CN217870925U - Street building with pipe gallery function - Google Patents

Street building with pipe gallery function Download PDF

Info

Publication number
CN217870925U
CN217870925U CN202222088603.4U CN202222088603U CN217870925U CN 217870925 U CN217870925 U CN 217870925U CN 202222088603 U CN202222088603 U CN 202222088603U CN 217870925 U CN217870925 U CN 217870925U
Authority
CN
China
Prior art keywords
pipe gallery
street
building
plate
piping lane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222088603.4U
Other languages
Chinese (zh)
Inventor
王晓鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Northwest Architecture Design and Research Institute Co Ltd
Original Assignee
China Northwest Architecture Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Northwest Architecture Design and Research Institute Co Ltd filed Critical China Northwest Architecture Design and Research Institute Co Ltd
Priority to CN202222088603.4U priority Critical patent/CN217870925U/en
Application granted granted Critical
Publication of CN217870925U publication Critical patent/CN217870925U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sink And Installation For Waste Water (AREA)

Abstract

The application discloses a street building with a pipe gallery function, which comprises a pipe gallery arranged along a street, wherein the pipe gallery is arranged on one side of a building body close to a street, the pipe gallery is connected to a part between one layer and two layers of the building body, the pipe gallery comprises a side plate, a top plate and a bottom plate, a ventilation mechanism is arranged on the side plate, and a drainage structure comprises a rainwater tank, a drainage channel and a water delivery pipe; the rainwater tank is arranged on the end side of the upper surface of the top plate, the rainwater tank is arranged along the extending direction of the street pipe gallery, the side plates and the bottom plate are internally provided with drainage channels communicated with each other, the rainwater tank is communicated with the drainage channels, and the drainage channels are connected to a municipal sewer through water pipes; the center of the upper surface of the bottom plate is provided with two parallel sliding grooves, the side plates are detachably provided with a base, and the base is provided with a bracket for mounting a pipeline; the middle part of the lower surface of the top plate is provided with a cable mounting rack. The utility model provides an among the prior art underground utility tunnel have the big and not good problem of ventilation effect of construction cost.

Description

Street building with pipe gallery function
Technical Field
This application belongs to pipe gallery technical field, concretely relates to building that has the street of pipe gallery function.
Background
The soft traditional city planning is all to make somebody a mere figurehead setting of cables such as electric power, communication, etc., like our common wire pole, light pole, signal lamp pole etc., be its pipe network structure system, along with the improvement that everybody required city appearance, new city planning or old city transformation are implemented according to the scheme that "cable falls to the ground", bury the cable under the road surface, but "zip fastener road" problem has appeared soon again, then introduced "utility tunnel" technique that has become mature abroad again, utility tunnel is the construction in the city underground, be used for laying the public tunnel of municipal pipeline such as electric power, communication, radio and television, feedwater in a concentrative way. The utility tunnel can effectively stop "zip fastener road" phenomenon, lets the technical staff need not to excavate the road surface repeatedly, just can salvage, maintain, dilatation transformation etc. all kinds of pipelines in the piping lane, reduces the pipeline time of salvageing simultaneously greatly. But city utility tunnel is not convenient for the staged construction, and disposable investment is big, and especially the utility tunnel construction investment of old city district is bigger, and the time limit for a project is longer. When the pipeline that lays in the trench is less, the construction and the maintenance cost of piping lane self are too big. The comprehensive pipe gallery is constructed by correctly predicting the prospective development plan so as to avoid reconstruction or waste caused by insufficient or overlarge capacity. The underground comprehensive pipe gallery is poor in ventilation effect and is in a semi-closed state for a long time, the oxygen content is rarefied than that in the atmosphere, and sometimes a certain amount of hydrogen sulfide, methane and carbon monoxide are generated due to long-term fermentation of sewage in a sump pit, so that the health of workers is influenced.
SUMMERY OF THE UTILITY MODEL
The embodiment of the application provides a street building with pipe gallery function, has solved among the prior art underground utility tunnel and has had the big and not good problem of ventilation effect of construction cost.
In order to achieve the purpose, the embodiment of the utility model provides a street building with a pipe gallery function, which comprises a building body, a pipe gallery along the street, a ventilation mechanism, a drainage structure, a base and a cable mounting rack;
the street-following pipe gallery is arranged on one side, close to a street, of the building body, is connected to a part between one floor and the second floor of the building body, and the lower part of the street-following pipe gallery is a passerby channel;
the pipeline corridor along the street comprises two side plates which are vertically arranged, a top plate and a bottom plate which are both horizontally arranged, and the two side plates are arranged between the top plate and the bottom plate; the side plates, the top plate and the bottom plate form a chamber, and the height inside the chamber is 1.5-2.2 m;
the ventilation mechanism is arranged on the side plate far away from the building body and comprises an exhaust fan and a shutter, the exhaust fan is arranged in a ventilation opening in the side plate, and the shutter is arranged on the outer side of the ventilation opening;
the drainage structure comprises a rainwater tank, a drainage channel and a water delivery pipe;
the rainwater groove is arranged on the end side of the upper surface of the top plate and is arranged along the extending direction of the street pipe gallery, the drainage channels communicated with each other are arranged in the side plates and the bottom plate, the rainwater groove is communicated with the drainage channels, and the drainage channels are connected to a municipal sewer through the water conveying pipes;
the center of the upper surface of the bottom plate is provided with two parallel sliding chutes which are arranged along the extending direction of the street pipe gallery and matched with moving wheels of the maintenance trolley;
the side plates are detachably provided with a base, and the base is provided with a bracket for mounting a pipeline; and a cable mounting rack is arranged in the middle of the lower surface of the top plate.
In a possible implementation manner, the building comprises a supporting column, wherein the supporting column is arranged on one side, away from the building body, of the street pipe gallery, the lower end of the supporting column is supported on the ground, and the upper end of the supporting column is connected to the lower surface of the bottom plate.
In a possible implementation mode, the pipeline corridor is arranged at the outer sides of one layer and two layers of the building body, one side, away from the building body along the pipeline corridor, of the building body is connected with the building body through a cable, and the cable is obliquely arranged.
In one possible implementation, the building body is a building, the pipeline along the street is arranged below two layers of the building, and the end part of the pipeline along the street extends to the outer sides of the two layers of the building.
In a possible implementation manner, an access hole is formed in the bottom plate, one side of the access door is hinged to the bottom plate, and the other side of the access door and the bottom plate are respectively provided with a lock catch and a lock pin which are matched with each other.
In one possible implementation, the base comprises a limiting block, a lateral mounting plate and a transverse mounting plate;
the side plates are provided with embedded parts, and the lateral mounting plates are fixed on the side plates through the embedded parts; the bracket is arranged on the transverse mounting plate;
the lateral wall of side direction mounting panel is provided with a plurality of recesses along its direction of height at the interval, the lateral wall department of recess lower part is provided with the butt joint piece, one side of horizontal mounting panel tip is provided with the joint piece, the width of joint piece is less than the butt joint piece is apart from the distance of recess upper portion lateral wall, joint piece joint in the recess diapire with between the butt joint piece, the stopper joint in horizontal mounting panel tip with between the recess lateral wall.
In a possible implementation manner, the number of the transverse mounting plates is multiple, the multiple transverse mounting plates are mounted along the height direction of the lateral mounting plate through the grooves, and the lengths of the multiple transverse mounting plates are gradually decreased from the middle to the top and the bottom.
In one possible implementation, a grid plate is arranged between the rainwater tank and the water inlet of the drainage channel.
In a possible implementation, two are adjacent be provided with the pontic structure between the following street piping lane, the pontic is provided with the pontic piping lane in the structure, pontic piping lane and its both sides along street piping lane intercommunication.
In one possible implementation, the inner wall of the chamber is provided with an insulating layer.
The embodiment of the utility model provides an in one or more technical scheme, following technological effect or advantage have at least:
the embodiment of the utility model provides a building in the street with piping lane function can get into the rainwater groove along the rainwater on the piping lane that flows automatically, finally carries to municipal sewer unified through drainage channel and raceway and handles. Along the street pipe gallery, the rain shed can be used as a sunshade and a rain shelter above the pedestrian passageway. The inside and external air current exchange rate of pipe gallery can be accelerated to the exhaust fan, and the shutter can be when not needing the ventilation, with the vent shutoff. Ventilation mechanism makes inside and the external intercommunication of piping lane, and then makes the inside air of piping lane obtain replacing, guarantees the content of oxygen on the one hand, and on the other hand prevents that harmful gas from gathering in the piping lane, avoids causing the influence to the staff is healthy. The utility model discloses a pipe gallery that normal utility tunnel is compared to the height of cavity inside is lower, overhauls the dolly for the flatbed, therefore the staff can sit and remove in the pipe gallery on the flatbed to improve maintenance efficiency, alleviate staff's intensity of labour. Along street piping lane's cavity promptly for supplying the piping lane that the pipeline passes through, pipeline accessible support fixed mounting, the cable that the diameters are less such as cable mounting bracket mountable cable, signal line to space in the make full use of piping lane, the staff of still being convenient for of such mounted position simultaneously maintains the cable. The utility model discloses a structure both is convenient for traditional aerial [ insulated ] cable reform transform on the spot, management maintenance, has absorbed the advantage of the unified municipal pipeline of utility tunnel integration again, still provides the umbrella-free space of sunshade rain-proof on the street for the citizen. The utility model discloses a bridge body piping lane can save valuable underground space, vacates the space for the renewal construction of facilities such as underpass roads, has simplified the pipeline and has laid the process, simultaneously, the utility model discloses a bridge body piping lane will be much lower than underground piping lane's cost.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings used in the description of the embodiments will be briefly described below. It is obvious that the drawings in the following description are only some of the embodiments described in the present application, and that other drawings can be derived from these drawings by a person skilled in the art without inventive effort.
Fig. 1 is the embodiment of the present invention provides a schematic structural diagram of a street building with a pipe gallery function.
Fig. 2 is a schematic structural view of the temporary building with pipe gallery function provided by the second embodiment of the present invention.
Fig. 3 is the utility model provides a along street piping lane's schematic structure.
Fig. 4 is a schematic structural diagram of a base according to an embodiment of the present invention.
Figure 5 is the utility model discloses along street piping lane and pontic piping lane's arrangement map that provides.
Reference numerals: 1-a building body; 2-along the street pipe gallery; 3-a ventilation mechanism; 4-side plate; 5-a top plate; 6-a bottom plate; 7-a chamber; 8-rain gutter; 9-a drainage channel; 10-water conveying pipe; 11-a chute; 12-a scaffold; 13-a cable mount; 14-a support column; 15-a cable; 16-an access door; 17-a limiting block; 18-a lateral mounting plate; 19-a transverse mounting plate; 20-grooves; 21-a butt block; 22-a clamping block; 23-a grid plate; 24-bridge body pipe gallery.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the embodiments of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, which are only for convenience of describing the embodiments of the present invention and simplifying the description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. The terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance. Furthermore, the terms "mounted," "connected," and "connected" are to be construed broadly and may, for example, be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the embodiments of the present invention can be understood by those skilled in the art according to specific situations.
As shown in fig. 1 to 5, the embodiment of the utility model provides a have building in the street of piping lane function, including building body 1, along the street piping lane 2, ventilation mechanism 3, drainage structures, base and cable mounting bracket 13.
Along street piping lane 2 set up in building body 1 one side near the street, along street piping lane 2 connect in building body 1's one deck and the part between the two layers, along street piping lane 2's lower part is the passerby passageway.
Along street piping lane 2 includes the curb plate 4 of two vertical settings and roof 5 and the bottom plate 6 that are the level setting, and two curb plates 4 set up between roof 5 and bottom plate 6. The side plate 4, the top plate 5 and the bottom plate 6 form a chamber 7, and the height inside the chamber 7 is 1.5-2.2 m.
Ventilation mechanism 3 sets up on keeping away from building body 1's curb plate 4, and ventilation mechanism 3 includes exhaust fan and shutter, and in the exhaust fan installed the vent on curb plate 4, the shutter was installed in the outside of vent.
The drainage structure includes a rain gutter 8, a drainage channel 9, and a water delivery pipe 10.
The distolateral side of roof 5 upper surface is provided with rainwater groove 8, and rainwater groove 8 arranges along the extending direction of street piping lane 2, is provided with the drainage channel 9 that is linked together in curb plate and the bottom plate 6, and rainwater groove 8 and drainage channel 9 communicate, and drainage channel 9 passes through raceway 10 and connects in municipal sewer.
The upper surface of the bottom plate 6 is an arched surface, and the two sides of the bottom plate 6 are provided with drainage grooves which are communicated with the drainage channel 9.
The center of 6 upper surfaces of bottom plate is provided with two parallel arrangement's spout 11, and spout 11 arranges along street piping lane 2's extending direction, and spout 11 cooperatees with the removal wheel of overhauing the dolly.
The side plate 4 is detachably provided with a base, and the base is provided with a bracket 12 for installing a pipeline. A cable mount 13 is provided at the middle of the lower surface of the top plate 5.
It should be noted that along street piping lane 2 can regard as the canopy that hides the shade and rain of passerby passageway top, and along street piping lane 2's cavity 7 is the piping lane that supplies the pipeline to pass through promptly, and the inside height of cavity 7 is decided according to actual conditions, if when actual installation space is great, the higher structure of inside height can be selected to the piping lane, otherwise, then selects the lower structure of inside height.
Rainwater on the pipeline corridor 2 along the street can automatically flow into a rainwater tank 8 and is finally conveyed to a municipal sewer for unified treatment through a drainage channel 9 and a water conveying pipe 10.
Pipeline accessible support 12 fixed mounting, the inside and external air current exchange rate of piping lane can be accelerated to the exhaust fan, and the shutter can be when not needing the ventilation, with the vent shutoff. Ventilation mechanism 3 makes inside and the external intercommunication of piping lane, and then makes the inside air of piping lane obtain replacing, guarantees the content of oxygen on the one hand, and on the other hand prevents that harmful gas from gathering in the piping lane, avoids causing the influence to the staff is healthy. The overground ventilation condition is good, so the exhaust fan can be selectively installed, and the number of the shutters can be increased after the exhaust fan is cancelled.
The utility model discloses a pipe gallery that normal utility tunnel is compared to the height of 7 inside cavities is lower, overhauls the dolly for the flatbed, therefore the staff can sit and remove in the pipe gallery on the flatbed to improve maintenance efficiency, alleviate staff's intensity of labour, avoid the staff to bow to move ahead and have the problem that intensity of labour is big.
The cable mounting bracket 13 can be used for mounting cables, signal wires and other cables with smaller diameters, so that the space in a pipe gallery is fully utilized, and meanwhile, the mounting position is convenient for workers to maintain the cables.
The common classification modes of the underground pipe gallery mainly include three types: trunk type utility tunnel, branch type utility tunnel and cable line type piping lane. The utility model discloses an even can not replace trunk type utility tunnel along street piping lane 2, also can replace branch line type, cable line type piping lane completely, at least it can let city "spider web" type pipe network structure system of current situation no longer need bury the underground.
The utility model discloses a structure both has been convenient for traditional aerial [ insulated ] cable's transformation on the spot, management maintenance, has sucked the advantage that utility tunnel integrated unified municipal pipeline again, still provides the umbrella-free space that takes shelter from rain on the street for the citizen, the utility model discloses a canopy structure not only is wind and rain shelter but also is the piping lane. The space such as low-lying ground, basement, underground pipe gallery is the place that is most easily suffered flood, and the utility model discloses a along street pipe gallery 2 does not have these worries, not only can prevent flood damage, still can provide the convenience of holding temporarily and climbing to take refuge to wait for the pedestrian on the flooded road even. The utility model discloses a following street piping lane 2 can save valuable underground space, has vacated the space for the renewal construction of facilities such as underpass road, has simplified the pipeline and has laid the process, simultaneously, the utility model discloses a following street piping lane 2 will be much lower than underground pipe gallery's cost, compares underground pipe gallery, because it does not dodge the problem with other underground pipe networks or underground space's alternately, its cost can reach below the latter ten minutes even, has reduced the investment.
In this embodiment, the building comprises a supporting column 14, the supporting column 14 is disposed on one side of the pipe gallery 2 away from the building body 1, the lower end of the supporting column 14 is supported on the ground, and the upper end of the supporting column 14 is connected to the lower surface of the bottom plate 6.
It should be noted that the support columns 14 are able to take up part of the weight along the street galleries 2, thereby improving the structural stability of the building as a whole.
As shown in fig. 1, in the first embodiment, the pipe gallery 2 along the street is disposed at the outer side of the first floor and the second floor of the building body 1, the side of the pipe gallery 2 away from the building body 1 along the street is connected with the building body 1 through the cable 15, and the cable 15 is disposed obliquely.
It should be noted that the first embodiment of the present invention is only a rainshed structure, and therefore the cable 15 can bear part of the gravity of the pipe rack 2, thereby improving the structural stability of the whole building. The support column 14 of the embodiment can also be arranged along the street pipe gallery 2 to bear part of the gravity of the street pipe gallery 2.
As shown in fig. 2, in the second embodiment, the building body 1 is a building, the pipe gallery 2 is disposed below the second floor of the building, and the end of the pipe gallery 2 extends to the outside of the second floor of the building.
It should be noted that, in the second embodiment, the case of combining the building with the pipeline corridor 2 is shown, and most of the top plate 5 of the pipeline corridor 2 is connected to the second floor of the building. The support column 14 of the embodiment can also be arranged along the street pipe gallery 2 to bear part of the gravity of the street pipe gallery 2.
In this embodiment, the bottom plate 6 is provided with an access opening, one side of the access door 16 is hinged to the bottom plate 6, and the other side of the access door 16 and the bottom plate 6 are respectively provided with a lock catch and a lock pin which are matched with each other.
It should be noted that personnel can access the interior of the pipe gallery through the access door 16 to perform maintenance on the pipeline. An annular groove 20 is formed in the circumferential direction of the access hole, a sealing ring is arranged at the position of the annular groove, and the sealing ring can improve the sealing performance when the access door 16 is closed. Staff's accessible access hole gets into inside the piping lane to realize the maintenance of pipeline.
Ventilation mechanism 13 still can set up on the access door, and then reduces piping lane trompil quantity, optimizes the piping lane structure. As shown in fig. 4, in this embodiment, the base includes a stopper 17, a lateral mounting plate 18, and a transverse mounting plate 19.
The side plates 4 are provided with embedded parts, and the lateral mounting plates 18 are fixed on the side plates 4 through the embedded parts. The bracket 12 is mounted on a transverse mounting plate 19.
The lateral wall of lateral direction mounting panel 18 is provided with a plurality of recesses 20 along its direction of height at the interval, and lateral wall department of the recess 20 lower part is provided with butt joint piece 21, and one side of 19 tip of horizontal mounting panel is provided with joint piece 22, and the width of joint piece 22 is less than the distance of butt joint piece 21 apart from 20 upper portion lateral walls of recess, and joint piece 22 joint is between recess 20 diapire and butt joint piece 21, and stopper 17 joint is between 19 tip of horizontal mounting panel and the recess 20 lateral wall.
It should be noted that the number of transverse mounting plates 19, and the configuration of the brackets 12 thereon, may be varied depending on the actual pipeline configuration. During specific installation, with the joint piece 22 lateral shifting of 19 tip of lateral mounting board to recess 20 in, then lateral mounting board 19 of downward movement again, make joint piece 22 joint between recess 20 diapire and butt piece 21, remove stopper 17 to recess 20 in again, make stopper 17 joint between 19 tip of lateral mounting board and recess 20 lateral wall, and then install lateral mounting board 19 on lateral mounting board 18 fast, this mounting means need not bolted connection, consequently the installation effectiveness is high, is applicable to the utility model discloses the installation space that the structure is restricted.
In this embodiment, the number of the transverse mounting plates 19 is plural, the plural transverse mounting plates 19 are mounted in the height direction of the lateral mounting plate 18 through the grooves 20, and the lengths of the plural transverse mounting plates 19 decrease from the middle to both the top and the bottom.
It should be noted that the lengths of the plurality of transverse mounting plates 19 decrease from the middle to the top and bottom ends, that is, the middle transverse mounting plate 19 is the longest, the transverse mounting plates 19 located at the top and bottom are the shortest, and the length of the middle transverse mounting plate 19 decreases toward the length of the transverse mounting plates 19 located at the top and bottom. Therefore, when the height in the street pipe gallery 2 is lower, the end parts of the two adjacent transverse mounting plates 19 are different in length, so that a maintenance space is reserved for workers, the hands of the workers can be easily extended to the innermost side of the transverse mounting plates 19, and the smooth maintenance of pipelines by the workers is guaranteed.
In this embodiment, a grid 23 is provided between the rain gutter 8 and the water inlet of the drainage channel 9.
It should be noted that the louver 23 prevents foreign materials from entering the drain passage 9.
As shown in fig. 5, in this embodiment, a bridge structure is provided between two adjacent pipe corridors 2, a bridge pipe corridor 24 is provided on the bridge structure, and the bridge pipe corridor 24 is communicated with the pipe corridors 2 on both sides.
It should be noted that the bridge body pipe gallery 24 is communicated with the pipeline gallery 2 along the street, so that the whole pipe gallery forms a space communicated with each other, the arrangement of the ground pipelines is realized, and the requirement of crossed arrangement of the pipelines is met.
In this embodiment, the inner wall of the chamber 7 is provided with a heat insulating layer.
It should be noted that the insulating layer can be selectively arranged, and the specific selection conditions are determined according to the actual use environment and the type of the pipeline in the pipe rack.
The heat preservation can reduce along the inside and external heat exchange of street piping lane 2, when preventing summer weather from being hot, the higher cable temperature that makes of piping lane inside temperature is higher and arouse the problem of conflagration to and when winter weather is cold, the lower problem that makes 10 pipelines of raceway of piping lane inside temperature.
In the present embodiment, it is apparent to those skilled in the art that the present invention is not limited to the details of the above-described exemplary embodiments, but can be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein.

Claims (10)

1. The utility model provides a street building with piping lane function which characterized in that: comprises a building body (1), a pipe gallery (2), a ventilation mechanism (3), a drainage structure, a base and a cable mounting rack (13);
the street-following pipe gallery (2) is arranged on one side, close to a street, of the building body (1), the street-following pipe gallery (2) is connected to a part between one floor and two floors of the building body (1), and a pedestrian passageway is arranged at the lower part of the street-following pipe gallery (2);
the pipeline corridor (2) comprises two side plates (4) which are vertically arranged, and a top plate (5) and a bottom plate (6) which are both horizontally arranged, wherein the two side plates (4) are arranged between the top plate (5) and the bottom plate (6); the side plates (4), the top plate (5) and the bottom plate (6) form a chamber (7), and the height of the inside of the chamber (7) is 1.5-2.2 m;
the ventilation mechanism (3) is arranged on the side plate (4) far away from the building body (1), the ventilation mechanism (3) comprises an exhaust fan and a shutter, the exhaust fan is installed in a ventilation opening in the side plate (4), and the shutter is installed on the outer side of the ventilation opening;
the drainage structure comprises a rainwater tank (8), a drainage channel (9) and a water delivery pipe (10);
the rainwater tank (8) is arranged on the end side of the upper surface of the top plate (5), the rainwater tank (8) is arranged along the extending direction of the street pipe gallery (2), the drainage channels (9) communicated with each other are arranged in the side plates and the bottom plate (6), the rainwater tank (8) is communicated with the drainage channels (9), and the drainage channels (9) are connected to a municipal sewer through the water conveying pipe (10);
the center of the upper surface of the bottom plate (6) is provided with two parallel sliding chutes (11), the sliding chutes (11) are arranged along the extending direction of the street pipe gallery (2), and the sliding chutes (11) are matched with moving wheels of the maintenance trolley;
a base is detachably mounted on the side plate (4), and a support (12) for mounting a pipeline is arranged on the base; and a cable mounting rack (13) is arranged in the middle of the lower surface of the top plate (5).
2. The walk-in building with pipe gallery function of claim 1, further comprising: still include support column (14), support column (14) set up in keep away from along street piping lane (2) one side of building body (1), the lower extreme of support column (14) supports on subaerial, the upper end of support column (14) connect in the lower surface of bottom plate (6).
3. The walk-in building with pipe gallery function of claim 1, further comprising: along street piping lane (2) set up in the outside on one deck and the second floor of building body (1), keep away from along street piping lane (2) one side of building body (1) through cable (15) with building body (1) connects, cable (15) slope sets up.
4. The walk-in building with pipe gallery function of claim 1, further comprising: building body (1) is for riding the building, along street piping lane (2) set up in the below on two layers on the building, the tip along street piping lane (2) extends to the outside on two layers on the building.
5. The walk-in building with pipe gallery function of claim 1, further comprising: the inspection door is characterized in that an access hole is formed in the bottom plate (6), one side of the inspection door (16) is hinged to the bottom plate (6), and the other side of the inspection door (16) and the bottom plate (6) are respectively provided with a lock catch and a lock pin which are matched with each other.
6. The walk-in building with pipe gallery function of claim 1, further comprising: the base comprises a limiting block (17), a lateral mounting plate (18) and a transverse mounting plate (19);
an embedded part is arranged on the side plate (4), and the lateral mounting plate (18) is fixed on the side plate (4) through the embedded part; the bracket (12) is mounted on the transverse mounting plate (19);
the lateral wall of side direction mounting panel (18) is provided with a plurality of recesses (20) along its direction of height at the interval, lateral wall department of recess (20) lower part is provided with butt joint piece (21), one side of horizontal mounting panel (19) tip is provided with joint piece (22), the width of joint piece (22) is less than butt joint piece (21) is apart from the distance of recess (20) upper portion lateral wall, joint piece (22) joint in recess (20) diapire with between butt joint piece (21), stopper (17) joint in horizontal mounting panel (19) tip with between the recess (20) lateral wall.
7. The walk-in building with pipe gallery function of claim 6, wherein: the number of the transverse mounting plates (19) is multiple, the transverse mounting plates (19) are mounted along the height direction of the lateral mounting plates (18) through the grooves (20), and the lengths of the transverse mounting plates (19) are decreased from the middle to the top and the bottom.
8. The walk-in building with pipe gallery function of claim 1, further comprising: a grid plate (23) is arranged between the rainwater tank (8) and the water inlet of the drainage channel (9).
9. The walk-in building with pipe gallery function of claim 1, further comprising: two adjacent be provided with the pontic structure between along street piping lane (2), the pontic is structural to be provided with pontic piping lane (24), pontic piping lane (24) and its both sides along street piping lane (2) intercommunication.
10. The walk-in building with pipe gallery function of claim 1, further comprising: and the inner wall of the cavity (7) is provided with a heat-insulating layer.
CN202222088603.4U 2022-08-08 2022-08-08 Street building with pipe gallery function Active CN217870925U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222088603.4U CN217870925U (en) 2022-08-08 2022-08-08 Street building with pipe gallery function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222088603.4U CN217870925U (en) 2022-08-08 2022-08-08 Street building with pipe gallery function

Publications (1)

Publication Number Publication Date
CN217870925U true CN217870925U (en) 2022-11-22

Family

ID=84074490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222088603.4U Active CN217870925U (en) 2022-08-08 2022-08-08 Street building with pipe gallery function

Country Status (1)

Country Link
CN (1) CN217870925U (en)

Similar Documents

Publication Publication Date Title
CN102494383B (en) Method for ventilating and dehumidifying underground garage
CN101566067B (en) Entire-underground cable tunnel safety manhole being used also as ventilation shaft
CN207685859U (en) A kind of underground pipe gallery
CN201509024U (en) Outdoor preloaded-box-type switch apparatus
CN110185292A (en) A kind of energy-saving and environmental protection, the Trinitarian industrial premises venue of ecology and its key node design and building method
CN217870925U (en) Street building with pipe gallery function
WO2024060816A1 (en) Novel 5g energy-saving cabinet and multifunctional pole application system
CN211368777U (en) Utility tunnel
CN217810463U (en) Bridge structure with pipe gallery function
CN1936440A (en) Super-energy-saving comfortible health-care type local air-conditioner
CN203940565U (en) Building pipe well formula ventilating system
CN207303804U (en) A kind of burned prefabricated substation
CN207989064U (en) Tunnel construction with generating function
CN112202138B (en) Spiral hidden excavation cable tunnel structure
CN211257072U (en) Utility tunnel ventilation unit, utility tunnel and utility tunnel system
CN205557571U (en) Prestressing force divides and adds series side storehouse drainage type underground pipe gallery
CN219411536U (en) Hidden drainage exhaust structure of roofing square
CN205742466U (en) Prestressing force is to adding series rain dirt shunting underground pipe gallery
CN102562153A (en) Setting method for auxiliary system of electric power tunnel
CN205557563U (en) Prestressing force list adds series pipe storehouse and share formula underground pipe gallery
CN213015639U (en) Vertical central tube corridor parking system
CN218292032U (en) Utility tunnel co-constructed with basement
CN217896727U (en) Sidewalk wind and rain pipe gallery
CN205557570U (en) Prestressing force divides and adds series pipe storehouse formula underground pipe gallery side by side
CN211063191U (en) Novel view type underground box-type substation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant