Attached beam type lifting scaffold for high-rise building Download PDFInfo
- Publication number
- CN2642925Y CN2642925Y CN 03279315 CN03279315U CN2642925Y CN 2642925 Y CN2642925 Y CN 2642925Y CN 03279315 CN03279315 CN 03279315 CN 03279315 U CN03279315 U CN 03279315U CN 2642925 Y CN2642925 Y CN 2642925Y
- Authority
- CN
- China
- Prior art keywords
- node
- side direction
- saddle
- stock
- stocks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000000725 suspension Substances 0.000 claims description 12
- 238000010276 construction Methods 0.000 abstract description 8
- 239000000463 material Substances 0.000 abstract description 4
- 238000000034 method Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 230000003321 amplification Effects 0.000 description 3
- 238000009435 building construction Methods 0.000 description 3
- 238000003199 nucleic acid amplification method Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000011017 operating method Methods 0.000 description 2
- 230000001737 promoting effect Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000008093 supporting effect Effects 0.000 description 2
- 230000009194 climbing Effects 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 230000001976 improved effect Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 230000011218 segmentation Effects 0.000 description 1
Images
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model discloses constitute the guide frame by side direction guide frame (1) and guide frame transverse link rod (2) etc. and constitute the cover frame by side direction cover frame (3) and cover frame transverse link rod (4) etc. and can slide relatively between cover frame and the guide frame. The frame nodes on the two sides of the guide frame and the sleeve frame are respectively and fixedly connected with the auxiliary beam duplex node fixed on the boundary beam of the high-rise building. And a steady piece (23) which can ensure the safety and convenient lifting of the scaffold and a building floor height change adjusting piece (25) are also arranged. The scaffold is suitable for the construction of high-rise buildings with vertical discontinuous beam structure parts (such as boundary beams) and can be lifted as required. The tower crane saves material and working days, does not occupy a tower crane, reduces the labor intensity of a scaffold worker, and is safe and reliable to use.
Description
The utility model relates to the suspended scaffold by the house supporting that the building operations personnel use, and specifically is meant a kind of highrise building attaching beam formula lifting false work.
At present, the general external scaffolding of using in the high-building construction, mainly contain console mode fastener steel tube frame, segmentation steel pipe frame, door frame, hanger---the hanging basket system etc. of encorbelmenting, although it is various informative, the material consumption amount is big, holding time long, consume the worker, scaffolder's high-altitude application environment is abominable but all exist to some extent, problems such as contingency accident easily take place, and make the outrigger engineering become headachy one difficulty in the high-building construction.A kind of wall-attached (shear wall) liftable out-mould scaffold pin of lifting had appearred carrying out according to the principle of climbing of creeping formwork in recent years in China's some areas high-building construction, it is compared with traditional console mode scaffold, save the frame material more than 90%, save work day more than 50%, neither take tower crane, reduced scaffolder's labour intensity again, improved operating environment, safe and reliable, solved the shelf pass difficult problem that the highrise building shear wall is partly constructed breakthroughly.But, in highrise building, account for the frame part and the balcony part of significant proportion, promptly be vertically to be discontinuous plate and girder construction part, in construction, still adopt traditional external scaffolding, spacious sick a lot of.
The purpose of this utility model is on the basis of existing wall-attached (shear wall) liftable external scaffolding, provides a kind of for vertically being the highrise building attaching beam formula lifting false work that discontinuous girder construction is partly constructed.
Solution of the present utility model is, still as existing wall-attached (shear wall) liftable external scaffolding, have two upright side direction saddles, the saddle transverse brace that between two side direction saddles, has several groups of differing heights that two ends are connected mutually with two side direction saddles respectively, go up most one group of saddle transverse brace below, have two upright side direction stocks, the upright loop bar of these two side direction stocks sliding sleeve respectively is combined in outside the upright guide rod of two side direction saddles, have between two side direction stocks two ends respectively with two side direction stocks be connected mutually on, following two groups of stock transverse braces, on two side direction saddles and two side direction stocks, be fixed with respectively and be used for the shelf lifting, following two saddle suspension ring and last, following two stock suspension ring have the front rail handrail that is connected mutually with it respectively in the outside of lateral guide top of the trellis and bottom.Feature part of the present utility model is, both sides also have respectively the upright auxiliary rod that is connected mutually with the side direction saddle, has the transverse brace that two ends are connected mutually with auxiliary rod respectively between the auxiliary rod; On two side direction saddles below two side direction stocks, all have node and saddle lower node on the saddle successively, have node on stock lower node and the stock respectively, on above-mentioned node, all have and the latch connecting hole in two side direction stock bottoms and top; Attaching beam duplex node with eight same structures, the structure of each attaching beam duplex node is, has a π type duplex node accessory, the mainboard central authorities of duplex node accessory have the strip through hole, long bolt and nut component is housed in the hole, all have upper and lower two pin holes on two side plates of duplex node accessory, a latch respectively is housed in the hole, an end of latch is fixed with cottor pin; Have two firmwares that are connected mutually and form by standard scaffold tubes and firmware node, have on the firmware node and the latch connecting hole.
This practical firewood type with said structure is when concrete the use, should hang in the high-rise building side that the side bar structure is arranged by its attaching beam duplex node, its specifically the method for hanging be, both sides all have preformed hole on the side bar in four adjacent from the bottom up floor rooms, pass preformed hole with the bolt and nut component on the attaching beam duplex node, respectively eight attaching beam duplex nodes are close to and are fixed on the side bar side (if the side bar of the 4th floor is not constructed from the bottom up, then treat construction good after fixing attaching beam duplex node again), again node on the saddle lower node of two side direction saddles and the saddle is locked with the latch of first floor and second layer building attaching beam duplex node from the bottom up respectively with the latch connecting hole mutually by it and connected, node on the stock lower node of two side direction stocks and the stock is locked company with the latch of the attaching beam duplex node of the second layer and three-storey building from the bottom up by it respectively mutually with the latch connecting hole.By above-mentioned connection, just can make whole scaffold be fixed on side of buildings firmly.The constructor stands on saddle transverse brace and the stock transverse brace, just can carry out constructing operation.When need promote the first floor height with side direction stock and stock transverse brace, respectively increase for two lateral guide top of the trellis and connect a firmware, to prevent the unstability of long vertical rod in the saddle.Available fastener is connected between the standard scaffold tubes of firmware and the saddle, and locking mutually with the latch connecting hole and the latch of the duplex node in the 4th floor room from the bottom up on the firmware node connects.Then jack is tensioned between uppermost saddle suspension ring and the stock suspension ring, again with node on two stock lower nodes and two stocks respectively with the latch of attached beam duplex node be separated, the pulling jack, just side direction stock and stock transverse brace upwards can be promoted, after promoting the first floor height, its node is retightened on the attaching beam duplex node of floor of living in, remove jack, just finish lifting, thereby can carry out the constructing operation of desired area.When needs promote the first floor height with side direction saddle and saddle transverse brace etc., jack is tensioned between nethermost saddle suspension ring and the stock suspension ring, and all the other operating procedures are identical with the operating procedure that above-mentioned side direction stock and stock transverse brace rise basically.This scaffold is by above-mentioned twice lifting, returns to the state before promoting again, and the climbed height of first floor of whole scaffold carries out so repeatedly, and scaffold just can constantly raise.Letdown procedure is just in time opposite with climb procedure.
The utility model is except that possessing all advantages that aforementioned wall-attached (shear wall) liftable external scaffolding had, also has following advantage: 1. the crane scope of application is partly constructed from single highrise building shear wall and develop into the construction of the highrise building that vertically is discontinuous girder construction part (as side bar), widened the scope that crane is used widely; 2. attaching beam duplex joint structure is light and handy, reasonable in design, connects and simple and direct, the rapid convenience of dismantling operation, and is safe and reliable, still can adapt under building preformed hole situation devious and normal the use; 3. the employing of firmware makes the scaffold rising and descends safer reliable; 4. all members can be gathered materials on the spot, and process easily and promote the use.
Below in conjunction with drawings and Examples the utility model is further specified.
Fig. 1 is that a kind of concrete structure of the present utility model is contained in the side schematic view on the highrise building;
Fig. 2 is the state diagram after the stock among Fig. 1 upwards promotes the first floor height;
Fig. 3 is Fig. 1 amplification assumption diagram at first floor building attaching beam duplex node place from the bottom up;
Fig. 4 is the vertical view of Fig. 3;
Fig. 5 is the structure chart of π type duplex node accessory;
Fig. 6 and Fig. 7 are respectively Fig. 1 amplification assumption diagram at the second layer and three-storey building attaching beam duplex node place from the bottom up;
Fig. 8 is the vertical view of Fig. 7;
Fig. 9 is Fig. 2 amplification assumption diagram at attaching beam duplex node place, the 4th floor room from the bottom up;
Figure 10 and Figure 11 are respectively elevation and the left view that floor height changes adjustment part;
Figure 12 is the structure chart of firmware.
Reference numeral among the above-mentioned figure is: 1, side direction saddle, 2, the saddle transverse brace, 3, the side direction stock, 4, stock transverse brace, 5, the saddle suspension ring, 6, the stock suspension ring, 7, front rail handrail, 8, auxiliary rod, 9, transverse brace, 10, node on the saddle, 11, saddle lower node, 12, stock lower node, 13, node on the stock, 14, with the latch connecting hole; 15, π type duplex node accessory, 16, the strip through hole, 17, bolt and nut component; 18, pin hole, 19, latch, 20, cottor pin, 21, firmware, 22, the standard scaffold tubes, 23, firmware node, 24, with latch connecting hole, 25, floor height changes adjustment part, 26, pin hole, 27, connecting hole, 28, the building side bar, 29, prepare the side bar of construction, 30, masonry.
Referring to Fig. 1, between saddle transverse brace (2) and the side direction saddle (1), and between stock transverse brace (4) and the side direction stock (3), all connect with fastener.Referring to Fig. 3, rounded on the saddle lower node (11) with latch connecting hole (14).Referring to Fig. 6, be Long Circle with latch connecting hole (14) on the node on the saddle (10), rounded on the stock lower node (12) with latch connecting hole (14).Referring to Fig. 7, be Long Circle with latch connecting hole (14) on the node on the stock (13).
Referring to Figure 10 and Figure 11, the utlity model has several floor height variation adjustment parts (25) that can be matched with π type duplex node accessory (15), each adjustment part (25) both sides, top all have, following two pin holes (26), two of bottoms all have a connecting hole (27), in the utility model lifting process, if the building floor height changes, the connecting hole (27) of this part can be connected by bolt mutually with the pin hole (18) of π type duplex node accessory (15), replace pin hole (18) with pin hole (26), the position that is equivalent to reduction or raise pin hole (18), the normal lifting of shelf when changing to satisfy the building floor height.
When the supporting capacity of side bar (28) can not satisfy the load that the utility model transmits, can be on beam pre-buried suspension ring, connect the oblique flexibility of being made up of reinforcing bar or wire rope, wire tensioner again and reinforce pull bar temporarily on suspension ring, this pull bar other end is fixed in the building structure that can be enough to load.
Claims (3)
1, a kind of highrise building attaching beam formula lifting false work, have two upright side direction saddles (1), the saddle transverse brace (2) that between two side direction saddles (1), has several groups of differing heights that two ends are connected mutually with two side direction saddles (1) respectively, in the below of going up one group of saddle transverse brace (2) most, have two upright side direction stocks (3), the upright loop bar of these two side direction stocks (3) sliding sleeve respectively is combined in outside the upright guide rod of two side direction saddles (1), have between two side direction stocks (3) two ends respectively with two side direction stocks (3) be connected mutually on, following two groups of stock transverse braces (4), on two side direction saddles (1) and two side direction stocks (3), be fixed with respectively, following two saddle suspension ring (5) and last, following two stock suspension ring (6), have the front rail handrail (7) that is connected mutually with it respectively in the outside of side direction saddle (1) top and bottom, it is characterized in that:
A) both sides have respectively the upright auxiliary rod (8) that is connected mutually with side direction saddle (1), have the transverse brace (9) that two ends are connected mutually with auxiliary rod (8) respectively between the auxiliary rod (8);
B) on two side direction saddles (1) of two side direction stocks (3) below, all have node on the saddle (10) and saddle lower node (11) successively, have node (13) on stock lower node (12) and the stock respectively in two side direction stocks (3) bottom and top, on above-mentioned node, all have and latch connecting hole (14);
C) has the attaching beam duplex node of eight same structures, attaching beam duplex node has a π type duplex node accessory (15), the mainboard central authorities of duplex node accessory (15) have strip through hole (16), bolt and nut component (17) is housed in the hole, all have upper and lower two pin holes (18) on two side plates of duplex node accessory (15), a latch (19) respectively is housed in the hole, and an end of latch (19) is fixed with cottor pin (20);
D) have two firmwares (21) that are connected mutually and form by standard scaffold tubes (22) and firmware node (23), have on the firmware node (23) and latch connecting hole (24).
2, scaffold as claimed in claim 1, it is characterized in that, all rounded with latch connecting hole (14) on saddle lower node (11) and the stock lower node (12) all is Long Circle with latch connecting hole (14) on node on the saddle (10) and the stock on the node (13).
3, as claim 1,2 described scaffolds, it is characterized in that, have and severally can change adjustment parts (25) with the matched floor height of π type duplex node accessory (15), each adjustment part (25) both sides, top all have upper and lower two pin holes (26), and the both sides, bottom all have a connecting hole (27).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 03279315 CN2642925Y (en) | 2003-09-15 | 2003-09-15 | Attached beam type lifting scaffold for high-rise building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 03279315 CN2642925Y (en) | 2003-09-15 | 2003-09-15 | Attached beam type lifting scaffold for high-rise building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2642925Y true CN2642925Y (en) | 2004-09-22 |
Family
ID=34303398
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 03279315 Expired - Fee Related CN2642925Y (en) | 2003-09-15 | 2003-09-15 | Attached beam type lifting scaffold for high-rise building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2642925Y (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104652803A (en) * | 2015-02-02 | 2015-05-27 | 成军 | Attached scaffold for electric lifting guide rails |
-
2003
- 2003-09-15 CN CN 03279315 patent/CN2642925Y/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104652803A (en) * | 2015-02-02 | 2015-05-27 | 成军 | Attached scaffold for electric lifting guide rails |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201826525U (en) | Climbing shuttering system device for buildings | |
CN111255217A (en) | Elevator shaft shaping operation platform and operation method thereof | |
CN115538792A (en) | Residential building machine installation construction method and structure | |
CN214195484U (en) | All-steel attached lifting scaffold | |
CN113062584A (en) | Multipoint elevator shaft construction lifting platform and construction method | |
CN2642925Y (en) | Attached beam type lifting scaffold for high-rise building | |
CN209011528U (en) | A kind of all steel attachment type raise scaffold | |
CN215291319U (en) | Multi-point elevator shaft construction lifting platform | |
CN201502170U (en) | Horizontal supporting device of building external frame | |
CN215564320U (en) | A construction platform for encorbelmenting structure curtain installation | |
CN2597606Y (en) | plate-attached lifting scaffold for high-rise building | |
CN2122191U (en) | Lifting scaffold with auxiliary beam for high building | |
CN2276046Y (en) | Divided multistage automatic climbing external scaffold | |
CN2120841U (en) | Plate-attached lift scaffold for high-storey building | |
CN2692260Y (en) | Column hoop type lifting scaffold for high-rise building | |
CN113445723A (en) | Construction platform for mounting overhanging structure curtain wall and mounting method | |
CN209924409U (en) | Wall-attached self-climbing electric lifting platform | |
CN2683758Y (en) | High-rise building column bolt type lifting scaffold | |
CN219931561U (en) | Integral lifting type elevator shaft operation platform | |
CN2385026Y (en) | Full-assembled lower-bearing bridged guide lifting framing scaffold | |
CN2175805Y (en) | Integrated lifting scaffold capable of being segmented | |
CN218406382U (en) | A operation platform that encorbelments for construction of roofing overlength structure of encorbelmenting | |
CN2167147Y (en) | Scaffold attached to the out wall of a build | |
CN2563239Y (en) | Plug rod type lift scaffold for high rised balcong | |
CN219118718U (en) | Climbing frame horizontal protection |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |