CN212716488U - Pipe grabbing machine carrying well site pipe rod storage pipe frame - Google Patents

Pipe grabbing machine carrying well site pipe rod storage pipe frame Download PDF

Info

Publication number
CN212716488U
CN212716488U CN202021104852.2U CN202021104852U CN212716488U CN 212716488 U CN212716488 U CN 212716488U CN 202021104852 U CN202021104852 U CN 202021104852U CN 212716488 U CN212716488 U CN 212716488U
Authority
CN
China
Prior art keywords
pipe
pole
well site
adjustable
storage rack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021104852.2U
Other languages
Chinese (zh)
Inventor
田志涛
崔荣海
陈绍维
姜文峰
刘鲁滨
范建国
杨向宽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
Sinopec Shengli Oilfield Co Binnan Oil Extraction Plant
Original Assignee
China Petroleum and Chemical Corp
Sinopec Shengli Oilfield Co Binnan Oil Extraction Plant
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Chemical Corp, Sinopec Shengli Oilfield Co Binnan Oil Extraction Plant filed Critical China Petroleum and Chemical Corp
Priority to CN202021104852.2U priority Critical patent/CN212716488U/en
Application granted granted Critical
Publication of CN212716488U publication Critical patent/CN212716488U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model provides a grab pipe machine and carry well site pipe pole and deposit pipe support, shovels under the pipe pole storage rack base, the grab pipe machine and grabs the inserted hole, adjustable pipe pole and separates shelves stake, adjustable pipe support limit shelves stake, adjustable pipe pole separate shelves stake with adjustable pipe support limit shelves stake has a plurality ofly respectively. The utility model discloses simple structure, not restricted by the well site, safe and reliable is applicable to on-spot extensive popularization and application.

Description

Pipe grabbing machine carrying well site pipe rod storage pipe frame
Technical Field
The utility model relates to a pipe support is deposited in well site is retrieved to tubular pole in the workover link among the oil industry field. The pipe grabbing machine has the characteristics of convenience in carrying and transferring, safety, simple structure and strong applicability.
Background
The pipe rod, also called drill rod, is a common device in the petroleum field, and is usually a steel pipe with a thread at the tail part, and is used for connecting the surface device of a drilling machine and the drilling and grinding device or bottom hole device positioned at the bottom end of a well. The purpose of the drill pipe is to carry drilling mud to the drill bit and, together with the drill bit, raise, lower or rotate the bottom hole assembly. The drill pipe must be able to withstand large internal and external pressures, twists, bends and vibrations. In the process of oil and gas exploitation and extraction, the drill pipe can be used for multiple times. The drill rods are divided into a kelly, a drill rod and a weighted drill rod. The connection sequence is square drill rod (1), drill rod (n, determined by well depth), weighted drill rod (n, determined by drill tool combination design). The classification of the drill rods, the drill rod joints, the drill rod specifications, and the steel grade and strength of the drill rods are described in detail.
The light pipe and the raw steel pipe are manufactured into the drill rod after a plurality of processing steps. Firstly, the outer surface of the light pipe is inwards bent through the treatment of a steel pipe thickening process, and the pipe wall of the steel pipe is thickened. Next, the screw is threaded and plated with copper which increases strength. Then, nondestructive quality control inspection is performed, and then welding of the steel pipe body joint is performed. The tube body is then subjected to a welding heat treatment and a welding finish treatment to relieve welding residual stresses. Other tests, including hardness, pressure and non-destructive tests, are performed on the finished steel pipe prior to painting and packaging the finished drill pipe.
In the process of oil exploitation, when a pipe rod used in a workover operation link is transported, the recovered pipe rod is randomly and temporarily stored on a well site due to the limitation of the well site and a transport vehicle. The falling of the pipe rod causes pollution to a well site, and solid wastes such as oil sludge and sand are generated in the process of recovering, cleaning and repairing the falling pipe rod. Meanwhile, in well repair operations, there are often several types of problems:
the first category is complex salvage, which means that the condition of objects falling in the well is very complex due to various reasons in the oil and gas well. Taking an example: the underground pipe column and tools are all stuck by a certain well, and the oil pipe is pulled off when a minor repair crew handles the underground pipe column and tools, so that the well cannot operate and only needs to be handed to a major repair crew for repair.
The second category is the repair of well casing, which is a necessary condition for ensuring the normal production of oil and gas wells, and the well casing damage often occurs due to various reasons, so the repair of well casing is one of the main tasks of major workover crews. The casing damage mainly has the following conditions: firstly, the diameter of the casing is reduced, namely the inner diameter of the casing of the oil well is reduced, so that a downhole tool cannot be used, and the oil well cannot normally produce; secondly, casing rupture, namely the casing of the oil well is ruptured to form a seam or a hole, so that a great amount of stratum sand flows into the well, and the oil-gas well stops production; thirdly, the casing is staggered and broken, some well casings can be broken, and the upper fracture and the lower fracture are staggered.
And thirdly, drilling the inner side of the casing, namely, using a small drill rod with a drill bit to go down from the old well casing, drilling a window (called as window in terms) at a preset position, drilling the small drill bit outwards from the window, drilling a small borehole, then putting the small casing and cementing the well. The project of drilling a section of slim hole completion from the inside of an old well casing to the outside is called old well sidetrack, which is suitable for the following conditions: the lower part of the old well is scrapped and cannot be exploited, and production can be recovered after sidetracking; old well bores have poor oil formation, while well formations are present near the well bore, and new reserves can be recovered after sidetrack drilling.
The problem of storing the pipe rods exists in the three main problems. The problem of storing the pipe rods is that well workover must be considered, and the success or failure of well workover is directly concerned.
For stopping the falling of the recovery pipe pole and reducing the production of oil sludge sand solid waste in the pipe pole transportation process, the field needs a well site pipe pole storage rack that the pipe grabbing machine carried the transportation, and the device should have simple structure, safe and reliable, uses convenient advantage.
The utility model adopts the pipe grabbing machine to carry, which is convenient for the transfer and use of the pipe frame; the length of the pipe support does not exceed the maximum external dimension of the pipe grabbing machine, so that safe walking is facilitated, and a pipe grabbing shovel grabbing port arranged on a pipe support base is convenient to lock and transport; thirdly, adjustable partition piles and side piles are adopted, and the storage quantity of the pipe rods is adjustable; the structure is simple, the well site is not limited, and the safety and the reliability are realized.
SUMMERY OF THE UTILITY MODEL
In order to solve the problem, the utility model provides a can realize workover in-process pipe pole and transport the pipe support of retrieving the well site and deposit temporarily, solve the well site pollution that the recovery pipe pole falls to the ground to deposit and cause oil pipe pole cleaning in-process oil mud sand solid waste's production. The device adopts the pipe grabbing machine to carry and transport, and the temporary well site storage rack of the double-pivot support pipe pole can avoid the pipe pole recovered in the well repair operation process to fall to the ground to deposit and stop the production of oil sludge sand in the pipe pole cleaning process. The device is characterized in that: firstly, the pipe frame is locked by a shovel grab of a pipe grabbing machine, so that the pipe frame is firmly fixed on the shovel grab; secondly, the length of the pipe support does not exceed the maximum external dimension of the pipe grabbing machine, so that the pipe support can walk safely; thirdly, because the pipe rod separating barrier piles and the side barrier piles are additionally arranged on the pipe frame, the height of the barrier piles can be adjusted according to the field recovery condition by the storage quantity of the pipe rods; fourthly, the problem that the recovery pipe rod falls to the ground to be stored and the production of oil sludge sand in the cleaning process of the pipe rod is avoided.
The specific implementation mode is as follows:
the utility model provides a grab pipe machine and carry well site pipe pole and deposit pipe support, shovels under pipe pole storage rack base, the grab pipe machine and grabs the inserted hole, adjustable pipe pole separates shelves stake, adjustable pipe support side rail stake.
Preferably, the adjustable pipe rod separation fender pile and the adjustable pipe frame side fender pile are respectively provided with a plurality of piles.
Preferably, the pole storage rack base is substantially rectangular with an interior cavity.
Preferably, the size of the lower shovel claw insertion opening of the pipe grabbing machine is consistent with the size of the shovel claw of the pipe grabbing machine.
Preferably, the number of the adjustable pipe rod separation barrier piles is two.
Preferably, the number of the adjustable pipe frame side rail piles is four.
The utility model discloses simple structure, not restricted by the well site, safe and reliable is applicable to on-spot extensive popularization and application.
Drawings
Fig. 1 is a schematic structural view of an embodiment of a pipe pole storage rack according to the present invention;
fig. 2 is a schematic structural diagram of a middle stop pile of the pipe pole storage pipe rack in fig. 1.
The reference numbers are as follows:
1-pipe pole storage rack base 2-pipe grabbing machine lower shovel grabbing insertion opening 3-pipe pole isolation adjustable gear pile
4-adjustable pipe frame side stop pile
Detailed Description
The following detailed description of the present invention is made with reference to the accompanying drawings and examples:
as shown in figure 1, the pipe support includes pipe pole storage rack base 1, grabs under the pipe machine shovel and grabs inserted hole 2, adjustable pipe pole separation shelves stake 3, adjustable pipe support limit shelves stake 4.
The first embodiment is as follows:
the concrete description is as follows:
pipe pole storage rack base 1 of cuboid has the firm function of pipe pole storage bearing, and its inside cavity that has for hold the pipe pole, grab the pipe machine down the shovel and grab inserted hole 2 setting at the middle part of pipe pole storage rack base 1, make things convenient for the oil pipe pole to transport grab the pipe machine down the shovel grab insert the lock solid grab the pipe machine of being convenient for on the shovel grabs and carry the transportation.
Adjustable pipe pole separates shelves stake 3 has two, can adjust shelves stake size, separates the inside parking space of pipe pole storage rack base 1, and the pipe pole of the well site of being convenient for is retrieved does not mix and puts. Adjustable pipe support border stake has 4, distributes in the upper surface four corners of pipe pole storage rack base 1, can retrieve the whole storage capacity of work load adjustment pipe support according to the scene.
Referring to the attached figure 2, each adjustable pipe rod separation retaining pile 3 and each adjustable pipe frame side retaining pile 4 are respectively provided with an independent height adjusting device for adjusting the height of each retaining pile according to the situation on site and increasing the application range of the pipe frame.
The utility model discloses the theory of operation as follows:
when pipe rods need to be replaced in a workover operation link, the pipe grabbing machine lower shovel grab insertion hole 2 is used for storing pipe racks of the pipe rods in a well site and locking the pipe racks into the pipe grabbing machine shovel grab, the pipe grabbing machine carries the pipe rods to transfer the well site, the well site is placed at a proper position, the two pipe racks are placed side by side, and the center distance is not less than 1.5 times of the wheel distance of the pipe grabbing machine. The size of the adjustable pipe rod separation retaining pile 3 and the size of the adjustable pipe frame side retaining pile 4 are adjusted according to the number of the recovery pipe rods. Firstly, respectively storing pipe rods to be recovered on pipe rod well site recovery pipe frames by a pipe grabbing machine, and emptying a pipe rod storage rack for well site operation; secondly, the pipe grabbing machine unloads pipe rods on the well pipe rod conveying vehicle, and the pipe rods are placed to a well site pipe rod storage pipe rack soaring pipe rod transfer vehicle; the third pipe grabbing machine is used for transporting the pipe rods temporarily stored on the well site storage pipe frame to a pipe rod transfer trolley; and finally, the pipe grabbing machine carries out the shoveling grabbing insertion hole 2 to take out the pipe rod well site recovery pipe frame, and the pipe rod transferring work of one well is completed.
Example two:
the concrete description is as follows:
the pipe pole storage rack base of cuboid has the firm function of pipe pole storage bearing, and its inside cavity that has for hold the pipe pole, grab the pipe machine down the shovel and grab the inserted hole setting on the upper portion of pipe pole storage rack base 1, the oil pipe pole is transported and is grabbed the pipe machine down the shovel and grab and insert and be convenient for grab the pipe machine and carry the transportation, and the pipe pole freely falls down in the same direction as gravity during the release, makes things convenient for the range of pipe pole. Although the processing has certain difficulty, the use is very convenient.
The adjustable pipe pole separates the fender stake and has 1, places in the middle of the centre. Adjustable pipe support limit shelves stake has 8, except that the upper surface four corners of pipe pole storage rack base respectively has one, respectively has an adjustable pipe support limit shelves stake in the middle of every limit, offers on base upper portion and grabs under the pipe machine shovel and grab under the inserted hole the condition, and intensive festival pipe support limit shelves stake is arranged and can not influence depositing of pipe pole, can heighten pipe pole on the contrary and deposit efficiency, increases the security of depositing.
Every adjustable pipe pole separates shelves stake and adjustable pipe support limit shelves stake structure basically the same, can use in mixture, adjustable pipe pole separates the height adjusting device that has independent on shelves stake and the adjustable pipe support limit shelves stake respectively, see figure 2, through height adjusting device, can adjust the height that adjustable pipe pole separates shelves stake and adjustable pipe support limit shelves stake, change the size of pipe pole parking space on the pipe pole parking frame base simultaneously, according to the needs on the scene, the pipe pole quantity that the adjustment can be deposited.
The utility model discloses the theory of operation as follows:
when a pipe rod needs to be replaced in a workover operation link, the pipe grabbing machine lower shovel claw insertion hole locks a well site pipe rod storage pipe frame into the pipe grabbing machine shovel claw from the upper side of a pipe rod storage frame base, the pipe grabbing machine carries the pipe rod to transport a well site, the well site is placed at a proper position, the two pipe frames are placed side by side, and the center distance is not less than 2 times of the wheel distance of the pipe grabbing machine. The height size of the adjustable pipe rod separation retaining pile and the adjustable pipe frame side retaining pile is adjusted according to the number of the recovery pipe rods. Firstly, respectively storing pipe rods to be recovered on pipe rod well site recovery pipe frames by a pipe grabbing machine, and emptying a pipe rod storage rack for well site operation; secondly, the pipe grabbing machine unloads pipe rods on the well pipe rod conveying vehicle, and the pipe rods are placed to a well site pipe rod storage pipe rack soaring pipe rod transfer vehicle; the third pipe grabbing machine is used for transporting the pipe rods temporarily stored on the well site storage pipe frame to a pipe rod transfer trolley; and finally, the pipe grabbing machine carries out the shoveling and grabbing insertion hole to take out the pipe rod well site recovery pipe frame, and the pipe rod transferring work of one well is completed.
The foregoing is only a part of the preferred embodiments of the present invention. Any person skilled in the art may modify the above-described embodiments or modify them to equivalent solutions. Therefore, any simple modifications or equivalent replacements made according to the embodiments of the present invention belong to the scope of the claimed invention.

Claims (1)

1. The utility model provides a grab pipe machine and carry well site pipe pole and deposit pipe support which characterized in that: the rectangular pipe pole storage rack base (1) has the function of stable pipe pole storage bearing, a cavity is formed in the rectangular pipe pole storage rack base and used for containing a pipe pole, and a lower shoveling and grabbing insertion hole (2) of the pipe grabbing machine is formed in the middle of the pipe pole storage rack base (1) so that the pipe grabbing machine can be carried and transported conveniently; the number of the adjustable pipe rod separating piles (3) is two, the size of each separating pile can be adjusted, the internal storage space of the base (1) of the pipe rod storage rack is separated, and pipe rods recovered in a well site are convenient to be placed in a non-mixing mode; adjustable pipe support border stake has (4), distributes in the upper surface four corners of pipe pole storage rack base (1), can retrieve the whole storage capacity of work load adjustment pipe support according to the scene.
CN202021104852.2U 2020-06-15 2020-06-15 Pipe grabbing machine carrying well site pipe rod storage pipe frame Active CN212716488U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021104852.2U CN212716488U (en) 2020-06-15 2020-06-15 Pipe grabbing machine carrying well site pipe rod storage pipe frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021104852.2U CN212716488U (en) 2020-06-15 2020-06-15 Pipe grabbing machine carrying well site pipe rod storage pipe frame

Publications (1)

Publication Number Publication Date
CN212716488U true CN212716488U (en) 2021-03-16

Family

ID=74951211

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021104852.2U Active CN212716488U (en) 2020-06-15 2020-06-15 Pipe grabbing machine carrying well site pipe rod storage pipe frame

Country Status (1)

Country Link
CN (1) CN212716488U (en)

Similar Documents

Publication Publication Date Title
US3848684A (en) Apparatus for rotary drilling
US8783339B2 (en) Tubular member adaptor apparatus
US6976534B2 (en) Slip element for use with a downhole tool and a method of manufacturing same
AU2011205189B2 (en) Anchor for use with expandable tubular
US9181764B2 (en) Pipe handling apparatus
US9574404B2 (en) High pressure large bore well conduit system
CN111433430A (en) Sequencing for drill rod handling
US20050257933A1 (en) Casing running head
CN101915059B (en) Process method for well completion at equal borehole diameter
US9493993B1 (en) Work string and method of completing long lateral well bores
CN106715827A (en) Liner drilling using retrievable directional bottom-hole assembly
CN105888549B (en) A kind of boring BHA of km depth L-type pre grouting from the surface and bore process
CN104632171A (en) Branching well staged fracturing well completion underground complete equipment and method
CN212716488U (en) Pipe grabbing machine carrying well site pipe rod storage pipe frame
CN213205612U (en) Inner guide and male cone combined drilling inner fishing tool
RU172470U1 (en) Telescopic drill pipe
CN103277050A (en) Recoverable whipstock and combined fishing tool thereof
US2940731A (en) Drill bit
US3221824A (en) Tool for laying a pipeline laterally of a well bore
CN203559776U (en) Guide locking mechanism suitable for sleeve driving head
US1360328A (en) Drill
CN217897797U (en) Four-level branch well tool system
AU2021204095B2 (en) Modular tubular product for well applications
CN114458214B (en) Large-size tail pipe hanger and use method thereof
CN212406612U (en) Sandstone geothermal well same-diameter well body structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant