CN208689614U - A kind of assembled architecture prefabricated components based on BIM5D - Google Patents

A kind of assembled architecture prefabricated components based on BIM5D Download PDF

Info

Publication number
CN208689614U
CN208689614U CN201820749915.6U CN201820749915U CN208689614U CN 208689614 U CN208689614 U CN 208689614U CN 201820749915 U CN201820749915 U CN 201820749915U CN 208689614 U CN208689614 U CN 208689614U
Authority
CN
China
Prior art keywords
bim5d
prefabricated components
assembled architecture
components based
dimension code
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820749915.6U
Other languages
Chinese (zh)
Inventor
李政道
王家远
彭明
朱俊乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen University
Shenzhen Genew Technologies Co Ltd
Original Assignee
Shenzhen University
Shenzhen Genew Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen University, Shenzhen Genew Technologies Co Ltd filed Critical Shenzhen University
Priority to CN201820749915.6U priority Critical patent/CN208689614U/en
Application granted granted Critical
Publication of CN208689614U publication Critical patent/CN208689614U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The utility model relates to assembled architecture technical fields, disclose a kind of assembled architecture prefabricated components based on BIM5D, the prefabricated components include: member body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed in the member body, and the member body includes the concrete structure and/or wood moulding structure of default specification and size;Design, production, the whole-process management of construction information that prefabricated components are realized by BIM5D technology, improve construction precision, reduce waste of material.

Description

A kind of assembled architecture prefabricated components based on BIM5D
Technical field
The utility model relates to assembled architecture technical field more particularly to a kind of assembled architecture based on BIM5D are pre- Component processed.
Background technique
Traditional interior wall partition wall or exterior wall are built with one piece one piece of brick mostly, the weight that assembled architecture rises Point is prefabrication, and a large amount of masonry work is changed into machinery production by site operation, quickly assembles after transport, and reaches Construction vision to the purpose quickly produced, the industry emerging as one, prefabricated panel is, from plant produced, to arrive building site group Dress, just like the progress as assembly line without any confusion, the importance of people is reduced, and mechanical and means of transport advantage is played.But It is in fact whether genuine such? the investigation of the sides of taking part in building of building trade is shown more according to us, it is really not so.Its existing rank The development of section still has construction problem not can solve.
Problem 1 uses concrete prefabricated wallboard or the cored slab of new material.It is not aware that on building site when plant produced The length of each piece of wall needed, factory produce the size of some fixations in advance, and general wall uses these different in width Board group closes out, and remainder is reused by cutting.Its length is about 300CM, substantially can satisfy the height of first floor Degree, by the way that in this hardened structure bulk transport to construction site, further working cut, is applied on wall, construction site Need a small-sized processing of cutting factory.
Problem 2, it is prefabricated by the whole wall of factory.Prefabricated several specifications can be generally used, first pass through BIM modeling in this case With calculation amount, compares and be adapted to standard house type.The garden and house type of some great development quotient is reproducible.The specification of wall is substantially solid Fixed such as width is 3 meters, 2 meters, 1 meter, the pre-cast concrete walling with door, concrete prefabricated wall with window etc..This prefabricated update It is advanced, directly reach the effect assembled a set of set house type room for spelling building blocks.Larger problem is still big in production difficulty, transport at This is higher.Assembled blanking management slightly has difficulty.
Problem 3, transport.Factory is more distant at a distance from building site, estimates the inaccuracy of dosage, usually will cause fortune The increase of defeated cost.
Problem 4, field management.It is cut in construction site, then transports and installed on corresponding partition wall upstairs.At this time Have some plates be not it is general, which is transported and puts work flowing water section, consigns to which teams and groups uses, a hand can only be leaned on It copies and is singly allocated.Inevitably there is the material transportation in the area A to the area B for example, usually having, leads to various in-fightings.
Problem 5, installation.By a series of transport in front, many batches of wallboards has been transported under wall, actually which block First install? installed after which block? this needs very careful planning, otherwise can encounter and accidentally fill, the wallboard of not at all easy completion Also to unload readjustment again.
Utility model content
The main purpose of the utility model is that proposing a kind of assembled architecture prefabricated components based on BIM5D, pass through BIM5D technology realizes design, production, the whole-process management of construction information of prefabricated components, improves construction precision, reduces material Material waste.
To achieve the above object, a kind of assembled architecture prefabricated components based on BIM5D provided by the utility model, packet Include: member body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed on the member body On, the member body includes the concrete structure and/or wood moulding structure of default specification and size.
Optionally, the positioning label is that ultra wide band UWB positions label.
Optionally, further include protective shell, form the paper chamber of an accommodating two-dimension code label, the guarantor in the protective shell The edge of protective case is provided with fixation hole, and the protective shell connects by the way that the muscle structure of the fixation hole and the prefabricated components is fixed It connects.
Optionally, the protective shell is plastic protection casing or metal coating shell.
Optionally, the protective shell is rectangle protective shell, and there are four fixation holes for setting on four angles of the rectangle.
Optionally, be stored on the two-dimension code label: project name, floor information, location information, is born building information Blame teams and groups' information, plan set-up time information, date of manufacture and component ID.
The utility model proposes a kind of assembled architecture prefabricated components based on BIM5D, which includes: component Main body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed in the member body, the structure Part main body includes the concrete structure and/or wood moulding structure of default specification and size;Prefabricated components are realized by BIM5D technology Design, production, the whole-process management of construction information, improve construction precision, reduce waste of material.
Detailed description of the invention
Fig. 1 is that a kind of assembled architecture prefabricated components structure based on BIM5D that the utility model embodiment one provides is shown It is intended to;
Fig. 2 is the two-dimension code label fixed structure chart that the utility model embodiment one provides.
Wherein, the appended drawing reference of Fig. 2 are as follows: 1- two-dimension code label, 2- protective shell, 3- fixation hole, 4- muscle structure.
The embodiments will be further described with reference to the accompanying drawings for the realization, functional characteristics and advantage of the utility model aim.
Specific embodiment
It should be appreciated that specific embodiment described herein is only used to explain the utility model, it is not used to limit this Utility model.
In subsequent description, it is only using the suffix for indicating such as " module ", " component " or " unit " of element Be conducive to the explanation of the utility model, itself there is no specific meanings.Therefore, " module " and " component " can be mixedly It uses.
Embodiment one
As shown in Figure 1, in the present embodiment, a kind of assembled architecture prefabricated components based on BIM5D, comprising: component master Body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed in the member body, the component Main body includes the concrete structure and/or wood moulding structure of default specification and size.
In the present embodiment, by BIM5D technology realize the designs of prefabricated components, production, construction information whole process pipe Reason, improves construction precision, reduces waste of material.
In the present embodiment, BIM5D is connected on the basis of as the term suggests being the 3D there are five dimension, known to us 4D time and 5D cost.In this case, BIM (Building Information Modeling, Building Information Model) No longer it is a simple Building Information Model, and is through whole building life cycle, extends BIM data and building Full-range application.So BIM5D is the management carried out on the basis of BIM to entire work progress, it is a kind of tool.It is common BIM5D software may be mounted on the mobile terminals such as mobile phone, plate, it is user-friendly.
In the present embodiment, the positioning label is that ultra wide band UWB positions label.
As shown in Fig. 2, in the present embodiment, prefabricated components further include protective shell 2, an accommodating is formed in the protective shell 2 The paper chamber of the two-dimension code label 1, the edge of the protective shell are provided with fixation hole 3, and the protective shell 2 passes through the fixation Hole 3 is fixedly connected with the muscle structure 4 of the member body.
The muscle structure is concrete structure, wood moulding structure or other support constructions.
In the present embodiment, the protective shell is plastic protection casing or metal coating shell.
In the present embodiment, the protective shell is rectangle protective shell, and there are four solid for setting on four angles of the rectangle Determine hole.
In the present embodiment, it is stored on the two-dimension code label: project name, building information, floor information, positioning letter Breath is responsible for teams and groups' information, plan set-up time information, date of manufacture and component ID.
In the present embodiment, the following table 1 is the information table of two-dimension code label:
Field attribute Attribute value
Project The square the XX second phase
Lou Dong A
Floor F3
Positioning A5-A6
It is responsible for teams and groups XX mono- is built
Plan the set-up time On April 10th, 2018
Date of manufacture On March 1st, 2018
Plate ID B654888
Table 1
In the present embodiment, it can be managed using BIM5D system in each production link, in design link, answer Carry out three-dimensional modeling with BIM5D system, virtual reality scenario, everybody is readable for design effect;In quantities calculation link, answer Accurate Model is carried out with BIM5D system, project amount and actual error are minimum, can be to prefabricated by the calculation amount product of Si Weier Material carries out classification statistics, can submit prefabrication, not waste material and transportation cost;At the construction field (site), using BIM5D system By model interaction to flowing water section.Automatically the material requested amount of each flowing water section is calculated;Link, construction are positioned in prefabricated components Personnel can select a face wall by mobile devices such as plates from model, check the essential information of wall, can also be from two dimensional code Upper barcode scanning understands house type applied by this plate and position;In quality safety management link, by mobile devices such as mobile phones, record into Degree, quality, safety problem.All-the-way tracking rectification, reduces Cost for Coordination;Link is inquired in item status, can be united by BIM5D The Construction Condition of meter project.
In the present embodiment, the utility model only protects the connection relationship between each component part of prefabricated components, does not protect Its function limitations, such as: the prior art can be used in the operating method and process of localization method, BIM5D software, these functions, Other modes can be used, not within the protection scope of this case.
It should be noted that, in this document, the terms "include", "comprise" or its any other variant are intended to non-row His property includes, so that the process, method, article or the device that include a series of elements not only include those elements, and And further include other elements that are not explicitly listed, or further include for this process, method, article or device institute it is intrinsic Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including being somebody's turn to do There is also other identical elements in the process, method of element, article or device.
Above-mentioned the utility model embodiment serial number is for illustration only, does not represent the advantages or disadvantages of the embodiments.
Through the above description of the embodiments, those skilled in the art can be understood that above-described embodiment side Method can be realized by means of software and necessary general hardware platform, naturally it is also possible to by hardware, but in many cases The former is more preferably embodiment.Based on this understanding, the technical solution of the utility model is substantially in other words to existing skill The part that art contributes can be embodied in the form of software products, which is stored in a storage and is situated between In matter (such as ROM/RAM, magnetic disk, CD), including some instructions are used so that terminal device (it can be mobile phone, computer, Server, air conditioner or network equipment etc.) execute method described in each embodiment of the utility model.
The above is only the preferred embodiments of the utility model, and therefore it does not limit the scope of the patent of the utility model, all Equivalent structure or equivalent flow shift made based on the specification and figures of the utility model, is applied directly or indirectly in Other related technical areas are also included in the patent protection scope of the utility model.

Claims (6)

1. a kind of assembled architecture prefabricated components based on BIM5D characterized by comprising member body, two-dimension code label and Positioning device, the two-dimension code label and positioning device are fixed in the member body, and the member body includes default rule The concrete structure and/or wood moulding structure of lattice and size.
2. a kind of assembled architecture prefabricated components based on BIM5D according to claim 1, which is characterized in that described fixed Position device is that ultra wide band UWB positions label.
3. a kind of assembled architecture prefabricated components based on BIM5D according to claim 1, which is characterized in that further include Protective shell, the interior paper chamber for forming an accommodating two-dimension code label of the protective shell, the edge of the protective shell is provided with solid Determine hole, the protective shell is fixedly connected by the fixation hole with the muscle structure of the prefabricated components.
4. a kind of assembled architecture prefabricated components based on BIM5D according to claim 3, which is characterized in that the guarantor Protective case is plastic protection casing or metal coating shell.
5. a kind of assembled architecture prefabricated components based on BIM5D according to claim 3, which is characterized in that the guarantor Protective case is rectangle protective shell, and there are four fixation holes for setting on four angles of the rectangle.
6. a kind of assembled architecture prefabricated components based on BIM5D according to claim 1, which is characterized in that described two It is stored on dimension code label: when project name, building information, floor information, location information, responsible teams and groups' information, plan installation Between information, date of manufacture and component ID.
CN201820749915.6U 2018-05-18 2018-05-18 A kind of assembled architecture prefabricated components based on BIM5D Active CN208689614U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820749915.6U CN208689614U (en) 2018-05-18 2018-05-18 A kind of assembled architecture prefabricated components based on BIM5D

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820749915.6U CN208689614U (en) 2018-05-18 2018-05-18 A kind of assembled architecture prefabricated components based on BIM5D

Publications (1)

Publication Number Publication Date
CN208689614U true CN208689614U (en) 2019-04-02

Family

ID=65877259

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820749915.6U Active CN208689614U (en) 2018-05-18 2018-05-18 A kind of assembled architecture prefabricated components based on BIM5D

Country Status (1)

Country Link
CN (1) CN208689614U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863777A (en) * 2021-10-20 2021-12-31 佛山市众盈新型装饰材料科技有限公司 Flame-retardant high-strength wood-plastic profile and preparation method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863777A (en) * 2021-10-20 2021-12-31 佛山市众盈新型装饰材料科技有限公司 Flame-retardant high-strength wood-plastic profile and preparation method thereof
CN113863777B (en) * 2021-10-20 2022-11-18 佛山市众盈新型装饰材料科技有限公司 Flame-retardant high-strength wood-plastic profile and preparation method thereof

Similar Documents

Publication Publication Date Title
CN108446867A (en) A kind of assembled architecture prefabricated components and its management method based on BIM5D
Innella et al. Lean methodologies and techniques for modular construction: Chronological and critical review
Polat Factors affecting the use of precast concrete systems in the United States
KR102302078B1 (en) Method and system using standardized structural components
US20070027732A1 (en) Context-sensitive, location-dependent information delivery at a construction site
Liu et al. Design for Manufacturing and Assembly: A BIM‐Enabled Generative Framework for Building Panelization Design
Gasparri et al. Construction management for tall CLT buildings: From partial to total prefabrication of façade elements
García-Alvarado et al. Architectural evaluation of 3D-printed buildings
Orlowski Assessment of manufacturing processes for automated timber-based panelised prefabrication
CN102262757A (en) Advanced planning system (APS)/manufacturing execution system (MES) lean manufacturing management system
CN208689614U (en) A kind of assembled architecture prefabricated components based on BIM5D
US8830239B2 (en) Materials management system and method
Noorzai et al. Lessons learned on selecting the best mass housing method based on performance evaluation criteria in Iran
Du et al. Dynamic decision support framework for production scheduling using a combined genetic algorithm and multiagent model
US11379626B2 (en) Construction management system
Lee et al. BIM‐Based Digital Fabrication Process for a Free‐Form Building Project in South Korea
US20100274374A1 (en) System and process for the detailed design and production of reinforcement for buildings
Mésároš et al. Adaptive design of formworks for building renovation considering the sustainability of construction in BIM environment—Case study
Bhattacharjee et al. Adoption of pre-fabrication in construction to achieve sustainability goals: an empirical study
Ahmad et al. Multicriteria decision analysis of steel and mass timber prototype buildings in the Pacific Northwest
CN111832995A (en) Logistics distribution method, device and system and computer readable storage medium
CN112395680A (en) Method and system for measuring and calculating engineering quantity of prefabrication scheme
Bartoszek et al. Impact of the selected disturbing factors on accuracy of the distance measurement with the use of ultrasonic transducers in a hard coal mine
US20070260344A1 (en) Module evaluation method and system
de Melo et al. Investigation of the supply chain of prefabricated wooden doors.

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant