CN213204137U - Novel support type of batter pile combined vertical anchor - Google Patents

Novel support type of batter pile combined vertical anchor Download PDF

Info

Publication number
CN213204137U
CN213204137U CN201921741050.XU CN201921741050U CN213204137U CN 213204137 U CN213204137 U CN 213204137U CN 201921741050 U CN201921741050 U CN 201921741050U CN 213204137 U CN213204137 U CN 213204137U
Authority
CN
China
Prior art keywords
pile
anchor
vertical anchor
batter
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921741050.XU
Other languages
Chinese (zh)
Inventor
周玉石
谢晓东
刘国锋
谢曙东
赵伟明
鲍国强
刘飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Teyu Technology Co ltd
Original Assignee
Shanghai Chengdi Rock Soil Design Co ltd
Shanghai Chengdixiangjiang Data Technology Co ltd
Chengdi Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Chengdi Rock Soil Design Co ltd, Shanghai Chengdixiangjiang Data Technology Co ltd, Chengdi Construction Group Co ltd filed Critical Shanghai Chengdi Rock Soil Design Co ltd
Priority to CN201921741050.XU priority Critical patent/CN213204137U/en
Application granted granted Critical
Publication of CN213204137U publication Critical patent/CN213204137U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a foundation ditch engineering field is a novel supporting type of batter pile combination vertical anchor, and the main constitution of novel supporting type has: inclined piles, vertical anchors, crown beams and cement-soil mixing piles. The inclined piles are mainly used for retaining soil in the front row and supporting soil on the slope, and the tops of the inclined piles are connected into a whole through the crown beams; the vertical anchor has the functions of increasing the anti-overturning capacity of the inclined pile, controlling the horizontal displacement of the side wall of the foundation pit and increasing the overall stability of the whole structure; the cement soil mixing pile has the main functions of stopping water, and ensuring that the soil body at the lower part of the inclined pile is dry and the anchoring force of the anchor rod or the anchor cable is not lost through precipitation. This novel support type is a foundation ditch retaining structure of interior support of nothing, can reduce the influence that the foundation ditch lateral wall warp too big to the surrounding environment production, has avoided traditional interior bearing structure to the influence of earth excavation and underground structure construction, shortens the construction period of engineering.

Description

Novel support type of batter pile combined vertical anchor
Technical Field
The utility model belongs to building foundation engineering field relates to a batter pile combines novel supporting type of erecting anchor.
Background
There are several types commonly used for shallow pit enclosures: the device comprises row piles and supports (anchor rods (cables)), double-row piles, a gravity type retaining wall, row pile cantilevers, row piles and inclined cast supports. When the supporting structure is adopted, the horizontal support covers the whole excavation surface of the foundation pit, so that the problems of excavation and transportation of earthwork in the foundation pit, inconvenience in construction of an underground structure, increase in construction period and construction cost of the whole project and the like are caused, and the larger the area of the foundation pit is, the more the problems are highlighted; because of the existing regulation, the length of the anchor rod (cable) can not exceed the ground red line, so that the anchor rod (cable) can not be used in many foundation pit projects; the construction of foundation pits smaller than 5m is more in three structures of double-row piles, gravity type retaining walls and row pile cantilevers, but the problem that the deformation of an enclosure wall body in the construction process is too large is serious; when the inclined throwing support is adopted, secondary excavation of earthwork at the bottom of the inclined throwing support is always a main problem in the use of the inclined throwing support.
Aiming at the defects of various enclosure types, domestic professionals create several new inclined throw support type enclosure knots for solving the problems, the solutions of the structures to the secondary excavation of earthwork at the lower part of an inclined support are basically consistent, one end in an inclined support pit is arranged below the excavation surface of a foundation pit, the earthwork in the pit is excavated once during the earthwork excavation, a water stop steel plate is welded on an inclined support rod piece, and then the inclined support rod piece penetrates through a bottom plate and the outer wall of a ground warehouse, so that the novel structure can influence the construction of an underground structure.
According to the analysis above, the utility model discloses combine the batter pile with erecting the anchor for the upper and lower component that does not influence the project construction of foundation ditch excavation face exists, avoids the bracing to pass bottom plate and outer wall, envelope to warp little, the protection that is favorable to all ring edge borders, is a simple, high-efficient, the novel envelope of operatable.
SUMMERY OF THE UTILITY MODEL
The utility model discloses the mesh is realized through following technical means:
the utility model provides a novel support type of batter pile combination vertical anchor which mainly comprises: inclined piles, vertical anchors, crown beams and cement-soil mixing piles; the inclined pile is arranged on an inclined supporting structure on the inner side of the foundation pit, a vertical anchor is arranged on the outer side of the inclined pile, a locking position of the vertical anchor is located on the upper portion of a top crown beam of the inclined pile, and a cement-soil mixing pile is arranged on the outer side of the vertical anchor.
The inclined pile is positioned on one side in the foundation pit, the pile end must enter a relatively stable soil layer, and the earthwork on the lower portion of the inclined pile is not dug.
The inclined pile is made of precast concrete piles or profile steel, the profile steel is mainly H-shaped steel or steel pipes, and a static pile machine is pressed in or inserted in a vibrating mode during construction.
The vertical anchor can be an anchor rod or an anchor cable locking position and is positioned at the upper part of the inclined pile crown beam, and the anchoring section of the vertical anchor is required to be positioned in a stable soil layer below the circular arc sliding surface at the bottom of the foundation pit.
The cement-soil mixing pile is positioned on the outer side of the vertical anchor, the distance between the cement-soil mixing pile and the vertical anchor is larger than 200mm, and the cement-soil mixing pile must be constructed before the vertical anchor.
When the front row of the inclined piles is used for retaining soil and supporting slope soil, the tops of the inclined piles are connected into a whole through the crown beams; the vertical anchor provides the anti-overturning capability of the batter pile and controls the horizontal displacement of the side wall of the foundation pit, so that the overall stability of the whole structure is improved; the cement soil mixing pile provides a water stopping effect, and the soil body at the lower part of the inclined pile is dried through precipitation, and the anchoring force of the anchor rod or the anchor cable is not lost.
The method has the following remarkable advantages:
1. the utility model discloses combine the batter pile with erecting the anchor, simple structure, the construction is cheap, does not have the construction technology difficult point.
2. Compared with the existing supporting type, the utility model discloses required construction space is less, and the structure is no longer than the land used red line.
3. Compare with current diagonal casting bracing structure, utility model construction completion back, the foundation ditch does not have bearing structure member, and the earthwork can adopt the big formula of digging to clear away in the pit, and the bracing bottom earthwork need not clear away, has practiced thrift the earthwork volume of digging, and the bracing need not pass underground structure.
4. Compare with cement soil gravity type barricade, the utility model discloses the front portion adopts the batter pile, and the vertical direction has perpendicular anchor, and bracing bottom earthwork does not excavate, is favorable to the slope earthwork to be stable, erects the anchor and can applys prestressing force, and envelope lateral deformation can obtain effective control, and the foundation ditch excavation can reduce to the minimum to the influence of all ring edge borders.
5. Compare with traditional envelope, the utility model discloses will be greater than traditional envelope to the saving of time limit for a project and cost.
Drawings
FIG. 1 is a cross-sectional view of a novel support type of a batter pile combined with a vertical anchor;
FIG. 2 is a first plan view of a novel support type of a batter pile combined with a vertical anchor;
FIG. 3 is a plan view II of a novel support type combining an inclined pile and a vertical anchor;
wherein: 1-anchor backing plate, 2-anchor, 3-crown beam, 4-inclined pile and 5-vertical anchor; 6-cement soil mixing pile, 7-slope protection, 8-cut-off ditch at the top of foundation pit, 9-underground structure and 10-potential sliding surface.
Detailed Description
The utility model relates to a novel excavation supporting type, its concrete type sees that the attached drawing shows, and main constitution has: inclined piles, vertical anchors, crown beams and cement-soil mixing piles; the inclined piles can be concrete precast piles or H-shaped steel or steel pipes, static pile machines or vibration is adopted to press the inclined piles into the soil, pile ends must be displaced relatively to stabilize the soil layer, the novel structure mainly has the main functions of front-row soil retaining and slope soil supporting, and the tops of the inclined piles are connected into a whole through crown beams; the vertical anchor is an anchor rod (cable), construction can be carried out by adopting a construction method, and the novel structure has the functions of increasing the anti-overturning capacity of the inclined pile and controlling the horizontal displacement of the side wall of the foundation pit; the cement-soil mixing pile can be constructed by adopting the existing cement-soil mixing pile construction equipment, and has the main effects of stopping water, and ensuring the drying of the soil body at the lower part of the inclined pile and the loss of the anchoring force of the anchor rod (cable) through precipitation. The utility model discloses the protection object is this kind of novel enclosure type, is not limited to the foundation ditch field and uses, is not limited to two kinds of plane distribution type that the drawing given, is not limited to the component material and the model in the novel structure, and similar structure is still the utility model discloses an in the protection range. The utility model discloses structure implementation process explains as follows:
firstly, accurately positioning according to a construction drawing, pressing or vibrating a static pressure pile machine into an inclined pile, wherein the pile end of the inclined pile must enter a relatively stable soil layer;
secondly, accurately positioning according to a construction drawing, and constructing a waterproof curtain;
thirdly, constructing a vertical anchor between the inclined pile and the waterproof curtain, wherein the top of the vertical anchor is positioned at the top of the inclined pile;
fourthly, connecting the top of the inclined pile with a crown beam reinforcement cage, enabling a vertical anchor bar to penetrate through the crown beam reinforcement cage, and sleeving a PVC pipe in the crown beam section of the anchor bar to prevent the anchor bar from being consolidated by concrete and being incapable of tensioning prestress;
fifthly, after the crown beam concrete and the vertical anchor anchoring body reach the design strength, tensioning the vertical anchor prestress and locking;
sixthly, excavating earthwork in the foundation pit, and excavating a sprayed concrete protective surface between the inclined piles along with construction;
seventhly, excavating the foundation pit to the bottom, constructing an underground structure, and backfilling the foundation pit after the underground structure is constructed;
and eighthly, removing the prestress of the vertical anchor, and pulling out the anchor rib when the vertical anchor is a recyclable anchor rod.

Claims (6)

1. The utility model provides a novel support pattern of batter pile combination vertical anchor which characterized in that, the novel support pattern of batter pile combination vertical anchor mainly constitute and have: inclined piles, vertical anchors, crown beams and cement-soil mixing piles; the inclined pile is arranged on an inclined supporting structure on the inner side of the foundation pit, a vertical anchor is arranged on the outer side of the inclined pile, a locking position of the vertical anchor is located on the upper portion of a top crown beam of the inclined pile, and a cement-soil mixing pile is arranged on the outer side of the vertical anchor.
2. The novel support type of the batter pile combined with the vertical anchor according to claim 1, wherein the batter pile is positioned at one side in the foundation pit, the pile end must enter a relatively stable soil layer, and the earthwork at the lower part of the batter pile is not dug out.
3. The novel support type of an inclined pile combined with a vertical anchor according to claim 1, wherein the inclined pile is made of a precast concrete pile or section steel, the section steel is mainly H-shaped steel or steel pipe, and a static pile machine is pressed in or inserted in a vibration mode during construction.
4. The novel support type of batter pile combined with vertical anchor as claimed in claim 1, wherein said vertical anchor can be anchor rod, and also can be anchor cable locking position positioned on the upper portion of batter pile crown beam, and the anchoring section of vertical anchor must be positioned in the stable soil layer below the circular sliding surface of foundation pit bottom.
5. A novel support form of an oblique pile combined with a vertical anchor is characterized in that the cement-soil mixing pile is positioned outside the vertical anchor and is spaced from the vertical anchor by more than 200mm, and the cement-soil mixing pile must be constructed before the vertical anchor.
6. The novel support type of the batter pile combined with the vertical anchor according to claim 1, wherein the tops of the batter piles are connected into a whole through the crown beams when the batter piles are used for retaining soil in the front row and supporting slope soil; the vertical anchor provides the anti-overturning capability of the batter pile and controls the horizontal displacement of the side wall of the foundation pit, so that the overall stability of the whole structure is improved; the cement soil mixing pile provides a water stopping effect, and the soil body at the lower part of the inclined pile is dried through precipitation, and the anchoring force of the anchor rod or the anchor cable is not lost.
CN201921741050.XU 2019-10-13 2019-10-13 Novel support type of batter pile combined vertical anchor Active CN213204137U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921741050.XU CN213204137U (en) 2019-10-13 2019-10-13 Novel support type of batter pile combined vertical anchor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921741050.XU CN213204137U (en) 2019-10-13 2019-10-13 Novel support type of batter pile combined vertical anchor

Publications (1)

Publication Number Publication Date
CN213204137U true CN213204137U (en) 2021-05-14

Family

ID=75817496

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921741050.XU Active CN213204137U (en) 2019-10-13 2019-10-13 Novel support type of batter pile combined vertical anchor

Country Status (1)

Country Link
CN (1) CN213204137U (en)

Similar Documents

Publication Publication Date Title
CN102094425B (en) Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam
CN103306289B (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN103321246B (en) Underground diaphragm wall based foundation pit construction method
CN109577277B (en) Wall-mounted drainage anchor rod retaining wall structure and construction method thereof
CN103103988A (en) Foundation ditch construction method of horizontal bracing structure of central island floor slaps
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN205975658U (en) Steel platform tower crane foundation
CN109914422A (en) A kind of steel pipe and soil nailing combined type foundation pit supporting construction and construction method
CN107326896A (en) One kind combination steel construction support pile and construction method
CN107740419A (en) Foundation pit supporting method and raked pile
CN108035360B (en) A method of for pattern foundation pit supporting structure
CN207159990U (en) One kind combination steel construction support pile
CN203768914U (en) Foundation pit bracing diagonal support pile structure
CN115652952B (en) Uplift pile and support pile combined inclined straight pile internal-support-free foundation pit supporting method
CN108005086B (en) A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure
CN213204137U (en) Novel support type of batter pile combined vertical anchor
CN111236259A (en) Combined lattice-shaped prefabricated pile wall supporting structure and construction method thereof
CN203373753U (en) Pile anchor retaining wall concrete anchor cable top beam structure of foundation ditches
CN111911183B (en) Tunnel hole entering construction method based on end wall type guide wall structure
CN112647509A (en) Novel support type of batter pile combined vertical anchor
CN109653193B (en) Reverse construction method for underground continuous wall
CN113293771A (en) Combined steel plate anchoring body
CN207193947U (en) It is a kind of to be used for rotary digging stake and the connection buckle of Larsen steel sheet pile
CN107100216B (en) The unilateral basic pile foundation of monolithic wall overhangs underpinning construction method
CN218757521U (en) PC construction method pile and inclined strut combined supporting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231206

Address after: Room J815, 3rd Floor, No. 5358 Huyi Road, Jiading District, Shanghai, June 2018

Patentee after: Zhongji Engineering (Shanghai) Geotechnical Co.,Ltd.

Address before: 201806 room j404, 3 / F, No. 5358, Huyi Road, Jiading District, Shanghai

Patentee before: Chengdi Construction Group Co.,Ltd.

Patentee before: Shanghai chengdixiangjiang Data Technology Co.,Ltd.

Patentee before: SHANGHAI CHENGDI ROCK-SOIL DESIGN Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240204

Address after: 201306 2nd Floor, No. 979 Zhuyunhan Road, Lingang New Area, Pudong New Area, Shanghai

Patentee after: Shanghai Teyu Technology Co.,Ltd.

Country or region after: China

Address before: Room J815, 3rd Floor, No. 5358 Huyi Road, Jiading District, Shanghai, June 2018

Patentee before: Zhongji Engineering (Shanghai) Geotechnical Co.,Ltd.

Country or region before: China