CN209339629U - A kind of construction discharging platform - Google Patents

A kind of construction discharging platform Download PDF

Info

Publication number
CN209339629U
CN209339629U CN201822090150.2U CN201822090150U CN209339629U CN 209339629 U CN209339629 U CN 209339629U CN 201822090150 U CN201822090150 U CN 201822090150U CN 209339629 U CN209339629 U CN 209339629U
Authority
CN
China
Prior art keywords
fixed
girder
floor
supporting plate
workbench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822090150.2U
Other languages
Chinese (zh)
Inventor
郭强
马千里
金雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Qianli Science And Technology Development Co Ltd
Original Assignee
Beijing Qianli Science And Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Qianli Science And Technology Development Co Ltd filed Critical Beijing Qianli Science And Technology Development Co Ltd
Priority to CN201822090150.2U priority Critical patent/CN209339629U/en
Application granted granted Critical
Publication of CN209339629U publication Critical patent/CN209339629U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forklifts And Lifting Vehicles (AREA)

Abstract

The utility model relates to a kind of construction discharging platforms, including fixing card, fixed device, girder and workbench, the fixing card inlay card is on floor, the fixed device is fixed on the side of fixing card, described girder one end is protruded into floor and is fixed in fixing card by fixed device, the other end and workbench consolidate and stretch out floor, and the side that girder stretches out floor is arranged in the workbench.By the inlay card fixing card on floor, girder is fixed in fixing card, avoids and is punched on floor, floor is damaged.

Description

A kind of construction discharging platform
Technical field
The utility model relates to the technical fields of construction, more particularly, to a kind of construction discharging platform.
Background technique
Discharging platform is that various provisional stations are often set up in construction site, can be carried out various masonry finishings and painting etc. In general operation can be used to carry within certain duration material, and in the framework type platform for wherein carrying out various operations, claim Be operating platform, it is a variety of that operating platform is divided into movable operation platform, console mode and overhanging type operating platform, also referred to as Transfer platform.
Existing overhanging type discharging platform is monoblock type, includes girder and workbench, girder one end is fixed on floor On, the other end is affixed with workbench and stretches out floor, and staff carries out discharging on workbench.
Prior art among the above has the following deficiencies: and generally punches on floor, installs anchoring piece, passes through anchoring Girder is fixed on floor by part in this way, is punched, may be damaged on floor to floor, influences the steady of floor It is qualitative.
Utility model content
The purpose of the utility model is to provide a kind of construction discharging platform, avoid being punched on floor, it is right Floor damages.
The purpose of this utility model has the technical scheme that
A kind of construction discharging platform, including fixing card, fixed device, girder and workbench, the fixing card On floor, the fixed device is fixed on the side of fixing card inlay card, and described girder one end is protruded into floor and passed through admittedly Determine device to be fixed in fixing card, the other end and workbench consolidate and stretch out floor, and the workbench setting is stretched in girder The side of floor out.
By using above-mentioned technical proposal, when installing girder, first by fixing card inlay card on floor, then by girder It is fixed in fixing card by fixed device, fixing card can guarantee the stability of girder.It avoids and is punched on floor, The problem of floor is damaged.
The utility model is further arranged to: the fixing card includes first horizontal portion, the second horizontal part and vertical portion, institute It states first horizontal portion to abut with floor upper surface, second horizontal part is abutted with floor lower surface, the first horizontal portion Length is longer than the second horizontal part, and the vertical portion is fixed between first horizontal portion and the second horizontal part.
By using above-mentioned technical proposal, fixing card is arranged to U-shaped, inlay card that can be more stable is on floor, together When first horizontal portion be longer than the second horizontal part, the stress-bearing capability of fixing card can be increased, enable the branch that fixing card is more stable Support the cargo on girder and workbench.
The utility model is further arranged to: the fixed device is fixed on the lateral surface of first horizontal portion, institute Stating fixed device includes accommodating chamber, fixing bolt, spring and Fixed latches, and described accommodating chamber one end is fixed in first horizontal portion On, the fixing bolt passes through first horizontal portion and girder by accommodating chamber, and one end that the fixing bolt passes through girder is arranged There are Fixed latches, the Fixed latches are connected on the side wall of girder;The right side of the spring one end and accommodating chamber is affixed, separately One end is fixed on fixing bolt, and the spring is set in outside fixing bolt.
By using above-mentioned technical proposal, during installation, fixing bolt is passed through into first horizontal portion and girder, to fixed spiral shell Fixed latches are inserted on bolt, Fixed latches are pushed against on the side wall of girder, and girder is fixed in fixing card;In disassembly, directly It connects and extracts Fixed latches out, fixing bolt is automatically recycled to accommodating chamber under the action of the spring, has installation and removal convenient The advantages of.
The utility model is further arranged to: the fixing bolt includes nut, screw rod and fixed ring, and the fixed ring is solid Fixed to be arranged on screw rod, the spring is fixed in fixed ring far from one end of girder, and the fixed ring is located at nut Inside and outside accommodating chamber, the screw rod passes through first horizontal portion and girder, is opened up on the screw rod for Fixed latches insertion Through-hole, the Fixed latches are inserted on screw rod.
By using above-mentioned technical proposal, screw rod is passed through into first horizontal portion and girder, while fixation is plugged on screw rod Bolt, Fixed latches are pushed against on the side wall of girder, and girder is fixed in fixing card, easy to operate.
The utility model is further arranged to: the workbench includes cross bar, vertical pole, movable pulley and supporting plate, the cross Bar is fixed between girder, and the vertical pole is fixed between cross bar, and the movable pulley is arranged by roll shaft adjacent Vertical pole between, the supporting plate is arranged on movable pulley.
By using above-mentioned technical proposal, workbench is arranged to slideable workbench, is loaded by cargo After on supporting plate, supporting plate can be dragged in floor and be unloaded, operator station is avoided to unload on workbench, Guarantee the safety of staff.
The utility model is further arranged to: the hinged limited block of the lateral surface of the girder, the top surface of the girder open up Limiting slot compatible with limited block, the limited block are caught in limiting slot and abut with supporting plate.
By using above-mentioned technical proposal, when being charged, supporting plate is pushed on workbench, limited block is overturn In limiting slot, limited block abuts inlay card with supporting plate, and supporting plate is fixed on workbench, is then freighted, and is freighting At later, limited block is detached from limiting slot, supporting plate is dragged in the first floor and is unloaded.The position of supporting plate can be controlled System, safety are higher.
The utility model is further arranged to: setting buffering ramp on the workbench, buffering ramp one end hinge It connects on cross bar, the other end is abutted with floor.
By using above-mentioned technical proposal, when supporting plate is pushed to workbench, supporting plate can be steady along buffering ramp Move on workbench;Into the first floor draw supporting plate when, supporting plate into cross buffer ramp buffering, more smoothly into Enter into the first floor, avoids because the difference in height between floor and workbench causes to run during mobile pallet It winnows with a dustpan, causes to spill outside the cargo on supporting plate.
The utility model is further arranged to: the supporting plate is hinged with pull rod close to the side of the first floor.
It can be pushed by pull rod by using above-mentioned technical proposal when promoting or pulling out workbench supporting plate Supporting plate operates more convenient.
In conclusion the advantageous effects of the utility model are as follows:
1. girder is fixed in fixing card by the inlay card fixing card on floor, avoids and is punched on floor, Floor is damaged.
2. by the way that cross bar, vertical pole, movable pulley and supporting plate are arranged on workbench, cargo is being loaded on supporting plate it Afterwards, supporting plate can be dragged in floor and is unloaded, operator station is avoided to unload on workbench, guarantee work The safety of personnel.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the utility model;
Fig. 2 is the structural schematic diagram of the protrusion workbench of the utility model;
Fig. 3 is the bottom view of the workbench of the utility model;
Fig. 4 is the fixing device schematic diagram of the utility model;
Fig. 5 is the cross-sectional view of the fixation device of the utility model.
In figure, 1, girder;11, hanging ring;12, link;13, wirerope;2, workbench;21, cross bar;211, first is horizontal Bar;212, second crossbar;22, vertical pole;23, movable pulley;231, roll shaft;24, supporting plate;241, pull rod;25, safe coaming plate;26, it limits Position block;27, limiting slot;28, ramp is buffered;3, fixing card;31, first horizontal portion;32, the second horizontal part;33, vertical portion;4, Floor;41, the first floor;42, the second floor;5, fixed device;51, accommodating chamber;511, bolt hole;52, fixing bolt;521, Screw rod;522, nut;523, fixed ring;53, spring.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
It referring to Fig.1, is a kind of construction discharging platform disclosed by the utility model, including girder 1, workbench 2 With fixing card 3, fixing card 3 is U-shaped, and on floor 4, fixing card 3 includes first horizontal portion 31, the second horizontal part 32 and erects inlay card Straight portion 33, first horizontal portion 31 protrude into the upper surface that floor 4 is connected to floor 4, and the outside of first horizontal portion 31, which is fixedly installed, to be used In the fixation device 5 of fixed girder 1, the second horizontal part 32 protrudes into the lower surface that floor 4 is connected to floor 4, first horizontal portion 31 Be longer than the second horizontal part 32, vertical portion 33 be fixed between first horizontal portion 31 and the second horizontal part 32 formed one it is firm Fixing card 3.Girder 1 is two, is arranged in parallel, and one end of girder 1, which protrudes into the first floor 41 and passes through fixed device 5, is fixed on the On one horizontal part 31, the other end stretches out the first floor 41, and girder 1 stretches out length direction of the one end along girder 1 of the first floor 41 Interval setting two is used to lift the hanging ring 11 of girder 1, and 11 position of hanging ring on two girders 1 is identical;In the second floor 42 Upper layer is embedded with link 12, and the setting of link 12 two is corresponding with two girders 1 respectively, draws between link 12 and hanging ring 11 Wirerope 13 is connect, one end that girder 1 stretches out the first floor 41 is socketed fixation upwards, keeps girder 1 more stable by wirerope 13.
Referring to Fig. 2 and Fig. 3, workbench 2 is arranged on girder 1, including cross bar 21, vertical pole 22, movable pulley 23 and supporting plate 24, cross bar 21 is fixed between adjacent girder 1, and cross bar 21 includes first crossbar 211 and second crossbar 212, and first is horizontal Bar 211 is fixed at the end that girder 1 stretches out 41 side of the first floor, and second crossbar 212 is fixed at girder 1 and protrudes into the The side of one floor 41, second crossbar 212 is close to the side that the first floor 41 is open;Vertical pole 22 is fixed at first crossbar Between 211 and second crossbar 212, vertical pole 22 along first crossbar 211 length direction even three, between adjacent vertical pole 22 It is connected with movable pulley 23 by roll shaft 231, movable pulley 23 is arranged six, and uniform setting is two rows of;Supporting plate 24 is horizontal to be placed on On movable pulley 23, supporting plate 24 is hinged with pull rod 241 close to one end of the first floor 41, can drag supporting plate 24 by pull rod 241 It is moved on workbench 2.The inlay card fixing card 3 on floor 4, girder 1 is fixed in fixing card 3, is avoided on floor 4 It is punched, floor 4 is damaged.
Referring to Fig. 4 and Fig. 5, fixed device 5 is fixed at the outside of girder 1, and the length direction along girder 1 is arranged two A, fixed device 5 includes accommodating chamber 51, fixing bolt 52, spring 53 and Fixed latches, and accommodating chamber 51 is rounded, and one end is fixed It is arranged on the side of first horizontal portion 31, the bolt hole 511 passed through for fixing bolt 52, fixing bolt is opened up on other end 52 one end passes through first horizontal portion 31 and girder 1, and one end that fixing bolt 52 passes through girder 1 offers inserting for Fixed latches The through-hole entered.Fixing bolt 52 includes screw rod 521, nut 522 and fixed ring 523, and fixed ring 523 is fixed at screw rod 521 On, fixed ring 523 and nut 522 are located inside and outside accommodating chamber 51.One end of spring 53 and the right side of accommodating chamber 51 Face consolidation, the other end and fixed ring 523 consolidate, and spring 53 is socketed in outside fixing bolt 52, and spring 53 is constantly in compressive state, Fixing bolt 52 can be made to be constantly in the state being retracted to accommodating chamber 51.Fixed latches are rectangular, Fixed latches insertion through-hole It is connected on the side wall of girder 1.When installing girder 1, fixing bolt 52 is passed through into first horizontal portion 31 and girder 1, to fixation Fixed latches are inserted on bolt 52, Fixed latches are pushed against on the side wall of girder 1, and girder 1 is fixed in fixing card 3;It is tearing open When unloading girder 1, directly Fixed latches to be extracted out, fixing bolt 52 is automatically recycled to accommodating chamber 51 under the action of spring 53, The fixation device 5 has the advantages that installation and removal are convenient.
Carry out girder 1 fixation when, first with lifting appliance by 3 inlay card of fixing card on floor 4, then by girder 1 is fitted in first horizontal portion 31, presses fixing bolt 52, so that fixing bolt 52 is passed through first horizontal portion 31 and girder 1, will consolidate Determine bolt insertion through-hole, fixing bolt 52 is pushed against Fixed latches on the side wall of girder 1 under the elastic force effect of spring 53, It is fixed on what girder 1 consolidated in fixing card 3.
Referring to Fig.1, in order to guarantee the safety of discharging platform, safe coaming plate 25 is fixedly installed on discharging platform, safety Coaming plate 25 is respectively fixedly disposed on girder 1 and first crossbar 211, and safe coaming plate 25 encloses discharging platform, ensure that The safety of discharging platform.
When carrying out discharging, supporting plate 24 is pushed on workbench 2, then cargo is unloaded on supporting plate 24, is dragged Pull rod 241 drags supporting plate 24 and the cargo being placed on supporting plate 24 into the first floor 41, when supporting plate 24 drags to first When in floor 41, staff unloads in the first floor 41, in order to guarantee the efficiency of work, can be set two it is identical Supporting plate 24 another supporting plate 24 can be put in staff when unloading the supporting plate 24 in the first floor 41 It sets on workbench 2, continues into loading, can guarantee the lasting progress of unloading in this way, ensure that working efficiency.
It is hingedly limited on girder 1 referring to Fig. 2 for the ease of the supporting plate 24 being pushed on workbench 2 is fixed Block 26, limited block 26 are symmetricly set on the lateral surface of two girders 1, are opened up on the top surface of girder 1 suitable with 26 phase of limited block The limiting slot 27 matched, limited block 26 can inlay card in limiting slot 27.When 26 inlay card of limited block is in limiting slot 27, limited block 26 It is abutted with supporting plate 24, supporting plate 24 is fixed on workbench 2.When being charged, supporting plate 24 is pushed to workbench 2 On, by 26 tumble card of limited block in limiting slot 27, limited block 26 is abutted with supporting plate 24, and supporting plate 24 is fixed on workbench It on 2, then freights, after loading is completed, limited block 26 is detached from limiting slot 27, supporting plate 24 is dragged in the first floor 41 Inside unload.
Referring to Fig.1, in order to guarantee that supporting plate 24 is smoothly pushed on workbench 2, in workbench 2 and the first floor 41 Between setting buffering ramp 28, buffer ramp 28 width and workbench 2 it is of same size, buffer 28 one end of ramp be hinged on In second crossbar 212, the other end is abutted with the first floor 41.When supporting plate 24 is pushed to workbench 2, supporting plate 24 can be along Buffering ramp 28 smoothly moves on workbench 2;Into the first floor 41 draw supporting plate 24 when, supporting plate 24 into cross buffering slope The buffering in road 28 more smoothly enters in the first floor 41, avoids the difference in height because between floor 4 and workbench 2 Cause to jolt during mobile pallet 24, causes to spill outside the cargo on supporting plate 24.
The embodiment of present embodiment is the preferred embodiment of the utility model, and not limitation is originally practical new according to this The protection scope of type, therefore: the equivalence changes that all structures, shape, principle according to the utility model are done should all be covered by practical Within novel protection scope.

Claims (8)

1. a kind of construction discharging platform, it is characterised in that: including fixing card (3), fixed device (5), girder (1) and work Make platform (2), for fixing card (3) inlay card on floor (4), the fixed device (5) is fixed at the side of fixing card (3) On face, described girder (1) one end is protruded into floor (4) and is fixed on fixing card (3) by fixed device (5), the other end and work Platform (2) consolidation and stretching floor (4), workbench (2) setting stretch out the side of floor (4) in girder (1).
2. a kind of construction discharging platform according to claim 1, it is characterised in that: the fixing card (3) includes First horizontal portion (31), the second horizontal part (32) and vertical portion (33), the first horizontal portion (31) are supported with floor (4) upper surface It connects, second horizontal part (32) abuts with floor (4) lower surface, and the length of the first horizontal portion (31) is longer than the second level Portion (32), the vertical portion (33) are fixed between first horizontal portion (31) and the second horizontal part (32).
3. a kind of construction discharging platform according to claim 2, it is characterised in that: the fixed device (5) is solid It is fixed to be arranged on the lateral surface of first horizontal portion (31), the fixed device (5) include accommodating chamber (51), fixing bolt (52), Spring (53) and Fixed latches, described accommodating chamber (51) one end are fixed on first horizontal portion (31), the fixing bolt (52) First horizontal portion (31) and girder (1) are passed through by accommodating chamber (51), one end that the fixing bolt (52) passes through girder (1) is set Fixed latches are equipped with, the Fixed latches are connected on the side wall of girder (1);Described spring (53) one end and accommodating chamber (51) Right side is affixed, and the other end is fixed on fixing bolt (52), and the spring (53) is set in fixing bolt (52) outside.
4. a kind of construction discharging platform according to claim 3, it is characterised in that: fixing bolt (52) packet Nut (522), screw rod (521) and fixed ring (523) are included, the fixed ring (523) is fixed on screw rod (521), described Spring (53) is fixed on fixed ring (523) far from the one end of girder (1), the fixed ring (523) and nut (522) difference position Inside and outside accommodating chamber (51), the screw rod (521) passes through first horizontal portion (31) and girder (1), the screw rod (521) On open up through-hole for Fixed latches insertion, the Fixed latches are inserted on screw rod (521).
5. a kind of construction discharging platform according to claim 1, it is characterised in that: workbench (2) packet Cross bar (21), vertical pole (22), movable pulley (23) and supporting plate (24) are included, the cross bar (21) is fixed between girder (1), institute It states vertical pole (22) to be fixed between cross bar (21), adjacent vertical pole is arranged in by roll shaft (231) in the movable pulley (23) (22) between, the supporting plate (24) is arranged on movable pulley (23).
6. a kind of construction discharging platform according to claim 5, it is characterised in that: the outside of the girder (1) The hinged limited block in face (26), the top surface of the girder (1) open up and limited block (26) compatible limiting slot (27), the limit Block (26) is caught in limiting slot (27) and abuts with supporting plate (24).
7. a kind of construction discharging platform according to claim 5, it is characterised in that: on the workbench (2) Setting buffering ramp (28), described buffering ramp (28) one end are hinged on cross bar (21), and the other end is abutted with floor (4).
8. a kind of construction discharging platform according to claim 5, it is characterised in that: the supporting plate (24) is close to the The side of one floor (41) is hinged with pull rod (241).
CN201822090150.2U 2018-12-12 2018-12-12 A kind of construction discharging platform Active CN209339629U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822090150.2U CN209339629U (en) 2018-12-12 2018-12-12 A kind of construction discharging platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822090150.2U CN209339629U (en) 2018-12-12 2018-12-12 A kind of construction discharging platform

Publications (1)

Publication Number Publication Date
CN209339629U true CN209339629U (en) 2019-09-03

Family

ID=67756951

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822090150.2U Active CN209339629U (en) 2018-12-12 2018-12-12 A kind of construction discharging platform

Country Status (1)

Country Link
CN (1) CN209339629U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965790A (en) * 2019-12-03 2020-04-07 山东国建工程集团有限公司 Building engineering assembled support

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965790A (en) * 2019-12-03 2020-04-07 山东国建工程集团有限公司 Building engineering assembled support

Similar Documents

Publication Publication Date Title
US11028651B2 (en) Drilling rig
CN201250064Y (en) Front launching nose type bridge girder erection machine for bridge erection
CN209397501U (en) Erection crane
CN209339629U (en) A kind of construction discharging platform
CN211395395U (en) T-beam hogging moment tensioning device for bridge construction
CN207772059U (en) Building block is rested delivery device
CN207829430U (en) Lifting type operation platform for suspension operation
CN213161606U (en) Steel bar mesh piece painting device in air entrainment board
CN110905206B (en) Overhanging discharging platform with drawing type channel and construction method
CN209324001U (en) A kind of slidingtype overhanging unloading platform
CN105908992A (en) Temporary support device and temporary support method for inclined column of building steel structure
CN107130804B (en) Auxiliary device and method for installing main truss during construction of truss type roof
CN201358764Y (en) Balance weight structure of vertical oil extractor
CN210195198U (en) Elevartor shaft moving platform
CN213198142U (en) T roof beam hydraulic pressure shedder
CN210620081U (en) Cantilever crane device suitable for dismantling external scaffold of assembled high-rise residence
CN203917788U (en) A kind of riveting work platform
CN209225031U (en) Upper rail can folding-jib moveable vertical hoisting mechanism
CN208666580U (en) Vehicle-mounted cargo handling facilities
CN202323725U (en) Hanging basket device for bridge construction
CN203188197U (en) Automatic hooking device and dynamic compactor
CN205954146U (en) Silicon wafer stick hoisting device
CN205527505U (en) Jack overhead hoist
CN207618835U (en) A kind of attached wall elevator with unloading function
CN211775897U (en) Side protection structure of unloading platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant