CN217581426U - Fixing temporary fixing device for special-shaped complex high-rise public building steel frame - Google Patents

Fixing temporary fixing device for special-shaped complex high-rise public building steel frame Download PDF

Info

Publication number
CN217581426U
CN217581426U CN202220932478.8U CN202220932478U CN217581426U CN 217581426 U CN217581426 U CN 217581426U CN 202220932478 U CN202220932478 U CN 202220932478U CN 217581426 U CN217581426 U CN 217581426U
Authority
CN
China
Prior art keywords
face
fixing
special
public building
steel frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220932478.8U
Other languages
Chinese (zh)
Inventor
陈贺
刘新宇
吕献广
宋浩
庞后明
马祎斌
曹国章
潘寿林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban Construction Yatai Group Co Ltd
Beijing Yatai Zhibo Technology Development Co Ltd
Original Assignee
Beijing Urban Construction Yatai Group Co Ltd
Beijing Yatai Zhibo Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban Construction Yatai Group Co Ltd, Beijing Yatai Zhibo Technology Development Co Ltd filed Critical Beijing Urban Construction Yatai Group Co Ltd
Priority to CN202220932478.8U priority Critical patent/CN217581426U/en
Application granted granted Critical
Publication of CN217581426U publication Critical patent/CN217581426U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A fixing temporary fixing device for a special-shaped complex high-rise public building steel frame relates to the technical field of building design and comprises fixing frames and supporting frames arranged on floor platforms, wherein the floor platforms are arranged among the fixing frames, each fixing frame is composed of a plurality of connecting rods, the connecting rods are connected end to end and welded together, the supporting frame is arranged on the uppermost connecting rod, and the supporting frame is arranged on the floor platform closest to the uppermost connecting rod; the utility model discloses the practicality is strong, uses unusual convenience, not only can carry out interim fixing to the upper end connecting rod, and the workman's welding of being convenient for can be suitable for multiple steelframe moreover and use cost is practiced thrift.

Description

Fixing temporary fixing device for special-shaped complex high-rise public building steel frame
Technical Field
The utility model belongs to the technical field of the architectural design technique and specifically relates to a fixed interim fixing device of complicated high-rise public building steelframe of dysmorphism is related to.
Background
The steel frame structure is well known to be of great importance in modern buildings, and is particularly indispensable in some high-rise buildings, because the building is high, the steel frame can be designed in sections for safety and other factors in the process of manufacturing and transporting, then the steel frame is transported to a construction site to be constructed and welded, particularly, when some arc-shaped steel frames are welded, the steel frame needs to be temporarily fixed and supported, the phenomenon that the arc-shaped steel frame collapses or deforms due to self weight to influence later construction is avoided, if large-scale equipment such as a tower crane is used for supporting, time is wasted, too much resources of the construction site can be occupied, construction of other departments is influenced, the design specifications of all the steel frames are different, the supporting structure with a single specification cannot completely meet the requirements, and resources are wasted due to repeated purchasing and manufacturing of other specifications.
SUMMERY OF THE UTILITY MODEL
In order to overcome not enough in the background art, the utility model discloses a fixed temporary fixing device of complicated high-rise public building steelframe of dysmorphism, the utility model discloses a set up the support frame on the floor platform nearest from the top connecting rod to reach the outside steelframe of auxiliary stay building, the workman's welding operation's of being convenient for purpose.
In order to realize the utility model aims at, the utility model adopts the following technical scheme:
the utility model provides a fixed interim fixing device of complicated high-rise public building steelframe of dysmorphism, includes the mount and sets up the support frame on the floor platform, and the floor platform sets up between each mount, and the mount comprises a plurality of connecting rods, and each connecting rod end to end welds together, is equipped with the support frame on the connecting rod of the top, and the support frame setting is on the floor platform nearest from the connecting rod of the top.
The support frame has the removal portion, the fixed part, the connecting box constitutes with spacing portion, the removal portion comprises connecting plate, vaulting pole and universal wheel, connecting plate lower part face evenly distributed has at least three vaulting pole, the one end of vaulting pole is connected with the lower part face of connecting plate, the other end of vaulting pole all is equipped with the universal wheel, be equipped with the fixed orifices on the connecting plate between each vaulting pole, the fixed orifices runs through the upper portion face and the lower part face of connecting plate, be equipped with the fixed part in the fixed orifices, be equipped with the connecting box on the fixed part, be equipped with spacing portion in the connecting box.
The universal wheels have the same structure and have self-locking function.
The fixing part comprises dead lever, fixture block, connecting axle, first magnetic path, footboard, second magnetic path and supporting shoe, and the dead lever is cylindrical structure, and the upper end of dead lever is equipped with the connecting box, and the dead lever side is equipped with at least one fixture block, and each fixture block structure is the same, and the even annular setting of each fixture block is in the side of dead lever, and the lower part face of dead lever is equipped with the spread groove, is equipped with connecting axle and first magnetic path in the spread groove, is equipped with the footboard on the connecting axle, is equipped with second magnetic path and supporting shoe on the footboard.
One side of the connecting groove penetrates through the side face of the fixed rod, a connecting shaft is arranged between two symmetrical inner wall faces of the connecting groove, two ends of the connecting shaft are respectively connected with the two inner wall faces of the connecting groove, and a first magnetic block is arranged on the top face of the connecting groove.
The pedal is of a rectangular structure, one end of the pedal is arranged in the connecting groove, a through hole is formed in the side face of one end of the pedal arranged in the connecting groove, the connecting shaft is arranged in the through hole, the upper portion face of the pedal is provided with a second magnetic block, the second magnetic block and the first magnetic block are arranged correspondingly, and the lower portion face of the pedal is provided with a supporting block.
The connecting box is composed of a shell and a bottom plate, the shell is of a hollow rectangular structure, the bottom plate is arranged on the lower surface of the shell, the upper surface of the bottom plate is connected with the lower surface of the shell, the lower surface of the bottom plate is connected with the upper surface of the fixing rod, and a limiting portion is arranged in the shell.
The limiting part is composed of a limiting plate, a spring and a limiting block, the limiting block is provided with the spring, the limiting plate is of a rectangular structure, the limiting plate is arranged in the shell, the side face of the limiting plate is connected with the inner wall face of the shell, the limiting plate is arranged in parallel with the bottom plate, limiting holes are evenly formed in the limiting plate, each limiting hole penetrates through the upper face and the lower face of the limiting plate, and the limiting block is arranged in each limiting hole.
Each limiting block has the same structure, the lower end of each limiting block penetrates through the limiting hole to be arranged in the shell, the lower surface of each limiting block is provided with a spring, the upper end of each spring is connected with the lower surface of each limiting block, and the lower end of each spring is connected with the upper surface of the bottom surface.
The utility model discloses a fixed temporary fixing device of a special-shaped complex high-rise public building steel frame, which comprises a fixing frame and a support frame arranged on a floor platform, wherein the support frame is arranged on the floor platform nearest to the uppermost connecting rod, so as to achieve the purpose of assisting in supporting the building external steel frame and facilitating the welding operation of workers; the utility model discloses the practicality is strong, uses unusual convenience, not only can carry out interim fixing to the upper end connecting rod, and the workman's welding of being convenient for can be suitable for multiple steelframe moreover and use cost is practiced thrift.
Drawings
Fig. 1 is a schematic perspective view of the present invention;
fig. 2 is a schematic perspective view of the moving part of the present invention;
FIG. 3 is a schematic view of the connection between the fixing rod, the connecting box and the limiting portion of the present invention;
FIG. 4 is a cross-sectional view of the position-limiting portion of the present invention;
fig. 5 is a schematic perspective view of the limiting plate of the present invention;
fig. 6 is a schematic perspective view of the fixing portion of the present invention;
FIG. 7 is a schematic view of the pedal of the present invention;
in the figure: 1. a connecting rod; 2. a floor platform; 3. a support frame; 4. a connecting plate; 5. a fixing hole; 6. a stay bar; 7. a universal wheel; 8. fixing the rod; 9. a connection box; 10. a limiting block; 11. a housing; 12. a base plate; 13. a spring; 14. a limiting plate; 15. a limiting hole; 16. a clamping block; 17. connecting grooves; 18. a connecting shaft; 19. a first magnetic block; 20. a pedal; 21. perforating; 22. a second magnetic block; 23. and (7) a supporting block.
Detailed Description
The invention will be explained in more detail by the following examples, which disclose the invention and are intended to protect all technical improvements within the scope of the invention.
Combine 1~7 a fixed interim fixing device of complicated high-rise public building steelframe of dysmorphism, including mount and the support frame 3 of setting on floor platform 2, floor platform 2 sets up between each mount, and the mount comprises a plurality of connecting rods 1, and each connecting rod 1 end to end welds together, is equipped with support frame 3 on the connecting rod 1 of the top, and support frame 3 sets up on the floor platform 2 nearest from connecting rod 1 of the top.
The support frame 3 has the removal portion, the fixed part, connecting box 9 and spacing portion constitute, the removal portion is by connecting plate 4, vaulting pole 6 and universal wheel 7 constitute, 4 lower part face evenly distributed of connecting plate have at least three vaulting pole 6, the one end of vaulting pole 6 is connected with the lower part face of connecting plate 4, the other end of vaulting pole 6 all is equipped with universal wheel 7, be equipped with fixed orifices 5 on the connecting plate 4 between each vaulting pole 6, fixed orifices 5 run through the upper portion face and the lower part face of connecting plate 4, be equipped with the fixed part in the fixed orifices 5, be equipped with connecting box 9 on the fixed part, be equipped with spacing portion in the connecting box 9.
The universal wheels 7 have the same structure, and each universal wheel 7 has a self-locking function.
The fixing portion is composed of a fixing rod 8, clamping blocks 16, a connecting shaft 18, a first magnetic block 19, a pedal 20, a second magnetic block 22 and supporting blocks 23, the fixing rod 8 is of a cylindrical structure, the upper end of the fixing rod 8 is provided with the connecting box 9, the side face of the fixing rod 8 is provided with at least one clamping block 16, the clamping blocks 16 are identical in structure, the clamping blocks 16 are evenly and annularly arranged on the side face of the fixing rod 8, the lower portion face of the fixing rod 8 is provided with a connecting groove 17, the connecting shaft 18 and the first magnetic block 19 are arranged in the connecting groove 17, the pedal 20 is arranged on the connecting shaft 18, and the second magnetic block 22 and the supporting blocks 23 are arranged on the pedal 20.
One side of the connecting groove 17 penetrates through the side surface of the fixed rod 8, a connecting shaft 18 is arranged between two symmetrical inner wall surfaces of the connecting groove 17, two ends of the connecting shaft 18 are respectively connected with the two inner wall surfaces of the connecting groove 17, and a first magnetic block 19 is arranged on the top surface of the connecting groove 17.
The pedal 20 is of a rectangular structure, one end of the pedal 20 is arranged in the connecting groove 17, a through hole 21 is formed in the side face of one end, arranged in the connecting groove 17, of the pedal 20, the connecting shaft 18 is arranged in the through hole 21, the upper portion face of the pedal 20 is provided with a second magnetic block 22, the second magnetic block 22 is arranged corresponding to the first magnetic block 19, and the lower portion face of the pedal 20 is provided with a supporting block 23.
The connecting box 9 is composed of a shell 11 and a bottom plate 12, the shell 11 is of a hollow rectangular structure, the bottom plate 12 is arranged on the lower surface of the shell 11, the upper surface of the bottom plate 12 is connected with the lower surface of the shell 11, the lower surface of the bottom plate 12 is connected with the upper surface of the fixing rod 8, and a limiting part is arranged in the shell 11.
The limiting part is composed of a limiting plate 14, a spring 13 and a limiting block 10, the limiting plate 14 is provided with the limiting block 10, the limiting block 10 is provided with the spring 13, the limiting plate 14 is of a rectangular structure, the limiting plate 14 is arranged in the shell 11, the side face of the limiting plate 14 is connected with the inner wall face of the shell 11, the limiting plate 14 is arranged in parallel with the bottom plate 12, limiting holes 15 are evenly formed in the limiting plate 14, each limiting hole 15 penetrates through the upper face and the lower face of the limiting plate 14, and the limiting block 10 is arranged in each limiting hole 15.
Each stopper 10 has the same structure, the lower end of each stopper 10 penetrates through a stopper hole 15 and is arranged in the casing 11, a spring 13 is arranged on the lower surface of each stopper 10, the upper end of the spring 13 is connected with the lower surface of each stopper 10, and the lower end of the spring 13 is connected with the upper surface of the bottom surface.
The embodiment discloses a temporary fixing device for fixing a special-shaped complex high-rise public building steel frame, when in use, a fixing rod 8 is inserted into a fixing hole 5, a clamping block 16 is arranged above a connecting plate 4, then a moving part is pushed to push the fixing rod 8 to the position below the steel frame needing to be welded, the steel frame is arranged above a limiting block 10, then the moving part is pushed towards the direction of a connecting rod 1, a concave surface at the lower part of the connecting rod 1 downwards extrudes the lower part of each contacted limiting block 10 until the limiting blocks 10 at two sides clamp the two sides of the connecting rod 1, the connecting rod 1 is prevented from being displaced on the fixing rod 8, the displacement quantity of the limiting block 10 is determined by the width of the connecting rod 1, so that the supporting frame 3 can be suitable for connecting rods 1 with various width specifications, the moving part is continuously pushed towards the direction of the connecting rod 1 until the clamping block 16 on the fixing rod 8 is clamped into the fixing hole 5, the lower end of the fixing rod 8 is abutted against the ground of a floor platform 2, so that the supporting frame 3 supports the steel frame below the connecting rod 1, then each universal wheel 7 is locked, so that the supporting frame 3 is fixed on the connecting rod 1, then a pedal 20 is fixed by a magnetic block 20, and then the magnetic block 20 is lifted from the fixing rod 1, and then the fixing rod 20 is lifted from the fixing rod 20, and the fixing rod 20 is lifted from the fixing rod 5, and the pedal 20, and the fixing rod 5, and the pedal 20.
The detailed description of the present invention is the prior art, and although the present invention has been specifically shown and described in connection with the preferred embodiments, the method and the way of implementing the technical solution are numerous, and it is only the preferred embodiments of the present invention described above, but those skilled in the art should understand that the present invention can be variously changed in form and detail without departing from the spirit and scope of the present invention defined by the appended claims, and the present invention is within the protection scope of the present invention.

Claims (9)

1. The utility model provides a fixed interim fixing device of complicated high-rise public building steelframe of dysmorphism, includes mount and support frame (3) of setting on floor platform (2), and floor platform (2) set up between each mount, its characterized in that: the fixing frame is composed of a plurality of connecting rods (1), the connecting rods (1) are welded together end to end, a supporting frame (3) is arranged on the connecting rod (1) at the top, and the supporting frame (3) is arranged on the floor platform (2) nearest to the connecting rod (1) at the top.
2. The special-shaped complex high-rise public building steel frame fixing temporary fixing device as claimed in claim 1, which is characterized in that: support frame (3) have the removal portion, the fixed part, connecting box (9) and spacing portion constitute, the removal portion is by connecting plate (4), vaulting pole (6) and universal wheel (7) constitute, connecting plate (4) lower part face evenly distributed has at least three vaulting pole (6), the one end of vaulting pole (6) is connected with the lower part face of connecting plate (4), the other end of vaulting pole (6) all is equipped with universal wheel (7), be equipped with on connecting plate (4) between each vaulting pole (6) fixed orifices (5), upper portion face and the lower part face that connecting plate (4) were run through in fixed orifices (5), be equipped with the fixed part in fixed orifices (5), be equipped with connecting box (9) on the fixed part, be equipped with spacing portion in connecting box (9).
3. The special-shaped complex high-rise public building steel frame fixing temporary fixing device as claimed in claim 2, which is characterized in that: the universal wheels (7) have the same structure, and each universal wheel (7) has a self-locking function.
4. The special-shaped complex high-rise public building steel frame fixing temporary fixing device as claimed in claim 2, wherein: the fixing part is composed of a fixing rod (8), clamping blocks (16), a connecting shaft (18), a first magnetic block (19), a pedal (20), a second magnetic block (22) and a supporting block (23), the fixing rod (8) is of a cylindrical structure, a connecting box (9) is arranged at the upper end of the fixing rod (8), at least one clamping block (16) is arranged on the side face of the fixing rod (8), the structures of the clamping blocks (16) are the same, the clamping blocks (16) are evenly and annularly arranged on the side face of the fixing rod (8), a connecting groove (17) is arranged on the lower portion face of the fixing rod (8), the connecting shaft (18) and the first magnetic block (19) are arranged in the connecting groove (17), the pedal (20) is arranged on the connecting shaft (18), and the second magnetic block (22) and the supporting block (23) are arranged on the pedal (20).
5. The special-shaped complex high-rise public building steel frame fixing temporary fixing device as claimed in claim 4, wherein: one side of the connecting groove (17) penetrates through the side face of the fixing rod (8), a connecting shaft (18) is arranged between two symmetrical inner wall faces of the connecting groove (17), two ends of the connecting shaft (18) are respectively connected with the two inner wall faces of the connecting groove (17), and a first magnetic block (19) is arranged on the top face of the connecting groove (17).
6. The special-shaped complex high-rise public building steel frame fixing temporary fixing device as claimed in claim 4, wherein: footboard (20) are the rectangle structure, and footboard (20) one end sets up in connecting groove (17), and the side that footboard (20) set up one end in connecting groove (17) is equipped with perforation (21), and connecting axle (18) set up in perforation (21), and the upper portion face of footboard (20) is equipped with second magnetic path (22), and second magnetic path (22) correspond the setting with first magnetic path (19), and the lower part face of footboard (20) is equipped with supporting shoe (23).
7. The special-shaped complex high-rise public building steel frame fixing temporary fixing device as claimed in claim 2, wherein: the connecting box (9) is composed of a shell (11) and a bottom plate (12), the shell (11) is of a hollow rectangular structure, the bottom plate (12) is arranged on the lower surface of the shell (11), the upper surface of the bottom plate (12) is connected with the lower surface of the shell (11), the lower surface of the bottom plate (12) is connected with the upper surface of the fixing rod (8), and a limiting part is arranged in the shell (11).
8. The special-shaped complex high-rise public building steel frame fixing temporary fixing device as claimed in claim 7, wherein: spacing portion comprises limiting plate (14), spring (13) and limiting block (10), is equipped with limiting block (10) on limiting plate (14), is equipped with spring (13) on limiting block (10), limiting plate (14) are the rectangle structure, limiting plate (14) set up in casing (11), the side of limiting plate (14) is connected with the internal face of casing (11), limiting plate (14) and bottom plate (12) parallel arrangement, evenly be provided with spacing hole (15) on limiting plate (14), each spacing hole (15) all run through the upper portion face and the lower part face of limiting plate (14), all be equipped with limiting block (10) in each spacing hole (15).
9. The special-shaped complex high-rise public building steel frame fixing temporary fixing device as claimed in claim 8, wherein: each stopper (10) structure is the same, and the lower extreme of each stopper (10) all passes spacing hole (15) and sets up in casing (11), and the lower part face of stopper (10) all is equipped with spring (13), and the upper end of spring (13) is connected with the lower part face of stopper (10), and the lower extreme of spring (13) is connected with the upper portion face of bottom surface.
CN202220932478.8U 2022-04-22 2022-04-22 Fixing temporary fixing device for special-shaped complex high-rise public building steel frame Active CN217581426U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220932478.8U CN217581426U (en) 2022-04-22 2022-04-22 Fixing temporary fixing device for special-shaped complex high-rise public building steel frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220932478.8U CN217581426U (en) 2022-04-22 2022-04-22 Fixing temporary fixing device for special-shaped complex high-rise public building steel frame

Publications (1)

Publication Number Publication Date
CN217581426U true CN217581426U (en) 2022-10-14

Family

ID=83543463

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220932478.8U Active CN217581426U (en) 2022-04-22 2022-04-22 Fixing temporary fixing device for special-shaped complex high-rise public building steel frame

Country Status (1)

Country Link
CN (1) CN217581426U (en)

Similar Documents

Publication Publication Date Title
CN102817484B (en) Heavy multifunctional combined supporting frame
CN210164286U (en) Support arrangement for high altitude large-span steel structure truss installation usefulness
CN217581426U (en) Fixing temporary fixing device for special-shaped complex high-rise public building steel frame
CN114704096A (en) Climbing formula quick detach concrete spreader in pit shaft
CN207827674U (en) A kind of special cage of building block pile
CN213805852U (en) Jacking device for mounting latticed shell
CN107043072A (en) Exempt from the integration of falling beam inner climbing crane tower support meanss and implementation
CN213204913U (en) Modular prefabricated staircase operation platform
CN212224669U (en) Super large box steel column installation system
CN210084690U (en) Hoistway with elevator
CN112982933B (en) Simple scaffold device for spherical tank construction
CN111962957A (en) Assembling tool for erecting power line steel pipe pole
CN117779822B (en) Combined jacket manufacturing, assembling and supporting device and application method thereof
CN220151000U (en) Ladder cage convenient to connect
CN215484487U (en) Skeleton convenient to install for assembly type structure
CN221236372U (en) Portable combined scaffold for building construction
CN217458539U (en) Hanging truss for hole
CN218028873U (en) Detachable operation platform that encorbelments of steel-pipe column high altitude butt joint
CN215290657U (en) Be used for building structure to assemble and use telescopic bracket
CN217393688U (en) Anti-toppling device for injection pipe in ingot mold
CN221096383U (en) Anti-overturning support frame for climbing operation ladder
CN212374758U (en) Climbing frame of tower crane
CN217576058U (en) Support for stacking and transporting laminated plates
CN217253967U (en) Climb a cat ladder welding frock
CN215443190U (en) Convenient installation system of large-scale round pin axle

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant