JP2006002439A - Heaving prevention method - Google Patents
Heaving prevention method Download PDFInfo
- Publication number
- JP2006002439A JP2006002439A JP2004179910A JP2004179910A JP2006002439A JP 2006002439 A JP2006002439 A JP 2006002439A JP 2004179910 A JP2004179910 A JP 2004179910A JP 2004179910 A JP2004179910 A JP 2004179910A JP 2006002439 A JP2006002439 A JP 2006002439A
- Authority
- JP
- Japan
- Prior art keywords
- ground
- pressure
- resistance
- excavation
- ground surface
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
この発明は、環境問題を引起すことなく経済的で安全な地下掘削工事の施工を提供する。 The present invention provides an economical and safe underground excavation work without causing environmental problems.
従来は、被圧地下水を汲み上げ同水位を下げて揚圧力を軽減する工法や、被圧地下水を含む層より下に土留壁を延伸し止水壁として同水圧を遮断する工法、また地盤改良をすることで同水圧の作用する面を下げて揚圧力を上回る土被りを確保する工法、等があるが、地盤沈下による環境問題や施工の信頼性と工事費の高額化など問題がある。 Conventional methods include pumping groundwater under pressure and lowering the water level to reduce the lifting pressure, extending the retaining wall below the layer containing the groundwater under pressure and blocking the water pressure as a water barrier, and improving the ground. However, there are methods such as lowering the surface on which the water pressure acts to secure a covering that exceeds the lifting pressure, but there are problems such as environmental problems due to land subsidence, reliability of construction and high construction costs.
本発明は、従来の工法に比べ環境問題を引起すことなく、確実な施工と工事費の軽減が可能な盤膨れ防止工事の実現を図る。 The present invention aims to realize a panel swelling prevention construction that can reliably perform construction and reduce construction costs without causing environmental problems as compared with conventional construction methods.
本発明は、被圧地下水圧の作用する不透水層から上部の地盤を同水圧を上回る質量の抵抗地盤とすることで、及び、実績と信頼性の高いグランドアンカーの抵抗力とを併用して、掘削地盤面を押上げる盤膨れを防止することを可能とした。 The present invention is to make the upper ground from the impermeable layer where the pressured groundwater pressure acts as the resistance ground of the mass exceeding the same water pressure, and in combination with the proven and reliable ground anchor resistance. It was possible to prevent the bulging of the board that pushed up the excavated ground surface.
本発明は、従来の工法に比べ安全な工事を提供し、かつ工事費の軽減を図ることが可能である。 The present invention can provide safer construction than conventional methods and can reduce construction costs.
本発明は、地下掘削時被圧地下水圧が不透水層より上部の地盤を押上げようとしたとき、質量の大きい物質にて造成された1重量地盤を含む抵抗地盤が、または同地盤と併用する3グランドアンカーの抵抗力が、被圧地下水圧に抵抗し掘削地盤面の***(盤膨れ)を防止する。
1重量地盤は、比重の異なる物質を同一容器内で攪拌すると、重力と浮力の働きにより比重の大きい物質が下部に比重の小さい物質が上部に堆積する。この現象を利用して質量の大きい置換材と地盤土砂との置換を可能とするものである。
In the present invention, when the ground pressure under pressure during underground excavation tries to push up the ground above the impermeable layer, the resistance ground including the one-weight ground formed of a material having a large mass is used together with the ground. The resistance force of the three ground anchors resists the pressure of groundwater under pressure and prevents the excavation ground surface from rising (swelling).
In the 1-weight ground, when substances having different specific gravity are stirred in the same container, substances having a large specific gravity are deposited on the lower part and substances having a small specific gravity are deposited on the upper part by the action of gravity and buoyancy. By using this phenomenon, it is possible to replace the replacement material having a large mass with the ground sediment.
1重量地盤は、アースオーガーにて施工し置換物質には鉄粒を使用する。施工機械は、バイブロ式地盤改良機や高圧噴射攪拌地盤改良機、大口径ボーリング機、多軸オーガーやベノト他各種地盤改良機械や場所打杭機械とすることも可能である。置換物質は鉄粉とすることも可能である。
3グランドアンカーはロータリーパーカッションにて施工し、受圧板はコンクリート二次製品を使用する。
本案は、掘削(掘削にかかわらず構造物設置)時等に掘削部土留壁(構造物壁)沿いの掘削面(受働抵抗)側下部に施工することで、受働抵抗を増大させ土留壁の根入長を低減(構造物の安定性を増加)することも可能である。
〔施工手順〕
1重量地盤は、置換しようとする区域下端まで減摩材を適度に地盤中に吐出しながら、オーガー正回転で削孔しオーガースクリューで地盤土砂を揚土する。
オーガー先端が基準深度に達したら減摩材を適度に混合した鉄粒を加圧吐出し、地盤土砂を鉄粒で押出すとともにオーガー正回転で攪拌し同スクリューで揚土しつつオーガーを引上げる。
置換しようとする区域上端までオーガー先端が達し所定の量の鉄粒が注入できたら、鉄粒の吐出を停止しオーガーを逆回転させ揚土していた土砂を圧密埋戻ししながら引上げる。
3グランドアンカーは支障のない深度まで掘削したところで施工し、受圧板は部分掘りして低く設置し地山はその後受圧板レベルまで掘削する。あらかじめ予定した余裕の範囲で受圧板をはずしさらに部分掘りして順次盛替え地山掘削をする。これらを所定の深度に達するまで繰返し掘削を完了する。
〔品質管理〕
1重量地盤施工中の管理は、置換材の供給量を管理するとともにオーガーのトルクを管理して、置換材が十分充填されたことを確認する。
1重量地盤施工後の管理は、あらかじめ地中応力測定用計器(間隙水圧計、土圧計、ひずみ計等)を埋設しておき、地中応力の増加状況を確認する。又ボーリングにて資料採取を行い確認するか、観測孔を設置し物理探査等(レーダー、弾性波、磁気、水平載荷等)を実施して確認する。
3グランドアンカーの管理は既定であるので省略する。
1 weight ground will be constructed by earth auger and iron particles will be used as replacement material. The construction machine can be a vibro-type ground improvement machine, a high-pressure jet agitating ground improvement machine, a large-diameter boring machine, a multi-axis auger, Benoto, and other various ground improvement machines and cast-in-place pile machines. The replacement substance may be iron powder.
3 The ground anchor will be constructed by rotary percussion, and the pressure receiving plate will be a concrete secondary product.
This plan increases the passive resistance by constructing the bottom of the excavation surface (passive resistance) side along the excavation part retaining wall (structure wall) during excavation (installation of structures regardless of excavation). It is also possible to reduce the insertion length (increase the stability of the structure).
[Construction procedure]
In the 1-weight ground, the anti-friction material is appropriately discharged into the ground at the lower end of the area to be replaced, and the ground is ground by the auger screw with the auger screw rotating.
When the tip of the auger reaches the reference depth, pressurize and discharge iron particles mixed with an appropriate amount of anti-friction material, extrude the ground earth and sand with iron particles and agitate the auger forward and pull up the auger while unloading with the same screw. .
When the tip of the auger reaches the upper end of the area to be replaced and a predetermined amount of iron particles can be injected, the discharge of the iron particles is stopped, the auger is rotated in the reverse direction, and the earth and sand that have been pumped up are pulled up while being consolidated backfilled.
3 Ground anchors will be constructed when excavated to a point where there is no hindrance, and the pressure plate will be partially dug and installed low, and the ground will then be excavated to the level of the pressure plate. Remove the pressure plate in the margin of the planned schedule and dig further and excavate the ground again. These are repeated until the predetermined depth is reached.
〔quality management〕
The management during the construction of 1 weight ground is to manage the supply amount of the replacement material and the torque of the auger to confirm that the replacement material is sufficiently filled.
For management after construction of 1-weight ground, underground stress measuring instruments (pore water pressure gauge, earth pressure gauge, strain gauge, etc.) are buried in advance to check the increase of underground stress. Also, collect data by boring and confirm, or install an observation hole and conduct physical exploration (radar, elastic wave, magnetism, horizontal loading, etc.).
Since management of 3 ground anchors is a default, it is omitted.
1重量地盤 2土留壁 3グランドアンカー
1 weight ground 2 retaining wall 3 ground anchor
Claims (2)
In addition to claim 1, a three-ground anchor in which a lower load-bearing body is connected to the ground deeper than the surface of the ground surface where the pressure is applied and a pressure-receiving plate grounded to the excavation ground surface or a load-bearing body buried directly below the ground is connected vertically. A bulge prevention construction method that resists pressured groundwater pressure and prevents the excavation ground surface from rising by using a considerable number of the joints and combining the pullout resistance of the anchor and the mass of the resistance ground.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004179910A JP2006002439A (en) | 2004-06-17 | 2004-06-17 | Heaving prevention method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004179910A JP2006002439A (en) | 2004-06-17 | 2004-06-17 | Heaving prevention method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2006002439A true JP2006002439A (en) | 2006-01-05 |
Family
ID=35771062
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2004179910A Pending JP2006002439A (en) | 2004-06-17 | 2004-06-17 | Heaving prevention method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2006002439A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110397044A (en) * | 2019-07-22 | 2019-11-01 | 中铁第四勘察设计院集团有限公司 | The prominent foundation ditch construction method and foundation pit structure gushed of anti-artesian water |
JP2019199692A (en) * | 2018-05-14 | 2019-11-21 | 鹿島建設株式会社 | Ground improvement structure and excavating method |
-
2004
- 2004-06-17 JP JP2004179910A patent/JP2006002439A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2019199692A (en) * | 2018-05-14 | 2019-11-21 | 鹿島建設株式会社 | Ground improvement structure and excavating method |
JP7017980B2 (en) | 2018-05-14 | 2022-02-09 | 鹿島建設株式会社 | Ground improvement structure and excavation method |
CN110397044A (en) * | 2019-07-22 | 2019-11-01 | 中铁第四勘察设计院集团有限公司 | The prominent foundation ditch construction method and foundation pit structure gushed of anti-artesian water |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100762991B1 (en) | Precast piling method injected with high-strength mortar | |
Brown | Practical considerations in the selection and use of continuous flight auger and drilled displacement piles | |
Hagenaar | The use and interpretation of SPT results for the determination of axial bearing capacities of piles driven into carbonate soils and coral | |
CN109208594B (en) | Treatment method for steel casing sinking meeting boulder, steel casing structure and drilled pile | |
CN101481913A (en) | Construction method of rock-socketed underground continuous wall punching slot section | |
CN107700508A (en) | A kind of shaped steel stirs the construction method of water spray soil curtain support pile | |
CN106049467A (en) | Method for treating slurry leakage of bored pile through percussion drill under complex geology | |
CN103821140A (en) | Constructing method for reinforcing soft soil foundations | |
CN109944251A (en) | The drawing hole construction method that soft rock stratum steel sheet pile is squeezed into | |
JP2006002439A (en) | Heaving prevention method | |
JP4066340B2 (en) | Ground improvement method | |
US3100381A (en) | Methods of producing caissons | |
Spagnoli et al. | Support for offshore monopile installation through the trench cutter technology | |
JPH03281826A (en) | Excavation method in cohesive soil ground | |
KR101224440B1 (en) | Construction method of screw file | |
GB2232701A (en) | Mini-piled retaining wall and a method for its construction | |
WO2009139510A1 (en) | Construction method for continuous cut-off wall using overlap casing | |
Brown | Recent advances in the selection and use of drilled foundations | |
CN106013238B (en) | A kind of big earthing open trench tunnel subsidence control method of soft stratum | |
CN205875128U (en) | Quincunx shaped steel cement stirring wall | |
CN107975056A (en) | The excessive processing method for causing water-stop curtain stake to be difficult to pile of Bored Pile Filling Coefficient | |
CN207143991U (en) | The high-pressure rotary-spray steel-pipe pile and Novel pile foundation ruggedized construction of a kind of existing building foundation stabilization | |
CN113832965B (en) | Steel sleeve wall protection device and sand-gravel region cast-in-place pile construction method | |
Rowe | The potentially latent dominance of groundwater in ground engineering | |
CN209144824U (en) | A kind of compound slope protection supporting construction of Muddy Bottoms clay deep-foundation pit engineering |