CN217896727U - Sidewalk wind and rain pipe gallery - Google Patents

Sidewalk wind and rain pipe gallery Download PDF

Info

Publication number
CN217896727U
CN217896727U CN202222081229.5U CN202222081229U CN217896727U CN 217896727 U CN217896727 U CN 217896727U CN 202222081229 U CN202222081229 U CN 202222081229U CN 217896727 U CN217896727 U CN 217896727U
Authority
CN
China
Prior art keywords
platform
sidewalk
inlet openings
fixedly connected
length direction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222081229.5U
Other languages
Chinese (zh)
Inventor
王晓鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Northwest Architecture Design and Research Institute Co Ltd
Original Assignee
China Northwest Architecture Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Northwest Architecture Design and Research Institute Co Ltd filed Critical China Northwest Architecture Design and Research Institute Co Ltd
Priority to CN202222081229.5U priority Critical patent/CN217896727U/en
Application granted granted Critical
Publication of CN217896727U publication Critical patent/CN217896727U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The application discloses a sidewalk wind and rain pipe gallery which comprises a supporting component, a first platform, a pipe gallery component and a plurality of crawling ladders; the supporting components and the first platform are arranged along the length direction of the sidewalk, the supporting components are arranged on two sides of the sidewalk, and the first platform is positioned above the sidewalk and fixedly connected with the supporting components; the pipe rack assembly is arranged on the top surface of the first platform; the first platform is provided with a plurality of first inlet openings along the length direction of the first platform; the ladder stands are respectively arranged corresponding to the first inlet openings, and the top ends of the ladder stands extend into the first inlet openings. This application has realized the space of rational utilization people side pavement overhead, does not occupy other spaces in ground, makes things convenient for the staff to overhaul work, provides the no umbrella space of sunshade rain on the street simultaneously for citizen.

Description

Sidewalk wind and rain pipe gallery
Technical Field
The application relates to the technical field of ground pipe galleries, in particular to a sidewalk wind and rain pipe gallery.
Background
The traditional urban planning method is to arrange cables such as electric power, communication and the like in an overhead manner, for example, a common telegraph pole and a signal lamp pole of a telegraph pole is a pipe network structure system, along with the improvement of the requirements of people on urban appearances, a new urban planning or old city reconstruction is implemented according to a scheme of 'cable landing', namely, the cables are buried under road surfaces, but the problem of 'zipper roads' is quickly caused, so that a 'comprehensive pipe gallery' technology which is mature abroad is introduced, namely, the cable is built underground in a city and is used for centrally laying public tunnels of municipal pipelines such as electric power, communication, broadcast television, water supply and the like. The underground comprehensive pipe gallery can effectively avoid the phenomenon of zipper roads, so that technicians can carry out rush repair, maintenance, expansion transformation and the like on various pipelines in the pipe gallery without repeatedly excavating road surfaces; meanwhile, the first-aid repair time of the pipeline is greatly shortened. The inspection wells, chambers and the like of the posts and various pipelines of the road are reduced;
however, the underground comprehensive pipe gallery has many defects, is inconvenient to construct in stages, has large one-time investment and difficult construction, has more technical problems in the construction process, has poor ventilation effect, is in a semi-closed state for a long time, has oxygen content thinner than that in the atmosphere, and is easy to threaten by oxygen deficiency for workers; therefore the design of ground pipe gallery has appeared among the prior art, but the ground pipe gallery among the prior art is for building alone, has taken up the space on ground, can not the space above the rational utilization road, and the above-ground pipe gallery among the prior art is not convenient for the staff to overhaul moreover.
SUMMERY OF THE UTILITY MODEL
This application is through providing a pavement wind and rain piping lane, solved among the prior art ground piping lane and built for alone, occupied the space on ground, can not the space above the rational utilization road, the staff of being not convenient for carries out the technical problem who overhauls, realized the space above the rational utilization pavement, do not occupy other spaces on ground, make things convenient for the staff to overhaul work, provide the no umbrella space of sunshade rain on the street simultaneously for citizen.
The application provides a sidewalk wind and rain pipe gallery which comprises a supporting component, a first platform, a pipe gallery component and a plurality of crawling ladders; the supporting component and the first platform are arranged along the length direction of the sidewalk, the supporting component is arranged on two sides of the sidewalk, and the first platform is positioned above the sidewalk and fixedly connected with the supporting component; the pipe rack assembly is arranged on the top surface of the first platform; the first platform is provided with a plurality of first inlet openings along the length direction of the first platform; a plurality of the cat ladder with a plurality of first access port corresponds the setting respectively, just the top of cat ladder stretches into to first access port.
In one possible implementation, the support assembly includes a plurality of support columns respectively disposed on both sides of the sidewalk along a length direction of the sidewalk; two sides of the first platform are respectively fixedly connected with the supporting columns; the crawling ladder is fixedly connected to the inner side of the supporting column.
In one possible implementation, the pipe gallery assembly includes a plurality of layers of support frames, a shelter, and a plurality of pipelines; the multilayer support frame is fixedly connected to the top surface of the first platform; a plurality of the pipelines are detachably connected to the multi-layer support frame; the shielding shed is located above the pipeline, and two sides of the shielding shed are fixedly connected with the top ends of the supporting columns respectively.
In one possible implementation, the sidewalk wind and rain pipe gallery further comprises a second platform and a plurality of tool boxes; the second platform is positioned below the first platform, and two sides of the second platform are fixedly connected with the supporting component; a plurality of second inlet openings are formed in one side of the second platform in a penetrating manner along the length direction of the second platform; the second inlet openings are respectively and correspondingly arranged with the first inlet openings up and down, and the crawling ladder penetrates through the second inlet openings; the tool boxes are arranged on the top surface of the second platform along the length direction of the second platform.
In a possible implementation, the two sides of the shielding shed are provided with drainage grooves.
In a possible implementation manner, the sidewalk wind and rain pipe gallery further comprises a liquid collecting box and an overflow pipe; the liquid collecting box is fixedly connected to the top surface of the first platform; the multilayer support frame is arranged in the liquid collecting box; the overflow pipe is arranged on two sides of the liquid collecting box, one end of the overflow pipe is communicated with the inside of the liquid collecting box, and the other end of the overflow pipe extends out of the outer side of the supporting column.
One or more technical solutions provided in the present application have at least the following technical effects or advantages:
the supporting component, the first platform, the pipe gallery component and the plurality of crawling ladders are arranged along the length direction of a sidewalk, the supporting components are arranged on two sides of the sidewalk, and the first platform is located above the sidewalk and fixedly connected with the supporting components; then arranging the pipe gallery component on the top surface of the first platform, so that the pipe gallery component is laid above the sidewalk through the first platform of the supporting component box, the space above the sidewalk is reasonably utilized, and other spaces on the ground are not occupied;
a plurality of first inlet openings are formed in the first platform in a penetrating manner along the length direction of the first platform; a plurality of cat ladders correspond the setting with a plurality of first inlet ports respectively, and the top of cat ladder stretches into to first inlet port, through setting up cat ladder and first inlet port, the staff can pass through cat ladder and first inlet port and enter into the first platform through the district and overhaul the piping lane, the maintenance efficiency to the piping lane has been improved, effectively solved among the prior art overground piping lane and built for alone, the space on ground has been occupied, can not the rational utilization space above the road, the technical problem that the staff was not convenient for overhaul, the space above the rational utilization pavement has been realized, do not occupy other spaces on ground, make things convenient for the staff to overhaul work, the no umbrella space of sunshade on the street of sheltering from rain is provided for citizen simultaneously.
Drawings
In order to clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required to be used in the embodiments of the present invention or the description in the prior art are briefly introduced below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a side view of a sidewalk storm drain gallery according to an embodiment of the present application;
FIG. 2 is an enlarged view of a portion of area A of FIG. 1;
FIG. 3 is a front view of a sidewalk storm drain gallery according to an embodiment of the present application;
fig. 4 is a partially enlarged view of the region B in fig. 3.
Reference numerals are as follows: 1-a support assembly; 11-a support column; 2-a first platform; 21-a first access port; 3-a pipe gallery assembly; 31-a multi-layer scaffold; 32-a shelter; 321-a drainage tank; 33-a line; 4, climbing a ladder; 5-sidewalk; 6-a second platform; 61-a second access port; 7-a tool box; 8-liquid collecting box; 9-overflow pipe.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the embodiments of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, which are only for convenience of describing the embodiments of the present invention and simplifying the description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. The terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance. Furthermore, the terms "mounted," "connected," and "connected" are to be construed broadly and may, for example, be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the embodiments of the present invention can be understood by those skilled in the art according to specific situations.
Referring to fig. 1 and 3, a sidewalk wind and rain pipe rack provided by the embodiment of the application comprises a support assembly 1, a first platform 2, a pipe rack assembly 3 and a plurality of ladder stands 4; the supporting component 1 and the first platform 2 are arranged along the length direction of the sidewalk 5, the supporting component 1 is arranged at two sides of the sidewalk 5, and the first platform 2 is positioned above the sidewalk 5 and fixedly connected with the supporting component 1; the pipe gallery component 3 is arranged on the top surface of the first platform 2; the first platform 2 is provided with a plurality of first inlet openings 21 along the length direction of the first platform; a plurality of cat ladders 4 correspond the setting with a plurality of first access ports 21 respectively, and the top of cat ladder 4 stretches into to first access port 21. In the embodiment of the application, the first platform 2 is arranged above the sidewalk 5, and the first platform 2 is supported by the support assembly 1, so that the pipe gallery assembly 3 can be laid on the first platform 2, and by arranging the ladder stand 4 and the first inlet 21, workers can enter the first platform 2 through the ladder stand 4 and the first inlet 21 in sections to overhaul the pipe gallery, so that the overhaul efficiency of the pipe gallery is improved; in addition, the ladder stand 4 in the embodiment of the application can be also selected and matched, namely, the ladder stand can be replaced by other lifting tools, for example, a lifting ladder can be reasonably selected and used according to the requirements of actual conditions when the ladder stand is actually built.
Referring to fig. 1 and 3, the supporting assembly 1 includes a plurality of supporting columns 11 respectively disposed at both sides of the sidewalk 5 along a length direction of the sidewalk 5; two sides of the first platform 2 are respectively fixedly connected with the support columns 11; the ladder stand 4 is fixedly connected to the inner side of the supporting column 11. Welding between first platform 2 and the support column 11 in this application embodiment sets up cat ladder 4 in the inboard of support column 11 for cat ladder 4 does not excessively occupy the space between two adjacent support columns 11, and the pedestrian is not influenced when passing through between two adjacent support columns 11.
Referring to fig. 1, the pipe rack assembly 3 includes a multi-layer support frame 31, a shelter 32, and a plurality of pipes 33; the multi-layer support frame 31 is fixedly connected to the top surface of the first platform 2; a plurality of pipelines 33 are detachably connected to the multi-layer support frame 31; the shielding shed 32 is located above the pipeline 33, and two sides of the shielding shed 32 are respectively and fixedly connected with the top end of the supporting column 11. Through setting up multilayer support frame 31 in this application embodiment for pipeline 33 can lay by the layering, sets up and shelters from canopy 32 and can protect pipeline 33, avoids the windy and sunny, prolongs pipeline 33's life.
Referring to fig. 1 and 3, the sidewalk wind and rain pipe gallery provided by the embodiment of the application further comprises a second platform 6 and a plurality of tool boxes 7; the second platform 6 is positioned below the first platform 2, and two sides of the second platform 6 are fixedly connected with the support assembly 1; one side of the second platform 6 is provided with a plurality of second inlet openings 61 along the length direction of the second platform; the plurality of second inlet openings 61 are respectively arranged corresponding to the plurality of first inlet openings 21 up and down, and the crawling ladder 4 penetrates through the second inlet openings 61; a plurality of tool boxes 7 are provided on the top surface of the second platform 6 along the length direction of the second platform 6. In the embodiment of the application, the fact that the workers need to carry the maintenance tools from the ground and climb onto the first platform 2 for maintenance when carrying out maintenance work is further considered, and the labor intensity of the workers is increased by carrying the maintenance tools from the ground, therefore, the embodiment of the application is further provided with the second platform 6 and the tool boxes 7, the tool boxes 7 are placed on the second platform 6 in sections, when the workers carry out maintenance, the workers firstly climb to the second platform 6 through the crawling ladder 4 and the second inlet 61, then take out the maintenance tools to be carried from the tool boxes 7, and then enter the first platform 2 through the crawling ladder 4 and the first inlet 21 for maintenance work, and the labor intensity of the workers is reduced; the toolbox 7 and the second platform 6 that this application embodiment provided can be according to the demand rational selection of the condition of reality whether choose for use when actually building.
Referring to fig. 1, drainage grooves 321 are provided at both sides of the blocking compartment 32. In the embodiment of the present application, a drainage groove 321 is further provided, so that rainwater can be drained away in rainy days.
Referring to fig. 2 and 4, the sidewalk wind and rain pipe gallery provided by the embodiment of the application further comprises a liquid collecting box 8 and an overflow pipe 9; the liquid collecting box 8 is fixedly connected to the top surface of the first platform 2; the multilayer support frame 31 is arranged in the liquid collecting box 8; the overflow pipe 9 sets up in the both sides of collecting liquid box 8, and the one end of overflow pipe 9 and the inside intercommunication of collecting liquid box 8, and the other end of overflow pipe 9 stretches out to the outside of support column 11. Further consider that when the pipeline 33 slightly leaks and is difficult to discover in this application embodiment, the liquid that leaks from pipeline 33 can drip to pavement 5, influences pedestrian's trip, therefore this application embodiment has further set up album liquid box 8 and overflow pipe 9 for the liquid that leaks in the pipeline 33 is collected in album liquid box 8, drains the outside of support column 11 through overflow pipe 9 when the liquid in album liquid box 8 is too much, can not drip to pavement 5, can not influence pedestrian's normal trip.
The application embodiment provides a people moving walkways wind and rain pipe gallery's theory of operation as follows:
the pedestrian walks in the below of second platform 6, through sheltering from canopy 32 and second platform 6 and providing the no umbrella space of sunshade rain for the pedestrian, the staff is when carrying out maintenance work, at first climb to second platform 6 through cat ladder 4 and second inlet port 61, take out the maintenance instrument that needs to carry from toolbox 7, then continue to climb upwards through cat ladder 4 and enter into first platform 2 through first inlet port 21 on, then patrol and examine the work of examining and repairing pipeline 33 on first platform 2, the staff is patrolling and examining and repairing the work and accomplish the back, only need descend to second platform 6, place the maintenance instrument in toolbox 7 can, need not make a round trip to follow subaerial maintenance instrument of carrying and climb, staff's intensity of labour has been reduced.
The embodiments in the present specification are described in a progressive manner, and the same or similar parts among the embodiments may be referred to each other, and each embodiment is described with emphasis on the difference from the other embodiments.
The above embodiments are only used to illustrate the technical solutions of the present application, and not to limit the present application; although the present application has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; such modifications or substitutions do not depart from the spirit and scope of the present disclosure.

Claims (6)

1. A sidewalk wind and rain pipe gallery is characterized by comprising a supporting component (1), a first platform (2), a pipe gallery component (3) and a plurality of crawling ladders (4);
the supporting component (1) and the first platform (2) are arranged along the length direction of a sidewalk (5), the supporting component (1) is arranged at two sides of the sidewalk (5), and the first platform (2) is positioned above the sidewalk (5) and fixedly connected with the supporting component (1);
the pipe rack assembly (3) is arranged on the top surface of the first platform (2);
the first platform (2) is provided with a plurality of first inlet openings (21) in a penetrating manner along the length direction of the first platform;
the ladder stands (4) are respectively arranged corresponding to the first inlet openings (21), and the top ends of the ladder stands (4) extend into the first inlet openings (21).
2. A sidewalk storm drain gallery according to claim 1, wherein the support assembly (1) comprises a plurality of support pillars (11) disposed on either side of the sidewalk (5) along a length direction of the sidewalk (5);
two sides of the first platform (2) are respectively fixedly connected with the supporting columns (11);
the crawling ladder (4) is fixedly connected to the inner side of the supporting column (11).
3. A sidewalk storm wind pipe corridor according to claim 2, wherein the pipe corridor assembly (3) comprises a plurality of layers of support frames (31), a shelter canopy (32) and a plurality of pipelines (33);
the multilayer support frame (31) is fixedly connected to the top surface of the first platform (2);
a plurality of the pipelines (33) are detachably connected to the multi-layer support frame (31);
the shielding shed (32) is located above the pipeline (33), and two sides of the shielding shed (32) are fixedly connected with the top ends of the supporting columns (11) respectively.
4. A sidewalk storm drain gallery according to claim 1, further comprising a second platform (6) and a plurality of toolboxes (7);
the second platform (6) is positioned below the first platform (2), and two sides of the second platform (6) are fixedly connected with the support assembly (1);
one side of the second platform (6) is provided with a plurality of second inlet openings (61) in a penetrating way along the length direction of the second platform;
the second inlet openings (61) are respectively arranged corresponding to the first inlet openings (21) up and down, and the ladder stand (4) penetrates through the second inlet openings (61);
the tool boxes (7) are arranged on the top surface of the second platform (6) along the length direction of the second platform (6).
5. A sidewalk storm sewer corridor according to claim 3, characterized in that both sides of the shelter (32) are provided with drainage channels (321).
6. A sidewalk storm drain according to claim 3, further comprising a drip box (8) and an overflow tube (9);
the liquid collection box (8) is fixedly connected to the top surface of the first platform (2);
the multilayer support frame (31) is arranged in the liquid collecting box (8);
the overflow pipe (9) is arranged on two sides of the liquid collecting box (8), one end of the overflow pipe (9) is communicated with the inside of the liquid collecting box (8), and the other end of the overflow pipe (9) extends out of the outer side of the supporting column (11).
CN202222081229.5U 2022-08-08 2022-08-08 Sidewalk wind and rain pipe gallery Active CN217896727U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222081229.5U CN217896727U (en) 2022-08-08 2022-08-08 Sidewalk wind and rain pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222081229.5U CN217896727U (en) 2022-08-08 2022-08-08 Sidewalk wind and rain pipe gallery

Publications (1)

Publication Number Publication Date
CN217896727U true CN217896727U (en) 2022-11-25

Family

ID=84139275

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222081229.5U Active CN217896727U (en) 2022-08-08 2022-08-08 Sidewalk wind and rain pipe gallery

Country Status (1)

Country Link
CN (1) CN217896727U (en)

Similar Documents

Publication Publication Date Title
CN106638681A (en) Integrated pipe gallery
CN103856151B (en) Gallery formula road wind/light energy composite power station
CN1319704A (en) underground comprehesive pipe gallery and system for comprehensive developing and utilizing underground space
CN106677209A (en) Intelligent comprehensive pre-fabricating pipe gallery and construction technique thereof
CN217896727U (en) Sidewalk wind and rain pipe gallery
CN1944827A (en) Method for building steel structure environment friendly energy saving building along hill slope
CN217811573U (en) Wind and rain pipe gallery for connecting buildings
CN107387112B (en) Urban transportation culvert or tunnel entrance anti-flooding masking device and method
CN217810464U (en) Double-deck wind and rain piping lane
CN213626858U (en) Double-layer dustproof shed for GIS equipment installation
CN115653046A (en) Rainwater collection system and method combined with urban landscape for old community transformation
CN217924073U (en) Wind and rain piping lane that combines with enclosure
CN109356224A (en) A kind of skyscraper rainwater-collecting self-loopa utilizes system
CN213086855U (en) Prestressing force transversely divides and adds vertical even pin-connected panel pipe gallery
CN205557579U (en) Well controllable formula underground pipe gallery in storehouse is assembled to adding to prestressing force
CN211621968U (en) Light-transmitting type movable canopy
CN210066387U (en) Space utilization system based on three-dimensional traffic and utility tunnel
CN217870925U (en) Street building with pipe gallery function
CN210669448U (en) Basic support structure suitable for cable crossing
CN220521405U (en) Utility tunnel structure is developed to rail transit vehicle base upper cover
CN217810463U (en) Bridge structure with pipe gallery function
CN215299897U (en) Prefabricated base of box-type substation
CN117309015B (en) Intelligent data acquisition device
CN218952929U (en) Double-picking type non-motor vehicle shed with charging piles
CN219162824U (en) Smart city traffic monitoring system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant