JP2005036524A - Anchor for construction - Google Patents

Anchor for construction Download PDF

Info

Publication number
JP2005036524A
JP2005036524A JP2003275057A JP2003275057A JP2005036524A JP 2005036524 A JP2005036524 A JP 2005036524A JP 2003275057 A JP2003275057 A JP 2003275057A JP 2003275057 A JP2003275057 A JP 2003275057A JP 2005036524 A JP2005036524 A JP 2005036524A
Authority
JP
Japan
Prior art keywords
head
anchor
shaft body
concrete foundation
wood
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2003275057A
Other languages
Japanese (ja)
Inventor
Suetoshi Saito
末敏 斎藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dandori Seisakusho Kk
Original Assignee
Dandori Seisakusho Kk
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dandori Seisakusho Kk filed Critical Dandori Seisakusho Kk
Priority to JP2003275057A priority Critical patent/JP2005036524A/en
Publication of JP2005036524A publication Critical patent/JP2005036524A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Dowels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide an anchor for a construction convenient for adjusting a space between a concrete foundation or the like and a lumber when the lumber is fixed directly on the concrete foundation, a concrete wall or a brick wall or the like. <P>SOLUTION: In the anchor 1 for the construction in which a shaft body 3 and a head section 2 are formed integrally, a plurality of flange-shaped rings 5 are formed to the head section 2, and a thin recessed section 4 is formed between the shaft body 3 and the head section 2. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明は、コンクリート基礎又はコンクリート壁若しくはレンガ壁等に木材を直接固定する際に、コンクリート等と木材との間の間隔を調整するのに都合のよい建築用アンカーに関する。   The present invention relates to an architectural anchor that is convenient for adjusting the interval between concrete and wood when the wood is directly fixed to a concrete foundation or a concrete or brick wall.

従来から、建物の壁等に形成された開口部に、窓や扉等の木枠を嵌め込む際に、木枠と開口部との間隔を調整して木枠を歪みなく取り付けるために使用する木ねじ等が知られている(例えば、特許文献1)。   Conventionally, when fitting a wooden frame such as a window or door into an opening formed on the wall of a building, etc., it is used to attach the wooden frame without distortion by adjusting the distance between the wooden frame and the opening. Wood screws and the like are known (for example, Patent Document 1).

この木ねじは、軸体の先端側にねじ込み用のねじ山と、頭部側に逆向きのねじ山を有している。開口部に木枠を固定した時、ねじ込み用のねじ山は、開口部にねじ込まれ、逆向きのねじ山は木枠内に位置している。ここで木ねじを緩めると、木枠は逆向きのねじ山が締めつけることになるので、開口部と離れるため、木ねじと開口部との間隔を調整することができる。   This wood screw has a screw thread for screwing on the tip end side of the shaft body and a reverse screw thread on the head side. When the wooden frame is fixed to the opening, the screw thread for screwing is screwed into the opening, and the reverse thread is located in the wooden frame. Here, when the wood screw is loosened, the screw thread in the opposite direction is fastened to the wood frame, so that the space between the wood screw and the opening can be adjusted because the wood frame is separated from the opening.

このような、木ねじは、開口部も木枠も共に木材である場合に使用が可能であるが、一方がコンクリートやレンガ等である場合には使用することができない。例えば、コンクリート基礎の上に直接根太を固定するような場合がこれに当る。この場合には、樹脂を円筒形に形成した建築用アンカーを使用することとなる。   Such wood screws can be used when both the opening and the wooden frame are made of wood, but cannot be used when one of them is concrete, brick, or the like. This is the case, for example, when joists are fixed directly on a concrete foundation. In this case, an architectural anchor in which a resin is formed in a cylindrical shape is used.

建築用アンカーは、根太とコンクリート基礎に設けた下穴に挿通し、建築用アンカーに形成された孔に木ねじを挿通して、かなづち等でコンクリート基礎に打ち込まれる。建築用アンカーの先端部分の孔の内径は木ねじの外径よりも小さいため、下穴の中で建築用アンカーの先端部分が広がり、コンクリート基礎と建築用アンカーが圧接することで根太がコンクリート基礎に固定される。
特開平9−217722号公報 (段落0019以降 図1)
The architectural anchor is inserted into a joist and a pilot hole provided in the concrete foundation, a wood screw is inserted into a hole formed in the architectural anchor, and is driven into the concrete foundation with a hammer. Since the inner diameter of the hole at the tip of the building anchor is smaller than the outer diameter of the wood screw, the tip of the building anchor spreads in the pilot hole, and the joist becomes the concrete foundation when the concrete foundation and the building anchor are pressed together. Fixed.
Japanese Patent Laid-Open No. 9-217722 (paragraph 0019 and subsequent figures)

しかし、上記のような建築用アンカーでは、コンクリートと根太との間隔を調整することができない。   However, in the construction anchor as described above, the interval between the concrete and the joist cannot be adjusted.

そこで本発明は、コンクリート基礎又はコンクリート壁若しくはレンガ壁等に木材を直接固定する際に、コンクリート基礎等と木材との間の間隔を調整するのに都合のよい建築用アンカーの提供を目的とする。   Then, this invention aims at provision of the anchor for a building convenient for adjusting the space | interval between a concrete foundation etc. and wood, when fixing wood directly to a concrete foundation or a concrete wall or a brick wall. .

上記目的を達成するために、請求項1に係る発明は、軸体と頭部が一体に形成された建築用アンカーにおいて、前記頭部には、複数形成されたフランジ状のリングが形成されており、前記軸体と前記頭部との間には肉薄の凹部が設けられていることを特徴としている。   In order to achieve the above object, the invention according to claim 1 is an architectural anchor in which a shaft body and a head are integrally formed, and a plurality of flange-shaped rings are formed on the head. And a thin concave portion is provided between the shaft body and the head.

請求項2に係る発明は、軸体と頭部が一体に形成された建築用アンカーにおいて、前記頭部は、ねじ山を有しており、前記軸体と前記頭部との間には肉薄の凹部が設けられていることを特徴としている。   According to a second aspect of the present invention, in the architectural anchor in which the shaft body and the head are integrally formed, the head has a screw thread, and a thin wall is provided between the shaft and the head. It is characterized in that a recess is provided.

請求項1に係る発明は、軸体と頭部が一体に形成された建築用アンカーにおいて、前記頭部には、複数形成されたフランジ状のリングが形成されており、前記軸体と前記頭部との間には肉薄の凹部が設けられている構成とすることで、頭部は木材に、軸体はコンクリートに圧接し、頭部と軸体が凹部で分離されることによってコンクリート等と木材との間隔を調整することが可能となる。   The invention according to claim 1 is the construction anchor in which the shaft body and the head are integrally formed, and a plurality of flange-shaped rings formed on the head, the shaft body and the head By adopting a structure in which a thin concave portion is provided between the head, the head is pressed against the wood, the shaft is pressed against the concrete, and the head and the shaft are separated from each other by the concave and the like. It is possible to adjust the distance from the wood.

請求項2に係る発明は、軸体と頭部が一体に形成された建築用アンカーにおいて、前記頭部は、ねじ山を有しており、前記軸体と前記頭部との間には肉薄の凹部が設けられている構成とすることで、コンクリート等と木材との間隔を調整し、固定することができる。   According to a second aspect of the present invention, in the architectural anchor in which the shaft body and the head are integrally formed, the head has a screw thread, and a thin wall is provided between the shaft and the head. By setting it as the structure by which the recessed part of is provided, the space | interval of concrete etc. and wood can be adjusted and fixed.

次に、本発明の建築用アンカーを、図面を基に説明する。図1は、本発明の建築用アンカーを示す正面図である。建築用アンカー1は、樹脂を円筒形に形成したものである。頭部2と軸体3の間に、外径が小さくなった凹部4が形成されている。頭部2にはフランジ状のリング5が3つ形成されており、頭部の頂面から凹部4に向けてリング5を分割するようなスリット6が設けられている。軸体3は、中央から先端部分に向かってスリット7が設けられており、その周囲に複数の凸部8が形成されている。軸体3の先端部分にはスリット7は形成されていない。   Next, the architectural anchor of the present invention will be described with reference to the drawings. FIG. 1 is a front view showing an architectural anchor of the present invention. The building anchor 1 is formed by forming a resin into a cylindrical shape. A recess 4 having a smaller outer diameter is formed between the head 2 and the shaft body 3. Three flange-shaped rings 5 are formed in the head 2, and slits 6 are provided to divide the ring 5 from the top surface of the head toward the recess 4. The shaft body 3 is provided with slits 7 from the center toward the tip, and a plurality of convex portions 8 are formed around the slit 7. The slit 7 is not formed at the tip of the shaft body 3.

図1では、頭部2にフランジ状のリング5を複数形成した実施例を示したが、本発明の建築用アンカー1はこのような実施例に限定されるものではない。例えば、リング5の代わりにねじ山を形成してもよい。   Although FIG. 1 shows an embodiment in which a plurality of flange-like rings 5 are formed on the head 2, the architectural anchor 1 of the present invention is not limited to such an embodiment. For example, a thread may be formed instead of the ring 5.

図2は、建築用アンカーに木ねじを挿通した状態を示す断面図である。建築用アンカー1には木ねじ9を挿通するための孔10が開けられている。その内径は頭部2の頂面から軸体3の中央部分にかけてが、木ねじ9のねじ山13の外径とほぼ等しく、軸体3の中央部分から軸体3の先端にかけては、それよりも小さくなっている。また、凹部4は肉薄に形成されている。   FIG. 2 is a cross-sectional view showing a state in which a wood screw is inserted through the building anchor. The building anchor 1 has a hole 10 through which the wood screw 9 is inserted. The inner diameter is substantially equal to the outer diameter of the screw thread 13 of the wood screw 9 from the top surface of the head 2 to the central portion of the shaft body 3, and from the central portion of the shaft body 3 to the tip of the shaft body 3, It is getting smaller. Moreover, the recessed part 4 is formed thinly.

木ねじ9は金属製であり、頭部11と軸体12を有し、軸体12には先端から軸体12の3分の2程度の長さまでねじ山13が転造されている。ねじ山13は、頭部11側のテーパよりも、先端側のテーパの方が、軸体12とのなす角が緩やかになるように形成されている。軸体12の頭部11側には、フランジ状に形成された複数のリング14がある。一方、頭部11の頂面には十字穴又は六角穴といった、ドライバービットを挿入するための図示しない穴が形成されている。
なお、本発明の建築用アンカー1は、木ねじ9以外にも、例えば特許文献1のように逆向きのねじ山を転造した木ねじ等も使用可能である。
The wood screw 9 is made of metal and has a head portion 11 and a shaft body 12, and a thread 13 is rolled on the shaft body 12 from the tip to a length of about two-thirds of the shaft body 12. The screw thread 13 is formed so that the angle formed with the shaft body 12 is gentler in the taper on the tip side than in the taper on the head 11 side. On the head 11 side of the shaft body 12, there are a plurality of rings 14 formed in a flange shape. On the other hand, a hole (not shown) for inserting a driver bit, such as a cross hole or a hexagon hole, is formed on the top surface of the head 11.
In addition to the wood screw 9, the building anchor 1 of the present invention can use a wood screw or the like obtained by rolling a reverse thread as in Patent Document 1, for example.

次に、本発明の建築用アンカー1を使用して、コンクリート基礎15に直接根太を固定する場合の手順を説明する。図3は、下穴を開けたコンクリート基礎と根太に建築用アンカーを挿入した状態を示す図である。まず、電動ドリル等でコンクリート基礎15と根太16に下穴17を開ける。下穴17の内径は、建築用アンカー1の軸体3の外径とほぼ同じか、わずかに大きいものである。そして、その下穴17に木ねじ9を途中まで挿入した建築用アンカー1を挿入し、かなづち等で木ねじ9の頭部11を叩くことによって、木ねじ9と建築用アンカー1を下穴17に挿入していく。この時、リング5は変形しながら根太16に開けられた下穴17に侵入していき、弾性力によって根太16と建築用アンカー1のリング5が圧接する。   Next, the procedure in the case of directly fixing joists to the concrete foundation 15 using the building anchor 1 of the present invention will be described. FIG. 3 is a view showing a state in which a building foundation is inserted into a concrete foundation and joists having a prepared hole. First, a pilot hole 17 is formed in the concrete foundation 15 and joists 16 with an electric drill or the like. The inner diameter of the pilot hole 17 is substantially the same as or slightly larger than the outer diameter of the shaft body 3 of the building anchor 1. Then, the building anchor 1 with the wood screw 9 inserted partway is inserted into the prepared hole 17, and the head 11 of the wood screw 9 is hit with a hammer or the like to insert the wood screw 9 and the building anchor 1 into the prepared hole 17. To go. At this time, the ring 5 penetrates into the pilot hole 17 formed in the joist 16 while being deformed, and the joist 16 and the ring 5 of the building anchor 1 are pressed against each other by the elastic force.

木ねじ9をかなづち等で下穴17にさらに叩き込んでいくことで、軸体3の先端部分が孔10の内径の細くなった部分に侵入する。すると、緩やかなテーパとなっているねじ山13が、細い内径を徐々に押し広げ、それに伴い凸部8が下穴17の側面に圧接される。この時、スリット7が形成されていなかった先端部分が木ねじ9の押し広げようとする力に対抗できなくなって割れる。このようにして、頭部2は根太16に圧接し、軸体3はコンクリート基礎15に圧接する。木ねじ9の頭部11が建築用アンカー1の頭部2に入り、建築用アンカー1の頭部2と木ねじ9の頭部2が根太16の上面と面一になる。この時根太16はコンクリート基礎15に密着している。   By further striking the wood screw 9 into the pilot hole 17 with a pinch or the like, the tip portion of the shaft body 3 enters the portion where the inner diameter of the hole 10 is reduced. Then, the thread 13 having a gentle taper gradually expands the narrow inner diameter, and accordingly, the convex portion 8 is pressed against the side surface of the pilot hole 17. At this time, the tip portion where the slit 7 is not formed cracks because it cannot resist the force of the wood screw 9 trying to spread. In this way, the head 2 is pressed against the joist 16 and the shaft 3 is pressed against the concrete foundation 15. The head 11 of the wood screw 9 enters the head 2 of the building anchor 1, and the head 2 of the building anchor 1 and the head 2 of the wood screw 9 are flush with the upper surface of the joist 16. At this time, the joists 16 are in close contact with the concrete foundation 15.

図4は、コンクリート基礎と根太との間隔を調整している状態を示す図である。建築用アンカー1全体を下穴17に完全に挿通した後、ドライバー等で木ねじ9を左回り、すなわち木ねじ9を取り出す方向へ回転させる。木ねじ9に形成された複数のリング14が建築用アンカー1の頭部2にひっかかるため、頭部2は木ねじ9と一緒に図の上方向にもちあがろうとする。この時、根太16には頭部2に形成されたリング5が圧接しているため、根太16も一緒にもちあがろうとする。   Drawing 4 is a figure showing the state where the space between a concrete foundation and joists is adjusted. After the entire building anchor 1 is completely inserted into the pilot hole 17, the wood screw 9 is rotated counterclockwise by a screwdriver or the like, that is, rotated in the direction of taking out the wood screw 9. Since the plurality of rings 14 formed on the wood screw 9 catches on the head 2 of the building anchor 1, the head 2 tends to move upward together with the wood screw 9. At this time, since the ring 5 formed on the head 2 is in pressure contact with the joist 16, the joist 16 also tries to come together.

このように、建築用アンカー1の頭部2が木ねじ9の動きに追従して上方向に持ちあがろうとする一方で、軸体3は凸部8がコンクリート基礎15に圧接しているためその場に留まろうとする。そのため、頭部2を持ち上げようとする力は肉薄に形成された凹部4に集中し、一定以上の力が掛かったところで凹部4は破断し、頭部2と軸体3は2つに分離する。その後、木ねじ9を緩めたりねじ込んだりすることで、根太16もそれに追従して上下に移動し、コンクリート基礎15と根太16との間隔が調整できる。   Thus, while the head 2 of the anchor 1 for construction follows the movement of the wood screw 9 and tries to lift upward, the shaft body 3 has its convex portion 8 pressed against the concrete foundation 15 so that Try to stay in play. Therefore, the force to lift the head 2 concentrates on the thinly formed recess 4, and when the force of a certain level or more is applied, the recess 4 is broken, and the head 2 and the shaft 3 are separated into two. . Thereafter, by loosening or screwing the wood screw 9, the joist 16 also moves up and down following it, and the interval between the concrete foundation 15 and the joist 16 can be adjusted.

図5は、コンクリート基礎と根太の間にパッキンを挟み込んだ状態を示す図である。このように、コンクリート基礎15と根太16との間隔が決定したら、パッキン18等を挟んでコンクリート基礎15と根太16との間隔を固定する。このようにして床板の水平が容易に確保できる。   FIG. 5 is a view showing a state where packing is sandwiched between a concrete foundation and a joist. Thus, if the space | interval of the concrete foundation 15 and the joist 16 is determined, the space | interval of the concrete foundation 15 and the joist 16 will be fixed on both sides of packing 18 grade | etc.,. In this way, the level of the floor board can be easily secured.

なお、上記実施例では、軸体3に直線状のスリット7と複数の凸部8を形成した建築用アンカー1を用いて説明したが、本発明はこのようなものに限定するものではない。直線状のスリット7ではなく、円弧等の曲線で構成されたスリットや、曲線と直線を組み合わせたようなスリット等を有する建築用アンカーも従来から存在しており、そのようなものにも本発明は適用可能である。また、凸部8の代わりにくさび型の突起が形成された建築用アンカー等にも適用可能である。   In addition, although the said Example demonstrated using the anchor 1 for construction which formed the linear slit 7 and the several convex part 8 in the shaft 3, the present invention is not limited to such a thing. Architectural anchors having slits that are not linear straight slits 7 but curved lines such as arcs, or slits that combine curved lines and straight lines, and the like have also existed in the past. Is applicable. Further, the present invention can also be applied to a building anchor or the like in which a wedge-shaped protrusion is formed instead of the convex portion 8.

さらに、上記実施例ではコンクリート基礎に根太を直接固定する場合で説明したが、その他、コンクリート壁やレンガ壁等の開口部に木枠を取り付けるような場合にも使用することが可能である。   Further, in the above embodiment, the joist is directly fixed to the concrete foundation. However, the present invention can also be used when attaching a wooden frame to an opening such as a concrete wall or a brick wall.

本発明の建築用アンカーを示す正面図である。It is a front view which shows the anchor for construction of this invention. 建築用アンカーに木ねじを挿通した状態を示す断面図である。It is sectional drawing which shows the state which penetrated the wood screw in the anchor for construction. 下穴を開けたコンクリート基礎と根太に建築用アンカーを挿入した状態を示す図である。It is a figure which shows the state which inserted the anchor for construction into the concrete foundation and joist which opened the pilot hole. コンクリート基礎と根太との間隔を調整している状態を示す図である。It is a figure which shows the state which is adjusting the space | interval of a concrete foundation and joists. コンクリート基礎と根太の間にパッキンを挟み込んだ状態を示す図である。It is a figure which shows the state which inserted packing between the concrete foundation and the joist.

符号の説明Explanation of symbols

1 建築用アンカー
2 頭部
3 軸体
4 凹部
5 リング
1 Building Anchor 2 Head 3 Shaft 4 Recess 5 Ring

Claims (2)

軸体と頭部が一体に形成された建築用アンカーにおいて、
前記頭部には、複数形成されたフランジ状のリングが形成されており、
前記軸体と前記頭部との間には肉薄の凹部が設けられていることを特徴とする建築用アンカー。
In an architectural anchor in which the shaft and the head are integrally formed,
The head is formed with a plurality of flange-shaped rings,
A building anchor characterized in that a thin recess is provided between the shaft and the head.
軸体と頭部が一体に形成された建築用アンカーにおいて、
前記頭部は、ねじ山を有しており、
前記軸体と前記頭部との間には肉薄の凹部が設けられていることを特徴とする建築用アンカー。
In an architectural anchor in which the shaft and the head are integrally formed,
The head has a thread;
A building anchor characterized in that a thin recess is provided between the shaft and the head.
JP2003275057A 2003-07-16 2003-07-16 Anchor for construction Pending JP2005036524A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003275057A JP2005036524A (en) 2003-07-16 2003-07-16 Anchor for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003275057A JP2005036524A (en) 2003-07-16 2003-07-16 Anchor for construction

Publications (1)

Publication Number Publication Date
JP2005036524A true JP2005036524A (en) 2005-02-10

Family

ID=34211816

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003275057A Pending JP2005036524A (en) 2003-07-16 2003-07-16 Anchor for construction

Country Status (1)

Country Link
JP (1) JP2005036524A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100930082B1 (en) * 2008-07-25 2009-12-07 공관택 Plastic long anchor
JP2013540960A (en) * 2010-09-01 2013-11-07 ヒルティ アクチエンゲゼルシャフト Expansion anchor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100930082B1 (en) * 2008-07-25 2009-12-07 공관택 Plastic long anchor
JP2013540960A (en) * 2010-09-01 2013-11-07 ヒルティ アクチエンゲゼルシャフト Expansion anchor

Similar Documents

Publication Publication Date Title
US9976298B2 (en) Concealed structural post fastening device and method
US7717015B2 (en) Brick tie anchor and drive tool
KR100897721B1 (en) Anchor bolt for panel and setting up method thereof
JP2005036524A (en) Anchor for construction
JP2009138341A (en) Metallic expansion anchor
JP5198736B2 (en) Mounting structure to the frame of the opening frame
JPH03107605A (en) Expansion plug
US20090142160A1 (en) Raised recess truss head screw
JP2004339797A (en) Anchor metal fitting
KR20080105665A (en) Ancher bolt
JP4221582B2 (en) Wood screw for wood fastening
JP3805641B2 (en) Fastener
JP4655293B2 (en) Jointing device with double-drawing plate
KR100842414B1 (en) Fixation using anchor bolt
JP2008019584A (en) Framework reinforcing structure between pole and horizontal member
JP4183434B2 (en) Building material screws
JP2011117191A (en) Drift pin
KR200290214Y1 (en) Locking device of anchor bolt
JP2946210B1 (en) Adjustment screw and method of mounting frame using the adjustment screw
KR200232416Y1 (en) Structure of anchor bolt
JP2003227182A (en) Joint structure of timber
KR200394408Y1 (en) Anchor Volt
JP2005273241A (en) Anchor and its construction method
JPH10252223A (en) Joint for threaded reinforcing bar
JP3506844B2 (en) Concrete formwork holding method