Prior art keywords
equipment
diagnosis
trouble
deterioration
measurement data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2003015499A
Other languages
Japanese (ja)
Inventor
Masato Itagaki
正人 板垣
Kenji Nakagawa
憲治 仲川
Jiro Ebara
二郎 江原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Plant Technologies Ltd
Original Assignee
Hitachi Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Industries Co Ltd filed Critical Hitachi Industries Co Ltd
Priority to JP2003015499A priority Critical patent/JP2004227357A/en
Publication of JP2004227357A publication Critical patent/JP2004227357A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Testing And Monitoring For Control Systems (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a system that detects a sign of the occurrence of a trouble, prepares required parts beforehand, avoids a sudden shutdown of facilities, carries out a scheduled maintenance, and performs appropriate diagnosis of deterioration, even in the facilities with a multiplicity of watch items. <P>SOLUTION: The system measures a state of operation of the facilities with a measuring instrument installed on the facilities periodically, collects the measured data by an arithmetic processing means, and diagnoses deterioration of the facilities with the collected measured data. In collecting the measured data, the system decides the state of operation of the facilities with the arithmetic processing means, differentiates the measured data by state of operation, and records the data along with measuring time data. The system compares the measured data of a fixed period recorded for each measuring item with a value of diagnostic level already established, corresponding to them, and diagnoses deterioration of the facilities. The system then decides diagnosis items and estimates which portion or component is causing the trouble. <P>COPYRIGHT: (C)2004,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】
本発明は、設備に設置した測定器で設備の動作状態を定期的に測定し、その測定データを収集し、収集した測定データにより該設備を診断する設備の劣化診断方法と劣化診断装置に関する。
【0002】
【従来の技術】
従来の設備の劣化診断においては、通常その管理対象設備の性能を表わす代表的測定データを複数個連続測定し、その個々の値のいずれかが予め定めておいた基準値(診断レベル値)に到達したら劣化状態になったと判断し、その旨を警告するようにしている。設備の管理者はこの警告に基づいて、設備の性能チェック,部品修理,部品交換等のメンテナンス作業を実施する。
【0003】
設備として空気圧縮機を例にとって説明する。
空気圧縮機(以下、圧縮機と略記)は工場用空気源などとして使用されており、空気タンク(レシーバタンク)に高圧空気を供給しているが、使用量の変動により高圧空気の吐出を停止することがある。この場合、入口部を閉じて空気吸込みを遮蔽しており、ロータは復帰に備えてほぼ大気圧以下の圧力状態で回転している。即ち、圧縮機では高圧空気を吐出している全負荷運転(ロード運転)と、吐出してない非全負荷運転(アンロード運転)となり、分単位でそれらの運転状態が切り替っている。
【0004】
運転状態の切り替りを吐出圧力で表すと概ね図9に示す通りであり、実線で示す折れ線12は圧縮機出口圧力、破線で示す折れ線13はレシーバタンク圧力である。
【0005】
起動すると数分間で昇圧され、例えば設定圧力の0.69(MPa)になり、レシーバタンクに高圧空気が供給され、空気の消費量と供給量が等しければ、全負荷運転状態(ロード運転)が続く。
【0006】
消費空気量が減少するとレシーバタンク圧力13は高くなり、上限圧力0.71(MPa)に到達すると、圧力スイッチにより圧縮機入口アンロード弁が作動して、圧縮機の空気入口部を密閉状態にする。これにより、入口圧力は大気圧より低く負圧になり、さらに圧縮機出口とレシーバタンク間にある逆止弁は高圧空気の逆流を阻止し、アンロード弁に連動している放気弁は圧縮機出口側空気を大気に放出する。これにより圧縮機出口圧力12は急激に低圧力になり、0.03(MPa)程度となる。つまり、圧縮機の負荷は低減され圧縮機のロータは回転しているが真空に近い状態になり、圧縮機を駆動している電動機の電力値が低下した省電力状態のアンロード運転となる。
【0007】
レシーバタンク内の高圧空気が消費され、レシーバタンク圧力13が下り、下限圧力0.61(MPa)に到達すると、圧縮機のアンロード弁が元にもどり、入口部が全開となりロード運転となる。
【0008】
このように、圧縮機は分単位で頻繁にロード運転とアンロード運転が繰り返されている。また、このような設備でも負荷状態(ロード運転とアンロード運転)に影響されない監視(測定)項目もあり、この項目は運転状態の区別無しで監視測定される。
【0009】
設備保全のための劣化診断では診断レベル値として上限値あるいは下限値を設定し、それらの値に達したら警報を出す方法をとっており、診断レベル値として通常は細かく区分せず全体の最大値であるロード運転の上限値のみを採用している。なお、このような技術を示すものとして、特開平11−3113号公報がある。
【0010】
【特許文献】
特開平11−3113号公報
【0011】
【発明が解決しようとする課題】
通常の設備においては、監視のために多数のデータ測定項目があり、ある測定項目が予め設定された診断レベル値に到達すると、警報が発せられる。設備の管理者は、この警報表示によりトラブル発生原因を推定する診断作業を行うが、通常は該当測定項目が異常になる原因は複数項目あり、第1段階の診断のみで直ちにトラブル発生の原因部位あるいは部品まで、推定することはほとんど不可能なことが多い。又、警報が発せられる以前に、その診断レベル値に近づいた旨、その予兆を捉えても同様である。
【0012】
しかも、同じ測定項目であっても、運転状態に応じて診断レベル値は異なり、従ってその診断作業は大変繁雑である。
【0013】
そして、トラブル発生の原因部位あるいは部品を推定する場合、設備の管理者はこれらの部位あるいは部品に関連する測定データの値を評価する。換言すれば、第2の劣化診断をすることになる。このように、構成要素の多い設備における劣化診断作業は、何段階にも展開することになる。
【0014】
このように、複数台設備の複数個の診断項目を測定している場合、劣化診断作業は繁雑であり、しかも高度な技術判断が要求されるため時間も掛かる。
【0015】
このように劣化診断作業に、時間を費やしていることは、運転状態を更に悪化させ、その結果設備を停止させしてしまう可能性がある。このような停止が突発的に発生すると、生産現場ではその損失は大きい。さらに、停止した場合、直ちに故障部品を交換できるように、該当部品の在庫状態を把握し、停止し復旧するまでの時間を最少にする必要がある。
【0016】
それゆえ本発明の目的は、多数設備の多数個の診断項目を測定している場合であっても、トラブル発生の原因部位あるいは部品を迅速に推定し、適正な劣化診断を行うことができる設備の劣化診断方法と劣化診断装置を提供することにある。
【0017】
【課題を解決するための手段】
上記目的を達成する本発明方法の特徴とするところは、設備に設置した測定手段で設備の動作状態を定期的に測定し、その測定データを収集し、収集した測定データにより該設備を診断する設備の劣化診断方法において、収集した測定データが診断レベル値データベースに予め設定されている診断レベル値を越えているかどうかを比較する劣化診断を行い、さらにトラブル発生原因データベースにて、発生原因の可能性大の部位あるいは部品を選択し、トラブル発生原因部位あるいは部品を推定することにある。
【0018】
特に、診断レベル値に対する測定データの比率を算出して近接度を求めることを各診断項目について行い、それらの近接度を比率の大きい順に並べてトラブル発生順位付けを行い、さらに、各診断項目に関連する複数の診断項目があれば、該関連する複数の診断項目における近接度の高いものからトラブル発生原因部位あるいは部品を推定する。
【0019】
また、上記目的を達成する本発明装置の特徴とするところは、設備に設置した測定手段で設備の動作状態を定期的に測定し、その測定データを収集し、収集した測定データにより該設備を診断する設備の劣化診断装置において、診断項目に対応する測定データが診断レベル値データベースに予め設定されている診断レベル値を越えているかどうか比較する診断手段と、該診断項目についてトラブル発生原因データベースにより、トラブル発生原因の可能性大の部位あるいは部品を推定する推定手段を備えたことにある。
【0020】
【発明の実施の形態】
以下、本発明の一実施形態を図に従って説明する。
図1において、設備運転施設1には、例えば圧縮機のような管理対象である設備1aがあり、その運転状態をデータ測定手段1bで測定している。設備用集中制御手段(コンピュータ)1cは内蔵している通信プロトコルによりデータ測定手段1bに対し予め決めてある測定のサンプリング周期でオンラインによりリアルタイムで測定データを伝送させている。
【0021】
紙面の簡略化のために設備1aやデータ測定手段1bは1個ずつ記載しているが、実際には設備1aは複数個存在し、データ測定手段1bは個々の設備1aについて複数個存在する。
【0022】
従って、設備用集中制御手段1cでは、データ測定手段1bで測定した性能に関する各測定データに設備1aのコード,測定項目のコード,ロード運転あるいはアンロード運転など運転状態を表わすコードを付加する。また、測定のサンプリング周期は決められており、一定期間(例えば、1日間)に多数回測定されるので、設備用集中制御手段1cでは各測定データにさらに測定の日時の関するデータと何番目のサンプリングに当たる測定データであるか順序に関するデータを付加して内蔵している通信プロトコルにより通信インターフェース1dと通信手段3を介して、遠隔にある中央管理施設2の中央管理装置(コンピュータ)4に送る。以下、個々の測定データとこれに対応して付加される上記したコードやデータの一連のものを送信データと呼ぶ。
【0023】
中央管理施設2では通信インターフェース2aを介して設備用集中制御手段1cから送信されてくる送信データを中央管理装置4において内蔵している通信プロトコルに従って収集(データの取り込み)し、次のように処理する。
【0024】
中央管理装置4には、個々の送信データから設備1aのコード,測定項目のコードおよび運転状態を表わすコードを読んで設備1a毎の運転状態を判定する運転状態判定手段4aと、各設備1aの各測定項目について運転状態判定手段4aで判定した運転状態毎に区別して各測定データに測定の日時の関するデータと何番目のサンプリングに当たる測定データであるか順序に関するデータとを付加して収録するデータ演算処理手段4bを備えている。
【0025】
このデータ演算処理手段4bでは測定項目毎に収録し、一定期間例えば1日分の測定データの収録をする。更に測定項目毎に各運転状態について1日分(一定期間)の測定データが溜まったところで各運転状態毎に区別して測定データの最大値、最小値、平均値を算出して収録することも行う。
【0026】
最大値の算出では、コードで指定できる特定の測定項目について1日分(一定期間)の全測定データについてサンプリング順番に沿って2個の測定データを順次読み出して大きい方を選択することを繰り返し、最後に残るものを最大値とする。最小値の算出では、逆に小さいほうを選択することで実行する。平均値は、コードで指定できる特定の測定項目について1日分(一定期間)の全測定データを加算しそのサンプリング数で除すことで得ることができる。以下、これら最大値、最小値、平均値をデータ演算値と呼ぶ。
【0027】
中央管理装置4は、このデータ演算値と診断レベル値データベース5aに予め設定してある該当の診断レベル値とを比較して、運転状態を診断する第1の運転状態診断手段4cと、さらにトラブル部位あるいは部品を推定するために、トラブル発生原因データベース5bを参考にして推定する診断項目選定手段4dと、第2の運転状態診断手段4eと、この結果からトラブル原因部位あるいは部品を推定するトラブル原因部品推定手段4fと、この診断結果に基づいて警告提示する診断結果表示手段4gとを備えている。
【0028】
換言すると、中央管理装置4では、各設備1a固有の技術情報である診断レベル値データベース5aとトラブル発生原因データベース5bを用いて、トラブル発生原因に対応する部位あるいは部品を段階的に推定する。図1では、2段階でトラブル原因推定を行う構成となっているが、設備が複雑で部品数が多く、高度の技術判断が必要な場合には、トラブル原因推定を3段階以上の構成で行うようにしてもよい。
【0029】
診断結果表示手段4gにおける警告提示は、画面点滅,音声等であり、この提示内容の一部は、前述の通信インターフェース1d及び2a及び通信手段3により設備運転施設1の設備用集中制御手段1cに内蔵してある表示手段1eに送信する。
【0030】
図1では中央管理装置4の構成を図2に示す劣化診断のフローに合わせてデータ処理の流れを中心とした機能で示しているが、実際には運転状態判定手段4a,データ演算処理手段4b,第1の運転状態診断手段4c,診断項目選定手段4d,第2の運転状態診断手段4e,トラブル原因部品推定手段4f,診断結果表示手段4g,診断レベル値データベース5a,トラブル発生原因データベース5bおよび図2のフローを実行するプログラムを格納している図示していないROMや収集した測定データや演算結果などを収録する図示していないRAMなどがバスに繋がっていて、通信インターフェース2aで設備運転施設1などの外部と連動する。
【0031】
運転状態判定手段4a,データ演算処理手段4b,第1の運転状態診断手段4c,診断項目選定手段4d,第2の運転状態診断手段4eおよびトラブル原因部品推定手段4fは、その機能を上記ROMにプログラムとして持たせ、演算処理は中央処理手段(CPU)で実行するようにしても良い。
【0032】
次に、図1の設備1aを圧縮機と仮定し、中央管理装置4における設備の劣化診断方法について、図2に従って説明する。
【0033】
中央管理装置4は、ステップ(以下Sと略す。)11で通信インターフェース2aを介して送信データを取り込むと、運転状態判定手段4aに送る。
【0034】
運転状態判定手段4aは、S12で送信データから運転状態を表わすコードを読んで、運転状態の区別が不必要な測定データを抽出してデータ演算処理手段4bに送って収録させる。運転状態を表わすコードとしてロード運転あるいはアンロード運転のコードがあれば、S13にて測定データを全負荷運転(ロード運転)状態と非全負荷運転(アンロード運転)状態とに分類し、データ演算処理手段4bに送って収録させる。
【0035】
ここで、全負荷運転、非全負荷運転および区別しない運転の各状態における、監視測定項目の具体例を述べる。
【0036】
スクリュー圧縮機の測定データにおいて、モータ電流値や吐出圧力などは、ロード状態とアンロード状態で大幅に変化するので、測定データは区別して演算処理される。しかし、圧縮機に供給される潤滑油の給油圧力や温度などは、ロード状態とアンロード状態で変化しないので、測定データは区別されずに演算処理される。
【0037】
データ演算処理手段4bでは上記した運転状態の3分類に応じて個々に区別して収録しており、1日分における測定データが溜まったところで、S14A〜S14Cにおいて前述の方法で最大値(Xa)、最小値(Xi)および平均値(Xm)をデータ演算値として算出し、収録するとともに第1の運転状態診断手段4cに送る。
【0038】
第1の運転状態診断手段4cでは、S15で上記データ演算値に対する診断を診断レベル値に基づいて行う。診断レベル値は設備1aの機種に対応し、さらに運転状態を考慮して、前述の診断レベル値データベース5aに予め設定(格納)されている。この診断において、データ演算値として、通常は最大値を用いることが多いが、測定項目の特性を考慮して、平均値あるいは最小値を使用することもある。この場合、予め設定されている診断レベル値データベース5aの値は、それらに対応するものを使用する。
【0039】
ここで、第1の運転状態診断手段4c,診断項目選定手段4d,第2の運転状態診断手段4eおよびトラブル原因部品推定手段4fにおける、劣化診断方法を詳細に説明する。
【0040】
1日毎における測定データのトレンドの一例は図5の通りであり、図5は次の手順で求められる。即ち、前述のように監視対象である設備の測定項目毎の測定データは一定時間間隔(サンプリング周期)毎に運転状態を示すコードを付けて収集され、ロード運転とアンロード運転を区別して、1日分の測定データが収録されている。これら全データから平均値(Xm)が算出され、個々の数値の大小比較から各最大値(Xa)と最小値(Xi)が算出される。1日経過すると、ある監視項目に対して、ロード状態とアンロード状態での平均値、最大値及び最小値の合計6個のデータ演算値か、区別なし状態での平均値、最大値及び最小値の合計3個のデータ演算値、のいずれかが求まる。
【0041】
これらのデータ演算値の推移の一例を表したのが、図5であり、横軸が日にち、
縦軸が測定値となる、ロード運転とアンロード運転の各最大値(Xa)、最小値(Xi)および平均値(Xm)の合計6本の折れ線グラフである。しかし、ここでは上限値(診断レベル値11)で判定する場合の3本10a〜10cのみを示した。なお、送信データには測定した日時のコードを付けてあるから、演算や表示のための期間や月日の指定は容易である。
【0042】
図2におけるS15の第1の診断は、図5のトレンドの最大値(Xa)から判断する。この最大値(Xa)10aと、図5に示した診断レベル値(A0)11とを比較し判定する。この場合、
(1a) Xa<A0であればYESで、S17に進む。
(1b) Xa≧A0であればNOで、S16に進み、
アラーム表示(警報)する。
【0043】
このS15の第1の診断(運転状態診断又は劣化診断)において、同時に図7にて定義する「近接度Zr」なる指標を算出し評価する。この「近接度Zr」は測定データ(この場合1日の最大値Xa)の該当診断レベル値(A0)に対する近接割合を、その比率で求めた値で無次元量(−)である。1日毎の測定データが蓄積されると、複数個の第1の診断項目に対して、全て図7に示す近接度Zrが求められ、図8に示すように、その近接度Zrの値の大きい順(1.0に近い順)に順位づけられ予め整理される。
【0044】
従って、図8において、上位に位置する項目の方が、下位にあるものに比べて該当の診断レベル値に近づいていることになる。換言すれば、トラブル発生の可能性の大きい順に順位づけられことである。
【0045】
従って、近接度Zrが1.0以上(測定データが診断レベル値を越えている)の場合は、上記(1b)の状態(判定NO)であり、S16に進みアラーム表示(警報)が発せられる。しかし、ほとんどの場合、近接度Zrが1.0未満の場合であり、上記(1a)の状態(判定YES)である。この場合の診断手順を以下に述べる。
【0046】
S15の第1の診断において、YESと判断されると、次にS17の診断項目選定を行う。図1に示すように中央管理装置4には、設備1aに関するトラブル発生原因データベース5bが備わっており、その一例は図6に示すとおりである。
【0047】
図6は設備1aを空気用スクリュー圧縮機と仮定した場合の関連データベースの抜粋である。このトラブル発生原因データベース5bには、監視項目である複数個の「第1の診断項目」に対して、「運転状態」(ロード、アンロード)を区別した「診断レベル値」(この部分が診断レベル値データベース5aである)があり、第1の診断項目が診断レベル値に到達した場合、その原因となる「トラブル発生原因」と「原因部位・部品」が記載されていて、診断項目を選択できる。
【0048】
しかし、番号1の「電流値」の項目で示すように、その「トラブル発生原因」も「吐出圧力上昇」「供給電圧低下」「機械損失増加」があり、該当する部位・部品も複数個あるように関連する診断項目が複数存在する場合には、直ちにトラブル原因部品を推定することが出来ない。
【0049】
測定データが診断レベル値に到達する以前においても、現時点で最もトラブル発生の可能性が高い第1の診断項目はどれであるかは、図8の近接度順位の相対位置関係で判断出来る。しかし、どの部位あるいは部品かまで推定することは、原因が複数個あるため、トラブル発生の可能性が大きい部品を直ちに推定することは難しい。そこでS17の診断項目選定において、これらの内どれから診断するか選定作業を行う。その手順は、以下のとおりである。
【0050】
トラブル発生の原因部位あるいは部品を選定する場合、第1の診断項目以外の他の測定データのどれが、最も診断レベル値に近いかで判断することとする。第1の診断項目が番号1の「電流値」の場合には、その関連する第2の診断項目は、吐出圧力、供給電圧、振動のいずれかである。これらの測定データは図6における第1の診断項目の他の項目であり、これが第2の診断項目に該当している。
【0051】
そこで、S18の第2の診断およびS19のトラブル原因部品推定では、図6のトラブル発生原因データベースおよび図8の近接度の順位関係で比較検討を行い、トラブル原因部品の推定を行う。これらの診断の内容を図6にて、更に具体例で説明すれば、下記のとおりである。
【0052】
一例を示す図8において、第1の診断項目で圧縮機製番XX1の「電流値」の近接度が最上位にあれば、これが最短時間でトラブルになる可能性が高いと判断する。次いで、どの「原因部位あるいは部品」が該当するか判断するのに、図6において「第2の診断項目」の「吐出圧力」「供給電圧」「振動」の近接度順位を判断する。これらの内、図8に示すように同一圧縮機製番XX1における「吐出圧力」が「電流値」の次ぎに最上位であることを第2の診断S18で確認すると、原因部位・部品として「電流値」における「吐出圧力」に対応する「アンローダ弁類」がトラブル原因である可能性が高いとトラブル原因部品推定手段4fで判断する(S19)。ここまでが、図1における第1の運転状態診断手段4cからトラブル原因部品推定手段4fまでの手順であり、図2におけるS15の第1の診断項目からS19のトラブル原因部品推定の手順である。
【0053】
図1の診断結果表示手段4gは、上述した診断結果に応じて、トラブル発生以前においても、トラブル発生可能性大の診断項目および該当する原因部品を推定し、S20にて診断結果を画面表示する。さらに、表示結果に従ってS21にて、該当部品を用意したり、メンテナンス時期の計画などのメンテナンス準備を行う。
【0054】
さらに、S22にて運転改良内容を図1の診断結果表示手段4gおよび設備用集中制御手段1cにおける表示手段1eに表示する。
【0055】
その運転改良の表示内容は、トラブル発生の可能性大の部位あるいは部品を有する設備を明示して、
(a)近接度が1.0以上であれば、
「直ちに停止すること。」なる音声付加の警報表示を行う。
(b)近接度が1.0未満であれば、
「該当部品の在庫の有無を確認し、無ければアンロード状態に入ったら、直ちに停止すること。」なる音声付加の警報表示を行う。
であり、設備の管理者は画面指示に従って操作する。基本的には、該当設備を停止することになる。
【0056】
一方、第1の診断項目の近接度Zrが1.0以上の(1b)状態(判定NO)の場合の診断手順を以下に述べる。
この場合は、直ちに図2のS16のアラーム表示をし、画面表示に加えて警告音や音声等を伴って提示する。その後の手順は、トラブル未発生の場合と同じ様に、S17の診断項目選定を近接度順位関係から限定し、図6のトラブル発生データベースにて、S18の第2の診断とS19のトラブル発生部品推定を経て、該当部品を推定し、S20で以上の診断結果を表示する。その後は、S23にて部品交換等のメンテナンス作業を実行する。実際は、この様にならないために、トラブル発生以前の予兆を捉えて対策することが重要である。このように、第1の診断で第1の診断項目が診断レベル値未満であっても以上であっても、S19にてトラブル発生原因部位あるいは部品の推定を行う。
【0057】
最後に、S24で処理停止の是非を判断し、通常は最初のS11に戻り、上述の手順を繰り返し続行する。
【0058】
以上説明したように本実施形態によれば、トラブル発生以前にトラブル発生の可能性が最も高い監視項目および該当部品を推定することが出来、圧縮機が故障停止する以前にその予兆を捉えることが出来、突然の圧縮機停止を回避することが出来る。
【0059】
図3は、本発明の他の一実施形態を示している。
図3における中央管理装置4は、図1の中央管理装置4にさらに部品在庫データベース5cと、この部品在庫データベース5cに基づき推定した原因部位あるいは部品の在庫状況を検索する該当部品在庫検索手段4hを備えたものである。そして、図3の中央管理装置4の構成は、図4に示す劣化診断のフローに合わせてデータ処理を行い、図1の診断結果表示手段4gは、診断結果・在庫検索結果表示手段4gとなっている。
【0060】
図3のトラブル原因部品推定手段4fで図4のトラブル原因部品推定S19を行った後、S25の該当部品在庫検索を部品在庫データベース5cにて行い、何処にどれだけあるか調べ、S20において診断結果と部品在庫検索結果を表示する。この部品在庫データベース5cは、通信手段3により、設備使用者以外のメンテナンス会社,メーカー,特約店など関連部署全てのデータベースを随時検索することも可能である。
【0061】
このようにして、トラブル発生の可能性が高い部品の在庫を調べ、設備停止以前に手元に取り寄せておけば、停止後の復旧作業を直ちに行うことが出来るし、又、停止以前に生産に影響しない時期に計画的に止めて、交換整備作業を行うことができる。トラブル発生の可能性が高い部品の在庫状況は設備運転施設1側の表示手段1に送っておくと良い。
【0062】
上記各実施形態では、中央管理装置4を設備運転施設1から離れた場所に設置している例であるが、中央管理装置4を設備運転施設1内に設置してもよく、その場合は設備用集中制御手段1cと中央管理装置4が持つ機能を1個の演算処理手段に合体せしめるようにしても良い。また、中央管理装置4の各手段4a〜4fをそれらの機能が分かりやすいように区分けして示したが、1個のマイクロプロセッサチップに格納してあるソフトプログラムで構成させることができる。
【0063】
【発明の効果】
以上述べたように本発明によれば、多数設備の多数個の診断項目を測定している場合であっても、トラブル発生の原因部位あるいは部品を迅速に推定し、適正な劣化診断を行うことができる。
【図面の簡単な説明】
【図1】本発明の一実施形態である設備の劣化診断装置を示すブロック図である。
【図2】図1に示した設備の劣化診断装置における劣化診断のフローチャートである。
【図3】本発明の他の一実施形態である設備の劣化診断装置を示すブロック図である。
【図4】図3に示した設備の劣化診断装置における劣化診断のフローチャートである。
【図5】設備における一測定データのトレンドグラフである。
【図6】本発明におけるトラブル発生原因データベースの一例を示す図である。
【図7】本発明における近接度を定義する図である。
【図8】本発明における図7における近接度に基づくトラブル発生予測順位付けの一例を示す図である。
【図9】圧縮機の代表的な運転パターンを示す図である。
【符号の説明】
1…設備運転施設
1a…設備
1b…データ測定手段
1c…設備用集中制御手段
1d、2a…通信インターフェース
1e…表示手段
3…通信手段
4…中央管理装置
4a…運転状態判定手段
4b…データ演算処理手段
4c…第1の運転状態診断手段
4d…診断項目選定手段
4e…第2の運転状態診断手段
4f…トラブル原因部品推定手段
4g…診断結果表示手段
5a…診断レベル値データベース
5b…トラブル発生原因データベース
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method and apparatus for diagnosing deterioration of equipment, which periodically measures the operation state of the equipment with a measuring instrument installed in the equipment, collects measurement data of the equipment, and diagnoses the equipment based on the collected measurement data.
[0002]
[Prior art]
In conventional deterioration diagnosis of equipment, usually, a plurality of representative measurement data representing the performance of the equipment to be managed are continuously measured, and one of the individual values is set to a predetermined reference value (diagnosis level value). When it arrives, it is determined that the battery has degraded, and a warning is given to that effect. Based on this warning, the facility manager performs maintenance work such as checking the performance of the facility, repairing parts, and replacing parts.
[0003]
An air compressor will be described as an example of the equipment.
An air compressor (hereinafter abbreviated as compressor) is used as an air source for factories and supplies high-pressure air to an air tank (receiver tank). Sometimes. In this case, the inlet is closed to block air suction, and the rotor is rotating at a pressure substantially equal to or lower than the atmospheric pressure in preparation for the return. That is, the compressor performs a full-load operation (load operation) in which high-pressure air is discharged and a non-full-load operation (unload operation) in which no high-pressure air is discharged, and the operation state is switched in units of minutes.
[0004]
The switching of the operating state is generally represented by the discharge pressure as shown in FIG. 9, where a broken line 12 shown by a solid line is a compressor outlet pressure and a broken line 13 shown by a broken line is a receiver tank pressure.
[0005]
When activated, the pressure is increased in a few minutes, for example, to a set pressure of 0.69 (MPa), high-pressure air is supplied to the receiver tank, and if the amount of consumption and supply of air is equal, the full load operation state (load operation) Continue.
[0006]
When the amount of consumed air decreases, the receiver tank pressure 13 increases. When the upper limit pressure reaches 0.71 (MPa), the compressor inlet unload valve is actuated by a pressure switch to seal the air inlet of the compressor. I do. As a result, the inlet pressure becomes lower than the atmospheric pressure and becomes a negative pressure, the check valve between the compressor outlet and the receiver tank prevents the backflow of high-pressure air, and the discharge valve linked to the unload valve compresses. The air at the outlet of the machine is released to the atmosphere. As a result, the compressor outlet pressure 12 rapidly drops to about 0.03 (MPa). That is, the load on the compressor is reduced, and the rotor of the compressor is rotating but close to a vacuum, and the unload operation in the power saving state in which the electric power of the motor driving the compressor is reduced.
[0007]
When the high-pressure air in the receiver tank is consumed and the receiver tank pressure 13 drops and reaches the lower limit pressure of 0.61 (MPa), the unload valve of the compressor returns to its original position, the inlet is fully opened, and the load operation is started.
[0008]
As described above, the compressor is frequently subjected to the load operation and the unload operation every minute. In addition, even with such equipment, there is a monitoring (measurement) item that is not affected by the load state (load operation and unload operation), and this item is monitored and measured without distinguishing the operation state.
[0009]
In the deterioration diagnosis for equipment maintenance, an upper limit or lower limit is set as a diagnostic level value, and a warning is issued when these values are reached. Only the upper limit of road operation is adopted. Note that Japanese Unexamined Patent Application Publication No. 11-3113 discloses such a technique.
[0010]
[Patent Document]
JP-A-11-3113
[0011]
[Problems to be solved by the invention]
In a typical facility, there are a number of data measurement items for monitoring, and when a certain measurement item reaches a preset diagnostic level value, an alarm is issued. The equipment manager performs diagnostic work to estimate the cause of the trouble by displaying this alarm. Usually, there are multiple causes of the relevant measurement item becoming abnormal. Or it is almost impossible to estimate even the parts. Further, the same applies to the fact that the diagnosis level value is approached before the alarm is issued and the sign of the approach is detected.
[0012]
In addition, even if the measurement items are the same, the diagnostic level value differs depending on the operation state, and the diagnostic work is very complicated.
[0013]
Then, when estimating a trouble-causing site or component, the equipment manager evaluates the value of measurement data related to the site or component. In other words, the second deterioration diagnosis is performed. As described above, the deterioration diagnosis work in equipment having many components is developed in several stages.
[0014]
As described above, when a plurality of diagnostic items of a plurality of equipments are measured, the deterioration diagnosis work is complicated and requires a long time because advanced technical judgment is required.
[0015]
As described above, spending time on the deterioration diagnosis work may further degrade the operation state, and as a result, may stop the equipment. If such an outage occurs suddenly, the loss at the production site is large. Furthermore, in the case of a stop, it is necessary to grasp the stock status of the part and to minimize the time from stop to recovery so that the failed part can be replaced immediately.
[0016]
Therefore, an object of the present invention is to provide a facility capable of quickly estimating a trouble-causing site or a part and performing an appropriate deterioration diagnosis even when measuring a large number of diagnostic items of a large number of facilities. It is an object of the present invention to provide a deterioration diagnosis method and a deterioration diagnosis device.
[0017]
[Means for Solving the Problems]
The feature of the method of the present invention that achieves the above object is to periodically measure the operation state of the equipment by measuring means installed in the equipment, collect the measurement data, and diagnose the equipment based on the collected measurement data. In the equipment deterioration diagnosis method, a deterioration diagnosis is performed to compare whether the collected measurement data exceeds the diagnosis level value preset in the diagnosis level value database, and the cause of occurrence can be determined in the trouble occurrence cause database. The purpose of the present invention is to select a part or part having a large size and to estimate a part or part causing the trouble.
[0018]
In particular, calculating the ratio of the measurement data to the diagnostic level value to obtain the proximity is performed for each diagnostic item, and the proximity is arranged in descending order of the ratio to rank the trouble occurrences. If there are a plurality of diagnostic items to be performed, a trouble-causing site or a part is estimated from those having a high degree of proximity among the plurality of related diagnostic items.
[0019]
Further, the feature of the apparatus of the present invention that achieves the above object is that the operating state of the equipment is periodically measured by measuring means installed in the equipment, the measurement data is collected, and the equipment is operated based on the collected measurement data. In a deterioration diagnosis device for equipment to be diagnosed, a diagnosis means for comparing whether measured data corresponding to a diagnosis item exceeds a diagnosis level value preset in a diagnosis level value database, and a trouble occurrence cause database for the diagnosis item That is, there is provided an estimating means for estimating a part or a part having a high possibility of causing a trouble.
[0020]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, an embodiment of the present invention will be described with reference to the drawings.
In FIG. 1, an equipment operation facility 1 has an equipment 1a to be managed, such as a compressor, for example, and its operation state is measured by a data measurement unit 1b. The facility centralized control means (computer) 1c transmits the measurement data to the data measurement means 1b online in real time at a predetermined measurement sampling cycle by a built-in communication protocol.
[0021]
Although the equipment 1a and the data measuring means 1b are described one by one for simplicity of the paper space, a plurality of equipments 1a actually exist, and a plurality of data measuring means 1b exist for each equipment 1a.
[0022]
Accordingly, the equipment centralized control means 1c adds a code of the equipment 1a, a code of a measurement item, a code indicating an operation state such as a load operation or an unload operation to each measurement data relating to the performance measured by the data measurement means 1b. Since the measurement sampling cycle is determined and the measurement is performed many times in a certain period (for example, one day), the equipment centralized control means 1c further adds the data relating to the date and time of the measurement to each measurement data. Measurement data to be sampled or data related to the order is added to the data and sent to the central management device (computer) 4 of the remote central management facility 2 via the communication interface 1d and the communication means 3 by a built-in communication protocol. Hereinafter, a series of individual measurement data and the above-described codes and data added corresponding thereto will be referred to as transmission data.
[0023]
The central management facility 2 collects (takes in data) transmission data transmitted from the facility central control means 1c via the communication interface 2a according to a communication protocol built in the central management apparatus 4, and processes as follows. I do.
[0024]
The central management unit 4 reads the code of the equipment 1a, the code of the measurement item, and the code representing the operation state from the individual transmission data to determine the operation state of each equipment 1a. Data to be recorded by separately adding data relating to the date and time of measurement and data relating to the order of the measurement data corresponding to the number of samplings to each measurement data separately for each operation state determined by the operation state determination means 4a for each measurement item. An arithmetic processing unit 4b is provided.
[0025]
The data arithmetic processing means 4b records for each measurement item, and records measurement data for a certain period, for example, one day. Further, when measurement data for one day (a certain period) is accumulated for each operation state for each measurement item, the maximum value, minimum value, and average value of the measurement data are calculated and recorded separately for each operation state. .
[0026]
In the calculation of the maximum value, for a specific measurement item that can be specified by the code, two measurement data are sequentially read out in accordance with the sampling order for all the measurement data for one day (a certain period), and a larger one is repeatedly selected. The last one is the maximum value. The calculation of the minimum value is executed by selecting the smaller one. The average value can be obtained by adding all the measurement data for one day (for a certain period) for a specific measurement item that can be specified by the code and dividing by the number of samples. Hereinafter, these maximum value, minimum value, and average value are referred to as data operation values.
[0027]
The central management unit 4 compares the data operation value with a corresponding diagnosis level value preset in the diagnosis level value database 5a, and diagnoses the operating state with a first operation state diagnosis unit 4c. Diagnosis item selection means 4d for estimating a part or part with reference to the trouble occurrence cause database 5b, second operating state diagnosis means 4e, and a trouble cause for estimating a trouble part or part from the result. The system includes a component estimating unit 4f and a diagnosis result display unit 4g for presenting a warning based on the diagnosis result.
[0028]
In other words, the central management device 4 estimates the parts or parts corresponding to the cause of the trouble in stages using the diagnostic level value database 5a and the trouble cause database 5b, which are technical information unique to each facility 1a. In FIG. 1, the trouble cause is estimated in two stages. However, when the equipment is complicated, the number of parts is large, and advanced technical judgment is required, the trouble cause is estimated in three or more stages. You may do so.
[0029]
The warning presentation on the diagnosis result display means 4g is a blinking screen, a voice, and the like. This is transmitted to the built-in display means 1e.
[0030]
In FIG. 1, the configuration of the central management unit 4 is shown with functions centering on the flow of data processing in accordance with the flow of the deterioration diagnosis shown in FIG. 2, but in actuality, the operating state determination means 4a and the data calculation processing means 4b , First operating state diagnostic means 4c, diagnostic item selecting means 4d, second operating state diagnostic means 4e, trouble cause component estimating means 4f, diagnosis result display means 4g, diagnostic level value database 5a, trouble occurrence cause database 5b, A ROM (not shown) storing a program for executing the flow shown in FIG. 2 and a RAM (not shown) storing collected measurement data and calculation results are connected to the bus. Interacts with the outside such as 1.
[0031]
The operating state determining means 4a, the data operation processing means 4b, the first operating state diagnosing means 4c, the diagnostic item selecting means 4d, the second operating state diagnosing means 4e, and the trouble cause component estimating means 4f store their functions in the ROM. The program may be provided, and the arithmetic processing may be executed by a central processing unit (CPU).
[0032]
Next, assuming that the equipment 1a in FIG. 1 is a compressor, a method for diagnosing deterioration of the equipment in the central management device 4 will be described with reference to FIG.
[0033]
When the central management device 4 captures the transmission data via the communication interface 2a in step (hereinafter abbreviated as S) 11, the central management device 4 sends the data to the operation state determination means 4a.
[0034]
The operating state determining means 4a reads the code representing the operating state from the transmission data in S12, extracts the measurement data which does not require the distinction of the operating state, and sends the data to the data processing means 4b for recording. If there is a code indicating a load operation or an unload operation as a code representing the operation state, the measured data is classified into a full load operation (load operation) state and a non-full load operation (unload operation) state in S13, and data calculation is performed. It is sent to the processing means 4b for recording.
[0035]
Here, specific examples of monitoring measurement items in each state of full-load operation, non-full-load operation, and non-discriminating operation will be described.
[0036]
In the measurement data of the screw compressor, the motor current value, the discharge pressure, and the like greatly change between the loaded state and the unloaded state, so that the measurement data is separately processed. However, since the lubricating oil supply pressure and temperature supplied to the compressor do not change between the loaded state and the unloaded state, the measurement data is processed without distinction.
[0037]
The data arithmetic processing means 4b separately records the data according to the above-described three classifications of the operating state, and when the measurement data for one day is accumulated, the maximum value (Xa), S14A to S14C, The minimum value (Xi) and the average value (Xm) are calculated as data operation values, recorded and sent to the first operating state diagnostic means 4c.
[0038]
In S15, the first operating state diagnosis means 4c performs a diagnosis on the data calculated value based on the diagnosis level value. The diagnostic level value corresponds to the model of the equipment 1a, and is set (stored) in advance in the diagnostic level value database 5a in consideration of the operation state. In this diagnosis, a maximum value is usually used as a data operation value, but an average value or a minimum value may be used in consideration of characteristics of a measurement item. In this case, the preset values of the diagnostic level value database 5a use those corresponding thereto.
[0039]
Here, a method of diagnosing deterioration in the first operating state diagnostic means 4c, the diagnostic item selecting means 4d, the second operating state diagnostic means 4e and the trouble cause component estimating means 4f will be described in detail.
[0040]
An example of the trend of the measurement data every day is as shown in FIG. 5, and FIG. 5 is obtained by the following procedure. That is, as described above, the measurement data for each measurement item of the equipment to be monitored is collected with a code indicating the operation state at fixed time intervals (sampling periods), and the load operation and the unload operation are distinguished from each other. Contains daily measurement data. The average value (Xm) is calculated from all the data, and the maximum value (Xa) and the minimum value (Xi) are calculated from the magnitude comparison of the individual numerical values. After one day, for a certain monitoring item, a total of six data operation values of the average value, the maximum value, and the minimum value in the load state and the unload state, or the average value, the maximum value, and the minimum value in the undiscriminated state One of the three data operation values in total of the values is obtained.
[0041]
FIG. 5 shows an example of the transition of these data operation values, where the horizontal axis represents the date,
It is a total of six line graphs of the maximum value (Xa), the minimum value (Xi), and the average value (Xm) of the load operation and the unload operation in which the vertical axis is the measured value. However, here, only three 10a to 10c in the case where the determination is made based on the upper limit (diagnosis level value 11) are shown. Since the transmission data is provided with a code of the measured date and time, it is easy to specify a period and a date for calculation and display.
[0042]
The first diagnosis in S15 in FIG. 2 is determined from the maximum value (Xa) of the trend in FIG. The maximum value (Xa) 10a is compared with the diagnostic level value (A0) 11 shown in FIG. in this case,
(1a) If Xa <A0, YES, proceed to S17.
(1b) If Xa ≧ A0, NO, proceed to S16,
Display an alarm (alarm).
[0043]
In the first diagnosis (operation state diagnosis or deterioration diagnosis) in S15, an index called “proximity Zr” defined in FIG. 7 is calculated and evaluated at the same time. The “proximity Zr” is a dimensionless amount (−), which is a value obtained by calculating the proximity ratio of the measured data (in this case, the maximum value Xa for one day) to the corresponding diagnosis level value (A0). When the measurement data for each day is accumulated, the proximity Zr shown in FIG. 7 is obtained for all of the plurality of first diagnosis items, and as shown in FIG. 8, the value of the proximity Zr is large. They are ordered in order (closer to 1.0) and arranged in advance.
[0044]
Therefore, in FIG. 8, the higher-ranked item is closer to the corresponding diagnosis level value than the lower-ranked item. In other words, they are ranked in descending order of the possibility of trouble occurrence.
[0045]
Therefore, when the proximity Zr is 1.0 or more (the measurement data exceeds the diagnostic level value), the state is the state (1b) (determination NO), and the process proceeds to S16 where an alarm display (alarm) is issued. . However, in most cases, the proximity Zr is less than 1.0, which is the state (1a) (determination YES). The diagnosis procedure in this case will be described below.
[0046]
If YES is determined in the first diagnosis in S15, a diagnosis item is selected in S17. As shown in FIG. 1, the central management device 4 is provided with a trouble occurrence cause database 5b relating to the equipment 1a, and an example thereof is as shown in FIG.
[0047]
FIG. 6 is an excerpt of a related database when the equipment 1a is assumed to be a screw compressor for air. In the trouble occurrence cause database 5b, a “diagnosis level value” that distinguishes “operating state” (load, unload) from a plurality of “first diagnosis items” which are monitoring items (this portion is a diagnosis level value). If the first diagnosis item reaches the diagnosis level value, the "trouble occurrence cause" and "cause part / part" which cause the first diagnosis item are described, and the diagnosis item is selected. it can.
[0048]
However, as shown in the item of "current value" of number 1, the "trouble causes" also include "discharge pressure rise", "supply voltage drop", and "mechanical loss increase", and there are a plurality of applicable parts and parts. As described above, when there are a plurality of related diagnosis items, it is not possible to immediately estimate a trouble-causing component.
[0049]
Even before the measurement data reaches the diagnosis level value, it is possible to determine which of the first diagnosis items is most likely to cause a trouble at this time based on the relative positional relationship of the proximity rank in FIG. However, since it is difficult to estimate which part or component there are a plurality of causes, it is difficult to immediately estimate a component having a high possibility of occurrence of a trouble. Therefore, in the diagnosis item selection in S17, a work of selecting which of these is to be diagnosed is performed. The procedure is as follows.
[0050]
When selecting a trouble-causing site or a part, it is determined which measurement data other than the first diagnosis item is closest to the diagnosis level value. When the first diagnosis item is the “current value” of No. 1, the related second diagnosis item is any one of the discharge pressure, the supply voltage, and the vibration. These measurement data are other items of the first diagnosis item in FIG. 6, and correspond to the second diagnosis item.
[0051]
Therefore, in the second diagnosis in S18 and the trouble cause component estimation in S19, comparison and examination are performed based on the trouble occurrence cause database in FIG. 6 and the proximity relationship in FIG. 8 to estimate the trouble cause component. The details of these diagnoses will be described in more detail with reference to FIG. 6 as follows.
[0052]
In FIG. 8 showing an example, if the proximity of the “current value” of the compressor serial number XX1 is the highest in the first diagnostic item, it is determined that this is likely to cause a trouble in the shortest time. Next, in order to determine which “cause part or part” corresponds, in FIG. 6, the proximity order of “discharge pressure”, “supply voltage”, and “vibration” of the “second diagnostic item” is determined. Of these, as shown in FIG. 8, it is confirmed in the second diagnosis S18 that the "discharge pressure" in the same compressor serial number XX1 is the highest next to the "current value". The trouble cause component estimating means 4f determines that the "unloader valves" corresponding to the "discharge pressure" in the "value" is highly likely to be the cause of the trouble (S19). The procedure up to this point is the procedure from the first operating state diagnostic means 4c to the trouble cause component estimating means 4f in FIG. 1, and the procedure from the first diagnosis item in S15 to the trouble cause component estimation in S19 in FIG.
[0053]
The diagnosis result display means 4g of FIG. 1 estimates a diagnosis item having a high possibility of occurrence of a trouble and a corresponding cause component even before the occurrence of a trouble in accordance with the above-described diagnosis result, and displays the diagnosis result on the screen in S20. . Further, in S21, corresponding parts are prepared, and maintenance preparation such as maintenance time planning is performed in S21.
[0054]
Further, in S22, the details of the operation improvement are displayed on the diagnosis result display means 4g of FIG. 1 and the display means 1e of the facility centralized control means 1c.
[0055]
The display contents of the operation improvement clearly indicate facilities or parts having parts or parts that are likely to cause trouble,
(A) If the proximity is 1.0 or more,
A warning message with the sound "Stop immediately" is displayed.
(B) If the proximity is less than 1.0,
A warning message is displayed with a voice message saying "Check if the corresponding parts are in stock, and if not, stop immediately after entering the unloading state."
And the facility manager operates according to the screen instructions. Basically, the corresponding equipment will be stopped.
[0056]
On the other hand, a diagnosis procedure when the proximity Zr of the first diagnosis item is 1.0 or more (1b) (determination NO) will be described below.
In this case, the alarm display of S16 in FIG. 2 is immediately performed, and the alarm display and the sound are presented in addition to the screen display. In the subsequent procedure, similarly to the case where no trouble has occurred, the diagnosis item selection in S17 is limited based on the proximity order relation, and the second diagnosis in S18 and the trouble occurrence component in S19 are performed in the trouble occurrence database in FIG. After the estimation, the corresponding part is estimated, and the above diagnosis result is displayed in S20. After that, maintenance work such as component replacement is performed in S23. In fact, in order to prevent this from happening, it is important to take a pre-warning sign before the occurrence of the trouble and take measures. As described above, whether or not the first diagnosis item is less than or equal to the diagnosis level value in the first diagnosis, the trouble occurrence site or component is estimated in S19.
[0057]
Finally, in S24, it is determined whether or not to stop the process. Normally, the process returns to the first step S11, and the above procedure is repeated and continued.
[0058]
As described above, according to the present embodiment, it is possible to estimate a monitoring item and a corresponding part with the highest possibility of occurrence of a trouble before the occurrence of a trouble, and to grasp a sign of the trouble before the compressor stops due to a failure. Yes, sudden compressor stoppage can be avoided.
[0059]
FIG. 3 shows another embodiment of the present invention.
The central management unit 4 in FIG. 3 further includes a parts inventory database 5c and a corresponding parts inventory search unit 4h for searching for a cause part or a part inventory status estimated based on the parts inventory database 5c in addition to the central management apparatus 4 of FIG. It is provided. Then, the configuration of the central management device 4 in FIG. 3 performs data processing in accordance with the flow of the deterioration diagnosis shown in FIG. 4, and the diagnosis result display means 4g in FIG. 1 becomes a diagnosis result / stock search result display means 4g. ing.
[0060]
After the trouble cause component estimating means 4f of FIG. 3 performs the trouble cause component estimation S19 of FIG. 4, the corresponding parts stock search of S25 is performed in the parts stock database 5c to check where and how much is present, and in S20 the diagnosis result And display the parts inventory search results. The parts inventory database 5c can be searched by the communication means 3 at any time for databases of all related departments such as maintenance companies, manufacturers, dealers, etc. other than the facility users.
[0061]
In this way, if the inventory of parts that are likely to cause troubles is checked and ordered before the equipment is stopped, restoration work after the stop can be performed immediately, and production may be affected before the stop. It can be scheduled to be stopped at a time when it is not needed, and replacement maintenance work can be performed. It is preferable to send the stock status of parts having a high possibility of occurrence of trouble to the display means 1 of the facility operating facility 1.
[0062]
In each of the above embodiments, the central management device 4 is installed at a location remote from the facility operation facility 1. However, the central management device 4 may be installed within the facility operation facility 1, and in that case, the facility The functions of the centralized control unit 1c and the central management unit 4 may be combined into one arithmetic processing unit. In addition, although the respective means 4a to 4f of the central management device 4 are shown separately for easy understanding of their functions, they may be constituted by a software program stored in one microprocessor chip.
[0063]
【The invention's effect】
As described above, according to the present invention, even when a large number of diagnostic items of a large number of facilities are measured, it is possible to quickly estimate a trouble-causing site or a part and perform an appropriate deterioration diagnosis. Can be.
[Brief description of the drawings]
FIG. 1 is a block diagram showing an equipment deterioration diagnosis apparatus according to an embodiment of the present invention.
FIG. 2 is a flowchart of a deterioration diagnosis in the equipment deterioration diagnosis apparatus shown in FIG. 1;
FIG. 3 is a block diagram showing an equipment deterioration diagnosis apparatus according to another embodiment of the present invention.
FIG. 4 is a flowchart of a deterioration diagnosis in the equipment deterioration diagnosis apparatus shown in FIG. 3;
FIG. 5 is a trend graph of one measurement data in the equipment.
FIG. 6 is a diagram illustrating an example of a trouble occurrence cause database according to the present invention.
FIG. 7 is a diagram that defines proximity in the present invention.
8 is a diagram showing an example of the trouble occurrence prediction ranking based on the proximity in FIG. 7 in the present invention.
FIG. 9 is a diagram showing a typical operation pattern of the compressor.
[Explanation of symbols]
1. Facility operating facilities
1a ... Facilities
1b Data measurement means
1c: Centralized control means for equipment
1d, 2a ... Communication interface
1e: display means
3. Communication means
4: Central management device
4a: Operating state determination means
4b Data processing means
4c: First operating state diagnostic means
4d: Diagnosis item selection means
4e... Second operating state diagnostic means
4f: Trouble cause component estimation means
4g ... Diagnostic result display means
5a: Diagnosis level value database
5b: Trouble occurrence database

Claims (6)

設備に設置した測定手段で設備の動作状態を定期的に測定し、その測定データを収集し、収集した測定データにより該設備を診断する設備の劣化診断方法において、
収集した測定データが診断レベル値データベースに予め設定されている診断レベル値を越えているかどうかを比較する劣化診断を行い、さらにトラブル発生原因データベースにて、発生原因の可能性大の部位あるいは部品を選択し、トラブル発生原因部位あるいは部品を推定することを特徴とする設備の劣化診断方法。
In the equipment deterioration diagnosis method of periodically measuring the operation state of the equipment with the measuring means installed in the equipment, collecting the measurement data, and diagnosing the equipment with the collected measurement data,
Perform a deterioration diagnosis to compare whether the collected measurement data exceeds the diagnosis level value preset in the diagnosis level database, and further check the trouble occurrence cause database for parts or parts that have a high possibility of occurrence. A method for diagnosing deterioration of equipment, comprising selecting and estimating a trouble-causing site or part.
上記請求項1に記載の設備の劣化診断方法において、さらに該トラブル発生原因部位あるいは部品の部品在庫検索手段にて該当する部品の在庫状況を検索することを特徴とする設備の劣化診断方法。2. The method for diagnosing deterioration of equipment according to claim 1, further comprising the step of searching for a part where the trouble has occurred or the part inventory status of the part by means of a part inventory search means for the part. 上記請求項1あるいは請求項2に記載の設備の劣化診断方法において、
診断レベル値に対する測定データの比率を算出して近接度を求めることを各診断項目について行い、それらの近接度を比率の大きい順に並べてトラブル発生順位付けを行い、さらに、各診断項目に関連する複数の診断項目があれば、該関連する複数の診断項目における近接度の高いものからトラブル発生原因部位あるいは部品を推定することを特徴とする設備の劣化診断方法。
In the method for diagnosing deterioration of equipment according to claim 1 or 2,
Calculating the ratio of the measurement data to the diagnostic level value to determine the proximity is performed for each diagnosis item, and the proximity is arranged in descending order of the ratio to rank trouble occurrences. A deterioration diagnosis method for a facility characterized by estimating a trouble-causing site or a part from a plurality of related diagnosis items having a high degree of proximity, if any.
上記請求項1あるいは請求項2に記載の設備の劣化診断方法において、さらに第2の劣化診断結果に基づいて運転改良内容を表示手段に表示して、運転改良の警報表示を行うことを特徴とする設備の劣化診断方法。The method for diagnosing deterioration of equipment according to claim 1 or 2, further comprising the step of displaying operation improvement contents on a display means based on the second deterioration diagnosis result, and performing an alarm display of operation improvement. Method for diagnosing equipment deterioration. 設備に設置した測定手段で設備の動作状態を定期的に測定し、その測定データを収集し、収集した測定データにより該設備を診断する設備の劣化診断装置において、
診断項目に対応する測定データが診断レベル値データベースに予め設定されている診断レベル値を越えているかどうか比較する診断手段と、
該診断項目についてトラブル発生原因データベースにより、トラブル発生原因の可能性大の部位あるいは部品を推定する推定手段
を備えたことを特徴とする設備の劣化診断装置。
In the equipment deterioration diagnosis device that periodically measures the operation state of the equipment with the measuring means installed in the equipment, collects the measurement data, and diagnoses the equipment with the collected measurement data,
Diagnostic means for comparing whether measurement data corresponding to a diagnostic item exceeds a diagnostic level value preset in a diagnostic level value database,
An equipment deterioration diagnosis apparatus characterized by comprising an estimating means for estimating a part or a part having a large possibility of a trouble occurrence cause using a trouble occurrence cause database for the diagnosis item.
上記請求項5に記載の設備の劣化診断装置において、さらに、該推定手段で推定したトラブル発生原因の可能性が大である部品の在庫状況を検索表示する、該当部品在庫検索手段と、
を備えたことを特徴とする設備の劣化診断装置。
6. The equipment deterioration diagnosis apparatus according to claim 5, further comprising: a corresponding parts inventory search means for searching and displaying a stock status of parts having a high possibility of a trouble occurrence estimated by the estimation means;
An equipment deterioration diagnosis device, comprising:
JP2003015499A 2003-01-24 2003-01-24 Method and device for diagnosing deterioration of facilities Pending JP2004227357A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003015499A JP2004227357A (en) 2003-01-24 2003-01-24 Method and device for diagnosing deterioration of facilities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003015499A JP2004227357A (en) 2003-01-24 2003-01-24 Method and device for diagnosing deterioration of facilities

Publications (1)

Publication Number Publication Date
JP2004227357A true JP2004227357A (en) 2004-08-12

Family

ID=32903228

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003015499A Pending JP2004227357A (en) 2003-01-24 2003-01-24 Method and device for diagnosing deterioration of facilities

Country Status (1)

Country Link
JP (1) JP2004227357A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2007122902A1 (en) * 2006-03-24 2007-11-01 Hitachi Kokusai Electric Inc. Substrate treating device managing method
JP2010113672A (en) * 2008-11-10 2010-05-20 Hitachi Ltd Terminal, program, and inventory management method
WO2014003178A1 (en) * 2012-06-29 2014-01-03 株式会社日立製作所 Control system for machinery and equipment
JP2016177800A (en) * 2015-03-20 2016-10-06 東洋ビルメンテナンス株式会社 Inspection management device, inspection support system, inspection management method, inspection support method, inspection management program, and inspection support program
JPWO2016117021A1 (en) * 2015-01-20 2017-07-13 株式会社日立製作所 Machine diagnostic device and machine diagnostic method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2007122902A1 (en) * 2006-03-24 2007-11-01 Hitachi Kokusai Electric Inc. Substrate treating device managing method
US7930049B2 (en) 2006-03-24 2011-04-19 Hitachi Kokusai Electric Inc. Control method for a substrate processing apparatus
JP2010113672A (en) * 2008-11-10 2010-05-20 Hitachi Ltd Terminal, program, and inventory management method
WO2014003178A1 (en) * 2012-06-29 2014-01-03 株式会社日立製作所 Control system for machinery and equipment
CN104246638A (en) * 2012-06-29 2014-12-24 株式会社日立制作所 Control system for machinery and equipment
CN108762236A (en) * 2012-06-29 2018-11-06 株式会社日立产机*** The management system of mechanical equipment
JPWO2016117021A1 (en) * 2015-01-20 2017-07-13 株式会社日立製作所 Machine diagnostic device and machine diagnostic method
US10295995B2 (en) 2015-01-20 2019-05-21 Hitachi, Ltd. Machine diagnostic apparatus and machine diagnostic method
JP2016177800A (en) * 2015-03-20 2016-10-06 東洋ビルメンテナンス株式会社 Inspection management device, inspection support system, inspection management method, inspection support method, inspection management program, and inspection support program

Similar Documents

Publication Publication Date Title
EP1111550B1 (en) Method and system for monitoring the condition of an individual machine
JP5129725B2 (en) Device abnormality diagnosis method and system
EP1538503A1 (en) Distributed power generation plant automated event assessment and mitigation plan determination process
CN110347124A (en) The diagnostic service system and diagnostic method of network is utilized
JP2000259222A (en) Device monitoring and preventive maintenance system
JP4067811B2 (en) Remote monitoring system and remote monitoring method for high temperature parts
JP2008088961A (en) Gas turbine performance diagnostic system and diagnostic method, and display screen
EP3944043B1 (en) Maintenance work assistance device
JP2007140997A (en) Apparatus for diagnosing fault
JP6176377B1 (en) Equipment management system, equipment management method and program
JP4056032B2 (en) Plant equipment management device
JP2013085355A (en) Management method of maintenance inspection information and management system
US20020138169A1 (en) Device for calculating overall plant efficiency
JP2004227357A (en) Method and device for diagnosing deterioration of facilities
CN110687851A (en) Terminal operation monitoring system and method
CN111258868B (en) Method and system for automatically monitoring and acquiring equipment data
JP2004152017A (en) Maintenance system evaluation device for evaluating maintenance system for facility, maintenance system evaluation method, and program and recording medium for making computer implement the method
JP7329753B2 (en) Information processing device, information processing method, and learning device
JP2003208220A (en) Method and device for diagnosing deterioration of facility
US20230011992A1 (en) Diagnostic device, diagnostic method, and recording medium
JP2005284982A (en) Abnormality diagnosis apparatus, abnormality diagnosis method, power generator monitoring system, and fuel exhaustion notification device
JP2009080649A (en) Production quality system
JP2008140109A (en) Process operation support apparatus, and process operation support method
JP7019978B2 (en) Equipment management system, equipment management method and program
JP5831197B2 (en) Evaluation apparatus, evaluation method, and evaluation program