JP2007285659A - Hot water supply device - Google Patents

Hot water supply device Download PDF

Info

Publication number
JP2007285659A
JP2007285659A JP2006116224A JP2006116224A JP2007285659A JP 2007285659 A JP2007285659 A JP 2007285659A JP 2006116224 A JP2006116224 A JP 2006116224A JP 2006116224 A JP2006116224 A JP 2006116224A JP 2007285659 A JP2007285659 A JP 2007285659A
Authority
JP
Japan
Prior art keywords
hot water
boiling
amount
time
water supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2006116224A
Other languages
Japanese (ja)
Inventor
克也 ▲桑▼木
Katsuya Kuwaki
Koji Senda
孝司 千田
Shigehiko Matsuoka
滋彦 松岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daikin Industries Ltd
Original Assignee
Daikin Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daikin Industries Ltd filed Critical Daikin Industries Ltd
Priority to JP2006116224A priority Critical patent/JP2007285659A/en
Publication of JP2007285659A publication Critical patent/JP2007285659A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Heat-Pump Type And Storage Water Heaters (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a hot water supply device for avoiding the run-out of hot water even when serving hot water to be supplied in a midnight time zone. <P>SOLUTION: The hot water supply device 1 uses a heating means for heating water and a hot water storage tank 31 for storing hot water produced with the boiling-up operation. It comprises heat quantity data acquiring means T6-T13, 40, 42, P3, a heat quantity data recording means 62, a data calculating means 61, and a boiling-up operation time control means 66. The heat quantity data acquiring means acquire heat quantity data for hot water served by users. The data calculating means calculates the heat quantity of hot water predicted to be served on the day by time zones in accordance with the heat quantity data recorded by the heat quantity data recording means and calculates a boiling-up operation time required for boiling-up operation in accordance with the heat quantity of hot water predicted to be served. The boiling-up operation time control means determines a boiling-up starting time to execute boiling-up operation in a predetermined time zone in accordance with the boiling-up operation time. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

使用する湯量を学習する給湯装置に関する。   The present invention relates to a hot water supply device that learns the amount of hot water to be used.

従来、深夜電力時間帯などの所定時間帯に貯湯タンク内の温湯を沸き上げて貯湯し、貯湯タンク内に貯湯された温湯を給湯する給湯装置がある。このような給湯装置には、所定時間帯の終了の直前に沸き上げが完了するように、所定時間帯の開始時点よりも沸き上げ開始を遅らせるピークシフト制御を行うものがある。このピークシフト制御は、所定時間帯の開始時点に電力使用が集中するのを防止するとともに、貯湯タンク内の温湯を沸き上げた後の放熱による温度低下を極力防止するために行われている。   2. Description of the Related Art Conventionally, there is a hot water supply device that boils hot water in a hot water storage tank and stores hot water in a predetermined time zone such as a midnight power time zone, and supplies hot water stored in the hot water storage tank. Some hot water supply apparatuses perform peak shift control that delays the start of boiling from the start time of the predetermined time period so that the boiling is completed immediately before the end of the predetermined time period. This peak shift control is performed to prevent concentration of power use at the start of a predetermined time zone and to prevent temperature drop due to heat dissipation after boiling hot water in the hot water storage tank as much as possible.

特許文献1の技術では、設定された残湯熱量レベルから残湯熱量が少なくなると、残湯熱量が残湯熱量レベルになるまで沸き上げ運転を行っている。
特開2005−76940号公報
In the technique of Patent Document 1, when the remaining hot water calorie decreases from the set remaining hot water calorie level, the boiling operation is performed until the remaining hot water calorie reaches the remaining hot water calorie level.
JP 2005-76940 A

しかしながら、深夜時間帯(シフト中やシフト後の沸き上げ運転中)に給湯の使用があった場合に、深夜時間帯の残り時間(朝まで)では沸き上がらない場合がある。これは、沸き上げ時間を深夜時間帯移行時の残湯熱量から推定するためである。このため湯切れや電気代の高い昼間時間帯に沸き上げ運転を行う恐れがある。
特許文献1の技術では、このような場合に、残湯熱量レベル以下になるため残湯熱量レベル以上まで沸き上げ運転を行わせることにより、湯切れが起こらないようにしている。しかし、残湯熱量レベルが下がった後に沸き上げ運転を行っているために、深夜時間帯の給湯負荷があった場合に、深夜時間帯が終わるまでに沸き上げ運転を終了させることができなくなる恐れがある。
However, when hot water is used during the midnight hours (during the shift or during the heating operation after the shift), the boiling may not occur during the remaining time (until morning) of the midnight hours. This is because the boiling time is estimated from the amount of remaining hot water at the time of shifting to the midnight time zone. For this reason, there is a risk of boiling-up operation during daytime hours when hot water runs out and electricity costs are high.
In the technique of Patent Document 1, in such a case, since the remaining hot water calorie level is lower than the remaining hot water calorie level, the boiling operation is performed to a level higher than the remaining hot water calorie level so that hot water does not run out. However, because the boiling operation is performed after the remaining hot water calorie level is lowered, there is a risk that the boiling operation cannot be completed by the end of the midnight hours when there is a hot water supply load in the midnight hours There is.

本発明の課題は、深夜時間帯に給湯の使用があった場合においても、湯切れを回避することができる給湯装置を提供することにある。   An object of the present invention is to provide a hot water supply apparatus that can avoid hot water shortage even when hot water is used in the midnight time zone.

第1発明に係る給湯装置は、加熱手段によって水を加熱する沸き上げ運転によりできた温水を貯湯タンクに貯湯する給湯装置であって、熱量データ取得手段と、熱量データ記録手段と、データ算出手段と、沸き上げ運転時間制御手段とを備える。熱量データ取得手段は、ユーザが使用した温水の熱量データを取得する。熱量データ記録手段は、熱量データ取得手段により取得された熱量データを時間帯別に記録する。データ算出手段は、熱量データ記録手段に記録された熱量データに基づいて貯湯タンク内の残湯熱量と当日の時間帯別の予測使用熱量とを算出し、残湯熱量と予測使用湯熱量とに基づいて沸き上げ運転に必要な沸き上げ運転時間を算出する。
沸き上げ運転時間制御手段は、沸き上げ運転時間に基づいて、所定時間帯に沸き上げ運転を行うように沸き上げ運転の沸き上げ開始時刻を決定する。
A hot water supply apparatus according to a first aspect of the present invention is a hot water supply apparatus for storing hot water produced by a boiling operation in which water is heated by a heating means in a hot water storage tank, wherein the calorific data acquisition means, the calorific data recording means, and the data calculation means. And a boiling operation time control means. The calorie data acquisition means acquires the calorific data of the hot water used by the user. The heat quantity data recording means records the heat quantity data acquired by the heat quantity data acquisition means for each time zone. The data calculating means calculates the amount of remaining hot water in the hot water storage tank and the predicted amount of heat used according to the time zone of the day based on the amount of heat data recorded in the heat amount data recording means. Based on this, the boiling operation time required for the boiling operation is calculated.
The boiling operation time control means determines the boiling start time of the boiling operation based on the boiling operation time so that the boiling operation is performed in a predetermined time zone.

本発明では、過去の給湯負荷の時間帯別のデータにより、当日の時間帯別の給湯負荷を予測している。そして、沸き上げ開始時刻を演算する際、予測給湯負荷に基づいて必要な沸き上げ運転時間を算出し、沸き上げ開始時刻を決定している。
これにより、深夜時間帯に給湯負荷がある場合にも、深夜時間帯に沸き上げが終了するように沸き上げ運転を行うため、電気代を低減できる。このため、エネルギーを節約することができる。また、深夜時間帯の給湯負荷を考慮して沸き上げ量を決定しているため湯切れが起こるのを低減させることができる。
In this invention, the hot water supply load according to the time zone of the day is estimated by the data according to the time zone of the past hot water supply load. Then, when calculating the boiling start time, the required boiling operation time is calculated based on the predicted hot water supply load, and the boiling start time is determined.
Thereby, even when there is a hot water supply load in the midnight hours, the heating operation is performed so that the boiling is completed in the midnight hours, so that the electricity bill can be reduced. For this reason, energy can be saved. Moreover, since the amount of boiling is determined in consideration of the hot water supply load in the midnight hours, it is possible to reduce the occurrence of hot water shortage.

第2発明に係る給湯装置は、第1発明に係る給湯装置であって、沸き上げ運転時間制御手段は、所定時間帯の終了時刻に沸き上げ運転が終了するように沸き上げ開始時刻を決定する。
この給湯装置では、所定時間帯の終了時刻に沸き上げ運転が終了するように沸き上げ開始時刻を決定している。このため、所定時間帯の開始時点に電力使用が集中するのを防止することができる。また、貯湯タンクの温湯を沸き上げた後の放熱による温度低下を極力防ぐことができる。
A hot water supply apparatus according to a second aspect of the present invention is the hot water supply apparatus according to the first aspect of the present invention, wherein the boiling operation time control means determines the boiling start time so that the boiling operation ends at the end time of the predetermined time zone. .
In this hot water supply apparatus, the boiling start time is determined so that the boiling operation ends at the end time of the predetermined time period. For this reason, it can prevent that electric power use concentrates on the start time of a predetermined time slot | zone. Moreover, the temperature fall by the heat radiation after boiling the hot water of a hot water storage tank can be prevented as much as possible.

第3発明に係る給湯装置は、第1発明または第2発明に係る給湯装置であって、データ算出手段は、残湯熱量と所定時間帯以外の時間帯における予測使用湯熱量と所定時間帯における予測使用湯熱量とに基づいて前記沸き上げ運転時間を算出する
この給湯装置では、沸き上げ運転を行う深夜時間帯の使用量を考慮して沸き上げ運転時間を決定しているため、沸き上げ運転を行っているときに、給湯の利用があっても適切な量の温湯を沸かすことができる。
A hot water supply apparatus according to a third aspect of the invention is the hot water supply apparatus according to the first or second aspect of the invention, wherein the data calculating means is the amount of heat of predicted hot water used in the time zone other than the remaining hot water heat amount and the predetermined time zone and the predetermined time zone. The boiling operation time is calculated based on the predicted amount of hot water used. In this hot water supply device, the boiling operation time is determined in consideration of the amount used in the midnight hours when the boiling operation is performed. When performing hot water, an appropriate amount of hot water can be boiled even if hot water is used.

第1発明に係る給湯装置では、深夜時間帯に給湯負荷がある場合にも、深夜時間帯に沸き上げが終了するように沸き上げ運転を行うため、電気代を低減できる。このため、エネルギーを節約することができる。また、深夜時間帯の給湯負荷を考慮して沸き上げ量を決定しているため湯切れが起こるのを低減させることができる。
第2発明に係る給湯装置では、所定時間帯の開始時点に電力使用が集中するのを防止することができる。また、貯湯タンクの温湯を沸き上げた後の放熱による温度低下を極力防ぐことができる。
In the hot water supply apparatus according to the first aspect of the invention, even when there is a hot water supply load in the midnight time zone, the heating operation is performed so that the boiling is completed in the midnight time zone, so the electricity cost can be reduced. For this reason, energy can be saved. Moreover, since the amount of boiling is determined in consideration of the hot water supply load in the midnight hours, it is possible to reduce the occurrence of hot water shortage.
In the hot water supply apparatus according to the second aspect of the present invention, it is possible to prevent power usage from concentrating at the start time of the predetermined time zone. Moreover, the temperature fall by the heat radiation after boiling the hot water of a hot water storage tank can be prevented as much as possible.

第3発明に係る給湯装置では、沸き上げ運転を行う深夜時間帯の使用量を考慮して沸き上げ運転時間を決定しているため、沸き上げ運転を行っているときに、給湯の利用があっても適切な量の温湯を沸かすことができる。   In the hot water supply apparatus according to the third aspect of the invention, the boiling operation time is determined in consideration of the amount of use in the midnight time zone during which the boiling operation is performed. Even an appropriate amount of hot water can be boiled.

以下、図面に基づいて、本発明に係る給湯装置1の実施形態について説明する。
<ヒートポンプ給湯機の構成>
図1は、本発明の一実施形態に係る給湯装置1の概略構成図である。給湯装置1は、CO2冷媒を用いて蒸気圧縮式の冷凍サイクル運転を行うことによって、水道水を加熱し家庭の浴槽5などに温湯を供給する装置である。給湯装置1は、主として、温湯を貯める貯湯タンク31を有する貯湯ユニット3と、冷媒回路20を有するヒートポンプユニット2とを備えている。
Hereinafter, an embodiment of a hot water supply apparatus 1 according to the present invention will be described based on the drawings.
<Configuration of heat pump water heater>
FIG. 1 is a schematic configuration diagram of a hot water supply apparatus 1 according to an embodiment of the present invention. The hot water supply device 1 is a device that heats tap water and supplies hot water to the bathtub 5 at home by performing a vapor compression refrigeration cycle operation using CO2 refrigerant. The hot water supply device 1 mainly includes a hot water storage unit 3 having a hot water storage tank 31 for storing hot water and a heat pump unit 2 having a refrigerant circuit 20.

(1)貯湯ユニット
図2は貯湯ユニット3の概略図である。貯湯ユニット3は、主に、貯湯タンク31と、加熱循環路39と、給湯出湯口33から給湯接続口41または風呂循環往口43までの給湯配管51と、追い焚き循環路47とで構成されている。
(1−1)貯湯タンクおよび加熱循環路
貯湯タンク31は、底壁に給水口32が設けられ、上壁に給湯出湯口33と追い焚き出湯口34とが設けられる。貯湯タンク31は、給水口32からに水道水が供給され、給湯出湯口33から貯湯タンク31に貯まった高温の温湯を出湯し、浴槽5などに供給可能である。給水口32には、水道水を供給する給水用流路38が接続される。また、貯湯タンク31の底壁には、取水口35が開設され、側壁(周壁)の上部に給湯口36が開設されている。取水口35と給湯口36とは、加熱循環路39に接続されており、加熱循環路39には、循環ポンプP1と、後述するヒートポンプユニット2の水熱交換器22とが接続されている。
(1) Hot Water Storage Unit FIG. 2 is a schematic view of the hot water storage unit 3. The hot water storage unit 3 is mainly composed of a hot water storage tank 31, a heating circulation path 39, a hot water supply pipe 51 from the hot water supply outlet 33 to the hot water connection port 41 or the bath circulation outlet 43, and a recirculation circulation path 47. ing.
(1-1) Hot Water Storage Tank and Heating Circulation Path The hot water storage tank 31 is provided with a water supply port 32 on the bottom wall and a hot water supply hot water outlet 33 and a reheating hot water outlet 34 on the upper wall. The hot water storage tank 31 is supplied with tap water from the water supply port 32, can discharge hot hot water stored in the hot water storage tank 31 from the hot water supply / outlet port 33, and can supply the hot water to the bathtub 5 or the like. A water supply channel 38 for supplying tap water is connected to the water supply port 32. In addition, a water intake 35 is formed in the bottom wall of the hot water storage tank 31, and a hot water supply port 36 is formed in the upper part of the side wall (peripheral wall). The water intake port 35 and the hot water supply port 36 are connected to a heating circuit 39, and a circulation pump P 1 and a water heat exchanger 22 of the heat pump unit 2 described later are connected to the heating circuit 39.

また、貯湯タンク31には、周壁に上下方向の上から50リットルピッチで貯湯タンク31内の各層の温湯の温度を検出する残湯50リットル温度センサT7、残湯100リットル温度センサT8、残湯150リットル温度センサT9、残湯200リットル温度センサT10、および残湯250リットル温度センサT11が設けられる。さらに、貯湯タンク31の最上部(つまり0リットルの位置)に、最上部の温湯の温度を検出する缶体上温度センサT6が設けられる。本実施形態において、残湯50リットル温度センサT7、残湯100リットル温度センサT8、残湯150リットル温度センサT9、残湯200リットル温度センサT10、残湯250リットル温度センサT11、および缶体上温度センサT6は、サーミスタからなる。   The hot water storage tank 31 includes a 50 liter temperature sensor T7 for detecting the temperature of hot water in each layer in the hot water storage tank 31 at a pitch of 50 liters from the top to the bottom on the peripheral wall, a 100 liter temperature sensor T8 for remaining hot water, A 150 liter temperature sensor T9, a remaining hot water 200 liter temperature sensor T10, and a remaining hot water 250 liter temperature sensor T11 are provided. Furthermore, a can body temperature sensor T6 for detecting the temperature of the uppermost hot water is provided at the uppermost portion of the hot water storage tank 31 (that is, at the position of 0 liter). In the present embodiment, the remaining hot water 50 liter temperature sensor T7, the remaining hot water 100 liter temperature sensor T8, the remaining hot water 150 liter temperature sensor T9, the remaining hot water 200 liter temperature sensor T10, the remaining hot water 250 liter temperature sensor T11, and the can body temperature. The sensor T6 is a thermistor.

加熱循環路39は、主に、循環ポンプP1と、三方弁V2とで構成され、ヒートポンプユニット2の水熱交換器22と熱交換路49により接続されている。
循環ポンプP1は、貯湯タンク31の取水口35の近傍に接続されている。また、循環ポンプP1の吐出側には、水熱交換器22が接続されている。循環ポンプP1は、貯湯タンク31内の未加熱水を取水口35から加熱循環路39に流出させ、水熱交換器22内の熱交換路49に未加熱水を流入させる。水熱交換器22に流入された未加熱水は、水熱交換器22内の熱交換路49において加熱され、給湯口36から貯湯タンク31内に返流される。また、加熱循環路39には、熱交換路49の下流側(具体的には、水熱交換器22と三方弁V2との間)に出湯温度センサT4が設けられ、熱交換路49の上流側(具体的には、循環ポンプP1と水熱交換器22との間)に入水温度センサT5が設けられる。出湯温度センサT4と入水温度センサT5とは、サーミスタからなる。
The heating circulation path 39 is mainly composed of a circulation pump P1 and a three-way valve V2, and is connected by a water heat exchanger 22 of the heat pump unit 2 and a heat exchange path 49.
The circulation pump P <b> 1 is connected to the vicinity of the water intake 35 of the hot water storage tank 31. A water heat exchanger 22 is connected to the discharge side of the circulation pump P1. The circulation pump P <b> 1 causes unheated water in the hot water storage tank 31 to flow out from the water port 35 to the heating circulation path 39, and causes unheated water to flow into the heat exchange path 49 in the water heat exchanger 22. Unheated water that has flowed into the water heat exchanger 22 is heated in the heat exchange path 49 in the water heat exchanger 22 and returned to the hot water storage tank 31 from the hot water supply port 36. The heating circulation path 39 is provided with a tapping temperature sensor T4 on the downstream side of the heat exchange path 49 (specifically, between the water heat exchanger 22 and the three-way valve V2), and upstream of the heat exchange path 49. The incoming water temperature sensor T5 is provided on the side (specifically, between the circulation pump P1 and the water heat exchanger 22). The hot water temperature sensor T4 and the incoming water temperature sensor T5 are composed of a thermistor.

三方弁V2は、加熱循環路39内の給湯口36側に設けられ、貯湯タンク31の底壁に設けられる返水口37に接続されるバイパス用流路50と接続されている。このため、本実施例では、バイパス用流路50を温湯が流れずに、取水口35から加熱循環路39に入った水(温湯)が加熱循環路39を流れて給湯口36から貯湯タンク31に戻る通常運転と、取水口35から加熱循環路39に入った水(温湯)が加熱循環路39を流れて三方弁V2を介し、バイパス用流路50を通過して、返水口37から貯湯タンク31に戻るバイパス運転とを行うことができる。   The three-way valve V <b> 2 is provided on the hot water supply port 36 side in the heating circuit 39, and is connected to a bypass channel 50 connected to a water return port 37 provided on the bottom wall of the hot water storage tank 31. For this reason, in this embodiment, hot water does not flow through the bypass channel 50, but water (hot water) that has entered the heating circuit 39 from the water intake 35 flows through the heating circuit 39 and flows from the hot water supply port 36 to the hot water storage tank 31. Normal operation returning to, and water (hot water) that has entered the heating circuit 39 from the water intake 35 flows through the heating circuit 39, passes through the bypass channel 50 via the three-way valve V2, and stores hot water from the water return port 37. Bypass operation returning to the tank 31 can be performed.

(1−2)給湯配管
給湯配管51は、貯湯タンク31の給湯出湯口33に接続されており、浴槽5に温湯を供給する浴槽湯はり系統51aとそれ以外に温湯を供給する給湯系統51bとの2系統に分岐されている。
浴槽湯はり系統51aでは、給湯出湯口33から吐出された温湯は、湯はり混合弁V4により水道水と混合され、湯はり電磁弁V5および風呂循環ポンプP2を介して風呂循環往口44から浴槽5に供給される。湯はり混合弁V4は、ユーザが設定した温度になるように温湯と水道水との混合比率を調整している。湯はり電磁弁V5は、ユーザがリモコン7により浴槽5に湯を溜める「湯はり指令」を出したときに、開になり浴槽5に温湯を供給する。なお、ここに言う「湯はり指令」とは、浴槽5に温湯を自動的に供給する際に後述する制御部6が出す指令のことである。なお、湯はり電磁弁V5の下流側には、湯はり流量センサ42と湯はり温度センサT13とが設けられている。湯はり流量センサ42は、湯はりに使用した温湯の流量を検知できる流量計である。また、湯はり温度センサT13は、湯はりに使用した温湯の温度を検知できる温度センサであり、サーミスタからなる。なお、浴槽湯はり系統51aは、後述する浴槽循環路43の往管部と接続されており、風呂循環ポンプP2以降の管路は浴槽循環路43の往管部の管路と共有されている。
(1-2) Hot-water supply piping The hot-water supply piping 51 is connected to the hot-water supply outlet 33 of the hot water storage tank 31, and includes a hot-water supply system 51b for supplying hot water to the bathtub 5 and a hot-water supply system 51b for supplying hot water to the rest. It is branched into two systems.
In the bathtub hot water system 51a, the hot water discharged from the hot water supply outlet 33 is mixed with tap water by the hot water mixing valve V4, and from the bath circulation outlet 44 through the hot water solenoid valve V5 and the bath circulation pump P2. 5 is supplied. The hot water mixing valve V4 adjusts the mixing ratio of hot water and tap water so that the temperature is set by the user. The hot water solenoid valve V5 is opened and supplies hot water to the bathtub 5 when the user issues a “hot water command” for storing hot water in the bathtub 5 by the remote controller 7. The “hot water command” referred to here is a command issued by the control unit 6 described later when hot water is automatically supplied to the bathtub 5. A hot water flow rate sensor 42 and a hot water temperature sensor T13 are provided downstream of the hot water solenoid valve V5. The hot water flow rate sensor 42 is a flow meter that can detect the flow rate of hot water used for hot water. The hot water temperature sensor T13 is a temperature sensor that can detect the temperature of the hot water used in the hot water beam, and is composed of a thermistor. The bathtub hot water system 51a is connected to an outward pipe portion of a bathtub circulation path 43, which will be described later, and the pipeline after the bath circulation pump P2 is shared with the pipeline of the forward pipe portion of the bathtub circulation path 43. .

給湯系統51bでは、給湯出湯口33から吐出された温湯は、給湯混合弁V3により水道水と混合され、給湯接続口41から家庭の給湯蛇口やシャワーなどに接続されている給湯管52に供給されている。給湯系統51bでは、さらに、給湯混合弁V3の下流側に、給湯温度センサT12と給湯流量センサ40とが設けられている。給湯温度センサT12は、給湯蛇口やシャワーなどにより使用される温湯の温度を検知できる温度センサであり、サーミスタからなる。また、給湯流量センサ40は、給湯蛇口やシャワーなどにより使用される温湯の流量を検知できる流量計である。   In the hot water supply system 51b, the hot water discharged from the hot water supply outlet 33 is mixed with tap water by the hot water mixing valve V3 and supplied from the hot water connection port 41 to the hot water supply pipe 52 connected to a domestic hot water tap or a shower. ing. In the hot water supply system 51b, a hot water supply temperature sensor T12 and a hot water supply flow rate sensor 40 are further provided on the downstream side of the hot water supply mixing valve V3. The hot water supply temperature sensor T12 is a temperature sensor that can detect the temperature of hot water used by a hot water supply faucet or a shower, and includes a thermistor. The hot water flow rate sensor 40 is a flow meter that can detect the flow rate of hot water used by a hot water tap or a shower.

(1−3)追い焚き循環路
追い焚き循環路47には、熱交循環ポンプP3と追い焚き熱交換器46とが接続されている。追い焚き循環路47は、貯湯タンク31の上部に開設されている追い焚き出湯口34と貯湯タンク31の下部に開設されている追い焚き返湯口48とに接続されている。また、浴槽5に接続される浴槽循環路43が設けられており、浴槽循環路43には風呂循環ポンプP2と追い焚き熱交換器46とが接続されている。また、貯湯ユニット3には、浴槽循環路43の端部(浴槽5側)に風呂循環往口44と風呂循環戻口45とが設けられており、風呂循環往口44と風呂循環戻口45とを浴槽5と接続して、浴槽循環路43を形成している。これにより、ユーザは、浴槽5内の温湯を追い焚きしたいときに追い焚き循環路47と浴槽循環路43との温湯を循環させ、貯湯タンク31内の温湯と浴槽5内の温湯とを熱交換させることにより、浴槽5内の温湯を温めることができる。
そして、追い焚き運転の際には、熱交循環ポンプP3が駆動することで、貯湯タンク31内の温湯を、追い焚き出湯口34から追い焚き循環路47に取り込んで、追い焚き熱交換器46に流通させ、浴槽循環路43を流れる温湯と熱交換させている。
(1-3) Reheating Circulation Path The recirculation circulation path 47 is connected to the heat exchange circulation pump P3 and the reheating heat exchanger 46. The reheating circulation path 47 is connected to the reheating hot water outlet 34 provided at the upper part of the hot water storage tank 31 and the reheating hot water supply port 48 provided at the lower part of the hot water storage tank 31. Moreover, the bathtub circulation path 43 connected to the bathtub 5 is provided, and the bath circulation pump P <b> 2 and the reheating heat exchanger 46 are connected to the bathtub circulation path 43. Further, the hot water storage unit 3 is provided with a bath circulation outlet 44 and a bath circulation return 45 at the end of the bathtub circulation path 43 (tub 5 side). Are connected to the bathtub 5 to form a bathtub circulation path 43. Accordingly, when the user wants to recharge the hot water in the bathtub 5, the hot water in the recirculation circulation path 47 and the bathtub circulation path 43 is circulated to exchange heat between the hot water in the hot water storage tank 31 and the hot water in the bathtub 5. By doing, the hot water in the bathtub 5 can be warmed.
During the reheating operation, the heat exchange circulation pump P3 is driven, so that the hot water in the hot water storage tank 31 is taken into the recirculation circulation path 47 from the reheating outlet 34 and reheated heat exchanger 46. The heat is exchanged with the hot water flowing through the bathtub circulation path 43.

(2)ヒートポンプユニット
ヒートポンプユニット2は、屋外に設置されており、冷媒回路20を有している。この冷媒回路20は、圧縮機21と、熱交換路49を構成する水熱交換器22と、電動膨張弁V1と、蒸発器23とを順に接続して構成される。すなわち、圧縮機21と水熱交換器22とを接続し、水熱交換器22と電動膨張弁V1とを接続し、電動膨張弁V1と蒸発器23とを接続し、蒸発器23と圧縮機21とをアキュムレータ25を介して接続している。これにより、圧縮機21が駆動すると、水熱交換器22において熱交換路49を流れる水が加熱されることになる。また、この冷媒回路20は、水熱交換器22と電動膨張弁V1との間の冷媒管と、蒸発器23とアキュムレータ25との間の冷媒管とを熱交換させる液ガス熱交換器24を備えている。また、蒸発器23にはこの蒸発器23の能力を調整するファン26が付設されている。
(2) Heat Pump Unit The heat pump unit 2 is installed outdoors and has a refrigerant circuit 20. The refrigerant circuit 20 is configured by sequentially connecting the compressor 21, the water heat exchanger 22 constituting the heat exchange path 49, the electric expansion valve V <b> 1, and the evaporator 23. That is, the compressor 21 and the water heat exchanger 22 are connected, the water heat exchanger 22 and the electric expansion valve V1 are connected, the electric expansion valve V1 and the evaporator 23 are connected, and the evaporator 23 and the compressor 21 is connected via an accumulator 25. Thereby, when the compressor 21 is driven, the water flowing through the heat exchange path 49 in the water heat exchanger 22 is heated. The refrigerant circuit 20 includes a liquid gas heat exchanger 24 that exchanges heat between the refrigerant pipe between the water heat exchanger 22 and the electric expansion valve V1 and the refrigerant pipe between the evaporator 23 and the accumulator 25. I have. The evaporator 23 is provided with a fan 26 for adjusting the ability of the evaporator 23.

また、ヒートポンプユニット2には、各種のセンサが設けられている。具体的には、ヒートポンプユニット2には、圧縮機21の吐出温度を検出する吐出温度センサT1、圧力保護スイッチとしてのHPS53、蒸発器23内を流れる冷媒の温度(すなわち蒸発温度に対応する冷媒温度)を検出する蒸発温度センサT2、ユニット内に流入する室外空気の温度を検出する外気温度センサT3が設けられている。本実施例に置いて、吐出温度センサT1、蒸発温度センサT2、および外気温度センサT3は、サーミスタからなる。   The heat pump unit 2 is provided with various sensors. Specifically, the heat pump unit 2 includes a discharge temperature sensor T1 that detects the discharge temperature of the compressor 21, an HPS 53 as a pressure protection switch, and the temperature of the refrigerant flowing in the evaporator 23 (that is, the refrigerant temperature corresponding to the evaporation temperature). ) And an outdoor temperature sensor T3 for detecting the temperature of the outdoor air flowing into the unit. In this embodiment, the discharge temperature sensor T1, the evaporation temperature sensor T2, and the outside air temperature sensor T3 are composed of thermistors.

(3)制御部
本実施形態の給湯装置1は制御部6を備えている。制御部6は、図3に示すように、熱量データ記録手段62と、データ算出手段61と、過不足判断手段63と、沸き上げ運転時間制御手段66とを有している。熱量データ記録手段62は、各種センサからの生データ、後述するデータ算出手段61が算出した算出データなどを記録している。データ算出手段61は、熱量データ記録手段62に記録された生データから、1時間単位のユーザの使用湯熱量、ユーザがその時点でどのくらいのペースで湯熱量を使用したかを表す使用ペース、次の日の予測使用湯熱量、予測使用湯熱量に基づいて深夜時間帯における沸き上げ運転時間などを算出している。また、過不足判断手段63は、使用湯熱量および予測使用湯熱量を基にして現在の残湯熱量が最適であるかどうかを判断している。なお、ここに言う「残湯熱量」とは貯湯タンク内に残っている湯熱量のことである。そして、沸き上げ運転時間制御手段66は、沸き上げ運転時間に基づいて深夜時間帯に沸き上げ運転が終了するように沸き上げ運転の開始時刻を決定している。制御部6は、例えば、CPU、メモリ、入出力インターフェースなどを有するマイクロコンピュータを用いて構成される。また、制御部6は、図3に示されるように、リモコン7の制御信号および各種センサT1〜T13,40,42の検出信号を受けることができるように接続されるとともに、これらの制御信号および検出信号に基づいて各種機器および弁21,26,64,65,V1〜V5を制御することができるようにされている。
(3) Control part The hot water supply apparatus 1 of this embodiment is provided with the control part 6. FIG. As shown in FIG. 3, the control unit 6 includes a calorie data recording unit 62, a data calculation unit 61, an excess / deficiency determination unit 63, and a boiling operation time control unit 66. The calorie data recording means 62 records raw data from various sensors, calculation data calculated by the data calculation means 61 described later, and the like. The data calculation means 61 is based on the raw data recorded in the calorific value data recording means 62, the amount of hot water used by the user per hour, the usage pace indicating how much hot water the user used at that time, Based on the predicted amount of hot water used on the day of the day and the predicted amount of hot water used, the boiling operation time in the midnight time zone is calculated. Further, the excess / deficiency determination means 63 determines whether or not the current remaining hot water heat amount is optimal based on the used hot water heat amount and the predicted used hot water heat amount. The “remaining hot water calorie” mentioned here is the hot water remaining in the hot water storage tank. The boiling operation time control means 66 determines the start time of the boiling operation based on the boiling operation time so that the boiling operation ends in the midnight time zone. The control unit 6 is configured using, for example, a microcomputer having a CPU, a memory, an input / output interface, and the like. Further, as shown in FIG. 3, the control unit 6 is connected so as to be able to receive the control signal of the remote controller 7 and the detection signals of the various sensors T1 to T13, 40, 42, and these control signals and Various devices and valves 21, 26, 64, 65, and V1 to V5 can be controlled based on the detection signal.

<ヒートポンプ給湯機の動作>
(1)ヒートポンプユニットの動作
まず、圧縮機21を駆動するとともに、循環ポンプP1を駆動する。
冷媒回路20側では、圧縮機21に吸入された低圧のガス冷媒は、圧縮されて高圧のガス冷媒となる。その後、高圧のガス冷媒は、水熱交換器22に送られて、循環ポンプP1によって供給される未加熱水と熱交換を行って凝縮し、高圧の液冷媒となる。そして、この高圧の液冷媒は、液ガス熱交換器24に流入し、蒸発器23において蒸発されたガス冷媒と熱交換を行ってさらに冷却され、過冷却状態になる。そして、過冷却状態になった高圧の液冷媒は、電動膨張弁V1によって圧縮機21の吸入圧力近くまで減圧されて低圧の気液二相状態の冷媒となって蒸発器23に送られ、蒸発器23においてファン26によって供給される室外空気と熱交換を行って蒸発して低圧のガス冷媒となる。
そして、低圧のガス冷媒は、液ガス熱交換器24に流入し、水熱交換器22において凝縮された液冷媒と熱交換を行ってさらに加熱され、過熱状態になる。この低圧のガス冷媒は、アキュムレータ25に流入し、アキュムレータ25に流入した低圧のガス冷媒は、再び、圧縮機21に吸入される。
<Operation of heat pump water heater>
(1) Operation of heat pump unit First, the compressor 21 is driven and the circulation pump P1 is driven.
On the refrigerant circuit 20 side, the low-pressure gas refrigerant sucked into the compressor 21 is compressed into a high-pressure gas refrigerant. Thereafter, the high-pressure gas refrigerant is sent to the water heat exchanger 22 and is condensed by exchanging heat with unheated water supplied by the circulation pump P1 to become a high-pressure liquid refrigerant. Then, the high-pressure liquid refrigerant flows into the liquid gas heat exchanger 24, is further cooled by exchanging heat with the gas refrigerant evaporated in the evaporator 23, and enters a supercooled state. The supercooled high-pressure liquid refrigerant is reduced to near the suction pressure of the compressor 21 by the electric expansion valve V1, and is sent to the evaporator 23 as a low-pressure gas-liquid two-phase refrigerant. Heat is exchanged with outdoor air supplied by the fan 26 in the vessel 23 to evaporate into a low-pressure gas refrigerant.
Then, the low-pressure gas refrigerant flows into the liquid gas heat exchanger 24, exchanges heat with the liquid refrigerant condensed in the water heat exchanger 22, and is further heated to be in an overheated state. The low-pressure gas refrigerant flows into the accumulator 25, and the low-pressure gas refrigerant that has flowed into the accumulator 25 is again sucked into the compressor 21.

(2)貯湯ユニットの動作
(2−1)沸き上げ運転
貯湯タンク31および加熱循環路39側では、貯湯タンク31の底部に設けた取水口35から貯留水が流出し、これが加熱循環路39の熱交換路49を流通する。このように、加熱循環路39の熱交換路49を流通する未加熱水が、凝縮器として機能している水熱交換器22によって加熱され、(沸き上げられ)、三方弁V2を介して給湯口36から貯湯タンク31の上部に返流される。そしてこのような動作を継続して行うことによって、貯湯タンク31に高温の温湯を供給している。また、三方弁V2では、沸き上げ温度が所定温度以下である場合に、バイパス運転を行い、所定温度以下の低温の温湯を給湯口36から貯湯タンク31に返流させずに返水口37から貯湯タンク31に返流させるように切換を行っている。
(2) Operation of the hot water storage unit (2-1) Boiling operation On the hot water storage tank 31 and the heating circuit 39 side, the stored water flows out from the water intake 35 provided at the bottom of the hot water storage tank 31, The heat exchange path 49 is circulated. In this way, unheated water flowing through the heat exchange path 49 of the heating circulation path 39 is heated by the hydrothermal exchanger 22 functioning as a condenser (boiling), and hot water is supplied through the three-way valve V2. It returns to the upper part of the hot water storage tank 31 from the port 36. The hot water is supplied to the hot water storage tank 31 by continuously performing such an operation. The three-way valve V2 performs a bypass operation when the boiling temperature is equal to or lower than a predetermined temperature, and stores hot water from the water return port 37 without returning low-temperature hot water below the predetermined temperature from the hot water supply port 36 to the hot water storage tank 31. Switching is performed so as to return to the tank 31.

(2−2)給湯制御
給湯系統51bでは、ユーザが設定した温度になるように給湯混合弁V3において水道水と貯湯タンク31内の温湯とが混合されて給湯接続口41から温湯を供給している。なお、給湯系統51b内の給湯温度センサT12と給湯流量センサ40とにより計測されている給湯温度と給湯流量とは制御部6の熱量データ記録手段62に送られて記録されている。
(2-2) Hot Water Supply Control In the hot water supply system 51b, tap water and hot water in the hot water storage tank 31 are mixed in the hot water mixing valve V3 so that the temperature set by the user is reached, and hot water is supplied from the hot water supply connection port 41. Yes. The hot water supply temperature and the hot water supply flow rate measured by the hot water supply temperature sensor T12 and the hot water supply flow rate sensor 40 in the hot water supply system 51b are sent to and recorded in the heat quantity data recording means 62 of the control unit 6.

また、浴槽湯はり系統51aでは、ユーザがリモコン7により「湯はり指令」を出すと、湯はり電磁弁V5が開になり浴槽5に温湯が供給される。このとき、湯はり混合弁V4は、ユーザが設定した温度に基づいて混合比率を調整し、水道水と貯湯タンク31内の温湯とを混合している。なお、浴槽湯はり系統51a内の湯はり温度センサT13により計測されている湯はり温度と湯はり流量センサ42により計測されている湯はり流量とは、制御部6の熱量データ記録手段62に送られて記録されている。   In the bathtub hot water system 51 a, when the user issues a “hot water command” using the remote controller 7, the hot water solenoid valve V 5 is opened and hot water is supplied to the bathtub 5. At this time, the hot water mixing valve V4 adjusts the mixing ratio based on the temperature set by the user, and mixes the tap water and the hot water in the hot water storage tank 31. The hot water temperature measured by the hot water temperature sensor T13 in the bathtub hot water system 51a and the hot water flow rate measured by the hot water flow rate sensor 42 are sent to the heat quantity data recording means 62 of the controller 6. Has been recorded.

(2−3)追い焚き運転
ユーザがリモコン7により「追い焚き指令」を出すと、熱交循環ポンプP3が駆動して追い焚き循環路47内に貯湯タンク31内の温湯が循環する。また、同時に、風呂循環ポンプP2が駆動して浴槽循環路43内に浴槽5内の温湯が循環する。そして、追い焚き熱交換器46により、貯湯タンク31内の温湯と浴槽5内の温湯とを熱交換させて、浴槽5内の温湯を加熱している。なお、熱交循環ポンプP3の駆動時間は、制御部6の熱量データ記録手段62に送られて記録されている。また、缶体上温度センサT6により計測されている缶体上部の温湯温度も熱量データ記録手段62に送られて記録されている。
(2-3) Reheating Operation When the user issues a “renewal instruction” using the remote controller 7, the heat exchange circulation pump P 3 is driven and the hot water in the hot water storage tank 31 circulates in the recirculation circulation path 47. At the same time, the bath circulation pump P <b> 2 is driven to circulate the hot water in the bathtub 5 in the bathtub circulation path 43. The reheating heat exchanger 46 heats the hot water in the hot water storage tank 31 and the hot water in the bathtub 5 to heat the hot water in the bathtub 5. The driving time of the heat exchanger pump P3 is sent to and recorded in the heat quantity data recording means 62 of the control unit 6. Further, the hot water temperature at the upper portion of the can body measured by the on-body temperature sensor T6 is also sent to the calorie data recording means 62 and recorded.

(3)残湯熱量の過不足判断
(3−1)予測使用湯熱量の算出
熱量データ記録手段62は、缶体上温度センサT6、給湯温度センサT12、湯はり温度センサT13、および給水温度センサが取得する温度データと、給湯流量センサ40および湯はり流量センサ42が取得する流量データと、熱交循環ポンプP3の運転時間データとを1時間おきに記録している。データ算出手段61は、温度データ、流量データ、および運転時間データに基づいて、1時間単位にユーザが使用した使用湯熱量と、ユーザがその時点でどのくらいのペースで湯熱量を使用したかを表す使用ペースとを算出している。算出された使用湯熱量および使用ペースは、図4に示されるようにように熱量データ記録手段62により7日間記録される。すなわち、熱量データ記録手段62には、1時間間隔の時間帯別に過去7日間分の使用湯熱量が蓄積されている。そして、データ算出手段61は、この7日間分の使用湯熱量を基にして本日の予測使用湯熱量を各時間帯別に算出している(図4参照)。ここで算出された、予測使用湯熱量は、熱量データ記録手段62に記録される。
(3) Determination of excess or deficiency of remaining hot water heat amount (3-1) Calculation of predicted hot water heat amount The calorie data recording means 62 includes a can body temperature sensor T6, a hot water temperature sensor T12, a hot water temperature sensor T13, and a hot water temperature sensor. Temperature data acquired by the water heater, flow rate data acquired by the hot water supply flow rate sensor 40 and the hot water flow rate sensor 42, and operation time data of the heat exchanger pump P3 are recorded every other hour. The data calculation means 61 represents the amount of hot water used by the user per hour based on the temperature data, flow rate data, and operation time data, and how much hot water the user used at that time. The usage pace is calculated. The calculated amount of hot water used and the pace of use are recorded for 7 days by the calorie data recording means 62 as shown in FIG. That is, in the calorie data recording means 62, the amount of hot water used for the past seven days is accumulated for each time period of one hour interval. And the data calculation means 61 calculates today's estimated amount of hot water used for each time zone based on the amount of hot water used for 7 days (see FIG. 4). The predicted hot water heat amount calculated here is recorded in the heat amount data recording means 62.

(3−2)温湯過多の判断
図5は、残湯熱量が過多であるかを判断する過不足判断手段63の処理の流れを表すフローチャートである。この過不足判断手段63は、このフローチャートの処理により残湯熱量が過多であると判断すると、リモコン7の表示部64に「使用量少なめ」とユーザに残湯熱量が余剰になっていることを知らせる表示をしたり、リモコン7に内蔵されているスピーカ65から「必要に応じてエコ停止をおすすめします」というアナウンスを流したりする。なお、ここに言う「エコ停止」とは、第1特定時刻まで沸き上げ運転を行わないように停止指令をすることである。また、ここに言う「第1特定時刻」とは、電気料金の安くなる深夜時間帯の開始時刻で、例えば午後11時のことであり、さらに、「深夜時間帯」とは、午後11時から翌7時までの時間である。
(3-2) Determination of Excessive Hot Water FIG. 5 is a flowchart showing the flow of processing of the excess / deficiency determination means 63 for determining whether the amount of remaining hot water heat is excessive. If the excess / deficiency determination means 63 determines that the amount of remaining hot water is excessive by the processing of this flowchart, the display unit 64 of the remote control 7 indicates that the amount of remaining hot water is excessive for the user as “use less amount”. A notification is displayed, or an announcement “Eco-stop is recommended if necessary” from the speaker 65 built in the remote controller 7. Note that “eco-stop” as used herein refers to a stop command so that the boiling operation is not performed until the first specific time. In addition, the “first specific time” mentioned here is the start time of the midnight time zone when the electricity rate is reduced, for example, at 11:00 pm, and the “midnight time zone” is from 11:00 pm The time until the next 7 o'clock.

まず、ステップS1では、ユーザがリモコン7上で「おまかせモード」にしているかどうかを確認する。「おまかせモード」の場合に、ステップS2へ移行し、そうでない場合にステップS1へ戻る。なお、ここに言う「おまかせモード」とは、過去7日間の使用湯熱量を時間帯別に学習し、当日必要となる湯量を予測することにより、最適なタイミングで残湯熱量が多いまたは少ないことを報知する制御モードである。ステップS2では、使用湯熱量が7日間分あるかどうかを確認し、使用湯熱量が7日間分ある場合にはステップS3へ移行し、そうでない場合にはステップS1へ戻る。ステップS3では、現時刻総使用湯熱量が2時間後の予測総使用湯熱量と使用ペース定数とを合わせたものよりも小さくなっているかどうかを確認し、小さくなっていればステップS4へ移行し、そうでなければステップS1へ戻る。なお、ここに言う「現時刻総使用湯熱量」とは、ユーザが1日のうちの第2特定時刻(午前5時)からの使用湯熱量の累計のことである。なお、ここで「第2特定時刻」は、1日を判断する時刻のことで、例えば、午前5時〜翌午前4時59分を基準にして1日を数えるなら午前5時とする。また、ここに言う「使用ペース定数」とは、データ算出手段61により生データに基づいた算出された使用ペースに基づく定数のことである。ステップS4では、第2特定時刻(午前5時)から「使用量少なめ」とリモコン7の表示部64に表示されていないかを確認し、「使用量少なめ」と表示されていない場合にはステップS5へ移行し、そうでない場合にはステップS1へ戻る。ステップS5では、リモコン7の表示部64に「使用量少なめ」と表示し、リモコン7に内蔵されているスピーカ65より「必要に応じてエコ停止をおすすめします」とアナウンスする。このように過不足判断手段63では、残湯熱量と使用ペースと予測残湯熱量とに基づいて2時間後に適切な残湯熱量があるかどうかを判断している。   First, in step S1, it is confirmed whether or not the user is in the “auto mode” on the remote controller 7. In the “auto mode”, the process proceeds to step S2, and otherwise, the process returns to step S1. In addition, “Omakase mode” here refers to the fact that the amount of hot water used in the past 7 days is learned by time period, and the amount of hot water remaining at the optimal timing is high or low by predicting the amount of hot water required on the day. This is a control mode for notification. In step S2, it is confirmed whether or not the amount of hot water used is for seven days. If the amount of hot water used is for seven days, the flow proceeds to step S3, and if not, the flow returns to step S1. In step S3, it is confirmed whether or not the total hot water heat amount at the current time is smaller than the sum of the predicted total hot water heat amount and the use pace constant after 2 hours, and if it is smaller, the process proceeds to step S4. Otherwise, the process returns to step S1. Note that the “current time total hot water heat amount used” here refers to the cumulative amount of hot water heat used from the second specific time (5:00 am) of the day. Here, the “second specific time” is a time for determining one day. For example, if the day is counted from 5 am to 4:59 am the next day, it is 5 am. The “use pace constant” referred to here is a constant based on the use pace calculated by the data calculation means 61 based on the raw data. In step S4, it is confirmed from the second specific time (5:00 am) whether or not “small amount of use” is displayed on the display unit 64 of the remote controller 7, and if “small amount of use” is not displayed, step The process proceeds to S5, and if not, the process returns to Step S1. In step S5, “small amount of use” is displayed on the display unit 64 of the remote controller 7, and the speaker 65 built in the remote controller 7 announces “We recommend eco-stop if necessary”. As described above, the excess / deficiency determination means 63 determines whether there is an appropriate amount of remaining hot water after 2 hours based on the amount of remaining hot water, the pace of use, and the predicted amount of remaining hot water.

(4)ピークシフト制御
深夜時間帯に、一斉に沸き上げ運転を行うと、深夜時間帯の前半に電力集中が起こる恐れがある。この電力集中を避けるために、沸き上げ運転の時間帯を残湯熱量を基に深夜時間帯の後半にずらすピークシフト制御を行っている。次に、ピークシフト制御について説明する。
(4) Peak shift control If boiling operation is performed all at once in the midnight hours, power concentration may occur in the first half of the midnight hours. In order to avoid this power concentration, peak shift control is performed to shift the boiling operation time zone to the latter half of the midnight time zone based on the amount of remaining hot water. Next, peak shift control will be described.

データ算出手段61では、予測使用湯熱量に基づいて、予測使用湯熱量をまかなえるだけの温湯を深夜時間帯に沸き上げる沸き上げ運転時間を算出している。この沸き上げ運転時間は、時間帯別に予測された予測使用湯熱量に基づいて、翌日の昼間時間帯に使用されることが予測されている時間帯別の昼間予測使用湯熱量の合計から、残湯熱量を差し引き、深夜時間帯で使用されることが予測されている時間帯別の深夜予測使用湯熱量の合計を加えることにより、深夜時間帯に沸き上げる沸き上げ量を算出している。なお、ここに言う、「昼間時間帯」とは、深夜時間帯以外の時間帯で、例えば、午前7時から午後23時までの時間帯のことである。この沸き上げ量に基づいて沸き上げ運転時間を算出している。そして、沸き上げ運転時間制御手段66は、沸き上げ運転が深夜時間帯の終わりの時刻(すなわち午前7時)に終わるように、沸き上げ運転の開始時刻を決定している。   The data calculation means 61 calculates a boiling operation time in which hot water sufficient to cover the predicted amount of hot water used for boiling is heated at midnight based on the predicted amount of hot water used. This boiling operation time is calculated based on the predicted amount of hot water used for each day of the year, and is calculated from the sum of the predicted amount of hot water used in the daytime for each day that is predicted to be used in the daytime hours of the next day. By subtracting the amount of hot water and adding the total amount of midnight predicted hot water usage for each time zone that is predicted to be used in the midnight time zone, the amount of boiling heated in the midnight time zone is calculated. The “daytime time zone” referred to here is a time zone other than the midnight time zone, for example, a time zone from 7:00 am to 23:00 pm. The boiling operation time is calculated based on this amount of boiling. The boiling operation time control means 66 determines the start time of the boiling operation so that the boiling operation ends at the end time of the midnight time zone (that is, 7:00 am).

図6は、ピークシフト制御における沸き上げ時間のタイムチャートの例である。ここでは、(1)に過去の時間帯別の使用湯熱量を考慮しない場合を、(2)に過去のデータから予測される給湯負荷を、(3)に過去の時間帯別の使用湯熱量を考慮した場合を表している。また、ここでは、貯湯タンク31に温湯が満タンの場合を1として、残湯熱量が2/5であり、当日に3/5だけ必要であるとする。   FIG. 6 is an example of a time chart of the boiling time in peak shift control. Here, when (1) does not consider the amount of hot water used for each past time zone, (2) shows the hot water supply load predicted from past data, and (3) shows the amount of hot water used for each past time zone. This represents the case where is considered. Here, it is assumed that the hot water in the hot water storage tank 31 is 1 and the remaining hot water calorie is 2/5 and only 3/5 is required on the day.

過去の時間帯別の使用湯熱量を考慮しないでピークシフトを行う場合では、午後11時の時点で残湯熱量が2/5であることから深夜時間帯に1/5だけ沸き上げるように沸き上げ時間を算出し、午前4時に沸き上げを開始している。しかしながら、例えば、深夜時間帯の午前5時から1/5の使用湯熱量があった場合に、沸き上げ時間を午後11時で決定しているために深夜時間帯の終了時刻(午前7時)に残湯熱量が2/5のままとなる。このため、当日は湯切れを起こしてしまう恐れがある。   When peak shift is performed without considering the amount of hot water used for each past time zone, the amount of remaining hot water is 2/5 at 11:00 pm. The raising time is calculated, and boiling starts at 4 am. However, for example, when there is 1/5 of the amount of hot water used from 5:00 am in the midnight hours, the boiling time is determined at 11:00 pm, so the end time of the midnight hours (7:00 am) The remaining hot water heat remains at 2/5. For this reason, there is a risk of running out of hot water on the day.

過去の時間帯別の使用湯熱量を考慮してピークシフトを行う場合では、まず、午後11時の時点での残湯熱量が2/5であることを確認する。次に、過去の時間帯別の使用湯熱量のデータから午前5時から1/5の使用湯熱量があることを予測する。そして、当日に3/5だけ必要であると予測しているため、これらを考慮して2/5沸き上げるように沸き上げ時間を算出し、沸き上げ時間の開始を午前1時に前倒しして設定する。すなわち、3/5(予測使用湯熱量)―2/5(残湯熱量)+1/5(深夜使用湯熱量)を計算することにより、沸き上げ時間を算出して沸き上げ開始時刻を決定している。これにより、深夜時間帯に1/5の使用湯熱量がある場合でも、当日に湯切れを起こさないだけの適切な温湯を沸き上げることができる。   In the case of performing a peak shift in consideration of the amount of hot water used for each past time zone, it is first confirmed that the amount of remaining hot water at 11:00 pm is 2/5. Next, it is predicted that there is 1/5 of the amount of hot water used from 5:00 am based on the data of the amount of hot water used for each past time period. And since it is predicted that only 3/5 is required on the day, the boiling time is calculated so that 2/5 is boiled in consideration of these, and the start of the boil time is set ahead by 1 am To do. That is, by calculating 3/5 (predicted amount of hot water used) -2/5 (remaining amount of hot water) + 1/5 (used hot water at midnight), the boiling time was calculated and the boiling start time was determined. Yes. Thereby, even when there is 1/5 of the amount of hot water used in the midnight hours, it is possible to boil up the appropriate hot water that does not cause hot water shortage on the day.

<特徴>
(1)
この給湯装置1では、所定時間帯の終了の直前に沸き上げが完了するように、所定時間帯の開始時点よりも沸き上げ開始を遅らせるピークシフト制御において、過去の給湯負荷の時間帯別の熱量データにより、データ算出手段61において当日の時間帯別の給湯負荷を予測している。そして、データ算出手段61は、沸き上げ開始時刻を演算する際、上記予測負荷量を考慮して必要な沸き上げ運転時間を算出し、沸き上げ開始時刻を決定している。また、沸き上げ運転時間制御手段66は、所定時間帯の終了時刻に沸き上げ運転が終了するように沸き上げ開始時刻を決定している。
<Features>
(1)
In this hot water supply device 1, in peak shift control that delays the start of boiling from the start time of the predetermined time period so that the boiling is completed immediately before the end of the predetermined time period, the amount of heat for each time period of the past hot water supply load. Based on the data, the data calculation means 61 predicts the hot water supply load for each time zone of the day. Then, when calculating the boiling start time, the data calculation means 61 calculates the required boiling operation time in consideration of the predicted load amount, and determines the boiling start time. In addition, the boiling operation time control means 66 determines the boiling start time so that the boiling operation ends at the end time of the predetermined time period.

このため、当日の予測使用湯熱量に対して残湯熱量では不足すると判断した時間帯に、追加の沸き上げ運転を行う沸き上げ制御において、深夜時間帯での給湯負荷に対しては、深夜時間帯で沸き上げを行って補うため、電気代を低減できる。このため、エネルギーを節約することができる。また、所定時間帯の開始時点に電力使用が集中するのを防止することができる。さらに、貯湯タンクの温湯を沸き上げた後の放熱による温度低下を極力防ぐことができる。   For this reason, in boiling control in which additional boiling operation is performed in a time zone in which it is determined that the remaining hot water heat amount is insufficient with respect to the predicted hot water heat amount for the day, for hot water supply loads in the late night time zone, Electricity costs can be reduced because it is made up by heating with a belt. For this reason, energy can be saved. In addition, it is possible to prevent power usage from being concentrated at the start time of the predetermined time period. Furthermore, it is possible to prevent as much as possible a decrease in temperature due to heat dissipation after boiling the hot water in the hot water storage tank.

(2)
この給湯装置1では、データ算出手段61は、沸き上げ運転を行う深夜時間帯の使用量を差し引いて沸き上げ運転時間を決定しているため、沸き上げ運転を行っているときに、給湯の利用があっても適切な量の温湯を沸かすことができる。
(3)
この給湯装置1では、データ算出手段61はリアルタイムに沸き上げ運転時間を算出しており、また、沸き上げ運転時間制御手段66はリアルタイムに沸き上げ開始時刻を変更している。このため、深夜時間帯に急に使用湯熱量が多くなっても翌日に湯切れを起こさないような適切な量の温湯を沸かすことができる。
(2)
In this hot water supply apparatus 1, the data calculating means 61 determines the boiling operation time by subtracting the amount of use in the midnight time zone during which the boiling operation is performed. Even if there is, an appropriate amount of hot water can be boiled.
(3)
In this hot water supply apparatus 1, the data calculating means 61 calculates the boiling operation time in real time, and the boiling operation time control means 66 changes the boiling start time in real time. For this reason, even if the amount of hot water used suddenly increases at midnight, an appropriate amount of hot water can be boiled so that hot water does not run out the next day.

<変形例>
以上にこの発明の具体的な実施の形態について説明したが、この発明は上記形態に限定されるものではなく、この発明の範囲内で種々変更して実施することができる。
(1)
上記実施形態に係る給湯装置1では、残湯熱量が過多であると過不足判断手段63が判断した場合に、表示部64に「使用量少なめ」と表示させたり、スピーカ65に「必要に応じてエコ停止をおすすめします」とアナウンスさせたりすることでユーザに沸き上げ運転を行わないことを勧めているが、ユーザに沸き上げ運転が必要ではないことを報知するだけではなく、さらに、自動的に特定時刻まで沸き上げ運転を行わないようにしても良い。これにより、ユーザが対応しなくとも、無駄な沸き上げ運転をさせることが無くなるため、ユーザに負担をかけずにランニングコストを削減できる。
<Modification>
Although specific embodiments of the present invention have been described above, the present invention is not limited to the above embodiments, and various modifications can be made within the scope of the present invention.
(1)
In the hot water supply apparatus 1 according to the above-described embodiment, when the excess / deficiency determination means 63 determines that the remaining hot water heat amount is excessive, the display unit 64 displays “less used amount” or the speaker 65 indicates “if necessary. It is recommended that users do not perform boiling operation by announcing, `` Eco stop is recommended '', but not only informs the user that boiling operation is not necessary, but also automatically In particular, the boiling operation may not be performed until a specific time. Thereby, even if a user does not respond, since a useless boiling operation is not performed, the running cost can be reduced without placing a burden on the user.

また、残湯熱量が不足であると過不足判断手段63が判断した場合に、表示部64に「使用量多め」と表示させたり、スピーカ65に「必要に応じて沸き上げをおすすめします」とアナウンスさせたりすることでユーザに沸き上げ運転が必要なことを報知しているが、ユーザに沸き上げ運転が必要なことを報知するだけでなく、さらに、自動的に沸き上げ運転を行うようにしても良い。これにより、ユーザが対応しなくとも、沸き上げ運転を行うことができるため、ユーザの負担を軽減できる。また、残湯熱量不足の報知をユーザが見落としたり聞き落としたりすることで、残湯熱量不足に対応できずに沸き上げ運転が行われないことを防ぐことができる。これにより、湯切れが起こることを防ぐことができる。   In addition, when the excess / deficiency determination means 63 determines that the remaining hot water heat amount is insufficient, the display unit 64 displays “use more” or the speaker 65 “recommends boiling if necessary”. To notify the user that the boiling operation is necessary, but not only notifying the user that the boiling operation is necessary, but also automatically performing the boiling operation. Anyway. Thereby, even if a user does not respond | correspond, since a boiling operation can be performed, a user's burden can be reduced. Moreover, it is possible to prevent the boiling operation from being performed without being able to cope with the shortage of the remaining hot water heat by allowing the user to overlook or hear the notification of the shortage of the remaining hot water heat. Thereby, it is possible to prevent the hot water from running out.

本発明に係る給湯装置は、深夜時間帯で沸き上げを行って補うため、エネルギーを節約することができ、使用する湯量を学習して沸き上げ湯量を決定する処理を行う給湯装置等として有用である。   Since the hot water supply apparatus according to the present invention is supplemented by boiling in the midnight time zone, it can save energy and is useful as a hot water supply apparatus that learns the amount of hot water to be used and determines the amount of hot water to be heated. is there.

本実施形態に係る給湯装置の概略図。The schematic diagram of the hot-water supply apparatus concerning this embodiment. 貯湯ユニットの概略図。Schematic of a hot water storage unit. 制御部の概略ブロック図。The schematic block diagram of a control part. 過去7日間における時間帯別の使用湯熱量のデータおよび本日の予測使用湯熱量。Data on hot water usage by time period for the past 7 days and today's predicted hot water usage. 過不足判断手段における、貯湯タンク内の温水過多の判断処理の流れを示すフローチャート図。The flowchart figure which shows the flow of the judgment process of the excessive hot water in a hot water storage tank in an excess and deficiency judgment means. 過不足判断手段における、貯湯タンク内の温水不足の判断処理の流れを示すフローチャート図。The flowchart figure which shows the flow of the judgment process of the lack of hot water in a hot water storage tank in an excess and deficiency judgment means. ピークシフト制御による沸き上げ時間のタイムチャート。Time chart of boiling time by peak shift control.

符号の説明Explanation of symbols

1 給湯装置
31 貯湯タンク
61 データ算出手段
62 熱量データ記録手段
T6 缶体上温度センサ(熱量データ取得手段)
T7 残湯50リットル温度センサ(熱量データ取得手段)
T8 残湯100リットル温度センサ(熱量データ取得手段)
T9 残湯150リットル温度センサ(熱量データ取得手段)
T10 残湯200リットル温度センサ(熱量データ取得手段)
T11 残湯250リットル温度センサ(熱量データ取得手段)
T12 給湯温度センサ(熱量データ取得手段)
T13 湯はり温度センサ(熱量データ取得手段)
P3 熱交循環ポンプ(熱量データ取得手段)
DESCRIPTION OF SYMBOLS 1 Hot water supply apparatus 31 Hot water storage tank 61 Data calculation means 62 Calorific value data recording means T6 Can body temperature sensor (caloric quantity data acquisition means)
T7 Remaining hot water 50 liter temperature sensor (calorie data acquisition means)
T8 Remaining hot water 100 liter temperature sensor (calorie data acquisition means)
T9 Remaining hot water 150 liter temperature sensor (calorie data acquisition means)
T10 Remaining hot water 200 liter temperature sensor (calorie data acquisition means)
T11 Residual hot water 250 liter temperature sensor (calorie data acquisition means)
T12 Hot water temperature sensor (calorie data acquisition means)
T13 Hot water temperature sensor (heat data acquisition means)
P3 Heat exchange circulation pump (heat data acquisition means)

Claims (3)

加熱手段によって水を加熱する沸き上げ運転によりできた温水を貯湯タンク(31)に貯湯する給湯装置(1)であって、
ユーザが使用した前記温水の熱量データを取得する熱量データ取得手段(T6〜T13,40,42,P3)と、
前記熱量データ取得手段により取得された前記熱量データを時間帯別に記録する熱量データ記録手段(62)と、
前記熱量データ記録手段に記録された前記熱量データに基づいて当日の前記時間帯別の予測使用湯熱量と貯湯タンク残湯熱量とを算出し、前記予測使用湯熱量と前記貯湯タンク残湯熱量とに基づいて前記沸き上げ運転に必要な沸き上げ運転時間を算出するデータ算出手段(61)と、
前記沸き上げ運転時間に基づいて、所定時間帯に前記沸き上げ運転を行うように前記沸き上げ運転の沸き上げ開始時刻を決定する沸き上げ運転時間制御手段(66)と、
を備える給湯装置(1)。
A hot water supply device (1) for storing hot water produced by a boiling operation in which water is heated by a heating means in a hot water storage tank (31),
Calorie data acquisition means (T6 to T13, 40, 42, P3) for acquiring calorific data of the hot water used by the user;
A heat quantity data recording means (62) for recording the heat quantity data acquired by the heat quantity data acquisition means for each time zone;
Based on the calorific value data recorded in the calorific value data recording means, the predicted amount of hot water used and the amount of hot water remaining in the hot water tank are calculated for each time zone of the day, and the predicted amount of hot water used and the amount of hot water remaining in the hot water tank Data calculating means (61) for calculating a boiling operation time required for the boiling operation based on
A boiling operation time control means (66) for determining a boiling start time of the boiling operation so as to perform the boiling operation in a predetermined time zone based on the boiling operation time;
A hot water supply device (1).
前記沸き上げ運転時間制御手段は、前記所定時間帯の終了時刻に前記沸き上げ運転が終了するように前記沸き上げ開始時刻を決定する、
請求項1に記載の給湯装置(1)。
The boiling operation time control means determines the boiling start time so that the boiling operation ends at an end time of the predetermined time period.
The hot water supply device (1) according to claim 1.
前記データ算出手段は、前記貯湯タンク残湯熱量と前記所定時間帯以外の時間帯における前記予測使用湯熱量と前記所定時間帯における前記予測使用湯熱量に基づいて前記沸き上げ運転時間を算出する、
請求項1または2のいずれかに記載の給湯装置(1)。
The data calculating means calculates the boiling operation time based on the amount of hot water remaining in the hot water storage tank, the predicted amount of hot water used in a time zone other than the predetermined time zone, and the predicted amount of hot water used in the predetermined time zone.
The hot water supply device (1) according to claim 1 or 2.
JP2006116224A 2006-04-19 2006-04-19 Hot water supply device Pending JP2007285659A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006116224A JP2007285659A (en) 2006-04-19 2006-04-19 Hot water supply device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006116224A JP2007285659A (en) 2006-04-19 2006-04-19 Hot water supply device

Publications (1)

Publication Number Publication Date
JP2007285659A true JP2007285659A (en) 2007-11-01

Family

ID=38757602

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006116224A Pending JP2007285659A (en) 2006-04-19 2006-04-19 Hot water supply device

Country Status (1)

Country Link
JP (1) JP2007285659A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009229016A (en) * 2008-03-24 2009-10-08 Panasonic Electric Works Co Ltd Hot-water storage type hot-water supply system
JP2009236437A (en) * 2008-03-28 2009-10-15 Hitachi Appliances Inc Heat pump water heater
JP2009281658A (en) * 2008-05-22 2009-12-03 Panasonic Corp Water heater
JP2010032079A (en) * 2008-07-25 2010-02-12 Aisin Seiki Co Ltd Cogeneration system
JP2010117058A (en) * 2008-11-11 2010-05-27 Chofu Seisakusho Co Ltd Storage heat pump water heater and heat pump current-carrying method
JP2015175555A (en) * 2014-03-17 2015-10-05 株式会社コロナ hot water storage type water heater
JP2016217622A (en) * 2015-05-20 2016-12-22 三菱電機ビルテクノサービス株式会社 Water heater operation control device and program
JP2017083045A (en) * 2015-10-26 2017-05-18 パナソニックIpマネジメント株式会社 Heat pump water heater

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009229016A (en) * 2008-03-24 2009-10-08 Panasonic Electric Works Co Ltd Hot-water storage type hot-water supply system
JP2009236437A (en) * 2008-03-28 2009-10-15 Hitachi Appliances Inc Heat pump water heater
JP2009281658A (en) * 2008-05-22 2009-12-03 Panasonic Corp Water heater
JP2010032079A (en) * 2008-07-25 2010-02-12 Aisin Seiki Co Ltd Cogeneration system
JP2010117058A (en) * 2008-11-11 2010-05-27 Chofu Seisakusho Co Ltd Storage heat pump water heater and heat pump current-carrying method
JP2015175555A (en) * 2014-03-17 2015-10-05 株式会社コロナ hot water storage type water heater
JP2016217622A (en) * 2015-05-20 2016-12-22 三菱電機ビルテクノサービス株式会社 Water heater operation control device and program
JP2017083045A (en) * 2015-10-26 2017-05-18 パナソニックIpマネジメント株式会社 Heat pump water heater

Similar Documents

Publication Publication Date Title
JP4324154B2 (en) Hot water storage water heater
JP2007285659A (en) Hot water supply device
JP5724418B2 (en) Hot water supply apparatus and method for performing heat treatment thereof
JP2007285653A (en) Hot water supply device
JP4525820B2 (en) Water heater
KR101479877B1 (en) Storage type hot water supply device
JP2014066496A (en) Hot water supply device
JP2014149094A (en) Hot water supply device
JP6107958B2 (en) Heat storage system
JP2013130334A (en) Hot water storage type water heater
JP5329245B2 (en) Water heater
KR101471309B1 (en) Storage type hot water supply device
JP6065548B2 (en) Hot water storage hot water system
JP2007132594A (en) Reservoir type hot water supply device
JP6628643B2 (en) Hot water supply system
JP2007017134A (en) Heat pump type hot-water supply unit, and controller for heat pump type hot-water supply unit
JP2010007891A (en) Heat pump storage type hot water supplying/heating device
JP2013088065A (en) Liquid heater
JP4316521B2 (en) Water heater
JP6164241B2 (en) Water heater
JP7035969B2 (en) Hot water storage type hot water supply device
JP4946835B2 (en) Water heater
JP2008122018A (en) Hot water supply apparatus and method for computing hot water storage amount
JP2010159904A (en) Storage type hot-water supply heating device
JP2007132559A (en) Hot water storage type water heater

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080811

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080819

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081020

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090224

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090427

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20090427

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20090929