CN218991142U - Building installation rail guard - Google Patents

Building installation rail guard Download PDF

Info

Publication number
CN218991142U
CN218991142U CN202320065499.9U CN202320065499U CN218991142U CN 218991142 U CN218991142 U CN 218991142U CN 202320065499 U CN202320065499 U CN 202320065499U CN 218991142 U CN218991142 U CN 218991142U
Authority
CN
China
Prior art keywords
guard
rail
railing
shaped
auxiliary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320065499.9U
Other languages
Chinese (zh)
Inventor
黄艳冬
李子超
赵辰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Zhugong Assembly Construction Co ltd
Original Assignee
Shandong Zhugong Assembly Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Zhugong Assembly Construction Co ltd filed Critical Shandong Zhugong Assembly Construction Co ltd
Priority to CN202320065499.9U priority Critical patent/CN218991142U/en
Application granted granted Critical
Publication of CN218991142U publication Critical patent/CN218991142U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model relates to the technical field of buildings, in particular to a building installation protective guard, which comprises two protective rods, wherein a protective guard and an auxiliary railing are arranged between the two protective rods, T-shaped threaded rods are movably arranged at the side end parts of the protective guard and the auxiliary railing, and the end parts of each T-shaped threaded rod are arranged in the protective rods through threads. According to the utility model, the upper end part of the lower railing is arranged into the guard rail and the auxiliary railing through threads, when a user installs two guard bars, the user can change the angle between the two guard bars according to the building ground requirement, when the two guard bars change angles, the angle between the guard rail and the auxiliary railing can change, the guard rail and the auxiliary railing rotate through the connecting plate, and the guard rail and the auxiliary railing are designed to be capable of changing angles, so that the user can conveniently install the guard bars at multiple angles, and the practicability of the guard bars is greatly improved.

Description

Building installation rail guard
Technical Field
The utility model relates to the technical field of buildings, in particular to a building installation protective fence.
Background
A large number of guard rails need to be installed in a building construction place, the guard rails can play a blocking role to prevent pedestrians from entering by mistake, but the existing guard rails for buildings cannot be changed in angle, the existing building guard rails are pure right-angle guard rails, the guard rails cannot be changed according to actual topography when in use, and the use difficulty is high.
Disclosure of Invention
In order to overcome the defects in the prior art, the utility model provides a building installation protective fence.
In order to solve the technical problems, the utility model provides the following technical scheme: the utility model provides a building installation rail guard, includes two guard bars, two install the rail guard between the guard bar and assist the railing, the equal movable mounting of side tip of rail guard and assist the railing has T shape threaded rod, every the tip of T shape threaded rod is all installed in the guard bar through the screw thread, at least two lower railing are all installed to the lower tip of rail guard and assist the railing, keep away from T shape threaded rod one side the side tip slidable mounting of rail guard has the connecting plate, keeps away from T shape threaded rod one side the side tip of assisting the railing rotates with the connecting plate to be connected, the side tip fixed mounting of connecting plate has T shape slide bar.
As a preferable technical scheme of the utility model, the side end parts of the guard rail and the auxiliary railing are respectively provided with a T-shaped groove, the end part of each T-shaped threaded rod is rotatably arranged in the T-shaped groove, and the circumferential surface of each T-shaped threaded rod is fixedly provided with a fixing sleeve.
As a preferable technical scheme of the utility model, a T-shaped chute is arranged at the side end part of the protective fence, the T-shaped slide bar is slidably arranged in the T-shaped chute, springs are fixedly arranged between the T-shaped slide bar and the inner wall of the T-shaped chute, and a rotating shaft is rotatably arranged between the connecting plate and the auxiliary railing.
Compared with the prior art, the utility model has the following beneficial effects:
1. the T-shaped threaded rod at the end part of the auxiliary railing is installed inside the other protective rod, because the length between the protective railing and the auxiliary railing is equal to the distance between the two protective rods, a user can push the auxiliary railing to one side of the protective railing, the auxiliary railing is stressed to drive the connecting plate to move, the connecting plate moves to drive the T-shaped slide rod to move, the T-shaped slide rod slides inside the T-shaped slide groove formed in the protective railing, at the moment, the distance between the protective railing and the auxiliary railing is shortened, the user can install the T-shaped threaded rod at the end part of the auxiliary railing into the protective rod, and the protective railing and the auxiliary railing are designed to be adjustable in length, so that the protective railing and the auxiliary railing are effectively and conveniently installed by the user.
2. The upper end of lower railing is through threaded mounting into rail guard and assist inside the railing, and the user is when installing two guard bars, and the user can change the angle between two guard bars according to building ground needs, and when two guard bars took place the angle change, can take place the angle change between rail guard and the assistance railing, and rail guard and assistance railing are rotated through the connecting plate, but through design into the angle change with rail guard and assistance railing to the facilitate the user carries out the multi-angle installation guard bar, has improved the practicality of guard bar greatly.
Drawings
FIG. 1 is a schematic view of a guard bar according to the present utility model;
FIG. 2 is a schematic diagram of a guard rail according to the present utility model;
FIG. 3 is a schematic view of the auxiliary rail of the present utility model;
fig. 4 is a schematic structural view of the connecting plate of the present utility model.
Wherein: 1. a protective rod; 11. a guard rail; 13. a T-shaped groove; 14. a T-shaped threaded rod; 15. a fixed sleeve; 16. t-shaped sliding grooves; 17. a lower railing; 2. a connecting plate; 21. a T-shaped slide bar; 22. a spring; 23. a rotating shaft; 24. auxiliary railing.
Detailed Description
In order that the manner in which the above recited features, objects and advantages of the present utility model are obtained will become readily apparent, a more particular description of the utility model will be rendered by reference to specific embodiments thereof which are illustrated in the appended drawings. Based on the examples in the embodiments, those skilled in the art can obtain other examples without making any inventive effort, which fall within the scope of the utility model. The experimental methods in the following examples are conventional methods unless otherwise specified, and materials, reagents, etc. used in the following examples are commercially available unless otherwise specified.
In the embodiment, as shown in fig. 1, fig. 2, fig. 3 and fig. 4, the building installation guard rail comprises two guard bars 1, a guard rail 11 and an auxiliary guard bar 24 are installed between the two guard bars 1, T-shaped threaded rods 14 are movably installed at the side end parts of the guard rail 11 and the auxiliary guard bar 24, the end parts of each T-shaped threaded rod 14 are installed in the guard bars 1 through threads, at least two lower guard bars 17 are installed at the lower end parts of the guard rail 11 and the auxiliary guard bar 24, a fixed sleeve 15 rotates to drive the T-shaped threaded rods 14 to rotate, the T-shaped threaded rods 14 rotate into threaded grooves formed in the guard bars 1, at the moment, the guard rail 11 is connected with the guard bars 1, a user installs the T-shaped threaded rods 14 at the end parts of the auxiliary guard bars 24 into the other guard bars 1, and can push the auxiliary guard bars 24 to one side of the guard rail 11 through threads, the auxiliary guard bars 24 are stressed to drive a connecting plate 2 to move, the T-shaped sliding rods 21 are driven to move, the T-shaped sliding rods 21 are arranged in the guard bars 11, and the side of the T-shaped sliding rods 16 are fixedly connected with the side of the end parts of the T-shaped threaded rods 2, which are far away from the side of the T-shaped threaded rods 2, and the side of the T-shaped sliding rods 2 is fixedly installed at the side of the end parts of the guard bars 2.
The T-shaped groove 13 has all been seted up to rail guard 11 and the side tip of assisting railing 24, the tip of every T-shaped threaded rod 14 all rotates to be installed in T-shaped groove 13 inside, the equal fixed cover 15 of circumference surface of every T-shaped threaded rod 14, the upper end of lower railing 17 is through screw thread installation into rail guard 11 and assisting railing 24 inside, the user when installing two guard bars 1, the user can change the angle between two guard bars 1 according to the building needs, when two guard bars 1 take place the angle change, can take place the angle change between rail guard 11 and assisting railing 24, rail guard 11 and assisting railing 24 take place the rotation through connecting plate 2, T-shaped spout 16 has been seted up to rail guard 11's side tip, T-shaped slide bar 21 slidable mounting is inside T-shaped spout 16, all fixed mounting spring 22 has between T-shaped slide bar 21 and the T-shaped spout 16 inner wall, rotate between connecting plate 2 and assisting railing 24 and install pivot 23.
Working principle:
firstly, when a user installs a guard rail 11 and an auxiliary railing 24, the user firstly fixes two guard bars 1 on the ground, the user firstly pushes a T-shaped threaded rod 14 at the side end part of the guard rail 11 to be opposite to a threaded groove on the side wall of the guard bar 1, the user rotates a fixed sleeve 15, the fixed sleeve 15 rotates to drive the T-shaped threaded rod 14 to rotate, the T-shaped threaded rod 14 rotates into the threaded groove formed by the guard bar 1, at the moment, the guard rail 11 is connected with the guard bar 1, the user installs the T-shaped threaded rod 14 at the end part of the auxiliary railing 24 into the other guard bar 1, because the length between the guard rail 11 and the auxiliary railing 24 is equal to the distance between the two guard bars 1, the user can push the auxiliary railing 24 to the guard rail 11, the auxiliary railing 24 is stressed to drive a connecting plate 2 to move, the connecting plate 2 moves to drive the T-shaped sliding rod 21 to move, the T-shaped sliding rod 21 slides inside the T-shaped sliding rod 16 formed by the guard rail 11, at the moment, the distance between the guard rail 11 and the auxiliary railing 24 is shortened, the user can install the T-shaped threaded rod 14 at the end part of the auxiliary railing 24 into the guard rail 1, the guard rail 24 can be conveniently installed into the guard rail 11 through the guard rail 24, and the guard rail can be conveniently installed by the guard rail 11.
Second, after the installation of the guard rail 11 and the auxiliary rail 24 is completed, the user can install the upper end of the lower rail 17 into the guard rail 11 and the auxiliary rail 24, the upper end of the lower rail 17 is installed into the guard rail 11 and the auxiliary rail 24 through threads, the user can change the angle between the two guard bars 1 according to the construction ground requirement when installing the two guard bars 1, and when the two guard bars 1 change angle, the guard rail 11 and the auxiliary rail 24 can change angle, the guard rail 11 and the auxiliary rail 24 rotate through the connecting plate 2, and the guard rail 11 and the auxiliary rail 24 are designed to change angle, so that the user can install the guard bars 1 at multiple angles, and the practicability of the guard bars 1 is greatly improved.
The embodiments of the present utility model have been described in detail with reference to the drawings, but the present utility model is not limited thereto, and various changes can be made within the knowledge of those skilled in the art without departing from the spirit of the present utility model.

Claims (6)

1. The utility model provides a building installation rail guard, includes two guard bars (1), its characterized in that, two install rail guard (11) and assist railing (24) between guard bar (1), the equal movable mounting of side tip of rail guard (11) and assist railing (24) has T shape threaded rod (14), every the tip of T shape threaded rod (14) is all through threaded mounting in guard bar (1), at least two lower railing (17) are all installed to the lower tip of rail guard (11) and assist railing (24), keep away from T shape threaded rod (14) one side the side tip slidable mounting of rail guard (11) has connecting plate (2), keeps away from the side tip of assisting railing (24) of T shape threaded rod (14) one side is connected with connecting plate (2) rotation, the side tip fixed mounting of connecting plate (2) has T shape slide bar (21).
2. A building installation guard rail according to claim 1, characterized in that the side ends of the guard rail (11) and the auxiliary rail (24) are provided with T-shaped grooves (13), and the end of each T-shaped threaded rod (14) is rotatably mounted inside the T-shaped groove (13).
3. A building installation guard rail according to claim 1, characterized in that the circumferential surface of each of the T-shaped threaded rods (14) is fixedly fitted with a fixing sleeve (15).
4. A building installation guard rail according to claim 1, characterized in that the side end of the guard rail (11) is provided with a T-shaped chute (16), the T-shaped slide bar (21) being slidably mounted inside the T-shaped chute (16).
5. The building installation guard rail of claim 4, wherein springs (22) are fixedly arranged between the T-shaped sliding rods (21) and the inner walls of the T-shaped sliding grooves (16).
6. A building installation guard rail according to claim 1, characterized in that a rotation shaft (23) is rotatably mounted between the connection plate (2) and the auxiliary rail (24).
CN202320065499.9U 2023-01-07 2023-01-07 Building installation rail guard Active CN218991142U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320065499.9U CN218991142U (en) 2023-01-07 2023-01-07 Building installation rail guard

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320065499.9U CN218991142U (en) 2023-01-07 2023-01-07 Building installation rail guard

Publications (1)

Publication Number Publication Date
CN218991142U true CN218991142U (en) 2023-05-09

Family

ID=86222640

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320065499.9U Active CN218991142U (en) 2023-01-07 2023-01-07 Building installation rail guard

Country Status (1)

Country Link
CN (1) CN218991142U (en)

Similar Documents

Publication Publication Date Title
CN108952123B (en) Slope finding and surface plastering device for concrete or mortar around floor drain and using method thereof
CN218991142U (en) Building installation rail guard
CN219177381U (en) Building design measuring equipment
CN111389861B (en) Steel construction building solid waste recovery processing equipment
CN116026993A (en) House construction engineering crack detection device
CN216621886U (en) Multi-functional intelligent air sampler
CN209364529U (en) A kind of digital precision cutter replacer
CN216974160U (en) Building templates of convenient connection
CN214365439U (en) Protection architecture for building engineering of adjustable size
CN219757324U (en) Level bar that building engineering used
CN116201354B (en) High-rise concrete structure support and construction method thereof
CN217639067U (en) Portable slope soil erosion and water loss observation device
CN216954610U (en) Soil and water conservation monitoring devices
CN220225916U (en) Wallboard for civil engineering construction
CN219734852U (en) Laser radar anemometer installing support
CN221120592U (en) Expansion screw for building decoration construction
CN221219324U (en) High leakproofness steel structure roof connection structure
CN218233502U (en) Foundation pit supporting structure
CN219490764U (en) Safety warning device for municipal works
CN216586527U (en) Anchor rod construction device for constructional engineering
CN219586607U (en) Safety warning mechanism for bridge construction
CN215366675U (en) Road surface floating device with adjusting mechanism for road paving
CN214368982U (en) Adjusting device of display
CN212537424U (en) Be used for large-scale bridge construction supervisory equipment
CN215052347U (en) Electronic warning board for building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant