CN209025668U - A kind of Shield-bored tunnels pass through river construction grouting equipment - Google Patents
A kind of Shield-bored tunnels pass through river construction grouting equipment Download PDFInfo
- Publication number
- CN209025668U CN209025668U CN201821437945.XU CN201821437945U CN209025668U CN 209025668 U CN209025668 U CN 209025668U CN 201821437945 U CN201821437945 U CN 201821437945U CN 209025668 U CN209025668 U CN 209025668U
- Authority
- CN
- China
- Prior art keywords
- shield
- injection pipe
- slurries
- waterglass
- gram
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The utility model discloses a kind of Shield-bored tunnels to pass through river construction grouting equipment, including carrying out the intracorporal slurries mixture of shield that is mixed and being delivered to shield machine and conveying device to grouting serous fluid, the forward upper of middle shield, which is equipped with, is injected into the middle shield injection pipe on the outside of shield body for grouting serous fluid, is equipped on the native storehouse rear wall of shield machine grouting serous fluid being injected into the intracorporal native storehouse injection pipe of soil on front side of cutterhead by Tu Cang;The inlet of middle shield injection pipe and native storehouse injection pipe is connect with the liquid outlet of slurries mixture and conveying device.The utility model simple structure and reasonable design and it is easy to use, using effect is good, slurries are injected to shield body side by middle shield injection pipe during shield-tunneling construction, and slurries can be injected into the soil body on front side of shield body by native storehouse injection pipe, ensure the Tunnel stability of safety for tunnel engineering and construction molding, the purpose of synchronous grouting during realization shield-tunneling construction, and construction efficiency is high, economical and practical.
Description
Technical field
The utility model belongs to Shield Construction Technique field, passes through river construction more particularly, to a kind of Shield-bored tunnels
Use grouting equipment.
Background technique
Shield method is a kind of Fully-mechanized construction method of modern constructing tunnel, and leading mechanical equipment to be used is shield
Machine uses the molding subway tunnel of shield construction for Shield-bored tunnels.The shield body of shield machine by anterior shield, middle shield and shield tail from
Assemble front to back, anterior shield front is equipped with cutterhead.When shield construction, the purpose of slip casting is starched by the slip casting injected
The purpose of liquid is filled the intracorporal gap of soil, realizes soil stabilization, control soil body sedimentation.
According to general knowledge known in this field, the grouting serous fluid injected during shield-tunneling construction at present (abbreviation slurries) includes single
Slurry and two kinds of dual slurry, wherein dual slurry includes that the dual slurry of cement and waterglass composition, a gram mud effect are formed with waterglass
Dual slurry etc..Wherein, gram mud effectiveness is derivative by synthesizing calcium base clay mineral, cellulose in Tunnel Engineering periphery filler
Agent, colloid stabilizer and dispersing agent are constituted, advantage: if first is that settled in shield machine driving, cavity, the danger feelings such as gush
When condition, what the characteristics such as sealing, filling and support of the material can be instant reaches the branch remedied, and will not generate prohibitively expensive
Out, usage mode is also simple and fast;Second is that in addition other expensive equipment need not be added, use on shield machine with can be convenient
High-speed mixer mixes to realize that gram mud imitates a slurries (i.e. gram mud imitates the slurries being mixed to form with water, and also referred to as gram mud imitates solution), and
Injected via pump, injection valve group and injection pipe above gram mud effect slurries and waterglass to native storehouse injection hole or shield machine surrounding into
It is mixed and is injected to mouth, effectively achieve the effect that sealing, filling and support.
River refers to the route that river water flows through, and is often referred to the water route that can be opened the navigation or air flight.Using shield method to the subway for passing through river
When tunnel is constructed, since constructed subway tunnel is located at below river, to avoid constructing tunnel process bring water source dirty
The problems such as dye, river sedimentation, difficulty of construction is larger, and construction environment safety requirements is higher.Nowadays, using shield method to wearing
When the subway tunnel in more river is constructed, focus on ensure construction environment safety, not polluted source, do not influence river and use
Aspect, there are mainly two types of conventional construction method: the first is the method improved to the following soil body of river original ground, such as
The original ground following soil body in river is improved using high-pressure rotary jet grouting pile, high-pressure slip-casting etc.;Second is to shield machine front end soil
The method of body progress pre-grouting.But when practice of construction, there are river sedimentations to be difficult to control for first method, settles larger, water
The problems such as source pollution is more serious, second method pre-grouting synchronous cannot be carried out with the work progress of shield-tunneling construction, and shield is applied
Work low efficiency, used resource and expense are larger, and input cost is high.Such as using shield method to the tunnel in the south water to north trunk canal passed through
When engineering is constructed, since the settlement request in south water to north trunk canal is high, water source is forbidden polluting, and above-mentioned first method can not be real
It applies, and second method be since pre-grouting and shield-tunneling construction synchronous cannot carry out, construction efficiency is low and input cost is high.
Utility model content
The technical problem to be solved by the utility model is in view of the deficiency of the prior art, provide a kind of subway
Shield driven tunnel crossing river construction use grouting equipment, simple structure and reasonable design and it is easy to use, using effect is good,
Slurries are injected to shield body side by middle shield injection pipe during shield-tunneling construction, and can be native to shield body front side by native storehouse injection pipe
Injection slurries in vivo, it is ensured that the Tunnel stability of safety for tunnel engineering and construction molding realizes that shield-tunneling construction is synchronous in the process
The purpose of slip casting, and construction efficiency is high, it is economical and practical.
In order to solve the above technical problems, the technical solution adopted in the utility model is: a kind of Shield-bored tunnels pass through river
Road construction grouting equipment, it is characterised in that: including carrying out the intracorporal slurry of shield that is mixed and being delivered to shield machine to grouting serous fluid
Liquid mixture and conveying device, the shield body are assembled from front to back by anterior shield, middle shield and shield tail, and the anterior shield front is equipped with
Cutterhead;The forward upper of the middle shield, which is equipped with, is injected into the middle shield injection pipe on the outside of shield body, the middle shield for the grouting serous fluid
Forward upper be provided with supply in shield injection pipe installation middle shield injected hole;Being equipped on the native storehouse rear wall of the shield machine will be described
Grouting serous fluid is injected into the intracorporal native storehouse injection pipe of soil on front side of the cutterhead by Tu Cang, is provided with confession on the rear wall of the Tu Cang
The native storehouse injected hole of native storehouse injection pipe installation, the middle shield injected hole are located on rear side of the native storehouse injected hole;The middle shield injection
The inlet of pipe and native storehouse injection pipe is connect with the liquid outlet of the slurries mixture and conveying device.
A kind of above-mentioned Shield-bored tunnels pass through river construction grouting equipment, it is characterized in that: the soil storehouse slip casting hole location
The rear wall top of Yu Tucang.
A kind of above-mentioned Shield-bored tunnels pass through river construction grouting equipment, it is characterized in that: it is described soil storehouse injected hole and
The middle shield injected hole is respectively positioned on the dead astern of the cutterhead.
A kind of above-mentioned Shield-bored tunnels pass through river construction grouting equipment, it is characterized in that: it is described soil storehouse injection pipe with
Shield body is laid in parallel, and the soil storehouse injection pipe and middle shield injection pipe are respectively positioned on right above the central axis of shield body;The middle shield
Injection pipe and the perpendicular laying of native storehouse injection pipe, the middle shield injection pipe are laid on a cross section of shield body.
A kind of above-mentioned Shield-bored tunnels pass through river construction grouting equipment, it is characterized in that: the slurries are mixed and defeated
Send device include gram mud effect is stirred with water and is obtained a gram high-speed mixer for mud effect slurries, will described gram of mud effect slurries with
Slurries delivery pipe that waterglass mixes and forms the dual slurry injection pipe of the grouting serous fluid, connect with dual slurry injection pipe, will
Described gram of mud effect slurries are pumped to gram mud effect pumping installations of dual slurry injection pipe and waterglass are pumped to dual slurry injection pipe
Waterglass pumping installations, with dual slurry injection pipe, the liquid outlet of the high-speed mixer imitates pumping installations by described gram of mud
It is connect with the inlet of dual slurry injection pipe, the liquid outlet of the waterglass pumping installations and the inlet of dual slurry injection pipe connect
It connects;The liquid outlet of the dual slurry injection pipe is connect with the inlet of slurries delivery pipe, the middle shield injection pipe and Tu Cang injection
The inlet of pipe is connect with the liquid outlet of slurries delivery pipe.
A kind of above-mentioned Shield-bored tunnels pass through river construction grouting equipment, it is characterized in that: described gram of mud effect pumping dress
It sets and imitates delivery pipe including gram mud conveyed to described gram of mud effect slurries, described gram of mud effect delivery pipe is connected to high-speed mixer
Liquid outlet and dual slurry injection pipe inlet between, the first hydraulic pump is housed in described gram of mud effect delivery pipe;
The waterglass pumping installations includes for the waterglass storage box of waterglass storage and to described gram of mud effect slurry
The waterglass delivery pipe that liquid is conveyed, the waterglass delivery pipe is connected to the liquid outlet of waterglass storage box and dual slurry is infused
Enter between the inlet of pipe, the second hydraulic pump is housed in the waterglass delivery pipe.
A kind of above-mentioned Shield-bored tunnels pass through river construction grouting equipment, it is characterized in that: first hydraulic pump and
Second hydraulic pump is variable-frequency electric hydraulic pump;
First flowmeter and first pressure gauge be housed, equipped with the in the waterglass delivery pipe in described gram of mud effect delivery pipe
Two flowmeters and second pressure gauge.
A kind of above-mentioned Shield-bored tunnels pass through river construction grouting equipment, it is characterized in that: the slurries are mixed and defeated
Sending device further includes the water filling device filled the water into high-speed mixer, and the water filling port of the water filling device stretches to high-speed mixer
Stir chamber in.
A kind of above-mentioned Shield-bored tunnels pass through river construction grouting equipment, it is characterized in that: the dual slurry injection pipe
For the tube body of inner hollow.
A kind of above-mentioned Shield-bored tunnels pass through river construction grouting equipment, it is characterized in that: the middle shield injection pipe and
Native storehouse injection pipe is straight tube, and the upper end of the middle shield injection pipe stretches on the outside of shield body, and the front end of soil storehouse injection pipe is stretched
Enter to native storehouse.
Compared with the prior art, the utility model has the following advantages:
1, simple structure and reasonable design and input cost is lower.
2, easy to use, easy for construction and using effect is good, has the advantage that first, Shield Construction Method Used mistake
Cheng Zhong, it is synchronous to carry out slip casting, Shield Construction Method Used efficiency can be effectively improved, resource input is reduced, reduces construction cost;The second,
Slurries mixture, conveying and injection can be automatically performed;Third, construction location are unrestricted, and slip casting position is flexible, thus can be effectively reduced
Slip casting expense;4th, slip casting effect is good, can be reduced construction safety risk, it is ensured that shield-tunneling construction process safety, can to shield body with open
It digs the gap of outer profile, excavate medium internal clearance, shield machine front hole, sandblasting, the leak region of the appearance of shield machine front etc.
It is handled, reaches sealing, the only resultant effects such as slurry, filling and support, while can effectively avoid settling excessive, customer service, periphery
There are holes, sandblasting for the soil body;5th, environmental pollution can be effectively reduced, and can be effectively controlled underground water loss;
6th, it is suitable for various driving media, is particularly suitable for passing through the shield tunnel construction mistake of river, existing building and structures
Journey, popularization and application foreground are extensive.
In conclusion the utility model simple structure and reasonable design and it is easy to use, using effect is good, shield is applied
Slurries are injected to shield body side by middle shield injection pipe during work, and can be infused by native storehouse injection pipe into the soil body on front side of shield body
Enter slurries, it is ensured that the Tunnel stability of safety for tunnel engineering and construction molding realizes synchronous grouting during shield-tunneling construction
Purpose, and construction efficiency is high, it is economical and practical.
Below by drawings and examples, the technical solution of the utility model is described in further detail.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the layout position illustration of shield injection pipe and native storehouse injection pipe in the utility model.
Description of symbols:
1-high-speed mixer;2-waterglass storage boxes;The first hydraulic pump of 3-1-;
The second hydraulic pump of 3-2-;4-1-first flowmeter;4-2-second flowmeter;
5-1-first pressure gauge;5-2-second pressure gauge;6-dual slurry injection pipes;
7-middle shield injection pipes;8-native storehouse injection pipes;9-Tu Cang;
10-shield bodies;11-slurries delivery pipes;12-grams of mud imitate delivery pipe;
13-waterglass delivery pipes;14-water tanks;15-water injection pipes;
16-waterglass injection pipes.
Specific embodiment
As shown in Figure 1 and Figure 2, the utility model includes the shield body 10 for carrying out mixture to grouting serous fluid and being delivered to shield machine
Interior slurries mixture and conveying device, the shield body 10 is assembled from front to back by anterior shield, middle shield and shield tail, before the anterior shield
Portion is equipped with cutterhead;The forward upper of the middle shield is equipped with the middle shield injection pipe that the grouting serous fluid is injected into 10 outside of shield body
7, the forward upper of the middle shield is provided with the middle shield injected hole that shield injection pipe 7 is installed in confession;9 rear wall of native storehouse of the shield machine
The grouting serous fluid is injected into the intracorporal soil storehouse injection pipe 8 of soil on front side of the cutterhead, the native storehouse 9 by native storehouse 9 by upper be equipped with
Rear wall on be provided with native storehouse injected hole for the installation of native storehouse injection pipe 8, the middle shield injected hole is located at the native storehouse injected hole
Rear side;Liquid outlet of the inlet of the middle shield injection pipe 7 and native storehouse injection pipe 8 with the slurries mixture and conveying device connects
It connects.
The grouting serous fluid is the common slurries of shield-tunneling construction, both can be single slurry, and be also possible to dual slurry.It is described double
Slurry can be formed using the dual slurry (i.e. cement-sodium silicate double liquid) of cement and waterglass composition, gram mud effect with waterglass
Dual slurry (i.e. gram mud effect-waterglass dual slurry) etc., use gram mud effect-waterglass dual slurry, specifically conventional gram of mud herein
Imitate slurries employed in engineering method.During practice of construction, the grouting serous fluid can be using note synchronous during shield-tunneling construction
Grouting serous fluid used when slurry, slurries used when can also use secondary grouting, practice of construction is flexible, the material of grouting serous fluid
It is unlimited, thus use is very easy, it is easy for construction and flexible.
In the present embodiment, the soil storehouse injected hole is located at the rear wall top in native storehouse 9.
Also, the soil storehouse injected hole and the middle shield injected hole are respectively positioned on the dead astern of the cutterhead.
As shown in Fig. 2, soil storehouse injection pipe 8 is laid with shield body 10 in parallel, soil storehouse injection pipe 8 and the injection of middle shield
Pipe 7 is respectively positioned on right above the central axis of shield body 10;The middle shield injection pipe 7 and the perpendicular laying of native storehouse injection pipe 8, it is described in
Shield injection pipe 7 is laid on a cross section of shield body 10.
In the present embodiment, the perpendicular laying of rear wall of the soil storehouse injection pipe 8 and native storehouse 9, the middle shield injection pipe 7 with
The rear wall in native storehouse 9 is laid in parallel.
It, can be right according to practice of construction situation using the utility model during carrying out Shield Construction Method Used using shield machine
Different slip casting positions carry out slip casting.Wherein, there are portals in front of hole or shield machine leak, sandblasting etc. occurs in front of shield machine
When situation, the grouting serous fluid is injected using the utility model and by native storehouse injection pipe 8, the grouting serous fluid injected is logical
It crosses native storehouse 9 to enter cutterhead and enter the soil body in front of shield machine after being thoroughly mixed by the cutterhead, exist to front
Hole filled, the region for leak, sandblasting occur blocked, complete soil stabilization in front of shield machine, thus can have
It imitates and the soil body of development end in front of shield machine is reinforced, continue to construct after front development end is stablized, can effectively ensure to construct
Safety, and construction speed will not be affected greatly, Shield Construction Method Used is high-efficient;When needing to control in shield tunneling process
When the soil body is settled or need to be reinforced to the shield machine side soil body above shield machine, infused using the utility model and by middle shield
Enter pipe 7 to injecting the grouting serous fluid on the outside of shield body 10, the grouting serous fluid from the middle shield top of shield machine injection shield body 10 with
Outside is excavated in the gap between medium (i.e. the soil body) and the excavation media voids on the outside of shield machine, to reach slip casting effect
Fruit effectively controls the safety and subsequent sedimentation value of shield-tunneling construction process, can accomplish close to zero sedimentation, while can also be effectively ensured
Under wear the normal use of existing engineering.
As shown in Figure 1, the slurries mixture and conveying device include being stirred simultaneously to gram mud effect with water in the present embodiment
A gram high-speed mixer 1 for mud effect slurries is obtained, described gram of mud effect slurries are mixed with waterglass and form the grouting serous fluid
Described gram of mud effect slurries are pumped to dual slurry by dual slurry injection pipe 6, the slurries delivery pipe 11 connecting with dual slurry injection pipe 6
Gram mud effect pumping installations of injection pipe 6 and the waterglass pumping installations and dual slurry that waterglass is pumped to dual slurry injection pipe 6
Injection pipe 6, the liquid outlet of the high-speed mixer 1 imitate the inlet of pumping installations and dual slurry injection pipe 6 by described gram of mud
Connection, the liquid outlet of the waterglass pumping installations are connect with the inlet of dual slurry injection pipe 6;The dual slurry injection pipe 6
Liquid outlet connect with the inlet of slurries delivery pipe 11, the inlet of the middle shield injection pipe 7 and native storehouse injection pipe 8 with slurry
The liquid outlet of liquid delivery pipe 11 connects.When practice of construction, the grouting serous fluid is gram mud effect-water that conventional shield machine slip casting uses
Glass dual slurry.
In the present embodiment, described gram of mud effect pumping installations includes gram mud effect conveying conveyed to described gram of mud effect slurries
Pipe 12, described gram of mud effect delivery pipe 12 are connected between the liquid outlet of high-speed mixer 1 and the inlet of dual slurry injection pipe 6,
First hydraulic pump 3-1 is housed in described gram of mud effect delivery pipe 12;
The waterglass pumping installations includes for the waterglass storage box 2 of waterglass storage and to described gram of mud effect slurry
The waterglass delivery pipe 13 that liquid is conveyed, the waterglass delivery pipe 13 are connected to the liquid outlet of waterglass storage box 2 and double
Between the inlet of slurry injection pipe 6, the second hydraulic pump 3-2 is housed in the waterglass delivery pipe 13.
In the present embodiment also, the first hydraulic pump 3-1 and the second hydraulic pump 3-2 are variable-frequency electric hydraulic pump.And
And the first hydraulic pump 3-1 and the second hydraulic pump 3-2 are high-pressure pump.In actual use, the first hydraulic pump 3-1 and
Second hydraulic pump 3-2 can also use other types of electric hydraulic pump.
In actual use, the first hydraulic pump 3-1 and the second hydraulic pump 3-2 be pumped by effect under, make to pump
It can be carried out and be sufficiently mixed to described in dual slurry injection pipe 6 grams of mud effect slurries and waterglass, and pumped in the grouting serous fluid
It can enter the soil body after to slip casting position and be sufficiently mixed, to effectively improve slip casting effect, reach sealing, only slurry, filling and branch
Support and other effects.
It is described equipped with first flowmeter 4-1 and first pressure gauge 5-1 in described gram of mud effect delivery pipe 12 in the present embodiment
Second flowmeter 4-2 and second pressure gauge 5-2 is housed in waterglass delivery pipe 13.
As shown in Figure 1, the dual slurry injection pipe 6 is the tube body of inner hollow in the present embodiment.Also, the biliquid
There are two the inlets and one and slurry that connect respectively with gram mud effect delivery pipe 12 and waterglass delivery pipe 13 for band on slurry injection pipe 6
The liquid outlet that liquid delivery pipe 11 connects.
For convenience of connection, between the liquid outlet of the slurries delivery pipe 11 and middle shield injection pipe 7 and native storehouse injection pipe 8 respectively
It is connected by a connecting tube.Also, connected between two connecting tubes and the liquid outlet of slurries delivery pipe 11 by tee tube
It connects.
In the present embodiment, the middle shield injection pipe 7 and native storehouse injection pipe 8 are straight tube, the upper end of the middle shield injection pipe 7
10 outside of shield body is stretched to, the front end of soil storehouse injection pipe 8 stretches in native storehouse 9.
To be easy to use, the slurries mixture and conveying device further include the water filling device filled the water into high-speed mixer 1,
The water filling port of the water filling device stretches in the stir chamber of high-speed mixer 1.The water filling device include water tank 14 and with
The water injection pipe 15 of the water outlet connection of water tank 14, the water outlet of the water injection pipe 15 are the water filling port of the water filling device.Together
When, equipped with the waterglass injection pipe 16 for injecting waterglass in the waterglass storage box 2, the waterglass injection pipe 16
Liquid outlet stretches in waterglass storage box 2.
When practice of construction, a gram mud effect is stirred with water and obtains gram mud by high-speed mixer 1 and imitates slurries, then is passed through
Described gram of mud effect slurries are pumped to dual slurry injection pipe 6 by described gram of mud effect pumping installations, while being pumped by the waterglass
Waterglass pump is synchronized and is sent to dual slurry injection pipe 6 by device;Also, in the effect of the first hydraulic pump 3-1 and the second hydraulic pump 3-2
Under, grouting serous fluid is formed after gram mud effect slurries and the waterglass mixing that are pumped in dual slurry injection pipe 6 and is conveyed by slurries
Pipe 11 and middle shield injection pipe 7 and/or slurries delivery pipe 11 and native storehouse injection pipe 8 inject corresponding slip casting position, expected from realization
Slip casting effect.
The above is only the preferred embodiment of the utility model, not imposes any restrictions to the utility model, all
According to any simple modification to the above embodiments of the utility model technical spirit, change and equivalent structural changes, still
Belong in the protection scope of technical solutions of the utility model.
Claims (10)
1. a kind of Shield-bored tunnels pass through river construction grouting equipment, it is characterised in that: including being mixed to grouting serous fluid
Match and be delivered to slurries mixture and the conveying device in the shield body (10) of shield machine, the shield body (10) is by anterior shield, middle shield and shield
Tail assembles from front to back, and the anterior shield front is equipped with cutterhead;The forward upper of the middle shield is equipped with and starches the slip casting
Liquid is injected into the middle shield injection pipe (7) on the outside of shield body (10), and the forward upper of the middle shield is provided with shield injection pipe (7) installation in confession
Middle shield injected hole;It is equipped on Tu Cang (9) rear wall of the shield machine and the grouting serous fluid is injected into institute by Tu Cang (9)
The intracorporal native storehouse injection pipe (8) of soil on front side of cutterhead is stated, is provided on the rear wall of the Tu Cang (9) and is installed for native storehouse injection pipe (8)
Native storehouse injected hole, the middle shield injected hole is located on rear side of the native storehouse injected hole;The middle shield injection pipe (7) and Tu Cang injection
The inlet for managing (8) is connect with the liquid outlet of the slurries mixture and conveying device.
2. a kind of Shield-bored tunnels described in accordance with the claim 1 pass through river construction grouting equipment, it is characterised in that: institute
State the rear wall top that native storehouse injected hole is located at Tu Cang (9).
3. a kind of Shield-bored tunnels according to claim 1 or 2 pass through river construction grouting equipment, feature exists
In: the soil storehouse injected hole and the middle shield injected hole are respectively positioned on the dead astern of the cutterhead.
4. a kind of Shield-bored tunnels according to claim 1 or 2 pass through river construction grouting equipment, feature exists
In: the soil storehouse injection pipe (8) is laid with shield body (10) in parallel, described soil storehouse injection pipe (8) and middle shield injection pipe (7) equal position
Right above the central axis of shield body (10);The middle shield injection pipe (7) and native storehouse injection pipe (8) perpendicular laying, it is described in
Shield injection pipe (7) is laid on a cross section of shield body (10).
5. a kind of Shield-bored tunnels according to claim 1 or 2 pass through river construction grouting equipment, feature exists
In: the slurries are mixed and conveying device includes being stirred and obtaining a gram high-speed mixer for mud effect slurries with water to gram mud effect
(1), described gram of mud effect slurries are mixed with waterglass and forms the dual slurry injection pipe (6) and dual slurry of the grouting serous fluid
The slurries delivery pipe (11) of injection pipe (6) connection, gram mud effect pump that described gram of mud effect slurries are pumped to dual slurry injection pipe (6)
It send device and waterglass is pumped to waterglass pumping installations and dual slurry injection pipe (6) of dual slurry injection pipe (6), it is described
The liquid outlet of high-speed mixer (1) is imitated pumping installations by described gram of mud and is connect with the inlet of dual slurry injection pipe (6), described
The liquid outlet of waterglass pumping installations is connect with the inlet of dual slurry injection pipe (6);The dual slurry injection pipe (6) goes out liquid
Mouthful connect with the inlet of slurries delivery pipe (11), the inlet of middle shield injection pipe (7) the He Tucang injection pipe (8) with slurry
The liquid outlet of liquid delivery pipe (11) connects.
6. a kind of Shield-bored tunnels pass through river construction grouting equipment according to claim 5, it is characterised in that: institute
Stating a gram mud effect pumping installations includes gram mud effect delivery pipe (12) conveyed to described gram of mud effect slurries, described gram of mud effect conveying
Pipe (12) is connected between the liquid outlet of high-speed mixer (1) and the inlet of dual slurry injection pipe (6), described gram of mud effect conveying
It manages and the first hydraulic pump (3-1) is housed on (12);
The waterglass pumping installations includes for the waterglass storage box (2) of waterglass storage and imitating slurries to described gram of mud
The waterglass delivery pipe (13) conveyed, the waterglass delivery pipe (13) are connected to the liquid outlet of waterglass storage box (2)
Between the inlet of dual slurry injection pipe (6), the second hydraulic pump (3-2) is housed on the waterglass delivery pipe (13).
7. a kind of Shield-bored tunnels pass through river construction grouting equipment according to claim 6, it is characterised in that: institute
Stating the first hydraulic pump (3-1) and the second hydraulic pump (3-2) is variable-frequency electric hydraulic pump;
First flowmeter (4-1) and first pressure gauge (5-1), the waterglass conveying are housed on described gram of mud effect delivery pipe (12)
It manages and second flowmeter (4-2) and second pressure gauge (5-2) is housed on (13).
8. a kind of Shield-bored tunnels pass through river construction grouting equipment according to claim 5, it is characterised in that: institute
It states slurries mixture and conveying device further includes the water filling device filled the water into high-speed mixer (1), the water filling of the water filling device
Mouth stretches in the stir chamber of high-speed mixer (1).
9. a kind of Shield-bored tunnels pass through river construction grouting equipment according to claim 5, it is characterised in that: institute
State the tube body that dual slurry injection pipe (6) are inner hollow.
10. a kind of Shield-bored tunnels according to claim 1 or 2 pass through river construction grouting equipment, feature exists
In: middle shield injection pipe (7) the He Tucang injection pipe (8) is straight tube, and the upper end of the middle shield injection pipe (7) stretches to shield body
(10) front end in outside, the soil storehouse injection pipe (8) stretches in Tu Cang (9).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821437945.XU CN209025668U (en) | 2018-09-04 | 2018-09-04 | A kind of Shield-bored tunnels pass through river construction grouting equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821437945.XU CN209025668U (en) | 2018-09-04 | 2018-09-04 | A kind of Shield-bored tunnels pass through river construction grouting equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209025668U true CN209025668U (en) | 2019-06-25 |
Family
ID=66877036
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821437945.XU Active CN209025668U (en) | 2018-09-04 | 2018-09-04 | A kind of Shield-bored tunnels pass through river construction grouting equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209025668U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113153321A (en) * | 2021-03-30 | 2021-07-23 | 中建八局轨道交通建设有限公司 | Muck improvement system for shield construction and construction method thereof |
TWI784775B (en) * | 2021-10-29 | 2022-11-21 | 潛盾工程有限公司 | The second backfill grouting structure for the protection of underground engineering shield tunnel buildings |
-
2018
- 2018-09-04 CN CN201821437945.XU patent/CN209025668U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113153321A (en) * | 2021-03-30 | 2021-07-23 | 中建八局轨道交通建设有限公司 | Muck improvement system for shield construction and construction method thereof |
CN113153321B (en) * | 2021-03-30 | 2023-03-14 | 中建八局轨道交通建设有限公司 | Muck improvement system for shield construction and construction method thereof |
TWI784775B (en) * | 2021-10-29 | 2022-11-21 | 潛盾工程有限公司 | The second backfill grouting structure for the protection of underground engineering shield tunnel buildings |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107120121B (en) | A kind of shield-tunneling construction supplements slip casting anti-settling control method in real time | |
CN105804770B (en) | The earth-filling method and its equipment in TBM method tunnel or tunnel construction | |
CN205477628U (en) | Biliquid thick liquid device is annotated in step in shield driving | |
CN209025668U (en) | A kind of Shield-bored tunnels pass through river construction grouting equipment | |
CN202140088U (en) | Shield machine foam agent injecting pipeline system capable of injecting bentonite symultaneously | |
CN105649650A (en) | Back pea gravel blow filling grouting construction method for single-shield hard rock roadheader after installing TBM pipe piece | |
CN109749748A (en) | A kind of rich water round gravel stratum shield sediment improvement method and sediment improvement agent | |
CN105386435A (en) | Double-liquid grouting system used for cement and water glass solution and construction process of double-liquid grouting system | |
CN105257303A (en) | Construction method capable of achieving synchronous double-grout grouting during shield tunneling | |
CN108166983B (en) | Novel shield tail wall back grouting liquid capable of preventing loss | |
CN207377573U (en) | Colluvial clay tunneltron booth structure | |
CN206737922U (en) | A kind of shield machine shield endnote sizing device | |
CN210714722U (en) | Synchronous double-liquid-slurry grouting system | |
CN207619995U (en) | A kind of material for diaphragm wall of Cofferdam construction high-pressure rotary jet grouting pile equipment | |
CN101892847A (en) | Novel double liquid grout injecting mixer | |
CN107387121A (en) | The all-hydraulic coupling control system of novel double liquid grout injecting | |
CN206487492U (en) | A kind of shield machine single fluid grouting pipe rapid translating two-liquid grouting device | |
CN109162667A (en) | Coal mining two-liquid grouting device | |
CN108587583A (en) | A kind of high proportion rectangular top pipe mud and preparation method thereof and construction method | |
CN103114601B (en) | The rapid hardening high pressure jet grouting of strong absorbent formation cuts infiltration method and device thereof | |
CN103015428B (en) | Double-pump pipe inserting and grouting adjusting and controlling device and double-pump pipe inserting and grouting adjusting and controlling method | |
CN110295599A (en) | A kind of proportioner suitable for biliquid single system chemical grouting | |
CN109707339A (en) | A kind of method for sealing of coal column grouting and reinforcing | |
CN206668271U (en) | A kind of shield machine grouting at the tail of the shield machine structure | |
CN201666156U (en) | Novel two-shot grouting mixer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |