Things are provided.
In addition, the above-mentioned shaft assembly is not limited to the one formed by the floor slabs provided next to each other between the adjacent columns or in the vertical direction, for example, formed over a plurality of floor slabs or columns, etc. Braces 14 are installed as described above for shafts of various sizes.

ブレース14は、鉄骨からなるもので各階層の床スラブ10の一辺部や複数の柱11の軸線によって(建造物の高さ方向に)形成される四辺形において対角線状に設置される。具体的には、複数のブレース14によって例えばK型、V型などを形成するように各柱11のキャピタル12またはキャピタル13、上下に配置された各階の床スラブ10等に固定されている。
図2(b)に例示したブレース14は、4本のブレース14を建造物の高さ方向において斜めに、もしくは筋交い状に配置固定しており、例えば一端部をキャピタル12に固定し、他端部を筋交いの交点部分となるように床スラブ10の側面部に設置されたアンカー等に固定されている。なお、ブレース14の他端部を、他の柱11に設けられたキャピタル12またはキャピタル13(ブレース14の一端部が固定されたキャピタル12またはキャピタル13に対して斜め上方、あるいは斜め下方に配置されたもの)に固定してもよい。
The brace 14 is made of a steel frame, and is installed diagonally in a quadrilateral formed by one side of the floor slab 10 of each layer and the axis of the plurality of pillars 11 (in the height direction of the building). Specifically, a plurality of braces 14 are fixed to the capital 12 or the capital 13 of each pillar 11, the floor slabs 10 of the respective floors arranged above and below, and the like so as to form, for example, a K-type and a V-type.
The brace 14 illustrated in FIG. 2B has four braces 14 arranged and fixed obliquely or in braces in the height direction of the building. For example, one end is fixed to the capital 12 and the other end is fixed. The part is fixed to an anchor or the like installed on the side surface of the floor slab 10 so as to be an intersection part of the brace. Note that the other end of the brace 14 is arranged on the other side of the capital 12 or 13 provided on the other pillar 11 (the upper side or the lower side of the capital 12 or the capital 13 to which the one end of the brace 14 is fixed). It may be fixed to the same).

図4および図5は、この実施例によるフラットスラブ構造の施工工程を示す説明図である。図4(a)〜図5(c)は、各柱11(柱11a〜11d)を設けるとともに上階の床スラブ10を設置する手順の一例を示したもので、フライングショア(支保工:型枠支持装置)21を使用して施工した場合を表している。このフライングショア21には、床スラブ10の複数の型枠等が配置固定されており、フライングショア21を移動することによって、複数の床スラブ10の床面配置と同様な状態で各型枠を移動することができる。
図4(a)は、図中左端の工区にフライングショア21を設置し、このフライングショア21によって隠れた位置に図示を省略した柱11a、キャピタル12等を構築し、さらにブレース14を固定した後、柱11b〜11dの構築を開始する状態を示している。なお、図中下側の床スラブ10aは、既にコンクリート打設が終了し、型枠等が取り除かれた後であり、その側面には例えば4本のブレース14と接合するアンカー15が固定されている。
4 and 5 are explanatory views showing the construction process of the flat slab structure according to this embodiment. 4 (a) to 5 (c) show an example of a procedure for installing each column 11 (columns 11a to 11d) and installing a floor slab 10 on an upper floor, and a flying shore (supporting work: mold) The frame support device) 21 is used for construction. A plurality of molds and the like of the floor slab 10 are arranged and fixed on the flying shore 21, and by moving the flying shore 21, each mold is placed in the same state as the floor surface arrangement of the plurality of floor slabs 10. Can move.
FIG. 4A shows a structure in which a flying shore 21 is installed in the leftmost work area in the drawing, a pillar 11a, a capital 12 and the like not shown are constructed at a position hidden by the flying shore 21 and a brace 14 is fixed. The state which starts construction | assembly of the pillars 11b-11d is shown. Note that the lower floor slab 10a in the drawing is after the concrete placement has been completed and the formwork and the like have been removed, and anchors 15 to be joined to, for example, four braces 14 are fixed to the side surfaces thereof. Yes.

ここで、上記の床スラブ10aは、前述の床スラブ10と同等なものである。また、上記のように床スラブ10aの例えば側面部分に、ブレース14を固定するアンカー15等を設ける場合には、床スラブ10aの型枠等にコンクリートを打設する前に、アンカー15等を所定位置に設置し、当該床スラブ10aを構成する鉄筋等と接合しておく。この後、床スラブ10aの型枠にコンクリートを打設し、このコンクリートを凝固させることによって当該床スラブ10aにアンカー15等を固定する。   Here, the floor slab 10a is equivalent to the floor slab 10 described above. Further, when the anchor 15 or the like for fixing the brace 14 is provided, for example, on the side surface portion of the floor slab 10a as described above, the anchor 15 or the like is set in advance before placing concrete on the formwork or the like of the floor slab 10a. It installs in a position and joins with the reinforcing bar etc. which comprise the said floor slab 10a. Thereafter, concrete is placed on the mold of the floor slab 10a, and the concrete is solidified to fix the anchor 15 and the like to the floor slab 10a.

図4〜図5に示した状態は、フライングショア21が配置されている位置まで、図中上側の床スラブ10が柱11aの上部まで構築され、当該柱11aや図示されない柱等によって床スラブ10が支持されており、床スラブ10aの下方に設置されている柱11、キャピタル12等についても構築施工が済んだ状態である。   4 to 5, the floor slab 10 on the upper side in the figure is constructed up to the top of the pillar 11a up to the position where the flying shore 21 is arranged, and the floor slab 10 is formed by the pillar 11a, a pillar (not shown), and the like. Is supported, and the construction work has been completed for the pillar 11, the capital 12, and the like installed below the floor slab 10 a.

フラットスラブ構造の各フロアを下階から順に施工し、前述のようにフライングショア21を設置した位置に柱11aを構築し、この柱11aの上方まで床スラブ10を構築した後、柱11aと同一フロアに柱11b〜11dを構築するとき、床スラブ10aを貫通している下階の各柱11の主鉄筋に帯鉄筋(hoop)を取り付ける。
また、予め地組により、柱11b〜11dを成す主鉄筋に、下端から柱頭に設けるキャピタル12またはキャピタル13の位置まで帯鉄筋を取り付けて柱筋16を組み上げておき、これら柱筋16を前述の床スラブ10を貫通している主鉄筋に、例えば機械式継手によって接続固定し、下階の各柱11を延設するように建て込む。
Each floor of the flat slab structure is constructed in order from the lower floor, and the pillar 11a is constructed at the position where the flying shore 21 is installed as described above. After constructing the floor slab 10 above the pillar 11a, the same as the pillar 11a When the pillars 11b to 11d are constructed on the floor, a tie bar is attached to the main reinforcement of each pillar 11 on the lower floor passing through the floor slab 10a.
Further, the reinforcing bars 16 are assembled to the main reinforcing bars forming the pillars 11b to 11d in advance by attaching band reinforcing bars from the lower end to the position of the capital 12 or the capital 13 provided at the top of the pillars. The main reinforcing bar penetrating the floor slab 10 is connected and fixed by, for example, a mechanical joint, and is built so as to extend each column 11 on the lower floor.

次に、図4(b)に示したように、建て込んだ柱11b〜11dの各柱筋16にシステム型枠17を建て込む。システム型枠17は、柱11b〜11dの各柱頭に、これから設けるキャピタル12,13の下端となる位置まで設置する。
上記のように設置した各システム型枠17にコンクリートを打設し、例えば2日程度養成して、コンクリート凝固後に各システム型枠17を、例えばクレーン等を用いて上方へ引き抜く。
Next, as shown in FIG.4 (b), the system formwork 17 is built in each column reinforcement 16 of the built-in pillar 11b-11d. The system formwork 17 is installed on each of the pillar heads of the pillars 11b to 11d up to a position that becomes a lower end of the capitals 12 and 13 to be provided.
Concrete is placed on each system mold 17 installed as described above, and is trained for, for example, about 2 days. After the concrete is solidified, each system mold 17 is pulled upward using, for example, a crane or the like.

次に、柱11b〜11dの柱頭にそれぞれキャピタル12またはキャピタル13を設置する。ここで例示する工区では、柱11cに鉄骨造のキャピタル13を設置し、柱11bおよび柱11dに鉄筋コンクリート造のキャピタル12を設置する。また、柱11b〜11dの中では柱11bのキャピタル12のみにブレース14を接続固定する。
柱11bと柱11dの柱頭には、キャピタル12の型枠を設置して格子状の鉄筋を組み上げ、各柱筋16と接合して固定する。このとき、柱11bのキャピタル12の鉄筋には、ブレース14のウェブ部の端部を固定するアンカー(図示省略)を組み込む。また、このアンカーにブレース14のウェブ部の端部を建方用ボルトを用いて固定する。この後、各柱11b,11dの柱頭の型枠にコンクリートを打設し、適宜、コンクリート硬化後に型枠を取り除いてキャピタル12を形成する。
Next, the capital 12 or the capital 13 is installed on the pillar heads of the pillars 11b to 11d, respectively. In the construction area illustrated here, a steel-framed capital 13 is installed on the column 11c, and a reinforced concrete-made capital 12 is installed on the columns 11b and 11d. Further, the brace 14 is connected and fixed only to the capital 12 of the pillar 11b in the pillars 11b to 11d.
The formwork of the capital 12 is installed on the tops of the pillars 11b and 11d to assemble the lattice-like reinforcing bars, and are joined and fixed to the pillars 16 respectively. At this time, an anchor (not shown) for fixing the end of the web portion of the brace 14 is incorporated into the reinforcing bar of the capital 12 of the column 11b. Moreover, the edge part of the web part of the brace 14 is fixed to this anchor using the bolt for construction. Thereafter, concrete is placed on the molds at the tops of the pillars 11b and 11d, and the capital 12 is formed by removing the molds as appropriate after the concrete is cured.

柱11cの柱頭には、鉄骨造の例えば図3に示したキャピタル13を設置固定する。キャピタル13は、工場または建設現場において、溶接またはボルトナット等を用いて枠体13aに鉄骨13bと鉄骨13cとを固定し、また、鉄骨13bと鉄骨13cとを固定して、図3に示した構造に組み立てる。また、キャピタル13は、鉄骨13bと鉄骨13cとの接合部分、即ち十字の中央部分の適当な位置に複数の貫通穴が設けられている。この貫通穴は、柱11cの各柱筋16(主鉄筋)の配置に対応して設けられており、当該キャピタル13を柱11cの柱頭に設置する際には、これらの貫通穴に柱11cの柱筋16(主鉄筋)が挿通され、これらの柱筋16がキャピタル13を貫通して上方へ突出する。なお、上記の貫通している柱筋16はキャピタル13、詳しくは鉄骨13b,13c等と接合され、この部分にはさらにコンクリートが打設される。また、このようにコンクリートを打設する前にキャピタル13の開口空間を防ぐキーストンプレート30を取り付けておく。
なお、キャピタル13にブレース14を接合する場合には、キャピタル13にブレース14のウェブ部の端部と接合するアンカー等を設けておき、キャピタル13を柱11cへ設置する際に適宜、ブレース14のウェブ部の端部を上記のアンカー等に接続固定する。
For example, a capital 13 shown in FIG. 3 is installed and fixed to the head of the pillar 11c. The capital 13 is shown in FIG. 3 by fixing the steel frame 13b and the steel frame 13c to the frame body 13a using welding or bolts and nuts at the factory or construction site, and fixing the steel frame 13b and the steel frame 13c. Assemble the structure. In addition, the capital 13 is provided with a plurality of through holes at an appropriate position of a joint portion of the steel frame 13b and the steel frame 13c, that is, a central portion of the cross. The through holes are provided corresponding to the arrangement of the column reinforcing bars 16 (main reinforcing bars) of the columns 11c. When the capital 13 is installed on the column heads of the columns 11c, the through holes are provided in the columns 11c. Column reinforcements 16 (main reinforcing bars) are inserted, and these column reinforcements 16 penetrate through the capital 13 and protrude upward. Note that the penetrating column reinforcement 16 is joined to the capital 13, more specifically, the steel frames 13b, 13c and the like, and concrete is further placed in this portion. In addition, the keystone plate 30 for preventing the opening space of the capital 13 is attached before placing concrete in this way.
In addition, when joining the brace 14 to the capital 13, the anchor etc. which join with the edge part of the web part of the brace 14 are provided in the capital 13, and when installing the capital 13 in the pillar 11c, the brace 14 of the brace 14 is suitably attached. The end of the web portion is connected and fixed to the anchor or the like.

柱11b〜11dの柱頭にキャピタル12およびキャピタル13を設置した後、図5(a)に示したようにフライングショア21を当該柱11b〜11dの設置位置へ移動させ、床スラブ10の型枠等を柱11b〜11dの上方へ移動・配置する。
次に、図5(b)のように柱11b〜11dの上方に床スラブ10を構築する。詳しくは、前述のようにフライングショア21を移動することによって他の工区(図中柱11aの左側の工区)から床スラブ10の型枠が柱11b〜11dの上方の工区へ移動する。このように移動してきた床スラブ10の型枠に沿って主鉄筋等の配筋を行う。
床スラブ10の各下端筋(図示省略)を柱11b〜11dの各キャピタル12,13の上面等に配筋し、アンボンドPC鋼線31を所定間隔を空けて上記の下端筋の間に配置する。その後、前述の下端筋の上側に上端筋を配筋し、さらに所定の懸垂曲線が得られるようにアンボンドPC鋼線31を配置して各鉄筋に結束する。
After the capital 12 and the capital 13 are installed on the heads of the pillars 11b to 11d, the flying shore 21 is moved to the installation positions of the pillars 11b to 11d as shown in FIG. Is moved and arranged above the pillars 11b to 11d.
Next, the floor slab 10 is constructed above the columns 11b to 11d as shown in FIG. Specifically, by moving the flying shore 21 as described above, the formwork of the floor slab 10 moves from another work area (the work area on the left side of the pillar 11a in the figure) to the work area above the pillars 11b to 11d. The main reinforcing bars and the like are arranged along the form of the floor slab 10 that has moved in this way.
The lower end bars (not shown) of the floor slab 10 are arranged on the upper surfaces of the capitals 12 and 13 of the columns 11b to 11d, and the unbonded PC steel wires 31 are arranged between the lower end bars at a predetermined interval. . Thereafter, the upper end bars are arranged on the upper side of the lower end bars, and the unbonded PC steel wire 31 is arranged so as to obtain a predetermined suspension curve and tied to each reinforcing bar.

前述のように各型枠に配筋を行った後、これらの型枠にコンクリートを打設し、床スラブ10を形成する。このとき、例えば床スラブ10の型枠に打設したコンクリートの保水養成を3日程度行い、さらに5日程度の凝固期間をおいてコンクリート強度を確認する。その後、アンボンドPC鋼線31に張力を加え、さらに1日程度経過後に後述するようにフライングショア21を移動させる。
上記の床スラブ10の型枠に打設したコンクリートが凝固した後、例えば柱11bのキャピタル12に建方用ボルトによって固定されているブレース14の一端部と、床スラブ10aの側面に設けられているアンカー15に建方用ボルトによって固定されているブレース14の他端部にそれぞれ溶接接合を施し、詳しくはブレース14のウェブ部をそれぞれ溶接して、ブレース14を所定のキャピタル12(またはキャピタル13)とアンカー15の間に配置固定する。
As described above, after arranging the molds, concrete is placed in these molds to form the floor slab 10. At this time, for example, the water retention of concrete placed in the form of the floor slab 10 is carried out for about 3 days, and the concrete strength is confirmed after a solidification period of about 5 days. Thereafter, tension is applied to the unbonded PC steel wire 31, and the flying shore 21 is moved as described later after about one day.
After the concrete cast in the form of the floor slab 10 is solidified, for example, it is provided on one end of the brace 14 fixed to the capital 12 of the pillar 11b by a building bolt and on the side surface of the floor slab 10a. The other ends of the braces 14 fixed to the anchors 15 by the building bolts are welded to each other, and more specifically, the web portions of the braces 14 are respectively welded, and the braces 14 are fixed to the predetermined capital 12 (or the capital 13). ) And the anchor 15.

上記のブレース14は、一端部を接合したキャピタル12の斜め下方に配置固定されているアンカー15に他端部を接合しているが、上記キャピタル12の斜め上方に配置される図示されないアンカー15、あるいは他の柱のキャピタル12やキャピタル13に接合するようにしてもよい。
また、キャピタル12またはキャピタル13は、複数のブレース14のウェブ部と接合できるように構成してもよく、図4〜図5に示したように2〜4本のブレース14ウェブ部を放射状に接合・固定する構成とすることも可能である。
The brace 14 has the other end joined to the anchor 15 arranged and fixed obliquely below the capital 12 with one end joined, but the anchor 15 not shown is arranged obliquely above the capital 12. Or you may make it join to the capital 12 and the capital 13 of another pillar.
Further, the capital 12 or the capital 13 may be configured to be able to be joined to the web portions of the plurality of braces 14, and as shown in FIGS. 4 to 5, 2 to 4 brace 14 web portions are joined radially. -It can also be configured to be fixed.

例えば、柱11bのキャピタル12は、床スラブ10aのアンカー15と接合する前述のブレース14の他に、斜め上方、即ち床スラブ10の上方に設置されるキャピタル12,13あるいはアンカー15等に固定されるブレース14(図示省略)とも接合可能に構成されている。
この場合、床スラブ10の上方において設置固定されるブレース14ウェブ部の端部と接合する例えば柱11bのキャピタル12に備えられたアンカーを、床スラブ10の床面から上方へ突出するようにしておく。
For example, the capital 12 of the column 11b is fixed to the capitals 12 and 13 or the anchor 15 installed obliquely above, that is, above the floor slab 10, in addition to the brace 14 that is joined to the anchor 15 of the floor slab 10a. The brace 14 (not shown) is also connectable.
In this case, for example, the anchor provided on the capital 12 of the pillar 11 b that is joined to the end of the brace 14 web portion that is installed and fixed above the floor slab 10 is projected upward from the floor surface of the floor slab 10. deep.

前述のように床スラブ10の型枠に打設したコンクリートを硬化させ、アンボンドPC鋼線31に張力を導入した後、図5(c)に示したようにフライングショア21を他の工区へ、例えば他の階層などへ移動させ、上記の他の工区において柱11、キャピタル12,13、床スラブ10、ブレース14等の施工を行う。   After the concrete placed on the formwork of the floor slab 10 is hardened as described above and tension is introduced into the unbonded PC steel wire 31, the flying shore 21 is moved to another work area as shown in FIG. For example, it is moved to another level or the like, and the pillars 11, the capitals 12 and 13, the floor slab 10, the braces 14 and the like are constructed in the other construction zones.

以上のように、この実施例によれば、柱11等の柱頭にキャピタル12またはキャピタル13を設け、これらにブレース14を固定するようにしたので、同一の床面上を耐震壁で仕切ることなく耐震性を高めることができ、また、屋内の通気性や照明効率を良好にすることができる。
また、鉄筋コンクリート造の耐震壁を備えていないことから、下階の床スラブ10等にかかる荷重を軽減することができ、耐性を高めることができる。
また、工場等において製造されたブレース14を使用することから、建設現場において行う耐震施工の工数等を抑制することができ、また作業を効率良く進行することによって工期を短縮することができる。
As described above, according to this embodiment, the capital 12 or the capital 13 is provided on the heads of the pillars 11 and the like, and the braces 14 are fixed to these, so that the same floor surface is not partitioned by the earthquake-resistant wall. Seismic resistance can be enhanced, and indoor ventilation and lighting efficiency can be improved.
Moreover, since the reinforced concrete structure earthquake-resistant wall is not provided, the load concerning the floor slab 10 etc. of a lower floor can be reduced, and tolerance can be improved.
Moreover, since the brace 14 manufactured in the factory etc. is used, the man-hour etc. of the earthquake-proof construction performed at a construction site can be suppressed, and a work period can be shortened by progressing work efficiently.

10,10a床スラブ
11,11a,11b,11c,11d柱
12キャピタル
13キャピタル
13a枠体
13b,13c鉄骨
14ブレース
15アンカー
16柱筋
17システム型枠
21フライングショア
30キーストンプレート
31アンボンドPC鋼線
101床スラブ
102柱
103キャピタル
104耐震壁
10, 10a floor slab 11, 11a, 11b, 11c, 11d pillar 12 capital 13 capital 13a frame 13b, 13c steel frame 14 brace 15 anchor 16 pillar reinforcement 17 system formwork 21 flying shore 30 keystone plate 31 unbonded PC steel wire 101 floor Slab 102 pillars 103 capital 104 seismic walls

Claims (4)

建造物を形成する鉄筋コンクリート造の複数の柱と、
前記柱の各柱頭に設置されるキャピタルと、
前記各柱のキャピタルによって支持固定された鉄筋コンクリート造の複数の床スラブと、
前記建造物の上下階層間に設置される鉄骨ブレースと、
を有し、
前記鉄骨ブレースは、
前記各柱の軸線および前記床スラブの一辺部によって形成される四辺形の軸組に対角線状に設置され、端部を前記キャピタルに接合する、
ことを特徴とするフラットスラブ構造。
A plurality of reinforced concrete columns forming the building;
Capital installed at each capital of the pillar;
A plurality of reinforced concrete floor slabs supported and fixed by the capital of each pillar;
Steel braces installed between upper and lower levels of the building;
Have
The steel brace is
It is installed diagonally on a quadrilateral shaft formed by the axis of each pillar and one side of the floor slab, and the end is joined to the capital.
Flat slab structure characterized by that.
前記キャピタルは、鉄筋コンクリート造であり、所定位置に配置される該キャピタルは前記鉄骨ブレースの端部と接合する固定部を有し、
前記鉄骨ブレースは、一端部を前記キャピタルの固定部に接合し、他端部を該キャピタルの斜め下方または斜め上方に配置されている、床スラブに設置された固定部または他のキャピタルの固定部に接合する、
ことを特徴とする請求項1に記載のフラットスラブ構造。
The capital is a reinforced concrete structure, and the capital disposed at a predetermined position has a fixing portion that joins an end of the steel brace,
The steel brace has one end joined to the fixed portion of the capital, and the other end is disposed obliquely below or obliquely above the capital, and is disposed on a floor slab or a fixed portion of another capital To join,
The flat slab structure according to claim 1.
前記キャピタルは、鉄骨造であり、所定位置に配置される該キャピタルは前記鉄骨ブレースの端部と接合する固定部を有し、
前記鉄骨ブレースは、一端部を前記キャピタルの固定部に接合し、他端部を該キャピタルの斜め下方または斜め上方に配置されている、床スラブに設置された固定部または他のキャピタルの固定部に接合する、
ことを特徴とする請求項1に記載のフラットスラブ構造。
The capital is a steel frame, and the capital arranged at a predetermined position has a fixing portion that joins an end of the steel brace,
The steel brace has one end joined to the fixed portion of the capital, and the other end is disposed obliquely below or obliquely above the capital, and is disposed on a floor slab or a fixed portion of another capital To join,
The flat slab structure according to claim 1.
必要な耐力に応じて鉄骨造のキャピタルまたは鉄筋コンクリート造のキャピタルをそれぞれの柱に設ける、
ことを特徴とする請求項1から3のいずれか1項に記載のフラットスラブ構造。
Depending on the required proof stress, each column will be provided with steel or reinforced concrete capital.
The flat slab structure according to any one of claims 1 to 3, wherein:
JP2013263546A 2013-12-20 2013-12-20 Flat slab structure Active JP6300228B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013263546A JP6300228B2 (en) 2013-12-20 2013-12-20 Flat slab structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013263546A JP6300228B2 (en) 2013-12-20 2013-12-20 Flat slab structure

Publications (2)

Publication Number Publication Date
JP2015117562A true JP2015117562A (en) 2015-06-25
JP6300228B2 JP6300228B2 (en) 2018-03-28

Family

ID=53530543

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013263546A Active JP6300228B2 (en) 2013-12-20 2013-12-20 Flat slab structure

Country Status (1)

Country Link
JP (1) JP6300228B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107893499A (en) * 2017-11-23 2018-04-10 西京学院 Light-duty spliced steel-concrete building plate composite flat beam and its construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6139455B2 (en) * 1980-12-17 1986-09-04 Kajima Corp
JPS63127513U (en) * 1987-02-13 1988-08-22
JPH0726423U (en) * 1993-10-21 1995-05-19 清水建設株式会社 Flat plate structure and brace member used for the same
JP2000257158A (en) * 1999-03-08 2000-09-19 Nkk Corp Frame structure formed of flat slabs and steel pipe columns
GB2352459A (en) * 1999-06-17 2001-01-31 Brian Horton Conical device for transferring loads from floors to columns
JP2005171548A (en) * 2003-12-09 2005-06-30 Asanuma Corp Reinforcing structure and reinforcing method for flat plate frame

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6139455B2 (en) * 1980-12-17 1986-09-04 Kajima Corp
JPS63127513U (en) * 1987-02-13 1988-08-22
JPH0726423U (en) * 1993-10-21 1995-05-19 清水建設株式会社 Flat plate structure and brace member used for the same
JP2000257158A (en) * 1999-03-08 2000-09-19 Nkk Corp Frame structure formed of flat slabs and steel pipe columns
GB2352459A (en) * 1999-06-17 2001-01-31 Brian Horton Conical device for transferring loads from floors to columns
JP2005171548A (en) * 2003-12-09 2005-06-30 Asanuma Corp Reinforcing structure and reinforcing method for flat plate frame

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107893499A (en) * 2017-11-23 2018-04-10 西京学院 Light-duty spliced steel-concrete building plate composite flat beam and its construction method

Also Published As

Publication number Publication date
JP6300228B2 (en) 2018-03-28

Similar Documents

Publication Publication Date Title
JP4823790B2 (en) Column unit and method of building building using column unit
KR101570484B1 (en) Half-PC Column using lightweight Encased Inner Form And Manufacturing Method Thereof, And Construction Method Using The Same
JP2018096071A (en) Composite building
JP2010261270A (en) Composite structure and method for constructing composite structure building
JP2016205051A (en) Construction method for structure
JP5865567B2 (en) Connecting slab and its construction method
JP6368584B2 (en) Foundation construction method
JP7118507B2 (en) Steel reinforced concrete wall pillar building structure
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JP2008266902A (en) Wall unit and earthquake-resistant wall
JP6300228B2 (en) Flat slab structure
JP2017014713A (en) Existing concrete structure reinforcement structure
JP2020026634A (en) Seismic isolation upper foundation structure and method for manufacturing the same, footing structure, and method for constructing seismic isolation foundation
JP5870455B2 (en) Precast concrete wall and joint structure between column and beam
JP6684088B2 (en) Seismic retrofitting structure and method for existing buildings
JP2008223242A (en) Manufacturing method for precast concrete panel
JP6576204B2 (en) Slab construction method
JP2006265897A (en) Seismic reinforcing structure for building
JP6261333B2 (en) Seismic reinforcement method
JP6114071B2 (en) Seismic isolation method for existing buildings and temporary structure under construction
JP7217195B2 (en) Double floor construction method
JP2013181334A (en) Earthquake strengthening method of building
JP2023022563A (en) Concrete wall construction method
JP2017500460A (en) Machine table foundation
JP2005171548A (en) Reinforcing structure and reinforcing method for flat plate frame

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160615

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20160721

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170308

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170314

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170510

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170912

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20171030

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180206

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180220

R150 Certificate of patent or registration of utility model

Ref document number: 6300228

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250