EP1870172A1 - Strangguss- und walzverfahren für mediumplatte - Google Patents

Strangguss- und walzverfahren für mediumplatte Download PDF

Info

Publication number
EP1870172A1
EP1870172A1 EP06722170A EP06722170A EP1870172A1 EP 1870172 A1 EP1870172 A1 EP 1870172A1 EP 06722170 A EP06722170 A EP 06722170A EP 06722170 A EP06722170 A EP 06722170A EP 1870172 A1 EP1870172 A1 EP 1870172A1
Authority
EP
European Patent Office
Prior art keywords
rolling
billet
continuous casting
streams
roller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP06722170A
Other languages
English (en)
French (fr)
Other versions
EP1870172B1 (de
EP1870172A4 (de
Inventor
Jie Liu
Hao Dong Huang
Long Zhen Li
Xu Yang
Leng Zhang
Yong Gang Ma
Xiao Chun Sha
Yi Kang Sun
Ming Ren Wang
Jie Fu Na
Heng Lu Zhang
Fu Xing Jin
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Angang Steel Co Ltd
Original Assignee
Angang Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Angang Steel Co Ltd filed Critical Angang Steel Co Ltd
Publication of EP1870172A1 publication Critical patent/EP1870172A1/de
Publication of EP1870172A4 publication Critical patent/EP1870172A4/de
Application granted granted Critical
Publication of EP1870172B1 publication Critical patent/EP1870172B1/de
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B1/00Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations
    • B21B1/46Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling metal immediately subsequent to continuous casting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B1/00Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations
    • B21B1/46Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling metal immediately subsequent to continuous casting
    • B21B1/463Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling metal immediately subsequent to continuous casting in a continuous process, i.e. the cast not being cut before rolling
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B13/00Metal-rolling stands, i.e. an assembly composed of a stand frame, rolls, and accessories
    • B21B13/22Metal-rolling stands, i.e. an assembly composed of a stand frame, rolls, and accessories for rolling metal immediately subsequent to continuous casting, i.e. in-line rolling of steel
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B37/00Control devices or methods specially adapted for metal-rolling mills or the work produced thereby
    • B21B37/46Roll speed or drive motor control
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B45/00Devices for surface or other treatment of work, specially combined with or arranged in, or specially adapted for use in connection with, metal-rolling mills
    • B21B45/02Devices for surface or other treatment of work, specially combined with or arranged in, or specially adapted for use in connection with, metal-rolling mills for lubricating, cooling, or cleaning
    • B21B45/0203Cooling
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D11/00Continuous casting of metals, i.e. casting in indefinite lengths
    • B22D11/12Accessories for subsequent treating or working cast stock in situ
    • B22D11/1206Accessories for subsequent treating or working cast stock in situ for plastic shaping of strands
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B15/00Arrangements for performing additional metal-working operations specially combined with or arranged in, or specially adapted for use in connection with, metal-rolling mills
    • B21B2015/0057Coiling the rolled product
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B45/00Devices for surface or other treatment of work, specially combined with or arranged in, or specially adapted for use in connection with, metal-rolling mills
    • B21B45/02Devices for surface or other treatment of work, specially combined with or arranged in, or specially adapted for use in connection with, metal-rolling mills for lubricating, cooling, or cleaning
    • B21B45/0203Cooling
    • B21B45/0209Cooling devices, e.g. using gaseous coolants
    • B21B45/0215Cooling devices, e.g. using gaseous coolants using liquid coolants, e.g. for sections, for tubes
    • B21B45/0218Cooling devices, e.g. using gaseous coolants using liquid coolants, e.g. for sections, for tubes for strips, sheets, or plates

Definitions

  • the application belongs to metallurgical metal processing field, more specifically relates to a continuous casting and rolling process for medium plate.
  • the traditional process comprise continuous casting thick billet with thickness of 200mm ⁇ 250mm, flame cutting, heating by walking-beam furnace, descaling, rolling by rough rolling group, shearing, descaling, rolling by finishing rolling train, stream cooling, coiling.
  • the CSP process comprises continuous casting thin billet with thickness of 50mm ⁇ 70mm, flame cutting, heating by tunnel furnace, descaling, rolling by finishing rolling train, stream cooling, coiling.
  • the ASP process has advantages of low cost, low investment, flexible production organization, simple maintaining, and low accident rate. But it still has disadvantages, for example, it uses too many old devices, the power of the motor of finishing rolling train is low, the speed of the roller table is low, the capacity of water supply is not enough, the strength of rolling mills' transmission system is not enough, the configuration of the power supply system is aging and so on. Therefore, the development of the technology is more or less limited, resulting that output can't reach requirement and the production development also be limited, and further the width precision, surface quality and shape control have certain limitation.
  • the invention is aimed at eliminating the disadvantages of the above plate production process.
  • the objects of the invention is to enhancing some crucial technique so as to save energy, not only improving the heating quality of billet but also improving the uniformity of plate thickness and quality of plate shape.
  • the invention has advantage of high width precision, improves the work rate and output of the rolling mill, and makes the continuous casting and rolling process for medium plate meet the requirement of modem manufacturing.
  • the production process of the invention substantially employs that of 02132970.2, and also makes some improvements basing on the former process, so as to improve the production capacity of the invention, broaden the range of the production categories, and meanwhile gain new revolution in the fields of shape control, width precision control and surface quality control.
  • the invention also can realize direct rolling of some steel grades.
  • the solution of the invention is a continuous casting and rolling process for medium plate comprising the following steps:
  • the exiting roller tables are covered by insulating covers, such that the temperature drop of the casting billet and the temperature difference between the intermediate billet's head and tail are reduced and the temperature of the billet when entering the finishing rolling mill can be increased by 30 °C ⁇ 50 °C and the temperature difference between the billet's head and tail can be decreased by 30°C ⁇ 50°C..
  • the vertical roller of the front and back vertical rollers provided in the rough rolling mill is top-attaching driven type, the size of rollers is ⁇ 1200mm/ ⁇ 1100mm ⁇ 430mm, and the power of main motor is AC1200kW X 2X 200/400r/min.
  • the vertical roller of the vertical rollers provided before F1 is top-driven attached type, the size of rollers is ⁇ 750mm/ ⁇ 600mm ⁇ 350mm, and the main drive motor is 2-AC 370kW X 550r/min.
  • hydraulic low-inertia kinks are provided between the finishing rolling stands in order to control tension between finishing rolling train and improve plate quality.
  • the cooling device is provided with 12 sets of online high-level water tank with a water amount of 1700m 3 /h and a water pressure of 0.05Mpa ⁇ 0.08Mpa.
  • Said mold is a mold for billet continuous casting which has a cavity whose four corners are in form of right angle or round angle or straight bevel angle
  • the right angle mold is traditional billet mold which is composed by two wide sidewalls and two narrow sidewalls with a right angle being formed between respective wide sidewall and narrow sidewall
  • the round angle or straight bevel angle mold for billet continuous casting is composed by two wide sidewalls and two narrow sidewalls, at both sides of each narrow sidewall, namely the inner sides connected with the wide sidewalls, respectively have a row of right-triangle shaped flange, the bevel of which directs to inside, one right-angle surface joins to the inner surface of the narrow sidewalls, and another right-angle surface is in the same plane with the side face of the narrow sidewalls, namely the another right-angle surface is an extension of the side face of the narrow sidewalls.
  • said four-streams-merging-one technique optimizes logistics in three walking-beam furnaces with cushioning zone into which the medium plate in single roller table of two casters with four streams is directly fed, so as to exert the producing capacity of caster, furnace and rolling line and realize half-rigid connection of rolling line, furnace and caster.
  • Said three kinds of timing control are:
  • the invention has the following advantages:
  • the invention improves the continuous casting and rolling process for medium/thin plate in terms of layout, devices and production process, so that the production ability, development of new grades, production quality are improved with the present invention, production capacity reaches 5000,000t per year, width precision within 0 ⁇ 10mm reaches 98.5%, the adjustment ability for shape control and crown control reaches advanced world standard, control ability of surface quality fully reaches the quality standard requirements of automobile's high grade panel (05), and the proportion of thin plate reaches advanced world standard.
  • the invention applies to a continuous casting and rolling process for 2150 medium plate.
  • Molten steel passes through three 250t top-bottom blowing converter, two molten iron desulphurizing and slag skimming station, two LF ladle furnace and one RH-TB vacuum processing device, and before being cast, it may be refined by LF ladle furnace or RH-TB vacuum processing device.
  • Continuous casting molten steel passes through mold, to form continuous casting billet having section thickness of 100mm-170mm, width of 900-2000mm and length of 11m ⁇ 18m by hydraulic oscillating, continuously bending and continuously straightening, and then the billet is subjected to flame cutting.
  • the billet has a maximum single weight of 38t, the average number of continuously casting furnaces is 30, and the average casting time is 37.3 minute per one furnace. Because of employing the technique of mold hydraulic oscillating, the quality of casting billet can be improved and also the billet surface defect can be eliminated.
  • Direct rolling, hot feeding and hot charging by two casters with four streams and four-streams-merging-one technique in which each of the two continuous casters' knockout roller tables respectively connects with entering roller table and exiting roller table of heating furnace, achieving rapid hot feeding and hot charging or direct rolling for continuous casting billet; continuous casting billet is fed to entering roller table of heating furnace through convey roller table, then fed into walking-beam furnace by long-course steel loader of the heating furnace in order to be heated.
  • the invention uses direct rolling technique for some kinds of carbon steel and certain kinds of lower alloy steel.
  • the exiting roller table of the continuous caster connects with the entering roller table of the heating furnace so that the continuous casting billet is directly fed into the heating furnace by the roller table for hot charging.
  • the hot charging temperature averagely is no less than 700°C.
  • One exiting roller table of the continuous caster connects with the exiting roller table of the heating furnace.
  • its length is automatically measured and also its temperature is measured by pyrometer, in order that the billet can be centered according the layout and then be heated.
  • a computer is used to optimize the heating control based on the temperature of the billet entering the furnace.
  • the billets are heated to 1150°C ⁇ 21250°C in the furnace, carried out of the furnace by the extractor of the furnace, and placed on the exiting roller table. This can not only save energy, but also shorten heating time and improve heating quality of the billet.
  • Some kinds of carbon steel and certain kinds of lower alloy steel, for example silicon steel may apply "lower temperature exiting" rolling technique, realizing rolling of different steel grades.
  • the long-course steel loader used in the present invention not only makes the furnace having the ability of heating billet but also has the cushion ability for matching continuous casting and rolling pace. If the rolling mill temporarily halts for a short while, it at most can store nine cushioning billets, therefore the casting production is not affected.
  • the four-streams-merging-one technique optimizes logistics in three walking-beam furnaces with cushioning zone into which the medium plate in single roller table of two casters with four streams is directly fed, so as to exert the producing capacity of caster, furnace and rolling line and realize half-rigid connection of rolling line, furnace and caster.
  • Said three kinds of timing control are:
  • Rough rolling the heated or direct rolled billet is conveyed by roller tables and passes through high-pressure water descaling box after the furnace so as to remove scale, and then enters into four-roller reversible rough rolling mill so as to be rolled.
  • the four-roller reversible rough rolling mill has attached front and back vertical rollers with a type of top-attaching driven.
  • the size of rollers is ⁇ 1200/ ⁇ 1100mm X 430mm, the maximum single-pass side-pressing amount is 50mm, the maximum rolling pressure is 3800kN, the rolling speed is 0 ⁇ 5.89m/s, and the power of main motor is AC1200kW X 2 X 200/400r/min.
  • the front and back vertical rollers of the four-roller reversible rough rolling mill are provided with automatic width control system (AWC), its main purpose being to correct error of billet width caused by rolling pressure change and correct the width difference between the billet's head and tail.
  • Width gage and pyrometer are provided after the four-roller reversible rough rolling mill, so as to monitor width and temperature of billet and provide correction data for setting of finishing rolling mill.
  • the four-roller reversible rough rolling mill is also provided with dust removal device.
  • Insulating cover is provided at the exiting roller table in order to reduce temperature drop of intermediate billet and temperature difference between the billet's head and tail.
  • Intermediate billet is conveyed to truncate scissor via insulating cover so as to truncate its head and tail.
  • Detector is provided in front of the truncate scissor in order to detect the shape of the billet's head, so as to reduce temperature drop of intermediate billet and temperature difference between the billet's head and tail, and also the temperature at the time of entering finishing rolling mill can be improved by 30°C ⁇ 50°C and the temperature difference between the billet's head and tail can be shorten by 30°C ⁇ 50°C. Therefore, it can realize the optimal truncation of the scissor, in order to reduce truncation loss and increase yield.
  • Edge heater is provided in front of the scissor.
  • the heater's parameters are as follows: the power of the main motor is 2 X 3000kW, the heating depth is 40mm ⁇ 60mm, the heating width is 100mm ⁇ 150mm, and the temperature rise is 60 °C ⁇ 100°C. This helps to improve temperature uniformity of the billet, reduce edge crack, and improve mischcrystal of edge microstucture. Also this helps to stabilize operation of the finishing rolling mill, and simultaneously this can satisfy the requirement of dual phase steel development.
  • the billet After being truncated head and tail, the billet enters into the high-pressure water descaling box before finishing rolling mill in order to remove regeneration scale.
  • billet passes through the small vertical roller device F 1 E before finishing rolling mill F 1 so as to be rolled.
  • the maximum pressing amount is 10mm
  • the maximum rolling pressure is 1000kN
  • the main driving motor is 2-AC 370kW X 550r/min.
  • the billet is rolled into 1.8mm ⁇ 25.4mm final plate.
  • F1 ⁇ F7 finishing rolling train all employ a device for axial shifting and bending working roller, the maximum shifting course is ⁇ 200mm, and the bending force is 1500kN.
  • F3 ⁇ F6 in ASP have the device for axial shifting and bending working roller, and bending force only has positive value, no negative value.
  • This not only can control thickness difference of plate section (crown and wedge) and plate flatness, but also can realize free rolling and increase rolling yield.
  • the production line uses hydraulic low-inertia kink in order to control tension between finishing rolling train and improve plate quality.
  • Stream cooling it uses three-stage stream cooling technique, in which roughly adjusting valve set and precisely adjusting valve set as well as 12 sets of online high-level water tank are provided, so as to stabilize water amount and water pressure of each cooling stage.
  • the water amount is 1700m 3 /h
  • the water pressure is 0.05Mpa ⁇ 0.08Mpa
  • the side water-jet pressure is 1Mpa ⁇ 1.2Mpa, so as to assure the plate's lengthwise temperature uniformity.
  • Coiling it uses stepping-controlled full hydraulic coiler to coil plate, in which automatic stepping control is performed by hydraulic-controlled side guide, pinch roller, wrapper roller's collapsible reels and high-responsivity wrapper roller to realize precise centering and micro-tension coiling of plate, reduce towered-shape, avoid the impaction of plate's head on wrapper roller and eliminate impression of plate's head and wrapper roller on plate
  • the automatic system of the production line is three-grade computer control system, the first grade being basic automatic system, the second grade being procedure control computer system and the third grade being production control computer system.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Metal Rolling (AREA)
EP06722170A 2005-03-28 2006-03-27 Strangguss- und walzverfahren für mediumplatte Expired - Fee Related EP1870172B1 (de)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CNA2005100461333A CN1840252A (zh) 2005-03-28 2005-03-28 中厚板坯连铸连轧板卷的生产工艺
PCT/CN2006/000518 WO2006102835A1 (fr) 2005-03-28 2006-03-27 Procede de coulage et de laminage en continu d’une tole moyenne

Publications (3)

Publication Number Publication Date
EP1870172A1 true EP1870172A1 (de) 2007-12-26
EP1870172A4 EP1870172A4 (de) 2009-01-14
EP1870172B1 EP1870172B1 (de) 2011-07-06

Family

ID=37029543

Family Applications (1)

Application Number Title Priority Date Filing Date
EP06722170A Expired - Fee Related EP1870172B1 (de) 2005-03-28 2006-03-27 Strangguss- und walzverfahren für mediumplatte

Country Status (6)

Country Link
EP (1) EP1870172B1 (de)
KR (1) KR100960096B1 (de)
CN (1) CN1840252A (de)
AT (1) ATE515334T1 (de)
AU (1) AU2006228889B2 (de)
WO (1) WO2006102835A1 (de)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101941024A (zh) * 2010-07-22 2011-01-12 河北省首钢迁安钢铁有限责任公司 一种消除热连轧过程中if钢边部翘皮的方法
CN102367546A (zh) * 2011-10-28 2012-03-07 首钢总公司 一种船板表面耐海岸大气腐蚀氧化铁皮的控制方法
CN103480649A (zh) * 2013-10-12 2014-01-01 钢铁研究总院 一种直接轧制生产长型材的方法
CN103862248A (zh) * 2014-03-19 2014-06-18 德龙钢铁有限公司 一种有效预防热轧过程头尾表面缺陷产生的方法
US9289807B2 (en) 2010-10-12 2016-03-22 Siemens Vai Metals Technologies Gmbh Energy and yield-optimized method and plant for producing hot steel strip
US9296027B2 (en) 2010-10-12 2016-03-29 Siemens Vai Metals Technologies Gmbh Method and plant for the energy-efficient production of hot steel strip
CN106583466A (zh) * 2016-12-14 2017-04-26 四川德胜集团钒钛有限公司 一种轧钢热送热装工艺

Families Citing this family (35)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100441724C (zh) * 2006-12-18 2008-12-10 马鞍山钢铁股份有限公司 薄板坯连铸连轧生产热轧双相钢的工艺
CN101209456B (zh) * 2006-12-27 2010-11-03 鞍钢股份有限公司 一种高强度中厚钢板生产方法
CN101293258B (zh) * 2007-04-25 2010-12-01 宝山钢铁股份有限公司 中薄板坯连铸连轧生产热轧带钢的方法
CN101306499B (zh) * 2008-06-23 2010-06-09 秦皇岛首秦金属材料有限公司 高炉炉壳用钢板的生产方法
CN101619384B (zh) * 2008-06-30 2012-09-26 鞍钢股份有限公司 步进式加热炉动梁自动踏步的烧钢方法
CN101428386B (zh) * 2008-11-06 2012-02-01 杭州钢铁集团公司 GCr15套圈冷冲成型方法
CN102102141B (zh) * 2009-12-22 2013-12-11 鞍钢股份有限公司 改善取向硅钢板组织均匀性的热轧工艺
JP5616817B2 (ja) * 2011-02-18 2014-10-29 東芝三菱電機産業システム株式会社 熱間圧延ラインの制御装置
CN103029010B (zh) * 2011-09-30 2015-12-02 宝山钢铁股份有限公司 一种金属板带的紧凑型生产工艺布置
CN103071973A (zh) * 2012-12-17 2013-05-01 福建宝达钢业有限公司 端板卷绕加工工艺
CN103882203A (zh) * 2012-12-21 2014-06-25 鞍钢股份有限公司 一种提高硅钢电磁性能的热轧方法
CN103302106B (zh) * 2013-07-09 2015-04-08 济钢集团有限公司 提升轧制过程中厚规格钢板平直度方法及其控制方式
CN103551394B (zh) * 2013-11-06 2015-11-18 北京首钢股份有限公司 一种低硅无取向硅钢厚度轮廓边部反翘的控制方法
CN104048846B (zh) * 2014-06-27 2016-08-17 安徽马钢和菱实业有限公司 中厚板火焰切割取样装置及其取样方法
CN106269871B (zh) * 2016-08-30 2017-12-08 武汉钢铁有限公司 一种在CSP产线采用升速轧制工艺生产厚度≤2.0mm低强度带钢的方法
CN106734252B (zh) * 2016-12-14 2019-01-04 四川德胜集团钒钛有限公司 一种板坯热送工艺
CN108941494B (zh) * 2018-09-25 2020-07-07 湖南华菱湘潭钢铁有限公司 一种中厚板连铸坯的热送热装工艺
CN109663819A (zh) * 2018-11-19 2019-04-23 包头钢铁(集团)有限责任公司 一种减小厚规格钢板长度方向头尾异形量的方法
CN109732050B (zh) * 2019-03-06 2023-11-03 南京钢铁股份有限公司 一种连铸机切前辊道冷却***
CN110280589A (zh) * 2019-07-31 2019-09-27 江苏省沙钢钢铁研究院有限公司 厚钢板及其轧制方法
CN111286576A (zh) * 2020-03-26 2020-06-16 山东泰山钢铁集团有限公司 一种弧度倒角结晶器连铸机生产不锈钢板坯的方法
CN111363900B (zh) * 2020-04-26 2021-11-16 陕西理工大学 一种介观尺度结构碳素钢及其制备方法
CN111702010B (zh) * 2020-06-23 2022-03-11 中冶赛迪工程技术股份有限公司 一种连铸连轧的薄带生产工艺
CN112122344B (zh) * 2020-09-09 2022-09-06 山西云时代太钢信息自动化技术有限公司 一种大断面铸坯热送热装的***平台
CN112692061A (zh) * 2020-12-09 2021-04-23 本钢板材股份有限公司 提高钢板表面质量的热轧方法
CN113634605B (zh) * 2021-08-25 2023-02-28 重庆钢铁股份有限公司 基于视觉识别的中厚板待轧钢板自动分钢控制***及方法
CN114472547B (zh) * 2022-02-08 2024-02-13 南京钢铁股份有限公司 一种轧制过程中头尾角部裂纹的控制方法
CN114632818B (zh) * 2022-03-14 2023-12-05 安阳钢铁股份有限公司 一种减少取向硅钢热轧边裂的工艺方法
CN114535317B (zh) * 2022-03-14 2023-12-29 武汉钢铁有限公司 一种提高短流程热轧无取向硅钢楔形精度的方法
CN114618895B (zh) * 2022-04-11 2022-11-08 福建三宝特钢有限公司 基于动态调节的热轧带轧制***
CN114798739B (zh) * 2022-04-29 2023-03-10 山东钢铁集团永锋临港有限公司 一种连铸多流16m小方坯多切分直轧棒材的方法
CN114713631B (zh) * 2022-05-18 2024-01-12 首钢长治钢铁有限公司 一种轧制生产***集成
CN114951581B (zh) * 2022-06-30 2023-08-15 山东钢铁集团永锋临港有限公司 一种小方坯热送自动控制方法
CN115323160B (zh) * 2022-08-30 2023-07-28 宝武集团鄂城钢铁有限公司 提高连铸坯热装比的方法及***
CN115846424B (zh) * 2022-11-15 2023-07-28 郑州大学 一种用于高通量连铸连轧铝合金板材温度控制装置及工艺

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5430930A (en) * 1993-10-12 1995-07-11 Italimpianti Of America, Inc. Method of manufacturing hot strip
US5564178A (en) * 1993-09-10 1996-10-15 Kyoei Steel Ltd. Process of producing a hot coil and a production system of producing the same
US5991991A (en) * 1995-07-31 1999-11-30 Mannesmann Aktiengesellschaft High-speed thin-slabbing plant

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2649918B1 (fr) * 1989-07-19 1994-06-10 Lorraine Laminage Lingotiere a plaques pour la coulee continue de metal
JP3174457B2 (ja) * 1994-05-17 2001-06-11 株式会社日立製作所 連鋳直結熱間圧延設備およびその圧延方法
JPH09192705A (ja) * 1996-01-18 1997-07-29 Mitsubishi Heavy Ind Ltd 熱間圧延ライン
JP3646627B2 (ja) * 2000-06-13 2005-05-11 Jfeスチール株式会社 鋼板の製造方法
CN1216700C (zh) * 2002-09-19 2005-08-31 鞍钢集团新钢铁有限责任公司 热轧带钢三段层流冷却工艺
CN1189256C (zh) * 2002-09-19 2005-02-16 鞍钢集团新钢铁有限责任公司 中薄板坯连铸连轧板卷的生产方法
US6884838B2 (en) * 2003-02-20 2005-04-26 Johns Manville International, Inc. Water repellant fiberglass binder

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5564178A (en) * 1993-09-10 1996-10-15 Kyoei Steel Ltd. Process of producing a hot coil and a production system of producing the same
US5430930A (en) * 1993-10-12 1995-07-11 Italimpianti Of America, Inc. Method of manufacturing hot strip
US5991991A (en) * 1995-07-31 1999-11-30 Mannesmann Aktiengesellschaft High-speed thin-slabbing plant

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of WO2006102835A1 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101941024A (zh) * 2010-07-22 2011-01-12 河北省首钢迁安钢铁有限责任公司 一种消除热连轧过程中if钢边部翘皮的方法
CN101941024B (zh) * 2010-07-22 2012-06-27 河北省首钢迁安钢铁有限责任公司 一种消除热连轧过程中if钢边部翘皮的方法
US9289807B2 (en) 2010-10-12 2016-03-22 Siemens Vai Metals Technologies Gmbh Energy and yield-optimized method and plant for producing hot steel strip
US9296027B2 (en) 2010-10-12 2016-03-29 Siemens Vai Metals Technologies Gmbh Method and plant for the energy-efficient production of hot steel strip
CN102367546A (zh) * 2011-10-28 2012-03-07 首钢总公司 一种船板表面耐海岸大气腐蚀氧化铁皮的控制方法
CN103480649A (zh) * 2013-10-12 2014-01-01 钢铁研究总院 一种直接轧制生产长型材的方法
CN103480649B (zh) * 2013-10-12 2016-10-05 钢铁研究总院 一种直接轧制生产长型材的方法
CN103862248A (zh) * 2014-03-19 2014-06-18 德龙钢铁有限公司 一种有效预防热轧过程头尾表面缺陷产生的方法
CN106583466A (zh) * 2016-12-14 2017-04-26 四川德胜集团钒钛有限公司 一种轧钢热送热装工艺

Also Published As

Publication number Publication date
KR100960096B1 (ko) 2010-05-31
AU2006228889B2 (en) 2009-08-27
KR20070112879A (ko) 2007-11-27
AU2006228889A1 (en) 2006-10-05
WO2006102835A1 (fr) 2006-10-05
EP1870172B1 (de) 2011-07-06
CN1840252A (zh) 2006-10-04
ATE515334T1 (de) 2011-07-15
EP1870172A4 (de) 2009-01-14

Similar Documents

Publication Publication Date Title
EP1870172B1 (de) Strangguss- und walzverfahren für mediumplatte
CN101391264B (zh) 一种薄中板连铸连轧生产的工艺方法
CN1189256C (zh) 中薄板坯连铸连轧板卷的生产方法
CN100438997C (zh) 紧凑型中宽带钢生产工艺
CN1972764A (zh) 连铸与轧制之间非连续金属板片制造过程及***
EP0594828B1 (de) Verfahren und anlage zum stranggiessen von brammen mittlerer dicke und zum unmittelbar nachfolgenden herstellen von warmbändern und -blechen
KR101809108B1 (ko) 열간 강 스트립의 에너지 효율적인 제조를 위한 방법 및 플랜트
CN110116135B (zh) 一种棒线材产品无头轧制生产方法
CN106552831A (zh) 一种薄规格热轧带钢的制造方法
CN105665443B (zh) 一种宽厚板轧机生产极限规格管线钢的轧制工艺
CN101658860A (zh) 一种薄板坯连铸连轧生产线
RU2166387C2 (ru) Установка для изготовления горячекатаной стальной ленты
EP0662358A1 (de) Verfahren und Anlage zum Stranggiessen von Braumen mittlerer Dicke und zum unmittelbar nachfolgenden Herstellen von Warmbänder und -blechen
WO1993023182A9 (en) Method and apparatus for intermediate thickness slab caster and inline hot strip and plate line
CN101293257A (zh) 一种利用紧凑式连铸连轧工艺生产热轧带钢的方法
CN101811136A (zh) 一种镁合金宽板铸轧设备
EP0655288A1 (de) Verfahren zum Stranggiessen und Verfahren zum Stranggiessen/Walzen von Stahl
CN109821903A (zh) 高强钢热轧板形的控制方法
CN108941196B (zh) 一种以200大断面方坯连续轧制小规格棒材的方法
CN103276286B (zh) 一种6~10mm的X80管线钢带生产方法
CN1978080A (zh) 一种带钢生产工艺-esp
CN101653779B (zh) 一种热轧带钢生产工艺-ehsp及方法
CN103764305B (zh) 用于生产轧制产品的方法及设备
CN107639116A (zh) 一种连铸生产线
CN109092895B (zh) 一种钢筋连铸连轧***以及钢筋连铸连轧生产方法

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20071001

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT DE FR IT TR

DAX Request for extension of the european patent (deleted)
RBV Designated contracting states (corrected)

Designated state(s): AT DE FR IT TR

A4 Supplementary search report drawn up and despatched

Effective date: 20081215

17Q First examination report despatched

Effective date: 20090311

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT DE FR IT TR

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602006022918

Country of ref document: DE

Effective date: 20110825

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: TR

Payment date: 20120105

Year of fee payment: 7

26N No opposition filed

Effective date: 20120411

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602006022918

Country of ref document: DE

Effective date: 20120411

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20140325

Year of fee payment: 9

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20140313

Year of fee payment: 9

Ref country code: AT

Payment date: 20140327

Year of fee payment: 9

Ref country code: IT

Payment date: 20140319

Year of fee payment: 9

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602006022918

Country of ref document: DE

REG Reference to a national code

Ref country code: AT

Ref legal event code: MM01

Ref document number: 515334

Country of ref document: AT

Kind code of ref document: T

Effective date: 20150327

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150327

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

Effective date: 20151130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151001

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150327

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150331

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150327