DE1940761C3 - Plant for continuous steel production - Google Patents
Plant for continuous steel productionInfo
- Publication number
- DE1940761C3 DE1940761C3 DE19691940761 DE1940761A DE1940761C3 DE 1940761 C3 DE1940761 C3 DE 1940761C3 DE 19691940761 DE19691940761 DE 19691940761 DE 1940761 A DE1940761 A DE 1940761A DE 1940761 C3 DE1940761 C3 DE 1940761C3
- Authority
- DE
- Germany
- Prior art keywords
- channel
- pig iron
- gutter
- steel
- plant
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- C—CHEMISTRY; METALLURGY
- C21—METALLURGY OF IRON
- C21C—PROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
- C21C5/00—Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
- C21C5/28—Manufacture of steel in the converter
- C21C5/285—Plants therefor
-
- C—CHEMISTRY; METALLURGY
- C21—METALLURGY OF IRON
- C21C—PROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
- C21C5/00—Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
- C21C5/56—Manufacture of steel by other methods
- C21C5/567—Manufacture of steel by other methods operating in a continuous way
Description
Die Erfindung bezieht sich auf eine Anlage für 45 Den betriebstechnischen Anforderungen kommtThe invention relates to a system for the operational requirements
kontinuierliche Stahlerzeugung mit einer der Rohei- insbesondere entgegen, daß die Doppelrinnen auscontinuous steel production with one of the Rohei- in particular opposed to that the double troughs
senerzeugung angeschlossenen Einrichtung zum Fri- mehreren Rinnenstücken bestehende Frischlinien bil-connected device for fringing several channel pieces to form existing fresh lines.
schen des in Rinnen gcfüh;» \ Roheisenstromes. den.between the in gcfüh; " \ Pig iron stream. the.
Der Wunsch, Stahl kontinuierlich oder abweichend Ein anderes Merkmal, für das um selbständigenThe desire to steel continuously or deviatingly Another characteristic for which to become self-employed
vom chargenweisen Erzeuten halbkontinuierlich wie 50 Patentschutz nachgesucht wird, besteht darin, daß dieof the batch-wise production semi-continuously as patent protection is sought, consists in the fact that the
etwa beim Stahlstranggicßen zu erzeugen, besteht seit Rinnenstürke hrw die Hn«tfistück-Rinnen quer 7iir to be produced in continuous steel casting , for example, has existed since the time of Gutterstürke
langem. Trotz großer Bemühungen ist es praktisch Frischlinienrichtung auf Gleisen verfahibar sind,long. Despite great efforts, it is practically possible to move fresh line direction on tracks,
bei Versuchseinrichtungen der unterschiedlichsten Dem Fach inn ist damit eine wertvolle AnweisungThe specialist is therefore a valuable instruction
Art geblieben. Der Großeinsatz solcher Vesfahren, gegeben, wie laufende Vorbereitungen einer Frischli-Kind of stayed. The large-scale use of such procedures, given such as ongoing preparations for a fresh food
zunächst für einfache Stahlsorten, steht noch aus und 55 nie in den betrieblichen Ablauf eines Dauerbetriebesinitially for simple steel grades, is still pending and 55 never in the operational sequence of a continuous operation
gilt als Ziel aller Anstrengungen. eingeplant werden können.is the goal of all efforts. can be scheduled.
An die Metallurgie sind Forderungen gestellt, die Die grundsätzliche Anordnung der Doppelrinnen
das Erschmelzen te Roheisens betreffen, dessen ergibt eine aus ihr folgende Möglichkeit für die Lage
Entschwefelung, Ti.nperaturregulierung und gleich- bclriebswichtiger Einrichtungen. Danach ist vorgesezeitige
oder stufenweise Entfernung aller liner- 60 hen, daß zwischen je einer Doppelrinne Vorratsbunwünschtei
Beglcitstoffe. Die Lösung dieser Aufgaben kcr fü«· Zuschlagstoffe angeordnet sihd.
führte bereits /ü dem bekannten Gegcnstromschlacke- Die Trennung der Frischlinien in Rinnenstücke,
Verfahren. Schlacke wird hierbei entgegengesetzt gestattet nach einem weiteren Merkmal der Erfindern
Roheisen bewegt, was auf Grund elcktroindukti- dung, daß zwischen zwei Rinnensiücken Abschlackver
Kräfte gelingt. 65 rinnen eingeschaltet sind.The metallurgy is subject to demands which concern the basic arrangement of the double channels for smelting the pig iron, which results in the possibility of desulphurisation, temperature regulation and similarly important facilities. After that, early or step-by-step removal of all liners that are unwanted in storage between each double channel is necessary. The solution to these tasks is arranged for aggregates.
has already led / u the famous Gegcnstromschlacke- Separation of fresh lines in gutter pieces procedures. According to a further feature of the inventors, slag is allowed to move in the opposite direction, which is due to electrical induction, so that slagging forces are achieved between two gullies. 65 channels are switched on.
Ungelöste Probleme jedoch konzentrieren sich in Ein anderer Vorzug der Erfindung gestattet, daßUnresolved problems, however, focus on Another advantage of the invention allows that
höhcrem Maße auf die cinrichtungstuchnischc Ausrü- am Ausgang einer Frischlinic entweder Roheisenab-to a greater extent on the facility sheet equipment at the exit of a fresh clinic either pig iron
slung. Verständlicherweise treten wiederum Schwic- sfichstelicn oder Verbindungen zu einer Stranggieß·slung. Understandably, there are alternating points or connections to a continuous casting.
'■-■'s"'■ - ■' s "
i 940i 940
anlage in angegebener Richtung vorgesehen sind. Die Slranggießanlage liegt direkt hinter der Stahlwerkshalle, so daß Hochofenanlage, Stahlwerkshalle und Stranggießanlage eine zusammengebaute Einheit bilden können.system are provided in the direction indicated. The Slranggießanlage is located directly behind the steelworks hall, so that the blast furnace system, steelworks hall and Continuous caster can form an assembled unit.
Jn der Zeichnung ist ein Ausführungsbeispiel der erfindungsgemäßen Anlage schematisch dargestellt und im folgenden näher erläutert.In the drawing is an embodiment of the Plant according to the invention shown schematically and explained in more detail below.
Die einzige Figur der Zeichnung bildet einen Grundriß der Anlage.The only figure in the drawing is a floor plan of the system.
Die neue Stahlwerks .nlage besteht aus zwei Hauptbereichen. Der erste i«t <ie Hochofenanlage 1 und den zweiten biidci die ~,gwitliche Stahlerzeugungshalle, deren Hauen! nsi.-jktion auf den Pfeilern 2 ruht. Innerhdh d:t τ Halle befinden sich sämtliche Einrichtu—-c zum kontinuierlichen Frischen des Stank. 5Z-^r Hochofen 3 der Hochofenanlage 1 weist aL * -jentliches Merkmal einen Hauptabstich 4 für das flüssige Roheisen auf. Es handelt sich dabei um eine offene oder übei deckte Rinne, in der das Roheisen direkt in die S' ühlerzeugungshalle 2 geleitet wird. Vom Hauptabstirh 4 kann gegebenenfalls eine Zweigrirme 5 in die Hochofenhalle 6 führen, sofern aus betrieblichen Gründen das Roheisen anderweitig verarbeitet werden soll. Die Zweigrinne, kann auch als zusätzliche Schlackenrinne dienen, um Reste aus dem Strom des Hauptr.bstichs 4 zu entfernen. Außerdem >st ein konventioneller Schlackenabstich 7 vorgesehen, der wie der konventionelle Roheisenabstich 8 in die Hochorenhalle 6 mündet.The new steel mill consists of two main areas. The first one is blast furnace plant 1 and the second one is the modern steel-making hall, its hewn! NSI junction rests on pillars 2. Inside the hall there are all facilities for the continuous freshening of the stench. 5 Z- ^ r blast furnace 3 of the blast furnace system 1 has aL * -jentliches feature a main tap 4 for the liquid pig iron. It is an open or covered channel in which the pig iron is fed directly into the S 'ühlzeugungshalle 2. If necessary, a two-screen screen 5 can lead from the main wall 4 into the blast furnace hall 6 if the pig iron is to be processed otherwise for operational reasons. The branch channel can also serve as an additional cinder channel to remove residues from the flow of the main trench 4. In addition, a conventional slag tap 7 is provided, which, like the conventional pig iron tap 8, opens into the high-arch hall 6.
An und für sich kann die Hochofenanlage 1 freistehen, es besteht jedoch die Möglichkeit, die Stahlerzeugungshalle mittels einer Wand 9 als zusammengehöriges Ganzes zu bauen.In and of itself, the blast furnace installation 1 can be free, However, there is the possibility of the steel production hall by means of a wall 9 as belonging together Build whole.
Das vom Hauptabstich 4 kommende Roheisen fließt in den wesentlichsten Teil der Erfindung. Dieser wird von einem oder auch mehreren Doppelrinnen 10 dargestellt. An den Hauptabstich 4 schließt sich eine Hosenstück-Rinne 11 an. Diese läuft in die Frischrintic 12 und 13 über. Jede der Frischrinnen 12 und 13 besitzt eine gewisse Länge, die nach metallurgischen Gesichtspunkten und der zu erzeugenden Menge Stahl pro Zeiteinheit festzulegen ist. Diese Länge ergibt sich durci aneinanderschließende Rinnenstücke E4. Jedes dieser Rinnenstücke 14 ist keramisch ausgemauert und weist im wesentlichen Röhrenform auf. Der Querschnitt der Röhren sowie dessen Form richten sich nach der Menge Roheisen, den anfallenden Abgasen nach Menge und Zusammensetzung, der erwünschten Schlackenschichtdicke sowie deren Breite, der Wärmeisolierung sowie nach Größe und Form von Zuführöffnungen für Frischmittel und Zuschläge.The pig iron coming from the main tap 4 flows into the most essential part of the invention. This is represented by one or more double channels 10. The main tap 4 closes a trouser-piece gutter 11. This overflows into the fresh rintic 12 and 13. Each of the fresh channels 12 and 13 has a certain length, which from a metallurgical point of view and the one to be produced The amount of steel per unit of time is to be specified. This length results from the mutually connecting pieces of gutter E4. Each of these channel pieces 14 is lined with ceramic and is essentially tubular on. The cross-section of the tubes and their shape depend on the amount of pig iron that Accruing exhaust gases according to quantity and composition, the desired slag layer thickness and their width, the thermal insulation and the size and shape of feed openings for fresh agent and Surcharges.
Die bisher ungelösten Probleme des betrieblichen Ablaufs beim kontinuierlichen Stahlerzeugen lösen nunmehr verfahrbare Rinnenstücke 14 auf Schienen IS und 16. Es ist vorteilhaft, solche Rinnenstiicke heb- und senkbar zu machen, beispielsweise innerhalb einer Grube. Beim Wechseln eHes Rinnenstükkes 14 ^hrt das verbrauchte über die Grube hinweg urd das vorbereitete tritt aus der Grube aus und wird in die »Frischlinie« eingefahren. Zwischen zwei, tire Frischlinie 17 bildenden Rinnensiücken 14, besieht die Möglichkeit, eine Abschlackrinne if anzuordnen. Solve the so far unsolved problems of the operational process in continuous steelmaking now movable channel pieces 14 on rails IS and 16. It is advantageous to use such channel pieces can be raised and lowered, for example within a pit. When changing eHes gutter piece 14 ^ hears the used up across the pit The prepared one emerges from the pit and is brought into the "fresh line". Between two, tire Fresh line 17 forming gutters 14, has the possibility of arranging a deslagging channel if.
5m Ausführ-ingsbeispiel ist demnach eine Vorlp frischslrecke mit den Frischrinnen 12 bzw. 13 gebildet. In Fließricbtung nach der Abzweigung der Vorschlacke mittels der Abschlackrinne 18 folgen in der Anordnung die Hauptfrischstrecke 19 bzw. 20. Der so anfallende Stahl kann entweder über den Abslich 21 in bereitstehende Pfannen abgegossen werden oder tritt in eine weitere nicht gezeigte Stranggießanlage in Richtung 22 ein.5m embodiment is therefore a template Frischslrecke formed with the fresh channels 12 and 13, respectively. In flow direction after the branching of the pre-varnish by means of the deslagging channel 18, the main freshening section 19 or 20 follow in the arrangement The resulting steel can either be poured into pans provided via Abslich 21 or enters a further continuous caster (not shown) in direction 22.
Die erfindungsgemäße Anordnung verbindet mehrere ^ löglichkeiten. Jede Doppelrinne 10 braucht nur so jeweils in einer der Yt' .,hrinnen 12 oder 13 betrieben zu werden. Dadurch kann wertvolle Zeit erspart werden, die für den Umbau der jeweils anderen Rinne zur Verfügung steht. Die Weiche 23 gestattet, entweder den Roheisenfluß in die Frischrinne 12 oder 13 as zu leiten. Eine solche Weiche läßt sich aus einer starren Aufmauerung bilden, wenn mechanisch bewegte Teile vermieden werden sollen.The arrangement according to the invention combines several possibilities. Each double channel 10 only needs to be operated in one of the Yt ' ., Channel 12 or 13. This saves valuable time that is available for converting the other channel. The switch 23 allows either the pig iron flow to be directed into the fresh channel 12 or 13 as. Such a switch can be formed from a rigid brickwork if mechanically moving parts are to be avoided.
Für beide Frischlinien 17 kommen Vorratsbunker 24 in Betracht, die in einer Reihe zwischen zwei Frischlinien 17 angeordnet sind und auf einer Förderbahn 25 in Richtung der Frischlinien 17 mit Zuschlagstoffen versorgt werden können. Von den in greifbarer Nähe angeordneten Vorratsbunkern führen Transportmittel 26 direkt zu den Einfuhröffnun^n 27, so daß — gleichgültig, welche Frischlinie einer Doppelrinne 10 in Betrieb steht — entweder nach links oder nach recht? die Zuschlagstoffe verteilt werden können. Dieses Merkmal gehört zu den wesentlichen Teilen der Erfindung, wonach die betrieblichen Schwierigkeiten überwunden werden sollen.For both fresh lines 17 storage bunkers 24 come into consideration, those in a row between two Fresh lines 17 are arranged and on a conveyor track 25 in the direction of the fresh lines 17 with aggregates can be supplied. Lead from the storage bunkers within easy reach Transport means 26 directly to the import openings 27, so that - no matter which fresh line one Double channel 10 is in operation - either to the left or to the right? the aggregates are distributed be able. This feature belongs to the essential parts of the invention, according to which the operational Difficulties are to be overcome.
Das Frisch"" selbst kann in bekannter Art und Weise mittels aauerstoffblaslanzen 28 erfolgen, was jedoch nicht zum Schutzumfang der Erfindung gehört, wie ebenso nicht zur Erfindung gehört, daß die Antriebsbewegung des Roheisens entweder aus Gefälle aufweisenden R:nnen hergeleitet wird oder aus elektroinduktiven Kräften, die in Form von elektrischen Spulen in der Metallurgie bereits praktische Anwendung gefunden haben. Ebenso ist es möglich, die Schlacke mechanisch, elektroinduktiv gegenüber dem Roheisen zu bewegen, was jedoch ebenfalls nicht zum Schutzumfang der Erfindung gehört.The fresh "" itself can be done in a known manner by means of oxygen blowing lances 28, what but does not belong to the scope of the invention, just as does not belong to the invention that the driving movement of the pig iron either from a slope having R: nnen is derived or from electroinductive forces in the form of electrical Coils in metallurgy have already found practical application. It is also possible to use the Slag mechanical, electro-inductive compared to that To move pig iron, which, however, also not to The scope of the invention belongs.
Es vcisic'iii sich, dsß die srfindi'.r.gsgcmäiV* Anordnung der Rinnenslücke 14 bezüglich der Frischlinienführung oder der Anzahl bzw ihrer Länge und ihrer körperlichen Ausgestaltung mannigfache Abwandlungen erfahren kann.It vcisic'iii that the srfindi'.r.gsgcmäiV * arrangement the channel gap 14 with respect to the fresh line management or the number or their length and their physical configuration various modifications can experience.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19691940761 DE1940761C3 (en) | 1969-08-11 | 1969-08-11 | Plant for continuous steel production |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19691940761 DE1940761C3 (en) | 1969-08-11 | 1969-08-11 | Plant for continuous steel production |
Publications (3)
Publication Number | Publication Date |
---|---|
DE1940761A1 DE1940761A1 (en) | 1971-02-25 |
DE1940761B2 DE1940761B2 (en) | 1972-06-22 |
DE1940761C3 true DE1940761C3 (en) | 1973-02-01 |
Family
ID=5742485
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19691940761 Expired DE1940761C3 (en) | 1969-08-11 | 1969-08-11 | Plant for continuous steel production |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE1940761C3 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2563301B1 (en) * | 1984-04-19 | 1986-06-27 | Bertin & Cie | ELASTIC SUSPENSION DEVICE WITH HIGH ANGULAR RIGIDITY |
DE102006056672A1 (en) | 2006-11-30 | 2008-06-05 | Sms Demag Ag | Method and apparatus for stainless steel production without electrical energy supply based on pig iron |
-
1969
- 1969-08-11 DE DE19691940761 patent/DE1940761C3/en not_active Expired
Also Published As
Publication number | Publication date |
---|---|
DE1940761A1 (en) | 1971-02-25 |
DE1940761B2 (en) | 1972-06-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO1996006193A1 (en) | Converters and method of refining metal melts, in particular refining pig iron to steel | |
DE3720886C2 (en) | ||
DE1940761C3 (en) | Plant for continuous steel production | |
DE2418109B1 (en) | Device and method for continuous steelmaking | |
EP1627085B1 (en) | Method for recovering metallic elements, especially metallic chromium, from slag containing metal oxides in an electric-arc furnace | |
DE1923596A1 (en) | Continuous process for steel production | |
EP0313959B1 (en) | Steel-making plant, especially mini-plant | |
WO2003106716A1 (en) | Method and production plant for producing products on the basis of carbon steel or stainless steel | |
EP1492893B1 (en) | Method and installation for producing stainless steel, especially high-quality steel containing chromium or nickel chromium | |
DE2900864A1 (en) | PROCESS FOR INJECTING POWDERED MATERIAL INTO A METALLURGICAL MELT | |
WO2021094412A1 (en) | Producing crude steel on the basis of a premelt | |
DE4404313C2 (en) | Process for melting and treating metals and plant for carrying out the process | |
DE1800131B1 (en) | Multi-zone melting process and multi-zone melting furnace for the continuous production of steel | |
DE2060493C3 (en) | Process for the continuous production of steel by spray-freshening and plant for carrying out the process | |
DE102010020179A1 (en) | Method for operating a floor flushing system of a BOF converter | |
DE2506704A1 (en) | METAL MELTING PLANT WITH A TREATMENT STAND FOR SETTING THE ANALYSIS OF METAL MELT, IN PARTICULAR FOR DESULFURIZING LIQUID CRUDE IRON OR CRUDE STEEL | |
DE2121071A1 (en) | Device for carrying out continuous melt-metallurgical reactions in connection with an electromagnetic countercurrent trough and method for operating the device | |
DE3618510A1 (en) | METHOD AND DEVICE FOR CONTINUOUS TREATMENT OF MELT-LIQUID METAL | |
DE3615096C1 (en) | Equipment and process for continuous oxidising and refining of crude iron to give steel | |
EP1640462A2 (en) | Method and device for the production of molten steel | |
DE3150291A1 (en) | Process for re-using dusts formed in stainless steel production | |
DE102016001246A1 (en) | Method and device for desulphurizing an iron melt | |
DE813752C (en) | Plant for the continuous melting and casting of metal alloys | |
EP0589366B1 (en) | Steelplant lay-out | |
AT223755B (en) | cupola |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C3 | Grant after two publication steps (3rd publication) | ||
E77 | Valid patent as to the heymanns-index 1977 | ||
8339 | Ceased/non-payment of the annual fee |