CN212336763U - Curtain wall installation guide rail device fixed on roof flower frame beam - Google Patents
Curtain wall installation guide rail device fixed on roof flower frame beam Download PDFInfo
- Publication number
- CN212336763U CN212336763U CN202020862142.XU CN202020862142U CN212336763U CN 212336763 U CN212336763 U CN 212336763U CN 202020862142 U CN202020862142 U CN 202020862142U CN 212336763 U CN212336763 U CN 212336763U
- Authority
- CN
- China
- Prior art keywords
- steel
- guide rail
- roof
- horizontal cantilever
- curtain wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Greenhouses (AREA)
Abstract
The utility model provides a curtain installation guide rail device who is fixed in roofing flower frame roof beam, includes at least a set of guide rail system, and every group guide rail system includes: the guide rail installation mechanism comprises two horizontal cantilever supports arranged above the roof truss beam and at least one guide rail channel steel, wherein the guide rail channel steel is arranged below the horizontal cantilever supports and is fixed with each other, and the two horizontal cantilever supports are fixedly connected through a steel square tube; each horizontal cantilever support is correspondingly provided with one fixing mechanism, each fixing mechanism comprises a steel stand column and an embedded steel plate fixed on the top surface of the roof flower stand beam, the steel stand column is arranged on the top of the roof flower stand beam, one end of each steel stand column is fixedly connected with the embedded steel plate, and the other end of each steel stand column is connected with the corresponding horizontal cantilever support; the horizontal traveling device is arranged in the guide rail channel steel and can move along the guide rail channel steel. The utility model discloses installation safety has improved whole installation effectiveness, simple to operate practices thrift the space.
Description
Technical Field
The utility model relates to a building technical field, concretely relates to be fixed in curtain installation guide rail device of roofing flower frame roof beam.
Background
In some projects, roof covering upper portion often can design some flower frame roof beams and increase the whole effect of building, and conventional curtain installation adopts the roof covering to set up hoisting device, is difficult to satisfy roofing structure top curtain installation, often assists the installation with the tower crane to the life cycle of tower crane has been prolonged, and is difficult to guarantee the safety in the installation.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a can the full coverage curtain plate installation facade scope, the curtain installation guide rail device who is fixed in roofing flower frame roof beam that has improved whole installation effectiveness.
The utility model discloses a following technical scheme realizes:
the utility model provides a curtain installation guide rail device who is fixed in roofing flower frame roof beam, includes at least a set of guide rail system, and every group guide rail system includes:
the guide rail mounting mechanism comprises two horizontal cantilever supports arranged above the roof flower shelf beam and at least one guide rail channel steel, the guide rail channel steel is arranged below the horizontal cantilever supports and fixed with each other, and the two horizontal cantilever supports are fixedly connected through a steel square tube;
each horizontal cantilever support is correspondingly provided with one fixing mechanism, each fixing mechanism comprises a steel stand column and an embedded steel plate fixed on the top surface of the roof flower shelf beam, the steel stand column is arranged at the top of the roof flower shelf beam, one end of each steel stand column is fixedly connected with the embedded steel plate, and the other end of each steel stand column is connected with the corresponding horizontal cantilever support;
and the horizontal traveling device is arranged in the guide rail channel steel and can move along the guide rail channel steel.
Further, fixed establishment still includes the steel bracing, steel bracing one end with horizontal cantilever supports and is connected, the other end with the steel stand is connected.
Further, fixed establishment still includes supplementary fixing device, supplementary fixing device is including arranging in the steel member of hanging of horizontal cantilever support bottom, the hangers board that is fixed in the roofing structural layer, hang the steel member with the hangers board passes through wire rope and connects.
Further, the bottom that the horizontal cantilever supported is equipped with the steel sheet, and every guide rail channel-section steel corresponds and is equipped with one the steel sheet, and the guide rail channel-section steel with the steel sheet is articulated.
Further, one side that horizontal cantilever support was provided with the steel bracing is equipped with the guide rail channel-section steel, the opposite side is equipped with hang the steel member.
Preferably, the number of the guide rail channel steels is two, the guide rail channel steel on the inner side is used for hoisting the curtain wall plate, and the guide rail channel steel on the outer side is used for assisting the installation of the curtain wall plate by the operating platform.
The utility model discloses have following advantage:
1. the auxiliary installation of the tower crane is not needed, so that the service cycle of the tower crane is prolonged, and the safety in the installation process is ensured.
2. The vertical face range of the curtain wall plate installation can be fully covered, and the overall installation efficiency is improved.
3. The installation is convenient, the space is saved, the coverage is wide, the construction is flexible and efficient, and the input cost is low.
4. The curtain wall is suitable for high-rise buildings with curtain walls on the outer vertical surfaces.
Description of the drawings:
FIG. 1 is a top view of the curtain wall mounting rail assembly of the present invention secured to a roof truss beam;
fig. 2 is a side view of the curtain wall mounting rail device fixed on the roof truss beam.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and specific embodiments.
Referring to fig. 1-2, a curtain installation guide rail device who is fixed in roofing flower frame roof beam includes at least two sets of guide rail system, and every group guide rail system includes:
the guide rail installation mechanism comprises two horizontal cantilever supports 11 arranged above a roof truss beam 10 and two guide rail channel steel 12, wherein the guide rail channel steel 12 is arranged below the horizontal cantilever supports 11 and is fixed with each other, the two horizontal cantilever supports 11 are fixedly connected through a steel square tube 13, and the adjacent horizontal cantilever supports 11 in each section are connected into a whole through the steel square tube 13, so that the overall stability and the stress effect are improved;
each horizontal cantilever support is correspondingly provided with a fixing mechanism, each fixing mechanism comprises a steel upright post 21 and an embedded steel plate 22 fixed on the top surface of the roof flower frame beam 10, the steel upright post 21 is arranged on the top of the roof flower frame beam 10, one end of each steel upright post 21 is fixedly connected with the embedded steel plate 22, and the other end of each steel upright post 21 is connected with the corresponding horizontal cantilever support 11; fixing mechanism still includes steel bracing 23, and 23 one end of steel bracing is connected with horizontal cantilever support 11, and the other end is connected with steel stand 21 increase steel bracing 23 on the steel stand 21, wherein, one side that horizontal cantilever support 11 was provided with steel bracing 23 is equipped with two guide rail channel-section steels 12, and inboard guide rail channel-section steel is used for hoist and mount curtain plate, and outside track channel-section steel sets up the supplementary curtain plate installation of operation platform and can improve curtain plate installation effectiveness like this.
Every section of vertical adoption single bracing of fixed establishment, steel stand 21 is as main supporting mechanism promptly, and can set up according to actual conditions is nimble, can practice thrift the space like this, promotes the bulk rigidity through setting up steel bracing 23, increases stability. In order to improve the rigidity of the mechanism, a steel plate 111 is arranged at the bottom of the horizontal cantilever support 11, the steel plate 111 is welded with the horizontal cantilever support 11, one steel plate 111 is correspondingly arranged on each guide rail channel steel 12, and the guide rail channel steel 12 is hinged to the steel plate 111.
In addition, the fixing mechanism further comprises an auxiliary fixing device, the auxiliary fixing device comprises a hanging steel member 24 and a hanging lug plate 25, the hanging steel member 24 is arranged at the bottom of the horizontal cantilever support 11 and is fixed on the roof structure layer 4, the hanging steel member 24 is connected with the hanging lug plate 25 through a steel wire rope 26, and the hanging steel member 24 is arranged on the other side of the horizontal cantilever support 11.
The horizontal traveling device 3 is arranged in the guide rail channel steel 12 and can move along the guide rail channel steel 12, and the horizontal traveling device can move in the whole vertical face in the guide rail channel steel 12 and can meet the requirements of material lifting and installation.
A construction method of a curtain wall installation guide rail device fixed on a roof truss beam comprises the following steps:
s1, embedding a steel plate on the top surface of the roof flower rack beam to serve as a support of the curtain wall mounting guide rail;
s2, sequentially mounting a support steel upright post, a cantilever horizontal support channel steel, a steel inclined strut and an auxiliary fixing device;
s3, installing a horizontal steel square tube, and connecting adjacent horizontal cantilever supports into a whole;
s4, sequentially welding two steel plates on the outer side of the horizontal cantilever support;
and S5, installing a guide rail channel steel and a horizontal walking device, wherein the guide rail channel steel is hinged with the upper steel plate.
The utility model discloses construction method is simple, only needs at the pre-buried steel sheet of roofing pergola roof beam top face, as the support of curtain installation guide rail, and erection bracing steel stand, cantilever horizontal support channel-section steel, steel bracing, horizontal steel square tube connect into stable whole with each section support in proper order, improve support rigidity and atress effect, horizontal cantilever supports inboard installation off-load wire rope, and the bottom is fixed in the roofing structural layer. Cantilever horizontal stay outside end welded fastening twice steel sheet, installation guide rail and horizontal running gear, inboard guide rail are used for hoist and mount curtain plate, and the outside guide rail is used for installing the installation of operation platform auxiliary curtain plate, improves curtain plate installation effectiveness.
The present invention has been described in detail with reference to the drawings and the embodiments, and those skilled in the art can make various changes to the present invention based on the above description. Therefore, certain details of the embodiments should not be construed as limitations of the present invention, as modifications of the materials of construction, specifications of materials, specific dimensions, manner of connection, etc. should be considered within the scope of the claims. The scope of the invention is to be determined by the appended claims.
Claims (6)
1. The utility model provides a be fixed in curtain installation guide rail device of roofing flower frame roof beam, its characterized in that includes at least a set of guide rail system, and every guide rail system of group includes:
the guide rail mounting mechanism comprises two horizontal cantilever supports arranged above the roof flower shelf beam and at least one guide rail channel steel, the guide rail channel steel is arranged below the horizontal cantilever supports and fixed with each other, and the two horizontal cantilever supports are fixedly connected through a steel square tube;
each horizontal cantilever support is correspondingly provided with one fixing mechanism, each fixing mechanism comprises a steel stand column and an embedded steel plate fixed on the top surface of the roof flower shelf beam, the steel stand column is arranged at the top of the roof flower shelf beam, one end of each steel stand column is fixedly connected with the embedded steel plate, and the other end of each steel stand column is connected with the corresponding horizontal cantilever support;
and the horizontal traveling device is arranged in the guide rail channel steel and can move along the guide rail channel steel.
2. The curtain wall mounting track assembly secured to a roof truss beam of claim 1 wherein the securing mechanism further includes a steel diagonal brace, one end of the steel diagonal brace being connected to the horizontal cantilever support and the other end being connected to the steel upright.
3. The curtain wall mounting rail assembly fixed to the roof truss beam as claimed in claim 2, wherein the fixing mechanism further comprises an auxiliary fixing device, the auxiliary fixing device comprises a hanging steel member disposed at the bottom of the horizontal cantilever support and a hanging lug plate fixed to the roof structure layer, and the hanging steel member and the hanging lug plate are connected through a steel wire rope.
4. The curtain wall mounting rail assembly secured to the roof truss beam of claim 3 wherein the bottom of the horizontal cantilevered support is provided with a steel plate, one of the steel plates is provided for each rail channel, and the rail channels are hinged to the steel plates.
5. The curtain wall mounting rail assembly secured to the roof truss beam of claim 4 wherein the horizontal cantilevered support is provided with the rail channel on one side and the hanger steel member on the other side with the steel diagonal brace.
6. The curtain wall mounting rail assembly fastened to the roof truss beam of claim 1 wherein there are two rail channel sections, the inner rail channel section being used to hoist curtain wall panels and the outer rail channel section being used to assist in mounting the curtain wall panels on the operating platform.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020862142.XU CN212336763U (en) | 2020-05-21 | 2020-05-21 | Curtain wall installation guide rail device fixed on roof flower frame beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020862142.XU CN212336763U (en) | 2020-05-21 | 2020-05-21 | Curtain wall installation guide rail device fixed on roof flower frame beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212336763U true CN212336763U (en) | 2021-01-12 |
Family
ID=74083701
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020862142.XU Active CN212336763U (en) | 2020-05-21 | 2020-05-21 | Curtain wall installation guide rail device fixed on roof flower frame beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212336763U (en) |
-
2020
- 2020-05-21 CN CN202020862142.XU patent/CN212336763U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207268073U (en) | Novel flexible formwork bearing frame | |
CN215803108U (en) | Attached beam type hanging basket | |
CN113152664A (en) | Steel structural framework and modularized additional elevator | |
CN109296192B (en) | Lifting frame for assembled building | |
CN215291322U (en) | Integrally assembled attached scaffold | |
CN214995827U (en) | Hanging basket support mechanism on structural beam | |
CN212336763U (en) | Curtain wall installation guide rail device fixed on roof flower frame beam | |
CN112323978A (en) | Corner structure of encorbelmenting and building structure | |
CN113175089A (en) | Construction method of large-span heavy cantilever truss | |
CN111519914A (en) | Curtain wall installation guide rail device fixed on roof truss beam and construction method | |
CN213014697U (en) | Corner structure of encorbelmenting and building structure | |
CN216428338U (en) | Supporting structure of pipe well pipeline | |
CN216512520U (en) | Lifting system suitable for small space | |
CN216787874U (en) | Large-scale ring type truss hoisting structure in large-span high altitude | |
CN215671292U (en) | Prefabricated wallboard supporting system | |
CN86203954U (en) | Wall bearing self-lifting scaffold | |
CN209780229U (en) | Jacking platform system of integrated tower crane | |
CN217326383U (en) | Parapet hanging basket structure | |
CN113756558A (en) | High-rise assembled steel structure system externally hung hanging basket installation structure and construction method thereof | |
CN203201127U (en) | Temporary support system for steel truss | |
CN217102809U (en) | Portal frame assembly for silo wall lifting support system | |
CN2263161Y (en) | Self-lifting scaffold | |
CN111456399A (en) | Large-span overhanging support system for corridor between high-rise units and construction method thereof | |
CN220336399U (en) | Profile steel construction platform for high-altitude overhanging | |
CN211949527U (en) | Combined hanging basket for construction of overhung eave of high-rise building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |