GB2205883A - Method of creating an artificial island - Google Patents

Method of creating an artificial island Download PDF

Info

Publication number
GB2205883A
GB2205883A GB8709122A GB8709122A GB2205883A GB 2205883 A GB2205883 A GB 2205883A GB 8709122 A GB8709122 A GB 8709122A GB 8709122 A GB8709122 A GB 8709122A GB 2205883 A GB2205883 A GB 2205883A
Authority
GB
United Kingdom
Prior art keywords
face
retaining
fill material
ramp
fill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
GB8709122A
Other versions
GB8709122D0 (en
GB2205883B (en
Inventor
Ronald Jarman Bridle
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
University College Cardiff Consultants Ltd
Cardiff University
Original Assignee
University College Cardiff Consultants Ltd
Cardiff University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by University College Cardiff Consultants Ltd, Cardiff University filed Critical University College Cardiff Consultants Ltd
Priority to GB8709122A priority Critical patent/GB2205883B/en
Publication of GB8709122D0 publication Critical patent/GB8709122D0/en
Publication of GB2205883A publication Critical patent/GB2205883A/en
Application granted granted Critical
Publication of GB2205883B publication Critical patent/GB2205883B/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/0017Means for protecting offshore constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

An artificial island is constructed by driving piles 1 into the sea or lake bed 2, constructing a retaining face by means of blocks or panels or other in filling between or around the piles, filling the structure with hydraulic fill material some of which escapes at the bottom to form a sloping ramp 7 and protecting the surface of this ramp against erosion. The structure may be reinforced by ties or mats attached to the elements of the face to help retain them against the pressure of the in fill material and to reinforce the structure. In an alternative method of construction the face may be constructed by wrapping material round lines lowered into the water from the surface. <IMAGE>

Description

11 2205883 METHOD OF CONSTRUCTING ARTIFICIAL ISLANDS AND LAND EXTENSIONS
The invention relates to a method for constructing an island in or an extension of land into a body of water for example the sea, an estuary or a lake.
The invention is defined in the claims appended hereto and embodiments of it will now be described with reference to the accompanying drawings in which:- Figure 1 is a fragmentary elevation in section through an artificial island of generally oval outline; Figures 2 and 3 show reinforcing means applicable to the construction of Figure 1; and Figure 4 shows an alternative construction for an island or extension of land onto the bed of the sea or a lake.
Referring first to Figure 1, in the construction of an artifical island, piles 1 are driven into the seabed 2, the piles are arranged around the perimeter of the intended island. Around the outline defined by the piles a retaining face is constructed for retaining fill material deposited within the piles. The face may comprise polymer or othd material wrappe d round the piles or by blocks or panels 3 of any suitable material supported by the piles. The blocks or panels may interlock with the piles or with another for additional security and to provide better sealing against the leakage of the hydraulic fill material which, as will be described later, forms the main body of the artificial island.
1 2 For additional support, a employed. These ties 4 extend panels forming the face and a central anchorage 5. They perform the dual function of maintaining the face against the pressure exerted by the fill material and of acting as a reinforcement for the fill after it has settled in position. In addition to the main ties 4, extending between the anchorage and the blocks or panels of the face subsidiary ties 6 may extend from the main ties 4 to the face blocks or panels. The arrangements of the ties is shown in plan in Figure 2.
Another method of reinforcement which serves the purposes both of anchoring the face and of reinforcing the filling is by means of mats formed by transversely crossing strips extending between the face panels. These mats may be built up from strips of net, fastened at their ends to the insides of the face panels, both ties and nets may be employed in combination in the same structure.
Once the structure is completed, hydraulic fill material is. pumped into it. As this material settles some escapes at the bottom of the structure below the retaining face where It forms a sloping surface or ramp 7 having a low angle of slope. Filling is continued until the structure is filled to above the water level 8.
system of ties may be betwe.en the blocks or 1 t, 1 3 The surface of the ramp 7 is then treated to protect it from scouring by the action of the water. This may be done by conventional methods used for the prevention of errosion or by the provision of artificial seaweed.
The edge of the structure where it protrudes from the water surface may be protected against errosion by wave action by providing pre-cast units of suitable material for example reinforced concrete 9 hanging over the edge and anchored internally to the structure.
The island may be completed by a layer of soil planted with trees and shrubs etc., for humanity purposes or it may be used to support buildings or other structures on its surface.
The hydraulic fill may comprise material-dredged from the seabed in the neighbourhood or locally available waste material or a combination of both thereby avoiding the cost of bringing fill materials from a distance.
The example just described was an island of oval form but the structure need not be an island it can be an extension of land into the sea or a lake or estuary or the in filling of a bay in the shoreline but the general method of construction is the same.
A further example of the invention will now be described with reference to Figure 4.
1 4 In the example described above, piles were first driven into the seabed and the fill retaining face was built up from below, such process necessarily requiring underwater work by divers. In the embodiment to be described, the base structure is built up at the water surface level and lowered to the sea or lake bed as the case may be.
In this embodiment, a number of stout lines 20 each bearing at its lower end a vacuum anchor 21 are lowered in the required positions for example from moored pontoons. As the lines are lowered, a cover 22 of suitable material for example a polymer is wrapped round the outside of the ring of guidelines and fixed to each line. The wrapping process is continued as the lines are lowered and ties or reinforcing mats may be added at suitable intervals as indicated in the example described with reference to Figures 1, 2 and 3.
As before, the structure is completed by pumping in the hydraulic fill protecting the ramp 7 which is formed at the base of the structure by the escaping in fill material against errosion and providing a seal 9 if necessary for additional protection against wave action.
This latter method of construction avoids the need for divers or frogmen to work underwater to affix the face material.
CC

Claims (11)

  1. C L A I M S: 1. A method of constructing an island in or an extension of
    land into water, the method comprising the steps of.
    i. constructing a retaining face for retaining hydraulic fill material; il. pumping hydraulic fill material into the space bounded by the retaining face so that part of the fill material escapes below the retaining face to form a ramp of low slope; and iii. protecting the ramp surface from scouring.
  2. 2. A method according to Claim 1 in which the face comprises piles supporting panels or blocks.
  3. 3. A method according to Claim 2 in which the panels or blocks are arranged to interlock one with another.
  4. 4. A method according to Claim 1 in which the face comprises piles or guidelines around which material is bound.
  5. 5. A method according to any preceding claim in which tie lines are fixed to the elements of the face structure to support them against the pressure of the in fill and to reinforce the in fill material.
  6. 6. A method according to any preceding claim in which mats are fo.rmed by strips extending from side to side of the structure and attached to elements of the face to support them against the pressure of the in fill and reinforce the structure. 1 6
  7. 7. A method according to any preceding claim in which the ramp is protected against scouring by artificial seaweed.
  8. 8. A method according to any preceding claim in which units are provided at the water surface to protect the structure against wave action.
  9. 9. A method according to Claim 1 in which the retaining face comprises material wrapped around guidelines which are lowered from the water surface.
  10. 10. An artificial island constructed by a method according to any preceding claim.
  11. 11. A construction according to any preceding claim comprising a portion of shoreline extended into water.
    Puclished 1988 at TI.e Patent Oflice. State House. 66 '1 Righ Rolborn, London WC1R 4TP. FiMher cepies maybe obtained from The P4tent Office, t 1 i 17
GB8709122A 1987-04-15 1987-04-15 Method of constructing artificial islands and land extensions Expired GB2205883B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
GB8709122A GB2205883B (en) 1987-04-15 1987-04-15 Method of constructing artificial islands and land extensions

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB8709122A GB2205883B (en) 1987-04-15 1987-04-15 Method of constructing artificial islands and land extensions

Publications (3)

Publication Number Publication Date
GB8709122D0 GB8709122D0 (en) 1987-05-20
GB2205883A true GB2205883A (en) 1988-12-21
GB2205883B GB2205883B (en) 1991-05-01

Family

ID=10615931

Family Applications (1)

Application Number Title Priority Date Filing Date
GB8709122A Expired GB2205883B (en) 1987-04-15 1987-04-15 Method of constructing artificial islands and land extensions

Country Status (1)

Country Link
GB (1) GB2205883B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001088278A1 (en) * 2000-05-15 2001-11-22 Vladimir Sandzhievich Boldyrev Artificial island, offshore structure for an artificial island and method for building an artificial island

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117661512B (en) * 2023-11-09 2024-04-26 中交二航局第一工程有限公司 Time-saving and material-saving control method for flexible shore protection hydraulic reclamation port

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001088278A1 (en) * 2000-05-15 2001-11-22 Vladimir Sandzhievich Boldyrev Artificial island, offshore structure for an artificial island and method for building an artificial island
US6520720B1 (en) 2000-05-15 2003-02-18 Vladimir Sandzhievich Boldurev Artificial island, artificial island support and method for building an artificial island

Also Published As

Publication number Publication date
GB8709122D0 (en) 1987-05-20
GB2205883B (en) 1991-05-01

Similar Documents

Publication Publication Date Title
US4966491A (en) Subsurface dune protection system and method
US5320455A (en) Geocell with facing panel
US20030091391A1 (en) Precast modular intermodal concrete shapes and methods of installation to form shoreline stabilization, marine and terrestrial structures
US7992509B1 (en) Shellfish habitats
KR102097580B1 (en) A Method for the Construction of Offshore Structures Using General Concrete
GB2205883A (en) Method of creating an artificial island
US20080219772A1 (en) Berm System
US5061122A (en) Method of constructing a man-made sea defense system in the open ocean
US3326005A (en) Retaining wall for waterways
JP2001152425A (en) Impervious structure of revetment
JP3510366B2 (en) How to build underwater structures
JPS58106007A (en) Underwater structure and construction thereof
JP2662604B2 (en) Wave-dissipating structure, its construction method and frame
JPS5942765B2 (en) cofferdam
EP0391736A2 (en) Underwater wall construction
JP3065555B2 (en) Earth removal type artificial ground, its construction method and construction unit used for it
JPH08184022A (en) Method of aerial reclamation construction
RU2097484C1 (en) Coast-protecting alluvial structure
JP2745097B2 (en) Construction method of low temperature liquefied gas underground tank
JPH06257163A (en) Droughty pontoon for constructing shallow foundation
KR100401214B1 (en) A breakwater for soft ground
JP2004011142A (en) Sea area environment-coexistent quay structure
JPS6215300Y2 (en)
JP2003221817A (en) Protecting mat
JPS61286417A (en) Cofferdam structure

Legal Events

Date Code Title Description
PCNP Patent ceased through non-payment of renewal fee

Effective date: 19960415