CN214327165U - Concrete sewage treatment plant with clearance function - Google Patents

Concrete sewage treatment plant with clearance function Download PDF

Info

Publication number
CN214327165U
CN214327165U CN202120192094.2U CN202120192094U CN214327165U CN 214327165 U CN214327165 U CN 214327165U CN 202120192094 U CN202120192094 U CN 202120192094U CN 214327165 U CN214327165 U CN 214327165U
Authority
CN
China
Prior art keywords
mud
cell body
sewage treatment
sleeve
concrete sewage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120192094.2U
Other languages
Chinese (zh)
Inventor
江光林
佘红斌
尹赞阳
胡新龙
程敬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Chicheng Building Materials Co ltd
Original Assignee
Hubei Chicheng Building Materials Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Chicheng Building Materials Co ltd filed Critical Hubei Chicheng Building Materials Co ltd
Priority to CN202120192094.2U priority Critical patent/CN214327165U/en
Application granted granted Critical
Publication of CN214327165U publication Critical patent/CN214327165U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model relates to a field of concrete manufacturing and processing especially relates to a concrete sewage treatment plant with clearance function, it includes upper end open-ended cell body, the diapire intercommunication of cell body has the mud discharging pool, the delivery port has been seted up to one side that the mud discharging pool was kept away from to the cell body, the delivery port is located the top of cell body diapire, the bottom in mud discharging pool is provided with row mud mouth, the vertical mud scraping plate that is provided with in the cell body, be provided with the driving piece that the mud scraping plate scraped cell body bottom silt got into in the mud discharging pool in the cell body top. This application has the effect of the inside silt of high-efficient clearance cell body.

Description

Concrete sewage treatment plant with clearance function
Technical Field
The application relates to the field of concrete manufacturing and processing, in particular to a concrete sewage treatment device with a cleaning function.
Background
Along with the development and scale expansion of the building industry, the demand of the market on concrete is increased, the concrete can generate a large amount of sewage in the production process, the sewage contains silt, aggregate, additives and other components, the sewage needs to be recycled and then discharged, and if the sewage is directly discharged, the pollution is caused, so that the environment protection and the water resource saving are not facilitated.
At present, concrete sewage generated in processing production is discharged into the concrete sewage to enter a sedimentation tank for sedimentation, and then a water source after sedimentation can be recycled, for example, the concrete sewage is used for flushing a concrete tank truck so as to save water resources.
Chinese patent with patent publication No. CN211536655U discloses a concrete sewage sedimentation tank, which comprises a tank body, wherein one end of the tank body is provided with a water outlet pipe which is vertically arranged and communicated with the tank body, the inner wall of the tank body is respectively provided with a horizontal positioning step, and a salvaging floating sieve is placed on the positioning step; the edges of the two ends of the salvaging floating sieve are provided with avoiding notches for accommodating the water outlet pipe to pass through.
In view of the above-mentioned related technologies, the inventor believes that after the precipitation treatment is completed, an operator is usually required to enter the precipitation tank to clean the impurities at the bottom of the tank, and the cleaning efficiency is low, so that improvement is needed.
SUMMERY OF THE UTILITY MODEL
In order to improve the cleaning efficiency of mud, this application provides a concrete sewage treatment plant with clearance function.
The application provides a concrete sewage treatment plant with clearance function adopts following technical scheme:
the utility model provides a concrete sewage treatment plant with clearance function, includes upper end open-ended cell body, the diapire intercommunication of cell body has row mud pond, the cell body is kept away from the delivery port has been seted up to one side in row mud pond, the delivery port is located the top of cell body diapire, the bottom in row mud pond is provided with row mud mouth, the vertical mud scraping plate that is provided with in the cell body, in the cell body top is provided with the drive the mud scraping plate is scraped the mud of cell body bottom gets into driving piece in the row mud pond.
Through adopting above-mentioned technical scheme, at first adjust the mud scraping plate to keep away from the inside wall butt in mud discharging pool with the cell body, discharge sewage into the cell body after from the upper end opening of cell body again, through a period of stewing, the impurity that contains the area in the sewage deposits at the cell body diapire and forms one deck silt, the valve through opening and close the delivery port will be located the sediment water discharge cell body more than the silt layer, then start driving piece drive mud scraping plate and remove towards mud discharging pool, in order to scrape silt to mud discharging pool in, and discharge by the mud discharging port, intersect and utilize the shovel to shovel out the operation to silt in artifical entering cell body, great improvement the efficiency of clearance silt.
Preferably, the top of mud scraping plate be provided with the driving piece links to each other drag for the kickboard, drag for the bottom of kickboard and flush with the surface of water of sewage, be provided with on the opening outer edge of cell body with arrange the dross of mud pond intercommunication and get rid of the groove.
Through adopting above-mentioned technical scheme, drag for kickboard and mud scraper synchronous motion through the driving piece drive, can accompany the reciprocating motion of driving piece, synchronous will float pushing the dross that the dross on top layer corresponds and get rid of the inslot and collect.
Preferably, a connecting rod is connected between the mud scraping plate and the floating salvaging plate, the bottom wall of the scum removing groove is lower than the top end of the mud discharging pool, and an outflow port is formed in one side of the scum removing groove.
Through adopting above-mentioned technical scheme, will drag for the kickboard and link to each other as an organic whole with the mud scraping board through the connecting rod, the wholeness is higher.
Preferably, the driving part comprises a screw rod and a driving motor, two ends of the screw rod are horizontally and rotatably connected to the top end of the pool body through a support, the driving motor is connected with the screw rod and drives the screw rod to rotate, and screw holes matched with the screw rods in circumferential side threads are formed in the side wall of the floating plate.
Through adopting above-mentioned technical scheme, drive the lead screw through starting driving motor and rotate, the screw thread is worn to establish on the inner wall of cell body is dragged for kickboard both sides butt in lead screw week side to the axial displacement of floatboard along the lead screw is dragged for in the injeciton.
Preferably, the connecting rod includes slide bar and sleeve pipe, sheathed tube one end is uncovered setting, the one end of slide bar slide peg graft extremely in the sleeve pipe, the slide bar is kept away from sheathed tube one end is provided with movable inlay card in the connecting piece in the mud scraping plate.
Through adopting above-mentioned technical scheme, the mutual cooperation of slide bar and sheathed tube makes the mud scraping plate and drag for the clearance between the kickboard adjustable to can take off the mud scraping plate from the slide bar under the cooperation of connecting piece and change or wash, the practicality is high.
Preferably, the connecting piece includes slider and spring, set up the confession on the lateral wall of connecting rod the spout that the slider slided in, the spring is located in the spout and one end with the spout tank bottom is fixed, and the other end butt is in on the lateral wall of slider, the mud scraper tip corresponds sets up the confession the caulking groove of slide bar tip embedding, and set up on the lateral wall with the caulking groove intercommunication is in order to supply slider male jack.
Through adopting above-mentioned technical scheme, operating personnel pushes the slider and goes deep into the jack, and the spring contracts to the spout in, then with the grafting to the sleeve pipe that the slide bar corresponds, the slide bar breaks away from the caulking groove gradually and separates with the mud scraper to realize dismantling of mud scraper.
Preferably, the side of the sliding rod is provided with a limiting sleeve in a threaded sleeve manner, and one end of the limiting sleeve is rotatably embedded in the sleeve.
By adopting the technical scheme, the inserting depth of the sliding rod and the sleeve can be adjusted by screwing the limiting sleeve, and the relative positions of the sliding rod and the sleeve are limited, so that the bottom sludge can be hung by the mud scraper.
Preferably, the port of the sludge discharge port is connected with a sludge discharge pipe, and a sludge outlet end of the sludge discharge pipe is movably provided with a flow stopping valve.
By adopting the technical scheme, whether sludge in the sludge discharge tank is discharged or not can be limited by screwing the stop valve, and the controllability is stronger.
Preferably, the periphery of the sludge discharge pipe is provided with a pipe body communicated with the inside of the sludge discharge pipe, the periphery of the pipe body is provided with a water suction pump, and one end of the water suction pump, which is far away from the sludge discharge pipe, is connected with a water tank.
Through adopting above-mentioned technical scheme, when silt concreties and blocks up the mud pipe, close the flow stopping valve, start the suction pump and take out the water in the water tank from the mud pipe back and go into the mud pond, will block up the department and utilize rivers impact force to wash away to ensure that follow-up silt is discharged smoothly.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the sludge scraping plate is additionally arranged in the pool body, along with the rotation of the screw rod, the sludge at the bottom of the pool body is smoothly scraped into the sludge discharging pool by the sludge scraping plate connected with the floating plate through the connecting rod, the stop valve is opened, the sludge is smoothly discharged from the sludge discharging pipe, manual sludge removal is not needed, and the efficiency is higher;
2. the connecting rod is divided into a sliding rod and a sleeve which are mutually inserted, when the mud scraper needs to be replaced, the sliding block is pressed to compress the spring, so that the sliding block is deeply inserted into the sliding groove, the limiting sleeve is rotated to gradually insert the sliding rod into the sleeve, and meanwhile, the end part of the sliding rod is separated from the caulking groove, so that the disassembly is realized;
3. when the sludge is solidified and blocks the sludge discharge pipe, the stop valve is closed, the water pump is started to reversely pump the water in the water tank into the sludge discharge tank from the sludge discharge pipe, and the blocked part is flushed away by utilizing the impact force of water flow so as to ensure that the subsequent sludge is smoothly discharged.
Drawings
Fig. 1 is a schematic structural diagram of the present invention;
fig. 2 mainly shows an exploded structural view of the connecting rod;
fig. 3 is an enlarged view at a in fig. 2.
Reference numerals: 1. a tank body; 2. a sludge discharge pool; 3. a water outlet; 4. a sludge discharge port; 5. a mud scraper; 6. a drive member; 61. a screw rod; 62. a drive motor; 63. a screw hole; 7. fishing out the floating plate; 8. a scum removing tank; 9. a connecting rod; 91. a slide bar; 92. a sleeve; 93. a connecting member; 901. a slider; 902. a spring; 903. a chute; 904. caulking grooves; 905. a jack; 906. a limiting sleeve; 10. an outflow port; 11. a sludge discharge pipe; 12. a flow stop valve; 13. a pipe body; 14. a water pump; 15. a water tank.
Detailed Description
The present application is described in further detail below with reference to the accompanying drawings.
Referring to fig. 1, this application embodiment discloses a concrete sewage treatment plant with clearance function, including upper end open-ended cell body 1, cell body 1 is the rectangle, the integrative intercommunication of diapire of cell body 1 has row mud pond 2, the both sides of row mud pond 2 all are the inclined plane setting, and transversal personally submit down trapezoidally, in order to ensure that silt can progressively slide into the bottom of the pool of row mud pond 2, row mud mouth 4 has been seted up to the bottom of row mud pond 2, the port department fixedly connected with mud pipe 11 of mud mouth 4, mud pipe 11 keeps away from the play mud end of row mud pond 2 and installs stop valve 12.
Referring to fig. 1, a pipe body 13 communicated with the inside of the sludge discharge pipe 11 is arranged on the periphery of the sludge discharge pipe 11, a water suction pump 14 is arranged on the periphery of the pipe body 13, one end, far away from the sludge discharge pipe 11, of the water suction pump 14 is connected with a water tank 15, when sludge is solidified and blocks the sludge discharge pipe 11, the flow stop valve 12 is closed, the water suction pump 14 is started to suck water in the water tank 15 back into the sludge discharge pool 2 from the sludge discharge pipe 11, and the blocked part is flushed away by water flow impact force to ensure that subsequent sludge is smoothly discharged.
Referring to fig. 1, delivery port 3 has been seted up to one side that mud discharging pool 2 was kept away from to cell body 1, and delivery port 3 is located the top of 1 diapire of cell body, and driving piece 6 has erect along its length direction level in the opening top of cell body 1, and driving piece 6 includes lead screw 61, and the both ends of lead screw 61 are connected at 1 top of cell body through the rotation of the support of fixing at 1 lateral wall of cell body, and the support outer wall has set firmly driving motor 62, and driving motor 62's output shaft and the one end coaxial fixation of lead screw 61.
Referring to fig. 1, a mud scraping plate 5 is slidably abutted to the bottom wall of a tank body 1, the mud scraping plate 5 is rectangular, the mud scraping plate 5 is vertically arranged, two sides of the mud scraping plate 5 are abutted to the inner wall of the tank body 1, a floating fishing plate 7 which is arranged on the periphery of a screw rod 61 in a penetrating manner through threads is arranged right above the mud scraping plate 5, the bottom end of the floating fishing plate 7 is flush with the water surface of sewage, a scum removing groove 8 which is communicated with a mud discharging tank 2 is arranged on the outer edge of an opening of the tank body 1, the bottom wall of the scum removing groove 8 is lower than the top end of the mud discharging tank 2, an outflow port 10 is arranged on one side of the scum removing groove 8, a screw hole 63 which is matched with the screw rod 61 is arranged on the surface of the floating fishing plate 7, the mud scraping plate 5 and the floating fishing plate 7 are parallel to each other, and a connecting rod 9 is connected between the mud scraping plate 5 and the floating fishing plate 7; the screw rod 61 is driven to rotate by starting the driving motor 62, and the two sides of the floating fishing plate 7 which is arranged on the peripheral side of the screw rod 61 in a penetrating way are abutted against the inner wall of the tank body 1 so as to limit the axial movement of the floating fishing plate 7 along the screw rod 61.
Referring to fig. 2 and 3, the connecting rod 9 includes a sliding rod 91 and a sleeve 92, the sliding rod 91 is a stepped rod, and further, one end of the sliding rod 91 with a smaller diameter is a small end, and the other end is a large end, one end of the sleeve 92 is fixedly connected to the side wall of the mud scraper 5, the other end of the sleeve 92 is arranged in an opening, the small end of the sliding rod 91 is correspondingly inserted into the opening of the sleeve 92, the end of the opening end of the sleeve 92 is further rotatably embedded with a limiting sleeve 906, threads are arranged on the periphery of the small end of the sliding rod 91, the small end of the sliding rod 91 penetrates through the inner wall of the limiting sleeve 906, and threads are also arranged on the inner wall of the limiting sleeve 906, so as to realize the threaded fit of the limiting sleeve 906 and the sliding rod 91; the one end that the sleeve 92 is kept away from to slide bar 91 is provided with the connecting piece 93 that the activity card inlayed in mud scraper 5, through screwing up stop collar 906 alright adjust the whole length of nepheline connecting rod 9, can cooperate connecting piece 93 smoothly to take off mud scraper 5 from slide bar 91 and change or wash.
Referring to fig. 2 and 3, the top end of the mud scraper 5 is correspondingly provided with an embedded groove 904 for the end of the sliding rod 91 to be embedded, the connecting member 93 comprises a sliding block 901 and a spring 902, the side wall of the sliding rod 91 is provided with a sliding groove 903 for the sliding block 901 to slide into, one end of the sliding block 901, which is far away from the sliding groove 903, is arranged in the sliding groove 903 and is fixed with the bottom of the sliding groove 903, the other end of the spring 902 abuts against the side wall of the sliding block 901, the end of the mud scraper 5 is correspondingly provided with the embedded groove 904 for the end of the sliding rod 91 to be embedded, when the mud scraper 5 needs to be disassembled, the sliding block 901 is pressed to go deep into the insertion hole 905, the spring 902 contracts into the sliding groove 903, then the limiting sleeve 906 is screwed, the sliding rod 91 is correspondingly inserted into the sleeve 92, and the sliding rod 91 gradually disengages from the embedded groove 904 from the mud scraper 5.
The implementation principle of the embodiment is as follows:
drive lead screw 61 through start-up driving motor 62 and rotate, drag for 7 butt of kickboard with lead screw 61 screw-thread fit and slide on the inner wall of cell body 1, get rid of the leading-in dross of floated impurity on the sewage surface of water and discharge from flow outlet 10 in 8, through connecting rod 9 with drag for the mud scraper 5 that kickboard 7 links to each other and accompany and drag for 7 synchronous motion of kickboard, the bottom butt of mud scraper 5 is on the diapire of cell body 1, scrape into the mud of cell body 1 in the mud pond 2 from mud pipe 11 discharges, it shovels out the operation to utilize the shovel in artifical entering cell body 1, great improvement the efficiency of clearance silt.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (9)

1. The utility model provides a concrete sewage treatment plant with clearance function which characterized in that: including upper end open-ended cell body (1), the diapire intercommunication of cell body (1) has row mud pit (2), cell body (1) is kept away from delivery port (3) have been seted up to one side of row mud pit (2), delivery port (3) are located the top of cell body (1) diapire, the bottom of row mud pit (2) is provided with row mud mouth (4), vertically in cell body (1) is provided with mud scraper (5), in cell body (1) top is provided with the drive mud scraper (5) are scraped the cell body (1) bottom silt gets into driving piece (6) in row mud pit (2).
2. The concrete sewage treatment device with the cleaning function according to claim 1, wherein: the top of mud scraping plate (5) be provided with driving piece (6) link to each other drag for kickboard (7), drag for the bottom of kickboard (7) and flush with the surface of water of sewage, the opening of cell body (1) is provided with on the outer edge with scum removal groove (8) of row mud pit (2) intercommunication.
3. The concrete sewage treatment device with the cleaning function according to claim 2, wherein: the mud scraping plate (5) and the floating plate (7) are connected with a connecting rod (9) therebetween, the bottom wall of the scum removing groove (8) is lower than the top end of the mud discharging pool (2), and one side of the scum removing groove (8) is provided with an outflow opening (10).
4. The concrete sewage treatment device with the cleaning function according to claim 3, wherein: the driving piece (6) comprises a screw rod (61) and a driving motor (62), the two ends of the screw rod (61) are connected to the top end of the pool body (1) through horizontal rotation of a support, the driving motor (62) is connected with and drives the screw rod (61) to rotate, and screw holes (63) which are matched with the screw rods (61) in circumferential side threads are formed in the side wall of the fishing floating plate (7).
5. The concrete sewage treatment device with the cleaning function according to claim 4, wherein: the connecting rod (9) comprises a sliding rod (91) and a sleeve (92), one end of the sleeve (92) is arranged in an open mode, one end of the sliding rod (91) is inserted into the sleeve (92) in a sliding mode, and one end, far away from the sleeve (92), of the sliding rod (91) is provided with a connecting piece (93) which is movably clamped and embedded into the mud scraper (5).
6. The concrete sewage treatment device with the cleaning function according to claim 5, wherein: the connecting piece (93) comprises a sliding block (901) and a spring (902), a sliding groove (903) for the sliding block (901) to slide into is formed in the side wall of the connecting rod (9), the spring (902) is located in the sliding groove (903), one end of the spring is fixed with the bottom of the sliding groove (903), the other end of the spring abuts against the side wall of the sliding block (901), an embedded groove (904) for the end portion of the sliding rod (91) to be embedded is correspondingly formed in the end portion of the mud scraping plate (5), and a jack (905) communicated with the embedded groove (904) for the sliding block (901) to be inserted is formed in the side wall of the mud scraping plate.
7. The concrete sewage treatment device with the cleaning function according to claim 6, wherein: the side of the sliding rod (91) is provided with a limiting sleeve (906) in a threaded sleeve mode, and one end of the limiting sleeve (906) is rotatably embedded in the sleeve (92).
8. The concrete sewage treatment device with the cleaning function according to claim 1, wherein: the port department of mud discharging port (4) is connected with mud discharging pipe (11), the play mud end activity of mud discharging pipe (11) is provided with flow stopping valve (12).
9. The concrete sewage treatment device with the cleaning function according to claim 8, wherein: the utility model discloses a mud pipe, including mud pipe (11), body (13) of all sides setting rather than inside intercommunication of mud pipe (11), the all sides of body (13) are provided with suction pump (14), suction pump (14) are kept away from the one end of mud pipe (11) is connected with water tank (15).
CN202120192094.2U 2021-01-23 2021-01-23 Concrete sewage treatment plant with clearance function Expired - Fee Related CN214327165U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120192094.2U CN214327165U (en) 2021-01-23 2021-01-23 Concrete sewage treatment plant with clearance function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120192094.2U CN214327165U (en) 2021-01-23 2021-01-23 Concrete sewage treatment plant with clearance function

Publications (1)

Publication Number Publication Date
CN214327165U true CN214327165U (en) 2021-10-01

Family

ID=77906286

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120192094.2U Expired - Fee Related CN214327165U (en) 2021-01-23 2021-01-23 Concrete sewage treatment plant with clearance function

Country Status (1)

Country Link
CN (1) CN214327165U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115748932A (en) * 2022-12-15 2023-03-07 宏昌建筑集团有限公司 Drainage ditch structure of campus playground

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115748932A (en) * 2022-12-15 2023-03-07 宏昌建筑集团有限公司 Drainage ditch structure of campus playground
CN115748932B (en) * 2022-12-15 2023-09-05 宏昌建筑集团有限公司 Drainage ditch structure of campus playground

Similar Documents

Publication Publication Date Title
CN214327165U (en) Concrete sewage treatment plant with clearance function
CN217398621U (en) Integrated sewage treatment device for livestock and poultry manure
CN115925077A (en) Slaughter, cooked food processing wastewater treatment and grease recovery system
CN213407825U (en) Secondary sedimentation tank
CN114105369A (en) Novel oil-water separation tank with slag scraping and oil-water separation functions
CN219690615U (en) Continuous high-efficient anti-blocking separation dredging device for underwater mud taking in river channel
CN209500910U (en) A kind of sewage-treatment plant being convenient to clean
CN216972155U (en) Floating disc type oil removing device based on self-rotating magnetic water
CN214758674U (en) Aquaculture bottom cleaning and decontamination device
CN215137184U (en) Printing and dyeing wastewater advanced treatment's light fenton device
CN213680132U (en) Waste water treatment device after metal waste residue is recycled
CN204723852U (en) A kind of factory waste water purification device
CN211035315U (en) Integrated air floatation machine
CN220834279U (en) Sewage treatment sedimentation tank sludge residue cleaning device
CN110593230A (en) Floater pushing and gathering mechanism for filter tank
CN220202819U (en) Automatic dredging mechanism
CN219355530U (en) Adjusting tank for treating waste liquid in circuit board production
CN220777080U (en) Fish culture pond bottom waste fitting discharging
CN215977165U (en) Water conservancy and hydropower engineering construction hole inner water conservancy diversion drainage structures
CN215161807U (en) Aeration grit chamber and sewage treatment system
CN218900939U (en) Wastewater air floatation precipitation integrated sedimentation tank
CN218740383U (en) Impurity removing device for silicon oil hydrolysate
CN219423798U (en) Efficient thickener
CN214936194U (en) High-efficient superficial layer dross collection device for air supporting machine
CN214570887U (en) Air-float sewage treatment device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211001