CN209052240U - A kind of tool for super high-rise building duplex elevator vertical transport - Google Patents

A kind of tool for super high-rise building duplex elevator vertical transport Download PDF

Info

Publication number
CN209052240U
CN209052240U CN201821892412.0U CN201821892412U CN209052240U CN 209052240 U CN209052240 U CN 209052240U CN 201821892412 U CN201821892412 U CN 201821892412U CN 209052240 U CN209052240 U CN 209052240U
Authority
CN
China
Prior art keywords
elevator
protective platform
tool
super high
rise building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821892412.0U
Other languages
Chinese (zh)
Inventor
许立山
蒋凯
田雨
王瑞
张轩奎
王坤
陈国良
谢宝祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN201821892412.0U priority Critical patent/CN209052240U/en
Application granted granted Critical
Publication of CN209052240U publication Critical patent/CN209052240U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B50/00Energy efficient technologies in elevators, escalators and moving walkways, e.g. energy saving or recuperation technologies

Landscapes

  • Types And Forms Of Lifts (AREA)

Abstract

A kind of tool for super high-rise building duplex elevator vertical transport, including lift car, moving machine room, hanging beam, workbench and the protective platform component being sequentially arranged from bottom to top, protective platform component includes the third layer protective platform being sequentially arranged from bottom to top, second layer protective platform and the oblique protective platform of the first floor;Moving machine room includes motor, elevator traction machine and control cabinet, and the wirerope of elevator traction machine is stored on the hoist ropes ropewinder near elevator pit.The utility model greatly improves the conevying efficiency of construction stage construction personnel and material, permanent elevator is realized simultaneously to come into operation as early as possible, service floor will be synchronized and be climbed as civil engineering structure increases, its environmental protection, energy conservation, the advantage for dropping low cost aspect are played, and conevying efficiency, safety, reliability are much higher than traditional architecture construction elevator.

Description

A kind of tool for super high-rise building duplex elevator vertical transport
Technical field
The utility model belongs in construction the technical field for being directed to construction of super highrise building, and in particular to one kind is used for The tool of super high-rise building duplex elevator vertical transport.
Background technique
With the development of domestic economy, many terrestrial reference super high-rise buildings gradually emerge.Super high-rise building is in large scale, Construction site workload is big, it is ensured that construction personnel fast reaches operation side, is baptism to vertical transport system.Tradition Under engineering construction mode, the main tool that super high-rise building uses attached wall type temporary construction elevator to transport as personnel substantially is faced When the construction elevator speed of service is slow, conevying efficiency is low, and live temporary construction elevator position is limited, it cannot be guaranteed that solving Super High The transport power demand of construction site;The hoistway of formal elevator is occupied, and holding time is long, influences the peace of later period formal elevator Dress, can adversely affect the whole duration of engineering;Therefore, solving the vertical transport power of super high-rise building becomes the difficulty in constructing Topic.
Duplex elevator is to be initially formed elevator shaft when horizontal structure construction is in lowrise layer, install duplex elevator, check and accept It comes into operation after.The computer room of duplex elevator be can self climbing temporary machine room, rise to ten layers, i.e. Core Walls Structure and building every time Plate ten floors of every rising, elevator(lift) machine room rebound once.Top out and elevator(lift) machine room completion after, by new elevator traction The calculator room equipments such as machine control cabinet are mounted in final computer room, can be exchanged into final formal elevator after replacing corresponding component.
Utility model content
The purpose of the utility model is to provide a kind of tools for super high-rise building duplex elevator vertical transport, to solve The slow technical problem of the conventional lift speed of service of the prior art;And solve the problems, such as that prior art safety, reliability are low.
To achieve the above objectives, the present invention adopts the following technical solutions:
A kind of tool for super high-rise building duplex elevator vertical transport, it is characterised in that: including from bottom to top sequentially Lift car, moving machine room, hanging beam, workbench and the protective platform component of setting, the protective platform component include under Third layer protective platform, second layer protective platform and the oblique protective platform of the first floor being sequentially arranged on and;The moving machine room packet Motor, control cabinet and elevator traction machine are included, the spare wirerope of the elevator traction machine is stored near elevator pit On hoist ropes ropewinder.
It is further preferred that the hanging beam is scalable hanging beam, telescopic arms one end, which is fallen, connects the wall after being set to elevator In hole to be provided, the other end is overlapped on floor.
Further, midfoot support frame is equipped between the third layer protective platform and second layer protective platform, including Top chan frame, lower part chan frame, and and the column that is supported between top chan frame and lower part chan frame.
Further, waterproof layer is affixed between the second layer protective platform and hoistway inner wall.
Further, pulling apparatus crane is installed on the workbench.
Further, the hanging beam is lifted up by the lifting rope that workbench is transferred.
In addition, the moving machine room is equipped with from lifting device.
It is connect after being set to elevator in the hole to be provided of wall it is further preferred that third layer protective platform one end is fallen, the other end It is overlapped on floor.
Compared with prior art the utility model have the characteristics that and the utility model has the advantages that
It is 4m/s, load-carrying number that the load-carrying of the utility model design duplex elevator, which is 1800Kg and 3600Kg, the speed of service, It is 24 people and 46 people, the speed of service is approximately 4 times of common construction elevator, and passenger's transport power of separate unit duplex elevator is same specification construction About 12 times of elevator, greatly improve the efficiency of construction stage personnel transport, while realizing permanent elevator and coming into operation as early as possible, Services Building Layer will be synchronized and be climbed as civil engineering structure increases, and play its environmental protection, energy conservation, the advantage for dropping low cost aspect, and Transportation Efficiency Rate, safety, reliability are much higher than traditional architecture construction elevator.
The utility model has the characteristics that safety, is applicable in, and has good promotion and practical value, after extensive popularization and application Good economic benefit can be generated.
Detailed description of the invention
Fig. 1 is the initial mounting state figure of the utility model;
Fig. 2 is that the utility model relates to the structural schematic diagrams that protective platform component ramps up;
Fig. 3 be the utility model relates to the structural schematic diagram that is lifted up of workbench;
Fig. 4 be the utility model relates to the structural schematic diagram that is lifted up of hanging beam;
Fig. 5 the utility model relates to moving machine room and the structural schematic diagram that is lifted up of carriage.
Appended drawing reference: 1- lift car;2- moving machine room;3- hanging beam;5- workbench;6- second layer protective platform;7- The oblique protective platform of the first floor;8- third layer protective platform;9- hoist ropes ropewinder;10- hole to be provided;11- floor;Branch in the middle part of 12- Support frame frame;13- lifting rope;14- control cabinet;15- motor;16- elevator traction machine.
Specific embodiment
To make technological means of the utility model, character of innovation, reaching purpose and effect is easy to understand, below The present invention will be further described.
The embodiment recorded herein is the specific specific embodiment of the utility model, for illustrating the utility model Design, be it is explanatory and illustrative, should not be construed as the limit to the utility model embodiment and the scope of the utility model System.In addition to the embodiment recorded herein, those skilled in the art can also be public based on the claim of this application book and specification institute For the content opened using obvious other technical solutions, these technical solutions include using doing to the embodiment recorded herein The technical solution of any obvious substitutions and modifications out.
A kind of tool for super high-rise building duplex elevator vertical transport, as shown in Figure 1, including sequentially setting from bottom to top Lift car 1, moving machine room 2, hanging beam 3, workbench 5 and the protective platform component set, protective platform component include from lower and On the oblique protective platform 7 of third layer protective platform 8, second layer protective platform 6 and the first floor that is sequentially arranged;Moving machine room 2 includes Including motor 15, elevator traction machine 16 and control cabinet 14, the wirerope of elevator traction machine 16 is stored near elevator pit Hoist ropes ropewinder 9 on;Hanging beam 3 is scalable hanging beam, and telescopic arms one end falls the hole to be provided for connecing the wall after being set to elevator In 10, the other end is overlapped on floor 11;Midfoot support frame is equipped between third layer protective platform 8 and second layer protective platform 6 Frame 12, including top chan frame, lower part chan frame, and and be supported between top chan frame and lower part chan frame Column;Waterproof layer is affixed between second layer protective platform 6 and hoistway inner wall;Pulling apparatus is installed to rise on workbench 5 Heavy-duty machine;Hanging beam 3 is lifted up by the lifting rope 13 that workbench 5 is transferred;Moving machine room 2 is equipped with from lifting device;Third layer 8 one end of protective platform, which is fallen, to be connect after being set to elevator in the hole to be provided 10 of wall, and the other end is overlapped on floor 11.
Fig. 1 is the initial mounting state figure of the utility model, and specific step is as follows, and a. completes hoistway wall, utilizes inner cylinder Steel beam lifting equipment installs hoistway high position sizing protective platform, carries out waterproof measure, in case rainwater, sundries enter hoistway;B. pacify Fill every layer of hall door of guide rail and elevator;D., moving machine room is installed, is attached on guide rail, using itself lifting device, is installed Afterwards from being promoted, running space is moved out of to carriage;E. routinely assembled carriage;F. pit and electric component installation, debugging;
Fig. 2 shows the preparation stage one is risen to, using hoist engine or other lifting means, upper protective component, and benefit are promoted The hole to be provided reserved with wall after hoistway, the platform that properly protects are fixed;
Fig. 3, which is shown, rises to the preparation stage two, using workbench installation guide rail, bracket and entrance hall, is equipped on workbench Pulling apparatus crane has suspension pulling apparatus rope on the girder steel of third layer protective platform lower part, and installment work platform can edge Guide rail is run up and down, and elevator can operate normally during this period, and only during cage guide is elevated into hoistway, elevator needs of short duration It stops operation;
Fig. 4 shows elevator hop step one, promotes workbench, while promoting scalable hang using two pulling apparatus Beam.Scalable backbar one end is put off in wall reserving hole by semi-girder, and the other end is then supported on (floor on hall door floor Lower section has floor beam to share stress), in the case where promoting operating condition, then acted on appropriate by the lifting rope that installment work platform in top is transferred 50mm is mentioned, the contracting mechanism in driving beam carries out whole promotion so that backbar semi-girder is retracted and is detached from support.
Fig. 5 shows elevator hop step two, promotes moving machine room and carriage.It should check that rope and associated safety are arranged before jump After applying satisfaction, using moving machine room from lifting device, using the scalable hanging beam in top as spandrel girder, computer room and carriage are carried out simultaneously Slowly promoted.After the completion of jump, the installment works such as hoistway signaling switch, hall door and calling, the Show Button of subsequent installation are carried out, Then official acceptance enables.
The duplex elevator described in the utility model above-described embodiment finally completes elevator shaft computer room construction, removes anti- Fall platform, removes mounting platform, and carriage and hanger are moved on the position of final elevator conversion and install last root guide rail. After the completion of computer room secondary structure, start finally to be converted.Electric component and loss component are replaced, elevator debugs examination again After can come into operation.
The above is only the preferred embodiment of the present invention, is not intended to limit the utility model, all practical at this Within novel spirit and principle, any modification, equivalent replacement, improvement and so on should be included in the guarantor of the utility model Within the scope of shield.

Claims (8)

1. a kind of tool for super high-rise building duplex elevator vertical transport, it is characterised in that: including sequentially setting from bottom to top Lift car (1), moving machine room (2), hanging beam (3), the workbench (5), protective platform component set, the protective platform component Including the third layer protective platform (8), second layer protective platform (6) and the oblique protective platform of the first floor being sequentially arranged from bottom to top (7);The moving machine room (2) includes motor (15), elevator traction machine (16) and control cabinet (14), the elevator traction machine (16) Wirerope be stored on the hoist ropes ropewinder (9) near elevator pit.
2. a kind of tool for super high-rise building duplex elevator vertical transport as described in claim 1, it is characterised in that: institute Stating hanging beam (3) is scalable hanging beam, and telescopic arms one end, which is fallen, to be connect after being set to elevator shaft in the hole to be provided (10) of wall, another End is overlapped on floor (11).
3. a kind of tool for super high-rise building duplex elevator vertical transport as described in claim 1, it is characterised in that: institute It states and is equipped with midfoot support frame (12) between third layer protective platform (8) and second layer protective platform (6), including upper slot steel framework Frame, lower part chan frame, and and the column that is supported between top chan frame and lower part chan frame.
4. a kind of tool for super high-rise building duplex elevator vertical transport as described in claim 1, it is characterised in that: institute It states and is affixed with waterproof layer between second layer protective platform (6) and hoistway inner wall.
5. a kind of tool for super high-rise building duplex elevator vertical transport as described in claim 1, it is characterised in that: institute It states and pulling apparatus crane is installed on workbench (5).
6. a kind of tool for super high-rise building duplex elevator vertical transport as described in claim 1, it is characterised in that: institute Hanging beam (3) are stated to be lifted up by the lifting rope (13) that workbench (5) are transferred.
7. a kind of tool for super high-rise building duplex elevator vertical transport as described in claim 1, it is characterised in that: institute Moving machine room (2) are stated to be equipped with from lifting device.
8. a kind of tool for super high-rise building duplex elevator vertical transport as described in claim 1 ~ 7 any one, Be characterized in that: described third layer protective platform (8) one end, which is fallen, to be connect after being set to elevator in the hole to be provided (10) of wall, other end overlap joint On floor (11).
CN201821892412.0U 2018-11-16 2018-11-16 A kind of tool for super high-rise building duplex elevator vertical transport Active CN209052240U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821892412.0U CN209052240U (en) 2018-11-16 2018-11-16 A kind of tool for super high-rise building duplex elevator vertical transport

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821892412.0U CN209052240U (en) 2018-11-16 2018-11-16 A kind of tool for super high-rise building duplex elevator vertical transport

Publications (1)

Publication Number Publication Date
CN209052240U true CN209052240U (en) 2019-07-02

Family

ID=67053544

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821892412.0U Active CN209052240U (en) 2018-11-16 2018-11-16 A kind of tool for super high-rise building duplex elevator vertical transport

Country Status (1)

Country Link
CN (1) CN209052240U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110817661A (en) * 2019-10-22 2020-02-21 日立电梯(上海)有限公司 Elevator system used during construction
CN112938670A (en) * 2021-02-26 2021-06-11 日立电梯(上海)有限公司 Skip-floor elevator terminal station protection device and debugging method thereof
CN113581982A (en) * 2021-08-02 2021-11-02 美迪斯电梯有限公司 Skip floor elevator using elevator guide rail to ascend
CN114380179A (en) * 2021-12-27 2022-04-22 上海建工四建集团有限公司 Safety construction method for hoistway elevator
US11396442B2 (en) 2020-05-09 2022-07-26 Otis Elevator Company Low cost roped jump lift concept
CN114829288A (en) * 2019-12-19 2022-07-29 通力股份公司 Elevator arrangement and method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110817661A (en) * 2019-10-22 2020-02-21 日立电梯(上海)有限公司 Elevator system used during construction
CN114829288A (en) * 2019-12-19 2022-07-29 通力股份公司 Elevator arrangement and method
US11993484B2 (en) 2019-12-19 2024-05-28 Kone Corporation Elevator arrangement and method
US11396442B2 (en) 2020-05-09 2022-07-26 Otis Elevator Company Low cost roped jump lift concept
CN112938670A (en) * 2021-02-26 2021-06-11 日立电梯(上海)有限公司 Skip-floor elevator terminal station protection device and debugging method thereof
CN112938670B (en) * 2021-02-26 2023-03-10 日立电梯(上海)有限公司 Skip-floor elevator terminal station protection device and debugging method thereof
CN113581982A (en) * 2021-08-02 2021-11-02 美迪斯电梯有限公司 Skip floor elevator using elevator guide rail to ascend
CN114380179A (en) * 2021-12-27 2022-04-22 上海建工四建集团有限公司 Safety construction method for hoistway elevator
CN114380179B (en) * 2021-12-27 2023-05-26 上海建工四建集团有限公司 Safety construction method of hoistway elevator

Similar Documents

Publication Publication Date Title
CN209052240U (en) A kind of tool for super high-rise building duplex elevator vertical transport
US7635049B2 (en) Method and apparatus for installing an elevator during the construction of a building
EP1583710B1 (en) Method and apparatus for installing an elevator during construction of a building
EP2490973B1 (en) Method in the manufacture of an elevator
CN110228743B (en) Overhead two-to-one suspension ratio construction elevator for elevator shaft traction and operation method thereof
CN107399656B (en) Outdoor elevator and construction method thereof
CN110371823B (en) Self-lifting hoisting equipment suitable for assembly type additional elevator construction and construction method
CN103195256A (en) Hanging column type steel structure jig frame construction method
CN109779244A (en) A kind of self-elevating type elevator hoistway exterior wall creeping formwork operating platform construction
CN102502378A (en) Climbing elevator for building construction
CN106121255A (en) Apparatus installed by a kind of Super High glass curtain wall
CN113137054A (en) Method for setting inverted hoisting power equipment in attached lifting scaffold
CN106567542B (en) A kind of Super High two tall buildings Steel corridor assemble method
CN115538792A (en) Residential building machine installation construction method and structure
CN108286332A (en) A kind of concrete of crossing soars aloft beam from climbing monoblock type bylinder system and construction method
CN102718109A (en) Method for transforming construction elevator into passenger-goods elevator
CN210735910U (en) Self-lifting hoisting equipment suitable for assembly type additional elevator construction
CN203097281U (en) Nuclear power station double-layer containment vessel hydraulic creeping formwork
CN201460186U (en) Adhesive lifting scaffold
CN208648493U (en) A kind of no scaffold installation elevator operation platform device
CN113175203A (en) Method for setting lifting power equipment in attached lifting scaffold
CN209481015U (en) A kind of Miniature stair
CN208122299U (en) A kind of concrete of crossing soars aloft beam from climbing monoblock type tub system
CN203269287U (en) Underneath type elevator without machine room
CN113323368A (en) Lifting construction method for external protection hanging frame of assembled building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant