JP2011095918A5 - - Google Patents

Download PDF

Info

Publication number
JP2011095918A5
JP2011095918A5 JP2009248053A JP2009248053A JP2011095918A5 JP 2011095918 A5 JP2011095918 A5 JP 2011095918A5 JP 2009248053 A JP2009248053 A JP 2009248053A JP 2009248053 A JP2009248053 A JP 2009248053A JP 2011095918 A5 JP2011095918 A5 JP 2011095918A5
Authority
JP
Japan
Prior art keywords
task
tasks
order
process diagram
information indicating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009248053A
Other languages
Japanese (ja)
Other versions
JP5443945B2 (en
JP2011095918A (en
Filing date
Publication date
Application filed filed Critical
Priority to JP2009248053A priority Critical patent/JP5443945B2/en
Priority claimed from JP2009248053A external-priority patent/JP5443945B2/en
Publication of JP2011095918A publication Critical patent/JP2011095918A/en
Publication of JP2011095918A5 publication Critical patent/JP2011095918A5/ja
Application granted granted Critical
Publication of JP5443945B2 publication Critical patent/JP5443945B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Description

本発明のプロジェクト計画装置は、入力部と表示部とを備え、制約条件の理論に従ってプロジェクトを計画するためのプロジェクト計画装置であって、タスク同士の階層関係には、子タスクを実行するためには、親タスクの全ての先行タスクが完了していなければならず、親タスクの後続タスクを実行するためには、全ての子タスクが完了していなければならない、というテクニカルな依存関係があるものにおいて、前記入力部を用いたユーザの操作に応じて、プロジェクト遂行に必要な各タスクの所要時間を示す情報、及び、各タスクの実行に必要なリソースを示す情報の入力を受けるとともに、タスク同士の順序関係を示す情報、及び、タスク同士の階層関係を示す情報の入力を受けて所定の領域に記憶しておく情報取得手段と、前記記憶しておいた所要時間を示す情報と前記リソースを示す情報と前記順序関係を示す情報と前記階層関係を示す情報とに基づいて、前記順序関係と前記階層関係とに従うように、かつ、前記階層関係における下位のタスクを持たないタスク(以下、「末端タスク」という。)間で、各タスクの実行時にそれぞれが必要とするリソースが競合するか否かを判断して、競合するものにおいては所定のルールでリソースが時間的に重複しないように、各タスクの順序を決定し、当該順序に従って各タスクを示す要素を配置した第1の工程図を作成し、前記表示部に表示する工程図作成手段と、前記階層関係における下位のタスクを持つタスク(以下、「親タスク」という。)の開始点と終了点とを仮想的なノード(以下、「仮想ノード」という。)とし、前記順序関係に基づいて、末端タスク及び仮想ノードで構成される仮想的な工程図を対象として、前記プロジェクトにおけるクリティカルチェーン上にある末端タスク及び仮想ノードを決定し、前記第1の工程図または前記第1の工程図から作成した第2の工程図の少なくとも一方に、前記クリティカルチェーン上の末端タスクを示す要素を、前記クリティカルチェーン上にない末端タスクを示す要素とは区別可能に表示するクリティカルチェーン決定手段と、を備えることを特徴とする。
The project planning device of the present invention includes an input unit and a display unit, and is a project planning device for planning a project according to the theory of constraint conditions. In order to execute a child task in a hierarchical relationship between tasks Has a technical dependency that all predecessors of the parent task must be completed and all child tasks must be completed in order to execute the successor task of the parent task In response to the user's operation using the input unit, the information indicating the time required for each task necessary for executing the project and the information indicating the resource required for executing each task are input. information indicating the order relationship, and an information obtaining means for storing in a predetermined area receives the input of information indicating the hierarchical relationship between tasks, the Symbol Based on the information indicating the required time had been with the information indicating the resource and the information indicating the order relationship with said information indicating a hierarchical relationship, and to follow with the hierarchical relationship between the order relation, and, the hierarchical It is determined whether or not resources necessary for each task compete between tasks that do not have subordinate tasks in the relationship (hereinafter referred to as “end task”). The order of each task is determined so that resources do not overlap in time according to the rules, and a first process diagram in which elements indicating each task are arranged according to the order is created and displayed on the display unit Means and the start point and end point of a task having a lower-order task in the hierarchical relationship (hereinafter referred to as “parent task”) are virtual nodes (hereinafter referred to as “virtual nodes”). , Based on the order relation, for a virtual process diagram composed of end tasks and virtual nodes, determine end tasks and virtual nodes on the critical chain in the project, and the first process diagram or Critical that displays an element indicating an end task on the critical chain in at least one of the second process diagrams created from the first process diagram so as to be distinguishable from an element indicating an end task not on the critical chain And a chain determining means.

本発明のプロジェクト計画プログラムは、制約条件の理論に従ってプロジェクトを計画するためのプロジェクト計画プログラムであって、タスク同士の階層関係には、子タスクを実行するためには、親タスクの全ての先行タスクが完了していなければならず、親タスクの後続タスクを実行するためには、全ての子タスクが完了していなければならない、というテクニカルな依存関係があるものにおいて、入力部と表示部とを備えたコンピュータを、前記入力部を用いたユーザの操作に応じて、プロジェクト遂行に必要な各タスクの所要時間を示す情報、及び、各タスクの実行に必要なリソースを示す情報の入力を受けるとともに、タスク同士の順序関係を示す情報、及び、タスク同士の階層関係を示す情報の入力を受けて所定の領域に記憶しておく情報取得手段、前記記憶しておいた所要時間を示す情報と前記リソースを示す情報と前記順序関係を示す情報と前記階層関係を示す情報とに基づいて、前記順序関係と前記階層関係とに従うように、かつ、前記階層関係における下位のタスクを持たないタスク(以下、「末端タスク」という。)間で、各タスクの実行時にそれぞれが必要とするリソースが競合するか否かを判断して、競合するものにおいては所定のルールでリソースが時間的に重複しないように、各タスクの順序を決定し、当該順序に従って各タスクを示す要素を配置した第1の工程図を作成し、前記表示部に表示する工程図作成手段、及び、前記階層関係における下位のタスクを持つタスク(以下、「親タスク」という。)の開始点と終了点とを仮想的なノード(以下、「仮想ノード」という。)とし、前記順序関係に基づいて、末端タスク及び仮想ノードで構成される仮想的な工程図を対象として、前記プロジェクトにおけるクリティカルチェーン上にある末端タスク及び仮想ノードを決定し、前記第1の工程図または前記第1の工程図から作成した第2の工程図の少なくとも一方に、前記クリティカルチェーン上の末端タスクを示す要素を、前記クリティカルチェーン上にない末端タスクを示す要素とは区別可能に表示するクリティカルチェーン決定手段、として機能させることを特徴とする。
Project planning program of the present invention is a project planning program for planning project in accordance theoretical constraints, a hierarchical relationship between tasks, in order to execute the child task, all predecessor parent task If there is a technical dependency that all child tasks must be completed in order to execute subsequent tasks of the parent task, input and display In response to a user operation using the input unit, the computer is provided with input of information indicating the time required for each task necessary for project execution and information indicating resources required for execution of each task. , information indicating the order relationship between tasks, and then stored in a predetermined area receives the information indicating the hierarchical relationship between tasks Placing information acquisition means, based on said information storage and information indicating the required time was allowed between the information indicating resource and the information indicating the order relationship indicating the hierarchical relationship, according to said hierarchical relationship between the order relationship In addition, it is determined whether or not resources required by each task compete between tasks that do not have lower-level tasks in the hierarchical relationship (hereinafter referred to as “end tasks”). In the case of competing items, the order of each task is determined so that resources do not overlap in time according to a predetermined rule, and a first process diagram in which elements indicating each task are arranged in accordance with the order is created and displayed. The process diagram creation means to be displayed in the section and the start point and end point of a task having a lower-order task in the hierarchical relationship (hereinafter referred to as “parent task”) Based on the order relation, the end task and the virtual node on the critical chain in the project are determined based on the virtual process diagram composed of the end task and the virtual node. In addition, at least one of the first process diagram or the second process diagram created from the first process diagram shows an element indicating an end task on the critical chain and an end task not on the critical chain. It is characterized by functioning as a critical chain determining means for displaying in a distinguishable manner from elements.

また、全く無関係な階層位置にあり、テクニカルな依存関係がないタスク同士であっても、リソースによって依存関係が発生する場合もある。図3に示す例では、互いに無関係な階層位置にあるタスクボックスT31、T61、T72で示されるタスクが、同じ時期に同じリソースAを必要としている。そこで、クライアント2は、タスクボックスT31、T61、T72の順序を、所定のルールで(ここでは、プロジェクトネットワーク図において上にあるタスクボックスTが左になるように)決定することにより、リソースの競合を解消する。すなわち、互いに無関係な階層位置にあるタスクボックスT31、T61、T72が、同じ時期に同じリソースAを必要とするために、互いに依存する(順序を持つ)関係となる。
このためには、各タスクの実行に必要なリソースを示す情報の入力を受けるとともに、タスク同士の順序関係を示す情報、及び、タスク同士の階層関係を示す情報の入力を受けて所定の領域に記憶しておく必要があるし、また、タスクの実行順序に関しては、各タスクの実行時にそれぞれが必要とするリソースが競合するか否かを判断して、競合するものにおいては上記ルールでリソースが時間的に重複しないように、同タスクの順序を決定する必要がある。

In addition, even if tasks are not related to each other and have no technical dependency, dependency may occur depending on resources. In the example shown in FIG. 3, the tasks indicated by the task boxes T31, T61, and T72 at hierarchical levels that are not related to each other require the same resource A at the same time. Therefore, the client 2 determines the order of the task boxes T31, T61, and T72 according to a predetermined rule (here, the task box T on the upper side in the project network diagram is on the left), thereby competing for resources. Is solved. In other words, the task boxes T31, T61, and T72 at hierarchical positions that are not related to each other require the same resource A at the same time, and thus have a relationship that depends on each other (has an order).
For this purpose, input of information indicating resources necessary for the execution of each task is received, and information indicating the order relationship between tasks and information indicating the hierarchical relationship between tasks are received in a predetermined area. It is necessary to memorize, and regarding the execution order of tasks, it is determined whether or not the resources required for each task compete at the time of execution of each task. It is necessary to determine the order of the tasks so as not to overlap in time.

Claims (6)

入力部と表示部とを備え、制約条件の理論に従ってプロジェクトを計画するためのプロジェクト計画装置であって、
タスク同士の階層関係には、子タスクを実行するためには、親タスクの全ての先行タスクが完了していなければならず、親タスクの後続タスクを実行するためには、全ての子タスクが完了していなければならない、というテクニカルな依存関係があるものにおいて、
前記入力部を用いたユーザの操作に応じて、プロジェクト遂行に必要な各タスクの所要時間を示す情報、及び、各タスクの実行に必要なリソースを示す情報の入力を受けるとともに、タスク同士の順序関係を示す情報、及び、タスク同士の階層関係を示す情報の入力を受けて所定の領域に記憶しておく情報取得手段と、
前記記憶しておいた所要時間を示す情報と前記リソースを示す情報と前記順序関係を示す情報と前記階層関係を示す情報とに基づいて、前記順序関係と前記階層関係とに従うように、かつ、前記階層関係における下位のタスクを持たないタスク(以下、「末端タスク」という。)間で、各タスクの実行時にそれぞれが必要とするリソースが競合するか否かを判断して、競合するものにおいては所定のルールでリソースが時間的に重複しないように、各タスクの順序を決定し、当該順序に従って各タスクを示す要素を配置した第1の工程図を作成し、前記表示部に表示する工程図作成手段と、
前記階層関係における下位のタスクを持つタスク(以下、「親タスク」という。)の開始点と終了点とを仮想的なノード(以下、「仮想ノード」という。)とし、前記順序関係に基づいて、末端タスク及び仮想ノードで構成される仮想的な工程図を対象として、前記プロジェクトにおけるクリティカルチェーン上にある末端タスク及び仮想ノードを決定し、前記第1の工程図または前記第1の工程図から作成した第2の工程図の少なくとも一方に、前記クリティカルチェーン上の末端タスクを示す要素を、前記クリティカルチェーン上にない末端タスクを示す要素とは区別可能に表示するクリティカルチェーン決定手段と、
を備えることを特徴とするプロジェクト計画装置。
A project planning device comprising an input unit and a display unit, for planning a project according to the theory of constraints,
In the hierarchical relationship between tasks, in order to execute a child task, all the preceding tasks of the parent task must be completed, and in order to execute the subsequent task of the parent task, all the child tasks must For technical dependencies that must be completed,
In response to a user operation using the input unit, information indicating the time required for each task required for project execution and information indicating resources required for executing each task are received , and the order of tasks Information acquisition means for receiving information indicating a relationship and information indicating a hierarchical relationship between tasks and storing the information in a predetermined area ;
Based on the stored information indicating the required time, the information indicating the resource, the information indicating the order relationship, and the information indicating the hierarchy relationship, according to the order relationship and the hierarchy relationship, and Among tasks that do not have lower-level tasks in the hierarchical relationship (hereinafter referred to as “end tasks”) , determine whether or not the resources required by each task conflict, Determining the order of each task so that resources do not overlap in time according to a predetermined rule, creating a first process diagram in which elements indicating each task are arranged according to the order, and displaying the first process diagram on the display unit Drawing means;
The start point and end point of a task having a lower-order task in the hierarchical relationship (hereinafter referred to as “parent task”) are defined as virtual nodes (hereinafter referred to as “virtual nodes”), and based on the order relationship. , For a virtual process diagram composed of end tasks and virtual nodes, determine end tasks and virtual nodes on the critical chain in the project, and from the first process diagram or the first process diagram Critical chain determination means for displaying an element indicating the end task on the critical chain in at least one of the created second process diagrams so as to be distinguishable from an element indicating the end task not on the critical chain;
A project planning apparatus comprising:
前記クリティカルチェーン上の末端タスク、及び、開始点の仮想ノードがクリティカルチェーン上にある親タスクを基点となるタスクとして、前記基点となるタスクに合流する末端タスクであって前記クリティカルチェーン上にない末端タスクを探索し、見つかった末端タスクの直後に合流バッファを設定し、当該合流バッファを示す要素を前記第1の工程図または前記第2の工程図の少なくとも一方に表示する合流バッファ設定手段
を備えることを特徴とする請求項1記載のプロジェクト計画装置。
The end task on the critical chain, and the end task that joins the task that is the base point with the parent task whose starting point virtual node is on the critical chain as the base task, and that is not on the critical chain A merge buffer setting means for searching for a task, setting a merge buffer immediately after the found end task, and displaying an element indicating the merge buffer in at least one of the first process diagram and the second process diagram; The project planning apparatus according to claim 1, wherein:
前記クリティカルチェーン上の末端タスクまたは前記クリティカルチェーン上の仮想ノードに合流する、末端タスクまたは仮想ノードであって前記クリティカルチェーン上にないものを探索し、見つかった末端タスク、及び、見つかった仮想ノードに対応する親タスクの開始点または終了点の直後に、合流バッファを設定し、当該合流バッファを示す要素を前記第1の工程図または前記第2の工程図の少なくとも一方に表示する合流バッファ設定手段
を備えることを特徴とする請求項1記載のプロジェクト計画装置。
Search for end tasks or virtual nodes that join the end task on the critical chain or the virtual node on the critical chain that are not on the critical chain. Immediately after the start point or end point of the corresponding parent task, a merging buffer is set, and a merging buffer setting means for displaying an element indicating the merging buffer in at least one of the first process diagram and the second process diagram. The project planning apparatus according to claim 1, further comprising:
制約条件の理論に従ってプロジェクトを計画するためのプロジェクト計画プログラムであって、タスク同士の階層関係には、子タスクを実行するためには、親タスクの全ての先行タスクが完了していなければならず、親タスクの後続タスクを実行するためには、全ての子タスクが完了していなければならない、というテクニカルな依存関係があるものにおいて、入力部と表示部とを備えたコンピュータを、
前記入力部を用いたユーザの操作に応じて、プロジェクト遂行に必要な各タスクの所要時間を示す情報、及び、各タスクの実行に必要なリソースを示す情報の入力を受けるとともに、タスク同士の順序関係を示す情報、及び、タスク同士の階層関係を示す情報の入力を受けて所定の領域に記憶しておく情報取得手段、
前記記憶しておいた所要時間を示す情報と前記リソースを示す情報と前記順序関係を示す情報と前記階層関係を示す情報とに基づいて、前記順序関係と前記階層関係とに従うように、かつ、前記階層関係における下位のタスクを持たないタスク(以下、「末端タスク」という。)間で、各タスクの実行時にそれぞれが必要とするリソースが競合するか否かを判断して、競合するものにおいては所定のルールでリソースが時間的に重複しないように、各タスクの順序を決定し、当該順序に従って各タスクを示す要素を配置した第1の工程図を作成し、前記表示部に表示する工程図作成手段、
及び、
前記階層関係における下位のタスクを持つタスク(以下、「親タスク」という。)の開始点と終了点とを仮想的なノード(以下、「仮想ノード」という。)とし、前記順序関係に基づいて、末端タスク及び仮想ノードで構成される仮想的な工程図を対象として、前記プロジェクトにおけるクリティカルチェーン上にある末端タスク及び仮想ノードを決定し、前記第1の工程図または前記第1の工程図から作成した第2の工程図の少なくとも一方に、前記クリティカルチェーン上の末端タスクを示す要素を、前記クリティカルチェーン上にない末端タスクを示す要素とは区別可能に表示するクリティカルチェーン決定手段、
として機能させることを特徴とするプロジェクト計画プログラム。
A project planning program for planning a project according to the theory of constraints. In order to execute child tasks, all preceding tasks of the parent task must be completed in the hierarchical relationship between tasks. In order to execute a task subsequent to a parent task, a computer having an input unit and a display unit in a technical dependency that all child tasks must be completed ,
In response to a user operation using the input unit, information indicating the time required for each task required for project execution and information indicating resources required for executing each task are received , and the order of tasks Information acquisition means for receiving information indicating a relationship and information indicating a hierarchical relationship between tasks and storing the information in a predetermined area ;
Based on the stored information indicating the required time, the information indicating the resource, the information indicating the order relationship, and the information indicating the hierarchy relationship, according to the order relationship and the hierarchy relationship, and Among tasks that do not have lower-level tasks in the hierarchical relationship (hereinafter referred to as “end tasks”) , determine whether or not the resources required by each task conflict, Determining the order of each task so that resources do not overlap in time according to a predetermined rule, creating a first process diagram in which elements indicating each task are arranged according to the order, and displaying the first process diagram on the display unit Drawing means,
as well as,
The start point and end point of a task having a lower-order task in the hierarchical relationship (hereinafter referred to as “parent task”) are defined as virtual nodes (hereinafter referred to as “virtual nodes”), and based on the order relationship. , For a virtual process diagram composed of end tasks and virtual nodes, determine end tasks and virtual nodes on the critical chain in the project, and from the first process diagram or the first process diagram Critical chain determining means for displaying an element indicating a terminal task on the critical chain in at least one of the created second process diagrams so as to be distinguishable from an element indicating a terminal task not on the critical chain;
Project planning program characterized by functioning as
前記コンピュータを、
前記クリティカルチェーン上の末端タスク、及び、開始点の仮想ノードがクリティカルチェーン上にある親タスクを基点となるタスクとして、前記基点となるタスクに合流する末端タスクであって前記クリティカルチェーン上にない末端タスクを探索し、見つかった末端タスクの直後に合流バッファを設定し、当該合流バッファを示す要素を前記第1の工程図または前記第2の工程図の少なくとも一方に表示する合流バッファ設定手段
として機能させることを特徴とする請求項4記載のプロジェクト計画プログラム。
The computer,
The end task on the critical chain, and the end task that joins the task that is the base point with the parent task whose starting point virtual node is on the critical chain as the base task, and that is not on the critical chain Functions as a merge buffer setting means for searching for a task, setting a merge buffer immediately after the found end task, and displaying an element indicating the merge buffer in at least one of the first process diagram and the second process diagram The project planning program according to claim 4, wherein:
前記コンピュータを、
前記クリティカルチェーン上の末端タスクまたは前記クリティカルチェーン上の仮想ノードに合流する、末端タスクまたは仮想ノードであって前記クリティカルチェーン上にないものを探索し、見つかった末端タスク、及び、見つかった仮想ノードに対応する親タスクの開始点または終了点の直後に、合流バッファを設定し、当該合流バッファを示す要素を前記第1の工程図または前記第2の工程図の少なくとも一方に表示する合流バッファ設定手段
として機能させることを特徴とする請求項4記載のプロジェクト計画プログラム。
The computer,
Search for end tasks or virtual nodes that join the end task on the critical chain or the virtual node on the critical chain that are not on the critical chain. Immediately after the start point or end point of the corresponding parent task, a merging buffer is set, and a merging buffer setting means for displaying an element indicating the merging buffer in at least one of the first process diagram and the second process diagram. The project planning program according to claim 4, wherein
JP2009248053A 2009-10-28 2009-10-28 Project planning device and project planning program Active JP5443945B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009248053A JP5443945B2 (en) 2009-10-28 2009-10-28 Project planning device and project planning program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009248053A JP5443945B2 (en) 2009-10-28 2009-10-28 Project planning device and project planning program

Publications (3)

Publication Number Publication Date
JP2011095918A JP2011095918A (en) 2011-05-12
JP2011095918A5 true JP2011095918A5 (en) 2013-03-21
JP5443945B2 JP5443945B2 (en) 2014-03-19

Family

ID=44112769

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009248053A Active JP5443945B2 (en) 2009-10-28 2009-10-28 Project planning device and project planning program

Country Status (1)

Country Link
JP (1) JP5443945B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5802611B2 (en) * 2012-06-07 2015-10-28 株式会社エヌ・ティ・ティ・データ Simulation apparatus, simulation method, and program
JP6297919B2 (en) * 2014-05-19 2018-03-20 株式会社日立製作所 Method for supporting work planning in software development, and work planning support device
JP6639115B2 (en) * 2015-06-11 2020-02-05 三菱重工業株式会社 Planning support system
WO2021044487A1 (en) * 2019-09-02 2021-03-11 日本電気株式会社 Processing device, processing method, and program
WO2021193800A1 (en) * 2020-03-27 2021-09-30 パナソニックIpマネジメント株式会社 Work management device and preparation instruction method
CN111913986B (en) * 2020-08-03 2024-04-16 支付宝(杭州)信息技术有限公司 Query optimization method and device
CN117132095B (en) * 2023-08-07 2024-03-01 中国船舶集团有限公司第七一九研究所 Ship development progress management system based on buffer area monitoring

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007140607A (en) * 2005-11-14 2007-06-07 Noriaki Aoki Medical management support apparatus, medical management support method, medical management support program and medical management support system
JP5127186B2 (en) * 2006-08-31 2013-01-23 株式会社リコー Workflow management system, workflow management method, workflow management program, and recording medium

Similar Documents

Publication Publication Date Title
JP2011095918A5 (en)
US9672276B2 (en) Multi-act creation user interface element
US8887163B2 (en) Task scheduling based on dependencies and resources
CA2959677C (en) Parametric inertia and apis
JP5431261B2 (en) Information management system, method and program
US8935705B2 (en) Execution of highly concurrent processing tasks based on the updated dependency data structure at run-time
JP2018037059A5 (en)
US9471211B2 (en) Chaining applications
JP2011028752A5 (en)
CN111026494B (en) Business process processing method, device and equipment
US20170220457A1 (en) Constructing test-centric model of application
Berthold et al. Parallelization of the FICO xpress-optimizer
JP2016045893A (en) Program information generation system, method, and program
EP2507752A1 (en) Framework for finding one or more solutions to a problem
CN102932200B (en) Monitoring method and device for information flow node processing time limit
KR101235330B1 (en) The Apparatus and Method for Integrated Management of Embedded Software Development Tools
CN109558159A (en) The update method and device of user interface in game
JP6900265B2 (en) Data analysis system and data analysis method
US10366130B2 (en) Generation of complementary applications
US20140114814A1 (en) Inventory use up on material location level
CN107135137B (en) Network group identification method and device
JP2008071160A (en) Software part providing system
US11846969B1 (en) UI state identification, navigation and crawling
JP7176434B2 (en) Information processing system, information processing device and data storage program
KR101989337B1 (en) Method and Apparatus for Displaying Real Time Wake Information in Radar System