Method for joining steel plate

Info

Publication number
JP2002303012A
JP2002303012A JP2001110563A JP2001110563A JP2002303012A JP 2002303012 A JP2002303012 A JP 2002303012A JP 2001110563 A JP2001110563 A JP 2001110563A JP 2001110563 A JP2001110563 A JP 2001110563A JP 2002303012 A JP2002303012 A JP 2002303012A
Authority
JP
Japan
Prior art keywords
steel plate
hole
stud bolt
base member
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001110563A
Other languages
Japanese (ja)
Inventor
Minoru Kanazawa
稔 金沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2001110563A priority Critical patent/JP2002303012A/en
Publication of JP2002303012A publication Critical patent/JP2002303012A/en
Pending legal-status Critical Current

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method for joining a steel plate, in which the steel plate can be joined simply to a substrate member without generating welding distortions. SOLUTION: A through-hole 6 is formed previously to the steel plate 4 in response to a site joined with the substrate member 2, and the steel plate 4 is attached closely to the substrate member 2 (Fig. 1 (a)). A stud bolt 16 and a sleeve 14 are inserted into the through-hole 6. The sleeve 14 is formed of an electrical insulating material, is interposed between the stud bolt 16 and the inner circumferential section 6a of the through-hole 6 and electrically insulated both the stud bolt and the inner circumferential section of the through-hole (Fig.1 (b)). Voltage is applied between the stud bolt 16 and the substrate member 2, and both the stud bolt and the substrate member are unified by arc welding. The sleeve 14 is removed, after welding and a nut 24 is installed to the stud bolt 16, and the steel plate 4 is clamped and fixed on the substrate member 2 side by the nut 24 (Fig.1 (c)).

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、鉄骨材等の下地部
材に鋼板を接合する方法に関し、特に鋼板に溶接歪み等
を生じることなく簡単に接合することができる方法に関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for joining a steel sheet to a base member such as a steel frame material, and more particularly to a method for easily joining a steel sheet without causing welding distortion or the like.

【0002】[0002]

【従来の技術】最近、工期の短縮や作業効率の向上を目
的として、鋼板コンクリート構造(SC構造)により構
築されるコンクリート構造物が登場している。この鋼板
コンクリート構造は、壁や床、天井等を構成する下地フ
レームを山形鋼や溝形鋼をはじめとする各種鉄骨材やア
ングル材等により構築し、この下地フレームに外側から
鋼板を張り付けて型枠を構成する。この型枠にコンクリ
ートを打設して、外側が鋼板により覆われたコンクリー
ト構造体を形成する。通常のコンクリート構造物の構築
に比べて型枠を撤去する必要がなく、型枠として使用し
た鋼板をそのまま仕上材や補強材として利用でき、材料
コストの削減が期待できるとともに、工期の短縮や作業
効率の向上をも図れる。
2. Description of the Related Art Recently, concrete structures constructed with a steel plate concrete structure (SC structure) have appeared for the purpose of shortening the construction period and improving work efficiency. In this steel plate concrete structure, the base frame that constitutes the walls, floor, ceiling, etc. is constructed from various steel frames and angle materials such as angle steel and channel steel, and a steel plate is attached to the base frame from the outside to form a mold. Make up the frame. Concrete is poured into the formwork to form a concrete structure whose outside is covered with a steel plate. Compared with the construction of ordinary concrete structures, there is no need to remove the formwork, and the steel plate used as the formwork can be used as a finishing material or reinforcing material as it is, which can reduce material costs, shorten the construction period and work Efficiency can be improved.

【0003】このような鋼板コンクリート構造物の構築
において、下地フレームに対し鋼板を張り付ける場合に
アーク式スタッド溶接法(特許第2909482号(特
開平7−323373号)等参照)が採用されていた。
このアーク式スタッド溶接法は、図5に示すように、あ
らかじめ鋼板4に下地部材2との接合位置に対応して貫
通孔6を形成しておき、鋼板4を下地部材2に密接させ
た後、貫通孔6に溶接ガンのスタッド7を当てて溶接を
行う。スタッド7外周には当該貫通孔6の開口部を覆っ
て溶融部の酸化を防止するためにアークシールド(フェ
ルール)8が取付けられる。そして、溶接ガンのスタッ
ド7の先端部7aと下地部材2との間にアーク放電を発
生させてスタッド7の先端部7aを溶融させるととも
に、その周辺部、即ち貫通孔6の内周部や下地部材2の
密接部をも溶融させて、図6に示すように、貫通孔6に
栓をするような溶接部9を形成して、この溶接部9によ
り鋼板4を下地部材2に一体的に接合するようになって
いる。1つの貫通孔6に対する溶接時間は通常0.5〜
1.0秒前後であり、作業はきわめて短時間で終了す
る。
[0003] In the construction of such a steel plate concrete structure, an arc stud welding method (see Japanese Patent No. 2909482 (Japanese Patent Application Laid-Open No. 7-323373)) has been adopted when a steel plate is stuck to an underlying frame. .
In this arc stud welding method, as shown in FIG. 5, a through hole 6 is formed in a steel plate 4 in advance corresponding to a joining position with the base member 2, and the steel plate 4 is brought into close contact with the base member 2. Then, welding is performed by applying a stud 7 of a welding gun to the through hole 6. An arc shield (ferrule) 8 is attached to the outer periphery of the stud 7 to cover the opening of the through hole 6 and prevent oxidation of the molten portion. Then, an arc discharge is generated between the tip 7a of the stud 7 of the welding gun and the base member 2 to melt the tip 7a of the stud 7 and the periphery thereof, that is, the inner periphery of the through hole 6 and the base. As shown in FIG. 6, a welded portion 9 that plugs the through hole 6 is formed by also melting the close contact portion of the member 2, and the steel plate 4 is integrated with the base member 2 by the welded portion 9. It is designed to join. The welding time for one through hole 6 is usually 0.5 to
This is about 1.0 second, and the work is completed in a very short time.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、このよ
うなアーク式スタッド溶接法を利用した鋼板の接合方法
には次のような問題点があった。すなわち、この接合方
法では、貫通孔6の内周部や下地部材2を溶融して貫通
孔6に栓をするような溶接部9を形成して鋼板4を下地
部材2に一体接合するようになっているから、貫通孔6
の周辺部が変形し、これによって鋼板4に歪みが生じる
という問題があった。この溶接歪みは、鋼板4に対して
後から塗装等の仕上処理を施す際に非常に障害になると
ともに美観を損ない、見栄えを悪化させるという問題を
引き起こした。
However, the method of joining steel sheets using the arc stud welding method has the following problems. That is, in this joining method, the steel plate 4 is integrally joined to the base member 2 by forming a welded portion 9 that melts the inner peripheral portion of the through hole 6 and the base member 2 to plug the through hole 6. The through hole 6
There is a problem that the peripheral portion of the steel sheet 4 is deformed, thereby causing distortion of the steel sheet 4. This welding distortion causes a problem that when the steel sheet 4 is subjected to a finishing treatment such as painting afterwards, it becomes a great obstacle, impairs aesthetic appearance, and deteriorates appearance.

【0005】本発明は、このような事情に鑑みてなされ
たものであって、その目的は、溶接歪みが発生すること
なく鋼板を下地部材に簡単に接合することができるよう
な鋼板の接合方法を提供することにある。
The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a method of joining steel sheets so that the steel sheets can be easily joined to a base member without generating welding distortion. Is to provide.

【0006】[0006]

【課題を解決するための手段】このような目的を達成す
るために本発明に係る鋼板の接合方法にあっては、鉄骨
材等の下地部材に鋼板を接合する方法であって、あらか
じめ前記鋼板に前記下地部材と接合される部位に対応し
て貫通孔を設けておき、前記鋼板を前記下地部材に密接
させた後、前記貫通孔にスタッドボルトを挿入するとと
もに前記貫通孔と当該スタッドボルトとの間に両者を電
気的に絶縁する絶縁材を介設し、そして前記スタッドボ
ルトと前記下地部材との間に電圧を印加して両者をアー
ク溶接により一体化し、その後、前記スタッドボルトに
ナットを装着して当該ナットで前記鋼板を前記下地部材
に締め付けて接合することを特徴とする(請求項1)。
In order to achieve the above object, a method of joining steel sheets according to the present invention is a method of joining steel sheets to a base member such as a steel frame material. A through hole is provided corresponding to a portion to be joined to the base member, and after the steel plate is brought into close contact with the base member, a stud bolt is inserted into the through hole and the through hole, the stud bolt and An insulating material that electrically insulates both is interposed therebetween, and a voltage is applied between the stud bolt and the base member to integrate the two by arc welding, and then a nut is attached to the stud bolt. The steel plate is attached and fastened to the base member with the nut to join the steel plate (claim 1).

【0007】この接合方法にあっては、鋼板に形成され
た貫通孔にスタッドボルトを挿入するとともに、スタッ
ドボルトと鋼板との間に絶縁材を介設するから、スタッ
ドボルトと下地部材との間だけをアーク溶接により一体
化することができ、鋼板は、下地部材に一体的に固設さ
れたスタッドボルトを通じてナットにより締め付けられ
て接合され、鋼板自体は溶融することがないから、鋼板
に溶接歪みが生じることはない。このことから、従来の
ように鋼板に対して後から塗装等の仕上を施すときでも
様々な障害が生じることがなく、良好に仕上げ処理を行
うことができる。また、溶融する部分は、スタッドボル
トと下地部材との間と非常に限られた部分だけなので、
鋼板を下地部材に対し側方からや下側からの接合も容易
に可能である。また、絶縁材をアークシールド(フェル
ール)として利用して溶融部の酸化を可及的に防止する
ことができる。
In this joining method, a stud bolt is inserted into a through hole formed in a steel plate and an insulating material is interposed between the stud bolt and the steel plate. Can be integrated by arc welding, and the steel sheet is joined by being tightened with nuts through stud bolts integrally fixed to the base member, and the steel sheet itself does not melt, so welding distortion Does not occur. For this reason, various obstacles do not occur even when the steel sheet is later subjected to finishing such as painting as in the related art, and the finishing treatment can be performed satisfactorily. Also, since the melting part is only a very limited part between the stud bolt and the base member,
It is also possible to easily join the steel plate to the base member from the side or from below. In addition, the insulating material can be used as an arc shield (ferrule) to prevent oxidation of the molten portion as much as possible.

【0008】また、この接合方法にあっては、前記下地
部材と前記鋼板との間に両者間の隙間を閉塞するための
スペーサを介設することを特徴とする(請求項2)。ス
ペーサの介設によって、下地部材と鋼板との間に生じる
隙間をなくして安定した状態で密接させることができ、
溶接作業を良好に実施することができる。
Further, in this bonding method, a spacer is provided between the base member and the steel plate for closing a gap therebetween. By the interposition of the spacer, it is possible to eliminate the gap generated between the base member and the steel plate, and to make a close contact in a stable state,
The welding operation can be performed well.

【0009】また、この接合方法にあっては、前記ナッ
トとして袋ナットを使用することを特徴とする(請求項
3)。袋ナットを使用することで、スタッドボルトの端
部を覆って外観上の見栄えを向上させることができる。
[0009] In this joining method, a cap nut is used as the nut. By using the cap nut, the end of the stud bolt can be covered and the appearance can be improved.

【0010】またさらにこの接合方法にあっては、前記
絶縁材として前記貫通孔内にスリーブを挿入することを
特徴とする(請求項4)。絶縁材としてスリーブを挿入
することで、スタッドボルトと貫通孔との間に簡単に絶
縁材を介設することができる。介設作業を簡略化して作
業の手間を軽減することができ、作業時間の短縮を図る
ことができる。
Further, in this bonding method, a sleeve is inserted into the through hole as the insulating material. By inserting a sleeve as an insulating material, the insulating material can be easily provided between the stud bolt and the through hole. The installation work can be simplified, the labor of the work can be reduced, and the work time can be shortened.

【0011】このスリーブにあっては、前記スタッドボ
ルトに前記ナットを装着する際に前記貫通孔から撤去す
るのが望ましい(請求項5)。スリーブを貫通孔から撤
去することで、再びこのスリーブを別の貫通孔において
絶縁材として再利用することができる。
In the sleeve, it is preferable that the sleeve be removed from the through hole when the nut is mounted on the stud bolt. By removing the sleeve from the through hole, the sleeve can be reused again as an insulating material in another through hole.

【0012】またさらにこの接合方法にあっては、前記
貫通孔の内周部に前記スタッドボルトの挿入側に向かっ
て漸次拡径して形成されたテーパ部が設けられていると
ともに、前記スリーブ及び前記ナットの外周部に前記貫
通孔のテーパ部に密着されるテーパ部が設けられている
ことが望ましい(請求項6)。このようなテーパ部が貫
通孔の内周部またはスリーブ若しくはナットの外周部に
設けられていることで、ナットと鋼板の間に十分な接触
面積を確保することができるとともに、ナットの締め付
け力を鋼板に対して良好に伝達することができ、鋼板を
下地部材に対し十分に固定することができる。特に鋼板
コンクリート構造物においては、鋼板の面内・面外の応
力を下地鉄骨にズレ無く良好に伝達することができる。
また、スリーブによって溶接時を溶接部と外部とを十分
に遮断してスリーブをアークシールドとして十分な機能
を発揮させることができる。
Further, in this joining method, a tapered portion is formed on an inner peripheral portion of the through hole so as to gradually increase in diameter toward an insertion side of the stud bolt. It is preferable that a tapered portion closely contacting the tapered portion of the through hole is provided on an outer peripheral portion of the nut (claim 6). By providing such a tapered portion on the inner peripheral portion of the through hole or the outer peripheral portion of the sleeve or the nut, a sufficient contact area can be secured between the nut and the steel plate, and the tightening force of the nut is reduced. Good transmission to the steel sheet can be achieved, and the steel sheet can be sufficiently fixed to the base member. In particular, in the case of a steel plate concrete structure, the in-plane and out-of-plane stresses of the steel plate can be satisfactorily transmitted to the base steel frame without displacement.
In addition, the sleeve can sufficiently shield the welded portion from the outside during welding, and the sleeve can exhibit a sufficient function as an arc shield.

【0013】またさらにこの接合方法にあっては、前記
スリーブの外周部に軸方向に沿ってガス抜き溝部が設け
られていることを特徴とする(請求項7)。このガス抜
き溝部を通じてアーク溶接により発生したガスを外部に
排出して、溶接品質の向上を図ることができる。
Further, in this joining method, a gas vent groove is provided along an axial direction on an outer peripheral portion of the sleeve (claim 7). The gas generated by the arc welding is discharged to the outside through the gas vent groove, so that the welding quality can be improved.

【0014】[0014]

【発明の実施の形態】以下に本発明に係る鋼板の接合方
法の実施の形態について添付図面を用いて説明する。図
1は、本発明に係る鋼板の接合方法の一実施形態を示し
たものである。なお、従来と同一の構成要素には同一の
符号を付すものとする。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a method for joining steel sheets according to the present invention will be described below with reference to the accompanying drawings. FIG. 1 shows an embodiment of a method for joining steel sheets according to the present invention. Note that the same components as those of the related art are denoted by the same reference numerals.

【0015】この方法は、各種鋼板4を山形鋼や溝形鋼
をはじめとする各種鉄骨材やアングル材等の下地部材2
に接合するのに適用される方法である。まず、図1
(a)に示すように、鋼板4にあらかじめ下地部材2が
接合される部位に対応して貫通孔6を形成しておく。こ
の貫通孔6は、下地部材2と鋼板4とを一体的に接合す
るために設けられるもので、鋼板4には、下地部材2が
接合される部位に沿って複数箇所にわたって設けられて
いる。本実施形態では、この貫通孔6が、下地部材に密
接した側から反対側に向かって内形寸法が漸次拡径され
て形成され、貫通孔6の内周部にはテーパ部6aが設け
られている。
In this method, various steel plates 4 are formed on a base member 2 made of various steel members such as angle irons and channel steels and angle materials.
This is the method applied for bonding to First, FIG.
As shown in (a), through holes 6 are formed in the steel plate 4 in advance corresponding to the portions where the base member 2 is joined. The through holes 6 are provided for integrally joining the base member 2 and the steel plate 4, and are provided in the steel plate 4 at a plurality of locations along the portion where the base member 2 is joined. In the present embodiment, the through-hole 6 is formed such that the inner dimension is gradually increased from the side in close contact with the base member to the opposite side, and a tapered portion 6 a is provided in the inner peripheral portion of the through-hole 6. ing.

【0016】次に、このようなテーパ部6aを有する貫
通孔6内に、図1(b)に示すようにスリーブ14とス
タッドボルト16とを挿入する。スリーブ14は、プラ
スチック材やゴム材をはじめとする各種電気絶縁材料に
より形成された部材で、図2に示すように、下端面から
上端面にかけて外形寸法が漸次拡径されて形成され、外
形形状がコーン形状をなしている。その外周部にはテー
パ部14aが設けられ、鋼板4の貫通孔6のテーパ部6
aに密着されるようになっている。また、その高さは、
鋼板4の板厚よりも短くして、下地部材2との間に溶接
用の隙間30を確保する。この隙間30は、後述する溶
接において溶融金属の盛り上がりを吸収するのに利用さ
れる。
Next, as shown in FIG. 1B, a sleeve 14 and a stud bolt 16 are inserted into the through hole 6 having such a tapered portion 6a. The sleeve 14 is a member formed of various electrical insulating materials such as a plastic material and a rubber material. As shown in FIG. 2, the sleeve 14 is formed by gradually increasing its outer dimension from the lower end surface to the upper end surface. Has a cone shape. A tapered portion 14 a is provided on an outer peripheral portion of the steel plate 4.
a. Also, its height is
A gap 30 for welding is secured between the steel plate 4 and the base member 2 by making the thickness smaller than the thickness of the steel plate 4. The gap 30 is used to absorb the swelling of the molten metal in welding described later.

【0017】また、その中央部には軸方向に沿って断面
円形状に中空部20が形成されている。この中空部20
はその上下両端部がスリーブ14の上端面及び下端面に
それぞれ開放され、スタッドボルト16はこの中空部2
0に挿入されて収容されるようになっている。中空部2
0の内径寸法はスタッドボルト16の外径寸法に相応し
て形成されている。
A hollow portion 20 is formed in the center at a circular section along the axial direction. This hollow part 20
The upper and lower ends of the sleeve 14 are open to the upper end surface and the lower end surface of the sleeve 14, respectively.
0 to be accommodated. Hollow part 2
The inner diameter of 0 is formed corresponding to the outer diameter of the stud bolt 16.

【0018】また、スリーブ14の外周部(テーパ部)
14aには、その表面部に沿って上端部から下端部にか
けて断面凹形状のガス抜き溝部22が形成されている。
このガス抜き溝部22は、スリーブ14が貫通孔6内に
挿入されたとき、鋼板4の貫通孔6の内周面とスリーブ
14との間に空隙部を形成して、後述する溶接工程にお
いてスタッドボルト16と下地部材2との間に行われる
アーク溶接により発生するガスを外部に排出する役割を
果たす。本実施形態では、このガス抜き溝部22がスリ
ーブ14の外周方向に沿って等間隔に4本形成されてい
る。スリーブ14は、スタッドボルト16と鋼板4の貫
通孔6の内周部6aとの間に介設され、鋼板4とスタッ
ドボルト16との間を電気的に絶縁するようになってい
る。
The outer peripheral portion (taper portion) of the sleeve 14
A gas vent groove 22 having a concave cross section is formed in the surface 14a from the upper end to the lower end along the surface.
When the sleeve 14 is inserted into the through hole 6, the gas vent groove 22 forms a gap between the inner peripheral surface of the through hole 6 of the steel plate 4 and the sleeve 14, and a stud is formed in a welding process described later. It serves to discharge gas generated by arc welding performed between the bolt 16 and the base member 2 to the outside. In the present embodiment, four gas vent grooves 22 are formed at equal intervals along the outer peripheral direction of the sleeve 14. The sleeve 14 is interposed between the stud bolt 16 and the inner peripheral portion 6 a of the through hole 6 of the steel plate 4, and electrically insulates the steel plate 4 from the stud bolt 16.

【0019】一方、スタッドボルト16は、断面円形状
に成形された丸棒状の部材であり、その外周部に雌ネジ
部16aが形成されている。本実施形態では、スタッド
ボルト16の長さは、鋼板の肉厚と同等若しくはこれよ
りも若干短く設定されている。
On the other hand, the stud bolt 16 is a round bar-shaped member formed in a circular cross section, and a female screw portion 16a is formed on an outer peripheral portion thereof. In the present embodiment, the length of the stud bolt 16 is set to be equal to or slightly shorter than the thickness of the steel plate.

【0020】これらスリーブ14およびスタッドボルト
16の挿入順序としては、先にスリーブ14を貫通孔6
内にはめ込んでから、スタッドボルト16をスリーブ1
4の中空部に挿入する形で後からはめ込むようにするの
が好ましい。スタッドボルト16の位置決めを容易に行
うことができ、スタッドボルト16の正しい位置に配置
することができる。
The order of inserting the sleeve 14 and the stud bolt 16 is as follows.
After inserting the stud bolt 16 into the sleeve 1
It is preferable to insert it into the hollow portion of No. 4 later. The stud bolt 16 can be easily positioned, and can be arranged at the correct position of the stud bolt 16.

【0021】このようにして鋼板4の貫通孔6にスリー
ブ14とスタッドボルト16を挿入した後、スタッドボ
ルト16と下地部材2との間に電圧を印加して、スタッ
ドボルト16と下地部材2とをアーク溶接する。ここ
で、スタッドボルト16と鋼板4との間には、絶縁材料
により形成されたスリーブ14が介在しているから、鋼
板4とスタッドボルト16との間にはアーク放電が生じ
ることはなく、両者が溶接されることはなく、鋼板に溶
接歪みが発生することはない。また、この溶接では、ス
タッドボルト16の先端部と下地部材2の表面部との間
にのみ電流を流して、あまり溶融させることなく効率よ
く溶接することができるから、ごく短時間で行われ、作
業にきわめてスムーズに行うことができる。また、この
溶接では、貫通孔にはめ込まれたスリーブ14が、溶接
部を外部と遮断するアークシールド(フェルール)とし
て働き、スタッドボルト16と鋼板4の貫通孔の内周部
との間の隙間を閉鎖して溶接部の酸化を防止する。ま
た、溶接により発生したガスは、スリーブ14に形成さ
れたガス抜き溝部22を通じて外部に排出することがで
きる。この溶接によってスタッドボルト16は下地部材
2に一体的に固設される。
After the sleeve 14 and the stud bolt 16 are inserted into the through hole 6 of the steel plate 4 in this manner, a voltage is applied between the stud bolt 16 and the base member 2 so that the stud bolt 16 and the base member 2 Arc welding. Here, since the sleeve 14 made of an insulating material is interposed between the stud bolt 16 and the steel plate 4, no arc discharge occurs between the steel plate 4 and the stud bolt 16. Is not welded, and no welding distortion occurs in the steel sheet. In addition, in this welding, current is applied only between the tip of the stud bolt 16 and the surface of the base member 2, and welding can be performed efficiently without melting much. Work can be performed very smoothly. Further, in this welding, the sleeve 14 fitted into the through hole functions as an arc shield (ferrule) for blocking the welded portion from the outside, and forms a gap between the stud bolt 16 and the inner peripheral portion of the through hole of the steel plate 4. Close to prevent oxidation of welds. In addition, gas generated by welding can be discharged to the outside through the gas vent groove 22 formed in the sleeve 14. By this welding, the stud bolt 16 is integrally fixed to the base member 2.

【0022】次に、図1(c)に示すように、貫通孔6
内からスリーブ14を撤去し、その後、スタッドボルト
16に図1(c)に示すようなナット24を装着する。
ナット24の内周部にはスタッドボルト16の雄ネジ部
16aに螺合する雌ネジ部24aが形成されている。さ
らに本実施形態では、このナット24がその上端部が閉
塞されて袋状に形成されて袋ナットになっていて、スタ
ッドボルトに装着した際にスタッドボルト16の突端部
を外側から覆い隠して見栄えを良くするようになってい
る。当該ナット24をスタッドボルト16に装着した後
に、当該鋼板4により形成されるコンクリート構造体の
壁面等への仕上作業を容易にすることができる。
Next, as shown in FIG.
After removing the sleeve 14 from the inside, a nut 24 as shown in FIG. 1C is attached to the stud bolt 16.
On the inner peripheral portion of the nut 24, a female screw portion 24a screwed to the male screw portion 16a of the stud bolt 16 is formed. Further, in the present embodiment, the nut 24 is formed in a bag shape by closing its upper end portion so as to form a bag nut. Is to improve. After the nut 24 is attached to the stud bolt 16, the finishing work on the wall surface or the like of the concrete structure formed by the steel plate 4 can be facilitated.

【0023】また、このナット24は、スリーブ14と
同様に、その外径寸法が下端面から上端面にかけて漸次
拡径されており、その高さは、アーク溶接による溶融金
属の盛り上がり部分と干渉しないように鋼板4の板厚よ
りも短くなっている。また、その全体形状はコーン状を
なし、その外周部にはテーパ部24bが形成されてい
る。このテーパ部24aは、ナット24が貫通穴6内の
奥深くにまでねじ込まれたときに当該貫通孔6の内周部
のテーパ部6aに当接して当該テーパ部6aを押圧する
ようになっている。これによって、ナット24はその締
め付け力がこれらテーパ部24a,6aを介して鋼板4
に伝達されるようになっており、下地部材2との間に鋼
板4を挟み込み、鋼板4を下地部材2に一体的に接合す
るようになっている。
The outer diameter of the nut 24, like the sleeve 14, is gradually increased from the lower end surface to the upper end surface, and its height does not interfere with the raised portion of the molten metal by arc welding. Thus, it is shorter than the thickness of the steel plate 4. The overall shape is a cone, and a tapered portion 24b is formed on the outer periphery. When the nut 24 is screwed deeply into the through hole 6, the tapered portion 24a comes into contact with the inner peripheral portion of the through hole 6 to press the tapered portion 6a. . As a result, the fastening force of the nut 24 is reduced by the steel plate 4 via the tapered portions 24a and 6a.
The steel plate 4 is sandwiched between the base member 2 and the steel plate 4 is integrally joined to the base member 2.

【0024】ナット24の閉塞された上端部について
は、ナット24が貫通孔内に奥深くねじ込まれて貫通孔
6内にすっぽり収容されたときに鋼板4の外表面と面一
になるようにその長さが寸法設定されるのが好ましい。
The closed upper end of the nut 24 is so long that it is flush with the outer surface of the steel plate 4 when the nut 24 is screwed deeply into the through hole and is completely accommodated in the through hole 6. Is preferably dimensioned.

【0025】なお、撤去したスリーブ14については、
再び他の貫通孔においてスタッドボルトを下地部材に溶
接する際に利用して転用を図るとよい。
The removed sleeve 14 is
It is preferable to use the stud bolt again when welding the stud bolt to the base member in another through hole.

【0026】以上この鋼板の接合方法にあっては、鋼板
4に形成された貫通孔6にスタッドボルト16を挿入す
るとともに、スタッドボルト16と鋼板4との間にスリ
ーブ14を介設するから、スタッドボルト16と下地部
材2との間だけをアーク溶接により一体化することがで
き、鋼板4自体は、下地部材2に一体的に固設されたス
タッドボルト16を通じてナット24により締め付けら
れて接合され、溶接されることがなく、溶接歪みが生じ
ることはない。このようなことから、従来のように鋼板
4に対して後から塗装等の仕上を施すときでも様々な障
害が生じることがなく、良好に仕上げ処理を行うことが
できる。また、溶融部が非常に少なくて済むことから、
このように鋼板を下地部材に対して上方から接合する場
合以外にも、側方から接合することや下側から接合する
ことを容易に行うことができる。
In this method of joining steel plates, the stud bolt 16 is inserted into the through hole 6 formed in the steel plate 4 and the sleeve 14 is interposed between the stud bolt 16 and the steel plate 4. Only the stud bolt 16 and the base member 2 can be integrated by arc welding, and the steel plate 4 itself is joined by being tightened by the nut 24 through the stud bolt 16 integrally fixed to the base member 2. , And no welding distortion occurs. For this reason, various obstacles do not occur even when the steel plate 4 is later subjected to finishing such as painting, as in the related art, and the finishing process can be performed satisfactorily. Also, since the melting part is very small,
In addition to the case where the steel sheet is joined to the base member from above, joining from the side and joining from below can be easily performed.

【0027】また、貫通孔6の内周部に外側に向かって
漸次拡径形成されたテーパ部6aが設けられ、かつナッ
ト24の外周部にこのテーパ部6aに対応して形成され
たテーパ部が設けられているから、ナット24が鋼板4
に接触した際に両者の間に十分な接触面積を確保するこ
とができるとともに、ナット24の締め付け力を鋼板4
に対して良好に伝達することができ、鋼板4を下地部材
2に対し十分に固定することができる。
A tapered portion 6a whose diameter is gradually increased toward the outside is provided on the inner peripheral portion of the through hole 6, and a tapered portion formed on the outer peripheral portion of the nut 24 in correspondence with the tapered portion 6a. Is provided, the nut 24 is
When it comes into contact with the steel plate 4, a sufficient contact area can be secured between them and the tightening force of the nut 24 is
, And the steel plate 4 can be sufficiently fixed to the base member 2.

【0028】また、スリーブ14の外周部にはガス抜き
溝部22が設けられているから、スタッドボルト16と
下地部材2とをアーク溶接する際に発生するガスを外部
に良好に排出することができ、溶接品質の向上を図るこ
とができる。
Further, since the gas vent groove 22 is provided on the outer peripheral portion of the sleeve 14, the gas generated when the stud bolt 16 and the base member 2 are arc-welded can be discharged well to the outside. In addition, the welding quality can be improved.

【0029】なお、鋼板4と下地部材2との間に隙間が
生じる場合や、鋼板4の板厚が薄いためにアーク溶接に
よる溶融金属の盛り上がり分を考慮してナットの高さ寸
法を小さくすると十分な強度の確保ができない場合など
には、図3に示すように、鋼板4と下地部材2との間に
スペーサ26を介設すると良い。スペーサ26は、鋼板
4を下地部材2に密接する前に、鋼板4側または下地部
材2側のいずれかにあらかじめ設けておくと作業上好ま
しい。このように鋼板4と下地部材2との間にスペーサ
24を介設しておけば、鋼板4と下地部材2との間に隙
間が生じても両者を安定した状態で密接させることがで
きる。なお、このような隙間がある場合には、この隙間
を溶接時にガス抜き通路路として利用すると良い。
When a gap is formed between the steel plate 4 and the base member 2 or when the height of the nut is reduced in consideration of the swelling of the molten metal due to arc welding due to the small thickness of the steel plate 4, When sufficient strength cannot be secured, for example, as shown in FIG. 3, a spacer 26 may be provided between the steel plate 4 and the base member 2. The spacer 26 is preferably provided on either the steel plate 4 side or the base member 2 side before the steel plate 4 is brought into close contact with the base member 2 in terms of work. If the spacer 24 is interposed between the steel plate 4 and the base member 2 as described above, even if a gap is formed between the steel plate 4 and the base member 2, both can be stably brought into close contact with each other. If there is such a gap, it is preferable to use this gap as a gas vent passage during welding.

【0030】本実施形態にあっては、貫通孔6、ナット
24及びスリーブ14の各外周部に各々対応したテーパ
部6a,14a,24aが設けられているが、本発明に
あっては、これら貫通孔6、ナット24及びスリーブ1
4に必ずしもテーパ部6a,14a,24aが設けられ
ている必要はなく、単にストレートな円筒面状に成形さ
れていてもよい。
In the present embodiment, the tapered portions 6a, 14a and 24a corresponding to the outer peripheral portions of the through hole 6, the nut 24 and the sleeve 14, respectively, are provided. Through hole 6, nut 24 and sleeve 1
4 does not necessarily have to be provided with the tapered portions 6a, 14a, and 24a, and may be simply formed into a straight cylindrical surface.

【0031】また、本実施形態にあっては、スタッドボ
ルト16を下地部材2に一体的に固定した後、貫通孔6
内にはめ込まれていたスリーブ14を撤去するようにな
っていたが、必ずしもスリーブ14は撤去する必要はな
く、図4に示すようにそのまま貫通孔6内に残置してお
き、スタッドボルト16に装着したナット24で外側か
ら押さえ付けて鋼板4を下地部材2側に接合するような
構造を採用してもかまわない。
In this embodiment, after the stud bolt 16 is integrally fixed to the base member 2, the through hole 6
The sleeve 14 that had been fitted inside was to be removed, but the sleeve 14 does not necessarily need to be removed, and is left in the through hole 6 as shown in FIG. It is also possible to adopt a structure in which the steel plate 4 is joined to the base member 2 by pressing it from the outside with the nut 24 formed.

【0032】また、本実施形態では、スタッドボルト1
6と鋼板4の貫通孔6の内周部との間に絶縁材としてス
リーブ14を介設するが、本発明にあってはこれに限ら
ず、この他に例えば貫通孔の孔内面に樹脂等の絶縁材を
塗布して絶縁膜を絶縁材として形成したりするようにし
てもよい。
In the present embodiment, the stud bolt 1
A sleeve 14 is provided as an insulating material between the inner wall 6 of the steel plate 4 and the inner periphery of the through hole 6. However, the present invention is not limited to this. May be applied to form an insulating film as an insulating material.

【0033】[0033]

【発明の効果】本発明に係る鋼板の接合方法によれば、
鋼板に形成された貫通孔にスタッドボルトを挿入すると
ともに、スタッドボルトと鋼板との間に絶縁材を介設す
るから、スタッドボルトと下地部材との間だけをアーク
溶接により一体化することができ、鋼板は、下地部材に
一体的に固設されたスタッドボルトを通じてナットによ
り締め付けられて接合され、鋼板自体は溶融することが
ないから、鋼板に溶接歪みが生じることはない。このこ
とから、従来のように鋼板に対して後から塗装等の仕上
を施すときでも様々な障害が生じることがなく、良好に
仕上げ処理を行うことができる。また、溶融する部分
は、スタッドボルトと下地部材との間と非常に限られた
部分だけなので、鋼板を下地部材に対し側方からや下側
からの接合も容易に可能である。また、絶縁材をアーク
シールド(フェルール)として利用して溶融部の酸化を
可及的に防止することができる(請求項1)。
According to the method for joining steel sheets according to the present invention,
Since the stud bolt is inserted into the through hole formed in the steel plate and the insulating material is interposed between the stud bolt and the steel plate, only the stud bolt and the base member can be integrated by arc welding. The steel sheet is joined by being tightened by a nut through a stud bolt integrally fixed to the base member, and the steel sheet itself does not melt, so that no welding distortion occurs in the steel sheet. For this reason, various obstacles do not occur even when the steel sheet is later subjected to finishing such as painting as in the related art, and the finishing treatment can be performed satisfactorily. Further, since the portion to be melted is only a very limited portion between the stud bolt and the base member, the steel plate can be easily joined to the base member from the side or from below. In addition, the insulating material can be used as an arc shield (ferrule) to prevent oxidation of the molten portion as much as possible (claim 1).

【0034】さらにこの接合方法にあっては、前記下地
部材と前記鋼板との間に両者間の隙間を閉塞するための
スペーサを介設することで、下地部材と鋼板との間に生
じる隙間をなくして安定した状態で密接させることがで
き、溶接作業を良好に実施することができる(請求項
2)。
Further, in this joining method, a gap formed between the base member and the steel sheet is provided by interposing a spacer between the base member and the steel sheet to close the gap therebetween. It is possible to make a close contact in a stable state without doing so, and it is possible to carry out the welding work well (claim 2).

【0035】また、前記ナットとして袋ナットを使用す
ることで、スタッドボルトの端部を覆って外観上の見栄
えを向上させることができる(請求項3)。
Further, by using a cap nut as the nut, the end of the stud bolt can be covered to improve the external appearance (claim 3).

【0036】さらに、前記絶縁材として前記貫通孔内に
スリーブを挿入することで、絶縁材としてスリーブを挿
入することで、スタッドボルトと貫通孔との間に簡単に
絶縁材を介設することができる。介設作業を簡略化して
作業の手間を軽減することができ、作業時間の短縮を図
ることができる(請求項4)。
Further, by inserting a sleeve into the through hole as the insulating material and inserting the sleeve as the insulating material, the insulating material can be easily provided between the stud bolt and the through hole. it can. It is possible to simplify the installation work, reduce the labor of the work, and shorten the work time (claim 4).

【0037】このスリーブにあっては、前記スタッドボ
ルトに前記ナットを装着する際に前記貫通孔から撤去す
れば、再びこのスリーブを別の貫通孔において絶縁材と
して再利用することができる(請求項5)。
In the sleeve, if the sleeve is removed from the through hole when the nut is mounted on the stud bolt, the sleeve can be reused as an insulating material in another through hole. 5).

【0038】またさらに、前記貫通孔の内周部に前記ス
タッドボルトの挿入側に向かって漸次拡径して形成され
たテーパ部が設けられているとともに、前記スリーブ及
び前記ナットの外周部に前記貫通孔のテーパ部に密着さ
れるテーパ部が設けられていれば、ナットと鋼板の間に
十分な接触面積を確保することができるとともに、ナッ
トの締め付け力を鋼板に対して良好に伝達することがで
き、鋼板を下地部材に対し十分に固定することができ
る。特に鋼板コンクリート構造物においては、鋼板の面
内・面外の応力を下地鉄骨にズレ無く良好に伝達するこ
とができる。また、スリーブによって溶接時を溶接部と
外部とを十分に遮断してスリーブをアークシールドとし
て十分な機能を発揮させることができる(請求項6)。
Further, a tapered portion is formed on an inner peripheral portion of the through hole so as to gradually increase in diameter toward an insertion side of the stud bolt, and a tapered portion is formed on an outer peripheral portion of the sleeve and the nut. If a tapered portion is provided in close contact with the tapered portion of the through hole, a sufficient contact area can be secured between the nut and the steel plate, and the nut tightening force can be transmitted well to the steel plate. Thus, the steel plate can be sufficiently fixed to the base member. In particular, in the case of a steel plate concrete structure, the in-plane and out-of-plane stresses of the steel plate can be satisfactorily transmitted to the underlying steel frame. In addition, the sleeve can sufficiently shield the welded portion from the outside during welding, and the sleeve can exhibit a sufficient function as an arc shield (claim 6).

【0039】またさらに、前記スリーブの外周部に軸方
向に沿ってガス抜き溝部が設けられていることで、この
ガス抜き溝部を通じてアーク溶接により発生したガスを
外部に排出して、溶接品質の向上を図ることができる
(請求項7)。
Further, since a gas vent groove is provided in the outer peripheral portion of the sleeve along the axial direction, gas generated by arc welding is discharged to the outside through the gas vent groove to improve welding quality. (Claim 7).

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る鋼板の接合方法の手順の一実施形
態を示した断面図である。
FIG. 1 is a sectional view showing an embodiment of a procedure of a method for joining steel sheets according to the present invention.

【図2】本発明に係る鋼板の接合方法で使用される絶縁
部材の一実施形態を示した斜視図である。
FIG. 2 is a perspective view showing an embodiment of an insulating member used in the method for joining steel sheets according to the present invention.

【図3】本発明に係る鋼板の接合方法の他の実施形態を
示した断面図である。
FIG. 3 is a cross-sectional view showing another embodiment of the method for joining steel sheets according to the present invention.

【図4】本発明に係る鋼板の接合方法の他の実施形態を
示した断面図である。
FIG. 4 is a sectional view showing another embodiment of the method for joining steel sheets according to the present invention.

【図5】従来の鋼板の接合方法を説明する説明図であ
る。
FIG. 5 is an explanatory view illustrating a conventional method for joining steel sheets.

【図6】従来の鋼板の接合方法により接合された鋼板の
接合部を示す断面図である。
FIG. 6 is a cross-sectional view showing a joint of steel plates joined by a conventional method for joining steel plates.

【符号の説明】 2 下地部材(鉄骨材) 4 鋼板 6 貫通孔 6a テーパ部 14 スリーブ 14a テーパ部 16 スタッドボルト 22 ガス抜き溝部 24 ナット[Description of Signs] 2 Base member (steel frame material) 4 Steel plate 6 Through hole 6a Tapered portion 14 Sleeve 14a Tapered portion 16 Stud bolt 22 Gas vent groove 24 Nut

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 鉄骨材等の下地部材に鋼板を接合する方
法であって、あらかじめ前記鋼板に前記下地部材と接合
される部位に対応して貫通孔を設けておき、前記鋼板を
前記下地部材に密接させた後、前記貫通孔にスタッドボ
ルトを挿入するとともに前記貫通孔と当該スタッドボル
トとの間に両者を電気的に絶縁する絶縁材を介設し、そ
して前記スタッドボルトと前記下地部材との間に電圧を
印加して両者をアーク溶接により一体化し、その後、前
記スタッドボルトにナットを装着して当該ナットで前記
鋼板を前記下地部材に締め付けて接合することを特徴と
する鋼板の接合方法。
1. A method for joining a steel plate to a base member such as a steel frame material, wherein a through hole is provided in advance in the steel plate at a portion to be joined to the base member, and the steel plate is connected to the base member. Then, a stud bolt is inserted into the through hole and an insulating material is provided between the through hole and the stud bolt to electrically insulate the stud bolt, and the stud bolt and the base member are A voltage is applied between the two to integrate them by arc welding, and thereafter, a nut is attached to the stud bolt, and the steel plate is fastened to the base member with the nut to join the steel plate. .
【請求項2】 前記下地部材と前記鋼板との間に両者間
の隙間を閉塞するためのスペーサを介設することを特徴
とする請求項1に記載の鋼板の接合方法。
2. The method for joining steel sheets according to claim 1, wherein a spacer for closing a gap between the base member and the steel sheet is provided between the base member and the steel sheet.
【請求項3】 前記ナットとして袋ナットを使用するこ
とを特徴とする請求項1または2に記載の鋼板の接合方
法。
3. The method according to claim 1, wherein a cap nut is used as the nut.
【請求項4】 前記絶縁材として前記貫通孔内にスリー
ブを挿入することを特徴とする請求項1〜4のいずれか
1項に記載の鋼板の接合方法。
4. The method according to claim 1, wherein a sleeve is inserted into the through hole as the insulating material.
【請求項5】 前記スタッドボルトに前記ナットを装着
する際に前記スリーブを前記貫通孔から撤去することを
特徴とする請求項4に記載の鋼板の接合方法。
5. The method according to claim 4, wherein the sleeve is removed from the through hole when the nut is mounted on the stud bolt.
【請求項6】 前記貫通孔の内周部に前記スタッドボル
トの挿入側に向かって漸次拡径して形成されたテーパ部
が設けられているとともに、前記スリーブ及び前記ナッ
トの外周部に前記貫通孔のテーパ部に密着されるテーパ
部が設けられていることを特徴とする請求項4または5
に記載の鋼板の接合方法。
6. A tapered portion having a diameter gradually increasing toward an insertion side of the stud bolt is provided in an inner peripheral portion of the through hole, and the through hole is provided in an outer peripheral portion of the sleeve and the nut. 6. A tapered portion which is provided in close contact with the tapered portion of the hole.
The method for joining steel sheets according to the above.
【請求項7】 前記スリーブの外周部に軸方向に沿って
ガス抜き溝部が設けられていることを特徴とする請求項
4〜5のいずれか1項に記載の鋼板の接合方法。
7. The method for joining steel sheets according to claim 4, wherein a gas vent groove is provided in an outer peripheral portion of the sleeve along an axial direction.
JP2001110563A 2001-04-09 2001-04-09 Method for joining steel plate Pending JP2002303012A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001110563A JP2002303012A (en) 2001-04-09 2001-04-09 Method for joining steel plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001110563A JP2002303012A (en) 2001-04-09 2001-04-09 Method for joining steel plate

Publications (1)

Publication Number Publication Date
JP2002303012A true JP2002303012A (en) 2002-10-18

Family

ID=18962310

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001110563A Pending JP2002303012A (en) 2001-04-09 2001-04-09 Method for joining steel plate

Country Status (1)

Country Link
JP (1) JP2002303012A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010283064A (en) * 2009-06-03 2010-12-16 Nippon Chemicon Corp Method of manufacturing lead terminal for capacitor
JP2018031112A (en) * 2016-08-22 2018-03-01 日新製鋼株式会社 Steel member
US20210381123A1 (en) * 2020-06-05 2021-12-09 Meishan Boya Advanced Materials Co., Ltd. Systems for preparing crystals

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010283064A (en) * 2009-06-03 2010-12-16 Nippon Chemicon Corp Method of manufacturing lead terminal for capacitor
JP2018031112A (en) * 2016-08-22 2018-03-01 日新製鋼株式会社 Steel member
US20210381123A1 (en) * 2020-06-05 2021-12-09 Meishan Boya Advanced Materials Co., Ltd. Systems for preparing crystals

Similar Documents

Publication Publication Date Title
JP2002303012A (en) Method for joining steel plate
JP2001304210A (en) Rod body joining-together fitting
JP3888551B2 (en) Vehicle door hinge mounting structure
JPH08260455A (en) Joint structure of concrete pile
JPH07227670A (en) Plug welding method for metal plate member
JPH0687164A (en) Ultrasonic welding method for resin case
JPH10338967A (en) Column-beam joint structure of steel frame structure
JP2003320462A (en) Method for projection welding and projection for resistance welding
JP4090145B2 (en) Pile joint structure and pile connection structure
JP2831023B2 (en) Nozzle for discharging molten metal
JP2003194021A (en) Bolt joint structure for members, nut and metal fitting
KR102502141B1 (en) form saver coupler
JP3424087B2 (en) Manufacturing method of welding dowel
JPH10317492A (en) Non-welding column and column joining structure of steel tube column
JP2000053039A (en) Rubber pad with separable core metal and manufacture thereof
JP2604511B2 (en) How to join columns and beams
JP4400905B2 (en) Steel pipe pile structure
JPH0633517A (en) Joint part structure of filling type steel pipe concrete column and beam and joining method therefor
JPH10292626A (en) Beam piercing sleeve fixing structure and fixture
JPH0860740A (en) Joining structure of column to column
JP2912926B2 (en) Joining method between steel and concrete using welding dowel
JPH07207770A (en) Joining structure for column to column
JPH04203041A (en) Joint structure between steel frame column and beam
JP2831617B2 (en) Parts for welded joints
JPH10110595A (en) Joint structure of concrete segment, and manufacture of joint part

Legal Events

Date Code Title Description
RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20040927