GB2339590A - Four day cycle for construction of semi precast multi-storey buildings - Google Patents

Four day cycle for construction of semi precast multi-storey buildings Download PDF

Info

Publication number
GB2339590A
GB2339590A GB9815030A GB9815030A GB2339590A GB 2339590 A GB2339590 A GB 2339590A GB 9815030 A GB9815030 A GB 9815030A GB 9815030 A GB9815030 A GB 9815030A GB 2339590 A GB2339590 A GB 2339590A
Authority
GB
United Kingdom
Prior art keywords
construction
concrete
floor
working
walls
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
GB9815030A
Other versions
GB2339590B (en
GB9815030D0 (en
Inventor
Tin Cheung Conrad Wong
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MADISON CONSULT SERV Ltd
Original Assignee
MADISON CONSULT SERV Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MADISON CONSULT SERV Ltd filed Critical MADISON CONSULT SERV Ltd
Priority to GB9815030A priority Critical patent/GB2339590B/en
Publication of GB9815030D0 publication Critical patent/GB9815030D0/en
Priority to SG9902532A priority patent/SG83718A1/en
Priority to CN 99110313 priority patent/CN1131918C/en
Publication of GB2339590A publication Critical patent/GB2339590A/en
Priority to HK00102388A priority patent/HK1023167A1/en
Application granted granted Critical
Publication of GB2339590B publication Critical patent/GB2339590B/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • E04B1/161Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with vertical and horizontal slabs, both being partially cast in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/04Devices for both conveying and distributing

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

2339590 4 DAY CYCLE FOR CONSTRUCTION OF SEMI PRECAST MULTI-STOREY
BUILDINGS This invention relates to an improved method of construction of multi- storey buildings using the semi precast method of construction. The semi- precast method of construction is disclosed in patent application number GB9626126.8, filed on 17th December 1996.
The present method of construction is particularly applicable to the construction of 2 or more multi storey buildings in high density areas where space is limited.
It is an advantage of the present method of construction that there is a significant reduction in the time taken to complete erection of the superstructure of the building, which in turn results in not only overall costs savings, but also earlier completion and occupation of the building. It is a further advantage of the present invention that there is a reduction in the number of workers required for the construction.
The speed of construction of a multi-storey building is determined by several factors. The most significant of these factors is the availability of materials for use in the construction and the availability of the tower crane to move concrete and materials from ground level to the working floor. The number of tower cranes that can be deployed on site is determined by the number of buildings being constructed at the site and by the radius of the crane.
A considerable amount of the tower crane's time is taken up transporting concrete from ground level to the working floor. Concrete is transported in traditional concrete buckets. As the concrete bucket can only hold a certain volume of concrete, a very large number of trips are necessary to transport the volume of concrete required for the work to be carried out. Thus other material can only be transported to the working floor when the crane is not transporting concrete.
In the construction of a typical multi-storey building for example the work schedule of the tower crane rotates between moving materials to the different wings of the building and moving concrete for the construction of the walls and floors of each wing. This requires careful planning to ensure maximal deployment of tower crane during the working day.
With the semi precast method of construction it can take up to 6 days for the completion of a typical floor. Using this method of construction the precast facade is erected first. The facade is lifted into place by a crane and once the facade is in place wall reinforcements are fixed. After the wall reinforcements have been fixed wall forms are erected around the wall reinforcements for the structural cross walls. Once this has been completed concrete is poured to create the structural cross walls. The wall forms are then removed once the structural walls are cast. Precast floor slabs are then lifted and placed on top of the cross walls and floor slab reinforcements are then fixed. The final step of the process is to concrete the floor slab. These steps are repeated for all wings of the floor in accordance with a carefully defined work schedule. A typical construction schedule for the 6 day cycle can be seen in Table 1.
-3In general terms the construction cycle for each wing is as follows:
Day 1: placing the precast facade and fixing the wall reinforcement.
Day 2: placing and fixing the wall form for the structural cross walls.
Day 3: concreting the cross walls.
Day 4: stripping wall forms and placing pre cast floor slabs.
Day 5: fixing timber slabs and floor slab reinforcements.
Day 6: concreting the floor slabs.
Thus with the normal 6 day cycle a total of 2 working days are taken up in the construction of each floor with concreting work and thus during this period the tower crane is not available to transport any other material to the working floor. As a result of this some workers at the site are idle.
The present invention relates to a method of construction of multi-storey buildings using the semi precast method of construction wherein the construction of each floor can be completed in 4 working days and wherein the tower crane is only employed to move materials, but not concrete needed in the construction of the walls and floors, to the working floor.
With the present invention the construction of a typical floor can be completed in 4 working days. This is achieved by eliminating the need to transport concrete to the working floor by the tower crane. Instead concrete is pumped to the working floor by a high pressure concrete pump from the concrete mixing device, situate at the ground level to the working floor. All operations for the completion of a wing are carried out in one day across the different wings of the building, thus minimizing the time workers are idle.
The concrete pump is connected to the outlet of a concrete mixing device to receive ready mixed concrete and the outlet of the concrete pump is attached to a suitable pipe to enable concrete delivered from the concrete mixing device to the be pumped to the working floor.
This then free's the tower crane to transport other material to the working floor.
At the working floor it is necessary to erect a hydraulic jib to enable concrete to be placed for both floor slabs and the structural cross walls. The hydraulic jib is itself placed on a portable steel column fitting which is supported over several floors and can be relocated upwards in accordance with the progress of the construction.
In order to use the concrete pump it is necessary to modify the concrete slump from the standard 75mm to 100mm by introducing a higher cement content into the concrete mix. The concrete thus maintains its strength but is easier to pump to the working floor.
Using this present method of construction the precast facade is lifted into place by a crane. Once the facade is in place wall reinforcements are fixed and the wall forms are erected around the wall reinforcements for the structural cross walls. Once this has been completed concrete is poured to create the structural cross walls. This can all be achieved in one day as the tower crane is available to transport material to the working floor and the concrete needed is pumped to the floor by the concrete pump.
After the structural cross walls are cast the wall forms are removed and the precast floor slabs are laid on the cross walls. This can be achieved during the second day of the construction cycle. Floor slab reinforcements are then laid for the flooF and the floor slabs can be concreted on the final day.
The cycle is the repeated for each wing of the floor and the entire floor can be completed in 4 days. These steps are repeated for all wings of the floor in accordance with a carefully defined work schedule. A typical construction schedule for the 4 day cycle can be seen in Table 2.
The operation of the 4 day cycle construction plan can be illustrated by the following timetable:
Day 1: place and fix precast facade, fix wall forms and concrete the walls.
Day 2: strip wall forms and place precast slabs and fix timber slabs.
Day 3: fix slab reinforcements.
Day 4: concrete floor slabs.
The actual sequence of construction of the 4 day cycle can be varied without any impact on the overall time to complete each floor. Thus for example it is possible for the different wings to reach different heights e.g wing A is completed to floor 10, while wing B is still at floor 8 and wings C & D are at floor 7.
In the 4 day cycle it is vital to ensure a constant supply of concrete. Traditionally concrete has been transported to the site by concrete mixing trucks from remote concrete batching plants. The problem with this method is that there are often delays in getting the concrete to the copstruction site, especially in built up areas, which in turn results in delays in the construction.
This problem is overcome by using a mobile batching plant of the type disclosed in patent application number GB 9622397.9, filed on 28th October 1996.
An onsite batching plant ensures adequate supplies of concrete are available when needed. The concrete produced by the batching plant is poured directly into the high pressure pump and is pumped by the high pressure concrete pump directly to the working floor.
TABLE 1 :Desc:ripU:io:n:::_ Day 1 2 3 4 5 6 Fix Wall Reinforcement moonoemum Concealed Conduit dam mmum Place Wall Form Concrete Wall Strip Wall Form Place Precast Slab Fix Timber Slab Form Fix Slab Reinforcement Concrete Slab Place Precast Facade TABLE 2 :D e: s:c:ri p:Ci o n. Da y 1 2 3 4 Fix Wall Reinforcement Place Precast Facade Concealed Conduit Place Wall Form PON Concrete Wall Strip Wall Form Place Precast Slab Fix Aluminium Slab Form Fix Slab Reinforcement Concrete Slab

Claims (3)

1. A method of construction of multi-storey buildings using the semi precast method of construction wherein the construction of each floor can be completed in 4 working days and wherein the tower crane is only employed to move materials, but not concrete needed in the construction of the walls and floors, to the working floor.
2. A method of construction as claimed above wherein the construction of a wing is carried out in 4 operations and wherein one operation is the placement and fixing of a precast facade and fixing of wall forms and concreting of the walls and wherein another operation is to strip the wall forms and place precast slabs and fix timber slabs and wherein another operation is to fix slab reinforcements and wherein another operation is to concrete the floor slabs and wherein all 4 operations can be carried out in one day across the different wings of the building such that all wings on one floor are completed in 4 days.
3. A method of construction as claimed above wherein the concrete required in the construction of the walls and the floor is delivered to the working floor by means of a high pressure pump via a suitable pipe means and wherein one end of the said pipe means is connected to a concrete mixing device to receive concrete and the other end of the said pipe means is connected to a hydraulic jib to facilitate the placement of concrete throughout the working floor and wherein the hydraulic jib is mounted on a detachable and portable column to facilitate the placement of the hydraulic jib on the working floor and relocation from the -10working floor.
A method of construction as claimed above wherein the concrete for use in the construction of the walls and the floors of the building is prepared on site by means of a batching plant and concrete mixing device and wherein the outlet of the concrete mixing device is connected to the said high pressure pump such that concrete from the concrete mixing device can be pumped to the working floor.
GB9815030A 1998-07-13 1998-07-13 4 Day cycle for constuction of semi precast multi-storey buildings Expired - Fee Related GB2339590B (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
GB9815030A GB2339590B (en) 1998-07-13 1998-07-13 4 Day cycle for constuction of semi precast multi-storey buildings
SG9902532A SG83718A1 (en) 1998-07-13 1999-05-20 4 day cycle for construction of semi precast multi-storey buildings
CN 99110313 CN1131918C (en) 1998-07-13 1999-07-13 Four-date construction period for semi-precast multistoried building
HK00102388A HK1023167A1 (en) 1998-07-13 2000-04-20 Four day cycle for construction of semi precast multi-storey buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB9815030A GB2339590B (en) 1998-07-13 1998-07-13 4 Day cycle for constuction of semi precast multi-storey buildings

Publications (3)

Publication Number Publication Date
GB9815030D0 GB9815030D0 (en) 1998-09-09
GB2339590A true GB2339590A (en) 2000-02-02
GB2339590B GB2339590B (en) 2002-08-21

Family

ID=10835325

Family Applications (1)

Application Number Title Priority Date Filing Date
GB9815030A Expired - Fee Related GB2339590B (en) 1998-07-13 1998-07-13 4 Day cycle for constuction of semi precast multi-storey buildings

Country Status (4)

Country Link
CN (1) CN1131918C (en)
GB (1) GB2339590B (en)
HK (1) HK1023167A1 (en)
SG (1) SG83718A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296837B (en) * 2011-07-13 2013-04-10 有利华建筑预制件有限公司 Multistoried building with prefabricated members and semi-prefabricating construction method of multistoried building

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4717517A (en) * 1982-08-13 1988-01-05 Halberstadt Alex E Concurrent method of building construction and formwork structure therefore

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4717517A (en) * 1982-08-13 1988-01-05 Halberstadt Alex E Concurrent method of building construction and formwork structure therefore

Also Published As

Publication number Publication date
HK1023167A1 (en) 2000-09-01
GB2339590B (en) 2002-08-21
SG83718A1 (en) 2001-10-16
CN1245239A (en) 2000-02-23
GB9815030D0 (en) 1998-09-09
CN1131918C (en) 2003-12-24

Similar Documents

Publication Publication Date Title
CN103615053B (en) Monolithic reinforced concrete structure post empiricism engineering method
CN107297810A (en) A kind of making of precast wall body component and installation method
CN109736354A (en) Tunnel open excavation section main structure construction method
CN108532466A (en) A kind of bridge pier over-form construction technique
CN109853956A (en) Residential building construction method
CN105780992A (en) Construction method of orthogonal and ortho-laid steel concrete vierendeel sandwich plate floor
CN104790565B (en) A kind of cast-in-place phosphogypsum bearing wall Temperature Variation In Buildings of Mixed Structures main body construction method
CN112411597A (en) Construction method of side formwork of underground bearing platform
CN109837910B (en) Foundation pit construction method combining reverse construction method and steel support
GB2339590A (en) Four day cycle for construction of semi precast multi-storey buildings
CN2239997Y (en) Ring beam capable of making prefabricated floor slab monolithic pure at the support
CN108396900A (en) A kind of double Shell roof boarding and its construction method
CN101240569A (en) In-situ integrated placing construction method for aerated concrete wall
WO1986000043A1 (en) Building system and portable masonry plant suitable therefor
JP2824455B2 (en) Outlet structure and construction method for large silo
CN111825420A (en) GRC cement board and preparation method thereof
CN111827239A (en) Construction method of assembled berthing pier
Grasser et al. Building with pumice
CN219006422U (en) Prefabricated cushion cap template of foam concrete
JP3292996B2 (en) Construction method of slab floor in steel building
CN102312578A (en) Integral vibration-free pouring and constructing method and application, mold and equipment thereof
Kulikov et al. The Prospects of a Small-Block House Building within the Concept of the Automated Structure Construction of Residential Buildings
DERRINGTON et al. THE APPLICATION OF PRECAST CONCRETE TO THE CONSTRUCTION OF ACTON LANE'B'POWER STATION.
Ruhnke et al. Description of tilt-up concrete wall construction
AU703801B2 (en) Building construction method

Legal Events

Date Code Title Description
PCNP Patent ceased through non-payment of renewal fee

Effective date: 20040713