DE539577C - Bedding machine for track renewal taking place in flow work - Google Patents

Bedding machine for track renewal taking place in flow work

Info

Publication number
DE539577C
DE539577C DE1930539577D DE539577DD DE539577C DE 539577 C DE539577 C DE 539577C DE 1930539577 D DE1930539577 D DE 1930539577D DE 539577D D DE539577D D DE 539577DD DE 539577 C DE539577 C DE 539577C
Authority
DE
Germany
Prior art keywords
track
ballast
bedding
old
long
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DE1930539577D
Other languages
German (de)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Application granted granted Critical
Publication of DE539577C publication Critical patent/DE539577C/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B27/00Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
    • E01B27/06Renewing or cleaning the ballast in situ, with or without concurrent work on the track
    • E01B27/11Renewing or cleaning the ballast in situ, with or without concurrent work on the track combined with concurrent renewal of track components

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Description

Bettungsmaschine für in Fließarbeit stattfindenden Gleisumbau Die Erfindung bezieht sich auf Bettungsmaschinen für in Fließarbeit stattfindenden Gleisumbau. Die Auswechselung eines Eisenbahngleises sowie die gleichzeitge Erneuerung der Bettung im Fließverfahren unter ausschließlicher Benutzung des auszuwechselnden Gleises bieten bei den bisher bekannten Verfahren und Einrichtungen insofern wesentliche Schwierigkeiten, als die Fördergefäße, welche den Neuschotter vom in der Umbaurichtung rückliegenden Bahnhof anbringen, an der Arbeitsstelle über die Schottermaschine im Rahmen des Lichtraumprofiles hinweggeführt werden müssen, um auf der anderen Seite die ausgegrabenen Bettungsstoffe aufzunehmen und nach dem vorliegenden Bahnhof weiterzubefördern. Bei der bisher üblichen Form der Schottermaschinen,welche mit ihren Grabeinrichtungen und Sieben sowie den zugehörigen Förderbändern den größten Teil des Lichtraumprofiles ausfüllten, verblieb nur oberhalb ein verhältnismäßig kleiner Raum zum Durchführen der Fördergefäße,. Diese konnten daher nur die Form von ziemlich niedrigen Kübeln mit verhältnismäßig geringem Fassungsraum erhalten.Bedding machine for track renewal taking place in continuous work The invention relates to bedding machines for track renewal taking place in continuous work. The replacement of a railway track and the simultaneous renewal of the bedding in the flow process with exclusive use of the track to be replaced offer essentials in the previously known processes and facilities Difficulties, as the conveyor vessels, which the new ballast from in the conversion direction Attach the rear station, at the work site over the ballast machine must be led away within the framework of the clearance profile in order to be on the other Page to pick up the excavated bedding material and to the present station to be promoted. With the previously usual form of ballast machines, which with Their grave facilities and sieves as well as the associated conveyor belts are the largest Filled part of the clearance profile, only a proportionate remained above small space for feeding through the conveying vessels. These could therefore only be the shape Obtained from fairly low pots with a relatively small capacity.

Diese Kübel bedingen aber die eingangs erwähnten Schwierigkeiten beim Gleisumbau, weil sie zwischen den beiden Bahnhöfen nur mit Hilfe besonders anzusetzender Laufrollen auf dem neu verlegten bzw. auf dem aufzunehmenden alten Gleise verfahren werden können und weil es ferner notwendig ist, die Kübel auf dem rückliegenden Bahnhof aus Eisenbahnwagen mit Neuschotter zu füllen und auf dem vorliegenden Bahnhof die alten Bettungsstoffe in Eisenbahnwagen umzuladen. Außerdem müssen die Kübel jedesmal vom vorliegenden zum rückliegenden Bahnhof leer zurückgebracht werden. Diese Arbeiten werden ganz besonders umfangreich und kostspielig, wenn die ganze alte Bettung durch neue Bettung ersetzt werden soll, was neuerdings angestrebt wird, um die alten Bettungsstoffe in ortsfesten Anlagen gründlich durchsieben und auswaschen zu können. In diesem Falle sind an -der Baustelle große Bettungsmengen zu befördern und demzufolge bei Anwendung der bekannten Umbauverfahren sehr viele Förderkübel zu bedie^en und zu bewegen.However, these buckets cause the difficulties mentioned at the beginning Track renewal, because between the two stations only with the help of extra attachments Move the rollers on the newly laid or on the old track to be added and because it is also necessary to put the buckets on the back To fill the station from railway wagons with new ballast and to the present station to reload the old bedding material in railroad cars. In addition, the buckets must each time they are brought back empty from the present station to the one behind. This work becomes particularly extensive and costly when the whole old bedding is to be replaced by new bedding, which is currently the aim, to thoroughly sift through and wash out the old bedding materials in fixed systems to be able to. In this case, large quantities of ballast must be transported to the construction site and consequently a large number of buckets when using the known conversion methods to operate and move.

Durch die im folgenden näher beschriebene neuartige Bettungsmaschine werden die vorstehend geschilderten Mängel im wesentlichen dadurch vermieden, daß bei dieser Maschine die Möglichkeit besteht, durch sie hindurch Fernzugbahnwagen von der Neugleisseite zur Altgleisseite überzuleiten.With the new bedding machine described in more detail below the deficiencies outlined above are essentially avoided in that With this machine there is the possibility of long-distance train carriages through it from the new track side to the old track side.

Auf der Zeichnung ist ein Ausführungsbeispiel des Erfindungsgegenstandes schematisch dargestellt, und zwar zeigt Abb. i die Seitenansicht der Bettungsmaschine mit einem üblichen Fernzugschotterwagen, der von dieser aus mit Altschotter gefüllt wird, Abb. z die entsprechende Stirnansicht der Bettungsmaschine, Abb. 3 den mit Altschotter beladenen Fernzugschotterwagen, wie er auf das noch liegende Gleis abgesetzt wind, und Abb. 4 die zu Abb. 3 gehörige Vorderansicht. Auf demAusgangsbahnhofA (nichtgezeichnet) ist der Umbauzug zusammengestellt. In .der Arbeitsrichtung hinter der Bettungsmaschine i sind Fernzugschotterwagen 2 und hinter diesen auf auswechselbaren Schienenrädern fahrbare Gleisrahmen angeordnet. Der Umbauzug fährt auf dem Neugleis zur Umbaustelle C. Dort bewegt sich die auf dem Streckengleis3 mittels auswechselbaren Schienenrädern beigeführte Bettungsmaschine i auf Raupenbändern 5 weiter und beginnt ihre Arbeit, nachdem sie vom neuen Streckengleis 3 abgerollt ist und nachdem bereits während des Heranfahrens des Bauzuges genügend viele Gleisrahmen des alten Streckengleises 3 ausgerollt und zu beiden Seiten der gleislosen Umbaustelle C bis zur Bettungsmaschine i auf dem von der Altbettung abgedeckten Erdkörper seitliche Hilfsschienen 7 verlegt worden sind (Abb. i). Fahrbar auf den seitlichen Hilfsschienen? sind sogenannte Beifuhrrollböcke 8, deren Plattform in Höhe des Streckengleises 3 liegt und auf deren jedem eine Achse der Fernzugschotterwagen 2 ruhen kann. Sobald der Fernzugschotterwagen2 am Ende des neuen Streckengleises angekommen ist, wird er auf zwei solcher Beifuhrrollböcke 8 auf den Hilfsschienen 7 bis vor die Bettungsmaschine i gefahren und auf diesem Wege an der jeweils in Betracht kommenden Stelle entleert. Ist der Fernzugschotterwagen 2 entleert und bis zur Bettungsmaschine i herangefahren, so wird er von den Beifuhrrollböcken 8 über ein ansteigendes Gleis 14 in der Bettungsmaschine i geschoben.The drawing shows an embodiment of the subject matter of the invention shown schematically, namely Fig. i shows the side view of the bedding machine with a standard long-distance train ballast wagon, which is filled with old ballast from here is, Fig.z the corresponding front view of the bedding machine, Fig. 3 the long-distance train ballast wagon loaded with old ballast, as it does on the one that is still lying Track offset wind, and Fig. 4 the front view associated with Fig. 3. At the departure station A. (not shown) the conversion train is put together. In the working direction behind the bedding machine i are long-distance train ballast wagons 2 and behind them on exchangeable ones Rail wheels arranged on mobile track frames. The renovation train runs on the new track to the conversion point C. There, the one on track 3 moves by means of exchangeable The bedding machine i supplied with rail wheels continues on caterpillars 5 and begins their work after it has rolled off the new track 3 and after already while the construction train is approaching, enough track frames on the old track 3 and rolled out on both sides of the trackless conversion point C to the bedding machine i laid lateral auxiliary rails 7 on the earth covered by the old bedding have been (Fig. i). Can you move on the auxiliary rails on the side? are so-called Beifuhr roll stands 8, the platform of which is level with the track 3 and on each of which one axis of the long-distance train ballast wagon 2 can rest. As soon as the long-distance train ballast wagon 2 When he arrives at the end of the new track, he will be placed on two such auxiliary roller stands 8 driven on the auxiliary rails 7 to in front of the bedding machine i and on this Paths emptied at the point in question. Is the long-distance train ballast wagon 2 is emptied and driven up to the bedding machine i, so it is removed from the auxiliary roller stands 8 pushed over a rising track 14 in the bedding machine i.

Die Bettungsmaschine i (vgl.Abb. i und 2) hat zwei seitlich angeordnete Becherwerke 15 und eine senkrecht zu diesen unmittelbar über dem Erdboden liegende Schnecke 16, die den Altschotter 17 aufreißt und den Becherwerken 15 zuführt. Die Becherwerke 15 geben den Altschotter 17 auf Förderbänder 18 ab, die ihn in den leeren Ferxizugschotterwagen 2 fördern. Der zwischen den Becherwerken 15 vorhandene freie Raum ist so groß, daß die Fernzugschotterwagen 2 auf dem ansteigenden Gleis 14 durch ihn hindurchfahren können (vgl. Abb. 2). Das Gleis 14 ist auf Querträgern i9 gelagert. Die Fernzugschotterwagen 2 haben Innenlager 2o, wenn die zufolge des Abstandes der Becherwerke 15 zur Verfügung stehende Breite restlos ausgenutzt werden soll (Abb. 2 und 4). Das ansteigende Gleis 14 endigt in der Höhe niedriger Abfuhrrollböcke 21, die auf in etwa gleicher Höhe wie das Streckengleis3 liegenden, auf der alten Bettung verlegten seitlichen Hilfsschienen 23 spuren. Die Abfuhrrollböcke 21 sind niedriger als die Beifuhrrollböcke B. Der über das in die Rettungsmaschine i eingebaute, ansteigende Gleis 14 geschobene leere Fernzugschotterwagen 2 wird auf zwei unter dem ausladenden Förderband 18 der Bettungsmaschine i aufgestellte Abfulirrollböcke 2i gebracht und dort mit Altschotter 17 beladen. Von den Abfuhrrollböcken 21 fährt dann der mit Altschotter 17 gefüllte Fernzugschotterwagen 2 unter Zuhilfenahme einer schiefen Ebene 24 (vgl. Abb.3) auf das noch liegende alte Streckengleis 3 und auf diesem zum Endbahnhof B (nicht gezeichnet).The bedding machine i (see Fig. I and 2) has two laterally arranged bucket elevators 15 and a screw 16 lying perpendicular to these directly above the ground, which tears up the old ballast 17 and feeds it to the bucket elevators 15. The bucket elevators 15 deliver the old ballast 17 onto conveyor belts 18 which convey it into the empty Ferxizugschotterwagen 2. The free space between the bucket elevators 15 is so large that the long-distance train ballast wagons 2 can pass through it on the ascending track 14 (see FIG. 2). The track 14 is supported on cross members i9. The long-distance train ballast wagons 2 have inner bearings 2o if the width available due to the distance between the bucket elevators 1 5 is to be fully utilized (Figs. 2 and 4). The ascending track 14 ends at the level of lower discharge roller stands 21, which are located at approximately the same height as the main track 3 and laid on the old bedding on the side auxiliary rails 23. The discharge roller stands 21 are lower than the delivery roller stands B. The empty long-distance train ballast wagon 2 pushed over the ascending track 14 built into the rescue machine i is brought onto two discharge roller stands 2i set up under the projecting conveyor belt 18 of the bedding machine i and loaded there with old ballast 17. The long-distance train ballast wagon 2 filled with old ballast 17 then travels from the discharge roller stands 21 with the aid of an inclined plane 24 (see Fig. 3) to the old track 3 that is still lying and on this to the terminal station B (not shown).

Durch die vorliegende Erfindung wird also erreicht, daß die üblichen Fernzugschotterwagen, so wie sie mit Schotter gefüllt auf dem Bahnhof A ankommen, unmittelbar den Schotter an die Umbaustelle schaffen bzw. von dieser den Altschotter wegbringen können, ohne daß ein nochmaliges Umladen der Fernzugschotterwagen erforderlich ist.By the present invention is achieved that the usual Long-distance train ballast wagons as they arrive at station A filled with ballast, Immediately move the ballast to the conversion site or remove the old ballast from there can take away without having to reload the long-distance train ballast wagons again is.

Claims (1)

PATENTANSPRÜCHE: i. Bettungsmaschine für in Fließaibeit stattfindendenGleisumbau, gekennzeichnet durch ein in der Höhe des Streckengleises (3) am Ende der seitlich auf dem Bahnunterbau verlegten Hilfsschienen (7) beginnendes, bis zur Höhe niedriger Abfuhrrollböcke (21), die auf in etwa gleicher Höhe wie das Streckengleis (3) liegenden Hilfsschienen (23) spuren, ansteigendes Gleis (14), das die entladenen Fernzugschotterwagen (2) aufnimmt, die mittels Beifuhrrollböcke (8), deren Plattform in Schienenhöhe des Streckengleises (3) liegt, angefahren sind, und zur Beladung mit Altschotter (17) an die auf den Hilfsschienen (23) spurenden, niedrigen Abfuhrrollböcke (21) abgibt. z. Rettungsmaschine nach Anspruch i mit zwei seitlich angeordneten Becherwerken, von denen aus der Altschotter auf die Fernzugschotterwagen fällt, und einer in Bettungshöhe liegenden, waagerechten Schnecke, dadurch gekennzeichnet, daß das ansteigende Gleis (14) zwischen den Becherwerken (15) und oberhalb der Schnecke (16) angeordnet ist.PATENT CLAIMS: i. Bedding machine for track renewal taking place in floodplain, characterized by a level with the track (3) at the end of the side Auxiliary rails (7) laid on the railway substructure beginning, up to the level lower Discharge roller stands (21) which are at approximately the same height as the main track (3) Auxiliary rails (23) tracks, ascending track (14) that supports the unloaded long-distance train ballast wagons (2) takes up, by means of Beifuhr roller blocks (8), the platform of which is at rail height of the main track (3) is, have been approached, and for loading with old ballast (17) to the low discharge roller stands (21) that track on the auxiliary rails (23) gives away. z. Rescue machine according to claim i with two laterally arranged bucket elevators, of which the old ballast falls onto the long-distance train ballast wagons, and one at bedding height lying, horizontal screw, characterized in that the rising track (14) is arranged between the bucket elevators (15) and above the screw (16).
DE1930539577D 1930-05-21 1930-05-21 Bedding machine for track renewal taking place in flow work Expired DE539577C (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE539577T 1930-05-21

Publications (1)

Publication Number Publication Date
DE539577C true DE539577C (en) 1931-11-30

Family

ID=6558613

Family Applications (1)

Application Number Title Priority Date Filing Date
DE1930539577D Expired DE539577C (en) 1930-05-21 1930-05-21 Bedding machine for track renewal taking place in flow work

Country Status (1)

Country Link
DE (1) DE539577C (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE892905C (en) * 1952-02-20 1953-10-12 Andreas P Nickelsen Machine that can be moved on the track to remove the ballast
EP0096236A1 (en) * 1982-05-19 1983-12-21 Max-Knape GmbH & Co. Bauunternehmung Track conveyer waggon, transport train and method of loading and unloading materials for railroad construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE892905C (en) * 1952-02-20 1953-10-12 Andreas P Nickelsen Machine that can be moved on the track to remove the ballast
EP0096236A1 (en) * 1982-05-19 1983-12-21 Max-Knape GmbH & Co. Bauunternehmung Track conveyer waggon, transport train and method of loading and unloading materials for railroad construction

Similar Documents

Publication Publication Date Title
AT505403B1 (en) MACHINE FOR RECEIVING AND STORING SMALL IRONS OF A TRACK AND PROCESS
DE2023931C2 (en) Track renewal train for continuously changing sleepers and / or rails on a track
DE2023979A1 (en) Processes and devices for continuously replacing or renewing sleepers and possibly the rails of a track
CH639717A5 (en) DEVICE FOR CONTINUOUSLY DISMANTLING OR REPLACING THE RAILS AND SILLS OF A TRACK.
DE2529135C2 (en) Track construction train for the renewal of a railway line
DE2619131A1 (en) METHOD AND DEVICE FOR REPLACING SECTIONS OF A TRACK
AT3878U2 (en) MACHINE AND METHOD FOR REMOVING AN OLD TRACK AND LAYING A NEW TRACK
DE4237712C2 (en) Plant for the production of a formation protection layer
AT3879U2 (en) MACHINE FOR RENEWING A TRACK
DE2503197A1 (en) CONSTRUCTION TRAIN TO RENOVATE A RAILWAY TRACK
EP0824163A2 (en) Track maintenance machine for removing the ballast
DE539577C (en) Bedding machine for track renewal taking place in flow work
EP0428781B1 (en) Track maintenance machine for distributing and profiling the track bedding ballast
DE3151030A1 (en) MOBILE PLANT FOR PRODUCING A BETWEEN PLANUM AND BULLET BED OF A PROTECTIVE LAYER
DE554384C (en) Loading device with a long conveyor
DE2943525C2 (en) Connection conveyor for conveyor belt systems
DE4101432A1 (en) Method of lowering railway track where it is above required level - involves first removing ballast between sleepers and subsequently removing remainder from under them
DE3420836A1 (en) Railway construction train for introducing a new track bed in track installations
DE1116257B (en) Method and device for receiving ballast under tracks
DE1904683A1 (en) ? for railroad tracks, especially those of the daytime fall
DE511224C (en) Replacement of railroad tracks and mechanical renewal and rolling of the bedding
AT4763U2 (en) METHOD FOR RENEWING A GRAVEL BED AND MACHINE
AT200604B (en) Track renewal procedure and device for its implementation
AT90348B (en) Jib lintel for filling railway embankments.
DE592211C (en) Repair wagon for renewing the bedding of track systems