JP2000241576A JP11045404A JP4540499A JP2000241576A JP 2000241576 A JP2000241576 A JP 2000241576A JP 11045404 A JP11045404 A JP 11045404A JP 4540499 A JP4540499 A JP 4540499A JP 2000241576 A JP2000241576 A JP 2000241576A
Authority
JP
Japan
Prior art keywords
blanket
wall
armature
formwork
slit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11045404A
Other languages
Japanese (ja)
Other versions
JP3729672B2 (en
Inventor
Mikio Enoeda
幹男 榎枝
Toshihisa Hatano
歳久 秦野
Toshikimi Kuroda
敏公 黒田
Noriaki Takahashi
範明 高橋
Toshio Osaki
敏雄 大崎
Takashi Sasaki
貴 佐々木
Koichi Yamada
弘一 山田
Shunichi Kuriki
俊一 栗木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kawasaki Heavy Industries Ltd
Japan Atomic Energy Agency
Original Assignee
Japan Atomic Energy Research Institute
Kawasaki Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Japan Atomic Energy Research Institute, Kawasaki Heavy Industries Ltd filed Critical Japan Atomic Energy Research Institute
Priority to JP04540499A priority Critical patent/JP3729672B2/en
Publication of JP2000241576A publication Critical patent/JP2000241576A/en
Application granted granted Critical
Publication of JP3729672B2 publication Critical patent/JP3729672B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/10Nuclear fusion reactors

Landscapes

  • Devices For Post-Treatments, Processing, Supply, Discharge, And Other Processes (AREA)
  • Moulds, Cores, Or Mandrels (AREA)

Abstract

PROBLEM TO BE SOLVED: To reduce costs by performing the HIP junction of an armor tile to a blanket first wall and then forming a slit between armor tiles by a specific procedure. SOLUTION: A spacer such as a carbon fiber reinforced carbon composite material CFC or an alumina long fiber composite material with a higher toughness than an armor tile member is buried into each gap C between armor tiles 3 in an assembly before performing the HIP junction of a small piece of armor tile 3 to a first wall 2 of a blanket 1, thus easy cutting and removal of the spacer is made possible without causing any crack in the armor tile 3 made of a fragile Be in the case when cutting and removing the space such as CFC and aluminum long fiber composite material after the HIP junction, and hence easy formation of a slit 5 can be done between the armor tiles 3 at a reduced manufacturing cost.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、トカマク型核融合
装置のブランケット第一壁が直接プラズマ粒子の照射を
受けないように外表面に接合されるアーマタイルに、熱
応力低減のためのスリットを形成する方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to forming a slit for reducing thermal stress in an armature tile which is bonded to an outer surface of a tokamak type fusion device so that a first wall of a blanket is not directly irradiated with plasma particles. On how to do it.

【0002】[0002]

【従来の技術】従来、トカマク型核融合装置の炉内構造
物であるブランケットの第一壁には、直接プラズマ粒子
の照射を受けないようにタイルをろう付けで貼り付ける
ことやボルト固定が考えられたが、ろう付けやボルト固
定では信頼性,耐久性に課題がある。また、タイルの熱
応力低減のため、タイルにスリットを入れることが考え
られたが、コスト高となることは勿論のこと、溝加工に
よりスリットを入れると、固くて脆いタイルは、割れて
欠ける心配がある。このため実際に適用された例はな
い。
2. Description of the Related Art Conventionally, it has been considered that a tile is brazed or bolted to a first wall of a blanket, which is a reactor internal structure of a tokamak-type fusion device, so as not to be directly irradiated with plasma particles. However, brazing and bolting have problems in reliability and durability. In order to reduce the thermal stress of the tiles, slits were considered to be inserted into the tiles. However, not only is the cost increased, but if slits are formed by groove processing, hard and brittle tiles may be cracked and chipped. There is. For this reason, there are no practical examples.

【0003】このようなことから現状では、ブランケッ
ト第一壁の外表面にベリリウムやボロンなどの原子番号
の低い材料のタイルをHIP接合することが考えられて
いる。しかし、第一壁の分散型強化銅(以下DSCuと
いう)とタイルのベリリウムやボロンとは異なる材料で
あり、しかも冷却されている第一壁と高熱にさらされる
タイルとの間には著しい温度差があるので、タイルの熱
応力を低減すべくスリット加工が必要となる。HIP接
合後の固くて脆いタイルそのものをスリット加工するこ
とは、技術的には可能であるが、コスト高の要因ともな
る。
Under such circumstances, it has been considered at present that HIP bonding of a tile made of a material having a low atomic number such as beryllium or boron is performed on the outer surface of the first blanket wall. However, the dispersion strengthened copper (DSCu) of the first wall and the beryllium or boron of the tile are different materials, and the temperature difference between the cooled first wall and the tile exposed to high heat is significant. Therefore, slit processing is required to reduce the thermal stress of the tile. It is technically possible to slit the hard and brittle tile itself after HIP bonding, but it also causes a cost increase.

【0004】[0004]

【発明が解決しようとする課題】そこで本発明は、HI
P接合後のアーマタイルへのスリット形成を容易にし、
コストを低減できるブランケット第一壁のアーマタイル
スリット形成方法を提供しようとするものである。
SUMMARY OF THE INVENTION Accordingly, the present invention relates to an HI
Facilitates slit formation on the armature tile after P joining,
An object of the present invention is to provide a method for forming an armature tile slit on a first blanket wall which can reduce costs.

【0005】[0005]

【課題を解決するための手段】上記課題を解決するため
の本発明のブランケット第一壁のアーマタイルスリット
形成方法の1つは、ブランケット第一壁の外表面に、一
定の間隙を存して多数の小片のアーマタイルを縦横に配
列して仮付けし、且つ各間隙にスペーサーを埋め、次に
その全面とブランケット側面の一部、またはブランケッ
ト全体をキャン部材で被ってシール溶接の上、HIP接
合によりこれらをブランケット第一壁と一体化し、次い
でキャン部材を機械加工により除去し、然る後各アーマ
タイル間のスペーサーを溝加工により除去してスリット
を形成することを特徴とするものである。
According to one aspect of the present invention, there is provided a method for forming an armature tile slit on a first blanket wall, the method comprising forming a gap on an outer surface of the first blanket wall. A large number of small pieces of armor tiles are arranged vertically and horizontally and temporarily attached, and spacers are filled in each gap. Then, the entire surface and a part of the blanket side surface, or the entire blanket is covered with a can member and sealed and welded, and HIP bonding is performed. By integrating them with the first blanket wall, the can member is removed by machining, and then the spacers between the armature tiles are removed by groove processing to form slits.

【0006】本発明のブランケット第一壁のアーマタイ
ルスリット形成方法の他の1つは、ブランケット第一壁
の外表面に沿い、多数の凹部を縦横に一定間隔に有する
型枠を予め製作し、次にこの型枠の各凹部にほぼ同じ寸
法形状の小片のアーマタイルを嵌め込んだ上、型枠をブ
ランケット第一壁の外表面に仮付けし、次いでその全面
とブランケット側面の一部、またはブランケット全体を
キャン部材で被ってシール溶接の上、HIP接合してこ
れらをブランケット第一壁と一体化し、次にキャン部材
を機械加工により除去した上、型枠の底部を機械切削に
より除去して小片のアーマタイルを露出させ、然る後型
枠を溝加工により除去して、アーマタイル間にスリット
を形成することを特徴とするものである。
Another method of forming an armature tile slit on the first blanket wall of the present invention is to pre-manufacture a formwork having a large number of recesses at regular intervals in the vertical and horizontal directions along the outer surface of the blanket first wall. Next, a small piece of armor tile of approximately the same size and shape is fitted into each recess of this formwork, and the formwork is temporarily attached to the outer surface of the blanket first wall, and then the entire surface and a part of the blanket side surface, or blanket The whole is covered with a can member, sealed and welded, HIP-joined to integrate them with the first wall of the blanket, then the can member is removed by machining, and the bottom of the form is removed by machining to remove small pieces. And exposing the armatures, and then removing the formwork by groove processing to form slits between the armatures.

【0007】本発明のブランケット第一壁のアーマタイ
ルスリット形成方法のさらに他の1つは、ブランケット
第一壁の外表面に沿い、多数の透かし穴を縦横に一定間
隔に有する型枠を予め製作し、次にこの型枠の各透かし
穴にほぼ同じ寸法形状の小片のアーマタイルを嵌め込ん
だ上、型枠をブランケット第一壁の外表面に仮付けし、
次いでその全面とブランケット側面の一部、またはブラ
ンケット全体をキャン部材で被ってシール溶接の上、H
IP接合してこれらをブランケット第一壁と一体化し、
次にキャン部材を機械加工により除去し、然る後型枠を
溝加工により除去して、アーマタイル間にスリットを形
成することを特徴とするものである。
[0007] Still another method of forming an armature tile slit on the first blanket wall according to the present invention is to pre-fabricate a formwork having a large number of open holes at regular intervals in the vertical and horizontal directions along the outer surface of the blanket first wall. Then, after inserting a small piece of armor tile of almost the same size and shape into each open hole of this mold, temporarily attach the mold to the outer surface of the blanket first wall,
Then, the entire surface and a part of the side surface of the blanket, or the entire blanket is covered with a can member and sealed and welded.
These are integrated with the blanket first wall by IP bonding,
Next, the can member is removed by machining, and then the mold is removed by groove processing to form a slit between the armature tiles.

【0008】本発明のブランケット第一壁のアーマタイ
ルスリット形成方法のさらに他の1つは、ブランケット
第一壁の外表面に沿い、多数の透かし穴を縦横に一定間
隔に有する型枠を予め製作し、次にこの型枠をブランケ
ット第一壁の外表面に仮付け後、型枠の各透かし穴にほ
ぼ同じ寸法形状の小片のアーマタイルを嵌め込み、次い
でその全面とブランケット側面の一部、またはブランケ
ット全体をキャン部材で被ってシール溶接の上、HIP
接合してこれらをブランケット第一壁と一体化し、次に
キャン部材を機械加工により除去し、然る後型枠を溝加
工により除去して、アーマタイル間にスリットを形成す
ることを特徴とするものである。
[0008] Still another method of forming an armature tile slit on the first blanket wall according to the present invention is to pre-fabricate a formwork having a large number of open holes at regular intervals in the vertical and horizontal directions along the outer surface of the blanket first wall. Then, after temporarily attaching this formwork to the outer surface of the blanket first wall, a small piece of armor tile of approximately the same size and shape is fitted into each open hole of the formwork, and then the entire surface and a part of the blanket side surface, or blanket Cover the whole with a can member, seal-weld and HIP
Joining and integrating these with the first blanket wall, then removing the can member by machining, and then removing the formwork by grooving to form slits between the armature tiles. It is.

【0009】前記のブランケット第一壁のアーマタイル
スリット形成方法の1つにおいて、スペーサーはアルミ
ナ長繊維複合材のようなセラミックス系材料、CFC
(炭素繊維強化炭素複合材)であることが好ましい。
In one of the above-mentioned methods for forming an armature tile slit on the first blanket wall, the spacer is made of a ceramic material such as an alumina long fiber composite material, or a CFC.
(Carbon fiber reinforced carbon composite).

【0010】前記のブランケット第一壁のアーマタイル
スリット形成方法の他の3つにおいて、型枠はアルミナ
長繊維複合材のようなセラミックス系材料、CFC(炭
素繊維強化炭素複合材)であることが好ましい。
In the above three other methods of forming an armature tile slit on the first wall of the blanket, the mold may be made of a ceramic material such as an alumina long fiber composite material or CFC (carbon fiber reinforced carbon composite material). preferable.

【0011】[0011]

【発明の実施の形態】本発明のブランケット第一壁のア
ーマタイルスリット形成方法の1つの実施形態を図によ
って説明する。図1に示すようにブランケット1のプラ
ズマと直接対面するDSCuより成る第一壁2の外表面
に、一定の間隙Cを存して多数の矩形の小片のBeより
成るアーマタイル3を配列して仮付けした上、各間隙C
に図2に示すようにブランケット1の第一壁2やアーマ
タイル3よりも靱性を有し、例え少々の削り残しがあっ
てもプラズマ発生,維持には無害な材料として、CFC
(炭素繊維強化炭素複合材)やアルミナ長繊維複合材な
どのスペーサー4を埋めた。次にその全面とブランケッ
ト1の側面の一部、またはブランケット1全体をキャン
部材,例えばSUS板(図示省略)で被ってシール溶接
の上、HIP接合により第一壁2とアーマタイル3及び
CFCやアルミナ長繊維複合材などのスペーサー4とを
一体化し、且つキャン部材とブランケット1とを一体化
した。次いでキャン部材を機械加工により除去した。然
る後各アーマタイル3間のCFCやアルミナ長繊維複合
材などのスペーサー4を、図3に示すように溝加工によ
り除去してスリット5を形成した。
DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the method for forming an armature tile slit of the first blanket wall of the present invention will be described with reference to the drawings. As shown in FIG. 1, on the outer surface of a first wall 2 made of DSCu directly facing the plasma of the blanket 1, armature tiles 3 made of a large number of small rectangular pieces of Be are arranged with a certain gap C therebetween. After attaching each gap C
As shown in FIG. 2, CFC is a material that is tougher than the first wall 2 and the armature 3 of the blanket 1 and is harmless to plasma generation and maintenance even if there is a little uncut portion.
Spacers 4 such as (carbon fiber reinforced carbon composite) and alumina long fiber composite were buried. Next, the entire surface and a part of the side surface of the blanket 1 or the entire blanket 1 is covered with a can member, for example, a SUS plate (not shown), sealed and welded, and the first wall 2 and the armature 3 and the CFC or alumina are bonded by HIP bonding. The spacer 4 such as a long fiber composite material was integrated, and the can member and the blanket 1 were integrated. Next, the can member was removed by machining. Thereafter, the spacers 4 such as CFC and alumina long fiber composite material between the respective armature tiles 3 were removed by groove processing as shown in FIG.

【0012】上記のようにアーマタイルスリット形成方
法の1つは、ブランケット1の第一壁2に小片のアーマ
タイル3をHIP接合する前のアセンブリー時に、アー
マタイル3間の各間隙Cにアーマタイル部材よりも靱性
を有するCFCやアルミナ長繊維などのスペーサー4を
埋めておくので、HIP接合後にCFCやアルミナ長繊
維複合材などのスペーサー4を切削除去する際、脆いB
eよりなるアーマタイル3にはき裂を生じさせずにスペ
ーサー4を容易に切削除去できる。従って、各アーマタ
イル3間には簡単にスリット5を形成できて、製作コス
トを低減できる。
As described above, one of the armature tile slit forming methods is that, during assembly before the small armature tile 3 is HIP-bonded to the first wall 2 of the blanket 1, each gap C between the armature tiles 3 Since the spacers 4 made of tough CFC or alumina long fiber are buried, when the spacers 4 made of CFC or alumina long fiber composite material are cut and removed after the HIP joining, brittle B
The spacer 4 can be easily cut and removed without causing cracks in the armature 3 made of e. Therefore, the slits 5 can be easily formed between the armature tiles 3, and the manufacturing cost can be reduced.

【0013】本発明のブランケット第一壁のアーマタイ
ルスリット形成方法の他の1つの実施形態を図によって
説明する。図4に示すように多数の矩形の凹部6を縦横
に一定間隔に有し、ブランケット1の第一壁2やアーマ
タイル3よりも靱性を有して例え少々削り残しがあって
もプラズマ発生、維持には無害な材料、例えばCFCや
アルミナ長繊維複合材などより成る型枠7を予め製作し
た。この型枠7は、ブランケット1の第一壁2の外表面
に沿うように形成されている。次に図5に示すようにこ
の型枠7の各凹部6に、夫々ほぼ同じ寸法形状の小片の
Beよりなるアーマタイル3を嵌め込み、アーマタイル
3側をブランケット1の第一壁2の外表面に向けて型枠
7を図6に示すように第一壁2の外表面に仮付けた。次
いでその型枠7の全面とブランケット1の側面の一部、
またはブランケット1全体をキャン部材、例えばSUS
板(図示省略)で被ってシール溶接の上、HIP接合に
より第一壁2とアーマタイル3及びCFCやアルミナ長
繊維複合材などより成る型枠7とを一体化し、且つキャ
ン部材とブランケット1とを一体化した。次にキャン部
材を機械加工により除去した上、型枠7の底部を機械切
削により除去して、小片のアーマタイル3を図7に示す
ように露出させた。然る後、型枠7を溝加工により除去
して、図8に示すようにアーマタイル3間にスリット5
を形成した。
Another embodiment of the method for forming the armature tile slit of the first blanket wall of the present invention will be described with reference to the drawings. As shown in FIG. 4, a large number of rectangular concave portions 6 are provided at regular intervals in the vertical and horizontal directions, and are tougher than the first wall 2 and the armature 3 of the blanket 1 and generate and maintain plasma even if there is a little uncut portion. A mold 7 made of a harmless material, for example, CFC or alumina long fiber composite material was manufactured in advance. The formwork 7 is formed along the outer surface of the first wall 2 of the blanket 1. Next, as shown in FIG. 5, the armature 3 made of Be, which is a small piece of approximately the same size and shape, is fitted into each of the recesses 6 of the mold frame 7 and the armature 3 is directed toward the outer surface of the first wall 2 of the blanket 1. The mold 7 was temporarily attached to the outer surface of the first wall 2 as shown in FIG. Next, the entire surface of the formwork 7 and a part of the side surface of the blanket 1,
Alternatively, the entire blanket 1 is made of a can member, for example, SUS.
After covering with a plate (not shown) and sealing and welding, the first wall 2 and the armature 3 and the formwork 7 made of CFC, alumina long fiber composite material or the like are integrated by HIP bonding, and the can member and the blanket 1 are connected. Integrated. Next, the can member was removed by machining, and the bottom of the mold 7 was removed by mechanical cutting to expose the small armature tile 3 as shown in FIG. Thereafter, the mold 7 is removed by groove processing, and as shown in FIG.
Was formed.

【0014】上記のようにアーマタイルスリット形成方
法の他の1つは、予め製作した型枠7の多数の凹部6に
小片のアーマタイル3を嵌め込んで、型枠7をブランケ
ット1の第一壁2の外表面に仮付けした後、キャン部材
で被ってシール溶接の上、HIP接合によりこれをブラ
ンケット1や第一壁2と一体化するので、前述のアーマ
タイルスリット形成方法の1つと比べ、アーマタイル3
の位置決め、仮付けが不要である。またHIP接合後、
アーマタイル3の表面の型枠7の底部を機械的切削によ
り除去することが容易であり、例えCFCやアルミナ長
繊維複合材が削り残った場合でも、プラズマ発生,維持
には無害であり、さらに型枠7を溝加工により除去する
際、脆いBeよりなるアーマタイル3にはき裂を生じさ
せずに型枠7を容易に溝加工により除去できる。従っ
て、各アーマタイル3間には簡単にスリット5を形成で
きて、製作コストを低減できる。
As described above, another method of forming an armature tile slit is to fit a small piece of the armature tile 3 into a large number of recesses 6 of a prefabricated formwork 7 and to attach the formwork 7 to the first wall of the blanket 1. After being temporarily attached to the outer surface of No.2, it is covered with a can member and sealed and welded, and this is integrated with the blanket 1 and the first wall 2 by HIP bonding. Armor tile 3
Positioning and temporary attachment are unnecessary. After HIP bonding,
The bottom of the formwork 7 on the surface of the armature tile 3 can be easily removed by mechanical cutting. Even if CFC or alumina long fiber composite material is left uncut, it is harmless to plasma generation and maintenance. When the frame 7 is removed by grooving, the mold frame 7 can be easily removed by grooving without causing cracks in the fragile Be armature tile 3. Therefore, the slits 5 can be easily formed between the armature tiles 3, and the manufacturing cost can be reduced.

【0015】本発明のブランケット第一壁のアーマタイ
ルスリット形成方法のさらに他の1つの実施形態を図に
よって説明する。図9に示すように多数の矩形の透かし
穴8を縦横に一定間隔に有し、ブランケット1の第一壁
2やアーマタイル3よりも靱性を有する材料、例えばC
FCやアルミナ繊維などより成る型枠9を予め製作し
た。この型枠9は、ブランケット1の第一壁2の外表面
に沿うように形成されている。次に図10に示すように
上記型枠9をブランケット1のDSCuより成る第一壁
2の外表面に仮付けの上、型枠9の各透かし穴8に、夫
々図11に示すように所要形状、寸法の小片のBeより
成るアーマタイル3を嵌め込んだ。尚、この型枠9は、
第一壁2の外表面に仮付けする前に、各透かし穴8にア
ーマタイル3を嵌め込み、その後第一壁2の外表面に仮
付けしてもよい。次いでその全面とブランケット1の側
面の一部、またはブランケット1全体をキャン部材、例
えばSUS板(図示省略)で被ってシール溶接の上、H
IP接合により型枠9及び各アーマタイル3を第一壁2
と一体化し、且つキャン部材をブランケット1と一体化
した。次にキャン部材を機械加工して除去した。然る後
型枠9のみを図12に示すように溝加工により除去し
て、アーマタイル3間にスリット5を形成した。
Still another embodiment of the method for forming an armature tile slit of the first blanket wall of the present invention will be described with reference to the drawings. As shown in FIG. 9, a material having a large number of rectangular open holes 8 at regular intervals in the vertical and horizontal directions and having tougher than the first wall 2 and the armature 3 of the blanket 1, for example, C
A mold 9 made of FC, alumina fiber, or the like was manufactured in advance. The form 9 is formed along the outer surface of the first wall 2 of the blanket 1. Next, as shown in FIG. 10, the mold 9 is temporarily attached to the outer surface of the first wall 2 made of the DSCu of the blanket 1 and is provided in each of the open holes 8 of the mold 9 as shown in FIG. An armor tile 3 made of a small piece of Be having a shape and dimensions was fitted. In addition, this formwork 9
Before the temporary attachment to the outer surface of the first wall 2, the armature 3 may be fitted into each of the watermark holes 8 and then temporarily attached to the outer surface of the first wall 2. Next, the entire surface and a part of the side surface of the blanket 1 or the entire blanket 1 is covered with a can member, for example, a SUS plate (not shown), and after sealing welding, H
The formwork 9 and each armature tile 3 are connected to the first wall 2 by IP joining.
And the can member was integrated with the blanket 1. Next, the can member was machined and removed. Then, only the formwork 9 was removed by groove processing as shown in FIG. 12 to form slits 5 between the armature tiles 3.

【0016】上記のようにアーマタイルスリット形成方
法のさらに他の1つは、予め製作した型枠9の多数の各
透かし穴8に小片のアーマタイル3を嵌め込んで、これ
をブランケット1の第一壁2に仮付けし、キャン部材で
被ってシール溶接した後、全体をHIP接合するので、
アーマタイル3の位置決め、仮付けが不要である。また
HIP接合後に型枠9を溝加工により除去するのは、量
が少ないだけ一層容易で、各アーマタイル3間には簡単
にスリット5を形成できて、製作コストを低減できる。
As described above, still another method of forming an armature tile slit is to insert a small piece of armature tile 3 into each of a number of open holes 8 of a prefabricated formwork 9 and to insert the small piece of armature tile 3 into the first blanket 1. After temporarily attaching to the wall 2, covering with a can member and sealing and welding, the whole is HIP joined,
It is not necessary to position and temporarily attach the armature 3. In addition, it is easier to remove the formwork 9 by groove processing after the HIP bonding because the amount is small, and the slits 5 can be easily formed between the armature tiles 3, so that the manufacturing cost can be reduced.

【0017】尚、前記のアーマタイルスリット形成方法
の1つでは、アーマタイル3がBeより成り、間隙Cに
埋めたスペーサー4はブランケット1の第一壁2やアー
マタイル3よりも靱性を有するCFCやアルミナ長繊維
複合材などより成るが、これに限定されるものではな
い。アーマタイル3は酸化物,炭化物,窒化物,珪化物
等の焼結材料から成るものでもよく、その際スペーサー
4はアーマタイル3よりも切削加工し易いものならばど
のような材料でもよい。また、小片のアーマタイル3の
形状は矩形で、第一壁2に縦横に配列されて、間隙Cが
格子状となっているが、形状は特に限定されるものでは
なく、間隙Cが一定となるように配列できる形状ならば
どのようなものでもよい。
In one of the above-described methods for forming an armature tile slit, the armature 3 is made of Be, and the spacer 4 buried in the gap C is made of CFC or alumina having toughness more than the first wall 2 of the blanket 1 or the armature 3. It is made of a long fiber composite material or the like, but is not limited thereto. The armature 3 may be made of a sintered material such as an oxide, a carbide, a nitride or a silicide. In this case, the spacer 4 may be made of any material which is easier to cut than the armature 3. In addition, the shape of the small armature tiles 3 is rectangular, and is arranged vertically and horizontally on the first wall 2 and the gap C has a lattice shape. However, the shape is not particularly limited, and the gap C is constant. Any shape may be used as long as it can be arranged in such a manner.

【0018】また、前記のアーマタイルスリット形成方
法の他の1つ及びさらに他の1つでは、型枠7の凹部6
や型枠9の透かし穴8の形状が矩形で縦横に配列されて
型枠が格子状となっているが、凹部6や透かし穴8の形
状は特に限定されるものではなく、凹部6や透かし穴8
間の寸法が一定となるように配列できる凹部6や透かし
穴8の形状ならばどのようなものでもよい。これに応じ
てアーマタイル3の形状も適宜選定される。また、型枠
7,9はブランケット1の第一壁2やアーマタイル3よ
りも靱性を有する材料、例えばCFCやアルミナ長繊維
複合材などより成るが、これに限定されるものではな
い。要はHIP接合の高温に耐えられる材料、高温下で
も有害なガスを発生しない材料、HIP接合しても第一
壁面やアーマタイルに着きにくい材料ならばどのような
ものでもよい。さらに、型枠7,9は、厚さに対し、高
さ,幅共に巨大寸法であるため、第一壁2の外表面への
仮付けのための組付けの際、予め凹部6や透かし穴8へ
小片のアーマタイル3を嵌め込むことにより、膨大な重
量となって組付けが厄介になると共に、型枠7,9が多
数のアーマタイル3の重量により歪みが生じると懸念さ
れる場合は、型枠7,9を夫々複数に分割して第一壁2
の外表面へ組付けるようにするとよい。
In another one of the above-mentioned armature tile slit forming methods and still another one, the concave portion 6 of the formwork 7 is provided.
The shape of the open hole 8 of the mold frame 9 is rectangular and arranged vertically and horizontally to form a lattice. However, the shape of the concave portion 6 and the open hole 8 is not particularly limited. Hole 8
Any shape may be used as long as the shape of the concave portion 6 and the open hole 8 can be arranged so that the dimension between them is constant. According to this, the shape of the armature 3 is also appropriately selected. The molds 7 and 9 are made of a material having tougher properties than the first wall 2 and the armature tile 3 of the blanket 1, for example, CFC and alumina long fiber composite material, but are not limited thereto. In short, any material can be used as long as it can withstand the high temperature of HIP bonding, does not generate harmful gas even at high temperature, and does not easily adhere to the first wall surface or armature tile even in HIP bonding. Further, since the molds 7 and 9 have a huge size in both height and width with respect to the thickness, the concave portions 6 and the watermark holes are required in advance when assembling for temporary attachment to the outer surface of the first wall 2. If the small armature tiles 3 are fitted into the armature tiles 8, the weight of the armature tiles 3 and 9 becomes enormous, making assembly troublesome. Each of the frames 7 and 9 is divided into a plurality
It is good to attach it to the outer surface of the.

【0019】[0019]

【発明の効果】以上の説明で判るように本発明のブラン
ケット第一壁のアーマタイルスリット形成方法によれ
ば、ブランケット第一壁にアーマタイルをHIP接合
後、アーマタイル間にスリットを形成することが容易
で、製作コストを低減できる。
As can be seen from the above description, according to the method for forming an armature tile slit on the first blanket wall of the present invention, it is easy to form a slit between the armature tiles after HIP joining the armature tile to the first blanket wall. Thus, the production cost can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明のブランケット第一壁のアーマタイルス
リット形成方法の1つにおいて、ブランケット第一壁の
外表面に、小片のアーマタイルを配列した状態を示す斜
視図である。
FIG. 1 is a perspective view showing a state in which small armor tiles are arranged on the outer surface of a first blanket wall in one of the methods for forming an armature tile slit on the first blanket wall of the present invention.

【図2】図1のブランケット第一壁の外表面の各アーマ
タイル間の間隙にCFCやアルミナ長繊維複合材などの
スペーサーを埋めた状態を示す斜視図である。
FIG. 2 is a perspective view showing a state in which spacers such as CFC and alumina long fiber composite material are buried in gaps between armature tiles on the outer surface of the first wall of the blanket of FIG. 1;

【図3】図2に示されるブランケット第一壁と各アーマ
タイル及びCFCやアルミナ長繊維複合材などのスペー
サーをHIP接合により一体化した後、各アーマタイル
間のCFCやアルミナ長繊維複合材などのスペーサーを
溝加工により除去してスリットを形成した状態を示す斜
視図である。
FIG. 3 is a block diagram showing the first wall of the blanket shown in FIG. 2 integrated with each armature tile and a spacer such as CFC or alumina long fiber composite material by HIP bonding, and then a spacer such as CFC or alumina long fiber composite material between each armature tile. FIG. 4 is a perspective view showing a state in which a slit is formed by removing a groove by groove processing.

【図4】本発明のブランケット第一壁のアーマタイルス
リット形成方法の他の1つにおいて用いる型枠を示す斜
視図である。
FIG. 4 is a perspective view showing a mold used in another method of forming an armature tile slit on the first blanket wall of the present invention.

【図5】図4の型枠の各凹部に小片のアーマタイルを嵌
め込んだ状態を示す斜視図である。
FIG. 5 is a perspective view showing a state where small armature tiles are fitted into respective concave portions of the mold of FIG. 4;

【図6】図5の型枠をブランケット第一壁に仮付けした
状態を示す斜視図である。
FIG. 6 is a perspective view showing a state in which the formwork of FIG. 5 is temporarily attached to a first blanket wall.

【図7】図6の型枠及びアーマタイルをHIP接合後、
型枠の底部を機械切削により除去して、小片のアーマタ
イルを露出させた状態を示す斜視図である。
FIG. 7 is a diagram showing a state in which the formwork and the armature of FIG.
It is a perspective view which shows the state which removed the bottom part of the mold by machine cutting, and exposed the small armature tile.

【図8】図7の型枠を溝加工により除去して、アーマタ
イル間にスリットを形成した状態を示す斜視図である。
FIG. 8 is a perspective view showing a state in which the mold of FIG. 7 is removed by groove processing to form slits between armature tiles.

【図9】本発明のブランケット第一壁のアーマタイルス
リット形成方法のさらに他の1つにおいて用いる型枠を
示す斜視図である。
FIG. 9 is a perspective view showing a mold used in still another method of forming an armature tile slit on the first blanket wall of the present invention.

【図10】図9の型枠をブランケット第一壁に仮付けし
た状態を示す斜視図である。
FIG. 10 is a perspective view showing a state where the formwork of FIG. 9 is temporarily attached to a first blanket wall.

【図11】図10の型枠の各透かし穴に小片のアーマタ
イルを嵌め込んだ状態を示す斜視図である。
FIG. 11 is a perspective view showing a state in which a small piece of armature is fitted into each open hole of the mold of FIG. 10;

【図12】図11の型枠及びアーマタイルをHIP接合
後、型枠のみを溝加工により除去して、アーマタイル間
にスリットを形成した状態を示す斜視図である。
FIG. 12 is a perspective view showing a state in which a slit is formed between the armatures by removing only the molds by grooving after HIP-joining the molds and the armatures of FIG. 11;

【符号の説明】[Explanation of symbols]

1 ブランケット 2 第一壁 3 小片のアーマタイル 4 CFC(炭素繊維強化炭素複合材) 5 スリット 6 凹部 7 型枠 8 透かし穴 9 型枠 C 間隙 DESCRIPTION OF SYMBOLS 1 Blanket 2 1st wall 3 Armature tile of a small piece 4 CFC (carbon fiber reinforced carbon composite material) 5 Slit 6 Concave part 7 Formwork 8 Open hole 9 Formwork C gap

───────────────────────────────────────────────────── フロントページの続き (72)発明者 秦野 歳久 茨城県那珂郡那珂町向山801−1 日本原 子力研究所 那珂研究所内 (72)発明者 黒田 敏公 茨城県那珂郡那珂町向山801−1 日本原 子力研究所 那珂研究所内 (72)発明者 高橋 範明 東京都江東区南砂2丁目6番5号 川崎重 工業株式会社東京設計事務所内 (72)発明者 大崎 敏雄 東京都江東区南砂2丁目6番5号 川崎重 工業株式会社東京設計事務所内 (72)発明者 佐々木 貴 東京都江東区南砂2丁目6番5号 川崎重 工業株式会社東京設計事務所内 (72)発明者 山田 弘一 東京都江東区南砂2丁目6番5号 川崎重 工業株式会社東京設計事務所内 (72)発明者 栗木 俊一 東京都江東区南砂2丁目6番5号 川崎重 工業株式会社東京設計事務所内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Toshihisa Hatano 801-1 Mukaiyama, Naka-machi, Naka-gun, Ibaraki Pref. Nipponbaru Nuclear Power Research Laboratory Naka Research Laboratory (72) Inventor Toshiko Kuroda 801 Mukaiyama, Naka-machi, Naka-gun, Ibaraki Prefecture -1 Nipponbaru Nuclear Power Laboratory Naka Laboratory (72) Inventor Noriaki Takahashi 2-6-5 Minamisuna, Koto-ku, Tokyo Kawasaki Heavy Industries, Ltd.Tokyo Design Office (72) Inventor Toshio Osaki Minamisuna, Koto-ku, Tokyo 2-6-5 Kawasaki Heavy Industries, Ltd. Tokyo Design Office (72) Inventor Takashi Sasaki 2-6-5 Minamisuna, Koto-ku, Tokyo Kawasaki Heavy Industries, Ltd. Tokyo Design Office (72) Inventor Koichi Yamada Tokyo 2-6-5 Minamisuna, Koto-ku, Tokyo Kawasaki Heavy Industries, Ltd. Tokyo Design Office (72) Inventor Shunichi Kuriki 2-6-6 Minamisuna, Koto-ku, Tokyo Issue Kawasaki Heavy Industries, Ltd., Tokyo design in the office

Claims (8)

【特許請求の範囲】[Claims] 【請求項1】 ブランケット第一壁の外表面に、一定の
間隙を存して多数の小片のアーマタイルを縦横に配列し
て仮付けし、且つ各間隙にスペーサーを埋め、次にその
全面とブランケット側面の一部、またはブランケット全
体をキャン部材で被ってシール溶接の上、HIP接合に
よりこれらをブランケット第一壁と一体化し、次いでキ
ャン部材を機械加工により除去し、然る後各アーマタイ
ル間のスペーサーを溝加工により除去してスリットを形
成することを特徴とするブランケット第一壁のアーマタ
イルスリット形成方法。
1. A large number of small pieces of armor tiles are temporarily arranged on the outer surface of a first wall of a blanket with a certain gap therebetween in a matrix, and spacers are buried in the gaps. A part of the side surface or the entire blanket is covered with a can member, and after seal welding, these are integrated with the first wall of the blanket by HIP joining, and then the can member is removed by machining, and then a spacer between each armature tile. Forming a slit on the first wall of the blanket, wherein the slit is formed by removing grooves by groove processing.
【請求項2】 ブランケット第一壁の外表面に沿い、多
数の凹部を縦横に一定間隔に有する型枠を予め製作し、
次にこの型枠の各凹部にほぼ同じ寸法形状の小片のアー
マタイルを嵌め込んだ上、型枠をブランケット第一壁の
外表面に仮付けし、次いでその全面とブランケット側面
の一部、またはブランケット全体をキャン部材で被って
シール溶接の上、HIP接合してこれらをブランケット
第一壁と一体化し、次にキャン部材を機械加工により除
去した上、型枠の底部を機械切削により除去して小片の
アーマタイルを露出させ、然る後型枠を溝加工により除
去して、アーマタイル間にスリットを形成することを特
徴とするブランケット第一壁のアーマタイルスリット形
成方法。
2. A formwork having a large number of recesses at predetermined intervals in the vertical and horizontal directions along the outer surface of the first blanket wall,
Next, a small piece of armor tile of approximately the same size and shape is fitted into each recess of this formwork, and the formwork is temporarily attached to the outer surface of the blanket first wall, and then the entire surface and a part of the blanket side surface, or blanket The whole is covered with a can member, sealed and welded, HIP-joined to integrate them with the first wall of the blanket, then the can member is removed by machining, and the bottom of the form is removed by machining to remove small pieces. Forming a slit between the armature tiles by exposing the armor tiles and then removing the formwork by grooving.
【請求項3】 ブランケット第一壁の外表面に沿い、多
数の透かし穴を縦横に一定間隔に有する型枠を予め製作
し、次にこの型枠の各透かし穴にほぼ同じ寸法形状の小
片のアーマタイルを嵌め込んだ上、型枠をブランケット
第一壁の外表面に仮付けし、次いでその全面とブランケ
ット側面の一部、またはブランケット全体をキャン部材
で被ってシール溶接の上、HIP接合してこれらをブラ
ンケット第一壁と一体化し、次にキャン部材を機械加工
により除去し、然る後型枠を溝加工により除去して、ア
ーマタイル間にスリットを形成することを特徴とするブ
ランケット第一壁のアーマタイルスリット形成方法。
3. A formwork having a plurality of open holes at regular intervals in the vertical and horizontal directions along the outer surface of the first wall of the blanket is prepared in advance. After inserting the armature tile, the formwork is temporarily attached to the outer surface of the blanket first wall, and then the entire surface and a part of the blanket side surface, or the entire blanket is covered with a can member and sealed and welded, and HIP bonding is performed. These are integrated with the first blanket wall, then the can member is removed by machining, and then the formwork is removed by grooving to form slits between the armature tiles. Armature tile slit forming method.
【請求項4】 ブランケット第一壁の外表面に沿い、多
数の透かし穴を縦横に一定間隔に有する型枠を予め製作
し、次にこの型枠をブランケット第一壁に仮付け後、型
枠の各透かし穴にほぼ同じ寸法形状のアーマタイルを嵌
め込み、次いでその全面とブランケット側面の一部、ま
たはブランケット全体をキャン部材で被ってシール溶接
の上、HIP接合してこれらをブランケット第一壁と一
体化し、次にキャン部材を機械加工により除去し、然る
後型枠を溝加工により除去して、アーマタイル間にスリ
ットを形成することを特徴とするブランケット第一壁の
アーマタイルスリット形成方法。
4. A formwork having a plurality of open holes at predetermined intervals vertically and horizontally along the outer surface of the first blanket wall is prepared in advance, and then the formwork is temporarily attached to the first blanket wall. Armature tiles of almost the same size and shape are fitted into each of the open holes, and then the entire surface and a part of the blanket side, or the entire blanket is covered with a can member and sealed and welded, and HIP-joined to integrate them with the blanket first wall. Forming a slit between the armature tiles by removing the can member by machining and then removing the formwork by grooving to form slits between the armature tiles.
【請求項5】 スペーサーがセラミックス系材料である
ことを特徴とする、請求項1記載のブランケット第一壁
のアーマタイルスリット形成方法。
5. The method of claim 1, wherein the spacer is a ceramic material.
【請求項6】 スペーサーがCFCであることを特徴と
する、請求項1記載のブランケット第一壁のアーマタイ
ルスリット形成方法。
6. The method of claim 1, wherein the spacer is CFC.
【請求項7】 型枠がセラミックス系材料であることを
特徴とする、請求項2、3、4のいずれかに記載のブラ
ンケット第一壁のアーマタイルスリット形成方法。
7. The method for forming an armature tile slit in a first blanket wall according to claim 2, wherein the mold is made of a ceramic material.
【請求項8】 型枠がCFCであることを特徴とする、
請求項2、3、4のいずれかに記載のブランケット第一
壁のアーマタイルスリット形成方法。
8. The method according to claim 1, wherein the mold is CFC.
The method for forming an armature tile slit on the first blanket wall according to claim 2.
JP04540499A 1999-02-23 1999-02-23 Blanket first wall armature slit forming method Expired - Fee Related JP3729672B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP04540499A JP3729672B2 (en) 1999-02-23 1999-02-23 Blanket first wall armature slit forming method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP04540499A JP3729672B2 (en) 1999-02-23 1999-02-23 Blanket first wall armature slit forming method

Publications (2)

Publication Number Publication Date
JP2000241576A true JP2000241576A (en) 2000-09-08
JP3729672B2 JP3729672B2 (en) 2005-12-21

Family

ID=12718326

Family Applications (1)

Application Number Title Priority Date Filing Date
JP04540499A Expired - Fee Related JP3729672B2 (en) 1999-02-23 1999-02-23 Blanket first wall armature slit forming method

Country Status (1)

Country Link
JP (1) JP3729672B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015059083A (en) * 2013-09-20 2015-03-30 アルストム テクノロジー リミテッドALSTOM Technology Ltd Method for applying heat resistant protection components onto surface of heat exposed component

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01206037A (en) * 1988-12-23 1989-08-18 Hitachi Ltd Composite strength member
JPH03122064A (en) * 1989-10-06 1991-05-24 Toshiba Corp Graphite-copper joined material and production therefor
JPH03123295U (en) * 1990-03-29 1991-12-16
JPH07187833A (en) * 1993-12-27 1995-07-25 Mitsubishi Chem Corp Carbon fiber reinforced carbon composite material
JPH0881279A (en) * 1994-09-14 1996-03-26 Fuji Heavy Ind Ltd Carbon fiber-reinforced carbonaceous composite material and its production
JPH1054688A (en) * 1996-08-08 1998-02-24 Japan Atom Energy Res Inst Manufacture of wall body for cooling

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01206037A (en) * 1988-12-23 1989-08-18 Hitachi Ltd Composite strength member
JPH03122064A (en) * 1989-10-06 1991-05-24 Toshiba Corp Graphite-copper joined material and production therefor
JPH03123295U (en) * 1990-03-29 1991-12-16
JPH07187833A (en) * 1993-12-27 1995-07-25 Mitsubishi Chem Corp Carbon fiber reinforced carbon composite material
JPH0881279A (en) * 1994-09-14 1996-03-26 Fuji Heavy Ind Ltd Carbon fiber-reinforced carbonaceous composite material and its production
JPH1054688A (en) * 1996-08-08 1998-02-24 Japan Atom Energy Res Inst Manufacture of wall body for cooling

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015059083A (en) * 2013-09-20 2015-03-30 アルストム テクノロジー リミテッドALSTOM Technology Ltd Method for applying heat resistant protection components onto surface of heat exposed component

Also Published As

Publication number Publication date
JP3729672B2 (en) 2005-12-21

Similar Documents

Publication Publication Date Title
US7850061B2 (en) Method for making a component including fluid flow channels
US5527634A (en) Multiple manifold fuel cell
US7153096B2 (en) Stacked laminate CMC turbine vane
EP1355320B1 (en) Cask and production method for cask
US8167537B1 (en) Air cooled turbine airfoil with sequential impingement cooling
IL137097A0 (en) Heat exchanger in composite material and method for making same
KR100484705B1 (en) Cask
JP6572210B2 (en) Seals for electrochemical devices, methods for manufacturing and fitting seals and the devices
KR20110060938A (en) Cylindrical sputtering target, and method for manufacturing same
EP1717201A1 (en) Mold, method for forming same, and method for producing polycrystalline silicon substrate using such mold
EP3132663A1 (en) Monolithic multi-module electronics chassis with multi-planar embedded fluid cooling channels
US20090255660A1 (en) High Thermal Conductivity Heat Sinks With Z-Axis Inserts
US8179028B1 (en) Prevention of core failures in large electric machines
EP1854773A1 (en) Sintered body with spacers, and production method and joining method for the same
JP2870687B2 (en) Tubesheet structure for heat exchanger and method for supporting and sealing heat pipe in heat exchanger
JP2000241576A (en) Method for forming armor tile slit of blanket first wall
JP2006313772A (en) Mold
EP3435523B1 (en) Magnet structure and motor
JPH07260151A (en) Combustion chamber with lining made of ceramics
EP0265777B1 (en) Method of preparing a ceramic monolithic structure having an internal cavity contained therein
Dickens Principles of design for laminated tooling
CN106862761A (en) The two-sided gas servicing unit of sheet metal pulsed laser welding
US3020222A (en) Method for casting side supporting plates onto the edges of spaced nuclear fuel plates
EP2062673B1 (en) A method of supporting a work piece
JP2001168252A (en) Semiconductor device and manufacturing method thereof

Legal Events

Date Code Title Description
RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20041224

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20050107

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050308

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050428

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051004

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051004

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081014

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081014

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091014

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101014

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111014

Year of fee payment: 6

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111014

Year of fee payment: 6

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121014

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121014

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131014

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131014

Year of fee payment: 8

R250 Receipt of annual fees