CN217784406U CN202221816916.0U CN202221816916U CN217784406U CN 217784406 U CN217784406 U CN 217784406U CN 202221816916 U CN202221816916 U CN 202221816916U CN 217784406 U CN217784406 U CN 217784406U
Authority
CN
China
Prior art keywords
screw rod
water conservancy
screw
fixing device
leveling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221816916.0U
Other languages
Chinese (zh)
Inventor
冯磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Chicheng Municipal Engineering Co ltd
Original Assignee
Anhui Chicheng Municipal Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Chicheng Municipal Engineering Co ltd filed Critical Anhui Chicheng Municipal Engineering Co ltd
Priority to CN202221816916.0U priority Critical patent/CN217784406U/en
Application granted granted Critical
Publication of CN217784406U publication Critical patent/CN217784406U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model belongs to the technical field of the water conservancy, especially, be a fixing device for water conservancy pipeline laying, comprising a base plate, the bottom fixed mounting of bottom plate has the leveling leg, the leveling leg includes first screw rod, the bottom threaded connection of first screw rod has the screwed pipe, the inside activity of screwed pipe is provided with the leveling pole, the bottom threaded connection of screwed pipe has the second screw rod. The quantity through the leveling leg sets up to four and four leveling leg symmetrical installations in the bottom plate four corners, size of a dimension through first screw rod and second screw rod equals, the external screw thread of screwed pipe and first screw rod and the external screw thread looks adaptation setting of second screw rod, avoid because of the easy height unevenness of foundation ditch when excavating, and lead to the pipeline to take place the skew extremely easily when placing, the stability of pipeline has been improved, through the inside internal thread of seting up of screw thread seat with twist and move screw rod external screw thread looks adaptation setting, the convenience is installed fixedly according to the water conservancy pipe diameter size of difference.

Description

Fixing device for laying water conservancy pipelines
Technical Field
The utility model belongs to the technical field of the water conservancy, concretely relates to fixing device is used in water conservancy pipeline laying.
Background
Hydraulic engineering is an engineering built for controlling and allocating surface water and underground water in the nature to achieve the purpose of removing harmful substances and benefiting benefits, and in order to prevent displacement of a pipeline, a clamping ring is usually arranged on the pipeline to fix the pipeline in the hydraulic engineering.
Present hydraulic engineering construction pipeline is most directly buried underground, does not have certain fixing device, because hydraulic engineering's foundation ditch is uneven when excavating easily, leads to the pipeline to take place the skew extremely easily when placing to lead to the dislocation of pipeline, and current pipeline fixing device, because the size of pipeline differs, need frequently to change suitable clamp ring, carry out the position that just can guarantee the piping erection with alone holding the pipeline in the fixed course to the pipeline.
SUMMERY OF THE UTILITY MODEL
To solve the problems set forth in the background art described above. The utility model provides a fixing device for water conservancy pipeline laying has solved hydraulic engineering's foundation ditch easy height unevenness when excavating, leads to the pipeline to take place the skew extremely easily when placing to lead to the problem of the dislocation of pipeline.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a water conservancy pipeline lays and uses fixing device, includes the bottom plate, the bottom fixed mounting of bottom plate has leveling leg, leveling leg includes first screw rod, the bottom threaded connection of first screw rod has the screwed pipe, the inside activity of screwed pipe is provided with leveling rod, the bottom threaded connection of screwed pipe has the second screw rod, the top fixed mounting of bottom plate has the base, the top fixed mounting of base has folder down, the inside fixedly connected with spring of folder down, the first splint of top fixedly connected with of spring, one side activity of folder is provided with fixing bolt down, the top movable mounting of folder has last folder down, go up the inside fixedly connected with screw thread seat of folder, the inside threaded connection of screw thread seat has the screw rod of twisting, the one end fixed mounting who twists the screw rod has the second splint.
Preferably, the number of the leveling legs is four, and the four leveling legs are symmetrically arranged at four corners of the bottom plate.
Preferably, the first screw rod and the second screw rod are equal in size, and the threaded pipe is matched with the external threads of the first screw rod and the second screw rod.
Preferably, the lower clamping piece is welded to the top of the bottom plate through the base, and the threaded seat is welded to the top of the upper clamping piece.
Preferably, the internal thread of seting up in the screw thread seat is with twist and move screw rod external screw thread looks adaptation setting, first splint and second splint size are equal.
Preferably, the number of the fixing bolts is four, and the four fixing bolts symmetrically penetrate through the lower clamping piece and the upper clamping piece.
Compared with the prior art, the beneficial effects of the utility model are that:
the number of the leveling legs is four, the four leveling legs are symmetrically arranged at four corners of the bottom plate, furthermore, the sizes of the first screw and the second screw are equal, the external threads of the threaded pipe and the first screw and the external threads of the second screw are matched and arranged, the problem that the pipeline is prone to deviation when being placed due to the fact that a foundation pit is prone to being uneven is avoided, the stability of the pipeline is improved, the spring and the first clamping plate are fixedly connected through the inner portion of the lower clamping piece, the threaded seat is welded to the top of the upper clamping piece, furthermore, the internal threads arranged inside the threaded seat and the external threads of the screwing screw are matched and arranged, the pipeline can be conveniently installed and fixed according to different diameters of the water conservancy pipe, the number of the fixing bolts is four, the four fixing bolts symmetrically penetrate through the lower clamping piece and the upper clamping piece, the water conservancy pipe is integrally installed, the stability of the pipeline is improved, and dislocation of the pipeline is prevented.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a complete structural schematic diagram of the present invention;
FIG. 2 is a perspective view of the lower clip of the present invention;
FIG. 3 is a perspective view of the upper clamp of the present invention;
fig. 4 is a three-dimensional structure view of the leveling leg of the present invention.
In the figure: 1. a base plate; 2. a base; 3. a spring; 4. leveling the legs; 5. adjusting a rod; 6. a first splint; 7. a lower clamp; 8. fixing the bolt; 9. a second splint; 10. screwing the screw rod; 11. a threaded seat; 12. an upper clamp; 13. a first screw; 14. a threaded pipe; 15. a second screw.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides the following technical solutions: the utility model provides a fixing device for water conservancy pipeline laying, comprising a base plate 1, the bottom fixed mounting of bottom plate 1 has leveling leg 4, leveling leg 4 includes first screw rod 13, the bottom threaded connection of first screw rod 13 has screwed pipe 14, the inside activity of screwed pipe 14 is provided with leveling rod 5, the bottom threaded connection of screwed pipe 14 has second screw rod 15, the top fixed mounting of bottom plate 1 has base 2, the top fixed mounting of base 2 has lower folder 7, the inside fixed connection of lower folder 7 has spring 3, the top fixedly connected with first splint 6 of spring 3, one side activity of lower folder 7 is provided with fixing bolt 8, the top movable mounting of lower folder 7 has upper clamping piece 12, the inside fixedly connected with screw base 11 of upper clamping piece 12, the inside threaded connection of screw base 11 has the screw rod 10 of twisting, the one end fixed mounting who twists screw rod 10 has second splint 9.
In an aspect of this embodiment, set up to four and four leveling legs 4 symmetrically install in bottom plate 1 four corners through the quantity of leveling leg 4, further, through the size of first screw 13 and second screw 15 equals, screwed pipe 14 and the external screw thread of first screw 13 and the external screw thread looks adaptation setting of second screw 15 avoid because of the easy height unevenness of foundation ditch when digging, and lead to the pipeline to take place the skew extremely easily when placing, improved the stability of pipeline.
In an aspect of this embodiment, through spring 3 and the first splint 6 fixed connection that lower clamp 7 inside set up, screw thread seat 11 welds at last clamp 12 top, and further, through the inside internal thread of seting up of screw thread seat 11 and twist screw rod 10 external screw thread looks adaptation setting, the convenience is installed fixedly according to the water conservancy pipe diameter size of difference.
In one aspect of this embodiment, the number of the fixing bolts 8 is four, and the four fixing bolts 8 symmetrically penetrate through the lower clamp 7 and the upper clamp 12, so that the water conservancy pipe is integrally installed, the stability of the pipeline is improved, and the pipeline dislocation is prevented.
The utility model discloses a theory of operation and use flow: through the quantity setting of leveling leg 4 to four and four leveling leg 4 symmetrical installations in 1 four corners of bottom plate, furtherly, size through first screw rod 13 and second screw rod 15 equals, screwed pipe 14 and the external screw thread of first screw rod 13 and the external screw thread looks adaptation setting of second screw rod 15, avoid because of the foundation ditch easy height unevenness when excavating, and lead to the pipeline to take place the skew extremely easily when placing, the stability of pipeline has been improved, spring 3 and first splint 6 fixed connection through the inside setting of folder 7 down, screw seat 11 welds at last folder 12 top, furtherly, through the inside internal thread of seting up of screw seat 11 and the external screw thread looks adaptation setting of twisting screw rod 10, conveniently install fixedly according to the water conservancy pipe diameter size of difference, set up to four and four fixing bolt 8 symmetrical penetrating lower folder 7 and upper folder 12 through the quantity of fixing bolt 8, carry out the integral erection to the water conservancy pipe, the stability of pipeline has been increased, prevent the emergence of pipeline dislocation.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a water conservancy pipeline lays and uses fixing device, includes bottom plate (1), the bottom fixed mounting of bottom plate (1) has leveling leg (4), its characterized in that: leveling leg (4) includes first screw rod (13), the bottom threaded connection of first screw rod (13) has screwed pipe (14), the inside activity of screwed pipe (14) is provided with leveling rod (5), the bottom threaded connection of screwed pipe (14) has second screw rod (15), the top fixed mounting of bottom plate (1) has base (2), folder (7) under the top fixed mounting of base (2), the inside fixedly connected with spring (3) of folder (7) down, the first splint (6) of top fixedly connected with of spring (3), the activity of one side of folder (7) is provided with fixing bolt (8) down, the top movable mounting of folder (7) has last folder (12) down, the inside fixedly connected with screw thread seat (11) of going up folder (12), the inside threaded connection of screw thread seat (11) has and moves screw rod (10) with to twist, the one end fixed mounting who moves screw rod (10) has second splint (9).
2. The fixing device for water conservancy pipeline laying of claim 1, characterized in that: the number of the leveling legs (4) is four, and the four leveling legs (4) are symmetrically arranged at four corners of the bottom plate (1).
3. The fixing device for water conservancy pipe laying of claim 1, characterized in that: the sizes of the first screw (13) and the second screw (15) are equal, and the threaded pipe (14) is matched with the external threads of the first screw (13) and the second screw (15).
4. The fixing device for water conservancy pipeline laying of claim 1, characterized in that: the lower clamping piece (7) is welded to the top of the bottom plate (1) through the base (2), and the threaded seat (11) is welded to the top of the upper clamping piece (12).
5. The fixing device for water conservancy pipe laying of claim 1, characterized in that: the internal thread that screw thread seat (11) inside was seted up with twist and move screw rod (10) external screw thread looks adaptation setting, first splint (6) and second splint (9) size are equal.
6. The fixing device for water conservancy pipe laying of claim 1, characterized in that: the number of the fixing bolts (8) is four, and the four fixing bolts (8) symmetrically penetrate through the lower clamping piece (7) and the upper clamping piece (12).
CN202221816916.0U 2022-07-15 2022-07-15 Fixing device for laying water conservancy pipelines Active CN217784406U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221816916.0U CN217784406U (en) 2022-07-15 2022-07-15 Fixing device for laying water conservancy pipelines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221816916.0U CN217784406U (en) 2022-07-15 2022-07-15 Fixing device for laying water conservancy pipelines

Publications (1)

Publication Number Publication Date
CN217784406U true CN217784406U (en) 2022-11-11

Family

ID=83937857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221816916.0U Active CN217784406U (en) 2022-07-15 2022-07-15 Fixing device for laying water conservancy pipelines

Country Status (1)

Country Link
CN (1) CN217784406U (en)

Similar Documents

Publication Publication Date Title
CN206145311U (en) Detachable water conservancy pipeline connecting piece of damping
CN217784406U (en) Fixing device for laying water conservancy pipelines
CN212107205U (en) Water conservancy pipeline supports connection structure
CN213745243U (en) Novel buried pipeline bracket
CN214497780U (en) Construction auxiliary device is prevented subsiding by town road construction underground piping
CN213393915U (en) Gas pipeline wears floor bearing strutting arrangement
CN209779663U (en) A stabilising arrangement for building pile
CN209958339U (en) Connecting piece for steel pipe piles and steel pipe piles
CN212203400U (en) Pipeline supporting and protecting device
CN211925033U (en) Lifting frame for household water pipeline
CN221300369U (en) Pre-buried adjustable water supply and drainage pipe hanging bracket
CN215484903U (en) Civil engineering construction support
CN216049805U (en) Assembled settlement monitoring plate
CN213479377U (en) Novel bridge pipeline supporting structure
CN221237288U (en) Building pipeline lays fixing device in hydraulic engineering
CN220539258U (en) Positioning and reinforcing device for embedded pipeline
CN212482462U (en) Mounting device of wall-hanging hydrostatic level
CN220469466U (en) Wall crack repairing device
CN213512378U (en) Pouring support for pipe joint installation
CN220337642U (en) Pipeline positioning support
CN214530546U (en) Headstock gear installing support
CN212389854U (en) Natural gas pipeline support
CN214146814U (en) Underground water pipeline supporting device
CN217454913U (en) Pipe supporting device
CN216201199U (en) Underground passage pipeline suspension bracket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant