EP3361005A1 - Ditch installation - Google Patents
Ditch installation Download PDFInfo
- Publication number
- EP3361005A1 EP3361005A1 EP17156035.2A EP17156035A EP3361005A1 EP 3361005 A1 EP3361005 A1 EP 3361005A1 EP 17156035 A EP17156035 A EP 17156035A EP 3361005 A1 EP3361005 A1 EP 3361005A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- bachverbauung
- plane
- carrier
- verbauungsstrukturen
- contour
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000009434 installation Methods 0.000 title description 2
- 239000000463 material Substances 0.000 claims abstract description 10
- 238000004873 anchoring Methods 0.000 claims abstract description 9
- 239000000758 substrate Substances 0.000 claims abstract description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 13
- 238000009412 basement excavation Methods 0.000 claims description 7
- 238000000034 method Methods 0.000 claims description 6
- IJJWOSAXNHWBPR-HUBLWGQQSA-N 5-[(3as,4s,6ar)-2-oxo-1,3,3a,4,6,6a-hexahydrothieno[3,4-d]imidazol-4-yl]-n-(6-hydrazinyl-6-oxohexyl)pentanamide Chemical compound N1C(=O)N[C@@H]2[C@H](CCCCC(=O)NCCCCCC(=O)NN)SC[C@@H]21 IJJWOSAXNHWBPR-HUBLWGQQSA-N 0.000 claims description 2
- 230000000717 retained effect Effects 0.000 claims 1
- 238000010276 construction Methods 0.000 description 4
- 239000002184 metal Substances 0.000 description 4
- 239000002023 wood Substances 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 230000004888 barrier function Effects 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 229910000746 Structural steel Inorganic materials 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000011010 flushing procedure Methods 0.000 description 2
- 239000004746 geotextile Substances 0.000 description 2
- 230000010354 integration Effects 0.000 description 2
- 230000014759 maintenance of location Effects 0.000 description 2
- 239000003643 water by type Substances 0.000 description 2
- 241000282414 Homo sapiens Species 0.000 description 1
- 210000001015 abdomen Anatomy 0.000 description 1
- 230000003187 abdominal effect Effects 0.000 description 1
- 239000004566 building material Substances 0.000 description 1
- 239000000969 carrier Substances 0.000 description 1
- 150000001875 compounds Chemical class 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000007493 shaping process Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 230000000087 stabilizing effect Effects 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/02—Stream regulation, e.g. breaking up subaqueous rock, cleaning the beds of waterways, directing the water flow
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B5/00—Artificial water canals, e.g. irrigation canals
- E02B5/08—Details, e.g. gates, screens
- E02B5/085—Arresting devices for waterborne materials, e.g. gratings
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
- E02B7/16—Fixed weirs; Superstructures or flash-boards therefor
Definitions
- the present invention relates to a Bach enclosure for retaining a material of a creek bed and a method for establishing a creek enclosure.
- Prior art creep barriers serve to retain material from a creek bed. In this way, steps can be formed. Through these steps, there is a slowing down of the flow velocity of the stream, which is particularly used in streams in the steep, and therefore often difficult to access, terrain. This slowing down of the flow rate can reduce the flushing away of the material of the streambed (for example, bedding).
- Object of the present invention is therefore to provide a Bachverbauung and a method for building a Bachverbauung that allow a reduction in the risk potential in the construction of the obstruction.
- this object is solved by the features of claim 13. This is done by material from a stream bed is removed to create a Aushubstelle, a Bachverbauung invention is placed in the excavation and the excavation is at least partially refilled.
- a Bachverbauung with a Verbauungs founded which includes a substantially arranged in a plane carrier and a sheet retainer, in particular a grid, and an anchor for anchoring in a subsoil as Bachverbauung, wherein the material through the grid of the creek bed is restrained.
- the flat restraint device carried by the carrier can be designed in various ways, in particular as a grid. Examples would be wire mesh mats, a rope net, an expanded metal, a perforated plate, a wire net and the like. But even a full-surface plate, various geotextiles and the like can be used depending on the situation.
- Belly abutments according to the invention can be prefabricated outside of the creek bed, for example simply as a steel structure (ie, for example, from commercially available steel profiles and metal sheets). This can be placed in the creek bed when erecting the creek, for example by crane. The lengthy construction of the Bachverbauung of wood, concrete, stones or other building material is thereby eliminated. In most cases, the Bachverbauung must be backfilled after placing in the creek bed and then ready for use. By significantly reducing the residence time of the workers in the creek bed, security is increased.
- a diversion of the brook when building the Bachverbauung can be done for example via pipes, hoses and the like, if necessary.
- the carrier may also be referred to as a frame.
- the Bachverbauung invention can always be used when at a running water to fast transport of the material of the streambed threatens by Mitschwemmen and co-pushing.
- the size of the watercourse is not of primary importance.
- the transition from flowing waters, referred to as streams, to flowing waters, called rivers, is fluid.
- a pull rod which is connected on the one hand to the carrier and on the other hand to the armature and which is arranged at an angle to the plane, wherein the anchor is preferably secured to a side facing away from the plane of the pull rod.
- the anchor can be designed as a dead man's anchor, which is sunk underground. This usually consists of a bulky object, such as a metal plate. Rope anchors or anchor rods and the like can also be used.
- the carrier can be particularly easily formed from one another attached, arranged substantially in the plane, struts.
- the struts may be attached to a central connector, where appropriate, the tie rod or the anchor may in turn be attached to the central connector. This design is characterized by a good relationship between stability and effort in the design.
- the contour may include a - preferably substantially horizontal - water bottom and a - preferably inclined in comparison to the water bottom - shore.
- the contour may include substantially horizontal shoulders that adjoin the portions of the contour designated as shore. These can be sunk underground and thus stabilize the stream bed, especially in the embankment area.
- the contour can be particularly easily performed by a trapezoidal recess in the upper part of the Bachverbauung.
- Such a contour can be particularly easily formed by two in a vertical arrangement of the plane overhead - preferably kinked - struts, preferably together with a central connector of the carrier.
- the central connecting piece of the carrier form the horizontal water bottom.
- the struts can lead away at an angle, so that the shore is formed.
- the overhead struts may have kinks, so that the from the connector pioneering parts of the bent struts forming the (horizontal) shoulders.
- the construction can be further simplified in that the four struts are symmetrical with the plane arranged perpendicular to an axis of symmetry, the axis of symmetry preferably being substantially vertical.
- the tie rod may be located substantially approximately perpendicular to the plane (ie, the angle would then be substantially approximately a right angle).
- the brook construction can have several structures - the structure of the structure is then constructed in a more or less modular way.
- the addressed contour may be formed by carriers and grids of several Verbauungs Modellen arranged side by side and / or one above the other.
- Each structure can have its own anchor position, but this is not absolutely necessary.
- a central concavity structure (with or without tie rod) is provided with an anchor, which is a simple embodiment.
- the building structures are connected in this case.
- rails may be provided, which are located on lower underlying Verbauungs Modellen be set up and thus form a basis for further Verbauungs Modellen that are placed on the rails.
- the adjacent Verbauungs Modellen for example by screws, are connected to each other.
- the Verbauungs taughten in the Aushubstelle of the streambed may preferably be provided that the Verbauungs Modellen the Abdominal Verification are placed as a whole in the excavation. In this case, no processing steps on the Bachverbauung or the Verbauungs Cook in the creek bed longer necessary, which minimizes the potential danger when building the Bachverbauung.
- Fig. 1 shows a schematic front view of a Bachverbauung invention 1 with a Verbauungs Quilt 3, consisting of the support 4 and designed as a grid retention device.
- the carrier 4 consists of four struts 8, which at a central connector 13 are attached. The connections are welded joints in this embodiment.
- the carrier 4 is formed symmetrically with respect to a vertical axis of symmetry X.
- the carrier 4 carries the grid 5, which in this case is a tailored structural steel mat.
- the grid 5 is shaped and fastened such that an upper contour 9 of the obstruction structure 3 results, which contour 9 substantially corresponds to the bottom of a brook bed and thus forms the desired overflow.
- a horizontal water base 11 is formed by the central connecting piece 13. Inclined to form the grid 5 together with the upper struts 8 in the picture shore 12. By a kink in the upper struts 8 and corresponding shaping of the grid 5 also horizontal shoulders 16 are present, which can be sunk in the streambed or a nearby embankment (lateral integration).
- the drawing plane of the Fig. 1 forms that plane in which the carrier 4 is arranged.
- the shoulders 16 are understood as parts of the contour 9 or as parts of the contour 9 together with in the drawing plane in this area arranged below grid 5, which can be sunk in the embankment (lateral integration).
- a Bachverbauung invention 1 with Verbauungs Quilt 3 is shown.
- the pull rod 6 at the end facing away from the carrier 4 z.
- B. a deadman armature 7 is arranged.
- Fig. 2 can be seen, there is a substantially vertical arrangement of the pull rod 6 to the carrier 4. Slight changes in Angles between the pull rod 6 and the carrier 4 can be made.
- an extended drawbar 6 can be used.
- Fig. 2 the surface of the subsoil or the creek bed is indicated by reference numeral 15, whereby the situation of Bachverbauung 1 in use is clarified.
- FIG. 3 is one of Fig. 1 similar front view of the Bachverbauung 1, the surface 15 is shown by dashed lines. The dotted line corresponds to the surface 15 in the plane of the carrier 4.
- Fig. 3 also schematically shows a slightly different embodiment from that Fig. 1 ,
- the shore sections 12 of the contour 9 are made steeper.
- the Bachverbautician 1 described here are installed transversely to the flow direction of the water in the channel and are therefore also called cross-locks or short locks.
- the embankment is stabilized.
- the Bachverbausch 1 invention can be used as an alternative to the usual Bachverbausch of wood, concrete, stones, etc.
- the water of the stream flow through only in the middle and forms the so-called drainage section / overflow section.
- a replaceable overflow plate 18 can be mounted, which is easily replaced when worn.
- the selected geometry of the Bachverbauung 1 the barrier shoulders or wings can be well integrated into the embankment, which, as already mentioned, stabilizes the embankment.
- an actual support surface (retaining device 5) for the backfilling of the Bachverbauung 1 is for example a structural steel mat. But it can also be a rope net, an expanded metal, a perforated plate, a wire mesh, etc. used as a support surface.
- a geotextile can be additionally attached to z. B. Materialausschwemmungen from the Bachverbauung 1 to prevent.
- the Bachverbauung 1 is anchored on the mountain side.
- anchoring for example, a deadman anchor can be used.
- FIG. 1 The Bachverbauung 1 or the Verbauungs Modellen 3 are ready pre-assembled on Baustellenlagerplatz.
- the fully assembled Verbauungs Modellen 3 can be quickly and safely placed and backfilled at the installation with excavator, mobile crane, helicopter or the like.
- Fig. 4 shows a schematic front view of an embodiment in which a plurality of Verbauungs Modellen 3 are modularly assembled to a Bachverbauung 1, as in a modular system.
- the Verbauungs füren 3 can be placed in each case on rails 17, which are arranged at the bottom of the Bachverbauung 1 or on the first row of the Verbauungs Modellen 3.
- the rails 17 allow a clean, accurate displacement of the individual Verbauungs Modell. 3
- the contour 9 is created by individual contours of different Verbauungs Modellen 3. In the area of the water bottom 11 and the bank 12, an overflow plate 18 is arranged. This can be easily replaced when worn.
- overflow plates 18 can - as already mentioned - of course also be used in embodiments that do not have multiple Verbauungs Modellen 3.
- Fig. 4 is also nice to recognize that corresponding Verbauungs füren 3 need not be made symmetrical or with a certain aspect ratio.
- the shape of the carrier 3 can be easily adapted to external conditions and desired contour 9.
- FIG Fig. 4 Marked points are possible anchor points 19, ie anchors 7 (optionally with tie rods 6) can be fastened at these points.
- Preferred may be an embodiment in which only a central Verbauungstechnik is connected to an anchor 7 with or without drawbar 6.
- Fig. 5 is a cross-section of one according to Fig. 4 to be used rail 17 is shown.
- the rail 17 can be easily done by, for example, welding two U-profiles (each with technological U-profiles).
- one of the U-profiles is placed on Verbauungs Modell 3.
- the other U-profile then serves as the basis for a building structure 3 to be arranged above it.
- Verbauungs Designen 3 are installed side by side and / or one above the other. They all consist of a frame and a support surface, as described above. The individual elements can be arranged side by side and on top of each other, anchored and backfilled. The geometry of the top row forms outflow section / overflow section. Again, a replaceable overflow plate 18 can be mounted.
- the anchoring of the individual Verbauungs Designen 3 is carried out as described above.
- a (guide) rail 17 can be placed under each row. The Verbauungs Modell 3 are then simply inserted into this rail 17. If necessary, the guide rail can be anchored as desired.
- the individual Verbauungs Modell 3 can be lifted and anchored after the series. Once all Verbauungs Modellen 3 are anchored, the Bachverbauung 1 can be backfilled.
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Bachverbauung zum Zurückhalten eines Materials (2) eines Bachbetts, wobei - eine Verbauungsstruktur (3) mit einem im Wesentlichen in einer Ebene angeordneten Träger (4) und einer vom Träger (4) getragenen flächigen Rückhaltevorrichtung (5), insbesondere einem Gitter (5), und - einen Anker (7) zur Verankerung des Trägers (4) in einem Untergrund.Bachverbauung for retaining a material (2) of a stream bed, wherein - A Verbauungsstruktur (3) with a substantially arranged in a plane carrier (4) and a carrier (4) carried by the flat retaining device (5), in particular a grid (5), and - An anchor (7) for anchoring the carrier (4) in a substrate.
Description
Die vorliegende Erfindung betrifft eine Bachverbauung zum Zurückhalten eines Materials eines Bachbetts sowie ein Verfahren zum Errichten einer Bachverbauung.The present invention relates to a Bach enclosure for retaining a material of a creek bed and a method for establishing a creek enclosure.
Bachverbauungen des Standes der Technik dienen dazu, Material eines Bachbetts zurückzuhalten. Auf diese Weisen können Stufen geformt werden. Durch diese Stufen ergibt sich eine Verlangsamung der Fließgeschwindigkeit des Baches, was insbesondere bei Bächen im steilen, und daher oft schwer zugänglichen, Gelände eingesetzt wird. Durch diese Verlangsamung der Fließgeschwindigkeit kann das Wegspülen des Materials des Bachbetts (beispielsweise Geschiebe) verringert werden.Prior art creep barriers serve to retain material from a creek bed. In this way, steps can be formed. Through these steps, there is a slowing down of the flow velocity of the stream, which is particularly used in streams in the steep, and therefore often difficult to access, terrain. This slowing down of the flow rate can reduce the flushing away of the material of the streambed (for example, bedding).
Gattungsgemäße Bachverbauungen werden meist aus Holz, Beton oder Steinen und dergleichen errichtet, nachdem der Bach bei Bedarf auf irgendeine Art umgeleitet wurde. Dies bedeutet aber, dass Arbeiter für längere Zeit im Bachbett arbeiten müssen, um die Bachverbauungen aus Holz, Beton oder Steinen im Bachbett zu errichten. Auch bei umgeleitetem Bach ist dies ein erhebliches Sicherheitsrisiko, das umso größer wird, je länger die Aufenthaltszeit der Arbeiter im Bachbett wird.Generic brook enclosures are usually made of wood, concrete or stones and the like, after the stream was redirected if necessary in any way. However, this means that workers have to work for a long time in the creek bed to build the creek structures of wood, concrete or stones in the streambed. Even with bypassed stream this is a significant security risk, which is the greater, the longer the residence time of the workers in the creek bed.
Aufgabe der vorliegenden Erfindung ist es daher, eine Bachverbauung und ein Verfahren zum Errichten einer Bachverbauung bereitzustellen, die eine Verringerung des Gefahrenpotentials beim Errichten der Verbauung erlauben.Object of the present invention is therefore to provide a Bachverbauung and a method for building a Bachverbauung that allow a reduction in the risk potential in the construction of the obstruction.
In Bezug auf die Bachverbauung wird dies durch die Merkmale des Anspruchs 1 gelöst. Dies geschieht durch eine Verbauungsstruktur mit einem im Wesentlichen in einer Ebene angeordneten Träger und einer vom Träger getragenen flächigen Rückhaltevorrichtung sowie einem Anker zur Verankerung des Trägers in einem Untergrund.With respect to the Bachverbauung this is solved by the features of
In Bezug auf das Verfahren wird diese Aufgabe durch die Merkmale des Anspruchs 13 gelöst. Dies geschieht, indem Material eines Bachbetts zur Schaffung einer Aushubstelle entfernt wird, eine erfindungsgemäße Bachverbauung in der Aushubstelle platziert wird und die Aushubstelle zumindest teilweise wieder gefüllt wird.With regard to the method, this object is solved by the features of
Schutz begehrt wird ebenfalls für die Verwendung einer Bachverbauung mit einer Verbauungsstruktur, welche mit einem im Wesentlichen in einer Ebene angeordneten Träger und eine flächige Rückhaltevorrichtung, insbesondere ein Gitter beinhaltet, sowie einem Anker zur Verankerung in einem Untergrund als Bachverbauung, wobei durch das Gitter das Material des Bachbetts zurückgehalten wird.Protection is also sought for the use of a Bachverbauung with a Verbauungsstruktur which includes a substantially arranged in a plane carrier and a sheet retainer, in particular a grid, and an anchor for anchoring in a subsoil as Bachverbauung, wherein the material through the grid of the creek bed is restrained.
Die vom Träger getragene flächige Rückhaltevorrichtung kann auf verschiedene Weisen, insbesondere als Gitter, ausgebildet sein. Beispiele wären Baustahlmatten, ein Seilnetz, ein Streckmetall, ein Lochblech, ein Drahtnetz und dergleichen. Aber auch eine ganzflächige Platte, verschiedene Geotextilien und dergleichen können je nach Situation eingesetzt werden.The flat restraint device carried by the carrier can be designed in various ways, in particular as a grid. Examples would be wire mesh mats, a rope net, an expanded metal, a perforated plate, a wire net and the like. But even a full-surface plate, various geotextiles and the like can be used depending on the situation.
Erfindungsgemäße Bauchverbauungen können außerhalb des Bachbetts vorgefertigt werden, beispielsweise einfach als Stahlkonstruktion (also bspw. aus handelsüblichen Stahlprofilen und Blechen). Diese kann beim Errichten der Bachverbauung, beispielsweise per Kran, im Bachbett platziert werden. Der langwierige Bau der Bachverbauung aus Holz, Beton, Steinen oder sonstigem Baumaterial entfällt dadurch. In den meisten Fällen muss die Bachverbauung nach dem Platzieren in dem Bachbett nur noch hinterfüllt werden und ist dann sofort einsatzbereit. Durch die erhebliche Verkürzung der Aufenthaltszeit der Arbeiter im Bachbett wird die Sicherheit erhöht.Belly abutments according to the invention can be prefabricated outside of the creek bed, for example simply as a steel structure (ie, for example, from commercially available steel profiles and metal sheets). This can be placed in the creek bed when erecting the creek, for example by crane. The lengthy construction of the Bachverbauung of wood, concrete, stones or other building material is thereby eliminated. In most cases, the Bachverbauung must be backfilled after placing in the creek bed and then ready for use. By significantly reducing the residence time of the workers in the creek bed, security is increased.
Eine Umleitung des Baches beim Errichten der Bachverbauung kann beispielsweise über Rohre, Schläuche und dergleichen geschehen, falls dies notwendig ist.A diversion of the brook when building the Bachverbauung can be done for example via pipes, hoses and the like, if necessary.
Der Träger kann auch als Rahmen bezeichnet werden.The carrier may also be referred to as a frame.
Strukturen mit einem Träger einer Rückhaltevorrichtung, einer Zugstange und einem Anker wurden im Stand der Technik lediglich als Verbauungsschilde zur Hangsicherung (also um das Abrutschen von Erdreich, Gestein oder Schnee zu verhindern) verwendet. Siehe hierzu beispielsweise die
Zur Erzeugung von Stufen in einem Bachbett sind solche Verbauungsschilde wegen der rechteckigen Geometrie der Rückhaltevorrichtung nicht geeignet, weshalb der Einsatz als Bachverbauung nicht naheliegt.For the creation of steps in a stream bed such Verschauungsschilde are not suitable because of the rectangular geometry of the restraint, which is why the use as a Bachverbauung not obvious.
Die erfindungsgemäße Bachverbauung kann immer dann eingesetzt werden, wenn bei einem Fließgewässer zu schneller Transport des Materials des Bachbetts durch Mitschwemmen und Mitschieben droht. Die Größe des Fließgewässers ist dabei nicht von primärer Bedeutung. Insbesondere ist der Übergang von Fließgewässern, die als Bäche bezeichnet werden, zu Fließgewässern, die als Flüsse bezeichnet werden, fließend.The Bachverbauung invention can always be used when at a running water to fast transport of the material of the streambed threatens by Mitschwemmen and co-pushing. The size of the watercourse is not of primary importance. In particular, the transition from flowing waters, referred to as streams, to flowing waters, called rivers, is fluid.
Vorteilhafte Weiterbildungen der Erfindung sind in den abhängigen Ansprüchen definiert.Advantageous developments of the invention are defined in the dependent claims.
Es kann eine Zugstange vorgesehen sein, welche einerseits mit dem Träger und andererseits mit dem Anker verbunden ist und welche in einem Winkel zur Ebene angeordnet ist, wobei der Anker vorzugsweise an einer von der Ebene wegweisenden Seite der Zugstange befestigt ist. Die Verankerung im Untergrund kann so auf einfache Weise geschehen.It may be provided a pull rod which is connected on the one hand to the carrier and on the other hand to the armature and which is arranged at an angle to the plane, wherein the anchor is preferably secured to a side facing away from the plane of the pull rod. The anchoring in the underground can be done so easily.
Der Anker kann als Totmann-Anker ausgebildet sein, der im Untergrund versenkt wird. Dieser besteht meist aus einem sperrigen Gegenstand, wie beispielsweise einer Metallplatte. Seilanker oder Ankerstäbe und dergleichen können aber auch zum Einsatz kommen.The anchor can be designed as a dead man's anchor, which is sunk underground. This usually consists of a bulky object, such as a metal plate. Rope anchors or anchor rods and the like can also be used.
Der Träger kann besonders einfach aus aneinander befestigten, im Wesentlichen in der Ebene angeordneten, Streben gebildet sein. In einer besonders bevorzugten Ausführung können die Streben an einem zentralen Verbindungsstück befestigt sein, wobei gegebenenfalls die Zugstange oder der Anker wiederum am zentralen Verbindungsstück befestigt sein kann. Diese Ausführung zeichnet sich durch ein gutes Verhältnis aus Stabilität und Aufwand bei der Konstruktion aus.The carrier can be particularly easily formed from one another attached, arranged substantially in the plane, struts. In a particularly preferred embodiment, the struts may be attached to a central connector, where appropriate, the tie rod or the anchor may in turn be attached to the central connector. This design is characterized by a good relationship between stability and effort in the design.
Bevorzugt kann es vorgesehen sein, dass bei senkrechter Anordnung der Ebene durch den Träger und die flächige Rückhaltevorrichtung eine Kontur vorliegt, die einem Grund eines Bachbetts gleicht oder entspricht. Durch die Schaffung einer Kontur, welche im Wesentlichen dem Grund eines natürlichen Bachbettes entspricht, kann besonders einfach die Strömung des Baches wie gewünscht beeinflusst werden. Die Kontur kann dabei eine - vorzugsweise im Wesentlichen waagrechte - Wassersohle und ein - vorzugsweise im Vergleich zur Wassersohle geneigtes - Ufer beinhalten. Außerdem kann die Kontur im Wesentlichen waagrechte Schultern beinhalten, die sich an die als Ufer bezeichneten Teile der Kontur anschließen. Diese können im Untergrund versenkt werden und dadurch eine Stabilisierung des Bachbettes, insbesondere im Böschungsbereich, erreichen.It may preferably be provided that, when the plane is arranged vertically through the carrier and the planar restraint device, there is a contour which equals or corresponds to a bottom of a creek bed. By creating a contour that essentially corresponds to the bottom of a natural creek bed, the flow of the creek can be particularly easily influenced as desired. The contour may include a - preferably substantially horizontal - water bottom and a - preferably inclined in comparison to the water bottom - shore. In addition, the contour may include substantially horizontal shoulders that adjoin the portions of the contour designated as shore. These can be sunk underground and thus stabilize the stream bed, especially in the embankment area.
Die Kontur kann besonders einfach durch eine trapezförmige Aussparung im oberen Bereich der Bachverbauung ausgeführt werden.The contour can be particularly easily performed by a trapezoidal recess in the upper part of the Bachverbauung.
Eine solche Kontur kann besonders einfach durch zwei in senkrechter Anordnung der Ebene obenliegende - vorzugsweise geknickte - Streben gebildet sein, vorzugsweise zusammen mit einem zentralen Verbindungsstück des Trägers. Dabei kann das zentrale Verbindungsstück des Trägers die waagrechte Wassersohle bilden. Daran anschließend können die Streben in einem Winkel wegführen, sodass das Ufer gebildet wird. Schließlich können die obenliegenden Streben Knicke aufweisen, so dass die vom Verbindungsstück wegweisenden Teile der geknickten Streben die (waagrechten) Schultern bilden.Such a contour can be particularly easily formed by two in a vertical arrangement of the plane overhead - preferably kinked - struts, preferably together with a central connector of the carrier. In this case, the central connecting piece of the carrier form the horizontal water bottom. Following this, the struts can lead away at an angle, so that the shore is formed. Finally, the overhead struts may have kinks, so that the from the connector pioneering parts of the bent struts forming the (horizontal) shoulders.
In einer besonders einfachen Ausführungsform können vier im Wesentlichen in einer Ebene angeordnete Streben vorliegen, die vorzugsweise mittels eines zentralen Verbindungsstücks miteinander verbunden sind.In a particularly simple embodiment, there may be four struts arranged essentially in one plane, which are preferably connected to one another by means of a central connecting piece.
Die Konstruktion kann weiter dadurch vereinfacht werden, dass dass die vier Streben bei senkrechter Anordnung der Ebene bezüglich einer Symmetrieachse symmetrisch sind, wobei die Symmetrieachse vorzugsweise im Wesentlichen vertikal verläuft.The construction can be further simplified in that the four struts are symmetrical with the plane arranged perpendicular to an axis of symmetry, the axis of symmetry preferably being substantially vertical.
Für optimale Stabilität und Zurückhaltefähigkeit kann die Zugstange im Wesentlichen annähernd senkrecht zur Ebene angeordnet sein (der Winkel würde dann also im Wesentlichen annähernd ein rechter Winkel sein).For optimum stability and retention, the tie rod may be located substantially approximately perpendicular to the plane (ie, the angle would then be substantially approximately a right angle).
Bei größeren Fließgewässern kann die Bachverbauung über mehrere Verbauungsstrukturen verfügen - die Verbauungsstruktur wird dann quasi modular aufgebaut.In larger streams, the brook construction can have several structures - the structure of the structure is then constructed in a more or less modular way.
Dabei kann die angesprochene Kontur durch Träger und Gitter mehrerer Verbauungsstrukturen gebildet sein, die nebeneinander und/oder übereinander angeordnet sind.In this case, the addressed contour may be formed by carriers and grids of several Verbauungsstrukturen arranged side by side and / or one above the other.
Jede Verbauungsstruktur kann dabei über ihre eigene Ankerposition verfügen, was aber nicht absolut notwendig ist. In vielen Fällen wird eine zentrale Verbauungsstruktur (mit oder ohne Zugstange) mit einem Anker versehen, was eine einfache Ausführungsform darstellt.Each structure can have its own anchor position, but this is not absolutely necessary. In many cases, a central concavity structure (with or without tie rod) is provided with an anchor, which is a simple embodiment.
Es kann außerdem vorgesehen sein, dass die Verbauungsstrukturen in diesem Fall miteinander verbunden werden. Insbesondere können Schienen vorgesehen sein, die auf weiter unten liegende Verbauungsstrukturen aufgesetzt werden und auf diese Weise eine Basis für weitere Verbauungsstrukturen bilden, die auf die Schienen aufgesetzt werden. Natürlich können auch die nebeneinander liegenden Verbauungsstrukturen, beispielsweise durch Verschraubungen, miteinander verbunden werden.It can also be provided that the building structures are connected in this case. In particular, rails may be provided, which are located on lower underlying Verbauungsstrukturen be set up and thus form a basis for further Verbauungsstrukturen that are placed on the rails. Of course, the adjacent Verbauungsstrukturen, for example by screws, are connected to each other.
Beim Platzieren der Bachverbauung oder, im Falle mehrerer Verbauungsstrukturen, der Verbauungsstrukturen in der Aushubstelle des Bachbetts kann bevorzugt vorgesehen sein, dass die Verbauungsstrukturen die Bauchverbauung als Ganzes in der Aushubstelle platziert werden. In diesem Fall sind keine Bearbeitungsschritte an der Bachverbauung oder der Verbauungsstruktur im Bachbett mehr nötig, was das Gefahrenpotenzial beim Errichten der Bachverbauung minimiert.When placing the Bachverbauung or, in the case of several Verbauungsstrukturen, the Verbauungsstrukturen in the Aushubstelle of the streambed may preferably be provided that the Verbauungsstrukturen the Abdominal Verification are placed as a whole in the excavation. In this case, no processing steps on the Bachverbauung or the Verbauungsstruktur in the creek bed longer necessary, which minimizes the potential danger when building the Bachverbauung.
Weitere Vorteile und Einzelheiten der Erfindung ergeben sich aus den Figuren und der dazugehörigen Figurenbeschreibung. Dabei zeigen:
- Fig. 1
- eine schematische Vorderansicht einer erfindungsgemäßen Bachverbauung,
- Fig. 2
- eine schematische Seitenansicht einer erfindungsgemäßen Bachverbauung, die in einem Bachbett eingesetzt ist (teilweise geschnitten),
- Fig. 3
- eine schematische Vorderansicht einer erfindungsgemäßen Bachverbauung, die in einem Bachbett eingesetzt ist,
- Fig. 4
- eine schematische Vorderansicht einer aus einer Vielzahl von Verbauungsstrukturen bestehende Bachverbauung, und
- Fig. 5
- eine Schiene zum Einsatz bei einer Bachverbauung mit mehreren Verbauungsstrukturen.
- Fig. 1
- a schematic front view of a Bachverbauung invention,
- Fig. 2
- a schematic side view of a Bachverbauung invention, which is used in a streambed (partially cut),
- Fig. 3
- a schematic front view of a Bachverbauung invention, which is used in a stream bed,
- Fig. 4
- a schematic front view of existing from a variety of Verbauungsstrukturen Bachverbauung, and
- Fig. 5
- a rail for use in a Bachverbauung with multiple Verbauungsstrukturen.
Der Träger 4 trägt das Gitter 5, welches in diesem Fall eine zugeschnittene Baustahlmatte ist. Das Gitter 5 ist in diesem Fall so geformt und befestigt, dass sich eine obere Kontur 9 der Verbauungsstruktur 3 ergibt, welche Kontur 9 im Wesentlichen dem Grund eines Bachbettes entspricht und so den gewünschten Überlauf bildet.The carrier 4 carries the
Vom Zentrum ausgehend ist durch das zentrale Verbindungsstück 13 eine waagrechte Wassersohle 11 gebildet. Geneigt dazu bildet das Gitter 5 zusammen mit den im Bild oberen Streben 8 Ufer 12. Durch einen Knick in den oberen Streben 8 und entsprechender Formung des Gitters 5 sind außerdem waagrechte Schultern 16 vorhanden, die im Bachbett oder einer naheliegenden Böschung versenkt werden können (seitliche Einbindung).Starting from the center, a horizontal water base 11 is formed by the central connecting
Die Zeichenebene der
Je nach Sinnzusammenhang werden die Schultern 16 als Teile der Kontur 9 oder als Teile der Kontur 9 zusammen mit in der Zeichenebene in diesem Bereich darunter angeordnetem Gitter 5 verstanden, welches in der Uferböschung versenkt werden kann (seitliche Einbindung).Depending on the context of meaning, the
In der Seitenansicht aus
Zur Erhöhung der Stabilität sind vom ankerseitigen Ende der Zugstange 6 außerdem Stabilisierungsseile 14 - in diesem Fall Stahlseile - zu den Enden der Streben 8 vorgesehen. Durch diese ergibt sich eine insgesamt pyramidenartige Struktur der Bachverbauung 1.To increase the stability of the anchor end of the tie rod 6 also stabilizing ropes 14 - provided in this case steel cables - to the ends of the
Um eine tiefere Versenkung des Ankers 7 im Untergrund zu erreichen, kann auch eine verlängerte Zugstange 6 eingesetzt werden.In order to achieve a deeper sinking of the
In
Hierzu ist auch in
Die hier beschriebenen Bachverbauungen 1 werden quer zur Fließrichtung des Wassers im Gerinne eingebaut und werden deshalb auch Quersperren oder kurz Sperren genannt.The
Mehrere hintereinander eingebaute Bachverbauungen 1 bilden eine Sperrentreppe.Several successive built
Mit Sperrentreppen wird die Fließgeschwindigkeit des Wassers in einem Wildbach verlangsamt, dadurch kann unter anderem das Wegspülen von Geschiebe verringert werden.With staircase steps, the flow velocity of the water in a torrent is slowed, thereby, among other things, the flushing away of bed load can be reduced.
Durch die Einbindung der Schultern 16 (auch genannt Sperrenschultern oder - flügel) in die Seitenhänge wird die Uferböschung stabilisiert.By integrating the shoulders 16 (also called barrier shoulders or wings) into the side slopes, the embankment is stabilized.
Die erfindungsgemäßen Bachverbauungen 1 können als Alternative zu den üblichen Bachverbauungen aus Holz, Beton, Steinen usw. verwendet werden.The
Allgemein kann durch die trapezförmige Aussparung im oberen Bereich der Bachverbauung 1 das Wasser des Baches nur in der Mitte durchfließen und bildet die sogenannte Abflusssektion / Überlaufsektion. Um den Überlauf vor Verschleiß durch das ständig fließende Wasser zu schützen, kann eine austauschbare Überlaufplatte 18 montiert werden, die bei Abnützung einfach ausgetauscht wird. Durch die gewählte Geometrie der Bachverbauung 1 können die Sperrenschultern oder -flügel gut in die Uferböschung eingebunden werden, das, wie bereits erwähnt, die Uferböschung stabilisiert.Generally, through the trapezoidal recess in the upper part of the
Als eigentliche Stützfläche (Rückhaltevorrichtung 5) für die Hinterfüllung der Bachverbauung 1 dient beispielsweise eine Baustahlmatte. Es kann aber auch ein Seilnetz, ein Streckmetall, ein Lochblech, ein Drahtnetz usw. als Stützfläche verwendet werden.As an actual support surface (retaining device 5) for the backfilling of the
Ein Geotextil kann zusätzlich angebracht werden, um z. B. Materialausschwemmungen aus der Bachverbauung 1 zu verhindern.A geotextile can be additionally attached to z. B. Materialausschwemmungen from the
Die Bachverbauung 1 wird bergseitig verankert. Als Verankerung kann beispielsweise ein Totmann-Anker verwendet werden. Als Alternative können natürlich auch alle anderen gängigen Verankerungsverfahren angewandt werden.The
Vorteile der erfindungsgemäßen Bachverbauungen 1: Die Bachverbauung 1 oder die Verbauungsstrukturen 3 werden am Baustellenlagerplatz fertig vormontiert. So können die fertig montierten Verbauungsstrukturen 3 am Montageort mit Bagger, Autokran, Helikopter oder dergleichen schnell und sicher platziert und hinterfüllt werden.Advantages of the invention Bachverbauungen 1: The
Dadurch ist der Arbeitsaufwand auf der Baustelle wesentlich geringer und somit weniger gefährlich im Vergleich zu herkömmlichen Bachverbauungen 1.As a result, the workload on the site is much lower and thus less dangerous compared to conventional Bachverbauungen. 1
Es ist in diesem Ausführungsbeispiel auch eine Verbindung der nebeneinander angeordneten Verbauungsstrukturen 3 durch Schraubverbindungen vorgesehen.It is also provided in this embodiment, a compound of juxtaposed
Die Kontur 9 wird durch Einzelkonturen verschiedener Verbauungsstrukturen 3 geschaffen. Im Bereich der Wassersohle 11 und des Ufers 12 ist eine Überlaufplatte 18 angeordnet. Diese kann bei Verschleiß leicht ausgetauscht werden.The
Solche Überlaufplatten 18 können - wie bereits erwähnt - natürlich auch bei Ausführungsformen verwendet werden, die nicht über mehrere Verbauungsstrukturen 3 verfügen.
Aus
Die mit Bezugszeichen 19 in
In
Im Einsatz wird eines der U-Profile auf Verbauungsstrukturen 3 aufgesetzt. Das andere U-Profil dient dann als Basis für eine darüber anzuordnende Verbauungsstruktur 3.In use, one of the U-profiles is placed on
Bei größeren Bauwerken kann also ein Baukastensystem zum Einsatz kommen. Dabei werden mehrere einzelne Verbauungsstrukturen 3 neben- und/oder übereinander eingebaut. Sie bestehen alle aus einem Rahmen und einer Stützfläche, wie oben beschrieben. Die einzelnen Elemente können so beliebig neben- und übereinander angeordnet, verankert und hinterfüllt werden. Die Geometrie der obersten Reihe bildet Abflusssektion / Überlaufsektion. Auch hier kann eine austauschbare Überlaufplatte 18 montiert werden. Die Verankerung der einzelnen Verbauungsstukturen 3 erfolgt wie oben beschrieben. Um die Montage bzw. das Einrichten einer Reihe zu erleichtern, kann unter jede Reihe eine (Führungs-) Schiene 17 gesetzt werden. Die Verbauungsstrukturen 3 werden dann einfach in diese Schiene 17 eingesetzt. Bei Bedarf kann die Führungsschiene beliebig verankert werden.For larger structures so a modular system can be used. Several
Bei den Bachverbauungen 1 mit Baukastensystem können die einzelnen Verbauungsstrukturen 3 nach der Reihe eingehoben und verankert werden. Sobald alle Verbauungsstrukturen 3 verankert sind, kann die Bachverbauung 1 hinterfüllt werden.In the
Claims (15)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP17156035.2A EP3361005B1 (en) | 2017-02-14 | 2017-02-14 | Ditch installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP17156035.2A EP3361005B1 (en) | 2017-02-14 | 2017-02-14 | Ditch installation |
Publications (2)
Publication Number | Publication Date |
---|---|
EP3361005A1 true EP3361005A1 (en) | 2018-08-15 |
EP3361005B1 EP3361005B1 (en) | 2019-10-16 |
Family
ID=58054012
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP17156035.2A Active EP3361005B1 (en) | 2017-02-14 | 2017-02-14 | Ditch installation |
Country Status (1)
Country | Link |
---|---|
EP (1) | EP3361005B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109371914A (en) * | 2018-12-25 | 2019-02-22 | 中国电建集团成都勘测设计研究院有限公司 | A kind of discharge channel structure convenient for later period reconstruction |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR3105273A1 (en) * | 2019-12-19 | 2021-06-25 | Pierre Jartoux | Ready-to-assemble set of parts for barring a torrent to maintain a fixed level ford. |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1941076A1 (en) * | 1968-08-03 | 1970-03-05 | Oesterr Alpine Montan | Lock for torrent barriers |
DE2300044A1 (en) * | 1973-01-02 | 1974-07-04 | Josef Schmidt | DEVICE FOR REDUCING WATER SPEED IN BACHLAEUFEN |
AT324232B (en) * | 1967-05-29 | 1975-08-25 | Oesterr Alpine Montan | RUST-SHAPED BARRIER FOR WILD FLOOR CONSTRUCTION |
DE29618691U1 (en) * | 1996-10-26 | 1997-01-30 | Bremer Schutz Verbauungen Gmbh | Wild wood catch and bedlock for torrents |
EP2848737A1 (en) | 2013-09-13 | 2015-03-18 | Mair Wilfried GmbH / Srl | Protection shield |
-
2017
- 2017-02-14 EP EP17156035.2A patent/EP3361005B1/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AT324232B (en) * | 1967-05-29 | 1975-08-25 | Oesterr Alpine Montan | RUST-SHAPED BARRIER FOR WILD FLOOR CONSTRUCTION |
DE1941076A1 (en) * | 1968-08-03 | 1970-03-05 | Oesterr Alpine Montan | Lock for torrent barriers |
DE2300044A1 (en) * | 1973-01-02 | 1974-07-04 | Josef Schmidt | DEVICE FOR REDUCING WATER SPEED IN BACHLAEUFEN |
DE29618691U1 (en) * | 1996-10-26 | 1997-01-30 | Bremer Schutz Verbauungen Gmbh | Wild wood catch and bedlock for torrents |
EP2848737A1 (en) | 2013-09-13 | 2015-03-18 | Mair Wilfried GmbH / Srl | Protection shield |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109371914A (en) * | 2018-12-25 | 2019-02-22 | 中国电建集团成都勘测设计研究院有限公司 | A kind of discharge channel structure convenient for later period reconstruction |
CN109371914B (en) * | 2018-12-25 | 2023-09-26 | 中国电建集团成都勘测设计研究院有限公司 | Drain channel structure convenient to later stage rebuild |
Also Published As
Publication number | Publication date |
---|---|
EP3361005B1 (en) | 2019-10-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3728743B1 (en) | Polygonal sprout system with nodes for reinforcing excavations | |
EP3441527B1 (en) | Shut-off device for preventing the passage of land vehicles | |
CH707671B1 (en) | Supporting masonry element and retaining wall made of supporting masonry elements. | |
EP3361005B1 (en) | Ditch installation | |
DE202021105799U1 (en) | Protective construction for high incline embankments in layered sloping soils in the coal mine | |
EP3696328B1 (en) | Method for installing vertical grids against burrowing animals | |
DE202005019792U1 (en) | Fish pass for overcoming water storage level comprises an upstream water inlet and a downstream water outlet and basins whereby sections of the fish pass in each case are prefabricated in trough from profiled material | |
EP3112537B1 (en) | Water-permeable support structure | |
EP1707685A2 (en) | Foundation for a high water barrier | |
AT516826B1 (en) | Device for excavation protection | |
DE2917994B1 (en) | Process for the production of a building pit lining or support wall from reinforced concrete for incisions in the terrain | |
DE202018106685U1 (en) | Retaining wall element and retaining wall of retaining wall elements | |
EP3480368A1 (en) | Facing plate system for producing a retaining structure or inclined embankment structure | |
WO2004044334A1 (en) | Floodwater protection system | |
DE4344703A1 (en) | Earthworks for dam | |
AT501178B1 (en) | ARRANGEMENT FOR ATTACHING OUTDOOR PATHES TO EXISTING ROAD CONSTRUCTIONS BZW. PITCHES OR THE LIKE | |
DE102004012295B4 (en) | Damm device | |
EP2302135B1 (en) | Prefabricated component element for underwater installation and module for reducing coastal erosion | |
DE2348043C3 (en) | Component for securing slopes or the like | |
CH714770A2 (en) | Retaining wall element and retaining wall of retaining wall elements. | |
DE1784327C (en) | Element for bank reinforcement | |
DE1059843B (en) | Device for the temporary reduction or deflection of the current in flowing waters | |
WO2004063471A1 (en) | Dyke reconstruction | |
EP3318675A1 (en) | Trough assembly with laying aid | |
DE1914740B1 (en) | Drainage device for a support wall designed as a space lattice wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20190211 |
|
RBV | Designated contracting states (corrected) |
Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20190710 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D Free format text: NOT ENGLISH |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 502017002547 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D Free format text: LANGUAGE OF EP DOCUMENT: GERMAN |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 1191369 Country of ref document: AT Kind code of ref document: T Effective date: 20191115 |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20191016 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200116 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200116 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200217 Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200117 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200224 Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 502017002547 Country of ref document: DE |
|
PG2D | Information on lapse in contracting state deleted |
Ref country code: IS |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200216 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 |
|
26N | No opposition filed |
Effective date: 20200717 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
REG | Reference to a national code |
Ref country code: BE Ref legal event code: MM Effective date: 20200229 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200214 Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200229 Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200229 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200214 Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200229 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200229 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20210214 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20210214 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: MT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191016 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IT Payment date: 20230227 Year of fee payment: 7 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20230425 Year of fee payment: 7 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 20240228 Year of fee payment: 8 |