CN215368593U - Carrying frame is built in room - Google Patents

Carrying frame is built in room Download PDF

Info

Publication number
CN215368593U
CN215368593U CN202121824466.5U CN202121824466U CN215368593U CN 215368593 U CN215368593 U CN 215368593U CN 202121824466 U CN202121824466 U CN 202121824466U CN 215368593 U CN215368593 U CN 215368593U
Authority
CN
China
Prior art keywords
locking
hole
carrying
block
hoop
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121824466.5U
Other languages
Chinese (zh)
Inventor
林小明
林武辉
翁祖辉
林冬梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gao Hua Fujian Construction Engineering Co ltd
Original Assignee
Gao Hua Fujian Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gao Hua Fujian Construction Engineering Co ltd filed Critical Gao Hua Fujian Construction Engineering Co ltd
Priority to CN202121824466.5U priority Critical patent/CN215368593U/en
Application granted granted Critical
Publication of CN215368593U publication Critical patent/CN215368593U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The application relates to a building and erecting frame, in particular to a building and erecting frame which comprises a building plate and a supporting rod, wherein the supporting rod is provided with a positioning hole; the support plate is provided with a locking clamp hoop, the locking clamp hoop is located on the outer wall of the support rod, a locking hole is formed in the locking clamp hoop in a penetrating mode, a locking bolt is arranged in the locking hole in a penetrating mode through the positioning hole, and the locking bolt is detachably connected with the locking clamp hoop. Through with the bracing piece, take the support plate split and become individuality to set up detachable locking bolt and locking clamp on taking the support plate, thereby can assemble and build the carrier for firm room, this application has the effect that makes the room build the carrier and can dismantle, the transportation of being convenient for.

Description

Carrying frame is built in room
Technical Field
The application relates to the technical field of house construction, in particular to a building erection and carrying frame.
Background
The house building refers to a house or a place where people perform production, life, residence or other activities, such as industrial buildings, civil buildings, agricultural buildings and the like; in the construction of house, because of the unable contact of some indoor high-order work operating personnel, need the room to build the carrier frame and cooperate the use this moment.
Chinese patent publication No. CN213654160U discloses a building frame, which comprises a carrying plate, a locking angle bar and a plurality of adjusting angle bars uniformly distributed at the bottom of the carrying plate, a plurality of positioning holes arranged on the locking angle bar, a locking rod slidably connected to the locking angle bar, a locking hole and a locking assembly arranged on the locking rod, an adjusting rod slidably connected to the adjusting angle bar, and a screw rod assembly arranged on the carrying plate and used for driving the adjusting angle bars to move up and down; when the locking hole is in butt joint with one of the positioning holes, the locking assembly is inserted into the positioning hole and the locking hole so as to determine the height of the carrying plate.
In view of the above-mentioned related art, the inventor believes that the building carrier is bulky and inconvenient to move indoors when moving indoors.
SUMMERY OF THE UTILITY MODEL
In order to facilitate the use of building the carrying frame, the application provides a building frame.
The application provides a pair of carrier is built in room adopts following technical scheme:
a building erecting frame comprises a erecting plate and a supporting rod, wherein the supporting rod is provided with a positioning hole; the support plate is provided with a locking clamp hoop, the locking clamp hoop is located on the outer wall of the support rod, a locking hole is formed in the locking clamp hoop in a penetrating mode, a locking bolt is arranged in the locking hole in a penetrating mode through the positioning hole, and the locking bolt is detachably connected with the locking clamp hoop.
Through adopting above-mentioned technical scheme, because the carrier frame is built in the room needs to use in various environment, some inside have higher building of choosing, have the vestibule and be far less than the inside condition, consequently some carrier frames can produce certain difficulty when passing through, if build the carrier frame with the room and disassemble into a plurality of little parts, assemble then can effectively avoid this problem when the transportation is built inside again.
Therefore, the room building and carrying frame is divided into the supporting rod, the carrying plate and the locking clamp, the positioning hole is formed in the supporting rod, the locking hole is formed in the locking clamp, the locking bolt penetrates through the locking hole and the positioning hole simultaneously, the carrying plate can pass through the supporting rod, the room building and carrying frame can be supported indoors for use, and convenience is improved.
Optionally, the locking clamp includes first semicircle hoop and second semicircle hoop, first semicircle hoop with take up board fixed connection, first semicircle hoop with the one end of second semicircle hoop all is provided with the dop, and the other end sets up all has the draw-in groove, the dop with the draw-in groove mutually supports, is located respectively the dop with on the draw-in groove the central point of locking hole all is located same axis.
Through adopting above-mentioned technical scheme, first semicircle hoop and the integrated into one piece of carrying board, first semicircle hoop and second semicircle hoop are through the cooperation relation of dop and draw-in groove again, make the locking clamp inseparabler with the being connected of carrying board, and dop and draw-in groove are all run through by the locking bolt, make the dismantlement and the installation on the bracing piece that the locking clamp can be more convenient.
Optionally, the chuck is a dovetail, the slot is a dovetail groove, and the dovetail groove are matched with each other.
By adopting the technical scheme, the dovetail is vertically inserted into the dovetail groove when the dovetail is installed, the acting force in the horizontal direction cannot easily separate the first semicircular hoop from the second semicircular hoop, the connection relation between the first semicircular hoop and the second semicircular hoop is enhanced, and the integrity of the locking hoop is enhanced.
Optionally, the number of the positioning holes is multiple, and the positioning holes are uniformly arranged at intervals along the length direction of the support rod.
By adopting the technical scheme, the height of the carrying plate is determined by the position of the positioning hole, so that the positioning holes are uniformly arranged at intervals, the height of the carrying plate can be adjusted, and the carrying plate can be selected according to different use requirements.
Optionally, the inner wall of the positioning hole is provided with a rubber sleeve.
Through adopting above-mentioned technical scheme, because the locating hole need bear the pressure of taking the board and passing through the locking bolt transfer, consequently set up the rubber sleeve in the inner wall of locating hole and be favorable to buffering the pressure that receives, reduce the damage to the locating hole structure, can also increase the frictional force to the locking bolt that inserts, make it be difficult for deviating from.
Optionally, the carrying plate comprises a first carrying block, a second carrying block and a magnetic splicing block, wherein a plurality of splicing heads are arranged on the magnetic splicing block, a plurality of splicing grooves are arranged on the first carrying block and the second carrying block, and the splicing grooves and the splicing heads are matched with each other and connected in a magnetic attraction manner; the first carrying block, the second carrying block and the magnetic splicing block horizontally penetrate through a connecting rod together.
Through adopting above-mentioned technical scheme, the board of taking on is further disassembled and is carried on piece, second and magnetism concatenation piece for first, and the volume reduces after the split, more is favorable to removing.
Optionally, an auxiliary seat is arranged on the bottom surface of the carrying plate, and the auxiliary seat is magnetically connected with the magnetic splicing block; the utility model discloses a fixing device, including auxiliary seat, fixed bolt, auxiliary rod's below is provided with the auxiliary rod, and the auxiliary rod slope sets up, the other end of auxiliary rod with the connection can be dismantled to the auxiliary seat, the solid fixed ring of other end fixedly connected with of auxiliary rod, gu fixed ring wears to be equipped with fixing bolt, fixing bolt runs through simultaneously the locating hole.
Through adopting above-mentioned technical scheme, the auxiliary seat is connected with magnetism splice piece magnetism, for the board of carrying provides the base, and increased the expansion possibility of building the carrier. The auxiliary rod, the supporting rod and the carrying plate which are obliquely arranged form a triangular supporting structure, and the triangular structure is stable, so that the whole building carrying frame has stability.
Optionally, the auxiliary seat is provided with a receiving hole into which one end of the auxiliary rod is inserted
Through adopting above-mentioned technical scheme, the auxiliary rod inserts in the accommodation hole for the auxiliary rod is difficult for removing when providing the holding power for taking the board, in order to improve overall structure's stability.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the building carrying frame is disassembled into small parts which are easy to carry by arranging the supporting rods, the carrying plates and the locking clamps, so that the mobility of the building carrying frame is improved;
2. the stability of the building and erecting frame is improved by arranging the auxiliary rod, the auxiliary seat, the dovetail groove and the dovetail;
3. the height of the carrying plate can be adjusted by arranging the positioning holes which are uniformly distributed at intervals.
Drawings
Fig. 1 is a schematic structural view of the whole of the building erection carriage of the present embodiment.
Fig. 2 is a sectional view for showing a connection relationship between the carrying plate and the support column.
Fig. 3 is a sectional view for illustrating a connection relationship between the auxiliary lever and the auxiliary seat.
Description of reference numerals: 1. a support bar; 2. building a support plate; 4. an auxiliary seat; 11. a circular truncated cone base; 12. positioning holes; 13. a rubber sleeve; 21. a first mounting block; 22. magnetic splice blocks; 23. a second mounting block; 24. locking the clamp; 25. a locking bolt; 26. a locking nut; 27. a connecting rod; 41. an auxiliary lever; 42. a fixing ring; 43. fixing the bolt; 44. fixing a nut; 45. an accommodation hole; 221. splicing heads; 222. splicing grooves; 241. a first semicircular hoop; 242. a second semi-circular hoop; 243. a dovetail groove; 244. dovetail joints; 245. a locking hole.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses carrier is built in room. Referring to fig. 1, the building carrier includes a carrier plate 2, four upright support bars 1, and a locking clip 24.
The upper level of the supporting rod 1 is provided with a plurality of positioning holes 12 in a penetrating mode, the positioning holes 12 are evenly arranged along the length direction of the supporting rod 1 at intervals, the inner walls of the positioning holes 12 are provided with rubber sleeves 13, and the outer walls of the rubber sleeves 13 are attached to the inner walls of the positioning holes 12. The bottom of the supporting rod 1 is fixed with a circular truncated cone base 11 to improve the contact area of the supporting rod 1 and the ground, so that the supporting rod 1 can be kept stable in a vertical state.
As shown in fig. 1 and fig. 2, the carrying plate 2 is a rectangular plate, and the carrying plate 2 includes a first carrying block 21, a second carrying block 23 and a magnetic splicing block 22, a plurality of splicing heads 221 are provided on the magnetic splicing block 22, a plurality of splicing grooves 222 are provided on the first carrying block 21 and the second carrying block 23, the splicing grooves 222 and the splicing heads 221 are mutually matched and magnetically attracted, and the first carrying block 21 and the second carrying block 23 can be made of materials with large strength, such as steel plates or carbon fiber plates, so as to support the movement of a person on the carrying plate 2.
As shown in fig. 2, the locking clip 24 includes a first semicircular clip 241 and a second semicircular clip 242, wherein the middle of the first semicircular clip 241 is welded to the right angle of the carrier plate 2, the opening of the first semicircular clip 241 faces outwards, and the second semicircular clip 242 is opposite to the opening of the first semicircular clip 241. One end of each of the first semicircular hoop 241 and the second semicircular hoop 242 is provided with a dovetail 244, the other end of each of the first semicircular hoop 241 and the second semicircular hoop 242 is provided with a dovetail groove 243, the dovetail 244 is matched with the dovetail groove 243, the dovetail grooves 243 and the dovetail grooves 243 are provided with locking holes 245, and the central points of the locking holes 245 on the dovetail grooves 243 and the dovetail 244 are located on the same axis.
The inner wall of the locking hoop 24 is attached to the outer surface of the support rod 1, a locking bolt 25 penetrates through the locking hole 245, the same locking bolt 25 sequentially penetrates through the locking hole 245 on one side of the locking hoop 24, the positioning hole 12 on the support rod 1 and the locking hole 245 on the other side of the locking hoop 24, and finally a locking nut 26 is screwed on the exposed end of the locking bolt 25, so that the fixed installation between the attachment plate 2 and the support rod 1 is realized.
As shown in fig. 3, the bottom surface of the mounting plate 2 is provided with an auxiliary seat 4, and the auxiliary seat 4 is magnetically connected with the magnetic splicing block 22. Be provided with the accommodation hole 45 on the supplementary seat 4, the below of supplementary seat 4 is provided with auxiliary rod 41, auxiliary rod 41 inclines to set up, the accommodation hole 45 is inserted to the one end of auxiliary rod 41, the other end fixed connection of auxiliary rod 41 has the solid fixed ring 42 of level setting, gu fixed ring 42 overlaps and locates on the bracing piece 1, gu fixed ring 42 still is equipped with fixing bolt 43, fixing bolt 43 runs through the through-hole (not marked in the figure) on the solid fixed ring 42 and the locating hole 12 on the bracing piece 1 simultaneously, and fixing bolt 43's the end that exposes is screwed there is fixation nut 44. The auxiliary rod 41, the carrying plate 2 and the support rod 1 form a triangular support structure, so that the stability of the building carrying frame is improved.
When the carrier frame is built in the installation room, earlier the vertical setting of bracing piece 1, the amalgamation again takes first semicircle hoop 241 and the second semicircle hoop 242 of four edges and corners department of support plate 2, forms locking clamp 24 after, inserts locking bolt 25 simultaneously in order to run through locking clamp 24 and bracing piece 1, again with supplementary seat 4 through with magnetism the concatenation piece 22 inhale to be connected, adsorb in the base of taking support plate 2. The fixing ring 42 is sleeved on the support rod 1 and then moved until the upper end of the auxiliary rod 41 is inserted into the accommodating hole 45, and finally the fixing bolt 43 is penetrated and the fixing nut 44 is locked to complete the installation.
The implementation principle of the building and carrying frame in the embodiment of the application is as follows: utilize the carrier can be disassembled and for parts such as bracing piece 1, carrying block and locking clamp 24, improved the mobility of carrier.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a carrier is built in room, includes carrier board (2), its characterized in that: the support rod (1) is further included, and a positioning hole (12) is formed in the support rod (1); be provided with locking clamp (24) on the board of taking (2), locking clamp (24) hoop in the outer wall of bracing piece (1), locking clamp (24) run through and are provided with locking hole (245), locking hole (245) with locating hole (12) wear to be equipped with locking bolt (25) jointly, locking bolt (25) with locking clamp (24) can dismantle the connection.
2. The building construction carriage according to claim 1, wherein: locking clamp (24) include first semicircle hoop (241) and second semicircle hoop (242), first semicircle hoop (241) with take up board (2) fixed connection, first semicircle hoop (241) with the one end of second semicircle hoop (242) all is provided with the dop, and the other end sets up and all has the draw-in groove, the dop with the draw-in groove is mutually supported, is located respectively the dop with on the draw-in groove the central point of locking hole (245) all is located same axis.
3. The building construction carriage according to claim 2, wherein: the clamping head is a dovetail joint (244), the clamping groove is a dovetail groove (243), and the dovetail joint (244) is matched with the dovetail groove (243).
4. The building construction carriage according to claim 1, wherein: the number of the positioning holes (12) is multiple, and the positioning holes (12) are uniformly arranged along the length direction of the support rod (1) at intervals.
5. The building construction carriage according to claim 1, wherein: and a rubber sleeve (13) is arranged on the inner wall of the positioning hole (12).
6. The building construction carriage according to claim 1, wherein: the carrying plate (2) comprises a first carrying block (21), a second carrying block (23) and a magnetic splicing block (22), a plurality of splicing heads (221) are arranged on the magnetic splicing block (22), a plurality of splicing grooves (222) are arranged on the first carrying block (21) and the second carrying block (23), and the splicing grooves (222) and the splicing heads (221) are matched with each other and connected in a magnetic attraction manner; the first carrying block (21), the second carrying block (23) and the magnetic splicing block (22) jointly horizontally penetrate through a connecting rod (27).
7. The building construction carriage according to claim 6, wherein: an auxiliary seat (4) is arranged on the bottom surface of the carrying plate (2), and the auxiliary seat (4) is magnetically connected with the magnetic splicing block (22); the utility model discloses a fixing device for fixing a car seat, including supplementary seat (4), the below of supplementary seat (4) is provided with auxiliary rod (41), and auxiliary rod (41) slope sets up, the other end of auxiliary rod (41) with supplementary seat (4) can be dismantled and be connected, the solid fixed ring of other end fixedly connected with (42) of auxiliary rod (41), gu fixed ring (42) wear to be equipped with fixing bolt (43), fixing bolt (43) run through simultaneously locating hole (12).
8. The building construction carriage according to claim 7, wherein: the auxiliary seat (4) is provided with an accommodating hole (45), and one end of the auxiliary rod (41) is inserted into the accommodating hole (45).
CN202121824466.5U 2021-08-05 2021-08-05 Carrying frame is built in room Active CN215368593U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121824466.5U CN215368593U (en) 2021-08-05 2021-08-05 Carrying frame is built in room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121824466.5U CN215368593U (en) 2021-08-05 2021-08-05 Carrying frame is built in room

Publications (1)

Publication Number Publication Date
CN215368593U true CN215368593U (en) 2021-12-31

Family

ID=79615771

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121824466.5U Active CN215368593U (en) 2021-08-05 2021-08-05 Carrying frame is built in room

Country Status (1)

Country Link
CN (1) CN215368593U (en)

Similar Documents

Publication Publication Date Title
CN215368593U (en) Carrying frame is built in room
CN217299743U (en) Adjustable positioning buckle for upright rod base of overhanging scaffold
CN112726832B (en) Steel structure integrated house building system capable of being repeatedly disassembled and assembled and assembling method
CN111576925B (en) Quick building steel support frame and implementation method thereof
CN211065913U (en) Cross column stand bearing device for exhibition
CN211597685U (en) Scaffold convenient to assemble and disassemble for green building
CN213143078U (en) Support system of deep foundation pit
CN111980052A (en) Electric power construction pile foundation structure
CN209947106U (en) Auxiliary device for economic management
CN219794587U (en) Construction frame convenient to detach for constructional engineering
CN219864173U (en) Stereoscopic warehouse building steel structure positioning device for nylon fiber cake finished products
CN219863915U (en) Building construction frame
CN214793160U (en) Distance measuring device for civil engineering
CN214272000U (en) Pile foundation construction platform of green engineering
CN219451411U (en) Frame device is chosen in construction
CN215254790U (en) Building engineering safety protection net
CN114150879A (en) Adjustable supporting device for splicing large-scale complex steel structure nodes
CN218205600U (en) Scaffold frame for building site convenient to installation
CN216616988U (en) Strutting arrangement for civil construction convenient to equipment and dismantlement
CN217652504U (en) Enclose fender convenient to equipment usefulness is dismantled in municipal garden construction
CN220353068U (en) Steel structure unit of integrated house
CN215407588U (en) Civil engineering uses supplementary strutting arrangement
CN218375734U (en) Fender is enclosed in assembly type construction
CN210947652U (en) Civil engineering construction support
CN218758979U (en) Lattice type cross supporting device

Legal Events

Date Code Title Description
GR01 Patent grant