EP3613944B1 - Water drainage system - Google Patents

Water drainage system Download PDF

Info

Publication number
EP3613944B1
EP3613944B1 EP19182486.1A EP19182486A EP3613944B1 EP 3613944 B1 EP3613944 B1 EP 3613944B1 EP 19182486 A EP19182486 A EP 19182486A EP 3613944 B1 EP3613944 B1 EP 3613944B1
Authority
EP
European Patent Office
Prior art keywords
tube
water
collar
wall
filtering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP19182486.1A
Other languages
German (de)
French (fr)
Other versions
EP3613944A1 (en
Inventor
Antonio Sanella
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Clivio Srl
Original Assignee
Clivio Srl
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Clivio Srl filed Critical Clivio Srl
Publication of EP3613944A1 publication Critical patent/EP3613944A1/en
Application granted granted Critical
Publication of EP3613944B1 publication Critical patent/EP3613944B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage

Definitions

  • the present invention relates to a subsoil water drainage system. Drainage systems are used in various sectors such as the stabilisation of an underground area subject to landslides or to increase safety during drilling, for example drilling tunnels. Such prior art system are for instance known from EP1911886A1 and EP1908884A1 .
  • one of the draining methods envisages the building of a small reinforced concrete tunnel in proximity to the area subject to landslides or the place in which a tunnel is to be built.
  • the tunnel is sufficiently wide to allow the passage of the workers.
  • drilling can be performed through corresponding drainage tubes.
  • a disposable drill bit is placed at the end of each drainage tube.
  • the tube is placed in rotation and in this way it is made to advance in the subsoil transversally to the tunnel.
  • Pressurised water is pumped to the bit in order to facilitate drilling, the removal of the drilled material and cooling.
  • the water is conveyed to the bit inside the tube, then it exits by crossing a non-return valve.
  • the filtering bodies are placed by interference inside through holes made on the wall of the tube.
  • the tube is made of metallic material and also the filtering bodies have an outer portion made of metallic material.
  • a drawback of this embodiment is that the pressurised water that is introduced into the tube during installation could overcome the interference between the filtering bodies and the tube, expelling the filtering bodies from the respective seats. This could therefore compromise both the correct installation of the drainage tube reducing the water flow rate to the disposable bit and the correct operation of the drainage pipe once installed. In fact, the absence of filtering bodies would cause the entry of debris. Or the filtering bodies, if removed from the correct position, could even obstruct the channel in an undesired way.
  • the technical task underlying the present invention is to propose a drainage system which obviates the drawbacks in the known art as described above.
  • an object of the present invention is to provide a drainage system able to improve the correct operation.
  • reference numeral 1 denotes a drainage system.
  • the drainage system 1 comprises a water drainage tube 2 for draining a liquid, typically water.
  • the tube 2 is made of metallic material.
  • the tube 2 comprises a wall 20 provided with through holes 21.
  • the wall 20 is a side wall of the tube 2 and the holes 21 cross the thickness of the wall 20.
  • the system 1 comprises a drill bit 22 placed at an end of the tube 2.
  • the drill bit 22 is preferably at least partially disposable. In fact it could be a single-use bit. Once used for drilling it is left in situ (until the end of drilling). In the solution of figure 2 the bit 22 is completely disposable. In an alternative solution the bit 22 could be at least partially removed making it transit inside the tube 2 (solution exemplified in figure 1 ).
  • the drainage system 1 comprises a group 300 of filtering bodies fitted in the corresponding holes 21.
  • the holes 21 are advantageously distributed along the length of the tube 2. They advantageously lie along the same straight line.
  • the holes 21 are facing along different dimensions. For example they may be distributed according to a helical trend. For example a part of the holes 21 face upwards, or downwards, others are afforded on the lateral sides.
  • the drainage system 1 is self-drilling. This means that the tube 2 responsible for drainage and comprising the bit 22 performs the drilling itself.
  • the tube 2 advantageously extends along an inclined straight line.
  • the bit 22 is higher. This facilitates the outflow of water.
  • the filtering bodies of said group 300 comprise at least a first filtering body 3 fitted in one of said holes 21.
  • the first filtering body 3 assumes a first configuration in which it comprises water-soluble waterproofing means 31 which prevents passage of water.
  • the first filtering body 3 assumes a second configuration wherein the water-soluble waterproofing means 31 is absent, enabling the water to pass through the thickness of a wall 20 of the tube 2. In fact, in the second configuration the water-soluble means 31 has been dissolved. This is because of the contact with the water pumped through the tube 2 during drilling or however with the subsequent contact with the water present in the subsoil and that the tube 2 proposes to drain.
  • Such water-soluble means 31 is/comprises for example a water-soluble glue (an example of the water-soluble means 31 could be the material known by the trade name of Hydrolene). It internally obstructs a passage section of the first body 3. One or more of the characteristics described with reference to the first filtering body 3 can be repeated for all the other filtering bodies of said group 300 of filtering bodies.
  • the first filtering body 3 of said group 300 comprises snap-fitting means 30 to the wall 20 of the tube 2.
  • the snap-fitting means 30 comprises flexible anchoring fins 301 to an internal surface 201 of the tube 2. Such fins 301 define flexible hooks.
  • the fins 301 are elastically deformable.
  • the first filtering body 3 of said group 300 comprises at least three fins 301 arranged along a circumference.
  • the first filtering body 3 of said group comprises at least six fins 301 arranged along a circumference.
  • the fins 301 are first deformed by moving towards each other and then they tend to return to the initial position moving away from each other.
  • the fins 301 are therefore first compressed towards the centre of the circumference and then they move away from said centre.
  • Each of said flexible anchoring fins 301 comprises a first and a second wall 304, 305 facing along opposite directions.
  • the first wall 304 defines a guide for insertion of the first filtering body 3 into the tube 2, in particular in one of the holes 21.
  • the second wall 305 opposes the extraction of the first filtering body 3 from the tube 2.
  • At least the first filtering body 3 of said group comprises a perimeter collar 302 and a grid 303 placed inside the collar 302.
  • the grid 303 performs a filtering action in the second configuration. In fact, it allows any debris to be kept outside preventing entry into the tube 2 letting the water to be drained pass through. In the first configuration the grid 303 is buried inside the waterproofing means 31.
  • the collar 302 and the grid 303 are in a single monolithic body.
  • the collar 302 and possibly also the grid are 303 made of plastic material.
  • the fins 301 could be made of plastic material.
  • the fins 301 are made of metallic material.
  • the fins 301 are made of steel.
  • the collar 302 is made of metallic material (preferably steel).
  • the grid 303 is made of metallic material, in particular steel.
  • the fins 301 are made in a single body with the collar 302 and are positioned at an end of the collar 302 that is located inside the tube 2.
  • the collar 302 is connected by interference in one of said corresponding holes 21.
  • At least one of said holes 21 is defined by a lateral surface that narrows a passage section proceeding from the inside of the tube 2 towards the outside of the tube 2 (moving along the thickness of the tube 2).
  • the lateral surface is a truncated cone shape. In this way it offers greater resistance to the movement of the filtering bodies 300 inside the tube 2.
  • the tube 2 comprises a plurality of chunks connected together. For example they can be screwed to each other.
  • the collar 302 externally comprises one or more reliefs 306 which increase the anchorage to the tube 2 (in particular the anchorage to the holes 21).
  • said one or more reliefs extend along an arc, particularly circumferentially (see figure 6 ).
  • the system 1 comprises a seal 307 interposed between the collar 302 and the tube 2 (see figure 7 ).
  • the tube 2 provided with the bit 22 at one end is inserted into the ground to be dug generating a drilling action.
  • pressurised water is conveyed through the tube 2 to the bit 22 and then dispensed externally.
  • Such water flowing between the tube 2 and the drilled hole facilitates the removal of drilling debris. It also facilitates the dissolution of the water-soluble waterproofing means 31 so as to allow the passage through said group 300 of filtering bodies of the water to be drained.
  • the tube 2 provided with the bit 22 has a further conduit 23 inside it.
  • Such conduit 23 and possibly at least a part of the bit 22 can be removed once drilling has finished.
  • the water pumped to the bit 22 returns upstream passing into a gap interposed between the conduit 23 and the tube 2.
  • the present invention achieves important advantages.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Electrical Discharge Machining, Electrochemical Machining, And Combined Machining (AREA)
  • Water Treatment By Electricity Or Magnetism (AREA)
  • Cyclones (AREA)

Description

  • The present invention relates to a subsoil water drainage system. Drainage systems are used in various sectors such as the stabilisation of an underground area subject to landslides or to increase safety during drilling, for example drilling tunnels. Such prior art system are for instance known from EP1911886A1 and EP1908884A1 .
  • In fact, by removing the presence of water, the risk of subsiding or landslide movements can be reduced. In fact, the lubricating action offered by the water is taken away and the solid structure remains more stable.
  • To date one of the draining methods envisages the building of a small reinforced concrete tunnel in proximity to the area subject to landslides or the place in which a tunnel is to be built. The tunnel is sufficiently wide to allow the passage of the workers. From such tunnel, drilling can be performed through corresponding drainage tubes. A disposable drill bit is placed at the end of each drainage tube. The tube is placed in rotation and in this way it is made to advance in the subsoil transversally to the tunnel. Pressurised water is pumped to the bit in order to facilitate drilling, the removal of the drilled material and cooling. The water is conveyed to the bit inside the tube, then it exits by crossing a non-return valve. In this way it will tend to be arranged in the gap between the tube and the hole just drilled pushing the material removed by the bit towards the tunnel. As the drainage tube advances new chunks are added at the base to accompany the need to extend the tube. Along the wall of the tube there are filtering bodies that after installation must allow the passage of water from the outside to the inside of the tube so that it can then be drained. During installation such filtering bodies must be obstructed so as to prevent the water that is pumped into the tube and must reach the disposable bit exiting the tube before reaching its destination. On this point, the filtering bodies are obstructed by a water-soluble waterproofing cap. Therefore during installation such cap will prevent the exit of the water. But, being water-soluble, it will dissolve in contact with water and therefore once the installation is complete the filtering bodies will allow the passage of water from the outside to the inside.
  • The filtering bodies are placed by interference inside through holes made on the wall of the tube. The tube is made of metallic material and also the filtering bodies have an outer portion made of metallic material.
  • A drawback of this embodiment is that the pressurised water that is introduced into the tube during installation could overcome the interference between the filtering bodies and the tube, expelling the filtering bodies from the respective seats. This could therefore compromise both the correct installation of the drainage tube reducing the water flow rate to the disposable bit and the correct operation of the drainage pipe once installed. In fact, the absence of filtering bodies would cause the entry of debris. Or the filtering bodies, if removed from the correct position, could even obstruct the channel in an undesired way.
  • In this context, the technical task underlying the present invention is to propose a drainage system which obviates the drawbacks in the known art as described above.
  • In particular, an object of the present invention is to provide a drainage system able to improve the correct operation.
  • The defined technical task and the specified aims are substantially achieved by a drainage system comprising the technical characteristics set forth in one or more of the appended claims.
  • Further characteristics and advantages of the present invention will become more apparent from the indicative and thus non-limiting description of a preferred but non-exclusive embodiment of a drainage system, as illustrated in the attached drawings, in which:
    • figure 1 shows a schematic view of a drainage system according to the present invention;
    • figure 2 shows a schematic view of a drainage system as an alternative to that of figure 1;
    • figures 3 and 4 show two perspective views of a component of a drainage system according to the present invention;
    • figure 5 shows a front view of an alternative component to that of figures 3 and 4 and related to a drainage system according to the present invention;
    • figure 6 shows a side view of an alternative component to that of figures 3, 4 and 5 and related to a drainage system according to the present invention;
    • figure 7 shows a partially sectioned side view of an alternative component to that of figures 3, 4, 5 and 6 and related to a drainage system according to the present invention.
  • In the appended figures of the drawings, reference numeral 1 denotes a drainage system. The drainage system 1 comprises a water drainage tube 2 for draining a liquid, typically water. Appropriately, the tube 2 is made of metallic material. The tube 2 comprises a wall 20 provided with through holes 21. The wall 20 is a side wall of the tube 2 and the holes 21 cross the thickness of the wall 20.
  • Appropriately, the system 1 comprises a drill bit 22 placed at an end of the tube 2. The drill bit 22 is preferably at least partially disposable. In fact it could be a single-use bit. Once used for drilling it is left in situ (until the end of drilling). In the solution of figure 2 the bit 22 is completely disposable. In an alternative solution the bit 22 could be at least partially removed making it transit inside the tube 2 (solution exemplified in figure 1).
  • The drainage system 1 comprises a group 300 of filtering bodies fitted in the corresponding holes 21. The holes 21 are advantageously distributed along the length of the tube 2. They advantageously lie along the same straight line. The holes 21 are facing along different dimensions. For example they may be distributed according to a helical trend. For example a part of the holes 21 face upwards, or downwards, others are afforded on the lateral sides.
  • Appropriately, the drainage system 1 is self-drilling. This means that the tube 2 responsible for drainage and comprising the bit 22 performs the drilling itself.
  • The tube 2 advantageously extends along an inclined straight line. In particular the bit 22 is higher. This facilitates the outflow of water.
  • The filtering bodies of said group 300 comprise at least a first filtering body 3 fitted in one of said holes 21. The first filtering body 3 assumes a first configuration in which it comprises water-soluble waterproofing means 31 which prevents passage of water. The first filtering body 3 assumes a second configuration wherein the water-soluble waterproofing means 31 is absent, enabling the water to pass through the thickness of a wall 20 of the tube 2. In fact, in the second configuration the water-soluble means 31 has been dissolved. This is because of the contact with the water pumped through the tube 2 during drilling or however with the subsequent contact with the water present in the subsoil and that the tube 2 proposes to drain. Such water-soluble means 31 is/comprises for example a water-soluble glue (an example of the water-soluble means 31 could be the material known by the trade name of Hydrolene). It internally obstructs a passage section of the first body 3. One or more of the characteristics described with reference to the first filtering body 3 can be repeated for all the other filtering bodies of said group 300 of filtering bodies.
  • The first filtering body 3 of said group 300 comprises snap-fitting means 30 to the wall 20 of the tube 2. The snap-fitting means 30 comprises flexible anchoring fins 301 to an internal surface 201 of the tube 2. Such fins 301 define flexible hooks. The fins 301 are elastically deformable. The first filtering body 3 of said group 300 comprises at least three fins 301 arranged along a circumference.
  • Advantageously, the first filtering body 3 of said group comprises at least six fins 301 arranged along a circumference.
  • During the fitting to the tube 2 the fins 301 are first deformed by moving towards each other and then they tend to return to the initial position moving away from each other. The fins 301 are therefore first compressed towards the centre of the circumference and then they move away from said centre.
  • Each of said flexible anchoring fins 301 comprises a first and a second wall 304, 305 facing along opposite directions. The first wall 304 defines a guide for insertion of the first filtering body 3 into the tube 2, in particular in one of the holes 21. The second wall 305 opposes the extraction of the first filtering body 3 from the tube 2.
  • At least the first filtering body 3 of said group comprises a perimeter collar 302 and a grid 303 placed inside the collar 302. The grid 303 performs a filtering action in the second configuration. In fact, it allows any debris to be kept outside preventing entry into the tube 2 letting the water to be drained pass through. In the first configuration the grid 303 is buried inside the waterproofing means 31.
  • In the preferred solution, the collar 302 and the grid 303 are in a single monolithic body. Appropriately the collar 302 and possibly also the grid are 303 made of plastic material. The fins 301 could be made of plastic material.
  • In an alternative solution the fins 301 are made of metallic material. In particular the fins 301 are made of steel. Appropriately, the collar 302 is made of metallic material (preferably steel). Advantageously, the grid 303 is made of metallic material, in particular steel.
  • The fins 301 are made in a single body with the collar 302 and are positioned at an end of the collar 302 that is located inside the tube 2.
  • Appropriately the collar 302 is connected by interference in one of said corresponding holes 21.
  • At least one of said holes 21 (in particular each one of said holes 21) is defined by a lateral surface that narrows a passage section proceeding from the inside of the tube 2 towards the outside of the tube 2 (moving along the thickness of the tube 2). In particular the lateral surface is a truncated cone shape. In this way it offers greater resistance to the movement of the filtering bodies 300 inside the tube 2.
  • In the preferred solution, the tube 2 comprises a plurality of chunks connected together. For example they can be screwed to each other.
  • The collar 302 externally comprises one or more reliefs 306 which increase the anchorage to the tube 2 (in particular the anchorage to the holes 21). Advantageously said one or more reliefs extend along an arc, particularly circumferentially (see figure 6).
  • Appropriately the system 1 comprises a seal 307 interposed between the collar 302 and the tube 2 (see figure 7).
  • During use (see figure 2), the tube 2 provided with the bit 22 at one end is inserted into the ground to be dug generating a drilling action. During drilling pressurised water is conveyed through the tube 2 to the bit 22 and then dispensed externally. Such water flowing between the tube 2 and the drilled hole facilitates the removal of drilling debris. It also facilitates the dissolution of the water-soluble waterproofing means 31 so as to allow the passage through said group 300 of filtering bodies of the water to be drained.
  • In an alternative solution (see figure 1), to minimise the risk of any subsiding during drilling, the tube 2 provided with the bit 22 has a further conduit 23 inside it. Such conduit 23 and possibly at least a part of the bit 22 can be removed once drilling has finished. During drilling the water pumped to the bit 22 returns upstream passing into a gap interposed between the conduit 23 and the tube 2.
  • The present invention achieves important advantages.
  • First of all it allows the corresponding tubes 21 of said group 300 of filtering bodies to be kept in position better. This is also thanks to the presence of the fins 301 that allow an improved retaining action to be performed. Any fins 301 made of metallic material also provide a contribution in such direction. The narrowing of the wall shapes the holes 21 so that they have a larger external section and a smaller internal section than the thickness of the tube 2, which makes it possible to prevent the filtering bodies being able to exit from the holes 21 and falling into the tube 2.
  • The invention conceived is susceptible to modifications and variations, all falling within the scope of the invention as defined by the appended claims.

Claims (10)

  1. A drainage system comprising:
    - a water drainage tube (2) comprising a wall (20) having through holes (21);
    - a group (300) of filtering bodies fitted in the corresponding through holes (21); the filtering bodies of said group (300) comprising at least a first filtering body (3) fitted in one of said holes (21) and which assumes a first configuration in which it comprises water-soluble waterproofing means (31) which prevents passage of water and a second configuration wherein the water-soluble waterproofing means (31) is dissolved, enabling the water to pass through the thickness of a wall (20) of the tube;
    characterised in that the first filtering body (3) of said group comprises snap-fitting means (30) to the wall (20) of the tube (2), said snap-fitting means (30) comprising flexible anchoring fins (301) to an internal surface (201) of the tube (2).
  2. The system according to claim 1, characterised in that the first filtering body (3) of said group (300) comprises at least three fins (301) arranged along a circumference.
  3. The system according to claim 1 or 2, characterised in that said fins (301) are made of steel.
  4. The system according to any one of the preceding claims, characterised in that each of said holes (21) is defined by a lateral surface which narrows a perpendicular section, proceeding from outside the tube (2) to inside the tube (2).
  5. The system according to any one of the preceding claims, characterised in that each of said flexible anchoring fins (301) comprises a first and a second wall (304, 305) facing along opposite directions, the first wall (304) defining a guide for insertion of the first filtering body (3) into the tube (2), the second wall (305) opposing extraction of the filtering body (3) from the tube (2).
  6. The system according to any one of the preceding claims, characterised in that at least the first filtering body (3) of said group comprises a perimeter collar (302) and an internal grid (303) which performs a filtering action in the second configuration.
  7. The system according to claim 6, characterised in that the fins (301) are made in a single body with the collar (302) and are positioned at an end of the collar (302) positioned inside the tube (2).
  8. The system according to claim 6 or 7, characterised in that said collar (302) and said grid (303) are a single monolithic body.
  9. The system according to any one of claims 6 to 8, characterised in that said collar (302) externally comprises reliefs (306) which increase the anchorage to the tube (2).
  10. The system according to any one of claims 6 to 9, characterised in that it comprises a seal (307) interposed between said collar (302) and the tube (2).
EP19182486.1A 2018-07-30 2019-06-26 Water drainage system Active EP3613944B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
IT102018000007633A IT201800007633A1 (en) 2018-07-30 2018-07-30 WATER DRAINAGE SYSTEM

Publications (2)

Publication Number Publication Date
EP3613944A1 EP3613944A1 (en) 2020-02-26
EP3613944B1 true EP3613944B1 (en) 2020-11-25

Family

ID=64049531

Family Applications (1)

Application Number Title Priority Date Filing Date
EP19182486.1A Active EP3613944B1 (en) 2018-07-30 2019-06-26 Water drainage system

Country Status (3)

Country Link
EP (1) EP3613944B1 (en)
ES (1) ES2855729T3 (en)
IT (1) IT201800007633A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113236359B (en) * 2021-05-28 2022-06-28 中煤科工集团西安研究院有限公司 Separation layer water drainage method, separation layer water drainage roadway system and construction method
CN113530599B (en) * 2021-07-21 2022-08-23 重庆交通大学 Tunnel drain pipe crystallization treatment device based on thing networking
CN113445959B (en) * 2021-08-10 2022-02-01 中铁二院工程集团有限责任公司 Drilling drainage structure of karst or fault tunnel and construction method and construction structure thereof

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ITPC20060043A1 (en) * 2006-10-02 2008-04-03 Cesare Melegari METHOD FOR THE REALIZATION OF DRAINAGE WORKS, IN PARTICULAR FOR THE STABILIZATION, OF VERSATIVES AND / OR UNSTABLE OR LANDSCAPE
ITPC20060044A1 (en) * 2006-10-02 2008-04-03 Cesare Melegari IMPROVED DRAINAGE TUBE

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
None *

Also Published As

Publication number Publication date
ES2855729T3 (en) 2021-09-24
EP3613944A1 (en) 2020-02-26
IT201800007633A1 (en) 2020-01-30

Similar Documents

Publication Publication Date Title
EP3613944B1 (en) Water drainage system
KR101933614B1 (en) Tunnel ground pre-reinforcement method using the steel pipe and Tunnel ground pre-reinforcement type tunnel excavation method
EP3382143B1 (en) Tunnel construction method using pre-support and post-support and apparatus suitable for same
KR20170087786A (en) Reinforcement method of Tunnel
KR101750273B1 (en) Tunnel Reinforcement structure and Tunnel Reinforcement methods using the same
KR100331969B1 (en) An apparatus and method for multi-step grouting using FRP tube
CN112879050B (en) Waterproof structure of drainage type tunnel primary support system and construction method thereof
CN100356035C (en) Method and device for drilling a hole and for securing an anchorage in a bore hole
US7628565B2 (en) Drainage pipe
CN110607995B (en) Method for preventing casing from being broken in new underground construction hydrological drilling
KR102215505B1 (en) Construction method of internal pre-support tunnel for complete blocking water of all directions of the tunnel
JP2001115458A (en) Deep well construction method using earth retaining wall
JP4074313B2 (en) Structure of steel sheet pile for water flow and water retaining wall, and its construction method.
KR100588606B1 (en) Multi in-situ packer set for deep depth grouting hole and grouting method
CN110359430A (en) A kind of Gravity Dam Foundation discharge structure
KR100901804B1 (en) Tunnel leakage controlling method
KR101807366B1 (en) A Foundation Method Of Continuous and Cut Off wall By Overlap Casing
CN110747853B (en) Method for removing steel bar body in multi-rod anchor cable and special pressure-resistant rod
CN210459133U (en) Gravity dam foundation drainage structures
CN205077490U (en) Prevent suck -back and prevent slip casting device that deposits in deep full water sand bed
KR101067218B1 (en) The Construction Method of laying Pipe Underground for Ultra soft Ground
CN113266305B (en) Close-range drainage drilling orifice pipe device for accumulated water in coal mine goaf and consolidation method thereof
KR102576665B1 (en) Leakage prevention structure and leak prevention construction method of structure
CN215520966U (en) Improved orifice pipe device for drilling hole in coal mine goaf accumulated water drainage
KR100585430B1 (en) Pipe shove in underground construction

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

17P Request for examination filed

Effective date: 20200722

RAX Requested extension states of the european patent have changed

Extension state: BA

Payment date: 20200722

Extension state: ME

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

INTG Intention to grant announced

Effective date: 20200820

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602019001471

Country of ref document: DE

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 1338518

Country of ref document: AT

Kind code of ref document: T

Effective date: 20201215

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: BUGNION S.A., CH

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20201125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210225

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210226

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210325

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210325

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210225

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG9D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602019001471

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

26N No opposition filed

Effective date: 20210826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210626

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210626

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210325

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

P01 Opt-out of the competence of the unified patent court (upc) registered

Effective date: 20230605

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20190626

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20230626

Year of fee payment: 5

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: BE

Payment date: 20230626

Year of fee payment: 5

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: IT

Payment date: 20230627

Year of fee payment: 5

Ref country code: ES

Payment date: 20230721

Year of fee payment: 5

Ref country code: CH

Payment date: 20230702

Year of fee payment: 5

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20240627

Year of fee payment: 6

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20240627

Year of fee payment: 6

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: AT

Payment date: 20240701

Year of fee payment: 6