GB2362673A - Formation of piles with enlarged base - Google Patents

Formation of piles with enlarged base Download PDF

Info

Publication number
GB2362673A
GB2362673A GB0012784A GB0012784A GB2362673A GB 2362673 A GB2362673 A GB 2362673A GB 0012784 A GB0012784 A GB 0012784A GB 0012784 A GB0012784 A GB 0012784A GB 2362673 A GB2362673 A GB 2362673A
Authority
GB
United Kingdom
Prior art keywords
concrete
auger
bore
forming
concrete pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
GB0012784A
Other versions
GB2362673B (en
GB0012784D0 (en
Inventor
Arwel Willams
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pennine Holdings Ltd
Original Assignee
Pennine Holdings Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pennine Holdings Ltd filed Critical Pennine Holdings Ltd
Priority to GB0012784A priority Critical patent/GB2362673B/en
Priority to GB0100250A priority patent/GB2362674A/en
Publication of GB0012784D0 publication Critical patent/GB0012784D0/en
Priority to EP01304590A priority patent/EP1158104A1/en
Priority to US09/865,650 priority patent/US20020008328A1/en
Publication of GB2362673A publication Critical patent/GB2362673A/en
Application granted granted Critical
Publication of GB2362673B publication Critical patent/GB2362673B/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/44Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)
  • Earth Drilling (AREA)

Abstract

A concrete pile with an enlarged base for structural foundations for buildings is formed by drilling a borehole with an auger, pumping fluid concrete into the borehole through a channel (22, figure 3) in the auger whilst retracting the auger from a lower portion of the bore, allowing concrete to fill the resulting void, applying pressure to the volume of fluid concrete by at least partly reinserting the auger into the lower portion of the bore such that the applied pressure causes the volume of concrete to expand radially and increase the diameter of the lower portion of the bore wall 26, retracting the auger from the remainder of the bore whilst pumping further concrete into the bore, such that a concrete pile is formed with an enlarged base that provides a greater load-bearing capacity. The auger comprises a stem with a tapering tip portion 16 that has at least one upstanding flight arranged in a helical fashion; the stem has a fluid channel that communicates between an inlet at the top of the stem and an outlet at the stem tip.

Description

2.362673 1 Pile Formation This invention relates to the formation of piles
for providing structural foundations for buildings or infra structures, in particular to the formation of concrete piles.
There are several different ways of forming a concrete pile in the ground. one way is to drill a bore hole into the ground with an auger and fill the hole with fluid concrete that is pumped through a f luid passage running down the length of the auger.
Another way is to create a bore hole by forcing a 15 vibrating poker into the ground, withdrawing the poker and filling the resulting void with fluid concrete - as the poker is being withdrawn. It is known to only partially fill the bore hole with concrete and then, reinsert the vibrating poker in order to expand the cross sectional area of the lower part of the pile, before filling the remaining upper part of the bore with concrete. However, due to the substantial mass of the poker, the vibrations produced by this vibrating poker method can propagate some distance, making it unsuitable when there are buildings or other structures present nearby.
According to one aspect of the invention, there is provided a method of forming a concrete pile in the ground using an auger having a stem with a fluid channel communicating between an inlet towards the top end of the stem and an outlet located towards the step tip, the method comprising the steps of:
(a) creating a bore hole by screwing the auger into the ground in an axial direction; 2608a4.doc 24 May 2000 2 (b) pumping f luid concrete into the bore hole through the fluid channel in the stem whilst retracting the auger from a lower portion of the bore, such that the lower portion of the bore becomes filled with a volume of fluid concrete; (c) applying a pressure to the volume of fluid concrete by at least partly reinserting the auger into the lower portion of the bore, such that the applied pressure causes the volume of concrete to expand radially, thereby increasing the diameter of the lower portion of the bore; and, (d) retracting the auger from the remainder of the bore whilst pumping further concrete into the bore, such that the bore fills with concrete and forms a concrete pile.
This will result in a generally cylindrical pile having an enlarged bulb like region at its lower end. Due to the increased cross sectional area at its lower end, the pile will have a greater load bearing capacity.
Because the bore hole is drilled with an auger, the bore hole can be formed in hard ground, and without significant vibration.
It will be appreciated that the auger need not be completely removed from the bore after having been partially reinserted into the lower portion of the bore a f irst time. Steps (b) and (c) may be repeated several times in a cyclic fashion, such that fluid concrete is pumped into the bore and compressed in stages until the lower portion of the bore has been expanded sufficiently.
2608a4.doc 24 May 2000 It will be further appreciated that the term concrete includes cements and other self setting fluid building materials, and/or that the concrete may be of a granular nature.
Preferably, the auger will be reinserted into the lower portion of the bore by screwing the auger into the concrete, since the screwing motion will provide a mechanical advantage in applying a pressure to the concrete, with the result that pressure applied to the concrete is not solely due to the weight of the auger.
Preferably, pressure to pump the fluid concrete will be applied to the fluid concrete at the inlet of the fluid passage by a pump. The pumping pressure may be continuously applied with the pump during steps (b) to (d). Preferably the pumping pressure will b. e.:in the range 0.3 bar to 3 bar. In particular, the pumping pressure will preferably be in the range 0.5 bar to 1 bar.
20-, To retract the auger, the auger will preferably be rotated in the opposite sense to that in which it is rotated when it is inserted. However, the auger may be retracted by simply pulling the auger in an upward direction, without rotating it.
Concrete will preferably be continuously pumped into the bore as the auger is being retracted, so that the chance of a void being formed in the concrete is reduced. (it will be understood that as used herein, the term retraction also covers extraction).
To increase the pressure of the concrete in the lower portion of the bore, fluid concrete will preferably continue to be pumped as the auger is reinserted into the 2608a4.doc 24 May 2000 4 lower portion of the bore.
The stem of the auger will preferably have a cylindrical shaft portion and a tip portion, the tip portion having at least one upstanding flight arranged thereon in a helical fashion to make it easier to screw the auger into the ground and the fluid concrete. The flight(s) may continue some distance up the shaft portion beyond the tip portion, and/or the shaft portion may have an additional helical upstanding flight arranged on a section thereof.
In a preferred embodiment, the tip portion will have two flights rotationally displaced by 180 degrees from one another.
At least part of the tip portion will preferably taper in order.t to displace the ground material sideways as the auger penetrates the ground. The tip may taper to a point, but in a preferred embodiment the tip will taper to a region of reduced diameter.
To reduce the amount of ground material that is displaced in an upward direction when the auger is screwed into the ground, the ratio of the maximum radial extent of the upstanding flights as measured from the centre of the auger and the radius of the shaft portion will preferably be between 4:3 and 32:30. In a preferred embodiment, this ratio will be substantially 35:30.
According to another aspect of the invention there is provided an auger for drilling a bore hole in the ground, comprising a stem with a tapering tip portion, the tapering tip portion having at least one upstanding flight arranged thereon in a helical fashion, and the stem having fluid channel communicating between an inlet towards the 2608a4.doc 24 May 2000 top end of the stem and an outlet towards the step tip.
According to yet another aspect of the invention, there is provided a method of f orming a concrete pile in a bore 5 hole in the ground comprising the steps of:
(a) filling a lower portion of the bore hole with a volume of fluid concrete; (b) applying a pressure to the volume of fluid concrete by at least party inserting an auger into the lower portion of the bore in an axial direction, such that the applied pressure causes the volume of concrete to expand radially, thereby increasing the diameter of the lower portion of 15 the bore; (c) retracting the auger from the remainder of the bore and filling the remainder of the bore with concrete; and, (d) allowing the concrete to cure.
The invention will now be further described by way of example with reference to the following drawings in which:
Figures 1 to 6 show a sequence of steps in the forming of a concrete pile in accordance with the invention; and Figure 7 is a side view of an auger for forming concrete piles as shown in Figure 1.
Figure 1 is a cross sectional view of part of an auger 10 which has penetrated some distance into the ground 12, thereby forming a partially dug bore hole 14 of cylindrical shape. The auger has a shaft 13 at the end of 2608a4.doc 24 May 2000 which there is a tapered drilling tip 16 with helically arranged flights 18 such that rotating the auger causes the auger to penetrate the ground. The auger is connected to a drilling rig (not shown) in order that the auger can be rotated whilst being retained in a substantially vertical position.
In Figure 2, the auger 10 has further penetrated the ground 12 and formed a bore hole 14 whose depth is approximately equal to the depth of the pile that is to be formed.
Retraction of the auger 10 is then initiated, and fluid concrete 24 is pumped into the lower part 20 of the bore hole 14 through a fluid channel 22 running down the centre of the shaft 13 of the auger 10 to an exit port 23 in the auger tip 16. The concrete is pumped into the bore hole as the auger is being retracted. The rate of retraction and the pump rate of concrete are matched so that there is a reduced risk of voids being formed or collapsable soil falling into the concrete 24. This is achieved by maintaining the pressure of the fluid concrete 24 in the fluid channel 22 as the auger is being retracted.
When the auger 10 is being retracted, the region of the bore hole 14 below the auger 10 fills with fluid concrete 24. Once the auger 10 has been retracted f rom, a lower portion 21 of the bore hole 14 as shown in Figure 3, the auger 10 is then at least partially reintroduced in a downward direction into the fluid concrete 24 in the lower portion 21 of the bore hole 14. The auger is reintroduced by rotating the auger 10, which is forced downward due to the engagement of the flights 18 in the fluid concrete 24 as the tip 16 is rotated.
2608a4.doc 24 May 2000 7 Figure 4 shows the auger 10 after it has been partially reintroduced into the lower portion 21 of the bore hole. The introduction of the auger 10 increases the pressure of the fluid concrete 24 in the lower portion 21 of the bore hole 14. Consequently, the side wall 26 of the lower portion of the bore hole expands outwardly, as shown in Figure 4. The resulting bore has a wider horizontal cross section in the lower portion 21. (The depth of the bore hole 14 will also increase due to the pressure applied to the concrete 24, but this increase -will be small in comparison to the depth of the bore hole 14).
The' auger then is retracted to a level where the tip 16 of the auger 10 is above the expanded portion of the bore 14 as shown in Figure 5. At this stage, the auger 10 can be retracted completely. Alternatively, the auger 10 can be reintroduced again in order to expand the bowe hole 14 in the region immediately above the expanded lower bore portion 21, or to further expand the lower bore hole 20, portion 21.
once the lower region of the bore has been sufficiently expanded by the reintroduction of the auger 10, the auger is withdrawn from the bore whilst pumping concrete into the bore 14. When the auger 10 is completely withdrawn, the resulting bore 14 is completely filled with concrete. An elongate metal cage 28 is then inserted into the concrete-filled bore 14 for structural support and the concrete 24 is allowed to set, resulting in a pile as shown in Figure 6.
The auger 10 of Figure 1 used to drill the bore hole 14 is shown in more detail on Figure 7. The tip 16 has a cylindrical portion 16a joined to the auger shaft 13, followed by a tapering portion 16b whose narrow end forms 2608a4.doc 24 May 2000 - 8 the lower extremity of the auger 10. Two upstanding helical flights 18a and 18b are disposed on the side surface 31 of the tip 16, the two flights 18a and 18b being rotationally separated by 180 degrees. The flights 18a and 18b are inclined with respect to the side surface 32 of the tip 16 such that when the auger rotates about 180 degrees about a vertical axis 30, the inclination of a flight in the radial direction will reverse, passing through a horizontal inclination after having been rotated through 90 degrees. When the auger 10 is rotated in the ground in one sense, the helically arranged flights will screw into the ground and f orce the auger to move in a downward direction. Rotating the auger in the opposite sense will cause the auger to move upwards.
is The diameter of the shaft 13 and the cylindrical portion 16a. of the tip 16 is approximately 3.00 mm. The tapering portion of the tip 16b tapers down to a diameter of about 100 mm at the extremity of the tip-16.
The radial extent of the flights as measured from the surface of the tip diminishes as the tips widens. When measured from the central axis 30, the radial extent of the flights is constant and about 175 mm. Therefore, in this example the ratio of the radial extent of the flights as measured from the central axis 30 and the radial extent of the tip varies between about 35:12 towards the narrow end of the tip and 35:30 when the tip is at its widest.
Because the flights 18a and 18b are relatively short in a radial direction as compared to the diameter of the tip 16, and because of the orientation of the flights, the auger 10 displaces earth predominantly in a sideways direction rather than in a vertical direction when it is 35 screwed into the ground. This means that displaced earth 2608a4.doc 24 May 2000 9 - is not brought up to the surface where it can be a nuisance.
The fluid channel 22 through which concrete is pumped, 5 here a tubular passage running down the length of the shaft and to the tip 16, is indicated by a dashed line. In this example, the long axis of the f luid channel 22 is co-axially aligned with the central axis 30 of the shaft 13.
The exit port 23 in the fluid passage 22 is situated on the side surface of the tip 16, such that concrete pumped through the auger 10 is injected into the bore hole 14 at an angle to the vertical direction. However, the exit port could alternatively be positioned in line with the long axis of the fluid channel 22.
R An expendable and releasable cap (not shown) placed on the exit port 23 is used to prevent soil being forced into the fluid channel and blocking it as the auger is drilling the bore hole 14. Af ter a hole 14 of the desired depth has been drilled with the auger 10, concrete is pumped into the fluid passage. The pressure of this concrete will build up until it reaches 0.5 bar and 1 bar and is sufficient to release the expendable cap from the exit port 23, thereby allowing fluid concrete to f low from the exit port 23 and into the bore 14.
As it will be appreciated from the above description, this invention provides a simple way of forming concrete piles having an enlarged base, without producing excessive vibration, and allowing firm or hard soils to be penetrated.
2608a4.doc 24 May 2000 -

Claims (12)

Claims
1. A method of forming a concrete pile in the ground using an auger having a stem with a fluid channel communicating between an inlet towards the top end of the stem and an outlet located towards the step tip, the method comprising the steps of:
(a) creating a bore hole by screwing the auger into the ground in an axial direction; (b) pumping fluid concrete into the bore hole through the fluid channel in the stem whilst retracting the auger from a lower portion of the bore, such that the lower portion of the bore becomes filled with a volume of fluid concrete; (c) applying a pressure to the volume-of fluid concrete by at least partly reinserting the auger into the lower portion of the bore, such that the applied pressure causes the volume of concrete to expand radially, thereby increasing the diameter of the lower portion of the bore; and, (d) retracting the auger from the remainder of the bore whilst pumping further concrete into the bore, such that the bore fills with concrete and forms a concrete pile.
2. A method of forming a concrete pile as claimed in Claim 1, wherein in step (c) the auger is reinserted into the lower portion of the bore by screwing the auger into the concrete.
3. A method of forming a concrete pile as claimed in Claim 1 or Claim 2, wherein a pumping pressure is 2608a4.doc 24 May 2000 11 - continuously applied with a pump during steps (b) to (d).
4. A method of forming a concrete pile as claimed in Claim 3, wherein the pumping pressure is in the range 5 0.5 bar to 1 bar.
5. A method of forming a concrete pile as claimed in any previous claim, wherein the auger is rotated when it is retracted at least partially from the bore.
6. A method of forming a concrete pile as claimed in any previous claim, wherein concrete is continuously pumped into the bore as the auger is being retracted.
7. A method of forming a concrete pile as claimed in any previous claim, wherein the stem of the auger has a cylindrical shaft portion and a tip portion.-with at least one upstanding flight arranged thereon in A helical fashion.
20.
8. A method of forming a concrete pile as claimed in Claim 7, wherein the tip portion has two flights rotationally displaced by 180 degrees from one another.
9. A method of f orming a concrete pile as claimed in Claim 7 or Claim 8, wherein at least part of the tip portion tapers to an area of reduced diameter.
10. A method of forming a concrete pile as claimed in any one of claims 7 to 9, wherein the ratio of the maximum radial extend of the upstanding flights from the centre of the auger and the radius of the shaft portion is between 4:3 and 32:30.
11. A method of forming a concrete pile as claimed in 2608a4.doc 24 May 2000 12 Claim 10, wherein the ratio is substantially 35:30.
12. An auger for drilling a bore hole in the ground, comprising a stem with a tapering tip portion, the tapering tip portion having at least one upstanding flight arranged thereon in a helical fashion, and the stem having f luid channel communicating between an inlet towards the top end of the stem and an outlet towards the step tip.
13. A method of forming a concrete pile in a bore hole in the ground comprising the steps of:
(a) f illing a lower portion of the bore hole with a volume of fluid concrete; (b) applying a pressure to the volume of fluid concrete by at least partly inserting an auger into the lower portion of the bore in an axial direction, such that the applied pressure causes the volume of concrete to expand radially, thereby increasing the diameter of the lower portion of the bore; (c) retracting the auger f rom the remainder of the bore and filling the remainder of the bore with concrete; and, (d) allowing the concrete to cure.
14. A method of forming a concrete pile substantially as herein described with reference to or as shown in the 30 accompanying drawings.
15. An auger for drilling a bore hole substantially as herein described with reference to or as shown in the accompanying drawings.
2608a4.doc 24 May 2000 1 t Amendments to the claims have been filed as follows Is Claims 1. A method of forming a concrete pile in the ground using an auger having a stem with a fluid channel communicating between an inlet towards the top end of the stem and an outlet located towards the stem tip, the method comprising the steps of:
(a) creating a bore hole by screwing the auger into the ground in an axial direction; (b) pumping fluid concrete into the bore hole through the fluid channel in the stem whilst retracting the auger from a lower portion of the bore, such that the lower portion is of the bore becomes filled with a volume of fluid concrete; (c) applying a pressure to the volume of fluid concrete by at least partly reinserting the auger into the lower portion of the bore, such that the applied pressure causes the volume of concrete to expand radially, thereby increasing the diameter of the lower portion of the bore; and, (d) retracting the auger from the remainder of the bore whilst pumping further concrete into the bore, such that the bore fills with concrete and forms a concrete pile.
2. A method of forming a concrete pile as claimed in Claim 1, wherein in step (c) the auger is reinserted into the lower portion of the bore by screwing the auger into the concrete.
3. A method of forming a concrete pile as claimed in Claim 1 or Claim 2, wherein a pumping pressure is 2608A4v2.DOC 18 October 2000 i A.
continuously applied with a pump during steps (b) to (d) 4. A method of forming a concrete pile as claimed in Claim 3, wherein the pumping pressure is in the range 0.5 bar to 1 bar.
5. A method of forming a concrete pile as claimed in any previous claim, wherein the auger is rotated when it is retracted at least partially from the bore.
6. A method of forming a concrete pile as claimed in any previous claim, wherein concrete is continuously pumped into the bore as the auger is being retracted.
7. A method of forming a concrete pile as claimed in any previous claim, wherein the stem of the. auger has a cylindrical shaft portion and a tip portion.-with at least one upstanding flight arranged thereon in a helical fashion.
20..
8. A method of forming a concrete pile as claimed in Claim 7, wherein the tip portion has two flights rotationally displaced by 180 degrees from one another.
9. A method of f orming a concrete pile as claimed in Claim 7 or Claim 8, wherein at least part of the tip portion tapers to an area of reduced diameter.
10. A method of forming a concrete pile as claimed in any one of claims 7 to 9, wherein the ratio of the maximum radial extend of the upstanding flights from the centre of the auger and the radius of the shaft portion is between 4:3 and 32:30.
11. A method of forming a concrete pile as claimed in 2608a4.doc 24 May 2000 1 11 1 r- v 1 i5 Claim 10, wherein the ratio is substantially 35:30.
12. A method of forming a concrete pile substantially as herein described with reference to or as shown in the 5 accompanying drawings.
0 1 2608A4V3.DOC 21 December 2000
12. A method of forming a concrete pile in a bore hole in the ground comprising the steps of:
(a) filling a lower portion of the bore hole with a volume of fluid concrete; (b) applying a pressure to the volume of fluid concrete by at least partly inserting an auger into the lower portion of the bore in an axial direction, such that the applied pressure causes the volume of concrete to expand radially, thereby increasing the diameter of the lower portion of the bore; is (c) retracting the auger from the remainder of the bore and filling the remainder of the bore with concrete; and, (d) allowing the concrete to cure.
13. A method of f orming a concrete pile substantially as herein described with reference to or as shown in the accompanying drawings.
14. An auger for drilling a bore hole substantially as herein described with reference to or as shown in the accompanying drawings.
2608A4v2.DOC 18 October 2000 Amendments to the claims have been filed as follows 14(0 Claims 1. A method of forming a concrete pile in the ground using an auger having a stem with a fluid channel communicating between an inlet towards the top end of the stem and an outlet located towards the stem tip, the method comprising the steps of:
(a) creating a bore hole by screwing the auger into the 10 ground in an axial direction; 1 (b) pumping fluid concrete into the bore hole through the fluid channel in the stem whilst retracting the auger from a lower portion of the bore, such that the lower portion is of the bore becomes filled with a volume of fluid concrete; (c) applying a pressure to the volume of fluid concrete by at least partly reinserting the auger into the lower portion of the bore, such that the applied pressure causes the volume of concrete to expand radially, thereby increasing the diameter of the lower portion of the bore; and, (d) retracting the auger from the remainder of the bore whilst pumping further concrete into the bore, such that the bore fills with concrete and forms a concrete pile.
2. A method of forming a concrete pile as claimed in Claim 1, wherein in step (c) the auger is reinserted into the lower portion of the bore by screwing the auger into the concrete.
3. A method of forming a concrete pile as claimed in Claim 1 or Claim 2, wherein a pumping pressure is 2608A4V3.DOC 21 December 2000 1 1 continuously applied with a pump during steps (b) to (d).
4. A method of forming a concrete pile as claimed in Claim 3, wherein the pumping pressure is in the range 0.5 bar to 1 bar.
5. A method of forming a concrete pile as claimed in any previous claim, wherein the auger is rotated when it is retracted at least partially from the bore.
6. A method of forming a concrete pile as claimed in any previous claim, wherein concrete is continuously pumped into the bore as the auger is being retracted.
7. A method of forming a concrete pile as claimed in any previous claim, wherein the stem of the auger has a cylindrical shaf t portion and a tip portion with at least one upstanding flight arranged thereon in a helical fashion.
8. A method of forming a concrete pile as claimed in Claim 7, wherein the tip portion has two flights rotationally displaced by 180 degrees from one another.
9. A method of forming a concrete pile as claimed in Claim 7 or Claim 8, wherein, at least part of the tip portion tapers to an area of reduced diameter.
10. A method of forming a concrete pile as claimed in any one of claims 7 to 9, wherein the ratio of the maximum radial extend of the upstanding flights from the centre of the auger and the radius of the shaft portion is between 4:3 and 32:30.
11. A method of forming a concrete pile as claimed in 2608A4V3.DOC 21 December 2000 le Claim 10, wherein the ratio is substantially 35:30.
GB0012784A 2000-05-26 2000-05-26 Pile formation Expired - Fee Related GB2362673B (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
GB0012784A GB2362673B (en) 2000-05-26 2000-05-26 Pile formation
GB0100250A GB2362674A (en) 2000-05-26 2000-05-26 Auger with helical flight and fluid channel
EP01304590A EP1158104A1 (en) 2000-05-26 2001-05-24 Pile formation
US09/865,650 US20020008328A1 (en) 2000-05-26 2001-05-25 Pile formation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB0012784A GB2362673B (en) 2000-05-26 2000-05-26 Pile formation

Publications (3)

Publication Number Publication Date
GB0012784D0 GB0012784D0 (en) 2000-07-19
GB2362673A true GB2362673A (en) 2001-11-28
GB2362673B GB2362673B (en) 2002-08-21

Family

ID=9892394

Family Applications (2)

Application Number Title Priority Date Filing Date
GB0100250A Withdrawn GB2362674A (en) 2000-05-26 2000-05-26 Auger with helical flight and fluid channel
GB0012784A Expired - Fee Related GB2362673B (en) 2000-05-26 2000-05-26 Pile formation

Family Applications Before (1)

Application Number Title Priority Date Filing Date
GB0100250A Withdrawn GB2362674A (en) 2000-05-26 2000-05-26 Auger with helical flight and fluid channel

Country Status (3)

Country Link
US (1) US20020008328A1 (en)
EP (1) EP1158104A1 (en)
GB (2) GB2362674A (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU781681B2 (en) * 2000-03-06 2005-06-09 Screw In Technologies Pty Ltd Anchor elements and methods and apparatus for fabricating anchor elements
GB0422062D0 (en) * 2004-10-05 2004-11-03 Screwfast Foundations Ltd A screw pile
CN101319499B (en) * 2007-06-07 2012-03-28 刘润郊 Pile forming method and device for screwed pedestal pile with large flow concrete filled by hole drilling pump
CN103290841B (en) * 2013-06-18 2015-06-03 江苏东恒大地工程技术有限公司 Pile mould with draw-pull type movable feed ports and construction method
CN103526746A (en) * 2013-09-30 2014-01-22 王志耸 Full-thread pile pouring machine extruding soil body and pile-forming construction method thereof
CN103741679A (en) * 2013-12-23 2014-04-23 广西科技大学 Production method for pipe sinking cast-in-place file
CN103741677A (en) * 2013-12-23 2014-04-23 广西科技大学 Production method for bored pile
JP6450951B2 (en) * 2014-06-30 2019-01-16 株式会社テノックス Hydraulic solidifying material liquid replacement column building method and hydraulic solidifying material liquid replacement column building block
JP2016056650A (en) * 2014-09-12 2016-04-21 株式会社テノックス Device and method for manufacturing hydraulic solidification material liquid-substituted column, and hydraulic solidification material liquid-substituted column
CN104389308A (en) * 2014-10-17 2015-03-04 中建四局第六建筑工程有限公司 Construction method of cast-in-situ stiff piles for foundation pit supporting
JP6629076B2 (en) * 2015-05-15 2020-01-15 創伸産業株式会社 Ground reinforcement method
US10634657B2 (en) * 2018-04-18 2020-04-28 6422277 Manitoba Ltd. Pile testing device
CA3230313A1 (en) 2021-08-31 2023-03-09 Alan Conte Matthew A system and method for installing an aggregate pier

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2042029A (en) * 1979-02-13 1980-09-17 Chuan Pao Chen P Method and apparatus for forming subterranean concrete piles
GB2048999A (en) * 1979-05-14 1980-12-17 Bullivant R Improvements relating to the construction of in situ piles
WO1986004941A1 (en) * 1985-02-25 1986-08-28 Edvin Lindell A method in the installation of piles and apparatus for carrying out the method

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3206936A (en) * 1960-12-15 1965-09-21 Herman L Moor Method and means for making concrete piles
FR1322130A (en) * 1961-02-28 1963-03-29 Method and apparatus for forming a concrete pile in the ground by drilling
NL189924C (en) * 1980-02-25 1993-09-01 Hollandsche Betongroep Nv SCREW DRILL FOR MAKING CONCRETE FOUNDATION POSTS INTO GROUND AND METHOD FOR USING THIS SCREW DRILL.
NL8102327A (en) * 1981-05-12 1982-12-01 Fundamentum Bv METHOD FOR MANUFACTURING A FOUNDATION POLE AND A TUBE TO BE USED THEREOF
JPS603317A (en) * 1983-06-18 1985-01-09 Teruo Koi Construction work of foundation pile
GB2202885B (en) * 1987-04-02 1990-11-07 Westpile Int Uk Ltd Piling and auger therefor
AT394592B (en) * 1990-12-12 1992-05-11 Kellner Willibald Method of producing a tubular foundation in the ground
GB2303868B (en) * 1995-07-31 1999-04-14 Cementation Piling & Found Improved auger piling
FR2758577B1 (en) * 1997-01-22 1999-03-12 Menard Soltraitement METHOD, DEVICE AND MATERIALS FOR CONSOLIDATING A FURNISHED AND / OR COMPRESSIBLE LAND, IN PARTICULAR FOR RECEIVING A BUILDING ON IT
GB2345715B (en) * 1999-01-12 2003-07-09 Kvaerner Cementation Found Ltd Composite auger piling

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2042029A (en) * 1979-02-13 1980-09-17 Chuan Pao Chen P Method and apparatus for forming subterranean concrete piles
GB2048999A (en) * 1979-05-14 1980-12-17 Bullivant R Improvements relating to the construction of in situ piles
WO1986004941A1 (en) * 1985-02-25 1986-08-28 Edvin Lindell A method in the installation of piles and apparatus for carrying out the method

Also Published As

Publication number Publication date
GB0100250D0 (en) 2001-02-14
EP1158104A1 (en) 2001-11-28
GB2362674A (en) 2001-11-28
GB2362673B (en) 2002-08-21
GB0012784D0 (en) 2000-07-19
US20020008328A1 (en) 2002-01-24

Similar Documents

Publication Publication Date Title
US3391544A (en) Means and method of forming concrete piles
US5934836A (en) Ground anchor device
US5919005A (en) Ground anchor device for penetrating an underground rock formation
US3842608A (en) Method and means for installing load bearing piles in situ
US3453832A (en) Cast-in-place casings for concrete piles
EP0831180B1 (en) Drill for making a pile in the ground and method applying this drill
US5219246A (en) Drills for piles and soil stabilization, and drilling method
US3864923A (en) Impacted casing method for installing anchor piles or tiebacks in situ
US6402432B1 (en) Method for installing load bearing piles utilizing a tool with blade means
EP1158104A1 (en) Pile formation
US6283231B1 (en) Soil displacing screw auger and method for making a concrete pile with this auger
US3206936A (en) Method and means for making concrete piles
JPS62501087A (en) Driving shoe for conductor pipe
US3568452A (en) Method and apparatus for forming bulbular base piles
EP1277887A2 (en) Displacement drilling tool and equipment using said tool
US6120214A (en) Process for constructing reinforced subterranean columns
GB2429229A (en) Methods and apparatus for the installation of foundation piles
US4761098A (en) Drilling means serving as ground anchor and method
US2650476A (en) Dowel rod anchor
CN209339143U (en) A kind of concrete pipe pile construction equipment
RU2128270C1 (en) Method of driving tubular pile into permafrost
RU2317373C1 (en) Method for bored pile erection in ground
KR101024257B1 (en) The earth anchor operate method which reinforces a soft ground and the device
RU2717554C1 (en) Bored pile device method
RU2328575C1 (en) Bored auger pile installation device

Legal Events

Date Code Title Description
732E Amendments to the register in respect of changes of name or changes affecting rights (sect. 32/1977)
PCNP Patent ceased through non-payment of renewal fee

Effective date: 20090526