CN213359378U - Aluminum mould board "two U hold in palm" connection support frock - Google Patents

Aluminum mould board "two U hold in palm" connection support frock Download PDF

Info

Publication number
CN213359378U
CN213359378U CN202022093951.1U CN202022093951U CN213359378U CN 213359378 U CN213359378 U CN 213359378U CN 202022093951 U CN202022093951 U CN 202022093951U CN 213359378 U CN213359378 U CN 213359378U
Authority
CN
China
Prior art keywords
column
shaped support
base
threaded shaft
double
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022093951.1U
Other languages
Chinese (zh)
Inventor
余德
王建林
杨雯静
张航瑜
严洪飞
段鹤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ycih No10 Construction Co ltd
Original Assignee
Ycih No10 Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ycih No10 Construction Co ltd filed Critical Ycih No10 Construction Co ltd
Priority to CN202022093951.1U priority Critical patent/CN213359378U/en
Application granted granted Critical
Publication of CN213359378U publication Critical patent/CN213359378U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses an aluminum template 'double U-shaped support' connecting and supporting tool, which comprises an early dismantling head, a base, a bottom column, a middle column, an upper column, a threaded shaft, a U-shaped support and a top column; the base is a wide square plate, and threaded through holes are formed in the periphery of the base; the bottom column is a cylinder and is fixedly arranged in the base; the middle column is arranged to be a cylinder and can be detachably connected and arranged on the bottom column in a switching mode, the upper column is arranged to be a cylinder and can be detachably connected and arranged on the middle column in a switching mode, the threaded shaft is connected to the center of the upper column in a threaded mode, the U-shaped supports are arranged to be two mutually matched and buckled in a matching mode, one of the U-shaped supports is fixedly arranged at the top of the threaded shaft, the other U-shaped support is arranged on the top column, and the other end of the top column is connected to the early-dismantling head; the problem of non-standard aluminium template dismouting support be difficult for the adjustment is solved.

Description

Aluminum mould board "two U hold in palm" connection support frock
Technical Field
The utility model relates to a construction technical field, concretely an aluminium template "two U hold in the palm" connection support frock.
Background
With the promotion of modern development strategy planning of energy conservation and emission reduction in China and the improvement of engineering quality standards, new materials in the market of buildings are continuously emerging, and in the construction of high-rise and super high-rise buildings, the aluminum template can be recycled and remolded into an excellent green building material, but the aluminum template is high in primary cost and only suitable for standard production and standard use. For projects with more changes in layer height and structure, the layer height of a non-standard layer is different from that of a standard layer, an original aluminum mould early-dismantling system (comprising an early-dismantling head and a vertical rod) is specially designed for a manufacturer, the requirement on the standardization degree is high, the original early-dismantling system cannot be used, and the application range of a support rod piece of the layer height use standard of the non-standard layer is limited after the support rod piece exceeds the maximum shoring range. The key need be solved its size and the atress of traditional fastener formula scaffold frame support connection and the installation firm scheduling problem.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an aluminium template "two U hold in the palm" connection support frock solves the problem that non-standard aluminium template dismouting supports the difficult adjustment.
In order to solve the technical problem, the utility model adopts the following technical scheme:
a double-U-support connecting and supporting tool for an aluminum template comprises an early dismantling head, a base, a bottom column, a middle column, an upper column, a threaded shaft, a U-shaped support and a top column; the base is a wide square plate, and threaded through holes are formed in the periphery of the base; the bottom column is a cylinder and is fixedly arranged in the base; the utility model discloses a quick-witted support, including the center post, the center post sets up to a cylinder and detachable joint and switching setting on the foundation pillar, go up the post and set up to root cylinder and detachable joint and switching setting on the center post, threaded shaft threaded connection is at last post center, the U type holds in the palm two that set up to mutual adaptation lock joint, and one of them is fixed to be set up at the top of threaded shaft, and the other one sets up on the fore-set, and the other end connection setting of fore-set is on early tearing open.
Furthermore, four reinforcing plates are arranged between the bottom column and the base.
Furthermore, positioning grooves are formed in the tops of the bottom column and the middle column, a rotating shaft groove is formed in the center of the bottom column and the middle column, and a bearing is embedded in the rotating shaft groove.
Furthermore, the bottoms of the middle column and the upper column are provided with step shafts, one step is fixedly arranged in the bearing, and the other step is connected in the positioning groove in a switching mode.
Furthermore, a roller is arranged between the step and the positioning groove.
Further, the threaded shaft is set as a bearing screw rod.
Furthermore, a fastening screw is rotatably arranged on the threaded shaft at the top of the upper column, and handles are arranged on two sides of the fastening screw.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the aluminum template 'double-U-shaped support' connecting and supporting tool of the utility model is convenient for workers to install and operate, can use local materials on the construction site, saves the cost and shortens the construction period;
2. the utility model relates to an aluminum template 'double U holds in the palm' connection support frock can realize that nonstandard layer template tears open early, reduces the number of die sets of joining in marriage, increases the template cycle number;
3. the utility model relates to an aluminum template 'double U holds in the palm' connection support frock simple structure, design benefit has solved all sorts of drawbacks of traditional concrete placement field interim wooden vaulting pole well, has greatly improved work efficiency, has reduced the potential safety hazard in building site, has higher economic value and social value;
4. the utility model relates to an aluminum mould board "two U hold in the palm" connection support frock has solved the problem that non-standard aluminum mould board dismouting supported the difficult adjustment.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
In the figure, 1-base, 2-thread through hole, 3-reinforcing plate, 4-bottom column, 5-middle column, 6-arc reinforcing part, 7-positioning groove, 8-bearing, 9-roller, 10-fastening screw, 11-handle, 12-thread shaft, 13-U-shaped support, 14-top column, 15-early dismantling head, 16-thread countersunk hole, 17-rotating shaft, 18-step shaft and 19-upper column.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Example 1:
the aluminum template 'double U-shaped support' connecting and supporting tool comprises an early dismantling head 15, a base 1, a bottom column 4, a middle column 5, an upper column 19, a threaded shaft 12, a U-shaped support 13 and a top column 14; specifically, in order to be convenient for firm standing, the base 1 is arranged to be a wide square plate, the periphery of the wide square plate is provided with the thread through holes 2, and the wide square plate is fastened and connected with the ground through expansion screws or other screws during use. The foundation column 4 sets up to a cylinder and fixed the setting in base 1, supports to set up the center pillar 5 into a cylinder and detachable and switching setting on foundation column 4 for the adaptation different floor heights, go up the post 19 and set up to root cylinder and detachable and switching setting on center pillar 5, so, center pillar 5 just can have more specific floor height to increase or reduce, can fasten in order to carry out small adjustment, with threaded shaft 12 threaded connection at center pillar 19. For the purpose of stable connection, the two U-shaped brackets 13 are arranged in a mutually matched and buckled mode, one of the two U-shaped brackets is fixedly arranged at the top of the threaded shaft 12, the other U-shaped bracket is arranged on the top column 14, the two U-shaped brackets 13 are in crossed connection, and the other end of the top column 14 is connected and arranged on the early-dismantling head 15.
In this device, increase or reduce through the center pillar 5 and adapt to different floor height, and the specific length of center pillar 5 can be according to specific needs and set up when processing, and in this device, center pillar 5 uses the grafting when using, easy to assemble like this, adjusts the use, simultaneously, supports can be stable after the fastening and supports.
Example 2:
on the basis of the above embodiment, in the present embodiment, four reinforcing plates 3 are provided between the bottom pillar 4 and the base 1 to enhance the stability of the support.
Example 3:
on the basis of the above embodiments, in this embodiment, in order to facilitate the rotation adjustment of the insertion, positioning grooves 7 are provided at the tops of the bottom pillar 4 and the middle pillar 5, a rotating shaft groove is provided at the center, and a bearing 8 is embedded in the rotating shaft groove.
Example 4:
on the basis of the above embodiments, in this embodiment, in order to facilitate the rotation adjustment of the insertion, the bottom portions of the middle column 5 and the upper column 19 are provided as the step shafts 18, one step is fixedly arranged in the bearing 8, and the other step is rotatably connected in the positioning groove 7.
Example 5:
on the basis of the above embodiment, in this embodiment, in order to fasten and prevent the bearing 8 from being crushed, and also to facilitate the rotation adjustment, the bearing is selected as a pressure bearing, and a roller 9 is provided between the step and the positioning groove 7 to assist the rotation while supporting the pressure.
Example 6:
on the basis of the above embodiment, in this embodiment, in order to ensure that the threaded shaft can bear pressure during the adjustment process, the threaded shaft 12 is provided as a bearing screw rod.
Example 7:
on the basis of the above embodiment, in the present embodiment, in order to assist the load bearing of the threaded shaft 12 and prevent the loosening, a fastening screw 10 is rotatably provided on the threaded shaft 12 at the top of the upper column 19, and handles 11 are provided on both sides of the fastening screw 10 for adjustment.
Reference throughout this specification to "one embodiment," "another embodiment," "an embodiment," "a preferred embodiment," or the like, means that a particular feature, structure, or characteristic described in connection with the embodiment is included in at least one embodiment described generally in this application. The appearances of the same phrase in various places in the specification are not necessarily all referring to the same embodiment. Further, when a particular feature, structure, or characteristic is described in connection with any embodiment, it is submitted that it is within the scope of the invention to effect such feature, structure, or characteristic in connection with other embodiments.
Although the invention has been described herein with reference to a number of illustrative embodiments thereof, it should be understood that numerous other modifications and embodiments can be devised by those skilled in the art that will fall within the spirit and scope of the principles of this invention. More specifically, various variations and modifications are possible in the component parts and/or arrangements of the subject combination arrangement within the scope of the disclosure, the drawings and the appended claims. In addition to variations and modifications in the component parts and/or arrangements, other uses will also be apparent to those skilled in the art.

Claims (7)

1. The utility model provides an aluminium template "two U hold in palm" connection support frock, includes early tear head (15), its characterized in that: comprises a base (1), a bottom column (4), a middle column (5), an upper column (19), a threaded shaft (12), a U-shaped support (13) and a top column (14); the base (1) is a wide square plate, and threaded through holes (2) are formed in the periphery of the base; the bottom column (4) is a cylinder and is fixedly arranged in the base (1); middle post (5) set up to a cylinder and detachable joint and switching setting on sill pillar (4), go up post (19) and set up to root cylinder and detachable joint and switching setting on middle post (5), threaded shaft (12) threaded connection is at last post (19) center, U type holds in the palm (13) and sets up to two of mutual adaptation lock joint, and one of them is fixed to be set up at the top of threaded shaft (12), and the other one sets up on fore-set (14), and the other end connection setting of fore-set (14) is on early-dismantling head (15).
2. The aluminum mould plate 'double-U-shaped support' connecting and supporting tool according to claim 1, which is characterized in that: four reinforcing plates (3) are arranged between the bottom column (4) and the base (1).
3. The aluminum mould plate 'double-U-shaped support' connecting and supporting tool according to claim 1, which is characterized in that: the top of the bottom column (4) and the middle column (5) is provided with a positioning groove (7), the center is provided with a rotating shaft groove, and a bearing (8) is embedded in the rotating shaft groove.
4. The aluminum mould plate 'double-U-shaped support' connecting and supporting tool according to claim 1, which is characterized in that: the bottoms of the middle column (5) and the upper column (19) are provided with step shafts (18), one step is fixedly arranged in the bearing (8), and the other step is connected in the positioning groove (7) in a rotating way.
5. The aluminum mould plate 'double-U-shaped support' connecting and supporting tool according to claim 1, which is characterized in that: a roller (9) is arranged between the step and the positioning groove (7).
6. The aluminum mould plate 'double-U-shaped support' connecting and supporting tool according to claim 1, which is characterized in that: the threaded shaft (12) is a bearing screw rod.
7. The aluminum mould plate 'double-U-shaped support' connecting and supporting tool according to claim 1, which is characterized in that: a fastening screw (10) is rotatably arranged on a threaded shaft (12) at the top of the upper column (19), and handles (11) are arranged on two sides of the fastening screw (10).
CN202022093951.1U 2020-09-22 2020-09-22 Aluminum mould board "two U hold in palm" connection support frock Active CN213359378U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022093951.1U CN213359378U (en) 2020-09-22 2020-09-22 Aluminum mould board "two U hold in palm" connection support frock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022093951.1U CN213359378U (en) 2020-09-22 2020-09-22 Aluminum mould board "two U hold in palm" connection support frock

Publications (1)

Publication Number Publication Date
CN213359378U true CN213359378U (en) 2021-06-04

Family

ID=76154717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022093951.1U Active CN213359378U (en) 2020-09-22 2020-09-22 Aluminum mould board "two U hold in palm" connection support frock

Country Status (1)

Country Link
CN (1) CN213359378U (en)

Similar Documents

Publication Publication Date Title
CN213359378U (en) Aluminum mould board "two U hold in palm" connection support frock
CN217151174U (en) Construction is with convenient to detach's supplementary installation device of scaffold frame
CN114046044B (en) Formwork support fastening tool
CN206655478U (en) Adjustable window hole molding board support meanss
CN205976118U (en) Outer decorative aluminum board articulates system
CN206530077U (en) A kind of support frame
CN102767280A (en) Quick-dismounting system and installation method for top plate
CN107190976A (en) A kind of construction formwork for placing
CN209891688U (en) High building quick-building safe construction foot rest
CN112538960A (en) Make things convenient for dismouting and firm scaffold frame
CN206844642U (en) A kind of construction formwork for placing
CN201151954Y (en) Steel column and concrete column connection structure
CN206625604U (en) A kind of lightweight steel construction component of quick construction
CN213015550U (en) Support frame for high-rise building construction
CN211817785U (en) Scaffold for building construction
CN212176738U (en) Convenient frock canopy device of environmental protection
CN215926689U (en) Building construction template
CN221256171U (en) Novel reinforcing structure for connecting diagonal bracing with template
CN216587691U (en) Foldable and reusable square waffle barrel inner support device
CN213015306U (en) Elevator shaft construction operation platform
CN216740507U (en) Outer wall dry-hanging stone mounting structure
CN217680487U (en) Inside creeping formwork device turns up
CN220467349U (en) Independent mast for lifting air pipe
CN211873960U (en) Support frame for building
CN215331401U (en) Scaffold installation device for building engineering construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant