EP2248948A1 - Supporting arch structure construction method - Google Patents

Supporting arch structure construction method Download PDF

Info

Publication number
EP2248948A1
EP2248948A1 EP09159584A EP09159584A EP2248948A1 EP 2248948 A1 EP2248948 A1 EP 2248948A1 EP 09159584 A EP09159584 A EP 09159584A EP 09159584 A EP09159584 A EP 09159584A EP 2248948 A1 EP2248948 A1 EP 2248948A1
Authority
EP
European Patent Office
Prior art keywords
frame structure
another
frame
swivel
relative
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP09159584A
Other languages
German (de)
French (fr)
Inventor
Eugenio Gutierrez Tenreiro
Martin Poljansek
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
European Union represented by European Commission
Original Assignee
European Union represented by European Commission
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by European Union represented by European Commission filed Critical European Union represented by European Commission
Priority to EP09159584A priority Critical patent/EP2248948A1/en
Priority to DK10717639.8T priority patent/DK2427601T3/en
Priority to ES10717639.8T priority patent/ES2627432T3/en
Priority to US13/318,984 priority patent/US8479473B2/en
Priority to PCT/EP2010/055937 priority patent/WO2010128002A2/en
Priority to EP10717639.8A priority patent/EP2427601B1/en
Priority to JP2012508999A priority patent/JP5690815B2/en
Publication of EP2248948A1 publication Critical patent/EP2248948A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/08Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/32Arched structures; Vaulted structures; Folded structures
    • E04B1/3205Structures with a longitudinal horizontal axis, e.g. cylindrical or prismatic structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3533Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by the raising of hingedly-connected building elements, e.g. arches, portal frames
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/38Arched girders or portal frames
    • E04C3/44Arched girders or portal frames of concrete or other stone-like material, e.g. with reinforcements or tensioning members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/07Reinforcing elements of material other than metal, e.g. of glass, of plastics, or not exclusively made of metal
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/40Plastics

Definitions

  • the present invention generally relates to a method of constructing a supporting architectural structure, or structural frame, having the form of an arch.
  • the invention is generically applicable to arch structures in lattice or shell form, in which the main structural forces are resolved into compressive forces, in particular to arch bridges, (e.g. supported deck arch bridges, suspended deck arch bridges, tied arch bridges, etc.) to large arched buildings, tunnels, galleries and temporary supporting structures.
  • arch bridges e.g. supported deck arch bridges, suspended deck arch bridges, tied arch bridges, etc.
  • supporting structure and "structural frame” designate the load-resisting sub-system of a construction (architectural structure), i.e. the part of the construction that transfers and possibly absorbs the main load through interconnected structural components or members.
  • arch bridges in particular of arch bridges, belong to the oldest engineered forms of construction and have played a fundamental role in the development of all advanced societies.
  • arch bridges were constructed from masonry, which conditioned the manner and methods of construction to such an extent that, even with the advent of the industrial revolution, the first iron bridges were constructed as arch (i.e. compressive load-carrying) structures.
  • arch bridges were constructed from masonry, which conditioned the manner and methods of construction to such an extent that, even with the advent of the industrial revolution, the first iron bridges were constructed as arch (i.e. compressive load-carrying) structures.
  • arch bridges i.e. compressive load-carrying
  • the introduction of modern materials permitted the adaptation of arch bridges for longer spans.
  • the development of high-strength tensile steel in the twentieth century made it possible to construct arch bridges with spans of hundreds of meters especially by means of transferring the reaction forces away from the abutments to the bridge deck itself (tied arch bridges).
  • FRPs glass-fibre reinforced composites
  • GFRCs have a rather low specific modulus which precludes them from use in stiffness-dominated bridge applications whenever spans in excess of a tens meters are called for.
  • long bridges made from FRPs are viable if they are multiply supported; however, in certain locations, multiple supports are not always physically possible or are too expensive to implement. For these reasons, current construction and installation practice has only resulted in medium-length multi-span or short, single-span, beam bridges.
  • WO 90/13715 A1 discloses a method of constructing an arched building structure that uses lightweight elongate frames, pivotally connected to each other at one end, wherein the frames are lifted simultaneously so that the pivotal connection forms a ridge of the building structure.
  • the free ends of the frames are anchored at abutments while the frames are held in the lifted position to form a three-pin arch frame building structure.
  • US 4,143,502 describes another method of constructing an arched building structure, wherein an elongate structural frame is bent into parabolic shape by lifting the medial portion thereof and fixing the opposed ends of the structural frame on abutments. When the ends are fixed, the flexed frame supports itself thanks to the abutments.
  • an initially straight or pre-curved frame structure having a first end and a second end opposite to the first end, is pivotally supported at the first and second ends, whereupon the first and second ends are pushed towards one another to achieve a displacement of the first and second ends relative to one another.
  • the reduction of the distance between the first and second ends causes them to pivot and the frame structure to progressively and flexibly bend, against its resiliency, into a final arched form.
  • the displacement of the first and second ends relative to one another is chosen to amount to at least 1% of the initial distance between the first and second ends.
  • the first and second ends are then fixed relative to one another in their displaced position so as to preserve the final arched form of the frame structure.
  • the arched supporting structure is kept in place by suitable containments of the arch reaction forces, either at the abutments (or building foundations), or in case of a tied arch, by tension in a structural component (e.g. the deck in case of a tied arch bridge) linking the first and second end of the frame structure.
  • An arched supporting structure erected according to the present method may be considered a "deployable" supporting structure in the sense that its constituent structural components generate an arch upon the application of a force provided by an actuated mechanism.
  • the frame structure is preferably configured such that its bending takes place over substantially the entire length between the ends of the frame structure.
  • frame structure is intended to cover, among others, a girder, a girder assembly, a beam, a beam assembly, or whichever structure that is to able to serve as a load-carrying structure when bent into an arched form as described above.
  • arched supporting structure achievable with the present invention might be part of the final construction or building.
  • the supporting structure is only temporarily used during the construction stage, e.g. as a falsework.
  • the frame structure comprises fibre-reinforced polymer elements extending from the first end to the second end.
  • FRPs exhibit very high strain-to-failure limits.
  • GFRC glass-fibre-reinforced composites
  • other materials may be chosen, provided that such materials are able to withstand the considerable bending stresses occurring in the frame structure when it is bent into its arched shape.
  • the FRP elements can be made using a variety of techniques, but the most attractive (and cheapest) solution is to use tubes or prismatic profilesthat can be easily manufactured using filament-winding or pultrusion techniques, respectively. It is also possible to form the frame structure from sandwich panels, which are assembled flat on the construction site, cross-raced, and then bent into the desired curvature.
  • curved FRP arch member would support working strain well in excess of the limits of steel or reinforced concrete members.
  • curved arch members made from FRP can be subject to an unloaded strain of the order of 0.2 to 0.3% just from the imposed curvature, whereas construction steel would yield at approximately 0.1% strain, making it impossible to generate the desired curvature without generating plastic deformations. It is expected that, under full load, the supporting structure could have a service strain of the order of 0.3 to 0.4% and a failure strain in excess of 1 %, which is considered an adequate safety margin.
  • a pre-curved frame structure it could be made from a plurality of segments of uniform curvature fabricated by means of the same mould. The segments could be joined on the construction site to form the initially pre-curved frame structure.
  • an initially arched frame structure one may arrive at more pronounced arch heights than with an initially straight frame structure. It should be noted that the initial distance between the ends of the supporting structure would be measured along the straight segment between the ends (not along the initial arch).
  • FRP supporting structures are, in principle, much lighter than such structures made from traditional materials like concrete, steel or wood, FRP supporting structures have the potential to substantially reduce construction costs and to be applicable to soil conditions where standard construction would otherwise require more extensive, and expensive, soil foundation.
  • Joining of FRP elements to form the frame structure could be carried out e.g. by using a vacuum-assisted resin-transfer moulding (VARTM) technique or in the case of profiles by connecting the pultruded profiles using standard joining techniques known to practitioners skilled in the art.
  • VARTM vacuum-assisted resin-transfer moulding
  • the frame structure is provided as a hollow fibre-reinforced polymer formwork for concrete or high-strength mortar.
  • concrete may be poured into the formwork.
  • This variant addresses, in particular, applications in which the supporting structure has to carry high loads.
  • There has been some concern over the safety of tied-arch bridges because the ties can be classified as fracture-critical members.
  • a fracture-critical member is one that would cause collapse of the bridge if it fractured. Since its tie resists the horizontal thrust of a tied-arch, most tied arches would collapse if the tie were lost.
  • One solution to mitigate the possibility of this type of collapse with the arch bridge system is to increase the overall capacity and stability of the arch by using e.g. hollow tubular elements as formwork that is filled with poured concrete.
  • the formwork may remain in place after the concrete or mortar has set (in which case the resulting supporting structure comprises both the set concrete or mortar and the formwork), or, alternatively, be removed so as to leave only the concrete structure.
  • the frame structure comprises steel and/or fibre-reinforced polymer rebar within the formwork.
  • the formwork and the reinforcement placed therein, are subjected to bending at the same time.
  • the reinforcement, being confined inside the formwork has to follow the curvature during the raising stage of the method.
  • the formwork may be filled with concrete or high strength mortar. Again, the formwork may be removed after the concrete or mortar has cured, or remain in place.
  • the first and second ends are preferably pivotally supported about a first and a second pivot axis, respectively, these pivot axes being substantially parallel to one another and substantially perpendicular to the displacement of the first and second ends relative to one another.
  • the bending of the frame structure takes place parallel to a plane that is perpendicular to the pivot axes.
  • the pivot axes may be horizontal (resulting in a vertical arch) but may also be inclined with respect to the horizontal plane (in which case the arch will be inclined with respect to the vertical plane containing the first and second end of the frame structure).
  • the forces exerted on the first and second ends to push them towards one another are transferred to the frame structure via the pivot axes.
  • the first end is pivotally supported by a first stationary swivel provided as part of a first abutment while the second end is pivotally supported with an actuatable swivel and pushing the first and second ends towards one another is carried out by the actuatable swivel pushing the second end and said stationary swivel exerting an opposite reaction force on the first end.
  • Actuators suitable for actuating the actuatable swivel are e.g. actuators currently used in the push-forward bridge launching technique.
  • the actuatable swivel is guided on rails (fixed to the ground).
  • the actuatable swivel is preferably fixed in a stationary position so as to become part of a second abutment, opposed to the first abutment.
  • the displacement of the first and second ends relative to one another amounts to at least 2%, preferably at least 3%, more preferably at least 5%, possibly even at least 10% or at least 15%, of the initial distance between the first and second ends.
  • the relative displacement amounts to around 5%, e.g. from 2% to 8% of the initial distance between the ends.
  • each of the first and second frame structures comprises an extrados surface (i.e. a surface lying radially outward when the frame structure is bent) and an intrados surface (i.e. a surface lying radially inward when the frame structure is bent).
  • the second frame structure is caused to progressively bend concomitantly with the first frame structure in such a way that one of the intrados and extrados surfaces of the first frame structure contacts the other of the intrados and extrados surfaces of the second frame structure at the latest when the first frame structure is in its final arched form.
  • the second frame structure is then fixed to the first frame structure at the meeting surfaces so as to prevent relative movement between them.
  • Such fixing of the second to the first frame structure is preferably achieved by gluing and/or with flanges.
  • the second frame structure is preferably of the same configuration as the first frame structure.
  • the first and second frame structures prior to bending, are arranged such that one of the intrados and extrados surfaces of the first frame structure is adjacent the other of the intrados and extrados surfaces of the second frame structure, a layer of glue being arranged between the adjacent surfaces.
  • the progressive bending is carried out while the glue has not set so that the first and second frame structures are allowed to slide along their lengths while they bend.
  • the fixing of the second frame structure to the first frame structure comprises letting the layer of glue set while keeping the first and second frame structures immobile with respect to one another when the first frame structure is in its final arched form.
  • Figs. 1 and 2 illustrates the general concept underlying the method of constructing an arched supporting structure.
  • An initially straight beam 10 of tubular (rectangular, round, trapezoidal or other) cross section is mounted pivotally supported at its ends 12, 14.
  • the pivot axes 16 are parallel to one another and perpendicular to the longitudinal axis 18 of the beam.
  • Figs. 1 and 2 show the longitudinal axis 18 and the pivot axes 16 to be horizontal; however, this is not necessary in general.
  • a stationary swivel 20 pivotally supports the first end 12 of the beam 10.
  • the stationary swivel 20 is firmly anchored in the ground so as to form a first abutment of the arched supporting structure to be constructed.
  • the second end 14 of the beam 10 is pivotally supported by a movable swivel 22, guided on rails (not shown in Figs. 1 and 2 ) extending along the direction of the longitudinal axis 18 of the beam.
  • An actuator 24 e.g. a hydraulic or other actuator as commonly used in incremental bridge launching technique
  • a small initial curvature (if not already present) is generated in the beam 10.
  • the initial curvature is chosen such that the bending goes into the desired direction.
  • the actuator 24 pushes the movable swivel 22 into the direction of the stationary swivel 20 and thus the second end 14 towards the first end 12 of the beam 10, the distance between the ends 12, 14 decreases.
  • the beam 10 bends under the applied load and assumes an arched form.
  • the distance between the first and second ends 12, 14 is measured between the pivot axes 16.
  • the displacement of the first and second ends 12, 14 relative to one another is calculated beforehand, in accordance with the desired span and arch height and the static requirements.
  • the relative displacement of the ends 12, 14 is significant in the sense that it is not merely a displacement that leads to a prestressing of the beam 10, as commonly used e.g. on arched concrete structures to compensate for sagging moments, but one that results in a significant displacement of the beam centre off the longitudinal axis 18.
  • the relative displacement of the ends amounts to at least 1 % of the initial distance between the first and second ends 12, 14.
  • the process of displacing the first and second end 12, 14 toward one another may be done in steps if the desired displacement is larger than the stroke length of the piston: the movable swivel 22 is then temporarily anchored in the ground or otherwise held in position, while the actuator 24 is brought closer. The next pushing step is then carried out essentially in the same way as the previous one after the movable swivel 22 has again been released.
  • the movable swivel 22 is fixed in a stationary position relative to the swivel 20 at the other end of the beam 10. This may be achieved by fixing the movable swivel 22 to a previously prepared foundation, a socle or other support firmly anchored in the ground. Additionally or alternatively, the swivels 20, 22 may be tied to one another (as in case of a tied arch bridge) e.g. via a tie beam extending along the straight line between the ends of the arched beam. In case of a tied arch, the outward-directed horizontal forces of the arch, are at least partially borne as tension by the tie beam, rather than by the ground, the foundations or other supports the arched supporting structure rests upon.
  • the frame structure (in the above example: the tubular beam) is preferably made from fibre-reinforced polymer (FRP) elements, such as e.g. elements made of glass, carbon or aramid fibre reinforced composites,
  • FRP fibre-reinforced polymer
  • Fig. 3 illustrates a variant of the method according to the invention, wherein the frame structure comprises a braced structure 30 with two initially straight longitudinal beams 32 arranged in parallel one to the other and a plurality of transverse beams 34 linking the longitudinal beams 32.
  • the framework is completed by diagonal steel bars, rods, or cables 36, which make the framework more resistant against longitudinal shear stress.
  • the frame structure is bent into arch shape in essentially the same way as the beam of Figs. 1 and 2 .
  • the first end of each longitudinal beam 32 is pivotally mounted on a stationary swivel 38, whereas the second end of each longitudinal beam 32 is mounted on a movable swivel 40, guided on a rail 42.
  • the initially slightly curved longitudinal beams 32 bend upwards until the frame structure finally reaches its planned curvature.
  • the frame structure could also comprise a cutout panel or shell.
  • the tubular elements of the longitudinal and transverse beams 32, 34 in Fig. 3 could be made using a filament winding process, or with arbitrary-shaped profile sections that could possibly be made using, for example, pultrusion techniques.
  • the beam elements are made to a length that is acceptable for transport and are joined on the construction site using, for example, vacuum-assisted resin transfer moulding or slot-in connectors 46 (as shown in Figs. 4 and 5 ).
  • the structural strength of the resulting joint can be increased by applying adhesive between the overlapping surfaces of the connector elements and the beam elements.
  • Fig. 6 shows an example of a swivel 50 for fixing the frame structure at its ends, usable as the stationary or the movable swivel.
  • the swivel 50 comprises a base 52 and a sleeve portion 54, which is pivotally fixed to the base 52.
  • the sleeve portion 54 is dimensioned such that the first or the second end of the supporting frame may be inserted into it.
  • the base 52 is fixed to a foundation (if it is used as the stationary swivel) or a sliding train (if it is used as the actuatable swivel).
  • the rotation about the pivot axes of the first and second ends is fixed by blocking the sleeve portion 54 with linchpins 56 and the movable swivel is also fixed to a foundation, e.g. with bolts.
  • Fig. 7 shows a modular composite deck assembly 60 made from FRP beams 62 and slotted FRP sandwich panels 64.
  • the deck assembly 60 may be suspended from it by means of cables.
  • Another possibility is to suspend a light deck from the supporting structure before the latter is raised, so that when the arch forms, the deck is automatically lifted into position.
  • the deck is preferably initially made from a lightweight composite box-beam, which is fitted with the heavy road-surface stratification once the final shape of the arch has been reached.
  • the support frame is preferably configured as a hollow formwork, into which concrete may be poured and allowed to set.
  • a support frame is illustrated in Fig. 8 .
  • the support frame comprises tubular formwork elements 70 having arranged in their interior a steel or fibre-reinforced polymer rebar and stirrups 72.
  • the steel or FRP rebar 72 is forced to follow the curvature of the arch being generated.
  • the formwork is filled through openings 74, provided in the formwork shell, with concrete 76 or high-strength mortar. Once the concrete 76 or mortar has set, the supporting structure is capable of supporting much higher loads than before.
  • a hogging moment may be induced in the set concrete or mortar by a further displacement of the ends of the supporting structure towards one another.
  • further displacement would be much smaller than 1% of the initial distance between the ends because the concrete or mortar would fail otherwise.
  • Filling the formwork with reinforced concrete could increase its buckling capacity by a factor of about 2 to 3, depending on the quality of the concrete or mortar used.
  • each of the frame structures has a relatively shallow section in the bending direction, so that the distance from the intrados and extrados surfaces to the respective neutral axis are small.
  • a square-section tube or profile with a height of 1 m in bending direction in such a way that the height-curvature imposes a strain of 3000 microstrain. If one bends a shallower tube or profile having a height of 1/3 m in bending direction to the same curvature, the resulting bending strains are approximately three times smaller.
  • the buckling capacity of the assembly would only be given by the individual shallow tube or profile sections (which is which is much smaller than the buckling capacity of the 1 m square section tube). If however, the shallow tubes or profiles are joined along their meeting surfaces after they have reached their final shape, the buckling capacity of the assembly becomes approximately the same as that of the 1 m square section tube or profile.
  • the shallow tubes or profiles have each an intrados surface and an extrados surface. As they are progressively bent concomitantly with one another, the intrados surfaces are compressed while the extrados surfaces are stretched, which locally results in relative movement between meeting surfaces, i.e. between the intrados surface 90 of the middle tube or profile and the extrados surface 88 of the lower tube or profile as well as between the extrados surface 92 of the middle tube or profile and the intrados surface 94 of the upper tube or profile.
  • the tubes or profiles Once the tubes or profiles have reached their final positions, they are fixed to one another by gluing and/or with bolted flanges.
  • layers of glue are applied between adjacent meeting surfaces when the shallow tubes or profiles 80, 82, 84 still have their initial shape and the bending is carried out while the glue has not yet set and allows the meeting surfaces to locally slide one with respect to another while they bend.
  • the layers of glue are simply let set while the shallow tubes or profiles 80, 82, 84 are kept immobile with respect to one another when they have reached their final arched form.
  • flanges may be used to bond and bolt the shallow tubes or profiles 80, 82, 84 together.
  • the assembly of shallow tubes or profiles 80, 82, 84 might serve as a formwork for concrete or mortar, depending on the application.
  • the frame structure to be bent into arch form according to the method of the present invention may be assembled from FRP I-beam elements 98 (sometimes also referred to as H- or double-T-beam elements), assembled together with bolted joints 100.
  • FRP I-beam elements 98 sometimes also referred to as H- or double-T-beam elements
  • bolted joints 100 The use of such profiles instead of hollow tubular profiles may be advantageous in case the frame structure of the construction needs not be filled with concrete or mortar.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

In a method of constructing a supporting structure (e.g. of a bridge or the roof of a building) in arched form, an initially straight or pre-curved frame structure (10), having a first end (12) and a second end (14) opposite to the first end, is pivotally supported at the first and second ends, whereupon the first and second ends are pushed towards one another to achieve a displacement of the first and second ends relative to one another. The reduction of the distance between the first and second ends causes them to pivot and the frame structure (10) to progressively and flexibly bend, against its resiliency, into a final arched form. The displacement of the first and second ends relative to one another is chosen to amount to at least 1% of the initial distance between the first and second ends. The first and second ends are then fixed relative to one another in their displaced position so as to preserve the final arched form of the frame structure.
Figure imgaf001

Description

    Technical field
  • The present invention generally relates to a method of constructing a supporting architectural structure, or structural frame, having the form of an arch. The invention is generically applicable to arch structures in lattice or shell form, in which the main structural forces are resolved into compressive forces, in particular to arch bridges, (e.g. supported deck arch bridges, suspended deck arch bridges, tied arch bridges, etc.) to large arched buildings, tunnels, galleries and temporary supporting structures.
  • Background Art
  • For the purposes of the present, the terms "supporting structure" and "structural frame" designate the load-resisting sub-system of a construction (architectural structure), i.e. the part of the construction that transfers and possibly absorbs the main load through interconnected structural components or members.
  • Supporting arch structures, in particular of arch bridges, belong to the oldest engineered forms of construction and have played a fundamental role in the development of all advanced societies. For many centuries, arch bridges were constructed from masonry, which conditioned the manner and methods of construction to such an extent that, even with the advent of the industrial revolution, the first iron bridges were constructed as arch (i.e. compressive load-carrying) structures. The introduction of modern materials permitted the adaptation of arch bridges for longer spans. The development of high-strength tensile steel in the twentieth century made it possible to construct arch bridges with spans of hundreds of meters especially by means of transferring the reaction forces away from the abutments to the bridge deck itself (tied arch bridges).
  • The traditional construction materials for structural components are concrete, steel and - nowadays to a lesser extent - wood. In the second half of the twentieth century, a new class of materials, fibre-reinforced polymers or plastics (FRP), slowly began to be considered as potential candidates as construction materials for addressing the limitations of concrete, wood and steel structures. These composite materials are most interesting for the construction industry due to their high strength, low weight and high corrosion resistance. Nevertheless, in spite of the continual reduction in their prime material cost, FRPs still remain relatively expensive in general, even when this handicap is offset on the long term by generally low life cycle cost.
  • The use of FRP in bridge construction has produced a number of interesting solutions for deck systems, described, for instance, in patents US 6,108,998 , US 6,170,105 and US 6,455,131 . However, although the potential (in terms of their mechanical properties) for the use of FRPs materials in long-span bridges is very high, the current material prices and the lack of production methods capable of producing the large components at acceptable market prices has restricted the spreading of such materials in bridge construction, particularly for single spans in excess of ten meters. Although, in principle, the use of cheaper FRPs (such glass-fibre reinforced composites, GFRC) is an acceptable option for short spans or long pedestrian bridges, GFRCs have a rather low specific modulus which precludes them from use in stiffness-dominated bridge applications whenever spans in excess of a tens meters are called for. Of course, long bridges made from FRPs are viable if they are multiply supported; however, in certain locations, multiple supports are not always physically possible or are too expensive to implement. For these reasons, current construction and installation practice has only resulted in medium-length multi-span or short, single-span, beam bridges.
  • In civil engineering applications, there is a need for cost-efficient construction methods for erecting supporting structures, in particular with medium and long spans.
  • WO 90/13715 A1 discloses a method of constructing an arched building structure that uses lightweight elongate frames, pivotally connected to each other at one end, wherein the frames are lifted simultaneously so that the pivotal connection forms a ridge of the building structure. The free ends of the frames are anchored at abutments while the frames are held in the lifted position to form a three-pin arch frame building structure. US 4,143,502 describes another method of constructing an arched building structure, wherein an elongate structural frame is bent into parabolic shape by lifting the medial portion thereof and fixing the opposed ends of the structural frame on abutments. When the ends are fixed, the flexed frame supports itself thanks to the abutments.
  • Technical problem
  • It is an object of the present invention to provide an alternative cost-efficient construction method for erecting an arched supporting structure. This object is achieved by a method as claimed in claim 1.
  • General Description of the Invention
  • According to the invention, in a method of constructing a supporting structure (of an architectural construction such as e.g. a bridge or the roof of a building) in arched form, an initially straight or pre-curved frame structure, having a first end and a second end opposite to the first end, is pivotally supported at the first and second ends, whereupon the first and second ends are pushed towards one another to achieve a displacement of the first and second ends relative to one another. The reduction of the distance between the first and second ends causes them to pivot and the frame structure to progressively and flexibly bend, against its resiliency, into a final arched form. The displacement of the first and second ends relative to one another is chosen to amount to at least 1% of the initial distance between the first and second ends. The first and second ends are then fixed relative to one another in their displaced position so as to preserve the final arched form of the frame structure. The arched supporting structure is kept in place by suitable containments of the arch reaction forces, either at the abutments (or building foundations), or in case of a tied arch, by tension in a structural component (e.g. the deck in case of a tied arch bridge) linking the first and second end of the frame structure. An arched supporting structure erected according to the present method may be considered a "deployable" supporting structure in the sense that its constituent structural components generate an arch upon the application of a force provided by an actuated mechanism. The frame structure is preferably configured such that its bending takes place over substantially the entire length between the ends of the frame structure.
  • It should be noted that the term "frame structure", as used herein, is intended to cover, among others, a girder, a girder assembly, a beam, a beam assembly, or whichever structure that is to able to serve as a load-carrying structure when bent into an arched form as described above.
  • It should also be noted that the arched supporting structure achievable with the present invention might be part of the final construction or building. However, it is also possible that the supporting structure is only temporarily used during the construction stage, e.g. as a falsework.
  • According to a preferred embodiment of the method, the frame structure comprises fibre-reinforced polymer elements extending from the first end to the second end. Compared to other construction materials, FRPs exhibit very high strain-to-failure limits. In the case of glass-fibre-reinforced composites (GFRC) such FRPs come even with a competitive price. Those skilled will appreciate that other materials may be chosen, provided that such materials are able to withstand the considerable bending stresses occurring in the frame structure when it is bent into its arched shape. The FRP elements can be made using a variety of techniques, but the most attractive (and cheapest) solution is to use tubes or prismatic profilesthat can be easily manufactured using filament-winding or pultrusion techniques, respectively. It is also possible to form the frame structure from sandwich panels, which are assembled flat on the construction site, cross-raced, and then bent into the desired curvature.
  • Experimental and analytical calculations have revealed that a curved FRP arch member would support working strain well in excess of the limits of steel or reinforced concrete members. For example, curved arch members made from FRP can be subject to an unloaded strain of the order of 0.2 to 0.3% just from the imposed curvature, whereas construction steel would yield at approximately 0.1% strain, making it impossible to generate the desired curvature without generating plastic deformations. It is expected that, under full load, the supporting structure could have a service strain of the order of 0.3 to 0.4% and a failure strain in excess of 1 %, which is considered an adequate safety margin.
  • If a pre-curved frame structure is to be used, it could be made from a plurality of segments of uniform curvature fabricated by means of the same mould. The segments could be joined on the construction site to form the initially pre-curved frame structure. By using an initially arched frame structure, one may arrive at more pronounced arch heights than with an initially straight frame structure. It should be noted that the initial distance between the ends of the supporting structure would be measured along the straight segment between the ends (not along the initial arch).
  • Given that FRP supporting structures are, in principle, much lighter than such structures made from traditional materials like concrete, steel or wood, FRP supporting structures have the potential to substantially reduce construction costs and to be applicable to soil conditions where standard construction would otherwise require more extensive, and expensive, soil foundation.
  • Joining of FRP elements to form the frame structure could be carried out e.g. by using a vacuum-assisted resin-transfer moulding (VARTM) technique or in the case of profiles by connecting the pultruded profiles using standard joining techniques known to practitioners skilled in the art.
  • In a particularly advantageous variant of the invention, the frame structure is provided as a hollow fibre-reinforced polymer formwork for concrete or high-strength mortar. When the first and second ends are fixed relative to one another in their displaced position, concrete may be poured into the formwork. As the concrete sets, it increases the overall capacity and stability of the arched supporting structure. This variant addresses, in particular, applications in which the supporting structure has to carry high loads. There has been some concern over the safety of tied-arch bridges because the ties can be classified as fracture-critical members. A fracture-critical member is one that would cause collapse of the bridge if it fractured. Since its tie resists the horizontal thrust of a tied-arch, most tied arches would collapse if the tie were lost. One solution to mitigate the possibility of this type of collapse with the arch bridge system is to increase the overall capacity and stability of the arch by using e.g. hollow tubular elements as formwork that is filled with poured concrete. It should be noted that the formwork may remain in place after the concrete or mortar has set (in which case the resulting supporting structure comprises both the set concrete or mortar and the formwork), or, alternatively, be removed so as to leave only the concrete structure.
  • According to a preferred embodiment of this variant of the invention, the frame structure comprises steel and/or fibre-reinforced polymer rebar within the formwork. The formwork and the reinforcement placed therein, are subjected to bending at the same time. The reinforcement, being confined inside the formwork has to follow the curvature during the raising stage of the method. Once the arch has been erected and fixed, the formwork may be filled with concrete or high strength mortar. Again, the formwork may be removed after the concrete or mortar has cured, or remain in place.
  • The first and second ends are preferably pivotally supported about a first and a second pivot axis, respectively, these pivot axes being substantially parallel to one another and substantially perpendicular to the displacement of the first and second ends relative to one another. In such configuration, the bending of the frame structure takes place parallel to a plane that is perpendicular to the pivot axes. It should be noted that the pivot axes may be horizontal (resulting in a vertical arch) but may also be inclined with respect to the horizontal plane (in which case the arch will be inclined with respect to the vertical plane containing the first and second end of the frame structure). Preferably, the forces exerted on the first and second ends to push them towards one another are transferred to the frame structure via the pivot axes.
  • Preferably, the first end is pivotally supported by a first stationary swivel provided as part of a first abutment while the second end is pivotally supported with an actuatable swivel and pushing the first and second ends towards one another is carried out by the actuatable swivel pushing the second end and said stationary swivel exerting an opposite reaction force on the first end. Actuators suitable for actuating the actuatable swivel are e.g. actuators currently used in the push-forward bridge launching technique. Preferably, the actuatable swivel is guided on rails (fixed to the ground). When the second end has reached its desired position, the actuatable swivel is preferably fixed in a stationary position so as to become part of a second abutment, opposed to the first abutment.
  • Preferably, the displacement of the first and second ends relative to one another amounts to at least 2%, preferably at least 3%, more preferably at least 5%, possibly even at least 10% or at least 15%, of the initial distance between the first and second ends. Most preferably, the relative displacement amounts to around 5%, e.g. from 2% to 8% of the initial distance between the ends. To give an idea about the resulting arch heights, the following table summarizes the raise of the centre of the frame structure caused by such displacements of the ends relative to one another in case of an initially straight, horizontal frame structure in case of a perfectly parabolic shape when bent.
    Displacement in % of arch length Arch height in % arch length
    1 6.12
    2 8.65
    3 10.59
    5 13.65
    10 19.24
    15 23.46
  • Hence, given an initially straight, horizontal frame structure having a length of 100 m between the points of application of the compressive forces at the ends and assuming a perfectly parabolic shape of the resulting arch, a relative displacement of the ends toward one another of about 5 m will lift the centre of the frame structure by about 14 m. Of course, the flexibility of the material of the frame structure has to be chosen in accordance with the desired bending to avoid failure of the material.
  • According to a preferred variant of the method, at least two frame structures (hereinafter referred to as the first and the second frame structure) are bent into arch shape. In this variant, each of the first and second frame structures comprises an extrados surface (i.e. a surface lying radially outward when the frame structure is bent) and an intrados surface (i.e. a surface lying radially inward when the frame structure is bent). The second frame structure is caused to progressively bend concomitantly with the first frame structure in such a way that one of the intrados and extrados surfaces of the first frame structure contacts the other of the intrados and extrados surfaces of the second frame structure at the latest when the first frame structure is in its final arched form. The second frame structure is then fixed to the first frame structure at the meeting surfaces so as to prevent relative movement between them. Such fixing of the second to the first frame structure is preferably achieved by gluing and/or with flanges. The second frame structure is preferably of the same configuration as the first frame structure. As those skilled will appreciate, by using relatively shallow frame structures, which are joined together, it is possible to reach significantly higher buckling capacities. On the other hand, by using a single frame structure having the dimensions of several shallow frame structures joined together, the material will fail much earlier for the bending strains at the intrados and/or extrados sides exceeding the tolerances.
  • According to a preferred embodiment of this variant of the invention, prior to bending, the first and second frame structures are arranged such that one of the intrados and extrados surfaces of the first frame structure is adjacent the other of the intrados and extrados surfaces of the second frame structure, a layer of glue being arranged between the adjacent surfaces. The progressive bending is carried out while the glue has not set so that the first and second frame structures are allowed to slide along their lengths while they bend. The fixing of the second frame structure to the first frame structure comprises letting the layer of glue set while keeping the first and second frame structures immobile with respect to one another when the first frame structure is in its final arched form.
  • Brief Description of the Drawings
  • Further details and advantages of the present invention will be apparent from the following detailed description of several not limiting embodiments with reference to the attached drawings, wherein:
  • Fig. 1
    is a lateral view of a straight beam before it is bent into an arched form;
    Fig. 2
    is a lateral view of the beam of Fig. 1 when bent into the arched form;
    Fig. 3
    is an illustration of the method according to the present invention applied to a braced structure;
    Fig. 4
    is a perspective view close-up of a T-joint of the braced structure of Fig. 3;
    Fig. 5
    is an exploded perspective view of the T-joint of Fig. 4;
    Fig. 6
    is a perspective view of a swivel for fixing an end of the frame structure to be bent into arched form;
    Fig. 7
    is perspective view of a modular composite deck system made from FRP beams and slotted FRP sandwich panels;
    Fig. 8
    is an illustration of the filling of an FRP formwork with concrete; and
    Fig. 9
    is a schematic illustration of the bending of a layered assembly of plural frame structures into an arched form;
    Fig. 10
    is a side view of an FRP I-beam as may be used in a frame structure to be bent according to the invention;
    Fig. 11
    is a side view of the I-beam of Fig. 10 when bent;
    Fig. 12
    is a perspective view of a bolted joint connecting two I-beam elements.
    Description of Preferred Embodiments
  • Figs. 1 and 2 illustrates the general concept underlying the method of constructing an arched supporting structure. An initially straight beam 10 of tubular (rectangular, round, trapezoidal or other) cross section is mounted pivotally supported at its ends 12, 14. The pivot axes 16 are parallel to one another and perpendicular to the longitudinal axis 18 of the beam. (Figs. 1 and 2 show the longitudinal axis 18 and the pivot axes 16 to be horizontal; however, this is not necessary in general.) A stationary swivel 20 pivotally supports the first end 12 of the beam 10. The stationary swivel 20 is firmly anchored in the ground so as to form a first abutment of the arched supporting structure to be constructed. The second end 14 of the beam 10 is pivotally supported by a movable swivel 22, guided on rails (not shown in Figs. 1 and 2) extending along the direction of the longitudinal axis 18 of the beam. An actuator 24 (e.g. a hydraulic or other actuator as commonly used in incremental bridge launching technique) is arranged to push the movable swivel 22 into the direction of the stationary swivel 20 at the first end 12 of the beam 10.
  • Before pushing the movable swivel 22, a small initial curvature (if not already present) is generated in the beam 10. The initial curvature is chosen such that the bending goes into the desired direction. When the actuator 24 pushes the movable swivel 22 into the direction of the stationary swivel 20 and thus the second end 14 towards the first end 12 of the beam 10, the distance between the ends 12, 14 decreases. As the beam length remains substantially the same, the beam 10 bends under the applied load and assumes an arched form. The distance between the first and second ends 12, 14 is measured between the pivot axes 16. The displacement of the first and second ends 12, 14 relative to one another is calculated beforehand, in accordance with the desired span and arch height and the static requirements. It is emphasized that the relative displacement of the ends 12, 14 is significant in the sense that it is not merely a displacement that leads to a prestressing of the beam 10, as commonly used e.g. on arched concrete structures to compensate for sagging moments, but one that results in a significant displacement of the beam centre off the longitudinal axis 18. In particular, the relative displacement of the ends amounts to at least 1 % of the initial distance between the first and second ends 12, 14. The process of displacing the first and second end 12, 14 toward one another may be done in steps if the desired displacement is larger than the stroke length of the piston: the movable swivel 22 is then temporarily anchored in the ground or otherwise held in position, while the actuator 24 is brought closer. The next pushing step is then carried out essentially in the same way as the previous one after the movable swivel 22 has again been released.
  • When the desired arch curvature is reached, the movable swivel 22 is fixed in a stationary position relative to the swivel 20 at the other end of the beam 10. This may be achieved by fixing the movable swivel 22 to a previously prepared foundation, a socle or other support firmly anchored in the ground. Additionally or alternatively, the swivels 20, 22 may be tied to one another (as in case of a tied arch bridge) e.g. via a tie beam extending along the straight line between the ends of the arched beam. In case of a tied arch, the outward-directed horizontal forces of the arch, are at least partially borne as tension by the tie beam, rather than by the ground, the foundations or other supports the arched supporting structure rests upon.
  • The frame structure (in the above example: the tubular beam) is preferably made from fibre-reinforced polymer (FRP) elements, such as e.g. elements made of glass, carbon or aramid fibre reinforced composites, In the case of an arch being formed in the manner of the variant using intrados/extrados concommittant surfaces, it could also be possible to use high-strength aluminium or steel alloys or any material that could accommodate the bending strains.
  • Fig. 3 illustrates a variant of the method according to the invention, wherein the frame structure comprises a braced structure 30 with two initially straight longitudinal beams 32 arranged in parallel one to the other and a plurality of transverse beams 34 linking the longitudinal beams 32. The framework is completed by diagonal steel bars, rods, or cables 36, which make the framework more resistant against longitudinal shear stress. As the different views of Fig. 3 show, the frame structure is bent into arch shape in essentially the same way as the beam of Figs. 1 and 2. The first end of each longitudinal beam 32 is pivotally mounted on a stationary swivel 38, whereas the second end of each longitudinal beam 32 is mounted on a movable swivel 40, guided on a rail 42. By progressively increasing the loads (illustrated by arrows 44) on the second end of each longitudinal beam 32, the initially slightly curved longitudinal beams 32 bend upwards until the frame structure finally reaches its planned curvature.
  • Instead of a tubular beam 10 as in Figs. 1 and 2 or a braced structure 30 as in Fig. 3, the frame structure could also comprise a cutout panel or shell. The tubular elements of the longitudinal and transverse beams 32, 34 in Fig. 3 could be made using a filament winding process, or with arbitrary-shaped profile sections that could possibly be made using, for example, pultrusion techniques.
  • Preferably, the beam elements are made to a length that is acceptable for transport and are joined on the construction site using, for example, vacuum-assisted resin transfer moulding or slot-in connectors 46 (as shown in Figs. 4 and 5). In the case of the tubular beam elements being slotted into the T connectors, the structural strength of the resulting joint can be increased by applying adhesive between the overlapping surfaces of the connector elements and the beam elements. Once joined, the beam and connector elements form the flexible frame structure that is then placed over the span to be bridged and locked into abutments on either side.
  • Fig. 6 shows an example of a swivel 50 for fixing the frame structure at its ends, usable as the stationary or the movable swivel. The swivel 50 comprises a base 52 and a sleeve portion 54, which is pivotally fixed to the base 52. The sleeve portion 54 is dimensioned such that the first or the second end of the supporting frame may be inserted into it. The base 52 is fixed to a foundation (if it is used as the stationary swivel) or a sliding train (if it is used as the actuatable swivel). Once the frame structure has reached the final curvature and required span, the rotation about the pivot axes of the first and second ends is fixed by blocking the sleeve portion 54 with linchpins 56 and the movable swivel is also fixed to a foundation, e.g. with bolts.
  • Fig. 7 shows a modular composite deck assembly 60 made from FRP beams 62 and slotted FRP sandwich panels 64. When the supporting structure is in place, the deck assembly 60 may be suspended from it by means of cables. Another possibility is to suspend a light deck from the supporting structure before the latter is raised, so that when the arch forms, the deck is automatically lifted into position. Given that the buckling load of an arch depends non-linearly on arch curvature, the arch will initially only be capable of supporting a small fraction of the ultimate buckling load. Therefore, in this case the deck is preferably initially made from a lightweight composite box-beam, which is fitted with the heavy road-surface stratification once the final shape of the arch has been reached.
  • To increase the overall capacity and stability of the supporting structure, the support frame is preferably configured as a hollow formwork, into which concrete may be poured and allowed to set. Such a support frame is illustrated in Fig. 8. The support frame comprises tubular formwork elements 70 having arranged in their interior a steel or fibre-reinforced polymer rebar and stirrups 72. When the support frame is bent during the raising stage, the steel or FRP rebar 72 is forced to follow the curvature of the arch being generated. After the arch has been erected and fixed, the formwork is filled through openings 74, provided in the formwork shell, with concrete 76 or high-strength mortar. Once the concrete 76 or mortar has set, the supporting structure is capable of supporting much higher loads than before. To further enhance the capacity of the supporting structure, a hogging moment may be induced in the set concrete or mortar by a further displacement of the ends of the supporting structure towards one another. However, such further displacement would be much smaller than 1% of the initial distance between the ends because the concrete or mortar would fail otherwise. Filling the formwork with reinforced concrete could increase its buckling capacity by a factor of about 2 to 3, depending on the quality of the concrete or mortar used.
  • As shown in Fig. 9, it is also possible to compose the supporting structure from a plurality of sequential overlapping frame structures (e.g. flat tubes/profiles). Each of the frame structures has a relatively shallow section in the bending direction, so that the distance from the intrados and extrados surfaces to the respective neutral axis are small. Assume that one bends a square-section tube or profile with a height of 1 m in bending direction in such a way that the height-curvature imposes a strain of 3000 microstrain. If one bends a shallower tube or profile having a height of 1/3 m in bending direction to the same curvature, the resulting bending strains are approximately three times smaller. If three such shallow tubes or profiles 80, 82, 84 are placed on top of one another and bent up to the same arch height as the tube of 1 m height, whilst they are allowed to slide along their lengths as they rise up, the buckling capacity of the assembly would only be given by the individual shallow tube or profile sections (which is which is much smaller than the buckling capacity of the 1 m square section tube). If however, the shallow tubes or profiles are joined along their meeting surfaces after they have reached their final shape, the buckling capacity of the assembly becomes approximately the same as that of the 1 m square section tube or profile.
  • The shallow tubes or profiles have each an intrados surface and an extrados surface. As they are progressively bent concomitantly with one another, the intrados surfaces are compressed while the extrados surfaces are stretched, which locally results in relative movement between meeting surfaces, i.e. between the intrados surface 90 of the middle tube or profile and the extrados surface 88 of the lower tube or profile as well as between the extrados surface 92 of the middle tube or profile and the intrados surface 94 of the upper tube or profile. Once the tubes or profiles have reached their final positions, they are fixed to one another by gluing and/or with bolted flanges. Preferably, layers of glue are applied between adjacent meeting surfaces when the shallow tubes or profiles 80, 82, 84 still have their initial shape and the bending is carried out while the glue has not yet set and allows the meeting surfaces to locally slide one with respect to another while they bend. In this case, the layers of glue are simply let set while the shallow tubes or profiles 80, 82, 84 are kept immobile with respect to one another when they have reached their final arched form. Additionally, flanges may be used to bond and bolt the shallow tubes or profiles 80, 82, 84 together. Of course, the assembly of shallow tubes or profiles 80, 82, 84 might serve as a formwork for concrete or mortar, depending on the application.
  • As illustrated in Figs. 10-12, the frame structure to be bent into arch form according to the method of the present invention may be assembled from FRP I-beam elements 98 (sometimes also referred to as H- or double-T-beam elements), assembled together with bolted joints 100. The use of such profiles instead of hollow tubular profiles may be advantageous in case the frame structure of the construction needs not be filled with concrete or mortar.
  • Legend:
  • 10
    Beam
    12
    First end
    14
    Second end
    16
    Pivot axis
    18
    Longitudinal axis
    20
    Stationary swivel
    22
    Movable swivel
    24
    Actuator
    30
    Braced structure
    32
    Longitudinal beam
    34
    Transverse beam
    36
    Diagonal steel bar, rod or cable
    38
    Stationary swivel
    40
    Movable swivel
    42
    Rail
    44
    Arrow
    46
    Slot-in connector
    50
    Swivel
    52
    Base
    54
    Sleeve portion
    56
    Linchpin
    60
    Deck assembly
    62
    FRP beam
    64
    Sandwich panel
    70
    Tubular formwork element
    72
    Rebar and stirrups
    74
    Opening
    76
    Concrete
    80
    Lower shallow tube or profile
    82
    Middle shallow tube or profile
    84
    Upper shallow tube or profile
    86
    Intrados surface of lower tube or profile
    88
    Extrados surface of lower tube or profile
    90
    Intrados surface of middle tube or profile
    92
    Extrados surface of middle tube or profile
    94
    Intrados surface of upper tube or profile
    96
    Extrados surface of upper tube or profile
    98
    I-beam element
    100
    Bolted joint

Claims (14)

  1. Method of constructing a supporting structure in arched form, comprising:
    providing an initially straight or pre-curved frame structure having a first end and
    a second end opposite to said first end, said first and second ends being separated from one another by an initial distance;
    pivotally supporting said first and second ends;
    pushing the first and second ends towards one another to achieve a displacement of said first and second ends relative to one another, thus causing the first and second ends to pivot and said frame structure to progressively and
    flexibly bend against a resiliency thereof into a final arched form, wherein the displacement of said first and second ends relative to one another amounts to at least 1% of the initial distance between said first and second ends; and
    fixing said first and second ends relative to one another in their displaced position so as to preserve the final arched form of said frame structure.
  2. The method according to claim 1, wherein said frame structure comprises fibre-reinforced polymer elements extending from said first end to said second end.
  3. The method according to claim 1 or 2, wherein said frame structure comprises fibre-reinforced polymer formwork and wherein concrete is poured into said formwork when said first and second ends are fixed relative to one another in their displaced position.
  4. The method according to claim 3, wherein said frame structure comprises steel- and/or fibre-reinforced polymer rebar within said formwork.
  5. The method according to any one of claims 1 to 4, wherein said first and second ends are pivotally supported about a first and a second pivot axis, respectively, said first and second pivot axes being substantially parallel to one another and substantially perpendicular to the displacement of said first and second ends relative to one another.
  6. The method according to any one of claims 1 to 5, wherein said pivotally supporting said first and second ends comprises pivotally supporting said first end with a first stationary swivel and pivotally supporting said second end with an actuatable swivel; and wherein pushing the first and second ends towards one another is carried out by said actuatable swivel pushing said second end and said stationary swivel exerting an opposite reaction force on said first end.
  7. The method according to claim 6, wherein said actuatable swivel is guided on rails.
  8. The method according to claim 6 or 7, wherein fixing said first and second ends relative to one another in their displaced position comprises fixing said actuatable swivel in a stationary position.
  9. The method according to any one of claims 1 to 8, wherein the displacement of said first and second ends relative to one another amounts to at least 2%, preferably at least 3%, more preferably at least 5%, possibly even at least 10% or at least 15%, of the initial distance between said first and second ends.
  10. The method according to any one of claims 1 to 9, wherein said bending occurs substantially over the entire length between said first and second ends of said frame structure.
  11. The method according to any one of claims 1 to 9, comprising providing a further initially straight or pre-curved frame structure, hereinafter referred to as the second frame structure, extending alongside the previously cited frame structure, hereinafter referred to as first frame structure, each of the first and second frame structures comprising an intrados surface and an extrados surface;
    causing said second frame structure to progressively bend concomitantly with said first frame structure in such a way that one of the intrados and extrados surfaces of the first frame structure contacts the other of the intrados and extrados surfaces of the second frame structure at the latest when said first frame structure is in its final arched form; and
    fixing said second frame structure to said first frame structure so as to prevent relative movement between them.
  12. The method according to claim 11, wherein said first and second frame structures are fixed to one another by gluing and/or with flanges.
  13. The method according to claim 11 or 12, wherein said second frame structure is of the same configuration as said first frame structure.
  14. The method according to any one of claims 11 to 13, wherein prior to bending, said first and second frame structures are arranged such that one of the intrados and extrados surfaces of the first frame structure is adjacent the other of the intrados and extrados surfaces of the second frame structure, a layer of glue being arranged between the adjacent surfaces, wherein said progressive bending is carried out while said glue has not set so that the first and second frame structures are allowed to slide along their lengths while they bend and wherein said fixing said second frame structure to said first frame structure comprises letting said layer of glue set while keeping said first and second frame structures immobile with respect to one another when said first frame structure is in its final arched form.
EP09159584A 2009-05-06 2009-05-06 Supporting arch structure construction method Withdrawn EP2248948A1 (en)

Priority Applications (7)

Application Number Priority Date Filing Date Title
EP09159584A EP2248948A1 (en) 2009-05-06 2009-05-06 Supporting arch structure construction method
DK10717639.8T DK2427601T3 (en) 2009-05-06 2010-04-30 STØTTEBUESTRUKTUR-DESIGN METHOD
ES10717639.8T ES2627432T3 (en) 2009-05-06 2010-04-30 Support arch structure construction procedure
US13/318,984 US8479473B2 (en) 2009-05-06 2010-04-30 Supporting arch structure construction method
PCT/EP2010/055937 WO2010128002A2 (en) 2009-05-06 2010-04-30 Supporting arch structure construction method
EP10717639.8A EP2427601B1 (en) 2009-05-06 2010-04-30 Supporting arch structure construction method
JP2012508999A JP5690815B2 (en) 2009-05-06 2010-04-30 Support arch structure construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
EP09159584A EP2248948A1 (en) 2009-05-06 2009-05-06 Supporting arch structure construction method

Publications (1)

Publication Number Publication Date
EP2248948A1 true EP2248948A1 (en) 2010-11-10

Family

ID=41066358

Family Applications (2)

Application Number Title Priority Date Filing Date
EP09159584A Withdrawn EP2248948A1 (en) 2009-05-06 2009-05-06 Supporting arch structure construction method
EP10717639.8A Not-in-force EP2427601B1 (en) 2009-05-06 2010-04-30 Supporting arch structure construction method

Family Applications After (1)

Application Number Title Priority Date Filing Date
EP10717639.8A Not-in-force EP2427601B1 (en) 2009-05-06 2010-04-30 Supporting arch structure construction method

Country Status (6)

Country Link
US (1) US8479473B2 (en)
EP (2) EP2248948A1 (en)
JP (1) JP5690815B2 (en)
DK (1) DK2427601T3 (en)
ES (1) ES2627432T3 (en)
WO (1) WO2010128002A2 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103866693A (en) * 2014-03-13 2014-06-18 中石化胜利建设工程有限公司 Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge
CN106760500A (en) * 2017-03-07 2017-05-31 中国五冶集团有限公司 A kind of formwork support structure of hole to be provided top cover construction
CN107217603A (en) * 2017-06-06 2017-09-29 中铁第四勘察设计院集团有限公司 Steel case arch ring vertical turn turning hinge and steel case arch ring vertical turn construction method
CN109468964A (en) * 2018-12-29 2019-03-15 中铁十局集团第二工程有限公司 A kind of rotation swivel construction method and rotation system
FR3080135A1 (en) * 2018-04-12 2019-10-18 Vinci Construction France METHOD AND DEVICE FOR FORMING PVC TUBES
CN111764300A (en) * 2020-07-21 2020-10-13 安徽省交通建设股份有限公司 Curved steel beam pushing system and construction method
CN113186795A (en) * 2021-04-19 2021-07-30 甘肃建投科技研发有限公司 Segmental precast concrete beam chord arch bridge
CN113585100A (en) * 2021-08-10 2021-11-02 中铁九局集团第七工程有限公司 Bridge incremental launching and turning automatic construction method

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2248948A1 (en) * 2009-05-06 2010-11-10 The European Union, represented by the European Commission Supporting arch structure construction method
CA2830108C (en) 2011-03-15 2019-04-16 Coobs Canada Limited A formwork for use in the construction of arched structures and a method of constructing arched structures
US9200462B2 (en) * 2012-06-04 2015-12-01 Meta Stages, Llc Mobile arched telescopic deployable stage system
KR101617720B1 (en) 2015-12-11 2016-05-03 표옥근 Arch-truss bridge having vibration absorbing mean for arch steel pipe
BE1023762B1 (en) * 2016-01-12 2017-07-14 Plakabeton Nv CONSTRUCTION ELEMENT FOR THE CONCLUSION OF A CONNECTION BETWEEN THERMAL INSULATED PARTS OF A BUILDING
US10179979B1 (en) * 2017-07-12 2019-01-15 Tidy Site Services, LLC Bridge span and methods of moving a bridge span
CN108411792A (en) * 2017-12-06 2018-08-17 王阳光 Long span curve T structures bridge is without closure segment rotator construction spatial form control method
RU2690245C2 (en) * 2017-12-15 2019-05-31 Дмитрий Николаевич Парышев Pipe-concrete arch
US10415265B1 (en) * 2018-03-20 2019-09-17 Gang Liang Convertible protective shelter
US10957967B2 (en) 2018-03-21 2021-03-23 Aecom Support structures for transportation systems
IT201800006801A1 (en) * 2018-06-29 2019-12-29 METHOD OF CONSTRUCTION AND DESIGN FOR THE REALIZATION OF A CURVED SELF-SUPPORTING WORK INCLUDING A PLURALITY OF ADJUSTABLE BLOCKS
CN109252683A (en) * 2018-10-31 2019-01-22 中国冶集团有限公司 A kind of lateral arc girder steel distortion downwarp bearing calibration
CN109440623B (en) * 2018-11-20 2023-12-08 湖南工业大学 Temporary splicing structure of precast bridge of concrete segment
CN110029593B (en) * 2019-04-12 2020-12-22 桂林理工大学 Stretching and anchoring device for multilayer prestressed fiber cloth reinforced beam
CN110361318B (en) * 2019-06-04 2020-09-01 浙江大学 Steel bridge deck corrosion fatigue coupling test method and device thereof
CN111767599B (en) * 2020-06-29 2024-02-09 中铁十二局集团有限公司 Direct elastic resistance method applied to initial structural design of tunnel
CN111778875B (en) * 2020-07-27 2021-09-24 山东交通学院 Roller type supporting leg, bridge turning system and construction method
CN112329107B (en) * 2020-11-05 2022-05-06 中铁二院工程集团有限责任公司 Bridge span type bearing structure of cross tunnel proximity region and calculation method
CN117166618B (en) * 2023-09-05 2024-04-19 北京市建筑工程研究院有限责任公司 Arch shell structure system and construction method thereof

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1139528B (en) * 1959-05-19 1962-11-15 Ingenjoers N Invent Aktiebolag Arch bridge
GB1202706A (en) * 1967-05-09 1970-08-19 Edwin Jacques Cohen Arched building members
GB1364900A (en) * 1971-12-10 1974-08-29 Cohen E J Building assembly for the erection of an arched resiliently flexi ble building member
US3899854A (en) * 1973-05-14 1975-08-19 Jon Vredevoogd Method of erection for a pretensioned membrane structure
US4065906A (en) * 1976-06-09 1978-01-03 Stowell Whitney Mears Method and apparatus for constructing buildings
US4143502A (en) 1975-07-14 1979-03-13 Wyche Cyril T Method of erecting a structural arch support
WO1990013715A1 (en) 1989-05-08 1990-11-15 Bsd Structures Pty. Ltd. Lift arch building system
US6108998A (en) 1996-09-30 2000-08-29 Martin Marietta Materials, Inc. Modular polymer matrix composite support structure and methods of constructing same
US6170105B1 (en) 1999-04-29 2001-01-09 Composite Deck Solutions, Llc Composite deck system and method of construction
US6455131B2 (en) 1997-06-02 2002-09-24 West Virginia University Modular fiber reinforced polymer composite deck system
WO2007084803A2 (en) * 2006-01-13 2007-07-26 Hillman John R Hybrid composite beam system

Family Cites Families (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2415240A (en) * 1944-03-10 1947-02-04 Michael A Fouhy Process of erecting large span buildings
US3057119A (en) * 1957-08-09 1962-10-09 Kessler Milton Method of erecting pre-stressed building construction
US3530622A (en) * 1966-05-23 1970-09-29 Edwin Jacques Cohen Building apparatus and method
US3708944A (en) * 1969-10-31 1973-01-09 M Miyake Method of making an arch
US3763618A (en) * 1971-02-22 1973-10-09 Dow Chemical Co Method of preparing arched structures
US4325207A (en) * 1978-04-25 1982-04-20 Canadian Patents & Development Ltd. Arch forming assembly
NO162124C (en) * 1984-06-22 1989-11-08 Arne Engebretsen TREATED BENCH OF WOODWOOD.
AU556275B2 (en) * 1984-11-29 1986-10-30 High Accolade Limited Post-tensioned steel frames and erection of such
US4745718A (en) * 1986-05-30 1988-05-24 Trus Joist Corporation Prestressed structural support and method for making same
JPH11280153A (en) * 1998-03-31 1999-10-12 Mitsubishi Heavy Ind Ltd Arch-shaped structure and its construction method
US6128864A (en) * 1999-09-07 2000-10-10 Barry; Michael A. Elliptical arch
JP4249890B2 (en) * 2000-09-19 2009-04-08 積水化学工業株式会社 Arched cover
EP2248948A1 (en) * 2009-05-06 2010-11-10 The European Union, represented by the European Commission Supporting arch structure construction method

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1139528B (en) * 1959-05-19 1962-11-15 Ingenjoers N Invent Aktiebolag Arch bridge
GB1202706A (en) * 1967-05-09 1970-08-19 Edwin Jacques Cohen Arched building members
GB1364900A (en) * 1971-12-10 1974-08-29 Cohen E J Building assembly for the erection of an arched resiliently flexi ble building member
US3899854A (en) * 1973-05-14 1975-08-19 Jon Vredevoogd Method of erection for a pretensioned membrane structure
US4143502A (en) 1975-07-14 1979-03-13 Wyche Cyril T Method of erecting a structural arch support
US4065906A (en) * 1976-06-09 1978-01-03 Stowell Whitney Mears Method and apparatus for constructing buildings
WO1990013715A1 (en) 1989-05-08 1990-11-15 Bsd Structures Pty. Ltd. Lift arch building system
US6108998A (en) 1996-09-30 2000-08-29 Martin Marietta Materials, Inc. Modular polymer matrix composite support structure and methods of constructing same
US6455131B2 (en) 1997-06-02 2002-09-24 West Virginia University Modular fiber reinforced polymer composite deck system
US6170105B1 (en) 1999-04-29 2001-01-09 Composite Deck Solutions, Llc Composite deck system and method of construction
WO2007084803A2 (en) * 2006-01-13 2007-07-26 Hillman John R Hybrid composite beam system

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103866693A (en) * 2014-03-13 2014-06-18 中石化胜利建设工程有限公司 Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge
CN103866693B (en) * 2014-03-13 2016-04-06 中石化胜利建设工程有限公司 A kind of mounting method of steel concrete bowstring arch bridge arch rib
CN106760500A (en) * 2017-03-07 2017-05-31 中国五冶集团有限公司 A kind of formwork support structure of hole to be provided top cover construction
CN106760500B (en) * 2017-03-07 2023-06-27 中国五冶集团有限公司 Template supporting structure for construction of reserved hole top cover
CN107217603A (en) * 2017-06-06 2017-09-29 中铁第四勘察设计院集团有限公司 Steel case arch ring vertical turn turning hinge and steel case arch ring vertical turn construction method
FR3080135A1 (en) * 2018-04-12 2019-10-18 Vinci Construction France METHOD AND DEVICE FOR FORMING PVC TUBES
CN109468964A (en) * 2018-12-29 2019-03-15 中铁十局集团第二工程有限公司 A kind of rotation swivel construction method and rotation system
CN111764300A (en) * 2020-07-21 2020-10-13 安徽省交通建设股份有限公司 Curved steel beam pushing system and construction method
CN111764300B (en) * 2020-07-21 2022-03-25 安徽省交通建设股份有限公司 Curved steel beam pushing system and construction method
CN113186795A (en) * 2021-04-19 2021-07-30 甘肃建投科技研发有限公司 Segmental precast concrete beam chord arch bridge
CN113585100A (en) * 2021-08-10 2021-11-02 中铁九局集团第七工程有限公司 Bridge incremental launching and turning automatic construction method

Also Published As

Publication number Publication date
JP2012526215A (en) 2012-10-25
ES2627432T3 (en) 2017-07-28
EP2427601A2 (en) 2012-03-14
WO2010128002A2 (en) 2010-11-11
EP2427601B1 (en) 2017-04-05
US20120096804A1 (en) 2012-04-26
WO2010128002A3 (en) 2011-06-16
US8479473B2 (en) 2013-07-09
JP5690815B2 (en) 2015-03-25
DK2427601T3 (en) 2017-06-06

Similar Documents

Publication Publication Date Title
EP2427601B1 (en) Supporting arch structure construction method
KR100423757B1 (en) Prestressed composite truss girder and construction method of the same
CA2762305C (en) Support structure for wind turbines and process for erecting the support structure
US7996944B2 (en) Tilt-lift method for erecting a bridge
US10161090B2 (en) Method for launching/constructing bridge using assembly of precast bottom plate and concrete-filled steel tube truss girder
CN100585082C (en) Assembled bridge building technique based on three steel tube longeron segments
CN101230607B (en) Structure combination parts for hollow slab
CN110205938B (en) Steel pipe arch installation method of through beam-arch combination bridge
EP4172425A1 (en) A structural truss, assembly and method of manufacture
JP4336659B2 (en) Construction method of upper-floor type suspension floor slab bridge
EA006124B1 (en) Doubly prestressed roof-ceiling construction with grid flat-soffit for extremely large spans
WO2019055818A1 (en) Apparatus, systems and methods for repairable precast moment-resisting buildings
CN112761051A (en) Prefabricated ultrahigh-performance concrete arch bridge and construction method thereof
AU2019206009A1 (en) Load bearing structure and sections therefore
GB2591905A (en) A structural truss, assembly and method of manufacture
CN101230677A (en) Force-bearing type template component
WO2022216177A1 (en) Structural element (embodiments)
JP4838329B2 (en) Construction method of upper-floor type suspension floor slab bridge
CN116802359A (en) Composite RCC bridge deck and prestressed parabolic bottom chord underslung type hollow steel girder bridge upper structure
CN117488648A (en) Truss girder-arch combined bridge structure and bridge construction method
CN112942363A (en) Deep basal pit prestressing force steel braced system
CN117513630A (en) Triangular support herringbone space special-shaped arch roof structure and construction method thereof
CN115707841A (en) Large-span beam structure combining arched beam and beam string
KR20110127788A (en) Prestressed concrete composite girder bridge
Ramakrishna et al. Folded-plate hangar roof extension, India

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA RS

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20110511