DE3244035A1 - Sectional renewal of continuous beams made of prestressed concrete - Google Patents
Sectional renewal of continuous beams made of prestressed concreteInfo
- Publication number
- DE3244035A1 DE3244035A1 DE19823244035 DE3244035A DE3244035A1 DE 3244035 A1 DE3244035 A1 DE 3244035A1 DE 19823244035 DE19823244035 DE 19823244035 DE 3244035 A DE3244035 A DE 3244035A DE 3244035 A1 DE3244035 A1 DE 3244035A1
- Authority
- DE
- Germany
- Prior art keywords
- section
- tendons
- joints
- concrete
- continuous
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/04—Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
ABSCHNITTSWEISE ERNEUERUNG VON DURCHLAUFTRÄGERNSECTIONAL RENEWAL OF CONTINUOUS BEAMS
AUS SPANNBETON Die Neuerung betrifft die Anordnung von Fugen in Spannbetonbauwerken, insbesondere Spannbetonbrücken, bei denen es von der Verkehrsaufgabe her erforderlich ist, innerhalb kurzer Zeit einzelne erneuerungsbedürftige Abschnitte ersetzen zu können.MADE OF PRECAST CONCRETE The innovation concerns the arrangement of joints in prestressed concrete structures, especially prestressed concrete bridges, where it is necessary due to the traffic situation is to replace individual sections in need of renewal within a short period of time can.
Bei Spannbetontragwerken haben sich durchlaufende Balkentragwerke, sogenannte 'Durchlaufträger', oder durchlaufende Rahmen-und Plattentragwerke bewährt, da sie sowohl von den Baukosten wie auch von der Dauerhaftigkeit und der Nutzung her in vielen Fällen entscheidende Vorteile bieten. Hierzu zählen weitgehende Wartungsfreiheit, kleine Bauhöhen, relativ geringe Durchbiegungen. Weiterhin lassen sich die Unterbauten material sparender und schlanker dimensionieren.In prestressed concrete structures, continuous beam structures, so-called 'continuous beams', or continuous frame and plate support structures, proven, because they depend on both the construction costs and the durability and use offer decisive advantages in many cases. These include extensive freedom from maintenance, small overall heights, relatively small deflections. Furthermore, the substructures Dimensioning material-saving and slimmer.
Die kurzfristige Austauschbarkeit einzelner erneuerungsbedürftiger Abschnitte dieser Konstruktionen ist jedoch entweder gar nicht möglich oder erfordert einen kaum vertretbaren Aufwand. In jedem Falle treten erhebliche Unsicherheiten am Übergangsbereich vom bestehenden zum abgetrennten und wieder eingesetzten Abschnitt auf.The short-term interchangeability of individual ones in need of renewal However, sections of these constructions are either not possible or required an effort that is hardly justifiable. In any case, there are considerable uncertainties at the transition area from the existing to the separated and reinserted section on.
Nimmt dieser Austauschvorgang sehr lange Zeit in Anspruch, so bedingt er eine entsprechend lange und kostspielige Nutzungsunterbrechung.If this exchange process takes a very long time, so conditionally it means a correspondingly long and costly interruption in use.
Der Stand der Technik ist bisher statt Ersatz erneuerungsbedürftiger Abschnitte entweder das ganze Tragwerk auszuwechseln, oder ein Tragwerk mit ständig offenen Fugen zu konstruieren, so daß erneuerungsbedürftige Abschnitte ausgewechselt werden können.The state of the art has so far been in need of renewal instead of replacement Sections either replace the whole structure, or a structure with constantly to construct open joints so that sections in need of renovation are replaced can be.
Diese offenen Fugen führen zu aufwendigen und sorgfältig zu wartenden Fugenabdeckungen. Außerdem wird hierdurch die erforderliche Konstruktionshöhe des Bauwerks größer und die Durchbiegungen nehmen gegenüber durchlaufenden Bauwerken zu. Da auch die unterstützenden Pfeiler an diesen Fugen verbreitert werden müssen, ergeben sich bei offenen Fugen sehr ungünstige wirtschaftliche und gestalterische Verhältnisse.These open joints lead to complex and carefully serviced Joint covers. In addition, the required construction height of the The structure is larger and the deflections increase compared to continuous structures to. Since the supporting pillars also have to be widened at these joints, Open joints result in very unfavorable economic and design aspects Conditions.
Der Erfindung liegt die Aufgabe zugrunde, Fugen in durchlaufenden Tragwerken so anzuordnen und auszubilden, daß während der Nutzung das Tragwerk an den Fugen nicht unterbrochen wird, d.h. Bewegungen in den Fugen ausgeschaltet werden, daß jedoch für den Fall des Auswechselns einzelner Abschnitte die Verbindung in den vorgesehenen Fugen leicht gelöst und der beschädigte oder verstärkungsbedürftige Abschnitt herausgenommen und der neue Abschnitt eingesetzt werden kann.The invention is based on the object of joints in continuous To arrange and train structures so that the structure is in use the joints are not interrupted, i.e. movements in the joints are eliminated, that, however, in the event of replacing individual sections, the connection in the intended joints easily loosened and the damaged or in need of reinforcement Section removed and the new section can be inserted.
Da in der Fuge hohe Zug-, Druck und Scherkräfte zu übertragen sind, muß sie mit einem hochfesten Material geschlossen werden. Gleichzeitig ist aber sicherzustellen, daß beim öffnen der Fuge mit hydraulischen Pressen oder ähnlichem der Spalt exakt an der vorgesehenen Stelle aufgeht, da der Bauabschnitt in Längsrichtung in der Regel nur wenige Millimeter oder Zentimeter bewegt werden kann.Since high tensile, pressure and shear forces have to be transmitted in the joint, it must be closed with a high-strength material. But at the same time ensure that when opening the joint with hydraulic presses or the like the gap opens exactly at the intended point, since the construction section runs in the longitudinal direction usually only a few millimeters or centimeters can be moved.
Die Aufgabe wird erfindungsgemäß dadurch gelöst, daß an geeigneten Quer schnitt stellen des Durchlaufträgers Fugen vorgesehen werden und daß in Verbund liegende Spannglieder unmittelbar vor den Fugen enden und dort verankert sind.The object is achieved according to the invention in that suitable Cross-section make the continuous beam joints are provided and that in composite lying tendons end immediately in front of the joints and are anchored there.
Weiter werden über die Abschnittsgrenzen hinweg kurze Spannglieder ohne Verbund vorgesehen, die von Lisenen oder Konsolen aus eingezogen und gespannt werden.Short tendons are also used across the section boundaries provided without a bond, drawn in and stretched from pilaster strips or consoles will.
Die Spannglieder ohne Verbund sowie deren Verankerungen werden mit korrosionssicheren Umhüllungen umgeben, die gleichzeitig gewährleisten, daß diese Spannglieder jederzeit aus ihren Spanngliedkanälen wieder herausgezogen werden können.The tendons without bond as well as their anchorages are with Corrosion-proof enclosures, which also ensure that this Tendons can be pulled out of their tendon channels at any time.
An den Abschnittsgrenzen werden Querschnittsflächen ausgebildet, die ein exaktes Trennen auch bei kleiner Längsbewehrung zulassen. Je nach der zu erwartenden Häufigkeit der Trennungen und der Anforderungen an die Dauerhaftigkeit und die Größe der Längsbewegung beim Trennen sind zwei Arten der Trennflächenausbildung vorgesehen.At the section boundaries, cross-sectional areas are formed which allow an exact separation even with small longitudinal reinforcement. Depending on the expected Frequency of separations and the requirements for durability and size the longitudinal movement during separation, two types of separation surface formation are provided.
Bei der ersten Art wird der Beton des vorangegangenen Abschnitts leicht profiliert und mit einem druckfesten Trennmittel, z.B. aus Kunststoff, beschichtet. Der folgende Abschnitt wird dann direkt anbetoniert.With the first type, the concrete from the previous section will be light profiled and coated with a pressure-resistant release agent, e.g. made of plastic. The following section is then concreted directly.
Beim Auswechseln eines Abschnitts wird um Profilierungstiefe auseinandergefahren, der alte Abschnitt herausgefahren und der neue Abschnitt eingeschoben.When replacing a section, the profile is moved apart by the depth of the profile, the old section pulled out and the new section pushed in.
Der Zwischenraum wird anschliessend mit einem flüssigen bzw. pastenartigen, in kurzer Zeit erhärtendem Material, z.B. Zementmörtel, Kunststoff o.dgl., gefüllt.The gap is then covered with a liquid or paste-like, Material that hardens in a short time, e.g. cement mortar, plastic or the like, is filled.
Bei der zweiten Art werden beiderseits im Beton verankerte Plattenpaare aus Metall oder Kunststoff an der Trennfuge vorgesehen. Die druckübertragenden Flächen werden fein profiliert und der feine Spalt zwischen den beiden Platten mit Kunstharz verfüllt sowohl bei der ersten Herstellung wie auch bei einer späteren Trennung.In the second type, pairs of plates are anchored in the concrete on both sides made of metal or plastic provided at the parting line. The pressure-transmitting surfaces are finely profiled and the fine gap between the two plates with synthetic resin filled both during the first production as well as during a later separation.
Bei der Ausführung der verankerten Plattenpaare in entsprechend rostgeschütztem Stahl ist es gegebenenfalls sinnvoll, die Zugkraftübertragung durch die Spannglieder ohne Verbund durch Stahlteile zu ersetzen, die mit den einbetonierten Stahlplatten durch hochfeste Schrauben verbunden werden.With the execution of the anchored plate pairs in appropriately rust-protected Steel, it may be useful to transfer the tensile force through the tendons without replacing the composite with steel parts, those with the concreted steel plates be connected by high-strength screws.
Der Wert der Erfindung liegt darin, daß die Fuge so ausgebildet ist, daß während der Benutzung des Tragwerkes alle Vorteile des durchlaufenden Trägers erhalten bleiben. Z.B. in wirtschaftlicher Hinsicht ergeben sich Ersparnisse an Beton, Bewehrungs- und Spann stahl - bedingt durch das günstige Tragverhalten des durchlaufenden Trägers - durch rationelle Fertigungsmöglichkeiten usw.The value of the invention lies in the fact that the joint is designed in such a way that that during the use of the structure all the advantages of the continuous beam remain. E.g. in economic terms savings result Concrete, reinforcement and prestressing steel - due to the favorable load-bearing properties of the continuous carrier - through rational production possibilities, etc.
Weiterhin ermöglicht die Fugenausbildung ein so rasches öffnen der Fuge und Ersetzen des alten Abschnittes durch einen neuen, daß in Bezug auf den dafür erforderlichen Zeitraum praktisch kein Unterschied zu Tragwerden mit ständig offenen Fugen besteht.Furthermore, the formation of the joints enables the quick opening Fugue and replace the old section with a new one that relates to the The time required for this is practically no different from being carried with constant open joints.
Darüber hinaus liegt ein Vorteil dieser Fugenausbildung auch darin, daß sich die Fuge als Sollrißfuge bemessen läßt in z.B. durch große Setzungen beanspruchten Tragwerken. Die Zugkräfte der Spannglieder im Fugenbereich können auch leicht nachreguliert werden und der dabei entstehende Fugenspalt kann durch Injizieren geschlossen werden.Another advantage of this joint design is that that the joint can be dimensioned as a predetermined crack joint, e.g. in areas exposed to large subsidence Structures. The tensile forces of the tendons in the joint area can also be easily readjusted and the resulting joint gap can be closed by injection.
Die Erfindung wird durch folgende Figuren erläutert: Fig. 1 zeigt den Querschnitt eines Tragwerks im Fugenbereich mit den erforderlichen Lisenen oder Konsolen an der Trennfuge.The invention is illustrated by the following figures: FIG. 1 shows the cross-section of a structure in the joint area with the required pilaster strips or Consoles at the parting line.
Fig. 2 zeigt denselben Bereich im Längsschnitt.Fig. 2 shows the same area in longitudinal section.
Fig. 3 zeigt das prinzipielle Fugendetail bei der Ausführung mit Trennmittel.Fig. 3 shows the basic joint detail in the version with a release agent.
Fig. 4 zeigt das Fugendetail bei der gepanzerten Ausführung mit Metall- oder Kunststoffplatten.Fig. 4 shows the joint detail in the armored version with metal or plastic sheets.
Fig. 5 zeigt die Laschenverbindung bei einer Panzerung analog zu Fig. 4.FIG. 5 shows the tab connection in the case of armoring analogous to FIG. 4th
An den freien Enden der Lisenen 1 werden Spanngliedverankerungen 2 angeordnet und Spannglieder 3 durch die Lisenen über die Fuge 4 geführt. Die Fuge wird mit einem Injektionsmaterial 5 gefüllt. Die Fugenflächen 6 sind profiliert oder nach Fig. 4 mit einer Panzerung 7 versehen, die mit den Ankern 8 im Betonquerschnitt 9 verankert sind.Tendon anchorages 2 are attached to the free ends of the pilaster strips 1 arranged and tendons 3 passed through the pilaster strips over the joint 4. The joint is filled with an injection material 5. The joint surfaces 6 are profiled or according to Fig. 4 with armor 7, which is connected to the anchors 8 in the concrete cross-section 9 are anchored.
Bei der Laschenverbindung nach Fig. 5 werden die Panzerungen 7 mit den Laschen 10 durch hochfeste Schrauben 11 verbunden.In the tab connection according to FIG. 5, the armor 7 with the brackets 10 are connected by high-strength screws 11.
Die Stahlpanzerung 7 wird mit den Spanngliedern 12 im Beton verankert.The steel armor 7 is anchored with the tendons 12 in the concrete.
LeerseiteBlank page
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19823244035 DE3244035A1 (en) | 1982-11-27 | 1982-11-27 | Sectional renewal of continuous beams made of prestressed concrete |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19823244035 DE3244035A1 (en) | 1982-11-27 | 1982-11-27 | Sectional renewal of continuous beams made of prestressed concrete |
Publications (1)
Publication Number | Publication Date |
---|---|
DE3244035A1 true DE3244035A1 (en) | 1984-05-30 |
Family
ID=6179286
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19823244035 Withdrawn DE3244035A1 (en) | 1982-11-27 | 1982-11-27 | Sectional renewal of continuous beams made of prestressed concrete |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE3244035A1 (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4709456A (en) * | 1984-03-02 | 1987-12-01 | Stress Steel Co., Inc. | Method for making a prestressed composite structure and structure made thereby |
DE19936756A1 (en) * | 1999-08-09 | 2001-02-15 | Boegl Max Bauunternehmung Gmbh | Track of a track-bound vehicle |
WO2003023144A1 (en) * | 2001-09-07 | 2003-03-20 | Shanghai Maglev Transportation Development Co., Ltd | A track structure of the rapid track transit |
WO2003035982A1 (en) * | 2001-10-26 | 2003-05-01 | Shanghai Maglev Transportation Development Co., Ltd | A prestressed track girder and its manufacture method |
NL1030736C2 (en) * | 2005-12-22 | 2007-06-25 | Movares Nederland Bv | Concrete over-bridging construction comprises body which extends over lower located ground surface and/or water and incorporates transport system upon it |
CN111608094A (en) * | 2020-05-28 | 2020-09-01 | 中铁六局集团有限公司 | Construction method for polishing and repairing beam surface of high-speed railway cast-in-place box beam |
CN114775408A (en) * | 2022-06-20 | 2022-07-22 | 湖南大学 | Combined box girder external prestressed tendon steering structure |
-
1982
- 1982-11-27 DE DE19823244035 patent/DE3244035A1/en not_active Withdrawn
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4709456A (en) * | 1984-03-02 | 1987-12-01 | Stress Steel Co., Inc. | Method for making a prestressed composite structure and structure made thereby |
DE19936756A1 (en) * | 1999-08-09 | 2001-02-15 | Boegl Max Bauunternehmung Gmbh | Track of a track-bound vehicle |
WO2003023144A1 (en) * | 2001-09-07 | 2003-03-20 | Shanghai Maglev Transportation Development Co., Ltd | A track structure of the rapid track transit |
EP1424443A1 (en) * | 2001-09-07 | 2004-06-02 | Shanghai Meglev Transportation Development Co. Ltd. | A track structure of the rapid track transit |
EP1424443A4 (en) * | 2001-09-07 | 2007-04-18 | Shanghai Meglev Transp Dev Co | A track structure of the rapid track transit |
WO2003035982A1 (en) * | 2001-10-26 | 2003-05-01 | Shanghai Maglev Transportation Development Co., Ltd | A prestressed track girder and its manufacture method |
NL1030736C2 (en) * | 2005-12-22 | 2007-06-25 | Movares Nederland Bv | Concrete over-bridging construction comprises body which extends over lower located ground surface and/or water and incorporates transport system upon it |
CN111608094A (en) * | 2020-05-28 | 2020-09-01 | 中铁六局集团有限公司 | Construction method for polishing and repairing beam surface of high-speed railway cast-in-place box beam |
CN114775408A (en) * | 2022-06-20 | 2022-07-22 | 湖南大学 | Combined box girder external prestressed tendon steering structure |
CN114775408B (en) * | 2022-06-20 | 2022-08-26 | 湖南大学 | Combined box girder external prestressed beam steering structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2717869A1 (en) | PROCESS FOR THE MANUFACTURING OF COMPONENTS FROM PRE-TENSIONED CONCRETE | |
DE3628876A1 (en) | Permanent shuttering | |
CH623376A5 (en) | ||
DE3244035A1 (en) | Sectional renewal of continuous beams made of prestressed concrete | |
AT396151B (en) | CONNECTING ELEMENT FOR CANTILEVER PLATES AND CONNECTING ELEMENT COMPOSED FROM MULTIPLE CONNECTING ELEMENTS | |
DE2237382A1 (en) | CONSTRUCTION WITH ADJUSTING GIRDERS FOR BRIDGES, VIADUCTS AND THE LIKE MADE OF PRE-TENSIONED CONCRETE AND PROCESS FOR THEIR PRODUCTION | |
DE2247609B1 (en) | PROCESS FOR CREATING A BRIDGE STRUCTURE FROM PRE-STRENGTHENED CONCRETE IN SECTIONAL FREE FRONT-FRAME | |
DE3806759C2 (en) | Method for renovating a hollow cylindrical building body and kit system therefor | |
DE102011102987A1 (en) | Incremental launching method for mounting road- and railway bridges with beam cross section, involves providing two steel main girders and carriageway slab made from steel, reinforced concrete or prestressed concrete | |
DE3738291C2 (en) | ||
DE19831984C2 (en) | Component with external tendons | |
DE1237603B (en) | Process for the production of long structures, in particular bridges, from steel or prestressed concrete | |
AT380502B (en) | METHOD AND DEVICE FOR WIDING RUNWAY PANELS, BRIDGE ROADWAYS OR THE LIKE. | |
DE102007003552B3 (en) | Bridge bearing structure has U-shaped concrete structure arranged in supporting region of superstructure beneath bottom booms of steel box girders which are equidistantly arranged from middle vertical plane | |
DE2718616A1 (en) | Cable stressed modular concrete bridge construction - has rigid anchor units inserted for direct cable anchorage before site concreting | |
DE920013C (en) | Process for the production of composite structures, in particular girder bridges and shell roofs | |
DE2156017A1 (en) | PRE-TENSIONED STEEL COMPOSITE BEAM | |
DE1931431A1 (en) | Lane board, especially for city high streets | |
DE3833202C2 (en) | Beam-like supporting element made of prestressed concrete | |
DE975466C (en) | Prestressed component and process for its manufacture | |
DE3242153A1 (en) | Method for installing a multi-field support framework | |
DE102006029130A1 (en) | Method for producing a segmented prefabricated bridge and segmented prefabricated bridge | |
DE202021103738U1 (en) | System for connecting precast concrete parts | |
AT237668B (en) | Joint formation for bridge structures, especially for elevated roads made of prestressed concrete | |
DE1534452C3 (en) | Superstructure made from reinforced precast concrete parts, especially for bridges |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
8139 | Disposal/non-payment of the annual fee |