CN218060414U - Piping lane prefab and assembled utility tunnel - Google Patents

Piping lane prefab and assembled utility tunnel Download PDF

Info

Publication number
CN218060414U
CN218060414U CN202221920439.2U CN202221920439U CN218060414U CN 218060414 U CN218060414 U CN 218060414U CN 202221920439 U CN202221920439 U CN 202221920439U CN 218060414 U CN218060414 U CN 218060414U
Authority
CN
China
Prior art keywords
pipe gallery
wall
piping lane
base
footstock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221920439.2U
Other languages
Chinese (zh)
Inventor
田建平
顾鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inner Mongolia Architectural Survey Design And Research Institute Co ltd
Original Assignee
Inner Mongolia Architectural Survey Design And Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inner Mongolia Architectural Survey Design And Research Institute Co ltd filed Critical Inner Mongolia Architectural Survey Design And Research Institute Co ltd
Priority to CN202221920439.2U priority Critical patent/CN218060414U/en
Application granted granted Critical
Publication of CN218060414U publication Critical patent/CN218060414U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a piping lane prefab and assembled utility tunnel, including the assembly subassembly, the assembly subassembly includes two piping lane bases, base outer wall, piping lane inner wall, piping lane outer wall and piping lane footstock; the positioning and supporting mechanism comprises a threaded column, a positioning block, a positioning groove, a supporting frame, a limiting frame and a central support. The utility model discloses a piping lane inner wall splices with the piping lane base, the inside that makes the screw thread post of piping lane inner wall slide in the locating piece is fixed a position, then remove the support frame and slide in the constant head tank, splice the installation to the support frame, then remove the piping lane footstock and cover on piping lane inner wall and support frame, then utilize the nut to be connected with the screw thread post, thereby the stability of piping lane prefab junction has been increased, then support power has been provided for piping lane prefab inner wall through support frame and center support, and then when concrete placement, need not to install additional support equipment alone and support, the operation steps are simplified, and the construction efficiency is improved.

Description

Piping lane prefab and assembled utility tunnel
The technical field is as follows:
the utility model relates to a piping lane technical field specifically is a piping lane prefab and assembled utility tunnel.
Background art:
the utility tunnel is an underground urban pipeline utility tunnel, namely a tunnel space is built underground in a city, various engineering pipelines such as electric power, communication, gas, heat supply, water supply and drainage and the like are integrated, a special overhaul port, a lifting port and a monitoring system are arranged, unified planning, unified design, unified construction and management are implemented, and the utility tunnel is an important infrastructure and a lifeline for guaranteeing urban operation; the prefabricated assembly type comprehensive pipe gallery is a comprehensive pipe gallery which is prefabricated in advance for each structural part of the comprehensive pipe gallery, then is quickly spliced in a construction site, and then is poured by utilizing concrete, and compared with the traditional pouring type pipe gallery, the construction method is simpler;
traditional assembled utility tunnel is when installing the use, is adopting the mode of concatenation to connect between the piping lane prefab usually to lead to stability between the piping lane prefab relatively poor, and then lead to when carrying out concrete placement, utilize a large amount of support devices to support utility tunnel inside usually, increased the operating procedure when constructing, influenced the efficiency of construction, for this reason, propose a piping lane prefab and assembled utility tunnel.
The utility model has the following contents:
an object of the utility model is to provide a piping lane prefab and assembled utility tunnel to solve one of the problem that proposes among the above-mentioned background art.
The utility model discloses by following technical scheme implement: piping lane prefab and assembled utility tunnel, include
The assembly component comprises two pipe gallery bases, base outer walls, pipe gallery inner walls, pipe gallery outer walls and pipe gallery top seats;
the positioning and supporting mechanism comprises a threaded column, a positioning block, a positioning groove, a supporting frame, a limiting frame and a central bracket;
two the bottom of piping lane base all is equipped with the base outer wall, two the top of piping lane base all is equipped with the piping lane footstock, the lateral wall symmetry sliding connection of piping lane base and piping lane footstock has two piping lane inner walls, the inboard symmetry sliding connection of base outer wall has two piping lane outer walls, two the even fixedly connected with screw thread post of inside wall of piping lane inner wall, the even fixedly connected with locating piece in one side that piping lane base and piping lane footstock are adjacent, the lateral wall sliding connection of screw thread post is in the inside wall of locating piece, two constant head tanks, two have all been seted up to the inside wall of piping lane inner wall, piping lane base and piping lane footstock the inside wall sliding connection of constant head tank has two support frames, two the equal fixedly connected with center support in inside part of support frame.
As further preferable in the present technical solution: the even fixedly connected with second steel reinforcement frame of inside wall of piping lane inner wall, the one end fixed connection of second steel reinforcement frame is in the inside wall of piping lane outer wall.
As a further preferred aspect of the present invention: pipe rack base, pipe rack inner wall and one side of pipe rack footstock are equipped with the inside concave part of pipe rack, the opposite side of pipe rack base, pipe rack inner wall and pipe rack footstock is equipped with the outer convex part of pipe rack, the inside concave part of pipe rack with the adaptation of pipe rack evagination portion.
As a further preferred aspect of the present invention: two the equal symmetry fixedly connected with of inside wall of support frame has two spacing.
As a further preferred aspect of the present invention: two cardboards of the equal symmetry fixedly connected with of inside wall of piping lane base, piping lane inner wall and piping lane footstock, one the inside wall sliding connection of cardboard has the fixed block, another the inside wall sliding connection of cardboard has the screw thread piece.
As a further preferred aspect of the present invention: the middle part of one side of fixed block is rotated through the bearing and is connected with the threaded rod, the lateral wall of threaded rod with the inside wall threaded connection of screw block.
As further preferable in the present technical solution: one side of the inner side wall of the threaded rod is connected with a sliding rod in a sliding mode.
As a further preferred aspect of the present invention: the even fixedly connected with first steel reinforcement frame of inside wall of piping lane base and piping lane footstock, one side fixed connection in one side of first steel reinforcement frame of base outer wall.
The utility model has the advantages that: the utility model discloses a piping lane inner wall splices with the piping lane base, the inside that the screw thread post that makes the piping lane inner wall slips into the locating piece is fixed a position, then remove the support frame and slide into in the constant head tank, splice the installation to the support frame, then remove the piping lane footstock and cover on piping lane inner wall and support frame, then utilize the nut to be connected with the screw thread post, thereby the stability of piping lane prefab junction has been increased, then support power has been provided for piping lane prefab inner wall through support frame and central support, and then when concrete placement, need not to install the support equipment alone and support, operating procedure when having simplified the construction, the efficiency of construction is improved.
Description of the drawings:
in order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic axial side structure view of the pipe gallery base of the present invention;
FIG. 3 is an exploded view of the structure of FIG. 2 in accordance with the present invention;
fig. 4 is a schematic sectional view of the present invention.
In the figure: 1. assembling the components; 2. a positioning support mechanism; 101. a pipe gallery base; 102. an outer wall of the base; 103. the inner wall of the pipe gallery; 104. the outer wall of the pipe gallery; 105. a pipe gallery top seat; 201. a threaded post; 202. positioning blocks; 203. positioning a groove; 204. a support frame; 205. a limiting frame; 206. a center support; 41. a first reinforcing bar frame; 42. a second steel bar frame; 43. a pipe gallery recess; 44. a pipe gallery outer convex part; 45. clamping a plate; 46. a fixed block; 47. a thread block; 48. a threaded rod; 49. a slide bar.
The specific implementation mode is as follows:
the technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts all belong to the protection scope of the present invention.
Examples
Referring to fig. 1-4, the present invention provides a technical solution: piping lane prefab and assembled utility tunnel, include
The assembly component 1 comprises two pipe gallery bases 101, base outer walls 102, pipe gallery inner walls 103, pipe gallery outer walls 104 and pipe gallery top seats 105;
the positioning and supporting mechanism 2 comprises a threaded column 201, a positioning block 202, a positioning groove 203, a supporting frame 204, a limiting frame 205 and a central bracket 206;
the bottom of two piping lane bases 101 all is equipped with base outer wall 102, the top of two piping lane bases 101 all is equipped with piping lane footstock 105, the lateral wall symmetry sliding connection of piping lane base 101 and piping lane footstock 105 has two piping lane inner walls 103, the inboard symmetry sliding connection of base outer wall 102 has two piping lane outer walls 104, the even fixedly connected with screw thread post 201 of the inside wall of two piping lane inner walls 103, the even fixedly connected with locating piece 202 in one side that piping lane base 101 and piping lane footstock 105 are adjacent, screw thread post 201's lateral wall sliding connection is in the inside wall of locating piece 202, piping lane inner wall 103, two constant head tanks 203 have all been seted up to the inside wall of piping lane base 101 and piping lane footstock 105, the inside wall sliding connection of two constant head tanks 203 has two support frames 204, the equal fixedly connected with center support 206 in middle part of the inside wall of two support frames 204.
In this embodiment, specifically: the inner side wall of the pipe gallery inner wall 103 is uniformly and fixedly connected with a second steel bar frame 42, and one end of the second steel bar frame 42 is fixedly connected with the inner side wall of the pipe gallery outer wall 104; a pourable space is formed between the inner 103 and outer 104 tube lane walls by the second steel frames 42.
In this embodiment, specifically: one side of the pipe rack base 101, the pipe rack inner wall 103 and the pipe rack top seat 105 is provided with a pipe rack inner concave part 43, the other side of the pipe rack base 101, the pipe rack inner wall 103 and the pipe rack top seat 105 is provided with a pipe rack outer convex part 44, and the pipe rack inner concave part 43 is matched with the pipe rack outer convex part 44; drive single piping lane prefab motion through the loop wheel machine, make piping lane convex part 44 slide in the pipe gallery concave part 43 to link together two pipe galleries after the concatenation.
In this embodiment, specifically: the inner side walls of the two support frames 204 are symmetrically and fixedly connected with two limit frames 205; the inner wall of the support frame 204 is provided with a supporting force by the limiting frame 205.
In this embodiment, specifically: the inner side walls of the pipe rack base 101, the pipe rack inner wall 103 and the pipe rack top seat 105 are symmetrically and fixedly connected with two clamping plates 45, the inner side wall of one clamping plate 45 is connected with a fixed block 46 in a sliding mode, and the inner side wall of the other clamping plate 45 is connected with a threaded block 47 in a sliding mode; carry on spacingly through cardboard 45 to fixed block 46 and screw thread piece 47.
In this embodiment, specifically: one side of the inner side wall of the threaded rod 48 is connected with a sliding rod 49 in a sliding manner; the threaded rod 48 is driven to rotate by rotating the sliding rod 49; the middle part of one side of the fixed block 46 is rotatably connected with a threaded rod 48 through a bearing, and the outer side wall of the threaded rod 48 is in threaded connection with the inner side wall of the threaded block 47; the threaded rod 48 is rotated to drive the spliced pipe gallery prefabricated members to move towards one another by the threaded block 47 and the clamping plate 45.
In this embodiment, specifically: the inner side walls of the pipe gallery base 101 and the pipe gallery top seat 105 are uniformly and fixedly connected with a first reinforcing steel bar frame 41, and one side of the base outer wall 102 is fixedly connected with one side of the first reinforcing steel bar frame 41; the first steel frames 41 provide a supporting force to one side of the pipe rack base 101, so that a space for pouring is formed between the pipe rack base 101 and the outer wall 102 of the base.
Working principle or structural principle: during the use, through removing two pipe gallery inner walls 103 and pipe gallery outer wall 104 and drive the screw thread post 201 motion, then insert pipe gallery inner wall 103 and pipe gallery outer wall 104 between pipe gallery base 101 and base outer wall 102, splice pipe gallery inner wall 103 and pipe gallery outer wall 104, then slide into the inside of locating piece 202 through the screw thread post 201 of motion, fix a position pipe gallery inner wall 103 and pipe gallery outer wall 104, then utilize nut extrusion locating piece 202 to be connected with screw thread post 201, thereby increased the stability of pipe gallery inner wall 103 and pipe gallery base 101 junction, then remove support frame 204 and drive spacing frame 205 and central support 206 motion, guide and fix a position the support frame 204 of motion through the constant head tank 203 that sets up in pipe gallery base 101 and pipe gallery inner wall 103, then remove pipe gallery footstock 105 and cover on pipe gallery inner wall 103 and support frame 204, make screw thread post 201 slide into the locating piece 202 on pipe gallery footstock 105, then the nut extrusion positioning block 202 is connected with the threaded column 201 again, so that the stability of the joint of the inner wall 103 of the pipe gallery and the top seat 105 of the pipe gallery is improved, the stability of the assembled pipe gallery prefabricated member is further improved, the inner wall of the support frame 204 is provided with supporting force through the arranged limiting frame 205 and the central support frame 206, then the inner wall of the pipe gallery prefabricated member is provided with supporting force through the support frame 204, further, when concrete is poured, a large amount of supporting equipment does not need to be independently arranged for supporting, the operation steps during construction are simplified, the construction efficiency is improved, the support frame 204 does not need to be disassembled after the pouring is finished, different pipelines are respectively limited through the arranged limiting frame 205 and the central support frame 206, a space for pouring is formed between the pipe gallery base 101 and the base outer wall 102 through the arranged first reinforcing frame 41, make the space that forms between piping lane inner wall 103 and the piping lane outer wall 104 pourable through the second steel bar frame 42 that sets up, when needs splice the intercommunication to the piping lane prefab after a plurality of concatenations, drive single piping lane prefab motion through the loop wheel machine, make piping lane evagination 44 slide in the piping lane indent 43, thereby link together two piping lanes after the concatenation, then slide in the inside of two cardboard 45 respectively through removing fixed block 46 and screw block 47, then drive threaded rod 48 through rotating slide bar 49 and rotate, pivoted threaded rod 48 utilizes screw block 47 and cardboard 45 to drive the piping lane prefab after a concatenation to the movement of another piping lane prefab after the concatenation, thereby make piping lane evagination 44 closely laminate with piping lane indent 43, then splice the piping lane prefab after assembling in proper order, after accomplishing, utilize the concrete to pour the top of piping lane footstock 105, then through piping lane inner wall 103 and piping lane outer wall 104, the space between piping lane base 101 and the base outer wall 102 carries out water conservancy diversion to the concrete, make concrete and pipe lane outer wall 101 and base outer wall 102 contact, the construction of the piping lane, the construction completion of piping lane operation.
The above description is only for the preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (8)

1. Piping lane prefab and assembled utility tunnel, its characterized in that includes
The assembly component (1) comprises two pipe gallery bases (101), a base outer wall (102), a pipe gallery inner wall (103), a pipe gallery outer wall (104) and a pipe gallery top seat (105);
the positioning and supporting mechanism (2) comprises a threaded column (201), a positioning block (202), a positioning groove (203), a supporting frame (204), a limiting frame (205) and a central support (206);
two the bottom of pipe gallery base (101) all is equipped with base outer wall (102), two the top of pipe gallery base (101) all is equipped with pipe gallery footstock (105), the lateral wall symmetry sliding connection of pipe gallery base (101) and pipe gallery footstock (105) has two pipe gallery inner walls (103), the inboard symmetry sliding connection of base outer wall (102) has two pipe gallery outer walls (104), two the even fixedly connected with screw thread post (201) of the inside wall of pipe gallery inner wall (103), the even fixedly connected with locating piece (202) of one side that pipe gallery base (101) and pipe gallery footstock (105) are adjacent, the lateral wall sliding connection of screw thread post (201) is in the inside wall of locating piece (202), two constant head tanks (203), two have all been seted up to the inside wall of pipe gallery inner wall (103), pipe gallery base (101) and pipe gallery footstock (105) the inside wall sliding connection of constant head tank (203) has two support frames (204), two the equal fixedly connected with spider (206) in middle part of support frame inside wall (204).
2. The pipe gallery prefabricated member and assembled comprehensive pipe gallery according to claim 1, wherein: the inside wall of pipe gallery inner wall (103) evenly fixedly connected with second steel bar frame (42), the one end fixed connection of second steel bar frame (42) is in the inside wall of pipe gallery outer wall (104).
3. The pipe gallery prefabricated member and assembled comprehensive pipe gallery according to claim 1, wherein: pipe gallery base (101), pipe gallery inner wall (103) and one side of pipe gallery footstock (105) are equipped with pipe gallery indent (43), the opposite side of pipe gallery base (101), pipe gallery inner wall (103) and pipe gallery footstock (105) is equipped with pipe gallery outer convex part (44), pipe gallery indent (43) with pipe gallery outer convex part (44) looks adaptation.
4. The pipe gallery prefabricated member and assembled comprehensive pipe gallery according to claim 1, wherein: the inner side walls of the two support frames (204) are symmetrically and fixedly connected with two limit frames (205).
5. The pipe gallery prefabricated member and assembled comprehensive pipe gallery according to claim 1, wherein: the equal symmetry of inside wall of pipe gallery base (101), pipe gallery inner wall (103) and pipe gallery footstock (105) has two cardboard (45), one the inside wall sliding connection of cardboard (45) has fixed block (46), another the inside wall sliding connection of cardboard (45) has screw thread piece (47).
6. The pipe gallery preform and fabricated pipe gallery of claim 5, wherein: the middle part of one side of the fixed block (46) is rotatably connected with a threaded rod (48) through a bearing, and the outer side wall of the threaded rod (48) is in threaded connection with the inner side wall of the threaded block (47).
7. The pipe gallery preform and assembly type pipe gallery according to claim 6, wherein: one side of the inner side wall of the threaded rod (48) is connected with a sliding rod (49) in a sliding mode.
8. The pipe gallery prefabricated member and assembled comprehensive pipe gallery according to claim 1, wherein: the inner side walls of the pipe gallery base (101) and the pipe gallery top seat (105) are uniformly and fixedly connected with a first reinforcing frame (41), and one side of the base outer wall (102) is fixedly connected to one side of the first reinforcing frame (41).
CN202221920439.2U 2022-07-22 2022-07-22 Piping lane prefab and assembled utility tunnel Active CN218060414U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221920439.2U CN218060414U (en) 2022-07-22 2022-07-22 Piping lane prefab and assembled utility tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221920439.2U CN218060414U (en) 2022-07-22 2022-07-22 Piping lane prefab and assembled utility tunnel

Publications (1)

Publication Number Publication Date
CN218060414U true CN218060414U (en) 2022-12-16

Family

ID=84401776

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221920439.2U Active CN218060414U (en) 2022-07-22 2022-07-22 Piping lane prefab and assembled utility tunnel

Country Status (1)

Country Link
CN (1) CN218060414U (en)

Similar Documents

Publication Publication Date Title
CN104790522A (en) Prefabricated assembling type steel-reinforced concrete column-steel beam frame structure system and construction method
CN114809062A (en) Integral bottom plate-integral vertical ring combined concrete bearing platform foundation and construction process thereof
CN111608662A (en) Shaft oversized-diameter integral moving metal template
CN218060414U (en) Piping lane prefab and assembled utility tunnel
CN215406163U (en) Assembled multilayer flat-top large-span pillar-free underground structure
CN212478172U (en) Splicing type prefabricated building concrete member
CN206703250U (en) A kind of precast concrete pipe culvert mould
CN109183843B (en) Prefabricated and assembled integral type concrete comprehensive pipe gallery and construction method
CN209868938U (en) Prefabricated piping lane forming die
CN109914476A (en) A kind of construction technology of cast-in-place city integrated piping lane
CN108571012A (en) Piping lane construction joint integrated installation mold construction technology
CN204608975U (en) A kind of prefabricated assembled profile steel concrete column-steel girder frame structural system
CN213952432U (en) Portable prefabricated inspection well template that can install fast and tear open
CN214194661U (en) Prefabricated cable shaft of assembled lightweight
CN203440827U (en) Bay bolt positioning mold for steel pipe support of overhead contact system of electric railway
CN210887303U (en) Coincide assembled utility tunnel structure
CN207862974U (en) The quick support shuttering system of city integrated piping lane construction
CN211030588U (en) Assembled steel pedestal
CN208183792U (en) A kind of piping lane outboard template trolley
CN209812672U (en) Prefabricated piping lane centre form mould
CN214946842U (en) Electric power push pipe glue-stopping platform positioning device
CN104989103A (en) Concrete filled steel tube pumping lifting-up stop valve installation method
CN219137751U (en) Pipe gallery pouring template assembly and pipe gallery
CN217923730U (en) Assembled concrete base for circular inspection well
CN217480252U (en) Assembled steel form for inspection well

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant