CN218061515U - Civil engineering construction pre-embedding equipment - Google Patents

Civil engineering construction pre-embedding equipment Download PDF

Info

Publication number
CN218061515U
CN218061515U CN202220879803.9U CN202220879803U CN218061515U CN 218061515 U CN218061515 U CN 218061515U CN 202220879803 U CN202220879803 U CN 202220879803U CN 218061515 U CN218061515 U CN 218061515U
Authority
CN
China
Prior art keywords
groove
rod
civil engineering
lower extreme
mounting panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220879803.9U
Other languages
Chinese (zh)
Inventor
张涛
付迪
刘宇
薛飞
严强华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Engineering Group Co Ltd
China Railway Construction Engineering Group Second Construction Co Ltd
Original Assignee
China Railway Construction Engineering Group Co Ltd
China Railway Construction Engineering Group Shandong Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Engineering Group Co Ltd, China Railway Construction Engineering Group Shandong Co Ltd filed Critical China Railway Construction Engineering Group Co Ltd
Priority to CN202220879803.9U priority Critical patent/CN218061515U/en
Application granted granted Critical
Publication of CN218061515U publication Critical patent/CN218061515U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a civil engineering pre-buried equipment, including the mounting panel, the lower extreme of mounting panel is equipped with a plurality of connecting thread grooves, every equal threaded connection in the connecting thread groove has the connecting rod, every the lower extreme of connecting rod all is equipped with the shifting chute, every equal sliding connection has the carriage release lever in the shifting chute, every the front side of connecting rod all is equipped with first mounting hole, every all install first fixing bolt on the first mounting hole, every the auxiliary rod is all installed to the lower extreme of carriage release lever, every the equal fixedly connected with base of lower extreme of auxiliary rod, every the upper end of base all rotates through the hinge and is connected with the folded sheet. The device can carry out quick adjustment according to the actual demand through the degree of depth of a fixing bolt adjusting base, and connecting rod and movable block isotructure that set up simultaneously can be dismantled this dismantlement and fold, the effectual area that reduces the device, and then the cost of transportation of lower device.

Description

Civil engineering construction pre-embedding equipment
Technical Field
The utility model relates to a civil engineering technical field especially relates to a civil engineering pre-buried equipment.
Background
The civil engineering is an engineering subject for building various facilities and places for activities such as human life, production, protection and the like, and covers the construction of buildings, structures and engineering works in the facilities and places in engineering ranges such as houses, roads, railways, airports, bridges, water conservancy projects, ports, tunnels, water supply and drainage, protection and the like in various categories such as the ground, the underground, the land, the water, the underwater and the like;
in civil engineering work progress, need install various equipment instrument, and in order to guarantee safety and stability, generally fix the built-in fitting inside the concrete earlier, current pre-buried operation, it is fixed to advance the installation through the bolt usually, it is more loaded down with trivial details to operate to the pre-buried pole from the area is little with concrete area of contact, deviates from easily, poor stability, and the pre-buried pole is fixed on the pre-buried board usually, leads to in the transportation, and area is great, and the cost of transportation is higher.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the shortcomings existing in the prior art and providing a civil engineering pre-buried equipment.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a civil engineering pre-buried equipment, includes the mounting panel, the lower extreme of mounting panel is equipped with a plurality of connecting thread grooves, every equal threaded connection has the connecting rod in the connecting thread groove, every the lower extreme of connecting rod all is equipped with the shifting chute, every equal sliding connection has the carriage release lever, every in the shifting chute the front side of connecting rod all is equipped with first mounting hole, every all install first fixing bolt on the first mounting hole, every the auxiliary rod, every are all installed to the lower extreme of carriage release lever the equal fixedly connected with base of lower extreme of auxiliary rod, every the upper end of base all is connected with the folded sheet through the hinge rotation, every the upper end of base all is equipped with two standing grooves, the upper end of mounting panel is equipped with two connecting blocks, be equipped with two on the mounting panel and correspond connecting block matched with adjusting part, every all be equipped with fixed establishment on the auxiliary rod.
Preferably, the fixing mechanism includes moving blocks arranged on each auxiliary rod, a through groove is formed in the upper end of each moving block, each auxiliary rod penetrates through the corresponding through groove, two limiting holes are formed in the front side of each auxiliary rod, a second mounting hole is formed in the front side of each moving block, a second fixing bolt is mounted on each second mounting hole, fixing blocks are fixedly connected to the left side and the right side of each moving block, and a first T-shaped groove and a second T-shaped groove are formed in each folding plate.
Preferably, the adjusting part is including setting up two welding grooves in the mounting panel upper end, two all be equipped with the welding bench, two on the welding bench all be equipped with the regulation thread groove, two equal threaded connection has adjusting threaded rod, two in the regulation thread groove adjusting threaded rod's the opposite side all rotates with the connecting block that corresponds and is connected, two all be equipped with the guide bar on the welding bench, two the guide bar all runs through the welding bench that corresponds and with the connecting block fixed connection that corresponds, two the upper end of connecting block all is equipped with vertical thread groove.
Preferably, each fixed block comprises an L-shaped plate and a limiting plate, and the moving blocks and the fixed blocks are made of stainless steel.
Preferably, each moving groove is a square groove, and each moving rod is a square rod.
Preferably, each of the first T-shaped grooves is a vertical T-shaped groove, and each of the second T-shaped grooves is a horizontal T-shaped groove.
Compared with the prior art, the device has the advantages that:
1. the utility model discloses a distance between folding plate and the mounting panel of downside can be adjusted through first fixing bolt in the setting, can adjust according to actual conditions, and the folding plate can be vertical folding in not using the process simultaneously, has reduced device's area, and the device of being convenient for carries the transportation.
2. The utility model discloses a set up adjusting part, connecting rod, connecting thread groove isotructure, can adjust the position of two corresponding connecting blocks through adjusting part, be convenient for be connected the device with other equipment, connecting rod accessible is rotatory to be dismantled simultaneously, after dismantling, has further reduced the device's area, and then has reduced the cost of transportation.
Drawings
Fig. 1 is a schematic structural view of a civil engineering construction pre-buried device provided by the utility model;
FIG. 2 is a cross-sectional view of FIG. 1;
FIG. 3 is an enlarged view of the structure at A in FIG. 2;
fig. 4 is an enlarged view of the structure at B in fig. 2.
In the figure: 1 mounting panel, 2 connecting rods, 3 carriage release levers, 4 standing grooves, 5 auxiliary rod, 6 folded sheets, 7 bases, 8 adjusting part, 9 connecting blocks, 10 movable blocks, 11 fixed blocks, 12 spacing holes, 13 first T-shaped grooves, 14 second T-shaped grooves, 15 first fixing bolt, 16 second fixing bolt.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-4, a civil engineering pre-buried equipment, including mounting panel 1, the lower extreme of mounting panel 1 is equipped with a plurality of connecting thread grooves, every connecting thread inslot all has connecting rod 2, connecting rod 2 can be dismantled or installed through the rotation, the lower extreme of every connecting rod 2 all is equipped with the shifting chute, equal sliding connection has carriage release lever 3 in every shifting chute, the front side of every connecting rod 2 all is equipped with first mounting hole, all install first fixing bolt 15 on every first mounting hole, the rear side of first fixing bolt 15 all extends to the shifting chute, can fix carriage release lever 3 fast through first fixing bolt 15, auxiliary rod 5 is all installed to the lower extreme of every carriage release lever 3, the equal fixedly connected with base 7 of the lower extreme of every auxiliary rod 5, the upper end of every base 7 all is connected with folding plate 6 through the hinge rotation, the upper end of every base 7 all is equipped with two standing grooves 4, when turning folding plate 6 ninety, folding plate 6 can rotate to the corresponding standing groove 4 in, the upper end of mounting panel 1 is equipped with two connecting blocks 9, mounting panel 1 is equipped with two matched with the adjusting part that corresponds to adjust the subassembly.
In the utility model, each auxiliary rod 5 is provided with a fixing mechanism, the fixing mechanism comprises a moving block 10 arranged on each auxiliary rod 5, the upper end of each moving block 10 is provided with a through groove, each auxiliary rod 5 runs through the corresponding through groove, the front side of each auxiliary rod 5 is provided with two limit holes 12, the front side of each moving block 10 is provided with a second mounting hole, a second fixing bolt 16 is mounted on the second mounting hole, the rear side of the second fixing bolt 16 can enter into the corresponding limit hole 12, the fixing of the moving block 10 is realized, the fixed blocks 11 are fixedly connected to the left side and the right side of each moving block 10, each folding plate 6 is provided with a first T-shaped groove 13 and a second T-shaped groove 14, each first T-shaped groove 13 is a vertical T-shaped groove, each second T-shaped groove 14 is a transverse T-shaped groove, when the folding plate 6 is rotated to a vertical position, the fixed blocks 11 at the two sides of the moving block 10 can be synchronously inserted into the corresponding first T-shaped groove 13, the fixing of the two folding plates 6 can be fixed, when the two folding plates 6 are rotated to a vertical position, the two horizontal T-shaped grooves are in the moving block 14, the moving block 10, and the moving block can be driven to be in a state when the second T-shaped groove 14 is moved from the vertical T-shaped groove;
the adjusting assembly 8 comprises two welding grooves formed in the upper end of the mounting plate 1, welding platforms are arranged on the two welding grooves, adjusting thread grooves are formed in the two welding platforms, adjusting threaded rods are connected in the two adjusting thread grooves in a threaded manner, the opposite sides of the two adjusting threaded rods are rotationally connected with the corresponding connecting blocks 9, guide rods are arranged on the two welding platforms, penetrate through the corresponding welding platforms and are fixedly connected with the corresponding connecting blocks 9, vertical thread grooves are formed in the upper ends of the two connecting blocks 9, the corresponding connecting blocks 9 can be driven to move left and right by rotating the adjusting threaded rods, the adjusting assembly can be adjusted to a proper position according to requirements, and is connected with other equipment through the connecting blocks 9;
every fixed block 11 includes that L shaped plate and limiting plate constitute, and every movable block 10 is the stainless steel with the material of fixed block 11, and every shifting chute is square groove, and every carriage release lever 3 is square pole, improves the stability that first fixing bolt 15 is fixed.
The utility model discloses during the use, after transporting the device to appointed position, through rotatory auxiliary rod 5, install auxiliary rod 5 in the threaded connection thread groove of mounting panel 1 lower extreme, then according to pre-buried degree of depth, loosen carriage release 3 through first fixing bolt 15, and move it to suitable position, fix carriage release 3 through first fixing bolt 15, rethread second fixing bolt 16 loosens movable block 10, mention movable block 10 upwards, two fixed blocks 11 break away from corresponding first T-slot 13 thereupon, rotate two folded sheets 6 this moment to ninety degrees and place at standing groove 4, move movable block 10 downwards again, make two fixed blocks 11 insert in second T-slot 14, fix two folded sheets 6, fix movable block 10 through second fixing bolt 16 at last, accomplish the equipment operation, when needing to be connected with external device, drive corresponding connecting block 9 through the rotation regulation threaded rod and move to suitable position, and carry out the installation operation can;
the device can carry out quick adjustment according to the actual demand through the degree of depth that first fixing bolt 15 adjusted base 7, and connecting rod 2 and the movable block 10 isotructure that set up simultaneously can dismantle this dismantlement and fold, the effectual area that has reduced the device, and then lower the cost of transportation of device.
The above, only be the embodiment of the preferred of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, which are designed to be replaced or changed equally, all should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a civil engineering construction pre-buried equipment, includes mounting panel (1), its characterized in that, the lower extreme of mounting panel (1) is equipped with a plurality of connecting thread grooves, every equal threaded connection has connecting rod (2), every in the connecting thread groove the lower extreme of connecting rod (2) all is equipped with the shifting chute, every equal sliding connection has carriage release lever (3), every in the shifting chute the front side of connecting rod (2) all is equipped with first mounting hole, every all install first fixing bolt (15), every on the first mounting hole auxiliary rod (5), every are all installed to the lower extreme of carriage release lever (3) the equal fixedly connected with base (7) of lower extreme of auxiliary rod (5), every the upper end of base (7) all is connected with folded sheet (6) through the hinge rotation, every the upper end of base (7) all is equipped with two standing grooves (4), the upper end of mounting panel (1) is equipped with two connecting blocks (9), be equipped with two and correspond connecting block (9) matched with adjusting part (8) on mounting panel (1), every auxiliary rod (5) all are equipped with fixed establishment.
2. The civil engineering pre-buried equipment of claim 1, wherein the fixing mechanism comprises moving blocks (10) arranged on each auxiliary rod (5), a through groove is formed in the upper end of each moving block (10), each auxiliary rod (5) penetrates through the corresponding through groove, two limiting holes (12) are formed in the front side of each auxiliary rod (5), a second mounting hole is formed in the front side of each moving block (10), a second fixing bolt (16) is mounted on each second mounting hole, fixing blocks (11) are fixedly connected to the left side and the right side of each moving block (10), and a first T-shaped groove (13) and a second T-shaped groove (14) are formed in each folding plate (6).
3. The civil engineering pre-buried equipment of claim 1, characterized in that, adjusting part (8) is including setting up two welding grooves in mounting panel (1) upper end, two all be equipped with the welding bench on the welding groove, two all be equipped with the regulation thread groove on the welding bench, two equal threaded connection has adjusting threaded rod in the regulation thread groove, two adjusting threaded rod's opposite side all rotates with connecting block (9) that correspond to be connected, two all be equipped with the guide bar on the welding bench, two the guide bar all runs through the welding bench that corresponds and with connecting block (9) fixed connection that corresponds, two the upper end of connecting block (9) all is equipped with vertical thread groove.
4. The civil engineering embedded equipment as claimed in claim 2, wherein each fixed block (11) comprises an L-shaped plate and a limiting plate, and the moving blocks (10) and the fixed blocks (11) are made of stainless steel.
5. A civil engineering pre-buried equipment according to claim 1, characterized in that each of the moving grooves is a square groove, and each of the moving rods (3) is a square rod.
6. A civil engineering pre-buried apparatus according to claim 2, characterised in that each of the first T-shaped grooves (13) is a vertical T-shaped groove and each of the second T-shaped grooves (14) is a transverse T-shaped groove.
CN202220879803.9U 2022-04-17 2022-04-17 Civil engineering construction pre-embedding equipment Active CN218061515U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220879803.9U CN218061515U (en) 2022-04-17 2022-04-17 Civil engineering construction pre-embedding equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220879803.9U CN218061515U (en) 2022-04-17 2022-04-17 Civil engineering construction pre-embedding equipment

Publications (1)

Publication Number Publication Date
CN218061515U true CN218061515U (en) 2022-12-16

Family

ID=84417779

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220879803.9U Active CN218061515U (en) 2022-04-17 2022-04-17 Civil engineering construction pre-embedding equipment

Country Status (1)

Country Link
CN (1) CN218061515U (en)

Similar Documents

Publication Publication Date Title
CN213233477U (en) Foundation pit supporting structure and foundation pit slope supporting system
CN110924650B (en) House construction operation platform and installation mode
CN113417455B (en) Self-reinforcing supporting rod for slip form construction
CN218061515U (en) Civil engineering construction pre-embedding equipment
CN112761409B (en) Auxiliary building system for 5G signal base station
CN105113536A (en) Movable sidewall formwork erecting system for underground structure and construction method of system
CN111946081A (en) Dig wall telephone
CN107313451B (en) Inner supporting device of basement prefabricated slab forming die and construction method thereof
CN208363650U (en) The mounting bracket of prefabricated components, the precast wall body containing the bracket
CN111502264B (en) Fixed template structure of pouring frame for civil construction engineering construction
CN110777837B (en) Construction method of fabricated building mixed tower crane
CN214364824U (en) Strutting arrangement for building engineering
CN220746937U (en) Reinforcing device for building foundation pit in civil engineering
CN206839615U (en) A kind of boring device of top plate
CN216921499U (en) Top bracing device for controlling crack of super-long reinforced concrete structure
CN220301867U (en) Building construction precast floor plank strutting arrangement
CN219866603U (en) Guide rail with adjustable height
CN210918169U (en) Outer frame in lighting well
CN212298225U (en) Measuring instrument fixing support for high-rise frame steel structure
CN217204082U (en) Civil engineering pile foundation construction structures
CN221031386U (en) Open cut rectangle side wall unilateral upright die strutting arrangement
CN218597382U (en) Prefabricated plate connection structure for building
CN219931627U (en) Unilateral formwork construction device of basement outer wall
CN217326550U (en) Brickwork construction pin-connected panel auxiliary fixtures
CN217975399U (en) Simple device for reinforcing stair step formwork

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 100071 Nord tower 1, 128 South Fourth Ring Road West, Fengtai District, Beijing.

Patentee after: China Railway Construction Engineering Group

Patentee after: China Railway Construction Group No.2 Construction Co.,Ltd.

Address before: Building 1, Nord center, No.128, South Fourth Ring Road West, Fengtai District, Beijing, 100070

Patentee before: China Railway Construction Engineering Group

Patentee before: CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP SHANDONG Co.,Ltd.