JP2010248796A - Concrete structure and support structure supported by the same - Google Patents

Concrete structure and support structure supported by the same Download PDF

Info

Publication number
JP2010248796A
JP2010248796A JP2009099567A JP2009099567A JP2010248796A JP 2010248796 A JP2010248796 A JP 2010248796A JP 2009099567 A JP2009099567 A JP 2009099567A JP 2009099567 A JP2009099567 A JP 2009099567A JP 2010248796 A JP2010248796 A JP 2010248796A
Authority
JP
Japan
Prior art keywords
loading means
concrete structure
support structure
concrete
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2009099567A
Other languages
Japanese (ja)
Inventor
Jin Kitahara
仁 北原
Shinichi Fuji
振一 藤
Chiyuki Hironaka
千行 弘中
Mitsuru Matsuzaki
満 松崎
Narihiro Yokoyama
成弘 横山
Toshimine Ezaki
敏峰 江崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SMCTECH CO Ltd
Original Assignee
SMCTECH CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SMCTECH CO Ltd filed Critical SMCTECH CO Ltd
Priority to JP2009099567A priority Critical patent/JP2010248796A/en
Publication of JP2010248796A publication Critical patent/JP2010248796A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To surely inhibit a support structure from moving in a face direction (that is, in a direction along a surface of a concrete structure), in a state that the support structure is supported by the concrete structure. <P>SOLUTION: The concrete structure 1 is previously provided with a charge undergoing means 4 for charging a base end 3a of the support structure 3, and an insertion portion 4a<SB>1</SB>for inserting the support structure 3, and a screw-in portion 4a<SB>2</SB>for screwing in the support structure 3 are preformed along the charging/uncharging direction A of the support structure 3 in the charge undergoing means 4. A screw 3a<SB>2</SB>of the support structure 3 is screwed into the screw-in portion 4a<SB>2</SB>, so that the support structure 3 can be supported by the concrete structure 1. This can surely inhibit the movement of the concrete structure 1 in the face direction B. <P>COPYRIGHT: (C)2011,JPO&amp;INPIT

Description

本発明は、コンクリート床版等のコンクリート構造物、及び該コンクリート構造物に着脱可能に支持される支柱構造体に関する。     The present invention relates to a concrete structure such as a concrete slab and a support structure that is detachably supported by the concrete structure.

従来、コンクリート床版等のコンクリート構造物であって、支柱状の構造体を着脱可能に支持できるようにしたものについては、種々の構造のものが提案されている(例えば、特許文献1参照。)。図4は、仮設用手摺り(支柱構造体)をコンクリート床版(コンクリート構造物)に取り付けた様子の一例を示す断面図であり、符号20はコンクリート床版を示し、符号23は仮設用手摺りを示し、符号24は、コンクリート床版20を挟持して仮設用手摺り23を固定できるように構成された挟持部を示す。     2. Description of the Related Art Conventionally, concrete structures such as concrete slabs that can support a columnar structure in a detachable manner have been proposed (see, for example, Patent Document 1). ). FIG. 4 is a cross-sectional view showing an example of a state in which a temporary handrail (post structure) is attached to a concrete floor slab (concrete structure). Reference numeral 20 denotes a concrete floor slab, and reference numeral 23 denotes a temporary hand. Reference numeral 24 denotes a holding portion configured to hold the concrete floor slab 20 and fix the temporary handrail 23.

特開2003−239529号公報JP 2003-239529 A

しかしながら、上記の従来品の場合には、仮設用手摺り23が面方向(矢印Bで示す方向)に移動しないように、挟持部24の締め付け力を十分に確保しておかなければならないという問題があった。     However, in the case of the above-described conventional product, a problem that the clamping force of the clamping portion 24 must be sufficiently ensured so that the temporary handrail 23 does not move in the surface direction (direction indicated by the arrow B). was there.

本発明は、上述の問題を解消することのできるコンクリート構造物及び支柱構造体を提供することを目的とするものである。     An object of this invention is to provide the concrete structure and support | pillar structure which can eliminate the above-mentioned problem.

請求項1に係る発明は、図1(a) (b) に例示するものであって、支柱状である支柱構造体(3)を着脱可能に支持できるように構成されたコンクリート構造物(1)において、
前記支柱構造体(3)の基端部(3a)を装入できるように構成された被装入手段(4)、
を備え、
該被装入手段(4)は、前記支柱構造体(3)が挿入される挿入部(4a)と、該支柱構造体(3)が螺入される螺入部(4a)と、を前記支柱構造体(3)の装脱方向(A)に沿って有することを特徴とする。
The invention according to claim 1 is illustrated in FIGS. 1 (a) and 1 (b), and is a concrete structure (1) configured to be able to detachably support a columnar structure (3) having a columnar shape. )
Loading means (4) configured to be able to load the base end (3a) of the support structure (3),
With
The loading means (4) includes an insertion portion (4a 1 ) into which the column structure (3) is inserted and a screw portion (4a 2 ) into which the column structure (3) is screwed. It has along the loading / unloading direction (A) of the said support | pillar structure (3), It is characterized by the above-mentioned.

請求項2に係る発明は、請求項1に係る発明において、前記被装入手段(4)は、前記支柱構造体(3)を装入できる、鋼製の筒状部材であり、
前記螺入部(4a)は、前記支柱構造体(3)の基端部に形成されたネジ部(3a)に螺合され得るように突出された突起部(4c)を有することを特徴とする。
The invention according to claim 2 is the steel member according to claim 1, wherein the loading means (4) is capable of loading the support structure (3).
The threaded portion (4a 2 ) has a protruding portion (4c) protruding so as to be screwed into a threaded portion (3a 2 ) formed at a base end portion of the support structure (3). And

請求項3に係る発明は、請求項2に係る発明において、前記コンクリート構造物(1)の略全体の外形を形成する構造物本体(2)、を備え、
前記被装入手段(4)は、前記支柱構造体(3)を装入することのできる装入穴(4b)を形成した状態で前記構造物本体(2)内に埋設されてなることを特徴とする。
The invention according to claim 3 is the invention according to claim 2, further comprising a structure body (2) that forms a substantially entire outer shape of the concrete structure (1),
The loading means (4) is embedded in the structure body (2) in a state where a loading hole (4b) into which the support structure (3) can be loaded is formed. Features.

請求項4に係る発明は、請求項2に係る発明において、前記コンクリート構造物(1)の略全体の外形を形成する構造物本体(2)と、
前記コンクリート構造物(1)を吊り上げるための吊り上げ用部材(図2(a) の符号11参照)と、
を備え、
前記被装入手段(図2(a) (b) の符号14参照)は該吊り上げ用部材(11)に取り付けられてなることを特徴とする。
The invention according to claim 4 is the invention according to claim 2, wherein the structure main body (2) that forms substantially the entire outer shape of the concrete structure (1);
A lifting member (see reference numeral 11 in FIG. 2 (a)) for lifting the concrete structure (1);
With
The loading means (see reference numeral 14 in FIGS. 2 (a) and 2 (b)) is attached to the lifting member (11).

請求項5に係る発明は、請求項1に係る発明において、前記支柱構造体(3)が前記被装入手段(4)に装入された状態で、該支柱構造体(3)側のネジ部(3a)が前記被装入手段(4)側の螺入部(4a)よりも、該被装入手段(4)の奥側に配置されるように構成されたことを特徴とする。 The invention according to claim 5 is the invention according to claim 1, wherein the support structure (3) is mounted on the support structure (3) in a state where the support structure (3) is inserted in the loading means (4). The portion (3a 2 ) is configured to be arranged on the back side of the loading means (4) with respect to the threaded portion (4a 2 ) on the loading means (4) side. .

請求項6に係る発明は、請求項1乃至5のいずれか1項に記載の発明において、前記支柱構造体(3)が、複数のパイプ部材(30,31)が連結されて構成されていることを特徴とする。     The invention according to claim 6 is the invention according to any one of claims 1 to 5, wherein the support structure (3) is configured by connecting a plurality of pipe members (30, 31). It is characterized by that.

請求項7に係る発明は、前記挿入部(4a)に挿入される被挿入部(3a)と、前記螺入部(4a)に螺入されるネジ部(3a)と、を備え、
請求項1乃至6のいずれか1項に記載のコンクリート構造物(1,10)における前記被装入手段(4,14)に着脱可能に支持されることを特徴とする支柱構造体に関する。
The invention according to claim 7 includes: an insertion portion (3a 1 ) to be inserted into the insertion portion (4a 1 ); and a screw portion (3a 2 ) to be screwed into the screwing portion (4a 2 ). ,
The column structure according to any one of claims 1 to 6, wherein the concrete structure (1, 10) according to any one of claims 1 to 6 is detachably supported by the loading means (4, 14).

なお、括弧内の番号などは、図面における対応する要素を示す便宜的なものであり、従って、本記述は図面上の記載に限定拘束されるものではない。     The numbers in parentheses are for the sake of convenience indicating the corresponding elements in the drawings, and therefore the present description is not limited to the descriptions on the drawings.

請求項1,3,4,6及び7に係る発明によれば、前記装脱方向に直交する方向への支柱構造体の移動は、前記被装入手段により阻止することができる。     According to the first, third, fourth, sixth and seventh aspects of the present invention, movement of the column structure in a direction orthogonal to the loading / unloading direction can be prevented by the loading means.

請求項2に係る発明によれば、突起部はポンチ加工により簡単に形成できるので、被装入手段の製造が簡単になるという効果を奏する。     According to the invention which concerns on Claim 2, since a projection part can be easily formed by punching, there exists an effect that manufacture of a to-be-inserted means becomes easy.

請求項5に係る発明によれば、支柱構造体が被装入手段に確実に支持されているかは、支柱構造体を軸方向に往復動させるだけで簡単に確認することができる。     According to the invention which concerns on Claim 5, it can be confirmed easily only by reciprocating the support | pillar structure to an axial direction whether the support | pillar structure is reliably supported by the to-be-inserted means.

図1(a) は、本発明に係るコンクリート構造物等の構造の一例を示す断面図であり、同図(b)は、その拡大断面図である。Fig.1 (a) is sectional drawing which shows an example of structures, such as a concrete structure based on this invention, The same figure (b) is the expanded sectional view. 図2(a) は、本発明に係るコンクリート構造物等の構造の他の例を示す断面図であり、同図(b)は、被装入手段の外観を示す斜視図である。FIG. 2 (a) is a sectional view showing another example of the structure of a concrete structure or the like according to the present invention, and FIG. 2 (b) is a perspective view showing the appearance of the loading means. 図3(a) 〜(c) は、支柱構造体の装入状態の種々の態様を示す断面図である。3 (a) to 3 (c) are cross-sectional views showing various modes of the state in which the support structure is inserted. 図4は、仮設用手摺り(支柱構造体)をコンクリート床版(コンクリート構造物)に取り付けた様子の一例を示す断面図である。FIG. 4 is a cross-sectional view showing an example of a state in which a temporary handrail (post structure) is attached to a concrete slab (concrete structure).

以下、図1乃至図3に沿って、本発明の実施の形態について説明する。     Hereinafter, embodiments of the present invention will be described with reference to FIGS. 1 to 3.

本発明に係るコンクリート構造物は、支柱状の構造体(以下、“支柱構造体”とする)を着脱可能に支持できるように構成されている。なお、本明細書におけるコンクリート構造物とは、コンクリート製の床版や壁や梁や柱等を含む概念であり、工場で製造する物(いわゆるプレキャスト製品)だけでなく、現場で製造する物(いわゆる現場打ち品)も含む概念である。また、本明細書における支柱構造体とは、
・ 建物を構築する際に床版に一時的に立設される仮設用手摺りや、
・ 建物を構築する際に床版や壁や柱に一時的に取り付けられる支柱
などを含む概念である。
The concrete structure according to the present invention is configured to be able to detachably support a columnar structure (hereinafter referred to as a “column structure”). In addition, the concrete structure in this specification is a concept including a concrete floor slab, a wall, a beam, a pillar, etc., and not only a thing manufactured at a factory (so-called precast product) but also a thing manufactured on the spot ( This is a concept including so-called on-site products. Moreover, with the support | pillar structure in this specification,
-Temporary handrails that are temporarily set up on the floor slab when building a building,
・ This concept includes floor slabs and columns that are temporarily attached to walls and pillars when building a building.

本発明に係るコンクリート構造物は、図1(a) (b) に符号1で例示するものであって、
・ 該コンクリート構造物1の略全体の外形を形成する構造物本体2(例えば、コンクリートや鉄筋で構成された複合体)と、
・ 支柱構造体3の基端部3aを装入できるように構成された被装入手段4と、
を備えている。そして、この被装入手段4は、前記支柱構造体3の装脱方向Aに沿って、
・ 前記支柱構造体3が挿入される挿入部4aと、
・ 該支柱構造体3が螺入される螺入部4aと、
を有している。図1(a) (b) に示す被装入手段4は、前記支柱構造体3を装入できる、鋼製の筒状部材であって、前記支柱構造体3を装入することのできる装入穴4bを形成した状態で前記構造物本体内に埋設されている。なお、コンクリート構造物がプレキャスト製品の場合には、該構造物をクレーンで吊り上げるための吊り上げ用部材(例えば、吊り上げ用のアイボルトを螺合するためのナット部材。図2(a)
の符号11参照)が構造物本体中に埋設されているのが一般的であるが、その吊り上げ用部材11(つまり、吊り上げ作業が終了してアイボルトが外された状態の吊り上げ用部材)に被装入手段14(例えば、前記支柱構造体3を装入できる、鋼製の筒状部材)を取り付けるようにしても良い。この場合の被装入手段は、図2(b)
に詳示するように、
・ 吊り上げ用部材11に螺合されるボルト部14aと、
・ 鋼製の筒状部材14bと、
により構成すると良い。そして、該筒状部材14bには、上述の挿入部や螺入部を設けておくと良い。
The concrete structure according to the present invention is exemplified by reference numeral 1 in FIGS. 1 (a) and 1 (b).
A structure main body 2 (for example, a composite composed of concrete or reinforcing bar) that forms the outer shape of substantially the entire concrete structure 1;
A loading means 4 configured to be able to load the base end portion 3a of the column structure 3;
It has. And this loading means 4 is along the loading / unloading direction A of the said column structure 3,
An insertion portion 4a 1 into which the support structure 3 is inserted;
A screw-in part 4a 2 into which the column structure 3 is screwed;
have. The loading means 4 shown in FIGS. 1 (a) and 1 (b) is a steel tubular member that can be loaded with the column structure 3, and can be loaded with the column structure 3. It is embedded in the structure body in a state where the entry hole 4b is formed. When the concrete structure is a precast product, a lifting member for lifting the structure with a crane (for example, a nut member for screwing a lifting eyebolt. FIG. 2 (a).
Is generally embedded in the main body of the structure, but the lifting member 11 (that is, the lifting member after the lifting operation is finished and the eyebolt is removed) is covered. You may make it attach the insertion means 14 (For example, the cylindrical member made from steel which can insert the said support | pillar structure 3). The loading means in this case is shown in FIG.
As detailed in
A bolt part 14a screwed to the lifting member 11,
A steel tubular member 14b;
It is good to comprise. And it is good to provide the above-mentioned insertion part and screwing part in this cylindrical member 14b.

ところで、上述の螺入部4aは、支柱構造体3の基端部に形成されたネジ部3aに螺合されるようなネジ部にしても良いが、図1(b) に符号4cで示すような突起部としても良い。そのような突起部4cはポンチ加工により簡単に形成できるので、被装入手段4の製造が簡単になるという効果を奏する。 Meanwhile, screw-join the club 4a 2 of the above may be the threaded portion, such as screwed into the screw portion 3a 2 formed at the base end portion of the bearing structure 3, but reference numeral 4c in FIG. 1 (b) It is good also as a projection part as shown. Since such a protrusion 4c can be easily formed by punching, there is an effect that the manufacture of the loading means 4 is simplified.

図1(a) (b) や図2(a) (b) に示すコンクリート構造物1,10では、被装入手段4,14の内部に支柱構造体3を装入するように構成されているが、その逆の構成(被装入手段の側にではなく支柱構造体の側に装入穴を形成しておいて、被装入手段を支柱構造体の装入穴に装入する構成)にしても良い。したがって、本明細書における“装入”とは、その両者、つまり、
・ 図1(a) (b) 及び図2(a) に示すように、被装入手段4,14に支柱構造体3を入れることによって該支柱構造体3を装着する態様と、
・ その逆の態様(つまり、支柱構造体に被装入手段を入れることによって該支柱構造体を装着する態様)
の両方を含む概念である。また、本明細書における“挿入”とは、
・ 図1(a) (b) 及び図2(a) に示すように、被装入手段4,14に支柱構造体3を挿し込むことによって入れる態様と、
・ その逆の態様(つまり、支柱構造体に被装入手段を挿し込むことによって入れる態様)
の両方を含む概念であって、挿入部にて被装入手段と支柱構造体とが接触しているか否かは問わない。さらに、本明細書における“螺入”とは、
・ 図1(a) (b) 及び図2(a) に示すように、支柱構造体3を被装入手段4,14にねじ入れる態様と、
・ その逆の態様(つまり、被装入手段を支柱構造体にねじ入れる態様)
の両方を含む概念である。
The concrete structures 1 and 10 shown in FIGS. 1 (a) and 1 (b) and FIGS. 2 (a) and 2 (b) are configured to insert the column structure 3 into the loading means 4 and 14. However, the opposite configuration (a configuration in which a loading hole is formed not on the loading means side but on the column structure side, and the loading means is loaded into the loading hole of the column structure body. ). Therefore, “charging” in this specification means both of them, that is,
As shown in FIGS. 1 (a), 1 (b) and 2 (a), a mode in which the support structure 3 is mounted by inserting the support structure 3 into the loading means 4 and 14;
-The reverse mode (that is, the mode in which the column structure is mounted by inserting the loading means into the column structure)
It is a concept that includes both. In addition, “insertion” in this specification means
As shown in FIGS. 1 (a), (b) and 2 (a), a mode in which the support structure 3 is inserted into the loading means 4 and 14, and
・ The reverse mode (that is, the mode of inserting by inserting the loading means into the column structure)
It is a concept including both of the above, and it does not matter whether the loading means and the support structure are in contact with each other at the insertion portion. Furthermore, “screwing” in this specification means
As shown in FIGS. 1 (a), 1 (b) and 2 (a), the column structure 3 is screwed into the loading means 4 and 14, and
・ The reverse mode (that is, the mode in which the loading means is screwed into the column structure)
It is a concept that includes both.

なお、上述のような被装入手段4,14に装入する支柱構造体3の基端部には、
・ 該被装入手段4,14の挿入部(図1(b) の符号4a参照)に挿入される被挿入部(同図の符号3a参照)と、
・ 該被装入手段4,14の螺入部(図1(b) の符号4a参照)に螺合されるネジ部(同図の符号3a参照)と、
を形成しておくと良い。この場合、被装入手段側の螺入部の長さ寸法(符号4aで示す寸法)と、支柱構造体側のネジ部の長さ寸法(符号3aで示す寸法)とを短くしておけば(つまり、ピッチ数を少なくしておけば)、支柱構造体3を装脱着する際に回す回数を少なくでき、その作業を容易にすることができる。この支柱構造体は、単一の部材(例えば、1本のパイプ部材)で構成しても良いが、複数の部材(例えば、複数のパイプ部材)を連結して構成しても良い。図1(a) に示す支柱構造体は複数の部材で構成されており、符号30は、両端にネジが切られた連結パイプを示し、符号31は、いわゆる単管パイプを示す。このような連結パイプ30を使用すれば、色々な長さの単管パイプを接続し、支柱構造体の長さを自由に変更できる。
In addition, in the base end part of the column structure 3 to be loaded into the loading means 4 and 14 as described above,
An inserted portion (see reference numeral 3a 1 in the figure) to be inserted into the insertion part of the loading means 4 and 14 (see reference numeral 4a 1 in FIG. 1B);
· Threaded join the club of該被charging means 4, 14 (see reference numeral 3a 2 of the drawing) screw portion to be screwed in (numeral 4a see 2 in FIG. 1 (b)),
It is good to form. In this case, the length of the threaded join the club of HiSoIri means side (dimension indicated by reference numeral 4a 2), if a shorter and length of the threaded portion of the pillar structure side (dimension indicated by reference numeral 3a 2) (That is, if the number of pitches is reduced), the number of rotations when attaching and detaching the support structure 3 can be reduced, and the work can be facilitated. Although this support | pillar structure may be comprised with a single member (for example, one pipe member), you may comprise it by connecting a some member (for example, several pipe member). The strut structure shown in FIG. 1 (a) is composed of a plurality of members. Reference numeral 30 indicates a connecting pipe with screws at both ends, and reference numeral 31 indicates a so-called single pipe. If such a connection pipe 30 is used, single pipe pipes of various lengths can be connected, and the length of the column structure can be freely changed.

ところで、支柱構造体側のネジ部3aは、当然ながら、被装入手段4に装入する際に螺入部4aに螺合される位置に形成されている必要がある。例えば、ネジ部3aが、図3(a) に示すように支柱構造体3の先端(図では下端)に形成されている場合には、螺入部4aは被装入手段4の奥側(図では下側)に形成しておく必要があり、ネジ部3aが図3(b)
に示す位置(つまり、先端よりも少し離れた位置)に形成されている場合には、螺入部4aは、それに対応した位置に形成しておく必要がある。さらには、図3(c)
に示すように、前記支柱構造体3が前記被装入手段4に装入された状態で、該支柱構造体側のネジ部3aが前記被装入手段側の螺入部4aよりも、該被装入手段4の奥側に配置されるように構成しても良い。以下、このような構成の効果について説明する。
Incidentally, the screw portion 3a 2 on the column structure side needs to be formed at a position where the screw portion 3a 2 is screwed to the screw portion 4a 2 when the screw portion 3a 2 is inserted into the loading means 4. For example, the screw portion 3a 2 is, if (in the figure the lower end) distal end of the bearing structure 3, as shown in FIG. 3 (a) is formed on the inner side of the threaded join the club 4a 2 is HiSoIri means 4 (The lower side in the figure) needs to be formed, and the screw portion 3a 2 is formed in FIG.
Position shown in (i.e., a position slightly away from the tip) when it is formed, the threaded join the club 4a 2, it is necessary to form at positions corresponding thereto. Furthermore, FIG. 3 (c)
As shown in FIG. 4, in the state in which the column structure 3 is inserted into the loading means 4, the screw portion 3a 2 on the column structure side is more than the screw portion 4a 2 on the loading means side. You may comprise so that it may arrange | position to the back side of the to-be-inserted means 4. FIG. Hereinafter, the effect of such a configuration will be described.

いま、図3(a) や(b) に示す構造のものでは、支柱構造体3がコンクリート構造物1に装着されている時は支柱構造体3のネジ部3aは被装入手段4の螺入部4aに螺合されることとなる。この場合、ネジ部3aが螺入部4aに ほんの少しだけ係止されてさえいれば、支柱構造体3は被装入手段4から抜けることは無いが、該支柱構造体3が僅かに回転されただけでネジ部3aと螺入部4aとの係合が外れてしまうおそれもある。そして、ネジ部3aと螺入部4aとが確実に係合状態にあるかどうかを確かめるには、支柱構造体3を掴んで“閉じ方向”に強く回転させる必要があり、その作業が煩雑であるという問題がある。これに対し、図3(c)
に示すような構成にすれば、支柱構造体3がコンクリート構造物1に装着されている時は支柱構造体3のネジ部3aは被装入手段4の螺入部4aに螺合されてはおらず、該支柱構造体3は 矢印Aに示す方向に 上下に僅かながらも“遊び”がある状態となる(当然ながら、支柱構造体3における、ネジ部3a以外の部分と螺入部4aとの間に隙間が形成されている必要がある)。つまり、矢印Aで示す方向に支柱構造体3を上下動させれば 該支柱構造体3は動くものの、被装入手段4から抜け出ることは無いという状態になる。したがって、支柱構造体3を抜こうとして抜けなければ、該支柱構造体3は被装入手段4に確実に支持されていることとなり、その確認作業を容易に行えるという効果がある。なお、その場合、支柱構造体3は、被装入手段4に支持されている状態でも軸方向Aには多少移動することとなるが、そのような遊びが問題にならない場合も多い。例えば、図1(a)
に示すように、コンクリート構造物としてのコンクリート床版1の端縁部に被装入手段4を設け、該被装入手段4に支柱構造体3を立設させて仮設の手摺りと利用するような場合は、該支柱構造体3には、水平方向の力や下方向の力は作用するものの、上方向の力は作用しないのが普通である。したがって、このような使用態様の場合には、図3(c)
に示すような構造は適している。
Now, in the structure shown in FIGS. 3 (a) and 3 (b), when the support structure 3 is attached to the concrete structure 1, the threaded portion 3 a 2 of the support structure 3 is attached to the loading means 4. so that the screwed into threaded join the club 4a 2. In this case, as long as the screw part 3a 2 is only slightly locked to the screw part 4a 2 , the support structure 3 will not come out of the loading means 4, but the support structure 3 will rotate slightly. There is a possibility that the engagement between the screw portion 3a 2 and the screw-in portion 4a 2 is disengaged only by being done. Then, check if the screw portion 3a 2 and the threaded join the club 4a 2 is securely in the engaged state, it is necessary to rotate strongly to "closing direction" grabbed bearing structure 3, complicated the work There is a problem that. In contrast, Fig. 3 (c)
If the configuration as shown in, when the bearing structure 3 is attached to the concrete structure 1 is screw part 3a 2 of the bearing structure 3 is screwed into threaded join the club 4a 2 of HiSoIri means 4 The support structure 3 is in a state where there is a slight “play” in the direction shown by the arrow A (naturally, the support structure 3 is not provided with the screw portion 3a 2 and the screw-in portion 4a 2. Need to have a gap between them). That is, if the column structure 3 is moved up and down in the direction indicated by the arrow A, the column structure 3 moves, but does not come out of the loading means 4. Therefore, if the column structure 3 is not pulled out without being pulled out, the column structure 3 is surely supported by the loading means 4, and the confirmation work can be easily performed. In this case, the column structure 3 moves somewhat in the axial direction A even when it is supported by the loading means 4, but such play often does not become a problem. For example, Fig. 1 (a)
As shown in FIG. 4, the loading means 4 is provided at the edge of the concrete floor slab 1 as a concrete structure, and the column structure 3 is erected on the loading means 4 to be used as a temporary handrail. In such a case, although a horizontal force and a downward force are applied to the support structure 3, an upward force is generally not applied. Therefore, in the case of such a usage mode, FIG.
A structure as shown in FIG.

1 コンクリート構造物
2 構造物本体
3 支柱構造体
3a 基端部
3a 被挿入部
3a ネジ部
4 被装入手段
4a 挿入部
4a 螺入部
4b 装入穴
4c 突起部
10 コンクリート構造物
11 吊り上げ用部材
14 被装入手段
30 パイプ部材
31 パイプ部材
A 支柱構造体の装脱方向
DESCRIPTION OF SYMBOLS 1 Concrete structure 2 Structure main body 3 Support | pillar structure 3a Base end part 3a 1 Insertion part 3a 2 Screw part 4 Insertion means 4a 1 Insertion part 4a 2 Screw part 4b Insertion hole 4c Protrusion part 10 Concrete structure 11 Lifting member 14 Inserting means 30 Pipe member 31 Pipe member A Loading direction of support structure

Claims (7)

支柱状である支柱構造体を着脱可能に支持できるように構成されたコンクリート構造物において、
前記支柱構造体の基端部を装入できるように構成された被装入手段、
を備え、
該被装入手段は、前記支柱構造体が挿入される挿入部と、該支柱構造体が螺入される螺入部と、を前記支柱構造体の装脱方向に沿って有する、
ことを特徴とするコンクリート構造物。
In a concrete structure configured to be able to detachably support a pillar structure that is in the form of a pillar,
A loading means configured to be able to load a base end portion of the support structure;
With
The loading means has an insertion portion into which the column structure is inserted and a screw-in portion into which the column structure is screwed along the loading / unloading direction of the column structure.
A concrete structure characterized by that.
前記被装入手段は、前記支柱構造体を装入できる、鋼製の筒状部材であり、
前記螺入部は、前記支柱構造体の基端部に形成されたネジ部に螺合され得るように突出された突起部を有する、
ことを特徴とする請求項1に記載のコンクリート構造物。
The loading means is a steel tubular member that can be loaded with the strut structure.
The screwed portion has a protruding portion that protrudes so as to be screwed into a screw portion formed at a base end portion of the support structure.
The concrete structure according to claim 1.
前記コンクリート構造物の略全体の外形を形成する構造物本体、を備え、
前記被装入手段は、前記支柱構造体を装入することのできる装入穴を形成した状態で前記構造物本体内に埋設されてなる、
ことを特徴とする請求項2に記載のコンクリート構造物。
A structure main body that forms an outer shape of substantially the entire concrete structure;
The loading means is embedded in the structure body in a state where a loading hole into which the support structure can be loaded is formed.
The concrete structure according to claim 2, wherein:
前記コンクリート構造物の略全体の外形を形成する構造物本体と、
前記コンクリート構造物を吊り上げるための吊り上げ用部材と、
を備え、
前記被装入手段は該吊り上げ用部材に取り付けられてなる、
ことを特徴とする請求項2に記載のコンクリート構造物。
A structure main body forming an outline of substantially the whole of the concrete structure;
A lifting member for lifting the concrete structure;
With
The loading means is attached to the lifting member.
The concrete structure according to claim 2, wherein:
前記支柱構造体が前記被装入手段に装入された状態で、該支柱構造体側のネジ部が前記被装入手段側の螺入部よりも、該被装入手段の奥側に配置されるように構成された、
ことを特徴とする請求項1に記載のコンクリート構造物。
In a state in which the support structure is inserted into the loading means, the threaded portion on the support structure side is disposed further to the back of the loading means than the screwed portion on the loading means side. Configured as
The concrete structure according to claim 1.
前記支柱構造体は、複数のパイプ部材が連結されて構成されている、
ことを特徴とする請求項1乃至5のいずれか1項に記載のコンクリート構造物。
The support structure is configured by connecting a plurality of pipe members,
The concrete structure according to any one of claims 1 to 5, wherein:
前記挿入部に挿入される被挿入部と、前記螺入部に螺入されるネジ部と、を備え、
請求項1乃至6のいずれか1項に記載のコンクリート構造物における前記被装入手段に着脱可能に支持される、
ことを特徴とする支柱構造体。
An inserted portion to be inserted into the insertion portion, and a screw portion to be screwed into the screwing portion,
It is detachably supported by the loading means in the concrete structure according to any one of claims 1 to 6.
A support structure characterized by that.
JP2009099567A 2009-04-16 2009-04-16 Concrete structure and support structure supported by the same Pending JP2010248796A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009099567A JP2010248796A (en) 2009-04-16 2009-04-16 Concrete structure and support structure supported by the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009099567A JP2010248796A (en) 2009-04-16 2009-04-16 Concrete structure and support structure supported by the same

Publications (1)

Publication Number Publication Date
JP2010248796A true JP2010248796A (en) 2010-11-04

Family

ID=43311427

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009099567A Pending JP2010248796A (en) 2009-04-16 2009-04-16 Concrete structure and support structure supported by the same

Country Status (1)

Country Link
JP (1) JP2010248796A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457483A (en) * 2018-05-25 2018-08-28 深圳市建设(集团)有限公司 A kind of multifunctional universal pre-embedded device and application method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55135763U (en) * 1979-03-22 1980-09-26
JPH02186054A (en) * 1989-01-11 1990-07-20 Sanyo Kokusaku Pulp Co Ltd Execution method for basic pillar
JPH0598800A (en) * 1991-10-11 1993-04-20 Ohbayashi Corp Anchoring of handrail for opening curing and its fixture
JPH0732111U (en) * 1993-11-19 1995-06-16 丸井産業株式会社 Mounting bracket for handrail support for construction
JPH0913689A (en) * 1995-06-30 1997-01-14 Kunimoto Shokai:Kk Installing device of temporary safe handrail

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55135763U (en) * 1979-03-22 1980-09-26
JPH02186054A (en) * 1989-01-11 1990-07-20 Sanyo Kokusaku Pulp Co Ltd Execution method for basic pillar
JPH0598800A (en) * 1991-10-11 1993-04-20 Ohbayashi Corp Anchoring of handrail for opening curing and its fixture
JPH0732111U (en) * 1993-11-19 1995-06-16 丸井産業株式会社 Mounting bracket for handrail support for construction
JPH0913689A (en) * 1995-06-30 1997-01-14 Kunimoto Shokai:Kk Installing device of temporary safe handrail

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457483A (en) * 2018-05-25 2018-08-28 深圳市建设(集团)有限公司 A kind of multifunctional universal pre-embedded device and application method

Similar Documents

Publication Publication Date Title
KR101456825B1 (en) Reinforcing bar coupler with pair of locking piece and connecting method of pre-assembled rebar cage using thereof
JP2008150940A (en) Anti-rotational adhesive insert
KR100977804B1 (en) Gang form
KR20100078070A (en) Supporter for slab form of concrete structure
JP2009121083A (en) Precast beam-column connection structure
JP2014055517A (en) Precast beam-column joint structure
JP2007146641A (en) Structure of joining part of precast concrete member, precast concrete assembly structure with the joining part, and method of forming the structure
JP2010248796A (en) Concrete structure and support structure supported by the same
JP2009133114A (en) Reinforcement structure of pole member with wall
JP2009102909A (en) Embedded hardware and method of mounting the same
US20190195255A1 (en) Accessory attachment structure for steel plate-reinforced concrete structure, design system and design method of steel plate-reinforced concrete structure, consruction method of steel plate-reinforced concrete structure, and steel plate-reinforced concrete structure
JP2008274570A (en) Precast concrete column, and method for joining precast concrete column and precast concrete beam together
JP5796940B2 (en) Method for joining concrete members
JP5867693B2 (en) Snake insert anchor bolt
JP2006342497A (en) Foundation structure of steel column base
JP5582566B2 (en) Wall panels
JP4111981B2 (en) Cylindrical sleeve for through-hole formation
JP2009102981A (en) Prestressed concrete structure
JP2008106516A (en) Support pipe bearing device
JP2005232750A (en) Reinforcing fitting for concrete structure
JP2007262715A (en) Reinforcing metal
JP7246971B2 (en) Column base hardware and column base structure
JP2011089370A (en) Joint structure of precast concrete beam member
JP2004353244A (en) Joint structure of steel pipe column and foundation
JP2009041327A (en) Spacer of form for construction

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120229

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130318

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130326

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20130806