GB1030619A - A process for the production of piles - Google Patents

A process for the production of piles

Info

Publication number
GB1030619A
GB1030619A GB47794/63A GB4779463A GB1030619A GB 1030619 A GB1030619 A GB 1030619A GB 47794/63 A GB47794/63 A GB 47794/63A GB 4779463 A GB4779463 A GB 4779463A GB 1030619 A GB1030619 A GB 1030619A
Authority
GB
United Kingdom
Prior art keywords
casing
concrete
mandrel
piles
dec
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
GB47794/63A
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ENTPR S H COURBOT
Original Assignee
ENTPR S H COURBOT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ENTPR S H COURBOT filed Critical ENTPR S H COURBOT
Publication of GB1030619A publication Critical patent/GB1030619A/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/28Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes
    • E02D7/30Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes by driving cores
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/10Follow-blocks of pile-drivers or like devices
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/54Piles with prefabricated supports or anchoring parts; Anchoring piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

1,030,619. Concrete piles. ENTERPRISES H. COURBOT. Dec. 3, 1963 [Dec. 3, 1962; July 15, 1963; Aug. 23, 1963], No. 47794/63. Heading E1H. A process for the production of piles comprises forming a casing from hollow -tube portions whichare adhesively secured end-toend and then filled, the length of the casing being increased as the driving of the pile progresses. The casing is made from a number of prefabricated tubes e.g. of concrete or metal which are bonded together by a synthetic adhesive having good mechanical properties. After the casing has penetrated to the required depth it is filled with concrete 4 which may be reinforced. For penetration a mandrel (Fig. 4, not shown) is used inside the casing, a helmet being disposed at the upper end of the mandrel for a better distribution of the forces applied during the driving. An expandible mandrel (Fig. 12, not shown) may be used. Some of the hollow tube portions may have lateral orifices, each orifice being equipped with a ball-type valve (Fig. 8, not shown) which prevents soil entering the casing but allows concrete passed into the casing to flow through the orifices into the surrounding soil. In an embodiment illustrated in (Fig. 13, not shown) drilling is effected by means of an Archimedean screw.
GB47794/63A 1962-12-03 1963-12-03 A process for the production of piles Expired GB1030619A (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
FR917339A FR1340087A (en) 1962-12-03 1962-12-03 Process for manufacturing a pile, in particular for a foundation, as well as piles conforming to those obtained by the present process or similar process
FR941503A FR83995E (en) 1962-12-03 1963-07-15 Method of manufacturing a pile, in particular for foundations, as well as piles conforming to those obtained by the present method or similar method
FR945568A FR1366598A (en) 1962-12-03 1963-08-23 Process for manufacturing piles intended in particular for construction and piles conforming to those obtained by applying the present process or a similar process

Publications (1)

Publication Number Publication Date
GB1030619A true GB1030619A (en) 1966-05-25

Family

ID=27246932

Family Applications (1)

Application Number Title Priority Date Filing Date
GB47794/63A Expired GB1030619A (en) 1962-12-03 1963-12-03 A process for the production of piles

Country Status (4)

Country Link
CH (1) CH429606A (en)
FR (3) FR1340087A (en)
GB (1) GB1030619A (en)
OA (1) OA00032A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4966498A (en) * 1989-08-16 1990-10-30 Berkel & Company Contractors, Inc. Pile-forming apparatus for use in low density overburden
EP0505218A1 (en) * 1991-03-22 1992-09-23 Westpile Limited Improvements in venting of landfill and control of leachate
WO2002020186A1 (en) * 2000-09-08 2002-03-14 Permavoid Limited Fluid movement apparatus
CN104652408A (en) * 2015-02-13 2015-05-27 福建省建专岩土工程有限公司 Strip-shaped sand bag pile and construction method thereof

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2621627B2 (en) * 1984-12-07 1990-02-02 Crambes Michel IMPROVEMENT OF THE COMPACTION-REINFORCEMENT-INJECTION AND DECOMPACTING-DRAINAGE PROCESS OF THE SOILS USING AUXILIARY TUBES
JPH03500431A (en) * 1987-10-07 1991-01-31 クラムベ ミッシェル Compaction of soil with secondary tubes - reinforcement, injection or loosening - improvements to the method of drainage

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4966498A (en) * 1989-08-16 1990-10-30 Berkel & Company Contractors, Inc. Pile-forming apparatus for use in low density overburden
EP0505218A1 (en) * 1991-03-22 1992-09-23 Westpile Limited Improvements in venting of landfill and control of leachate
WO2002020186A1 (en) * 2000-09-08 2002-03-14 Permavoid Limited Fluid movement apparatus
US6913420B2 (en) * 2000-09-08 2005-07-05 Permavoid Limited Fluid movement apparatus
CN104652408A (en) * 2015-02-13 2015-05-27 福建省建专岩土工程有限公司 Strip-shaped sand bag pile and construction method thereof
CN104652408B (en) * 2015-02-13 2016-04-13 福建省建专岩土工程有限公司 The stake of bar shaped sand pocket and construction method thereof

Also Published As

Publication number Publication date
OA00032A (en) 1966-01-15
FR83995E (en) 1964-11-06
CH429606A (en) 1967-01-31
FR1340087A (en) 1963-10-11
FR1366598A (en) 1964-07-10

Similar Documents

Publication Publication Date Title
GB1323031A (en) Method of reinforcing rock formation
GB1030619A (en) A process for the production of piles
ES449858A1 (en) Method for the production of piles cast in the ground and hollow auger for implementing the method
GB796262A (en) Improvements in or relating to piles
ES387639A1 (en) Anchor tie construction and method of setting an anchor tie in the ground
GB796959A (en) Improvements in or relating to the treatment of subterranean formations
DE1904371C3 (en) Method for producing a grouting anchor and sheathing for carrying out the method
CN205422599U (en) Strenghthened type drilling rod hole bottom blender
JPS55165314A (en) Method and device for chemical grouting for improvement of ground
GB256150A (en) Improvements in the construction of concrete piles
GB1029396A (en) Improvements in or relating to the production of structures from castable building material
GB1340355A (en) Method and apparatus for making a bore hole in the ground
FR2306307A1 (en) Valved injection tube string for anchoring embankments - has helical boring rib on end tube and threaded connexions
GB1410126A (en) Formation of piles in the ground
GB335101A (en) Improvements in supporting piles for buildings
GB596408A (en) Improvements relating to tunnelling and like subterranean operations
GB628795A (en) Improvements in or relating to piles
DE860175C (en) Equipment for the production of reinforced in-situ concrete piles
GB988706A (en) Improvements in or relating to the production of concrete piles
GB976550A (en) Method of securing anchor bolts in drill holes
GB1252321A (en)
GB699615A (en) Improved two part foundation pile
SU390277A1 (en) METHOD OF PASSAGE OF VERTICAL MINING OPERATIONS IN COMPLEX HYDROGEOLOGICAL CONDITIONS
GB959239A (en) Improvements in or relating to reinforced concrete piles
GB959265A (en) Improvements in and relating to piles