CN212247675U - Concrete filled steel tube sleeper type ballastless track - Google Patents

Concrete filled steel tube sleeper type ballastless track Download PDF

Info

Publication number
CN212247675U
CN212247675U CN202021668330.5U CN202021668330U CN212247675U CN 212247675 U CN212247675 U CN 212247675U CN 202021668330 U CN202021668330 U CN 202021668330U CN 212247675 U CN212247675 U CN 212247675U
Authority
CN
China
Prior art keywords
track
base
sleeper
bed plate
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021668330.5U
Other languages
Chinese (zh)
Inventor
孙立
王森荣
李启航
闫亚飞
李秋义
杨艳丽
朱彬
张世杰
吴欢
陈仲华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
China Railway Construction Corp Ltd CRCC
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
China Railway Construction Corp Ltd CRCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd, China Railway Construction Corp Ltd CRCC filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN202021668330.5U priority Critical patent/CN212247675U/en
Application granted granted Critical
Publication of CN212247675U publication Critical patent/CN212247675U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Railway Tracks (AREA)

Abstract

The utility model discloses a concrete filled steel tube pillow formula ballastless track, including base, bed board, the two formula sleepers of steel pipe concrete, its characterized in that: the lower part of the ballast bed plate is provided with a plurality of grooves which are sunken upwards, the base is provided with a plurality of upwards convex bosses formed when the base is poured, and a damping layer surrounding the bosses is arranged between the base and the ballast bed plate. The movement of the track bed plate is limited by the track bed plate groove and the base boss, the contact area of the track bed plate and the base is increased, and the integrity of the track structure is improved. Meanwhile, the thickness of the base is reduced to some extent, and the height of the track structure is reduced. Rubber vibration damping pads are additionally arranged between the track bed plate and the base, so that the vibration damping performance of the track structure is guaranteed, and the novel ballastless track structure can be applied to the urban rail transit field with higher requirements on the environment. The elastic base plate arranged between the groove of the ballast bed plate and the boss of the base can enhance the vibration reduction performance and also play a role in buffering, and the adverse effect of stress concentration on the track structure is reduced.

Description

Concrete filled steel tube sleeper type ballastless track
Technical Field
The utility model belongs to ballastless track field, concretely relates to steel pipe concrete pillow formula ballastless track.
Background
In the existing ballastless track structure cast-in-place by adopting the prefabricated sleeper, three types of ballastless tracks, namely a short sleeper type ballastless track, a long sleeper type ballastless track and a double-block type ballastless track, are mainly adopted.
Wherein, although the short sleeper has low cost, the geometric shape and position holding capacity of the track is poor, and the short sleeper cannot meet higher technical requirements.
The prestressed long sleeper can better ensure the geometric accuracy of a track structure, the integrity of the track panel is better, and the track accuracy is easy to control in a small-radius curve section. However, the sleeper penetrates through the longitudinal structural ribs of the track bed, the construction is complex, the bonding performance of the reinforcing steel bars in the holes and the track bed is poor, the vibration under the sleeper is insufficient, the contact surfaces of new and old concrete are more, the interface cracks are relatively more, and the integrity of the track bed is not very good.
The double-block sleeper mainly depends on the truss muscle to connect two concrete sleeper blocks, the track geometry shape and position holding ability is strong, the track bed integrity is good, but the processing cost is high, the truss muscle is easy to rust, it is used in urban rail transit, the fabrication cost is higher.
SUMMERY OF THE UTILITY MODEL
At least one in defect or improvement demand more than prior art, the utility model provides a steel pipe concrete pillow formula ballastless track has restricted the removal of railway roadbed board through set up the boss on recess, base on the railway roadbed board, has increased the area of contact of railway roadbed board and base, has improved track structure's wholeness. Meanwhile, the thickness of the base is reduced to some extent, and the height of the track structure is reduced. The rubber vibration damping pad added between the ballast bed plate and the base ensures the vibration damping performance of the track structure, so that the novel ballastless track structure can be applied to the urban rail transit field with higher requirements on the environment. The elastic base plate arranged between the groove of the ballast bed plate and the boss of the base can enhance the vibration reduction performance and also play a role in buffering, and the adverse effect of stress concentration on the track structure is reduced.
For realizing above-mentioned purpose, according to the utility model discloses an aspect provides a concrete filled steel tube pillow formula ballastless track, including base, railway roadbed board, the two formula sleepers of concrete filled steel tube, its characterized in that:
a plurality of grooves which are sunken upwards are arranged at intervals along the longitudinal direction of the track and extend along the transverse direction of the track, and the grooves are positioned between two adjacent steel pipe concrete double-block sleepers;
the base is provided with a plurality of bosses protruding upwards and formed during self pouring, the grooves are formed during pouring of the ballast bed board on the bosses, and the shapes of the bosses and the grooves are matched to form a limiting structure so as to reduce the height of the base;
the length of the groove in the transverse direction of the track is set as follows: the two ends of the sleeper block are positioned in the length range of the sleeper block of the steel tube concrete double-block sleeper.
Preferably, a vibration damping layer is arranged between the base and the ballast bed plate.
Preferably, between the base and the track bed plate, in the areas other than the bosses/grooves, rubber damping pads are provided.
Preferably, a ring of elastic pad is disposed between the outer circumference of the boss and the inner circumference of the groove.
Preferably, a layer of foam board is arranged between the top surface of the boss and the inner concave surface of the groove.
Preferably, the joints of the rubber vibration damping pad and the elastic base plate and the joints of the rubber vibration damping pad and the foam plate are all adhered with adhesive tapes for reinforcement.
Preferably, the elastic backing plate is ethylene propylene diene monomer.
Preferably, the bottom of the steel pipe concrete double-block sleeper is provided with a U-shaped rib, and the U-shaped rib is poured into the track bed slab.
In order to achieve the above object, according to another aspect of the present invention, there is provided a method for constructing a concrete filled steel tube sleeper type ballastless track in a non-vibration-damping section, comprising the steps of:
firstly, chiseling the surface of a bridge, cleaning sundries on the surface of a structure, and cleaning the surface of the structure; setting out a base sideline through the control point, then binding reinforcing steel bars, and paying attention to the position of the boss during binding without influencing the installation of the boss template; after the boss template is installed, cleaning accumulated water and sundries in the boss template; vibrating the concrete, closely vibrating the periphery of the boss and trowelling the surface of the base; after maintenance, when the strength of the base concrete reaches a preset percentage of the design strength, cleaning the surfaces of the base and the boss;
removing sundries in the range of the track bed plate, and paving steel bars at the bottom layer of the track bed plate according to the CP III control point; then cleaning the prefabricated steel pipe concrete double-block type sleeper and putting the sleeper in place; after the track panel is coarsely adjusted, binding steel bars on the top layer of the track bed slab, and performing insulation detection; then, starting to install a ballast bed plate template; after the installation is finished, fine adjustment is carried out on the track panel, and after the center line and the elevation of the track are adjusted, the track panel is fixed; cleaning sundries in the range of the ballast bed plate, spraying water to wet a pouring surface, starting pouring ballast bed concrete, tamping, finishing and trowelling the exposed surface of the concrete; after the concrete is initially set, the transverse restraint is loosened; removing the track bed plate template after the compressive strength of the track bed plate concrete reaches the preset strength;
and thirdly, maintaining the track structure after removing the track bed plate template.
In order to achieve the above object, according to another aspect of the present invention, there is provided a method for constructing a concrete filled steel tube sleeper type ballastless track at a vibration damping section, comprising the steps of:
firstly, chiseling the surface of a bridge, cleaning sundries on the surface of a structure, and cleaning the surface of the structure; setting out a base sideline through the control point, then binding reinforcing steel bars, and paying attention to the position of the boss during binding without influencing the installation of the boss template; after the boss template is installed, cleaning accumulated water and sundries in the boss template; vibrating the concrete, closely vibrating the periphery of the boss and trowelling the surface of the base; after maintenance, when the strength of the base concrete reaches a preset percentage of the design strength, cleaning the surfaces of the base and the boss;
secondly, drawing a side line according to the position of the boss, cutting the rubber damping pad according to the drawn line, and laying the rubber damping pad; sticking an elastic backing plate on the side surface of the boss, sticking a foam plate on the top of the boss, and fixing the foam plate by using an adhesive tape;
thirdly, removing sundries in the range of the track bed board, and paving the reinforcing steel bars at the bottom layer of the track bed board according to the CP III control point; then cleaning the prefabricated steel pipe concrete double-block type sleeper and putting the sleeper in place; after the track panel is coarsely adjusted, binding steel bars on the top layer of the track bed slab, and performing insulation detection; then, starting to install a ballast bed plate template; after the installation is finished, fine adjustment is carried out on the track panel, and after the center line and the elevation of the track are adjusted, the track panel is fixed; cleaning sundries in the range of the ballast bed plate, spraying water to wet a pouring surface, starting pouring ballast bed concrete, tamping, finishing and trowelling the exposed surface of the concrete; after the concrete is initially set, the transverse restraint is loosened; removing the track bed plate template after the compressive strength of the track bed plate concrete reaches the preset strength;
and fourthly, maintaining the track structure after the track bed plate template is removed.
The above-described preferred features may be combined with each other as long as they do not conflict with each other.
Generally, through the utility model discloses above technical scheme who conceives compares with prior art, has following beneficial effect:
1. the utility model discloses a steel pipe concrete pillow formula ballastless track through set up the boss on recess, base on the bed board, has restricted the removal of bed board, has increased the area of contact of bed board and base, has improved track structure's wholeness. Meanwhile, the thickness of the base is reduced to some extent, and the height of the track structure is reduced.
2. The utility model discloses a steel pipe concrete pillow formula ballastless track, the rubber damping pad that increases between bed board and base has guaranteed track structure's damping performance for novel ballastless track structure can be applied to the higher urban rail transit field of requirement to the environment. The elastic base plate arranged between the groove of the ballast bed plate and the boss of the base can enhance the vibration reduction performance and also play a role in buffering, and the adverse effect of stress concentration on the track structure is reduced.
3. The utility model discloses a concrete filled steel tube pillow formula ballastless track adopts the concrete filled steel tube sleeper among the track structure, and the sleeper passes through the concrete filled steel tube and connects for the track structure keeps the ability reinforcing of geometry position, and the U type muscle that sets up bottom the sleeper has simultaneously strengthened the connection performance of sleeper and bed board, makes the track structure wholeness strengthened. Compared with the traditional double-block type ballastless track structure, the novel ballastless track structure has the advantages that the cost is reduced to some extent by adopting the steel pipe concrete member with mature technology.
Drawings
Fig. 1 is a schematic plan view of a concrete filled steel tube sleeper-type ballastless track according to an embodiment of the present invention;
fig. 2 is a schematic plan view of a track bed plate and a groove of a concrete filled steel tube sleeper-type ballastless track according to an embodiment of the present invention;
fig. 3 is a schematic view of a bed plate and a base flat longitudinal section of a concrete filled steel tube sleeper-type ballastless track according to an embodiment of the present invention;
fig. 4 is a schematic cross-sectional view of a base boss and a bed plate groove of a concrete filled steel tube sleeper-type ballastless track according to an embodiment of the present invention;
FIG. 5 is an enlarged partial schematic view of FIG. 4;
FIG. 6 is a side view of the resilient pad of FIG. 2 at side A of the groove;
FIG. 7 is a side view of the resilient pad of FIG. 2 at side B of the groove;
fig. 8 is a schematic diagram of a foam board of a concrete filled steel tube sleeper-type ballastless track according to the embodiment of the present invention.
The dimensions in the figure are in mm.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention. Furthermore, the technical features mentioned in the embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other. The present invention will be described in further detail with reference to the following embodiments.
As shown in fig. 1-8, the utility model provides a concrete filled steel tube pillow formula ballastless track, include from supreme lower part basis, base 1, bed board 2, the two formula sleepers 3 of concrete filled steel tube that set gradually down. The method is divided into two schemes of a common section (a non-vibration-damping section) and a vibration-damping section.
Concrete filled steel tube sleeper type ballastless track of common section I
As shown in fig. 1-2, a plurality of grooves 21 recessed upwards are formed in the lower portion of the track bed plate 2 and are arranged at intervals along the longitudinal direction of the track, and the grooves 21 extend along the transverse direction of the track and are located between two adjacent steel pipe concrete double-block sleepers 3.
The base 1 is provided with a plurality of bosses 11 protruding upwards, wherein the bosses 11 are formed during pouring, the grooves 21 are formed during pouring of the ballast bed plate 2 on the bosses 11, and the shapes of the bosses and the grooves are matched to form a limiting structure, so that the height of the base 1 is reduced.
The length of the groove 21 in the track transverse direction is set as follows: the two ends of the steel tube concrete double-block sleeper are positioned in the length range of the sleeper block of the steel tube concrete double-block sleeper 3.
Preferably, the bottom of the steel pipe concrete double-block sleeper 3 is provided with a U-shaped rib, and the U-shaped rib is poured into the track bed slab 2.
In particular, the track bed plate is provided with a groove structure which can improve the integrity of the track structure and limit the displacement of the track structure under the combined action of the groove structure and the lug boss. The method specifically comprises the following steps: for a track bed plate with the length of 4.88m, 3 trapezoidal grooves with the same size and depth of 93mm are arranged between sleeper blocks, the distance between the grooves is 1.25m, the size of the groove close to the bottom of a track bed is 225mm multiplied by 1225mm, and the size of the groove in the track bed is 200mm multiplied by 1200 mm.
A prismatic table-shaped boss with the height of 132mm is arranged at the position, corresponding to the groove of the ballast bed plate, on the base, the lower surface of the boss is 225mm multiplied by 1225mm, and the upper surface of the boss is 200mm multiplied by 1200 mm.
The construction method in the non-vibration-damping area comprises the following steps:
1. the bridge surface is roughened, sundries on the structure surface are cleaned, and the surface of the bridge is cleaned by high-pressure water or high-pressure air. Carry out 1 sideline lofting of base through the control point, then carry out reinforcement, need pay attention to 11 positions of boss during the ligature, do not influence the installation of boss template. After the boss template is installed, accumulated water and sundries in the boss template are cleaned up. The concrete is vibrated by an inserted drum tamping bar, the periphery of the boss 11 needs to be vibrated compactly, and the surface of the base 1 is trowelled. After maintenance, when the strength of the base concrete reaches 75% of the design strength, the surfaces of the base 1 and the boss 11 are cleaned.
2. Removing impurities in the range of the track bed plate 2, and paving the reinforcing steel bars at the bottom layer of the track bed plate according to the CP III control point. And then cleaning the prefabricated steel pipe concrete double-block type sleeper 3 and putting in place. After the track panel is coarsely adjusted, the top layer steel bars of the track bed board 2 are bound, and insulation detection is carried out. Subsequently, the installation of the ballast bed slab formwork is started. After the installation is finished, the track panel is finely adjusted, and after the center line and the elevation of the track are adjusted, the track panel is fixed. Cleaning sundries in the range of the ballast bed plate 2, spraying water to wet the casting surface, starting to cast ballast bed concrete and tamping, and timely finishing and trowelling the exposed surface of the concrete. After the concrete is initially set, the transverse restraint is released. And (4) removing the track bed plate template after the concrete compressive strength of the track bed plate reaches 5 MPa.
3. And (5) maintaining the track structure after removing the track bed plate template.
Concrete filled steel tube sleeper type ballastless track of vibration reduction section
On the basis of the foregoing, except that, as shown in fig. 3-8, preferably, a damping layer is provided between the base 1 and the track bed slab 2. The damping layer comprises a rubber damping pad 4, an elastic backing plate 5 and a foam plate 6. In the vibration damping section, the size of the groove is relatively enlarged under the condition that the size of the boss is not changed due to the addition of the vibration damping layer.
Preferably, between the base 1 and the track bed plate 2, in areas other than the bosses 11/grooves 21, rubber damping pads 4 are provided.
Preferably, a ring of elastic pad plates 5 are provided between the outer circumference of the boss 11 and the inner circumference of the groove 21.
Preferably, a layer of foam sheet 6 is provided between the top surface of the boss 11 and the inner concave surface of the recess 21.
Preferably, the joints of the rubber vibration damping pad 4 and the elastic base plate 5 and the joints of the rubber vibration damping pad 4 and the foam plate 6 are all adhered with adhesive tapes 7 for reinforcement.
Preferably, the elastic pad 5 is ethylene propylene diene monomer.
Specifically, in order to improve the vibration damping performance of the track structure, a vibration damping material is additionally arranged between the ballast bed plate and the base. The method specifically comprises the following steps: the rubber damping pad is arranged at the contact position of the track bed plate and the base, the width of the damping pad is aligned with the track bed plate, the thickness of the damping pad is 27mm, and the static rigidity is 2 of 0.03 +/-0.005N/mm. An elastic base plate is arranged between the base limiting boss and the contact surface around the track bed plate groove, so that the damping effect is enhanced and the buffering effect is achieved. The elastic base plate is made of ethylene propylene diene monomer rubber, the thickness of the elastic base plate is 8mm, and one side of the elastic base plate is provided with a bulge for preventing the elastic base plate from jumping out. A foam board with the thickness of 10mm is arranged between the contact surface of the base limiting boss and the upper part of the ballast bed board groove.
The construction method in the vibration damping area comprises the following steps:
1. the bridge surface is roughened, sundries on the structure surface are cleaned, and the surface of the bridge is cleaned by high-pressure water or high-pressure air. Carry out 1 sideline lofting of base through the control point, then carry out reinforcement, need pay attention to 11 positions of boss during the ligature, do not influence the installation of boss template. After the boss template is installed, accumulated water and sundries in the boss template are cleaned up. The concrete is vibrated by an inserted drum tamping bar, the periphery of the boss 11 needs to be vibrated compactly, and the surface of the base 1 is trowelled. After maintenance, when the strength of the base concrete reaches 75% of the design strength, the surfaces of the base 1 and the boss 11 are cleaned.
2. Drawing a sideline according to the position of the boss 11, cutting the rubber damping pad 4 according to the drawn line, and laying the rubber damping pad. When in laying, the steel wire should be smooth, without folds and damage, and the joints are butted and cannot be overlapped. As shown in FIG. 3, the elastic pad 5 is stuck to the side surface of the boss 11, and the foam plate 6 is stuck to the top surface, and the foam plate is fixed by the tape 7 without bubbling or separation.
3. Removing impurities in the range of the track bed plate 2, and paving the reinforcing steel bars at the bottom layer of the track bed plate according to the CP III control point. And then cleaning the prefabricated steel pipe concrete double-block type sleeper 3 and putting in place. After the track panel is coarsely adjusted, the top layer steel bars of the track bed board 2 are bound, and insulation detection is carried out. Subsequently, the installation of the ballast bed slab formwork is started. After the installation is finished, the track panel is finely adjusted, and after the center line and the elevation of the track are adjusted, the track panel is fixed. Cleaning sundries in the range of the ballast bed plate 2, spraying water to wet the casting surface, starting to cast ballast bed concrete and tamping, and timely finishing and trowelling the exposed surface of the concrete. After the concrete is initially set, the transverse restraint is released. And (4) removing the track bed plate template after the concrete compressive strength of the track bed plate reaches 5 MPa.
4. And (5) maintaining the track structure after removing the track bed plate template.
To sum up, compare with prior art, the utility model discloses a scheme exists following apparent advantage:
1. the utility model discloses a steel pipe concrete pillow formula ballastless track through set up the boss on recess, base on the bed board, has restricted the removal of bed board, has increased the area of contact of bed board and base, has improved track structure's wholeness. Meanwhile, the thickness of the base is reduced to some extent, and the height of the track structure is reduced.
2. The utility model discloses a steel pipe concrete pillow formula ballastless track, the rubber damping pad that increases between bed board and base has guaranteed track structure's damping performance for novel ballastless track structure can be applied to the higher urban rail transit field of requirement to the environment. The elastic base plate arranged between the groove of the ballast bed plate and the boss of the base can enhance the vibration reduction performance and also play a role in buffering, and the adverse effect of stress concentration on the track structure is reduced.
3. The utility model discloses a concrete filled steel tube pillow formula ballastless track adopts the concrete filled steel tube sleeper among the track structure, and the sleeper passes through the concrete filled steel tube and connects for the track structure keeps the ability reinforcing of geometry position, and the U type muscle that sets up bottom the sleeper has simultaneously strengthened the connection performance of sleeper and bed board, makes the track structure wholeness strengthened. Compared with the traditional double-block type ballastless track structure, the novel ballastless track structure has the advantages that the cost is reduced to some extent by adopting the steel pipe concrete member with mature technology.
It will be appreciated that the embodiments of the system described above are merely illustrative, in that elements illustrated as separate components may or may not be physically separate, may be located in one place, or may be distributed over different network elements. Some or all of the modules can be selected according to actual needs to achieve the purpose of the scheme of the embodiment. One of ordinary skill in the art can understand and implement it without inventive effort.
In addition, it should be understood by those skilled in the art that in the specification of the embodiments of the present invention, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
In the description of the embodiments of the present invention, a large number of specific details are explained. It is understood, however, that embodiments of the invention may be practiced without these specific details. In some instances, well-known methods, structures and techniques have not been shown in detail in order not to obscure an understanding of this description. Similarly, it should be appreciated that in the foregoing description of exemplary embodiments of the invention, various features of the embodiments of the invention are sometimes grouped together in a single embodiment, figure, or description thereof for the purpose of streamlining the disclosure and aiding in the understanding of one or more of the various inventive aspects.
However, the disclosed method should not be interpreted as reflecting an intention that: rather, the claimed embodiments of the invention require more features than are expressly recited in each claim. Rather, as the following claims reflect, inventive aspects lie in less than all features of a single foregoing disclosed embodiment. Thus, the claims following the detailed description are hereby expressly incorporated into this detailed description, with each claim standing on its own as a separate embodiment of an embodiment of this invention.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solutions of the embodiments of the present invention, and not to limit the same; although the embodiments of the present invention have been described in detail with reference to the foregoing embodiments, it should be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.

Claims (8)

1. The utility model provides a concrete filled steel tube pillow formula ballastless track, includes base (1), bed board (2), the two formula sleepers of concrete filled steel tube (3), its characterized in that:
a plurality of grooves (21) which are sunken upwards are formed in the lower portion of the track bed plate (2) and are arranged at intervals along the longitudinal direction of the track, and the grooves (21) extend along the transverse direction of the track and are positioned between two adjacent steel pipe concrete double-block sleepers (3);
the base (1) is provided with a plurality of bosses (11) which are protruded upwards and formed when the base is poured, the grooves (21) are formed when the roadbed slab (2) is poured on the bosses (11), and the shapes of the bosses and the bosses are matched to form a limiting structure, so that the height of the base (1) is reduced;
the length of the groove (21) in the transverse direction of the track is set as follows: the two ends of the steel tube concrete double-block sleeper (3) are positioned in the length range of the sleeper blocks of the steel tube concrete double-block sleeper.
2. The steel pipe concrete sleeper-type ballastless track of claim 1, wherein:
a vibration damping layer is arranged between the base (1) and the track bed plate (2).
3. The steel pipe concrete sleeper-type ballastless track of claim 2, wherein:
a rubber vibration damping pad (4) is arranged between the base (1) and the track bed plate (2) in the area except for the lug boss (11)/the groove (21).
4. The steel pipe concrete sleeper-type ballastless track of claim 3, wherein:
and a circle of elastic cushion plate (5) is arranged between the outer periphery of the boss (11) and the inner periphery of the groove (21).
5. The steel pipe concrete sleeper-type ballastless track of claim 4, wherein:
and a layer of foam plate (6) is arranged between the top surface of the boss (11) and the inner concave surface of the groove (21).
6. The steel pipe concrete sleeper-type ballastless track of claim 5, wherein:
the rubber vibration damping pad (4) and the joint of the elastic base plate (5) and the rubber vibration damping pad (4) and the joint of the foam plate (6) are all pasted with adhesive tapes (7) for reinforcement.
7. The steel pipe concrete sleeper-type ballastless track of claim 4, wherein:
the elastic backing plate (5) is made of ethylene propylene diene monomer.
8. The steel pipe concrete sleeper-type ballastless track of claim 1, wherein:
the bottom of the steel pipe concrete double-block sleeper (3) is provided with U-shaped ribs, and the U-shaped ribs are poured into the track bed slab (2).
CN202021668330.5U 2020-08-11 2020-08-11 Concrete filled steel tube sleeper type ballastless track Active CN212247675U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021668330.5U CN212247675U (en) 2020-08-11 2020-08-11 Concrete filled steel tube sleeper type ballastless track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021668330.5U CN212247675U (en) 2020-08-11 2020-08-11 Concrete filled steel tube sleeper type ballastless track

Publications (1)

Publication Number Publication Date
CN212247675U true CN212247675U (en) 2020-12-29

Family

ID=73981544

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021668330.5U Active CN212247675U (en) 2020-08-11 2020-08-11 Concrete filled steel tube sleeper type ballastless track

Country Status (1)

Country Link
CN (1) CN212247675U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114016335A (en) * 2021-12-02 2022-02-08 南京铁道职业技术学院 Ballastless track plate and production method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114016335A (en) * 2021-12-02 2022-02-08 南京铁道职业技术学院 Ballastless track plate and production method thereof

Similar Documents

Publication Publication Date Title
CN207452594U (en) A kind of urban track traffic prestressing force slab track
CN108951306B (en) Ballast track bed and construction method thereof
CN101063289A (en) City-rail steel spring floating slab rail bed railroad switch construction method
CN109183530B (en) Line temporary overhead device and method for ballastless track disease remediation
CN212247675U (en) Concrete filled steel tube sleeper type ballastless track
JP2002227101A (en) Sleeper-integrated concrete ballast structure for railway line
CN108797228A (en) A kind of continuous supporting track structure of assemblyization and its construction, maintaining method
CN111877052A (en) Steel pipe concrete sleeper type ballastless track and construction method thereof
CN101967782A (en) Ladder-shaped rail construction method for urban rail transit
CN101177926A (en) City railway trapezoidal crosstie vibration-damping ballast construction method
CN107354826B (en) The rapid constructing method of tunnel built-in type rail system
CN110158982B (en) Concrete beam refitting structure and method based on bolt positioning structure
US4576510A (en) Technique for the location of expansion joints when casting a concrete bed
KR20020082728A (en) Process and frame for substituting steel girder of a railway bridge for concrete slab
JP3863142B2 (en) Paved road repair method
JP3566704B2 (en) Reinforcement structure of existing railway bridge
CN210826938U (en) Track structure suitable for urban rail transit construction is supporting 8 types track board
CN210134295U (en) Plate-type track system
CN114351926A (en) Anti-floating construction method for metal square box cast-in-place concrete hollow floor slab
CN114411551A (en) Bridge deck structure and express way maintenance construction process
CN210563525U (en) Concrete beam modified structure based on bolt positioning structure
JP3788774B2 (en) Railroad track structure and railroad track construction method
JPH07259001A (en) Strengthening construction method for existing ballast roadbed track
CN112030613A (en) Assembly type floating plate track structure adaptive to traveling direction
PL205126B1 (en) Method of placing a bituminous lagging in vicinity of a bus bar and apparatus therefor

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant