CN209653088U - A kind of novel transformer substation flood control drainage arrangement - Google Patents

A kind of novel transformer substation flood control drainage arrangement Download PDF

Info

Publication number
CN209653088U
CN209653088U CN201821966681.7U CN201821966681U CN209653088U CN 209653088 U CN209653088 U CN 209653088U CN 201821966681 U CN201821966681 U CN 201821966681U CN 209653088 U CN209653088 U CN 209653088U
Authority
CN
China
Prior art keywords
water
steel pipe
drainage arrangement
level gauge
flood control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821966681.7U
Other languages
Chinese (zh)
Inventor
陈红
闫辉
管维亚
丁锐
南开辉
童小东
李国文
刘迪
薛韬
沈高锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
Southeast University
Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University, Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd filed Critical Southeast University
Priority to CN201821966681.7U priority Critical patent/CN209653088U/en
Application granted granted Critical
Publication of CN209653088U publication Critical patent/CN209653088U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/30Flood prevention; Flood or storm water management, e.g. using flood barriers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/20Controlling water pollution; Waste water treatment

Landscapes

  • Control Of Non-Electrical Variables (AREA)

Abstract

The utility model relates to a kind of novel transformer substation flood control drainage arrangements, the drainage arrangement includes collecting-tank, water level monitoring device, drainage arrangement and steel pipe, the collecting-tank is built along substation's enclosure wall, the water-level detecting device is arranged in steel pipe, the drainage arrangement, steel pipe are arranged in collecting-tank, the water level monitoring device includes the first water-level gauge and the second water-level gauge, and first water-level gauge and the second water-level gauge are arranged in steel pipe;The utility model device have many advantages, such as relatively high precision, simple structure, occupy little space, cost is lower, is easily installed, and water discharging part setting rationally, can effectively solve because short time a large amount of precipitation bring transformer substation accumulated waters and rainwater reverse irrigation the problems such as.

Description

A kind of novel transformer substation flood control drainage arrangement
Technical field
The utility model relates to a kind of drainage arrangements, and in particular to a kind of novel transformer substation flood control drainage arrangement belongs to change Power station flood control safety engineering device technique field.
Background technique
With the fast development of Urbanization in China, demand, power supply reliability of the urban development to electric power are proposed more High requirement is also stepping up the security consideration of substation's construction.
Substation is built in field mostly, and ambient enviroment is severe, and the substation for being built in mountain area, lake or river region comes It says, situation is especially severe.Greatly due to topography variation, it has inconvenient traffic, therefore the difficulty of on duty or inspection work is all very big.For becoming When flood control measure only depends on the flood control measure of site absolute altitude or site tidal channel etc. itself for power station, the flood control of substation Safety suffers from into the side of body, it is therefore necessary to which the flood control and drainage project for improving itself just can ensure that the flood control safety of substation.
With the high speed development of science and technology, unattended intelligent substation greatly reduces people using more and more extensive Work cost, improves production efficiency, particularly suitable for the popularization and use of above-mentioned zone.But the precipitation of above-mentioned zone is big, especially When encountering typhoon or strong convective weather, often there is the case where precipitation is concentrated in the short time, therefore for intelligent substation, Flood control is particularly important.
For at present, two problems are primarily present in above-mentioned zone, when precipitation is big and concentrates: first, in substation Portion can rapid ponding, common gutter drainage speed be lower than ponding speed.Second, stand outside water level increase when can also pass through station Internal drainage mouth flows backward, and jeopardizes the safe operation of the electric power facilities such as distribution box.Meanwhile under exceedingly odious weather, operation maintenance personnel is caught up with Going to scene, there is also very big security risks, therefore, on the basis of intelligent substation possesses good development prospect, how The safety that can ensure substation needs us to constantly improve our current flood control drainage measures.
Summary of the invention
The utility model exactly for the technical problems in the prior art, provides a kind of novel transformer substation flood control draining Device, the technical solution precision is relatively high, simple structure, occupy little space, cost is lower, is easily installed.
To achieve the goals above, the technical solution of the utility model is as follows, a kind of novel transformer substation flood control drainage arrangement, The drainage arrangement includes collecting-tank, water level monitoring device, drainage arrangement and steel pipe, and the collecting-tank is along substation's enclosure wall It builds, the water-level detecting device is arranged in steel pipe, and the drainage arrangement, steel pipe are arranged in collecting-tank.
As a kind of improvement of the utility model, the water level monitoring device includes the first water-level gauge and the second water-level gauge, First water-level gauge and the second water-level gauge are arranged in steel pipe.
As a kind of improvement of the utility model, the steel pipe is provided in round steel pipe, is provided on the round steel pipe Aperture.
As a kind of improvement of the utility model, the drainage arrangement includes the first water pump, the second water pump and drainpipe, First water pump connects the first water-level gauge, and the second water pump connects the second water-level gauge, the first water pump and the second water pump with draining Pipe 6 is connected and extends to outside substation's enclosure wall.
As a kind of improvement of the utility model, the bottom of the round steel pipe is provided with grenadine, and steel pipe has anticorrosion Characteristic, bottom are equipped with grenadine, prevent sundries from entering.
As a kind of improvement of the utility model, the bottom of the round steel pipe is provided with steel pipe support, is used to support circle Shape steel pipe.
As a kind of improvement of the utility model, the elevation of bottom of the collecting-tank is lower than substation's ground elevation, is in Closed state, excess surface water can enter from water inlet and water inlet position is slightly above substation's ground elevation.
As a kind of improvement of the utility model, first water-level gauge and the second water level are calculated as parallel connection, and are all provided with Terminals there are two setting usually are in off-state, when water level rises, pass through water conduction, connection circuit;Two water-level gauge independences Work, it is mutually interference-free.
Compared with the existing technology, the utility model has the following advantages that, 1) the utility model device has precision relatively Height, simple structure, occupy little space, cost is lower, the advantages that being easily installed, and water discharging part setting is rationally, can effectively solve The problems such as flowing backward because of short time a large amount of precipitation bring transformer substation accumulated waters and rainwater;2) in the program, the bottom of round steel pipe is set It is equipped with grenadine, steel pipe has anti-corrosion property, and bottom is equipped with grenadine, prevents sundries from entering;3) first water-level gauge and second Water level is calculated as parallel connection, and is respectively provided with there are two terminals, is usually in off-state, when water level rises, by water conduction, Connection circuit;Two water-level gauges work independently, mutually interference-free.
Detailed description of the invention:
Fig. 1 is the utility model overall structure diagram;
Fig. 2 is utility model works schematic illustration;
In figure: the first water-level gauge of 1-;The second water-level gauge of 2-;3- round steel pipe;The first water pump of 4-;The first water pump of 5-;6- row Water pipe;7- collecting-tank;8- water inlet;9- substation ground;10- substation enclosure wall;11- pumping drainage mouth;12- steel mesh yarn; 13- steel pipe support.
Specific embodiment:
In order to deepen the understanding to the utility model, the present embodiment is described in detail with reference to the accompanying drawing.
Embodiment 1: referring to Fig. 1,2, a kind of novel transformer substation flood control drainage arrangement, the drainage arrangement include collecting-tank 7, Water level monitoring device, drainage arrangement and steel pipe, the collecting-tank are built along substation's enclosure wall 10, the water-level detecting device It is arranged in steel pipe 3, the drainage arrangement, steel pipe are arranged in collecting-tank 7.The water level monitoring device includes the first water-level gauge 1 and second water-level gauge 2, first water-level gauge 1 and the second water-level gauge 2 be arranged in steel pipe 3, the steel pipe is provided in round steel It manages, is provided with aperture on the round steel pipe, carries out aperture on the upside of round tube in the program, pressure is consistent inside and outside holding.
The drainage arrangement includes the first water pump 4, the second water pump 5 and drainpipe 6, the connection of the first water pump 4 first Water-level gauge 1, the second water pump 5 connect the second water-level gauge 2, and the first water pump and the second water pump are connected with drainpipe 6 and extend to change Outside power station enclosure wall 10.
Embodiment 2: referring to Fig. 1,2, as a kind of improvement of the utility model, the bottom of the round steel pipe is provided with net Yarn 12, steel pipe have anti-corrosion property, and bottom is equipped with grenadine, prevents sundries from entering, the bottom of the round steel pipe is provided with steel Pipe holder 13, is used to support round steel pipe.Remaining structure and advantage are identical with embodiment 1.
Embodiment 3: referring to Fig. 1,2, as a kind of improvement of the utility model, the elevation of bottom of the collecting-tank is lower than change Power station ground elevation is in closed state, and excess surface water can enter from water inlet and water inlet position is slightly above power transformation It stands ground elevation.Remaining structure and advantage are identical with embodiment 1.
Embodiment 4: referring to Fig. 1,2, as a kind of improvement of the utility model, first water-level gauge and the second water-level gauge For parallel connection, and it is respectively provided with that there are two terminals, wherein the second water-level gauge is higher than the first water-level gauge, is usually in off-state, When water level rises, pass through water conduction, connection circuit;Two water-level gauges work independently, mutually interference-free.I.e. when water level rises When to the first water-level gauge position, the first terminals of water-level gauge two trigger the first water pump, the first water by water conductive communication circuit Pump starts to carry out drainage works;If water level continuously rises at the second water-level gauge position, the electricity of the second water-level gauge and the second water pump Road connection, the second water pump start to carry out drainage works.Remaining structure and advantage are identical with embodiment 1.
Working principle: it catchments as shown in the flood control drainage arrangement figure and working principle diagram of Fig. 1 and Fig. 2 referring to Fig. 1, Fig. 2 Pond 7 is built along substation's enclosure wall 10, and collecting-tank is closed state, when substation ground 9 starts ponding, excess surface water Entered by the water inlet 8 of collecting-tank, the position of water inlet 8 is slightly above substation's ground level.Steel pipe support 13 with holes is solid Be scheduled on bottom of pond portion of catchmenting, steel pipe bottom is equipped with grenadine 12, the water of collecting-tank entered by steel pipe bottom and keep in collecting-tank Same SEA LEVEL VARIATION.First water-level gauge 1 and the second water-level gauge 2 are installed in inside steel pipe frame, are set there are two terminals, are in Off-state, water-level gauge are connected with water pump.As shown in Fig. 2, two water-level gauges are in parallel connection.When in collecting-tank water level inside It rises, is connected to the first water-level gauge 1 first, water is discharged from discharge outlet 11 by drainpipe 6 for the starting of the first water pump 4.When water level into One step rises at the second water-level gauge 2, and the second water pump 5 automatically turns on, and participates in drainage works.Pumping drainage makes water level in collecting-tank Decline, so that the first water-level gauge and the second water-level gauge are in off-state in anhydrous situation, water pump stops working.
It should be noted that above-described embodiment, is not used to limit the protection scope of the utility model, in above-mentioned technical side Made equivalents or substitution each fall within range protected by the claims of this utility model on the basis of case.

Claims (8)

1. a kind of novel transformer substation flood control drainage arrangement, which is characterized in that the drainage arrangement includes collecting-tank, water level monitoring dress Set, drainage arrangement and steel pipe, the collecting-tank are built along substation's enclosure wall, the water-level detecting device is arranged in steel pipe In, the drainage arrangement, steel pipe are arranged in collecting-tank.
2. a kind of novel transformer substation flood control drainage arrangement according to claim 1, which is characterized in that the water level monitoring dress It sets including the first water-level gauge and the second water-level gauge, first water-level gauge and the second water-level gauge are arranged in steel pipe.
3. a kind of novel transformer substation flood control drainage arrangement according to claim 2, which is characterized in that the steel pipe is set as Round steel pipe is provided with aperture on the round steel pipe.
4. a kind of novel transformer substation flood control drainage arrangement according to claim 3, which is characterized in that the drainage arrangement packet The first water pump, the second water pump and drainpipe are included, first water pump connects the first water-level gauge, and the second water pump connects the second water level Meter, the first water pump and the second water pump are connected with drainpipe and extend to outside substation's enclosure wall.
5. a kind of novel transformer substation flood control drainage arrangement according to claim 4, which is characterized in that the round steel pipe Bottom is provided with grenadine.
6. a kind of novel transformer substation flood control drainage arrangement according to claim 5, which is characterized in that the round steel pipe Bottom is provided with steel pipe support, is used to support round steel pipe.
7. a kind of novel transformer substation flood control drainage arrangement according to claim 6, which is characterized in that the bottom of the collecting-tank Portion's absolute altitude is lower than substation's ground elevation, is in closed state.
8. a kind of novel transformer substation flood control drainage arrangement according to claim 6 or 7, which is characterized in that first water Position meter and the second water level are calculated as parallel connection, and are respectively provided with there are two terminals.
CN201821966681.7U 2018-11-27 2018-11-27 A kind of novel transformer substation flood control drainage arrangement Expired - Fee Related CN209653088U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821966681.7U CN209653088U (en) 2018-11-27 2018-11-27 A kind of novel transformer substation flood control drainage arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821966681.7U CN209653088U (en) 2018-11-27 2018-11-27 A kind of novel transformer substation flood control drainage arrangement

Publications (1)

Publication Number Publication Date
CN209653088U true CN209653088U (en) 2019-11-19

Family

ID=68517167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821966681.7U Expired - Fee Related CN209653088U (en) 2018-11-27 2018-11-27 A kind of novel transformer substation flood control drainage arrangement

Country Status (1)

Country Link
CN (1) CN209653088U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113775031A (en) * 2021-09-10 2021-12-10 朱海龙 Intelligent water-absorbing disaster-preventing fire fighting emergency equipment for large flood prevention dragon
CN113982091A (en) * 2021-11-19 2022-01-28 国网冀北电力有限公司唐山供电公司 Novel transformer substation field area intelligent drainage system and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113775031A (en) * 2021-09-10 2021-12-10 朱海龙 Intelligent water-absorbing disaster-preventing fire fighting emergency equipment for large flood prevention dragon
CN113982091A (en) * 2021-11-19 2022-01-28 国网冀北电力有限公司唐山供电公司 Novel transformer substation field area intelligent drainage system and method

Similar Documents

Publication Publication Date Title
CN104264771B (en) Emergence treating method and the pre-front emergency disposal system of waterlogging before a kind of urban waterlogging is pre-
CN204139290U (en) Emergency disposal system before a kind of urban waterlogging is pre-
CN209653088U (en) A kind of novel transformer substation flood control drainage arrangement
JP6873444B2 (en) A system that uses the energy storage pipes of multiple high-rise buildings to generate electricity
CN102410132B (en) Open-channel rainwater generating system and method
CN102277863A (en) Method for circularly generating power with seawater and comprehensively utilizing seawater under action of artificial sea level fall
CN109060062B (en) Inner-barrel-limiting irrigation water quantity metering device
CN201588294U (en) Backflow-preventing type drainage structure of circulating water pump room
CN104454302A (en) High-rise rainwater collection device
CN111487389A (en) Surface runoff monitoring devices with adjustable soil and water conservation is used
CN207228278U (en) A kind of intelligent city builds rain recycling system
CN208949850U (en) A kind of draining of pipe well combination wind-light-electricity complementary changes salt system
CN110541389A (en) flood control and flood fighting emergency system in construction period and early warning method thereof
CN107942988B (en) Intelligent canal management system
CN205537843U (en) Urban waterlogging automatic monitoring station
CN104807517A (en) Monitoring system for automatically measuring water from open channel in irrigation area
CN209670037U (en) Cable hand wellhole self-draining arrangement
CN211849316U (en) Ecological flow facility of formula power station behind dam of compromise benefit and monitoring demand
CN204125968U (en) The anti-water collecting device of a kind of cable shaft
CN109235392A (en) A kind of draining of pipe well combination wind-light-electricity complementary changes salt system and its application method
CN202381240U (en) Open flume type rainwater power generation system
CN208456765U (en) A kind of artesian water power generator
CN204881728U (en) Monitoring devices of irrigated area open channel water gaging
CN220150477U (en) Rain and sewage diversion well with controllable sewage discharge flow
CN206491093U (en) A kind of pumping plant irrigated for irrigation and water conservancy

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191119

Termination date: 20201127